Supply: Siting, Drilling, and Construction Water Wells
Supply: Siting, Drilling, and Construction Water Wells
Supply: Siting, Drilling, and Construction Water Wells
First Edition
Copyright (C) 2007 American Water Works Association All Rights Reserved
Copyright 02007 American Water Works Association.
All rights reserved.
Printed in the United States of America.
No part of this publication may be reproduced or transmitted in any form or by any means,
electronic or mechanical, including photocopy, recording, or any information or retrieval
system, except in the form of brief excerpts or quotations for review purposes, without the
written permission of the publisher.
Disclaimer
This book is provided for informational purposes only, with the understanding that the pub-
lisher and authors are not thereby engaged in rendering engineering or other professional
services. The authors and publisher make no claim as to the accuracy of the book's contents,
or their applicability to any particular circumstance. The authors and publisher accept no
liability to any person for the information or advice provided in this book, or for loss or
damages incurred by any person as a result of reliance on its contents. The reader is urged to
consult with an appropriate licensed professional before taking any action or making any
interpretation that is within the realm of a licensed professional practice.
TD405.B56 2007
628.1'14-dc22
2007038967
Copyright (C) 2007 American Water Works Association All Rights Reserved
Contents
Copyright (C) 2007 American Water Works Association All Rights Reserved
vi Siting, Drilling, and Construction of Water Supply Wells
Index 195
About the Authors 222
Copyright (C) 2007 American Water Works Association All Rights Reserved
Basic Concepts
SOURCES OF GROUNDWATER
Groundwater is water that may have recently entered the soil as a result of rainfall or
snow melt, or it may be an ancient source found in geologic formations well below
the surface. This water is a portion of the hydrologic cycle (see Figure 1-1) where
water falIs to the earth and seeps into the soil and flows downward by gravity until it
contacts a layer of impervious strata. Groundwater typically flows down gradient,
taking the path of least resistance. Therefore, if high permeability underground
conduits or channels are present, the water will tend to flow along these pathways.
These formations may yield substantial quantities of water.
A body of rock that is sufficiently permeable to conduct groundwater to yield
economically significant quantities of water to wells and springs is called an aquifer.
Water that is located near the land surface, exposed to atmospheric pressure, and has
no overlying confinement is called the water table or surficial aquifer. The surface of
a water table aquifer tends to follow the surface of the ground, although some
conditions cause exceptions. Aquifers will recharge creeks, lakes, or rivers whose
bottoms are deeper than the top of the water table, and aquifers may be recharged by
those same water bodies where the surface of the aquifer is beneath the creek, lake,
or river bottom.
A spring forms when groundwater flows naturally from an aquifer to the
surface, such as near a creek, lake, or river. Water flowing from a spring may have
traveled hundreds of miles (kilometers) from where it seeped into the ground, or it
could be from a surface water source only a few yards away.
Water table aquifers that are located up to four ft (1.5 m) below the surface may
be subject to evaporation. Because there is little resistance to migration ofwater into
water table aquifers, they are also more susceptible to contamination than deeper
aquifers, a major consideration in locating wellfields. Below the water table aquifer
may be other aquifers. These aquifers will be separated by a layer of material such as
dolomite, clay, or other material that prevents or limits the exchange of water
Copyright (C) 2007 American Water Works Association All Rights Reserved
2 Siting, Drilling, and Construction of Water Supply Wells
recipitation on Evaporation
recipitationon
l/ I \‘o
/
h
Evaporation
Groundwater Flow
A A A
Impervious Strata
between the aquifer layers. Such limiting formations are called confining units or
aquitards.
Aquifers that are located further beneath the surface and have low permeability
formations above them are called confined aquifers. These aquifers may be under
pressure and are termed artesian aquifers if their water surface rises above the
bottom of the overlying confining bed when exposed to atmospheric pressure. The
termflowing artesian aquifers refers to those aquifers where the water surface rises
above the overlying confining unit and flows at land surface. An example is the
Floridan aquifer in southeast Florida that will “flow” 30 ft (10 m) above the ground
surface. Some confined aquifers are buried river valleys or the beds of an ancient
lake. Examples exist in the Midwest, where such buried rivers are highly permeable
and may yield large quantities of water.
The flow velocity and flow direction of groundwater depends on the elevation
of the recharge source, the permeability of soil and rock layers, and the relative
pressure of the groundwater. The movement of water through an aquifer is generally
quite slow; however, the long-term movement of water through the rock may
dissolve the formation. Eventually, this allows large cavities to interconnect and
form underground rivers or caverns that can be tapped as a public water supply
Copyright (C) 2007 American Water Works Association All Rights Reserved
Basic Concepts 3
source. At the same time, this water retains the dissolved minerals that often need to
be removed for water supply purposes.
When attempting to identify water supplies, one must evaluate the productivity
and water quality of each aquifer because the quantity and quality of water in the
aquifers may vary greatly. The quantity and quality of groundwater depends on
factors such as confinement, depth, aquifer thickness, rainfall, and geological
formation. For example, because their relatively high permeability provides
significant productivity, sand, shell, and gravel aquifers are more suitable for public
water system than clay, granite, or dolomite. Sandstone is porous and often yields
water of good quality in sufficient quantity to supply public water systems.
Limestone has moderate porosity but often contains cracks and cavities that can
provide substantial quantities of water ( A W A , 2003). Table 1-1 shows the
porosity of rock formations.
Throughout North America, groundwater can generally be found from a few
feet to hundreds of feet (or meters) below the land surface. However, except along
the coastlines, deeper waters tend to have poorer water quality as a result of minerals
dissolving into the water over many years. Deep formations are likely to be more
distant from recharge areas, so the water will be older and have been in contact with
the rock for a longer period of time. A balance must be struck in such areas between
the decreased water quality from deeper aquifers (which might require additional
treatment) and the potential for more productivity in a given well. Deep wells also
have higher construction costs but are less susceptible to contamination. Therefore,
while some deep aquifers may be prolific, the quality of water obtained from a well
may not be usable for drinking water without substantial treatment.
The United States Environmental Protection Agency (USEPA) has created
designations for aquifers based on water quality. While it is technically possible to
treat almost all water to obtain acceptable quality, treatment may not be economical
Copyright (C) 2007 American Water Works Association All Rights Reserved
4 Siting, Drilling, and Construction of Water Supply Wells
- ”f
or practical for waters with greater than 1O,OOO mg/L of total dissolved solids. Such
waters are generally not potential “underground sources of drinking water.” All
other aquifers are regulated as they may at some point be used for drinking water
purposes.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Figure 1-2 Typical well installation
quality. The water supply system must balance factors including well depth, geology
of the area, characteristics of the rock formations, and dissolved minerals in the
aquifer.
In most places, locating productive wells may be accomplished using local,
expert knowledge of the geology of the region and the experience with existing
wells. Figure 1-2 is an example of a well installation. Having noted the benefits of
groundwater supplies, these principles can provide guidance in searching for well
sites. There are several steps involved in identifying potential groundwater sources.
The first is to locate the literature, prior investigations,local or regional water supply
plans, and on-site activities of neighboring water purveyors with regard to
groundwater use. If groundwater is available, others will likely know about it. Oil
and gas drilling logs often identify formations that may be potential sources.
Agricultural interests are often the first to tap groundwater supplies.
The United States Geological Survey (USGS) has extensively studied
underground formations for the presence of suitable water throughout the United
States. For studies within the United States, the literature search should begin with
the USGS's Summary Appraisals of the Nation? Ground Water Resources (1978-
1982). Individual reports covering the region of interest can be obtained. Other
published reports on groundwater resources are available from federal and state
agencies that provide a summary of quantity and quality of available groundwater in
various geographic regions, including major basin areas and state, county, and local
regions.
Copyright (C) 2007 American Water Works Association All Rights Reserved
6 Siting, Drilling, and Construction of Water Supply Wells
Source: www.bcpa.net
Figure 1-3 Industrial aerial map
Source: www.bcpa.net
Figure 1-4 Residential aerial map
Copyright (C) 2007 American Water Works Association All Rights Reserved
Basic Concepts 7
Source: www.bcpa.net
Figure 1-5 Undeveloped area aerial map
Copyright (C) 2007 American Water Works Association All Rights Reserved
8 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Basic Concepts 9
Copyright (C) 2007 American Water Works Association All Rights Reserved
10 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Basic Concepts 11
but the focus for this book is on the ability to ensure long-term availability of the
water supply. The issues involved in determining sustainability include
0 Ongoing, consistent recharge of the aquifer,
Variability in water levels,
0 Water quality variability, and
0 Competing users.
Ongoing recharge of the aquifer can be discerned through the use of well
testing to monitor fluctuations in water levels with regard to rainfall. Locations
beside lakes and streams that flow consistently throughout the year may provide
good sites if no adverse environmental effects are experienced. Step-drawdown tests
(discussed in chapter 4 ) also are needed to determine how significant the impact of
the well may be to the aquifer locally and areally. Water rights access, a major factor
in 18 western states, and water use or consumptive use permits in the southeast limit
withdrawal amounts. Typically, development of new wellfields must demonstrate no
infringement on existing water rights or competing water uses. Field investigations
(as outlined in chapter 4) must be performed to confirm site-specific characteristics.
Water quality considerations (chapter 2) are important when deciding whether a
well site will provide water capable of potable use with reasonable treatment and
delivery cost. Deterioration of water quality can have significant financial
consequences because of higher treatment costs or the need to abandon the water
supply wells. Therefore, some exploratory work should be done to provide needed
details regarding water quality.
In conjunction with the evaluation, the following factors should be considered:
0 The location of the well sites in areas where the demands are highest
The cost to develop the water supply for the region
The conveyance and treatment costs
The potential revenue generation as it relates to construction and operating costs
Environmental concerns, such as for endangered species and critical habitat
0 Location of future growth
REFERENCE
AWWA (American Water Works Association). 2003. Manual M21-Groundwater.
American Water Works Association: Denver, Colo.: AWWA.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location,
Protection, and Water Quality
Until the 1960s, it was assumed that groundwater was not &ected by surface
activities. However, in the 1960s, the United States government found that nearly a
quarter of the country's wellfields were affected by surface contaminants ranging
from minerals to solvents and other hydrocarbons. This discovery provided
documentation that water table aquifers can be easily contaminated by spills from
surface activities. These problems led directly to the passage of the Safe Drinking
Water Act (SDWA) in 1974. Improved methods of chemical analysis and more
complete sampling of well water has revealed a large number of public water supply
wells contaminated by careless use and disposal of synthetic chemicals (Bloetscher,
et al., 2005). One example that has plagued water suppliers is leakage from
underground fuel tanks that have contaminated hundreds of sites across the
United States.
Copyright (C) 2007 American Water Works Association All Rights Reserved
14 Siting, Drilling, and Construction of Water Supply Wells
Legionella Zero -
Total coliforms Zero 5%
Bromate - 0.01
Chlorite - 1
HAAs - 0.06
T H M total Zero 1.1
Chloramines - 4.0
Chlorine - 4.0
Chlorine dioxide - 4.0
Antimony .005 0.005
Arsenic Zero 0.01
Asbestos 7 7
Barium 2 2
Beryllium 0.004 0.004
Cadmium 0.005 0.005
Chromium 0.1 0.1
Copper 1.3 1.3
Cyanide 0.2 0.2
Fluoride 4 4.0
Lead Zero 0.015
Mercury 0.002 0.002
Nitrate 10 10
Nitrite 1 1
Selenium 0.05 0.05
Thallium 0.0005 0.002
Gross alpha Zero 1 5 piC1L
Beta emitters Zero 4 mremlyr
Radium 2261228 Zero 5piCIL
Uranium Zero .03
Table continued next page.
supplies. The USEPA reported that over 1,000 synthetic organic compounds (SOCs)
have been found nationwide in drinking water samples. Although the potential risk
for the majority of the population was minimal, it was noted that many of the
contaminants detected were suspected carcinogens.
In the early 1980s, USEPA’s focus turned to volatile organic compounds (VOCs),
commonly used as solvents and found in groundwater systems throughout the US.
While the majority of VOCs were present at very low levels, pollution had occurred
in water supplies previously thought to be pristine. In the mid-l98Os, USEPA’s focus
turned toward the legal use of pesticides because numerous pesticides had been
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location, Protection, and Water Quality 15
Source: www.epa.gov
MCLG - Maximum Contaminant Limit Goal
MCL - Maximum Contaminant Limit
NOTE: Table does not include a myriad of organics,VOCs, and SOCs. Refer to USEPA website for these
constituents(numberingnearly 100).
found in both surficial and groundwater supplies. Efforts are still underway to
survey and assess the extent of pesticide contamination in water supplies.
Throughout the period, the USEPA continued to also focus on microbiological
outbreaks and the use of disinfectant techniques. From 1972-1981, there were 335
reported outbreaks of waterborne disease involving 78,000 people. Viruses
contributed to 11waterborne outbreaks involving 5,000 cases. However, while these
levels are historically low and continue to decline, concerns over Giardia LambLia
and Cryptosporidium bacteriological contaminants and viruses persist.
As part of the 1986 amendments, SDWA required the USEPA to specify
procedures compliance with the maximum contaminant levels (MCLs) and the use
of the best available technology for those utilities that cannot comply. A priority list
of contaminants that may have adverse impacts on the health of people and are
known to, or are anticipated to, occur in public drinking supplies was also compiled
as a requirement of the 1986 amendments. Possible sources of these contaminants
include industrial and chemical production and use sites; landfills; septic tanks; and
run-off areas. The 1986 SDWA Amendments gave USEPA the authority to allow
states to acquire primacy, the responsibility for SDWA enforcement, upon
compliance with specific federal criteria. In addition, a series of separate regulations
were promulgated that affect utilities under the auspices of SDWA. These are
discussed in the following sections.
Copyright (C) 2007 American Water Works Association All Rights Reserved
16 Siting, Drilling, and Construction of Water Supply Wells
Wellhead Protection
Wellhead or source water protection regulations were created to reduce the threat to
water supplies from contaminants in runoff or as a result of surface activities.
Watershed protection is a requirement of the SDWA Amendments of 1986 (Section
1428). Under Section 1428, each state must prepare a wellhead protection program
and submit it to the USEPA for approval. The protection of public water supply
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location, Protection, and Water Quality 17
-- ~ I
I __ -~ I _ -- 1__^ _-
Copyright (C) 2007 American Water Works Association All Rights Reserved
18 Siting, Drilling, and Construction of Water Supply Wells
-_ I I ~ _I
Zone 2 encompasses areas between the 10- and 30-day travel times within the
cone of influence. Hazardous materials are allowed in Zone 2 but are subject to 100
percent containment, daily inventory records, records of storage and use, emergency
plans for spills, acquisition of emergency control devices to continue the use,
monitoring of groundwater, reporting of spills, and certain other paperwork
requirements.
Zone 3 permits any use but requires a hazardous materials license above a
certain specified (or threshold) quantity. Zone 3 does not require notification of the
utility whose wellfield might be affected.
The following is an example of why wellhead protection is so important for
water suppliers. Figure 2-2 shows the Fort Lauderdale Peek-Dixie wellfield. At the
time of construction (1926), the city had a population of approximately 8,000 and
had little competition for water. The first production wells were located
approximately four miles inland away from any potential users or conflicts. This
wellfield was located in an isolated area of the county and thought to be an ideal site
for water supply. Figure 2-3 shows the area currently around this wellfield. The
wellfield is located in a neighborhood, and a golf course has been built around the
wells. Figure 2-4 shows a model developed to indicate the drawdowns of the well. Of
concern is the fact that the wells draw water from the south, where there is a
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location, Protection, and Water Quality 19
Copyright (C) 2007 American Water Works Association All Rights Reserved
20 Siting, Drilling, and Construction of Water Supply Wells
Source: www.bcpa.net
Figure 2-3 2003 aerial map of vicinity of Fort Lauderdale‘s Peele-Dixie Wellfield.
Compare to Figure 2-2.
potential contamination site despite the fact that the aquifer is very productive and
the wells have small zones of influence. If constructed today, the industrial site that
may contaminate this wellfield would not be permitted because it is in the 30-day
travel zone (see Figure 2-1).
In conjunction with wellhead protection efforts, water systems should identify
any groundwater sources they are using that may be directly affected by surface
water. The concern is that if there is minimal filtration occurring between the
surface and the water withdrawn from wells, contaminants, especially
microbiological constituents, may contaminate the water source. Water sources that
meet this criterion are considered “groundwater under the direct influence of
surface water.” If an aquifer is determined to be groundwater under the direct
influence of surface water and therefore vulnerable to contamination by disease-
causing organisms found in surface water, the well water must be treated under the
same requirements as a surface water system, meaning mandatory disinfection and
filtration.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location, Protection, and Water Quality 21
High quantities of minerals mean low quality water. A significant relationship exists
between mineral content and depth of groundwater; the mineral quality 'of
groundwater generally declines with depth. In many sedimentary basins, where the
older and deeper sediments were deposited by oceans, mineral content can change
very abruptly. Poor-quality water can be drawn upward after production begins
Copyright (C) 2007 American Water Works Association All Rights Reserved
22 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location, Protection, and Water Quality 23
__~__1
Bacteria are the most widely distributed life form on Earth (Chapelle, 1993).
Chapelle notes that bacteria are extremely important to consider in groundwater
projects as bacteria inhabit virtually every subsurface environment, producing
methane gas and consuming rich organic soils. The key bacteria families responsible
for waterborne diseases include gram-negative bacteria such as: Legionella, the
Pseudomonads, Klebsiella, Escherichia coli, Shigella, Enterobacter, Salmonella, and
Kbrio cholerae. Most of these pathogenic bacteria are approximately 0.4 to 14 vm
long and 0.2 to 12 pm wide, which mean they are much smaller than protozoans,
thus making it easier for them to move in the subsurface.
Bacteria have their own enzymes and most are mobile, allowing them to move
in the subsurface. Bacteria reproduce by splitting into daughter cells, each of which
continues to split, forming additional bacteria and eventually, a biomass. The
respiration ability of bacteria permits them to survive in soils and aquifers. There are
three respiration types:
1. Bacteria that use inorganic chemicals to serve as electron acceptors such as
oxygen, ferric iron, and sulfates.
2. Bacteria that are aerobic-requiring oxygen.
3. Bacteria that are facultative anaerobes-capable of fermentation or using
oxygen as electron receptors (Chapelle, 1993).
The respiration mechanism is important because it affects the ability of bacteria
to colonize wells and the aquifer; it also affects the growth rate of bacteria
indigenous to the aquifer as a result of the constituents introduced by surface
activities.
Bacteria will commonly colonize wells because of the nutrients that are brought
into the borehole by pumping. One example is Pseudomonas aeroginosa, one of the
most common opportunistic bacterial pathogens. It has a colonization rate of 2.6 to
24 percent of the human population (USEPA website) and is the most common
infection in hospitals. Pseudomonas aeroginosa is an extraordinarily versatile
organism that will live in nearly any environment. Pseudomonas aeroginosa requires
no specific vitamins, growth factors, or amino acids; it is a facultative anaerobe.
However, the most important concern about this pathogen is its ability to create a
slime matrix that encapsulates other bacteria and protects them from otherwise
harsh aquifer conditions.
Commonly found bacteria in the subsurface include Gallionella and
Desulfovibrogallionella. These are obligate aerobes that obtain energy by oxidizing
dissolved ferrous iron to form ferric oxyhydroxides-meaning it will be a problem in
wells constructed with steel materials (Chapelle, 1993). Desulfovibro is a sulfur-
reducing bacterium that uses hydrogen or simple organic compounds as an energy
source and sulfates as the terminal electron acceptor, which leads to hydrogen
sulfide gas formation (Chapelle, 1993). Sloughing events may introduce significant
Copyright (C) 2007 American Water Works Association All Rights Reserved
24 Siting, Drilling, and Construction of Water Supply Wells
quantities of these bacteria into the treatment plant. Other bacteria may also
colonize the slime matrix (Bloetscher, et al., 1997). Bacteria are generally removed
by filtration and destroyed by disinfection, although the Pseudomonads are resistant
to chlorine.
Viruses are molecular entities that possess little or no enzymatic capabilities, no
energy capability, and no mechanisms for synthesis. They are small-20 to 300 nm
in size. They cannot reproduce; they require a host cell to multiply. All viruses are
composed of nucleic acid and either RNA or DNA (but not both), which allows
them to replicate in other cells, including bacteria-where they are called
bacteriophages (Chapelle, 1993). Pathogenic viruses tend to be smaller than other
viruses and can only be seen with an electron microscope. Most are 27 to 70 nm in
size and are symmetrical in shape. Viruses are obligate parasites, always searching for
the correct host cell that will allow the virus to multiply. Viruses cannot survive or
infect without such a host organism or cell (Chapelle, 1993). The majority of
viruses tend to be resistant to chloroform but may be inactivated to various degrees
during wastewater treatment processes or by chlorine, bromine, ozone, ultraviolet
light, or formaldehyde (Block, 1989).Viruses are conserved at -20°C (Block, 1989).
Human viruses found in natural waters are almost always associated with fecal
material eliminated from the bodies of infected individuals. Therefore, virus
concentrations in wastewater are high, and groundwater that may be influenced by
treated wastewater or septic tanks may be contaminated. Major viruses of concern
are: Hepatitis A, Coxsackie, Echo, Norwalk, rota- and reoviruses (Block, 1989).
While vaccines may be available for some viruses, the wild strains never disappear
from the environment (Bouwer, 1991).
Communities with poor hygiene and a high proportion of children have
provided opportunities for a series of studies attempting to characterize the survival
times of various pathogens. The studies confirm that in groundwater, filtration by
straining is the most effective method for reducing bacterial presence in an aquifer
(Powelson, et al., 1993), while virus depletion is affected by adsorption to soil
particles (assuming there are no fractures or fissures in the rock that might cause
viruses to move significantly further from the source water, making them harder
to find).
Viruses and bacteria have been shown to live 28 to 90 days in groundwater and
move 7 to 30 meters routinely (Asano, 1991; Teusch, et al., 1991). In tests for viral
contamination under sludge land application sites, both Norwalk virus and hepatitis
A viruses have been known to move in the groundwater environment (Gerba and
Bitton, 1984). Vaughn et al. (1983) detected viruses originating in septic tanks that
had passed through 3.6 m of unsaturated soil and 67 m of saturated soil (Powelson,
et al., 1993).Schaub and Sorber (1977) recovered bacteriophage #2 in 47 percent of
samples after 72 hr, after it had flowed through 18 m of unsaturated, silty soils
(Powelson, et al., 1993). Janson, et al. (1989) recorded Echovirus 11 m deep, 14 m
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location, Protection, and Water Quality 25
Factor Comments
Moisture content Survival time increases with moisture and high rainfall
Moisture holding capacity Survival time less in sandy soils with lower moisture content
Temperature Survival time longer at lower temperature
from a recharge basin for reclaimed water (Powelson, et al., 1993).In a Waldo, Fla.
migrant camp, the survival of indigenous populations of total coliforms and fecal
streptococcus in situ was over 70 days, and a link was shown between the same
septic tanks and the presence of Echoviruses 22/23 (Feacham, et al., 1981).
Table 2-2 outlines the factors that can be expected to remove bacterial particles
successfully over a short distance. Filtration is useful because the bacteria are
relatively large and filter theory indicates that filtration will remove particles
successfully up to 1/2Oth of the pore size (Gerba and Bitton, 1984). Therefore,
smaller pores equal faster removal. Because of this correlation, the physical process
of particle removal in saturated soils is fairly well understood and is probably
adequate for predicting removal, except in fractured rock formations. Virus removal
faces the same problem with rock fractures (Yates, et al., 1987). The shape of the
bacteria also is a factor in removal via filtration (Gerba and Bitton, 1984).
Bacterial survival increases with increased moisture content, increased moisture
retention capability of the rock, warmer temperatures, higher pH, and increased
nutrient capacity (Teutsch, et al., 1991). It is not surprising that bacterial counts are
highest in areas having wet, organic-rich soils (Teutsch, et al., 1991). Sorption can
also play a role in bacterial survival. Clays are fine particles with negative charges
that are very conducive to sorption (Gerba and Bitton, 1984). The repulsing factors
resulting from these negative charges are reduced when sorption occurs. Cations in
solution (Fe+2,C U + and ~ , Zn+2)play a role in removal of bacteria, while anions have
little effect (Gerba and Bitton, 1984). Where soil is absent, the benefit of filtration
is eliminated, but the benefits of rock filtration and reduced surface biomass matter
may provide better indications of survival times (Bouwer, 1991).
While bacterial removal is preferentially accomplished in the soil via filtration,
sorption, or biodegradation, virus removal is most efficiently accomplished via soil
sorption although increases in temperature significantly affect viral survivability as
Copyright (C) 2007 American Water Works Association All Rights Reserved
26 Siting, Drilling, and Construction of Water Supply Wells
well (Gerba and Bitton, 1984). Inactivation ofviruses also appears to be dependent
on the efficiency of adsorption sites, temperature, and the initial number of viruses
discharged. Other factors include soil conditions, pH, moisture content, aerobic or
anaerobic conditions, particle size, clay content, organic content, cation-exchange
capacity, virus type, and rainfall (Keswick, et al., 1982). Table 2-3 shows the
maximum horizontal and vertical movement of a series of viruses.
True field studies are difficult to conduct because the use of actual viruses
injected into the ground is not viewed favorably, and lab studies often cannot
replicate the actual aquifer condition. What is known is that the survival of viruses
and bacteria in the subsurface is determined in part by their retention on soil
particles, which are generally dependent on temperature and rainfall. Table 2-4
outlines these factors.
Because viruses are sensitive to UV light, they are likely to be active longer in
groundwater than in surface water because UV rays do not penetrate the aquifer
system (Chapelle, 1993). Groundwater is assumed to be isothermal (constant
temperature) (Yates, et al., 1985). However, viruses can survive for years in
refrigerators at 41°C (39.2"F), and it appears for every 10°C increase, the virus die-
off rate doubles (Gerba and Bitton, 1984). Above 30°C (8G"F),temperature is the
controlling factor for virus survival (Gerba and Bitton, 1984). Gerba and Bitton's
(1984) multivariate study concluded that temperature could explain 77.5 percent of
the variation in die-off rates between samples (Yates,et al., 1985).
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location, Protection, and Water Quality 27
- - -
Organic matter Increased survival and regrowth with Soluble organic matter competes with
high amounts of organic matter viruses for adsorption sites
Virus type Inactivation varies by species Adsorption on soil sites and capsid
surfaces affect migration
Salt content Cations protect certain viruses Increased migration with higher cation
concentrations, but same may increase
sorption
Adapted from Yates, et al., 1987
Copyright (C) 2007 American Water Works Association All Rights Reserved
28 Siting, Drilling, and Construction of Water Supply Wells
Endocrine Disruptors
After three decades of focus on conventional priority pollutants, especially heavy
metals, acute toxins, and carcinogens caused by herbicides, pesticides, or high
volume industrial wastes, regulatory focus appears to be reorienting toward
endocrine disruptors. These regulatory concerns are a result of the effects of very
low levels of anthropogenic endocrine disrupting chemicals present in the
environment on aquatic wildlife. The USGS has recently completed a multiyear
project to study the occurrence of these chemicals in rivers (Koplin, et al., 2002).
Their results found endocrine disruptors, especially pharmaceutically active
substances (PASs), in many water bodies. The endocrine disruptors receiving
attention from the USGS and USEPA include polychlorinated biphenyls,
phthalates, alkylphenols, and PASs, such as drugs, estrogens, diagnostic agents,
personal care products, fragrances, and sunscreens.
Wastewater treatment plant secondary effluents contain measurable
concentrations of more than 1,000 man-made compounds, including a variety of
pesticides, herbicides, cleaning solvents, laundry detergents, household products,
surfactants, and PASs and their residues. These are only a portion of which have
been identified (Harries, et al., 1996). Initial screening of endocrine activity of
herbicides, PCBs, and pesticides has identified over 50 compounds as being
endocrine disruptors, most of which appear to have an estrogenic (feminizing)
effect of aquatic vertebrates. Plastic products like phthalates, bisphenol A and
phenylphenol, and PCBs are weak estrogens, as are laundry detergents, household
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location, Protection, and Water Quality 29
cleaning products, and surfactants that break down to alkylphenols. All are weak
estrogens found in the 10-9 (pg/L) range.
To date however, research conducted by the USEPA, USGS, various state
agencies, the Water Environment Research Foundation, and the Awwa Research
Foundation remains focused on detection methods and finding chemicals in the
environment, not on treatment. Little research has been focused on removal or
inactivation of the chemicals as a result of the lack of adequate screening methods to
determine removal efficiency of treatment.
The concentration of PASs in the environment is low compared to
conventional priority pollutants-in the pg/L or ng/L range. Until analytical
methods were developed to detect low levels of pharmaceuticals in the environment
and the associated responses were found, PASs were not viewed as a potential
environmental problem. Creating detection methods for all PAS formulations is
unreasonable because many formulations are not available because of patent
limitations and proprietary knowledge. However, it is now understood that
noticeable environmental responses can be elicited from aquatic organisms in the
1 ng/L ( range, which raises questions about the cumulative effects of the
hundreds of PASSthat may be present in wastewater (Daughton and Ternes, 1999).
It is evident that the regulation of PASs will be a major focus of regulatory
limitations and research in the near future.
Municipal wastewater effluent containing PASs may constitute a major
pollution source in the aquatic environment. Unused prescriptions are also often
disposed of through the sewage system. It is also not uncommon for 40 percent of a
drug dosage to be excreted to the sewage system after normal therapeutic use. The
actions of these chemicals may be compounding (Harries, et al., 1996), because
PASs are by nature biologically active compounds that are used and excreted in large
quantities by modern society. Naproxen, estrogens, clofibric acid, and diclofenic
were frequently detected downstream of treated effluent discharge in surface waters
at the pg/L level in Europe (Stumpf, et al., 1999).
While wastewater facilities are major contributors to water contamination, they
are not the only ones and perhaps not even the major one. Agricultural enterprises
practicing animal husbandry (chicken, turkey, hog, cattle, and dairy farms) have
made significant contributions. Over 70 percent of antibiotics used in the United
States are used on chicken farms. Estrogens are used to improve growth rates and
fecundity of animals.
Table 2-5 outlines the major PAS families and observed impacts to organisms.
These PASs are discharged to the environment, where they remain available to other
organisms. Aquatic organisms are particularly at risk, and have been studied the
most. The impact of discharge into a water body upstream of a source for drinking
water supply has not been studied, nor has the recharge area for groundwater that is
a groundwater supply. The long-term effects on organisms in the receiving water,
Copyright (C) 2007 American Water Works Association All Rights Reserved
30 Siting, Drilling, and Construction of Water Supply Wells
including on humans, is a concern. Two PAS groups have received the most
scrutiny-steroids and antibiotics-as they have existed in the environment the
longest and have the most obvious effects.
The PAS family that has attracted the most attention from a toxicological
perspective is the estrogen family. Both natural estrogens and synthetic compounds
that mimic estrogens reach the environment. Natural estrogenic compounds, such as
those used in estrogen replacement therapy, milk production enhancement,
prescribed growth enhancement in animals, athletic performance enhancement, and
oral contraceptives were among the first PASS detected. Unlike plastics and
pesticides, what little data exists indicates that these drugs are strongly estrogenic at
concentrations of (ng/L) and have been shown to alter local biota. The
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location, Protection, and Water Quality 31
Copyright (C) 2007 American Water Works Association All Rights Reserved
32 Siting, Drilling, and Construction of Water Supply Wells
decisions on expenditures, it should be noted that neither the preface to the Clean
Water Act nor the 1996 amendments to the SDWA mention cost as a part of the
laws, only protection of the public health and the ecosystem.
PERMITS
Permits are required for any well drilling operation. Exploratory drilling permits
must be secured and fees paid, generally at the state or county level. Obtaining
permits is usually the responsibility of the well driller or the engineer or
hydrogeologist in charge of the project for the owner. A hydrogeologist normally
supervises the work in the field, including the procurement of well construction
materials, well logging, conducting or overseeing geophysical logging, interpreting
logs, well designing, and certifying as-built well construction drawings.
After the exploratory work is completed, the production wells are drilled. To do
so, permits must be filed, fees must be paid, and monitoring must be conducted.
Federal, state, and local laws require information to be filed on a periodic basis
throughout the well construction process. Documentation of initial investigations,
pilot testing, and water supply development must be detailed and complete.
Multiple copies of reports pertaining to groundwater development may be required
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location, Protection, and Water Quality 33
by different agencies for differing purposes. A permit is generally required for well
completion reports, results of logging during construction, and field testing reports.
In addition to drilling and well completion reports, water quality reports
should be developed. More extensive testing of groundwater for contaminants that
may impact future implementation of regulatory requirements is recommended.
Information must also be filed with various government agencies involved in
groundwater monitoring of facilities that produce, handle, store, treat, or dispose of
chemicals determined to be hazardous to health or the environment. This
information, when combined with information provided by the groundwater well
developer, can increase understanding of the regional groundwater system under
study and its potential and reliability as a water supply.
Regulatory agencies are concerned about well construction and closure of a
well because of the possibility of cross contamination between shallow zones and
deeper high-quality aquifers. Reports that document field work can be very valuable
in later phases of groundwater development or protection. Proper land survey
location, global positioning system locations and description of the wells, and
complete as-built drawings of construction are desirable.
Permits, reports, and drawings should be planned as a part of the project. There
is a cost to provide this service on the part of engineers and hydrogeologists. Where
there is the potential for conflicts over water use, it may be desirable to consult an
attorney knowledgeable in aspects of the law involving groundwater and permit
procedures. Reports from the drilling process may be of great value in litigation and,
therefore, should be prepared with care and be subjected to appropriate legal,
technical, and managerial review.
REFERENCES
Arcand-Hoy, L.D., and Benson, W.H. 1998. Fish Reproduction: An Ecologically Relevant
Indicator of Endocrine Disruption. Environmental Toxicology und Chemistry,
17(1):49-57.
Asano, T. 1991. Planning and Implementation of Water Reuse Projects. Water Science and
Technology,24(9):1- 10.
Block,J.C. 1989. E s e s in WaterSupplies-Detection and Identification. New York: VCH Press.
Bloetscher, F., and Fergen, R.E. 2001. Are Pharmaceutically Active Substances (PASS)the
Next Major Water Pollution Issue?In Proc. of the Florida Section American Water Works
Association Annual Conference, Orlando, Fla.
Bloetscher, F., Muniz, A., and Witt, G.M. 2005. GroundwaterInjection:Modeling, Risks and
Regulations.New York: McGraw-Hill.
Bloetscher, F., Witt, G.M., and Dodd, A.E. 1997. Bacterial Issues in Raw Water Treatment.
In Proc. of the Florida WaterResource Conference, Orlando,FLa.
Bouwer, H. 1991. The Role of Groundwater Recharge in the Treatment and Storage of
Wastewater for Reuse. WaterScience and Ethnology, 24(9):259-302.
Copyright (C) 2007 American Water Works Association All Rights Reserved
34 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Regulations Regarding Well Location, Protection, and Water Quality 35
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods
Wells can be viewed as large holes in the ground, deeper than they are wide, and the
water supplied by them is relied on by water customers, agriculture, and other
interests. In addition to providing available water supply reliably, wells are designed
to last for 50 years or more, and the steps initially taken to design and drill the well
play a large role in the longevity of a well. Proper well construction should be based
on a thorough engineering study and designed to best accommodate existing
conditions and requirements.
There are many drilling and well construction methods that have been
developed depending on the purpose for which the well is to be constructed. Some
purposes for wells include
Water production (the focus of this handbook),
Oil and gas wells,
Geothermal wells,
Injection/disposal wells,
Aquifer storage and recovery wells, and
Environmental remediation and monitoringwells.
Environmental remediation wells are the shallowest of this group, often less than
20 feet deep, but oil and gas wells may be tens of thousands of feet deep. Water
supply wells fall somewhere in between.
Just as there are many purposes for wells, there are even more options for their
construction, including the following:
Hand dug Large diameter auger
Cable tool 0 Screened stem auger
Hollow stem auger Solid flight auger
Copyright (C) 2007 American Water Works Association All Rights Reserved
38 Siting, Drilling, and Construction of Water Supply Wells
Dug Wells
Hand digging wells is the oldest method of water well construction. As is to be
expected, hand digging a water well is extremely labor intensive, dangerous, and
time consuming. A dug well is frequently excavated using a pick and shovel, and a
hoist with a bucket. They are large in diameter, but relatively shallow (i.e., less than
30 ft in depth). Most dug wells are circular because this shape adds strength and is
usually easier to dig. Such wells can furnish relatively large supplies of water from
shallow sources. Depending on the formation, the well may be able to stand without
reinforcement, but more commonly, pilings, concrete, or bricks are used to create
support walls.
Once the top of the water table is encountered, it is very difficult to advance the
depth of the well into the aquifer. The limited production horizon severely limits
the quantity of groundwater available for extraction. The narrow production zone
also leaves the well vulnerable to changing water level elevations. During times of
little precipitation or drought the water table will become lower and lower.
Eventually the tap of the water table will be located below the bottom of the open
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 39
Well-Point Pump
Well Points
‘‘9
Figure 3-1 Operation of well points
hole, resulting in a dry well. The negative impacts of a well “gone dry” on a local
community are obvious.
Hand dug wells are rarely adequately protected from contamination. Impacts to
the well from surface run off, airborne material, animals, insects, and objects falling
into or finding entrance into the well are common. Concrete curbs are commonly
constructed around the edges because dug wells are easily polluted by surface water.
Although hand dug wells are still constructed in many parts of the world, they are
not commonly used as a source of groundwater for a modern water supply system in
developed countries and are rarely used in the United States.
Driven Wells
A driven well consists of a pointed steel screen, called a drive or wellpoint, and
lengths ofpipe attached to the top of the well point (see Figure 3-1). Well points are
driven into the formation with a weight, derrick, and pulley system. The driver
weighs between 30 to 75 lb and well points can be mechanically driven as deep as 50 ft.
If the diameters are small, they can occasionallybe installed by a hand driven system.
Figure 3-2 presents instruction as provided by the C.L. North Company of El Paso
Texas for the installation of driven wells. When constructing a driven well, an outer
casing is first installed by pounding the pointed screen into the formation. The steel
tip breaks through pebbles and thin layers of material and opens a passageway for
the screen. For small municipal water supplies, the driven well may be used in thin
deposits of sand and gravel found at shallow depths. The outer casing protects the
inner casing to which the pump is attached.
Copyright (C) 2007 American Water Works Association All Rights Reserved
40 Siting, Drilling, and Construction of Water Supply Wells
In sand and gravel formations, the outer casing should extend to just above the
drive point. The outer casing can be driven with a sledgehammer, or for larger pipes,
a tripod and pulley can be used. The tripod and pulley set-up raises and lowers a
heavy block onto a drive cap placed on top of the outer well point casing. Extra
heavy pipe should be used to withstand the load. If the ground is clay, the outside
casing should be set in a hole prepared by an auger prior to inserting the well point.
After the outer casing is set, the annular space between the bore hole and the outside
of the casing should be sealed with cement grout.
Driven wells range from 1 to 4 in. in diameter and rarely are driven more than
30 ft. The screen is an integral part of the portion driven into the ground, therefore,
only soft materials are easily penetrated. As a result, the production rate of driven
wells is limited. Instead of a single well, a battery of well points, with the wells
located a reasonable distance apart and connected by a common header to the
pump, can develop sufficient water to supply a small community. However, driven
wells are typically used to dewater construction sites.
California
The California, or stovepipe, method of well construction was developed in
California for water wells drilled in unconsolidated alluvial materials. Large wells,
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 41
16 to 20 in. (400 to 500 mm) in diameter and up to 300 ft (90 m) in depth, are
constructed using this method. The California drilling method uses the same
general principles used for cable tool rigs. Short lengths of sheet metal, either riveted
or welded together, are used for casing. After the casing is in place, it is perforated
using a Mills knife or similar device that tears the metal. The openings must not be
too large or the area perforated too much.
Jefting
Jetting is used to construct wells when water is found in sand at shallow depths,
although the method is applicable for deeper wells. Jetting equipment consists of a
drill pipe, or jetting pipe, that is equipped with a cutting bit on the bottom end.
Water is pumped into the well through the drill pipe and out of the drill bit against
the bottom of the drill hole. The casing usually is sunk as drilling proceeds. Jetted
wells are usually small in diameter, therefore deeper well construction becomes more
difficult to manage and control. To solve this problem, several lengths of casing with
different diameters may be telescoped one inside the other to reach the full depth.
Certain conditions make this method of well construction difficult. Rock and
boulders are barriers that cannot be overcome by water pressure, regardless of how
high the pressure might be. Formations of clay and hardpan become soft and sticky.
BUCKET-TYPE DRILLING
Although the previously described methods are used in many areas, they are rarely
used to supply treatment facilities serving local communities. The following methods
are more commonly used to establish well fields capable of meeting local demands.
Bucket-type drilling uses a rotating cylindrical bucket. Cutting blades mounted
on the bottom of the bucket cut the sediments, and the pieces of sediment are
retained in the bucket. When the bucket is full, it is withdrawn from the borehole,
swung to the side, and the hinged bottom is opened releasing the cuttings. Bucket-
type drilling can be used to drill wells from 10 to 60 in. in diameter and to a
maximum depth of about 100 ft.
Sediment samples recovered during borehole advancement are used to identify
the penetrated formations. Bucket drilling requires little or no fluid to be added to
the borehole during drilling, allowing for the recovery of water samples for analysis.
Bucket-type rigs are relatively simple in design and are capable of drilling quickly.
Figure 3-3 shows an example of a bucket-type drilling rig. Often, casing is advanced
into the borehole as part of the drilling activity. An advantage of this method is the
reduced possibility of cross contamination of fluids during drilling.
Bucket-type drilling produces a large quantity of cuttings and, once the
saturated zone has been penetrated, large volumes of fluids. Generally limited to
poorly lithified cohesive sediments, bucket drilling may be continued into sand and
sometimes gravel if the casing is advanced into the borehole during drilling, or if the
Copyright (C) 2007 American Water Works Association All Rights Reserved
42 Siting, Drilling, and Construction of Water Supply Wells
borehole is kept full of water. Once even moderately lithified sediments are
encountered, they will usually prove to be too resistant for bucket-type rigs to
penetrate.
The use of bucket-type drilling is dependent on the sediment types anticipated
to be encountered. Good results can be realized on generally unlithified cohesive
formations, such as glacial tills. Formations consisting of large boulders, competent
shale, chalk, or sandstone are extremely difficult if not impossible to penetrate using
this method, and it is impossible to penetrate well-lithified sediments, igneous, and
metamorphic rocks.
CABLE-TOOL METHOD
Cable-tool methods are also called percussion, spudder, and solid tool methods. The
cable-tool method was used as early as 300 BC to drill salt wells in China to depths as
great as 3,000 ft. Cable-tool drilling methods are commonly used today for shallow
wells but can be used for wells as deep as 1,000 ft. Cable-tool methods are
straightforward. The technical expertise required is less than for some other
methods although the details of construction and operation of the drilling machines
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 43
Sourre: www.esd.lbl.gov
Figure 3-4 Cable-tool drilling
vary widely. This drilling method is older than most other methods and is well
understood.
All cable-tool rigs create the borehole using the percussion and cutting action of
a drill bit. Figure 3-4 shows a cable-tool drilling rig. Cable-tool drilling is
accomplished by alternately raising and dropping a heavy drill bit (Figure 3-5)
suspended at the end of a cable, thereby pulverizing the formation below. As shown
in Figure 3-4, a casing is often used to keep the hole open when drilling in loose
material. The drill bit, a club-like, chisel-edged tool, breaks the formation into small
fragments. The bit turns with each blow. The bit is then returned to the bottom of
the borehole and the process is repeated until the desired depth is achieved. Cable-
roo1 wells can be from 4 to 18 in. in diameter. The length of the drill cable is
adjusted so that the bit will strike with the right amount of weight and stroke. The
cable is monitored to determine how well the tools are operating. The length of
stroke and rapidity of blows are continuously adjusted to maximize the rate of
penetration.
After several feet (one to two meters) of borehole are drilled, the bit and drill
string are pulled from the hole and swung aside. A bailer is used to remove the slurry.
The bailer consists of a 10- to 25-ft (3- to 8-m) long section of tubing with a check
valve in the bottom (see Figure 3-6). The bailer is smaller in diameter than the drill
hole so that it can move up and down freely ( A W A , 2003). Once the borehole has
Copyright (C) 2007 American Water Works Association All Rights Reserved
44 Siting, Drilling, and Construction of Water Supply Wells
Direction of Stroke
t
Water Force
Source: http://mo.water.usgs.gov
Figure 3-5 Cable-tool bit Figure 3-6 Bailer
been cleared of cuttings the bit is returned to the bottom of the borehole, and the
process is repeated until the desired depth is achieved.
The borehole must be straight and vertical, or plumb, for ease of operation and
for installation of casings, pumps, screens, and column pipes. In extreme cases,
lowering a pump into a well or pulling i t out may become impossible if the well is
not plumb. The first indication that the hole is not plumb is that the drilling tools
begin to stick. When this happens, drilling should stop and the hole realigned.
Although used less frequently, cable-tool rigs have certain advantages. The
ruggedness and simplicity of the drill rigs makes them easy to move across rough
terrain. Ease of repair also makes them ideal for isolated areas without access to
repair parts or power. Because little or no outside drilling fluids are introduced to
the well during drilling, representative water and formation samples can readily be
recovered as drilling progresses. Water is usually not necessary as drilling mud is not
used during operations, minimizing plugging of the formation and simplifying
development of the well. The use of a bailer to remove the cuttings from the well
aids in keeping the native formations clean of sediments produced during drilling.
Each time the bailer is removed from the borehole it is filled with cuttings and
formation fluids. Removal of these solids and fluids allows the formation fluids to
flow from the formation into the borehole, keeping the borehole wall clean. Most
types of formations can be drilled unless they are either very hard or very soft (clays).
Limited damage to the formation adjacent to the borehole occurs as the borehole
force is downward. In most cases, a cable-tool rig is light and can traverse rough
country easily.
Cable-tool drilling methods are slow, providing poor productivity in hard
formations or deep wells. The limitation of diameter may be a concern for high
productivity needs. The casing must often be advanced with the drill bit to maintain
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 45
the competency of the borehole and to prevent formation fluids and previously
drilled sediments from migrating within the hole. The action of the bit can damage
the borehole wall, resulting in a lower well efficiency than desired.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Next Page
46 Siting, Drilling, and Construction of Water Supply Wells
Reprinted from Ground WaterMonitoring & Review with permission of the National Ground Water Association.
Copyright 1987.
Figure 3-7 Hollow stem auger
has been achieved and the pilot bit has been removed, the well screen and riser can
be easily lowered down through the center of the augers. The well-screen gravel pack
is placed as the augers are pulled, not rotated, out of the borehole.
Advantages of the hollow stem auger drilling method include the following:
Drilling fluids are not introduced.
The borehole is drilled and the casing can be placed simultaneously.
Representative samples of aquifer fluids and formation material are easily
collected in uncontaminated condition.
0 The'drilling technique is fast.
However, hollow stem drilling methods are limited to softer formations, such as
loose sand, gravel, or unconsolidated formations. An auger can be used only where
formations, though relatively soft, will permit an open hole to be bored to depths
ranging from 25 to 60 ft (8 to 18 m) without caving. The most suitable formations
for bored wells are glacial till and alluvial valley deposits. The depth and diameter
are limited as well. Wet formations, such as running sands, will make drilling nearly
Copyright (C) 2007 American Water Works Association All Rights Reserved
Previous Page
Drilling Methods 47
ra
Pilot P
impossible and will contaminate water quality samples and formation samples.
Generally speaking, this type of well is not used for municipal supplies.
Copyright (C) 2007 American Water Works Association All Rights Reserved
48 Siting, Drilling, and Construction of Water Supply Wells
Rig
J
Drill Pipe
Mud Flow
*
drill string and out of the bit. The cuttings are returned to the surface by the drilling
fluid as it rises in the annular space between the drill string and the drilled
formation. The drilling fluid is cleaned and recirculated through the drill string.
Bit selection depends on the anticipated formations to be encountered. Figure
3-1 I shows a cutaway view of a typical tricone mill-tooth rotary drill bit. The bit size
is roughly the diameter of the borehole drilled. Different types of bits are used
depending on rock hardness and composition. Figure 3-12 shows a chart for bit
selection. Figures 3-13 to 3-15 show various bits and the type of rock for their
appropriate use. Drag bits have no moving parts: the blades (see Figure 3-13) are
designed to cut into soft formations, such as clay and poorly consolidated sands.
Mill tooth tricone bits (Figure 3-14) are used for moderately hard formations, while
tricone bits with carbide button inserts are used for harder formations, such as well-
cemented sandstone, micritic limestones, and dolomites. For very large diameter
drilling applications flat bottom bits are used (Figure 3-15). These are large drill bits
with many cutting heads.
Drill collars are heavy walled pipe machined from solid bars intended to keep
the borehole straight and plumb by placing weight directly on top of the bit (see
Figure 3-16). Drill collars allow weight to be placed directly downward to keep
pressure on the bit and force it into the rock. The combination of directing weight
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 49
Rotary Drill
Source: www.globalsecurity.org
Figure 3-12 Chart for bit selection
Copyright (C) 2007 American Water Works Association All Rights Reserved
50 Siting, Drilling, and Construction of Water Supply Wells
Source: wwwsorquato.com
Figure 3-1 3 Drag bits for unconsolidated and soft sediments
Source:John Largey
Figure 3-14 Tricone bits for moderately hard to hard formations (rear, mill tooth;
front, button)
downward and preventing bit wandering improves the efficiency of the bit action in
crushing the rock. Stabilizers (Figure 3-17) are positioned at various locations
within the lower part of the drill string. They are used to maintain borehole
geometry by keeping the bit and drill collars straight and plumb.
The drill pipe is normally in 20 or 30 ft sections referred to asjoints of pipe (see
Figure 3-18). It is usually made of manganese-carbon steel or a molybdenum alloy
steel. Drill pipe used for water well drilling is generally is 2.375 to 4.500 in. in
diameter. Proper size is important to minimize friction loss and therefore reduce
power required to rotate the drill string. The drill pipes are connected together with
threaded tool joints, which should be cleaned and lubricated before each connection
to prevent the threads from seizing.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 51
Figure 3-15 Flat bottom bit for large diameter drilling applications
Copyright (C) 2007 American Water Works Association All Rights Reserved
52 Siting, Drilling, and Construction of Water Supply Wells
Source:John Largey
Figure 3-18 Picking up drill pipe
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 53
- -
x
I _ "
NOTE:The overflow pipe, settling basin, and mud basin generally sit on the surface (as shown) or are cut 2-3 ft
into the surface
Figure 3- 19 Typical mud circulation system
and storage pits are simply dug into the ground and not lined. In many locations,
this type of circulation system is prohibited to prevent discharges that may affect a
surficial aquifer.
Drilling fluids perform four primary functions (Lehr, et al., 1988)
1. Remove the cuttings below the rotating bit,
2. Transport the cuttings up the borehole to the surface.
3. Maintain borehole stability.
4. Cool the bit.
In addition, additives such as drilling mud (Lehr, et al., 1988) assist to
Prevent fluid entry from the porous rocks,
Reduce drilling fluid losses into the formation,
Copyright (C) 2007 American Water Works Association All Rights Reserved
54 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 55
viscous enough to carry the cuttings to the surface given a certain up-hole velocity,
but to drop the cuttings quickly once it is returned to the mud system. Drilling fluid
viscosity is measured with a Marsh funnel. The drilling fluid is poured into the
funnel and the viscosity is determined by the amount of time (in seconds) it takes to
drain one quart out of the funnel. Lehr, et al. (1988) indicates that a good Marsh
funnel viscosity ranges from 35 to 45 sec. If the circulating mud begins to pick up
sand, the weight will increase, and viscosity will decrease. Under such conditions,
additional water or other additives should be mixed into the mud.
Settling is needed to remove the cuttings and allow recovery of the cuttings for
professionals to determine formation type and to make decisions about the
formations most likely to yield water. Once the mud is returned to the surface, it is
directed to the cleaning portion of the mud system. Shale shakers are used to first
remove the large cuttings (see Figure 3-20). Upon returning to the surface, the
drilling mud is directed over vibrating screens. In sandy formations, de-sanders can
also be used to remove excessive sand from the drilling mud (see Figure 3-21).
Drilling mud that is too thick will be difficult to clean and to remove from the
borehole wall once drilling is complete, extending the amount of time required for
well development. Low viscosity mud often has 10 to 15 percent solids, composed
mostly of heavy sand. If the viscosity is too low, cuttings will not be brought to the
surface, and lubrication will be inadequate for the drill bit and collars. Such a
situation increases the likelihood of the drill string getting stuck and the loss of
drilling fluids into the formation. Observation of the recovered cuttings can provide
insight into the efficiency of the mud cleaning system. Because the drilling mud
continuously circulates through the hollow drill pipe to the bit and back to the
surface, sand grains that are recirculating will become smaller and more rounded.
Copyright (C) 2007 American Water Works Association All Rights Reserved
56 Siting, Drilling, and Construction of Water Supply Wells
In highly porous formations, the low viscosity mud can migrate into cavities in
the formation prior to the mud building up on the borehole wall. This loss of
drilling mud can be a significant problem for the drill crew and may create
regulatory compliance concerns. At the same time, the sand content may decrease
where clays or other fines are introduced into the mud and not settled in the settling
basin. In such cases, the mud may need to be reconditioned.
Gel strength is a measure of the ability of the mud to suspend the cuttings in the
mud. Proper gel-strength drilling mud will suspend the cuttings in the mud when
circulation is stopped to add another section of drill pipe (make a connection),
thereby preventing the cuttings from settling on the bit, potentially causing it to
seize. However, if the gel strength is too high, large volumes of mud will be lost over
the shale shakers and the cuttings will not settle in the settling pit.
Mud rotary drilling systems use two basic drive systems. Rotary table drives rely
on a rotary table recessed into the floor of the drilling rig. A kelly bushing fits into
the rotary table. A multisided pipe, called the k d y , is attached to the top of the drill
string and slides through the kelly bushing. The rotational forces are transferred
from the rotary table, to the kelly bushing, to the kelly and through the drill string.
Top drive rigs have a hydraulic motor suspended from the traveling block. The drill
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 57
string is directly connected to the hydraulic drive motor (see Figure 3-22). Rotary
table systems use higher rotation speeds with lower torque resulting in higher rates
of penetration, but they also have a greater tendency for the borehole to deviate
from a vertical track. Top head drive systems, with lower rotational speeds and
higher torque, tend to drill a little slower than rotary table systems but generally drill
a more vertical hole.
Mud rotary drilling systems have a number of advantages over cable-tool and
auger systems. The first advantage is that they are much faster and can drill deeper
holes with much larger diameters. Good quality lithologic samples can be gained if
careful attention is paid to the amount of time it takes for the drilling fluid to reach
the surface (lag time). Because a casing is not installed during the drilling operation,
high quality geophysical logs can be conducted on open-hole sections.
However, mud rotary drilling has several disadvantages over cable-tool and
auger systems. Extensive knowledge of and experience with drilling mud properties
and interaction with various types of formations is essential. Problems with rotary
drilling methods occur when lost circulation zones are encountered and large
quantities of the mud are lost in highly porous formations, caverns, and fractures,
and become difficult to remove during development. Sidewall pressure is not
Copyright (C) 2007 American Water Works Association All Rights Reserved
Next Page
58 Siting, Drilling, and Construction of Water Supply Wells
”-
maintained under these circumstances, thereby allowing the potential for the
collapse of the borehole. A thick filter cake may also reduce upward velocity of the
drilling fluid and may interfere with the movement of the drill pipe and the installation
of casing, Use of drilling mud requires a significantlylarger site to stage, service, and
condition the mud. Potable water is also required, a problem in undeveloped areas.
Likewise, the mud must be brought in and hauled out after use, another problem in
many areas. Water samples cannot be secured during drilling operations-a packer
test must be used on completion of the drilling operation to isolate potential water
production zones.
Extensive development is required for mud rotary drilling operations because
of the introduction of drilling mud into permeable formations (the ones that are
most likely to yield water). The inability to remove the mud will reduce aquifer
yield. Monitoring the mud, mud quality, and drill string are among the reasons that
more technical expertise is required on the drill rig for rotary drilling methods.
Caution must be exercised when planning for the use of the mud rotary method
in an active well field. In such a situation, the borehole may intercept the cone of
influence of nearby producing wells. This can cause drilling mud to migrate from
the borehole being drilled toward the active wells, resulting in contamination of
these wells and a reduction in the yield from the aquifer. As a precaution, it is
recommended that active wells be taken out of service during the drilling of the new
wells. Preplanning and coordination with the facility affected by shutting down the
production wells will result in smoother running field operations.
A variation of the mud rotary method is the air rotary method. Air rotary
drilling entails using air as the drilling fluid instead of mud. Air rotary systems have
higher operating costs as a result of the power required to force air into the borehole
with enough force to dislodge the formation materials. Over time, these costs have
decreased. Pressures are 40 to 50 psi. Annular velocity is 2,000 to 5,000 ft per
minute for dry air. The annular velocity is based on borehole size, drill pipe size, and
air compressor capacity. Although air rotary drilling can result in very high drilling
costs, this drilling process can only be used where borehole stability is not a concern.
Introduced in the late 1970s, drilling with foam is also an option. Foam is
created by aerating the drilling fluids. It increases penetration rates when compared
to mud rotary drilling and does help stabilize the borehole to some degree. The
foaming agents must be a biodegradable liquid mixture of anionic surfactant, which
is added to fresh, hard water. The slow-moving foam has greater capacity for
carrying cuttings to the surface when compared to conventional air rotary drilling.
Other advantages include
Reduced air volume,
Reduced pressure requirements,
Increased well cleaning capabilities,
Copyright (C) 2007 American Water Works Association All Rights Reserved
Previous Page
Drilling Methods 59
REVERSE-CIRCULATION ROTARY
The reverse-circulation rotary method is virtually identical to the hydraulic rotary
method of drilling except that the drilling fluid circulates in the opposite direction.
Reverse-circulation drilling is best for large diameter, high capacity wells for large
water use projects. It is also less expensive than some other methods. Lehr et al.
(1988) notes that many wells have diameters of at least 24 in., with some having
diameters of more than 60 in. The reverse-circulation method typically uses clear
water with no mud additives. A pit is constructed so that the drilling fluid will flow
down the annular space between the bore hole and the drill pipe and return through
the bit and the inside of the drill pipe to the surface, carrying the cuttings with it. A
high-capacity pump is attached to the drill pipe to keep the fluid moving at high
velocity.
The borehole is stabilized by the hydrostatic pressure of the fluid in the
borehole. The fluid level is maintained at the ground surface. Keeping the borehole
open requires a large volume of water to maintain a head above the natural static
water level, which results in a flow into the formation. This higher head prevents the
wall from caving. Significant damage or collapse of the borehole may occur if fluid
circulation is lost. Caving may result from movement of fluid down the borehole
when formation materials will not accept water. If the formation is highly
permeable, the required head will be difficult to achieve. In such cases, processed
clays may be added to create a filter cake similar to the straight rotary process.
However, this defeats the primary advantage of the reverse-circulation method of
construction. In wet clay soils, collapse is a problem. Caustic soda is used to raise the
pH. Another option is to increase the amount of sodium silicate in the mud.
Bentonite mud can also be used to prevent collapse of clay formations. In some
instances, 20 to 50 gpm of make-up water may be needed in highly permeable soils.
This is in addition to the 500 gpm circulation rate of the mud.
Advantages of the reverse-circulation method include its ease of use in
situations where artificial-gravel-pack wells are specified because less mud cake
forms on the face of the borehole. Less development time is required because mud
does not intrude into porous formations. Test wells can be drilled and abandoned at
a minimum expense by plugging. The reverse-circulation method is also generally
faster than cable-tool drilling for drilling larger diameter wells, greater than about
18 in. However, the reverse-circulation method may prove problematic in soft,
loose, unconsolidated materials, such as dune sand and quicksand, because the water
pressure cannot keep the hole open.
Copyright (C) 2007 American Water Works Association All Rights Reserved
60 Siting, Drilling, and Construction of Water Supply Wells
REVERSE-AIR CIRCULATION
Reverse-air drilling methods have many of the characteristics of hydraulic rotary
drilling except that drilling mud is not used: air is. With reverse-air drilling, a small
steel or PVC air line connected to an air compressor is run inside the drill pipe. The
formation cuttings and formation water are lifted inside the drill pipe (see Figure 3-23).
Reverse-air drilling is capable of drilling large diameters wells in many formation
types. The wells can be drilled quickly and high quality lithologic samples can be
gathered. High quality water samples can also be obtained because there are no
drilling fluids recirculated into the borehole.
Advantages of reverse-air drilling include speed of drilling and the ability to
drill a wide variety of formation types. Reverse-air circulation is highly effective in
cavernous and karstic formations. Uncased formations from reverse-air drilling
permit excellent geophysical logs to be obtained. Sampling of water and obtaining
high quality cuttings are major reasons for pursuing reverse-air circulation methods.
The disadvantages of this method include the potential for bit plugging, cross
contamination of the aquifer, and intermixing of unconsolidated sediments in the
borehole. Stability of the borehole in deep, unconsolidated formations may be a
problem as no mud cake forms on the borehole.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 61
Movement of Water
(and Air) and Soil
Copyright (C) 2007 American Water Works Association All Rights Reserved
62 Siting, Drilling, and Construction of Water Supply Wells
the sampling cyclone, respectively. The air and cuttings return to the surface
through the inner tube to a sample cyclone where lithologic samples are recovered
(see Figures 3-26 and 3-27). Significant cores of the formation are recoverable with
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 63
DOWN-THE-HOLE-HAMMER
As with many other industries, well drilling has seen the introduction of new
methods in recent years. One of the more popular, and useful, is the down-the-hole-
hammer (DTHH) method shown in Figure 3-28. This drilling method combines
some of the elements of hydraulic drilling with those of the cable-tool method. The
turning action of the rotary rig is combined with the percussion action of cable-tool
drilling. A pneumatic drill is located at the bottom of the drill string. Air delivered
from an adequately sized compressor actuates a down-hole air piston, transmitting
blows from the bit to the formation. The repeated blows are similar to those
delivered by a cable-tool rig. The air used to actuate the hammer also removes the
cuttings from the borehole similar to reverse-air rotary drilling. Occasionally, as in
air rotary drilling, foaming additives are added to aid in removal of the cuttings.
This eliminates the need to remove the bit from the borehole and recover the
Copyright (C) 2007 American Water Works Association All Rights Reserved
64 Siting, Drilling, and Construction of Water Supply Wells
Movement of Cuttings
Soil
Downhole Hammer
. Bit
cuttings by using a bailer. As the blows are delivered, the drill pipe is slowly rotated
by either a top head drive or a rotary table. The rotating motion and the removal of
the cuttings allow the bit to deliver each successive blow to a different, clean surface
instead of repeatedly striking the same surface or previously cut rock fragments.
DTHH works well in situations where hard formations are anticipated and
borehole stability is not an issue. Wells drilled using this method are commonly
6 in. in diameter although hammer sizes range to about 17 in. in diameter.
Advantages of the DTHH method include
Rapid removal of cuttings,
Drilling mud not used,
High penetration rates in resistant formations,
High quality water and lithologic samples recovered,
Excellent geophysicallogs obtained, and
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 65
CORING
Coring, which is not a primary method of drilling, is used extensively to collect high
quality lithologic samples. Cores are cylinders of rock recovered from the formation
(See Figures 3-29 and 3-30). A number of tests maybe conducted on cores,
including hydraulic conductivity, porosity, permeability, and compressive strength.
This information will help professionals determine the appropriate factors to
include in designing the well pumps and determining the safe yield of the well. To
recovet a core, the following procedure is used:
0 Drill a pilot hole to the top of the formation where the core is to be recovered.
0 Trip out drill bit and drill pipe.
0 Trip in core barrel and drill pipe (see Figure 3-31).
0 Cut the core out of the formation where the core is desired. It is essential that
the core be cut, not pushed into the barrel.
0 Trip out the core barrel and drill pipe.
0 Recover the core.
Copyright (C) 2007 American Water Works Association All Rights Reserved
66 Siting, Drilling, and Construction of Water Supply Wells
External Greasing
Simple Adjustment
Double-Race Bearings or
Heavy-Duty Bearing Assembly
Small Large
Diameter Diameter
Barrels Barrels
The core should be placed in a box and labeled with core recovery date, depth,
well, and relevant observations at the time of collection. For core recovery, it is
essential that an experienced driller be used.
Drill to the next point where a core is desired.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Drilling Methods 67
Copyright (C) 2007 American Water Works Association All Rights Reserved
68 Siting, Drilling, and Construction of Water Supply Wells
is also an issue that must be planned. Waste cannot be placed on the surface or
disposed of on the ground. For instance, saltwater usually must be trucked off-site
for treatment. Sewers are not often availablewhere wells are being drilled and if they
are, the utility may not want drilling fluids in the sewer system. Federal, state, and
local regulations should be consulted prior to initiating a drilling project.
Copyright (C) 2007 American Water Works Association All Rights Reserved
REFERENCES
AWWA (American Water Works Association). 2003. Manual M21-Groundwater. Denver,
Colo.: AWWA.
Hackett, G. 1987. Drilling and Construction Monitoring Wells With Hollow-Stem Augers;
Part 1: Drilling Considerations. Ground WaterMonitoring 6Review, 7(4):51-62.
Lehr, J., Hurlburt, S., Gallagher, B., and Voytek, J. 1988. Design and Construction of Water
Wells: A Guide for Engineers, National Water Well Association. New York: Van
Nostrand Reinhold.
Scalf, M.J., McNabb, W., Dunlap, R., Crosby, R., and Fryberger,J. 1980. Manualfor Ground
Water Sampling Procedures. Ada, Okla.: R.S. Kerr Environmental Research Laboratory,
Office of Research and Development.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical Logging and Field Testing
Once the potential sites for the well location have been selected, a series of tests
should be run to better define the parameters of the subsurface environment,
including the quantity and quality of available water. These initial subsurface
investigations generally begin with construction of an exploratory or test well. The
goal of exploratory wells is to locate productive aquifers that yield sustainable high-
quality water. The initial test wells are used for lithologic logging, geophysical
logging, aquifer testing, and to collect cores and cuttings of the formation.
Lithologic sampling is the protocol used to obtain core samples and define the
formation type by depth. Geophysical logging consists of a variety of electronic
instruments used to define the rock types, water quality, porousness, and other
aquifer characteristics. Geophysical logs were developed by the oil and gas industries
for exploration. Depending on the needs from the well, a number of formations may
yield sufficient quantities of water for some period of time. However, for water
supply production wells, large, rechargeable aquifers are desirable. The following
aquifer formations are more likely to provide sufficient water for public water
supplies:
0 Shell, unconsolidated sands, and gravels of alluvial or glacial origin
0 Sandstones and conglomerates
0 Limestone
0 Porous or fractured volcanic rocks
Exploratory wells are drilled to determine an aquifer's characteristics,including
hydraulic conductivity, water quality, thickness, and areal extent. Newly drilled wells
can be used for borehole geophysical logging and aquifer testing. The drilling
method is dependent on the type ofwater samples desired and formation types that
are expected to be encountered during drilling (see chapter 3). As noted in chapter 1,
hydrogeologic reports already exist in many regions. From these interpretations,
Copyright (C) 2007 American Water Works Association All Rights Reserved
72 Siting, Drilling, and Construction of Water Supply Wells
~I
100 I00
msssiwsand ,with shale partingsfiningup
I10 110
120 120
smdyshafr tu,ith lexf fossil+ o n t i n u o w
130 130
sandyshde with l e d fossils Cmtinuws
potential aquifers can be identified. However, the increase in the need for new water
sources requires investigation in areas where little historical information is available.
Exploratory drilling efforts can fill in the details of the specific local hydrogeologic
environment in which drilling is proposed.
LITHOLOGIC LOGGING
The information required to develop lithologic logs is gathered while drilling is in
progress. Cores, cuttings, water samples, drill response, and other methods are used
to identify the different formation types encountered while drilling. The result will
be a lithologic log similar to that shown in Figure 4-1, which summarizes the
encountered subsurface formations. As noted in chapter 3, to accurately identify the
formation, the methods for drilling the well may be limited. Care must be exercised
by the driller in collecting water and formation samples. As the cuttings rise, the
quality of the cuttings may be affected by many variables such as the drilling
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 73
method, the time it takes for the samples to reach the surface (lag time), and
contamination from formations already penetrated. Therefore, the actual changes in
lithology may be only generally known. While useful for targeting further
investigations, only limited information about the aquifer parameters can be gained
from the cuttings and cores. Most hydrogeologists use lithologic logs to identify
specific areas where usable water is likely to be encountered in large quantities and
therefore requiring further investigation and geophysical logging.
Copyright (C) 2007 American Water Works Association All Rights Reserved
74 Siting, Drilling, and Construction of Water Supply Wells
The purposes and uses of various geophysical logs are outlined in the following
sections. Borehole logging is highly technical and quite involved, and no lay person
should use the information provided herein to attempt to interpret logs based solely
on the information provided. Log interpretation requires the use of experts using
specialized equipment. Accurate lithologic logging during drilling is crucial, so an
experienced geologist, hydrogeologist, groundwater engineer, and driller experienced
in well logging should be employed. Often it is wise to retain the expertise of a
logging specialist to evaluate logs. The equipment that is used is both extensive and
expensive. Specialty companies are usually hired to perform the logging and
interpretation the well site (see Figure 4-2). The discussion herein is designed to
provide insight on the capabilities and limitations of the logging tools found to be
most useful for groundwater exploration and to help water professionals understand
why certain logs should be used.
Geophysical logging is extensively used in the oil industry, and it is for oil
exploration that most of the logging techniques have been developed. As a result,
the focus of many logs and the geophysical logging industry in general is geared
toward petroleum, not clean water, which is rarely encountered in conjunction with
oil. Most of the texts on borehole logging present information tailored toward
petroleum exploration. The presence of low or nonsaline water in a formation
mandates the use of special analyses for interpretation. For a detailed discussion of
this subject, the reader is referred to Borehole Geophysics Applied to Groundwater
Investigation$,published by the National Water Well Association (Keys, 1989).
Single logs in a well are almost useless because there is limited basis on which to
interpret the log variations. Therefore, the use of multiple logs (a suite of logs) in a
single well will provide confidence in interpretations. Each type of log measures
different physical properties, and a combined analysis may resolve ambiguities that
might exist from a single log. The greater the number of wells logged in an area, the
greater the statistical confidence in the data and interpretations as being
representative of the subsurface environment. In addition, there are both surface and
subsurface methods that may prove useful. Surface methods are used to guide
subsurface logging.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical Logging and Field Testing 75
Electrical Resistivity
Electrical resistivity is probably the most commonly used surface geophysical
method for groundwater investigations. To gather data, electrodes placed into the
surface of the ground transmit current through the earth, and the voltage potential
is measured between two points near the center of the generated field (see Figure 4-3).
With the most common electrode arrangements, such as the Schlumberger array
and Wenner array, readings can be gathered using constant electrode spacing
(horizontal profiling), or the readings can be gathered at one location with
expanding electrode spacing (electrical sounding). The first method will show
apparent resistivities of materials at roughly the same depth along the transect
(two-dimensional),while the second method produces a depth profile of resistivity
(three-dimensional:AWWA, 2003).
Electrical resistivity is strongly affected by water content. As a result, data
collected involving the unsaturated zone can make interpretation of the saturated
zone quite difficult. Resistivity is largely determined by the rock-matrix density and
porosity, or by the saturating-fluid salinity (electrical conductivity). Coarse sediments
with low clay content will generally have higher resistivity than fine-grained
Copyright (C) 2007 American Water Works Association All Rights Reserved
76 Siting, Drilling, and Construction of Water Supply Wells
Power Source
I =Amperage
"Smart" V = Voltage
Electrodes A, B, M, N =indicate points
on the electrode
sediments. Old streambeds are often laden with silt and clay, so as a result, the
variations in response allow for surface detection and mapping of buried stream
channels or the depth profiling of shale-sandstone sequences.
Surface resistance methods are generally limited to use in
Simple geologic environments, with two or three distinct layers;
Areas where depth ofpenetration is limited to about 1,500 ft (460 m);
Areas where the depth to groundwater is small, because of the complications of
unsaturated materials; and
Non-urban or undeveloped areas as a result of the presence of buried metal
pipes, wires, and similar obstructions, which dominate measurements with
unwanted noise in developed areas.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical Logging and Field Testing 77
reliable the results will be from seismic surveying. Unconsolidated sands and gravels
exhibit low propagation velocities, whereas crystalline rocks exhibit the highest
propagation velocities. Propagation velocities are higher in saturated materials,
providing detection of the water-bearing strata.
Copyright (C) 2007 American Water Works Association All Rights Reserved
78 Siting, Drilling, and Construction of Water Supply Wells
Surface
Depti-
Diameter
Caliper Logs
Caliper logs are among the simplest logs and can reveal useful information for
interpretation of other logs. A multiarmed probe is lowered into the well to
determine the geometry of the borehole and variances in diameter. Caliper logs can
provide indications of the presence of high permeability fractured or cavernous
zones (by the arms extending outward indicating a larger and rougher borehole), as
well as the occurrence of swelling clays (the arms will tighten and indicate that the
borehole is smaller than the diameter of the bit used to drill as a result of the
expanding clays) and locally well-lithified layers in friable or unconsolidated rock or
sediment (the changes in the diameter of the borehole may be significant in a very
narrow horizon; see Figure 4-4). Caliper logs are important because the
interpretation of other geophysical logs vary with the borehole diameter. A good
quality caliper log will identify where compensations must be made.
Caliper logging is conducted using a probe that usually has either three or four
levered arms. As the probe is brought up through the hole, a record of the depth and
degree of extension of the arms is made. The results provide information about the
variations in the diameter of the borehole after drilling. Asymmetry of the borehole
can be measured using the four-armed probe but not with the three-arm probe.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 79
Inductor Capacitors
/ \I I
_IL
Constant AC
Current Generator
Electrode A
Figure 4-5 System used to make conventional single-point resistance and SP logs
Therefore, caliper logs are not useful for estimating diameter inside a casing as the
calipers only measure the casing diameter. They can, however, be used to determine
unknown well diameters and to determine the integrity of casings (i.e., collapsed
casing). It is recommended, whenever possible, to run a caliper log before setting the
casing as it will provide an indication of the annular space volume that must be filled
with grout and provide an estimate of the cement requirements.
Where:
R = resistance in ohms
E = potential in volts
I = current in amps
The simplest and least expensive electric resistivity log is the single-point
resistance log. The single-point resistivity log measures the potential drop between a
surface electrode and a down-hole electrode, which are also the current electrodes
(see Figure 4-5). The single-point resistivity log is used primarily for geological
correlation and the location of bed boundaries, changes in lithology (rock
characteristics), and fracture zones. Single-point resistivity logs have a very good
Copyright (C) 2007 American Water Works Association All Rights Reserved
80 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical Logging and Field Testing 81
Copyright (C) 2007 American Water Works Association All Rights Reserved
82 Siting, Drilling, and Construction of Water Supply Wells
Surface
I
Deptt-
0
Diameter Resistance
Figure 4-7 Example of caliper and electrical resistivity log for borehole
than the formation, the logs will not yield useful results, so this log should be used in
conjunction with other logs noted in this chapter.
Electrical Conductivity
Electrical conductivity (EC) logs are based on a relationship between the specific
conductance and the concentration of dissolved solids in the water. In most cases,
calibrated logs will show that there is a relatively linear relationship between the
two-more dissolved solids means higher conductivity (see Figure 4-8). The
conductivity of specific ions are known, and a water quality analysis will permit
investigators to determine if the logging results match the water quality and where
there may be other constituents of concern.
Gamma Logs
Gamma logs measure the total gamma radiation that is naturally released from the
formation. No radioactive materials are introduced into the well. Many naturally
occurring elements have radioactive isotopes that are harmless to humans but
measurable by gamma logging tools. The most significant natural source of gamma
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 83
Figure 4-8 Conductivity relationship to dissolved solids for specific conductivity logs
radiation is the decay of potassium-40 isotope and the daughter products of the
uranium and thorium decay series. Rocks and sediments with relatively high
concentrations of potassium, uranium, and thorium have high gamma response.
Gamma logs measure the ratios of three basic isotopes to one another: uranium-238,
thorium-232 and potassium-40. Table 4-2 shows the energy for each. Gamma
results increase linearly with silt and clay content (see Figure 4-9)
Clay-rich rocks, shales, and phosphatic rocks yield a high gamma response,
whereas nonphosphatic limestones and dolomites, and quartz sandstones tend to
yield low gamma responses ( A W A , 2003). The gamma log is the most commonly
used nuclear log. Gamma logs can be correlated with rock types based on the
radioactivity of the formation, cuttings, and cores. The amplitude of gamma logs
can be modified by changes in the density of the material through which the gamma
rays pass. As a result, the gamma log measures porosity as proportional to bulk
density. The following will inhibit the usefulness of gamma logs:
0 Large diameters wells,
0 Wells constructed with cable-tool methods, and
0 Wells already completed with casing and cement.
Copyright (C) 2007 American Water Works Association All Rights Reserved
84 Siting, Drilling, and Construction of Water Supply Wells
I
Silt and Clay Percent
Figure 4-10 shows an example of a gamma log in conjunction with a caliper log.
Limestone, alluvium, coal, gypsum, and anhydrite are all materials where the gamma
log shifts to the left, while granite and other hard rocks shift to the right. The latter
are not rocks likely to have much water useful for production. Figure 4-11 shows
that as the silt and clay content increases, the gamma pulses also increase (shift
right). SP logs used in conjunction with gamma logs will react similarly.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical logging and Field Testing 85
Surface
Deptt
/
5 Salt Water
0
Diameter Resistance Gamma
Figure 4-10 Example of comparison of gamma, resistivity, and caliper logs through shale
I--
, Gamma Log
Copyright (C) 2007 American Water Works Association All Rights Reserved
86 Siting, Drilling, and Construction of Water Supply Wells
I
Radium/Potassium
Gamma-gamma Logs
Gamma-gamma logs are radioactive tracer logs or surveys that are obtained by
introducing a gamma radiation-emitting material into the borehole (usually
cesium-137 or cobalt-60) and measuring the intensity of the backscattered
radiation. Gamma-gamma logs provide information on lithology and porosity but
should not be used in groundwater investigations because of their high costs and
liabilities associated with the potential loss or rupturing of the radioactive source
within the aquifer.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical Logging and Field Testing 87
Neutron logs
Neutron logs are used to find changes in porosity of the rock and sediments, which
may be related to the amount of fluid in the formation. The concept is based on the
emission of high energy neutrons from beryllium and an alpha-emitter (commonly
americium). The emitted neutrons interact with hydrogen atoms and release gamma
radiation, which is measured by a detector on the logging tool. The intensity of the
measured gamma radiation is proportional to the hydrogen atom concentration and
thus water content and the porosity of saturated rocks. Table 4-3 shows the neutron
response for a number of common elements with an initial energy of 2 million
electron volts. Calibration of neutron logs is critical to obtaining useful
information.
Neutron logs work very well to indicate lithology by identifying suspected
formations of sand, limestone, and sandstone that have pores and vugs that would
indicate high porosity. These pores are usually filled with water, which contains
hydrogen, a strong neutron absorber. However, coal, shale, and other formations
with high hydrogen content will provide false readings despite yielding results that
would indicate high porosity. The same problems that affect gamma-gamma logs
also affect neutron logs. EC logs help to show where these formations provide false
readings because the hydrogen effect is not a driving factor. As a result, the EC logs
will deflect in the opposite direction from the neutron log. Shale or clay will be
evident when a gamma log is used in conjunction with neutron logs because the
bound water will reflect high water content, which the gamma log will not. Neutron
logs are suggested to help determine how much of the conductivity is the result of
salinity from salt (NaC1).
Copyright (C) 2007 American Water Works Association All Rights Reserved
88 Siting, Drilling, and Construction of Water Supply Wells
Transit Time
Material Velocity (feet per second) (pec/feet)
~~~
Sandstone
Slightly consolidated 15,000- 17,000 58.8-66.7
Consolidated 19,000 52.6
Shale 6,000-16,000 62.5- 167
Limestone 19,000-210,OOOt 47.6-52.6
Dolomite 21,000-24,000 42.6-47.6
Anhydrate 20,000 50
Granite 19,000-20,000 50-52.5
Gabb'ro 23,600 42.4
Fresh water 5,000 200
Sea water 5,300 189
Adapted from Keys, 1989
SandlAIluvium
Sandstone
Limestone
Sandstone
Shale
Sandstone
Limestone
Note Line Where Sandstone
Acoustic Log Shows
Granite and Limestone
are Similar Granite
Figure 4- 13 Response of sediments to acoustic waves. Note that the granite and limestone
give similar results.
Acoustic logging
Acoustic or sonic logging involves the recording of the transit time of acoustic pulses
radiated from a tool in a borehole to one or more receivers also located on the tool.
Acoustical techniques can be used to send sound through a formation to determine
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 89
changes in lithology and types of formations. Table 4-4 shows an example from Keys
(1989). Table 4-4 and Figure 4-13 show that acoustical logging cannot be used alone
as granite and limestone have similar velocities for the sound waves (because
sedimentary rocks, cement, and hardness have similar responses), while the water
bearing characteristics are vastly different. Transit times for the acoustic waves are
related to formation mineralogy and the porosity of the rock. Most rock types have
a limited range of acoustic travel times, which allows for acoustic logs to be used to
determine lithology. The cement-bond log is a type of acoustic log that is used to
determine how well a casing has been cemented to the formation.
Acoustical logging is useful for consolidated formations and provides useful
information in uncased, fluid-filled boreholes. Figure 4-14 shows an example of an
acoustic log in conjunction with a caliper log. Saltwater will shift the response
slightly to the right. Limestone and granite provide similar responses so other logs
must be used to confirm which is present. Limestone will generally yield water while
granite generally will not.
Fluid Logs
Fluid logs include temperature, fluid resistance, and flowmeter logs. The tool used
for temperature logs usually contains a glass bead thermistor. Temperature logs can
be used to identify the boundaries of aquifer zones in boreholes; as water flows
through permeable zones, the normal geothermal gradient will vary. Temperature
logs are developed using a down-hole run. Temperature logs are useful in
conjunction with EC logs as temperature changes often occur where there is moving
Copyright (C) 2007 American Water Works Association All Rights Reserved
90 Siting, Drilling, and Construction of Water Supply Wells
log Suites
In no case should only one log be used because in no case can one log adequately
describe the lithology and hydrogeology of the well. Individual geophysical logs do
not provide unequivocal lithologic information. A high gamma response could be
produced by a shale bed or phosphatic limestone layer. By running a suite of logs,
more accurate qualitative and quantitative information of formation porosity,
hydraulic characteristics, and fluid conductivity can be measured. Figure 4-15 shows
a series of logs for a borehole (Bloetscher, et al., 2005). In a log suite, occurrences
such as shale layers are identifiable by a low resistivity and high gamma log response,
where those logs singly would provide no specific information indicating that the
layer was shale.
Further details of the logs are summarized in several reference books, most
notably Keys (1989). In determining which logs and tests should be required, the
following geologic logs should be considered for surface casing intended to protect
underground sources of drinking water:
Resistivity (long and short, normal and single-point); spontaneous potential;
gamma: and caliper logs before the casing is installed; and
A cement bond, temperature, and density log after the casing is set and the
annular space cemented, depending on casing material. If the hole is drilled
without the use of drilling muds or other additives, the fluid resistivity
flowmeter and temperature log should be performed under static and pumping
conditions.
No radioactive source should be placed down-hole in the underground source of
drinlung water or where water for potable use or human consumption is anticipated.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 91
0.00
Sand
Sandstone
20.00
Limestone
40.00
60.00
80.00
100.00
Sandstone
120.00
140.00
160.00
Table 4-5 outlines the application of types of geophysical methods that should
be used based on the formation type and investigation desired. Table 4-6
summarizes the response of four logs to porosity, an important property when
looking for water supply sources. Table 4-7 outlines a set of criteria suggested by
Keys (1989) for selecting logs to be run on a given project. It should be noted that
the same suite of logs may not be appropriate or cost effective in every instance.
Instead, careful consideration should be given to selecting the logs that will provide
the most useful information for making decisions based on the anticipated
geological environment where the wells are proposed to be constructed. In all cases,
a caliper log should be run. Other information that maybe gathered includes a radial
and side-view color television survey of the borehole under flowing and no-flow
conditions to help identify flow zones and sanding problems (see Figure 4-16).
Other geophysical logs should be considered depending on the formation,
availability of tools, cost of the project, and perceived hazards.
Copyright (C) 2007 American Water Works Association All Rights Reserved
92 Siting, Drilling, and Construction of Water Supply Wells
Groundwater
X X
location
Karst formation X X X X
Groundwater
X
pollution
Fracture zones X
Metallic objects
X X X
buried
Nonmetallic
X
objects buried
Seismic risk X
Foundation
X X X
design
Reprinted with permission of National Groundwater Association Press, copyright 1989.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 93
Borehole
Type of Log Property Measured Application Condition Limitations
Spontaneous Electric potential Lithology, water Uncased borehole Need salinity
potential caused by salinity quality, and water with water differences
content
Single-point Resistance of rock, High resolution Uncased borehole Not quantitative,
resistance water, and filled lithology and with water borehole diameter
voids fractures impacts results
Multi-electrode Resistance of rock Quantitative date Uncased borehole Normal logs do not
and fluids on salinity and with water measure thin bed
lithology thickness correctly
Gamma Natural gamma Lithology, use clay Any borehole None
radiation in rock and silt content for less than 24 in.
permeability diameter
Gamma-gamma Electron density Bulk density, Uncased borehole Severe borehole
porosity, moisture diameter effects
content, and
lithology
Neutron Hydrogen content Saturated porosity, Uncased borehole Borehole diameter
moisture content and chemical effects
and lithology
Acoustic Acoustic reflectivity Orientation of 3 to 16 in. fluid Does not detect
of borehole wall fracture, dip of bed filled borehole secondary porosity
Caliper Diameter of Lithology and All conditions None
borehole voids
Temperature Temperature of Flow and tempera- Fluid-filled Accuracy varies
water ture gradient borehole with probe
Conductivity Fluid resistivity Water quality, Fluid-filled Accuracy varies
contamination borehole with probe
location
Flow Fluid movement Flow in borehole Fluid-filled Accuracy varies
borehole with probe
Reprinted with permission of National Groundwater Association Press, copyright 1989.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Next Page
94 Siting, Drilling, and Construction of Water Supply Wells
cone of depression may be small. In tighter materials, the cone of depression may be
very significant.
Wells are normally placed far enough apart so that their cones of depression do
not overlap significantly. Wells should be sized to minimize drawdown so that the
aquifer can rebound quickly. Permanent drops in water levels can occur when the
aquifer is pumped too much, a phenomenon called mining of the aquifer. The Black
Creek aquifer in eastern North Carolina is such an example. When recharge to the
aquifer is inadequate, a new water source will need to be located.
Ideally, wells should be pumped continuously without permanent drawdowns
occurring. Where this is not possible, it is common practice to pump wells that have
a significant drawdown for only a few hours each day to allow the aquifer to recover.
An artesian well may be under enough pressure to cause the water to rise above the
confining unit, which may eliminate the need for pumping initially. However, after
an artesian well has been used for a period of time, the artesian pressure may reduce
until the water no longer flows to the surface.
It is more important to determine the appropriate casing depth than to locate
the pump depth. An improper casing depth may seal off highly productive zones.
Determining the casing depth is dependent on the results of the design
considerations, geophysical logs, and data collected during drilling. The data
required to determine casing depth includes
Lithology
Coredata
Borehole geophysics
Copyright (C) 2007 American Water Works Association All Rights Reserved
Previous Page
Geophysical togging and Field Testing 95
Copyright (C) 2007 American Water Works Association All Rights Reserved
96 Siting, Drilling, and Construction of Water Supply Wells
each well. Data sheets should be used to record the water level changes during the
pump test that include the date, time, depth to water, and casing elevations. Other
data should be gathered and correlated to specific wells.
Water levels can be measured using a hand-held tape with a weight attached to
the end to hold it straight and taut. The tape should be metal, and graduated in feet
and in tenths and hundredths of a foot, or some similar metric unit. Such
graduations facilitate calculations by eliminating conversion of fractions to decimal
equivalents. By chalking the lower portion of the tape and lowering it into the water
until an even foot graduation coincides exactly with the reference point, the precise
distance to water from the reference is made by subtraction. The wetted chalk is
easily identified, and direct readings to one hundredth of a foot can be made
( A W A , 2003).
Other methods of collecting water-level data include an electric tape that has an
insulated wire with an open-end weighted electrode on the end. When the electrode
enters the water, it completes a circuit that actuates a light, buzzer, meter, or other
signal device. The distance to water is then read directly from graduations on the
wire line. However, the graduations are not usually fine enpugh to permit a very
accurate reading without some supplementary device. Float-actuated recording
devices provide a means of collecting data continuously, but the time drive is not fast
enough for the early periods of a test program. Pressure transducers combined with a
data logger can provide an excellent record ofwater levels. Air-line devices have little
value for controlled tests, except where water-level fluctuations are very large.
Such a standard schedule can be easily followed and provides adequate data. All
times are calculated from the precise instant that the pump is turned on or off,
which is designated as zero. If the test extends beyond 24 hr, subsequent
measurements can be made at 4-hour intervals. The timing of measurements at the
onset of the test is critical. Each well should have at least one observer equipped with
measuring devices and a synchronized stopwatch. After 180 min, measurements do
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 97
not have to be made at a designated instant, but they must be accurate with regard to
the exact time that each measurement is maintained.
The data collected provides information on the aquifer performance, not well
performance. Each method involves turning a pumped well on or off and observing
what happens to the water level in nearby observation wells. All methods use the
Theis nonequilibrium formula or modifications thereto, which takes into account
the time that has elapsed since pumping began or ceased.
Ideally, all wells used in the analysis should fully penetrate the aquifer. Some
departures from this requirement can be tolerated, but the construction details of
the partially penetrating wells are required, and modifications to the equations are
required. Any wells in the area that are not involved in the test should be stabilized
before an aquifer test and maintained at the same pumping rate for the duration of
the test. During the aquifer test, well pumping should be at a steady, unvarying rate
and carefully measured. The pumping rate and water-level data should be carefully
computed and plotted. Each method uses the Theis formula to analyze variations in
drawdown with time, or variations in drawdown with distance from the pumped well.
A family of curves has been developed to facilitate aquifer evaluation under a
variety of conditions. The equations used for aquifer parameters are:
Where:
T = the transmissivity of the aquifer, in gpd/ft
Q = the discharge rate of the well, in gpm
u = for any given formation, is proportional to the ratio of Y2/T
W(u)= the “well function of u,” is determined from calculated tables
for each value of u
s = the drawdown at any point under study in the vicinity of the
discharging well, in ft.
Where:
r = the distance from the dischargingwell to the point where the
drawdown is being observed, in ft
S = the aquifer storage coefficient
T = the transmissivity of the aquifer
t = the elapsed time since discharge began, in days.
Copyright (C) 2007 American Water Works Association All Rights Reserved
98 Siting, Drilling, and Construction of Water Supply Wells
... . ..... .
..~
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 99
100
0.001 -
0.0001 -
0.00001 -
0.000001
0.01 0.1 1 10 100 1,000 10,000 100,000
1IU
type curves developed from the Theis formula. The type curve is superposed over
the field-data plot, keeping the respective graphical axes parallel. The curves are
adjusted horizontally and vertically to obtain the best match of the two curves. An
arbitrary match point is selected on the two graphs, and the field-curve and type-
curve coordinates for substitution in the appropriate equation are selected. A
different form of the type-curve solution is'the distance-drawdown method. In this
analysis, drawdowns in three or more observation wells at different distances from
the pumped well are compared with one another to observe trends in the drawdown
at each well in response to pumping.
An alternative solution is available for analyzing aquifer test data that is an
approximate version of the type-curve solution. For this solution, well-test data is
plotted on semilogarithmic paper and variations of the basic formula are used to
compute the aquifer transmissivity and storage coefficient. The drawdown data tend
to follow a straight line when plotted on semilog paper (Figure 4-18).
Copyright (C) 2007 American Water Works Association All Rights Reserved
100 Siting, Drilling, and Construction of Water Supply Wells
I
1 10 100 1.000
Time Since Pump Started (min)
pumping continued. The same curve options are available for this method of
calculation as for the drawdown method, except that the concept has been inverted.
The inverted curve indicates the rising levels in the observation wells. The recovery
curve is compared with the inverted drawdown curve to determine the
transmissivity and storage coefficient. The values should be similar to those
obtained using the drawdown calculation method. The same time periods for the
recovering water levels should be observed as for the drawdown method.
A straight-line solution can also be used. As in the drawdown methods, the data
curves are plotted on semilog paper, showing a rising trend in the recovery period.
With these modifications, the curves become straight lines. The same abbreviated
equations are used to compute the transmissivity and storage coefficient. In practice,
the recovery test is essentially the reverse of a drawdown test, therefore one
drawdown curve and one straight-line plot will serve equally well for either kind of
test data. Both kinds of data can be recorded on the same plot to check their
agreement ( A W A , 2003).
Caution needs to be used in analyzing recovery data. Water extracted from the
aquifer may recover very slowly from drainage from the unsaturated zone above.
Therefore, when it is anticipated that the amount of time for full recovery is
significantlygreater than the duration of the pump test, a reduction in the pump test
rate is recommended so that the test pumping rate is proportional to the ratio of
pumping time to recovery time.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical Logging and Field Testing 101
x x
Copyright (C) 2007 American Water Works Association All Rights Reserved
102 Siting, Drilling, and Construction of Water Supply Wells
increasing pumping rates. Ideally, the three rates should be at 50, 100, and 150
percent of the design pumping rate. Before each increase in pumping rate, water
levels are allowed to recover to static levels for at least the same amount of time as
the well was pumped. The changes in water levels within the well are measured with
an electric water-level probe (M-scope) during both the drawdown and recovery
periods. It is imperative that the M-scope be disinfected before use in each well and
after use in each well. The time increments for measurements are as follows: 1 min-
readings for the first 10 min, 2-min readings from 10 to 20 min, and 5-min readings
from 20 to 60 min and/or the end of the test.
From a measurement standpoint, the most important test measurements are the
first and last water-level measurements. If for some reason the well does not stabilize
at 60 min, the test readings should be measured until the well is stable. Each
successive rate (and recovery period) must be extended out to at least the longest
previous time interval, and a measurement must be obtained at the same time as the
end of the first drawdown step. The recovery period should be equal to the longest
time period in the drawdown step. Example: If step 1 lasts for 60 min, but the
second step indicates the well is still drawing down at 60 min, readings should
continue until the well is stable (for example, 100 min). Readings will then be
obtained at 60 min and at 100 min. The recovery for the second and third step must
also be 100 min, while recovery must be at least 100 min and readings must be
obtained at 60 min and 100 min for each step and recovery period.
Discharge from the well should be controlled by a gate valve and should be
measured using a calibrated flowmeter and/or an orifice manometer assembly. The
total drawdown (measured in the field) in a well is a function of the drawdown due
to aquifer characteristics and the drawdown due to the loss of efficiency from the
well. Total drawdown(s) can be written as the following equation (Dawson and
Istok, 1991):
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 103
Copyright (C) 2007 American Water Works Association All Rights Reserved
104 Siting, Drilling, and Construction of Water Supply Wells
.".." "-
may be computed from step-drawdown test data using the following equation
(Jacob, 1946):
(Eq. 4-7)
Where:
c = well loss constant, sec2/ft5
I = any given pumping step
A& = incremental drawdown associated with step i, ft
AQi = incremental pumping that produces incremental drawdown
(32) associated with step i, ft3/sec
Changes in Cvalues are affected by changes in discharge rates, shifting of the gravel
outside the wells, and/or development of the formation.
Equation 4-7 assumes that the production well is stable and that the value of C
does not change during the well production test. New wells, improperly designed
and/or constructed wells, and old wells can be unstable, therefore the calculated
value of C can be affected by changes in the discharge rate. The value of C calculated
for flow rates 1 and 2 of the step-drawdown test may be greater or less than that
calculated for flow rates 2 and 3. Sand and gravel often shift outside the production
well during discharge periods under the influence of high discharge rates. This may
result in either the development ot clogging of the pores of the well face. If the value
of C for steps 2 and 3 is considerably less than the value of C for steps 1 and 2, it is
probable that development of the well has occurred during the well production
(step-drawdown) test. A large increase in the value of Cwith higher discharge rates
indicates clogging has occurred during the well production test. Clogging may occur
for several reasons: fine-grained material clogging boreholes, the presence of
bacteria, and/or formation collapse. Formation collapse may be an indication of
sinkhole formation. If the production well is unstable, C may be calculated with
Equation 4-7 and data for flow rates for steps 1+2 and 3 or 2+3 and 1.
Borehole clogging as a result of incomplete well development or well
deterioration by bacteria or other concerns is generally negligible when Cis less than
5.0 sec2/ft5. Values of C between 5.0 and 10.0 sec2/ft5 indicate mild clogging or well
deterioration, and clogging or well deterioration is severe when C is greater than
40.0 sec2/ft5 (Walton, 1962, p. 27). Deteriorated wells may be returned to near
original yields by one of several rehabilitation methods. The success of the
rehabilitation can be appraised with the results of well production tests conducted
prior to and after rehabilitation.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical Logging and Field Testing 105
5, = c@ (Eq. 4-8)
Where:
sw = well loss, ft
c = well loss coefficient, sec2/ft5
Q= production well discharge, ft3/sec
For the purposes of this text, the theoretical drawdown is calculated as the total
(measured) drawdown minus the well loss in feet. The actual drawdown is the
drawdown as measured in the well.
The term well eflciency, in this context, can be misleading because is does not
indicate that the efficiency (productivity) is caused by both the well characteristics
(well loss) and aquifer characteristics (theoretical drawdown). Therefore, wells with
lower well efficiencies should not be thought of as necessarily inferior to wells with
higher well efficiencies. Well efficiencies of greater than 100 percent indicate that
the wells are developing.
Copyright (C) 2007 American Water Works Association All Rights Reserved
106 Siting, Drilling, and Construction of Water Supply Wells
Data Plot \ \
l8 \
’\
\
\
\
\
\
\
b\
\
\
\
.,
\
\
\
staying on a straight line, now curves and eventually defines a new straight line
having twice the slope of the original (see Figure 4-19).This phenomenon is known
as reflection. The aquifer is cut off by an impermeable barrier caused by the rising
side of a buried valley or intruded, impermeable formation. This situation is quite
common in the northern, once-glaciated parts of the United States. The effect is the
same as having a second well located across the barrier at the same distance from the
barrier as the actual well, pumping at the same rate. Data gathered and plotted in
this manner will indicate the presence, location (distance), and type of aquifer
boundary with respect to the pumped well.
A recharge zone creates the opposite phenomena from an impermeable
boundary. Instead of being cut off by an aquifer barrier, the aquifer is cut off by a
recharging stream-a situation that is often found in the field. The data plot begins
as expected, with a curved portion leading into a straight line. However, instead of
continuing on the straight line, as the data theoretically should for an infinite
aquifer, the plotted data curves above it and eventually defines a horizontal line
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 107
12 -
Legend
0 Observation Well No. 1
4 I , , I I I I l l I I
(see Figure 4-20). The rate of drawdown caused by the withdrawal well lessens
because of the water contributed to the aquifer by the stream and gradually
approaches a fixed value. The effect is the same as if a well, identical to the pumping
well, is introducing water to the aquifer instead of withdrawing it. The reflective
well is located at an equal distance from, and on the opposite side of, the recharge
boundary from the withdrawal well.
Comparisons
To provide a baseline for testing the well design procedure, Nuzman (1989)
developed some rule-of-thumb ratios between transmissivity and well specific
capacity (ATscnslrA, 2003):
Copyright (C) 2007 American Water Works Association All Rights Reserved
108 Siting, Drilling, and Construction of Water Supply Wells
These ratios were developed for a typical well radius of influence of 0.5 mi, and
effective well diameter of 24 in., and assuming a storativity coefficient typical for the
aquifer characteristics defined and the general assumptions of a theoretical aquifer
(homogenous, isotropic, instant release from storage, infinite area extent, and no
leakage or recharge). The equations are provided for purposes of comparison only
and should not be used exclusive of good field testing. Once the geological data is
secured, design information-size, materials, casing purpose-can be used to
determine the appropriate depth of the casing and screening.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 109
Copyright (C) 2007 American Water Works Association All Rights Reserved
110 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 111
15 mg/L-water for flood-type irrigation and where the nature of the water-
bearing formations and the overlying strata are such that pumping this amount
of sand will not seriously shorten the useful life of the well.
The limits suggest reasonable goals that can be achieved if good well design,
construction, and development practices are followed. In older wells or wells in
problem aquifers, a well may pump unacceptable amounts of sediment. If the well
cannot be redeveloped by conventional techniques, a special sand separator can be
installed as a permanent part of the well system. Although sand separators are
efficient, they may not remove all sediment and should not be used as a substitute
for good well design and construction practices. In addition, if sufficient sand is
removed, this removal could cause catastrophic collapse of the formation. The
testing procedure for a Rossum sand separator is well documented in AWWA
literature. While the Rossum sand tester is the method accepted by AWWA, the
authors’ experience has indicated that the use of a Lakos Lava1 sand separator
provides a better method of quantifying sand produced from a well.
The amount of sand produced in milligrams per liter for each individual
pumping rate is determined by the following equation (Witt and Andrews, 1993):
SWt(l,OOO>
S = (Eq. 4-13)
3.785Qt
Where:
S = sand content, mg/L
Swt = weight of sand, g
1,000 = equation constant, mg/g
3.785 = equation constant
Q = rate through the sand separator, gpm
t = time, min
The well should be pumped at its design rate for 2 hr, and sand samples should
be collected at 5,30,60, and 120 min without stopping the pumping. Sand samples
are removed from the sand separator and analyzed. The amount of sand pumped
during normal operation is reflected in the fourth (120 min) sand sample. This
sample is a realistic figure for the quantity of sand that will be produced during
normal well operations. 1.0 mg/L is the desired maximum. More sand, especially
after proper development of the well, may indicate grouting problems or a sand vein
in the production zone that may cause damage to the well and pumping equipment.
Large discrepancies in the amount of sand collected at the 5-min sample as
compared to the amount of the 120-min sample are of concern and may be an
indication of water hammer to the formation. Water hammer is a phenomenon
whereby the turn-on or turn-off of the well causes large pressure fluctuations in the
aquifer. Such fluctuations will dislodge sand and silt, and may cause damage to
Copyright (C) 2007 American Water Works Association All Rights Reserved
112 Siting, Drilling, and Construction of Water Supply Wells
limestone and sandstone. Water hammer often indicates operational failure of the
valves in a well and/or at the plant. It should be noted that the Lakos Lava1 sand
separator only removes sand particles in the range of 74 pm with 98 percent efficiency.
This means that particles less than 74 pm will pass through the sand separator.
Colloidal testing should be performed prior to well disinfection and after well
disinfection. This procedure will allow evaluation of the effectiveness of the
disinfection procedure. The filter pore spaces are 5.0 pm in size. This filter size
allows for the capture of most clay- and silt-sized particles. Clay- and silt-sized
particles can clog the gravel pack and well screens, causing increased drawdown, loss
of production, and increased operating cost. Continued withdrawal of silts and clays
can, like sand, cause sinkhole formation. The production of clays and silts may also
be an indication of structural concerns with the well casing and the screen. A
pressure gauge on each side (in-flow and out-flow) of the filter apparatus allows the
measurement of the change in pressure across the filter cartridge. The following is an
outline of the procedure to set up the cartridge filter:
1. Disinfect the filter holder with unscented Clorox' bleach and attach the
colloidal test apparatus to the side of the discharge line.
2. Flush Clorox' out of the cartridge filter holder by opening the valve to the
discharge line.
3. Insert the cartridge filters into the holder without touching the filter. (Open
an end of the plastic bag and insert the filter, then remove plastic bag.)
4. Turn on water to run through the filter.
5. Check and note the discharge rate after 5 min; check and note the pressure
in (Pin) and pressure out (Pout).
6. Check and note Pi, and Pout at least once a day. Note any color changes in
the filter and/or any growths on the filter. Once the pressure differential
between Pin and Pout increases to more than 28 psi, remove the filter using
plastic gloves.
The filter should be visually inspected and stored in a polyvinyl chloride (PVC)
container and any odor noted. Culture swabs may be obtained and sent for
microbiological analysis. The filters should be placed in PVC containers and sent
for x-ray diffraction and microscopic analysis by a qualified professional.
SDI testing, as defined in ASTM Standard D-4189-94, is an empirical
measurement to test for the potential of silt, colloidals, bacteria, colloidal silica,
organic molecules, and/or corrosion products that foul well screens and gravel
packs. The SDI test simply measures the decay in flow rate through a 47-mm
diameter, 0.45-pm pore-size membrane. The 0.45-pm membrane is used because it
is more susceptible to clogging from colloidal matter than from hard particles, such
as sand and scale. Furthermore, the 0.45-pm size is smaller than the 5.0-pm size of
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical Logging and Field Testing 113
the prefilter and therefore measures particles that would pass through the prefilter
and clog the membrane. (The membrane is approximately 0.5 pm in size.) The
measured decay in flow rate is converted to a number between 1 and 100.
The SDI number is a function of the rate at which the filter (membrane) clogs
with colloidal material. The larger the SDI number, the greater the fouling tendency
of the water. To perform the SDI test, a Millipore SDI or fouling index test kit or an
equivalent is required. The SDI equipment includes the following: 47-mm filter
holder, pressure regulator, pressure gauge, valves, fittings, tweezers, 0.45-pm
membrane filter discs, a stop watch, and a 500-mL graduated cylinder.
To calculate the SDI of a given water, the following formula is used:
T
SDI= (Eq. 4-14)
( 1 - T,)2 xlOO+TT
Where:
SDI = silt density index (an empirical number between I and 100)
Ti = the initial time to fill 500 mL, sec
TF= the final time to fill 500 mL, sec
TT= the total time test is performed, min
It is important to note the color of the filter because coloration is an indication
of the clogging medium. If microorganisms are suspected, it is important to preserve
the filter in a sterile container, such as a petri dish. This filter should be sent for
microbiological analysis.
One method of controlling the SDI is through the regulation of the uphole
velocity of water in the well. Decreasing the velocity will decrease the SDI of the
water. For water supply wells, an uphole velocity of less than 5.0 ft/sec is
recommended. Suspended solids create difficulty in the aquifer, generally causing
well plugging and a reduction in aquifer permeability, especially if the aquifer has
any chemical reaction with suspended solids or the ions among the solids. In many
cases, suspended solids can bypass filtration tests, thereby creating a buildup within
the wells that is unknown on the surface. To solve suspended solids problems, it is
best to redevelop or pump the wells to remove the suspended solids.
MICROBIOLOGICALISSUES
Understanding the microbiological activity can help with understanding the
chemical changes of the injected water. In stark contrast to public perception that
aquifers are “pristine” environments, bacteria naturally exist in most aquifer systems;
most aquifers with an organic content will have some degree of bacteriological
activity. The typical agents for microbiological fouling include iron, sulfur-reducing
and slime-producing organisms, although many others exist. As stated in chapter 2,
some of these organisms are opportunistic pathogens, which is an additional
Copyright (C) 2007 American Water Works Association All Rights Reserved
114 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 115
Copyright (C) 2007 American Water Works Association All Rights Reserved
116 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Geophysical togging and Field Testing 117
REFERENCES
American Water Works Association ( A W A ) . 2003. Manual M21-Groundwater. Denver,
Colo.: AWWA.
APHA, AWWA, and WEF (American Public Health Association, American Water Works
Association, and Water Environment Foundation). 2002. Standard Methods for the
Examination of Water and Wastewater. 19th ed. Washington, D.C.: APHA.
Bloetscher, F., Muniz, A., and Witt, G.M. 2005. Groundwater Injection: Modeling, Risks and
Regulations. New York: McGraw-Hill.
Dawson, K., and Istok, J. 1991. Aquifer Testing: Design and Analysis OfPumping and Slug
Tests, Chelsea, Mich.: Lewis Publishers.
Jacob, C.E. 1946. Drawdown Test to Determine Effective Radius of Artesian Well.
Transactions, ASCE, 112:1047-1070.
Keys, W.S. 1989. Borehole GeophysicsApplied to Groundwater Investigations. Dublin, Ohio:
National Water Well Association.
Nuzman, C.E. 1989. Well Hydraulic Flow Concept. In Recent Advances in Groundwater
Hydrology. Minneapolis, Minn.: American Institute of Hydrology.
National Groundwater Association. 1998. Manual of Water Well Construction Processes.
Westerville, Ohio: National Groundwater Association.
Scrivener, R.C., Shepard, T.J., and Garrjoch, N. 1986. Ore Genesis at Wheal Pendarues and
South Crotty Mine, Cornwall-A Preliminary Fluid Inclusion Study. Proceedings of the
Ussher Society, 6412.
Walton, W. C. 1962. Selected Analytical Methods for Well and Aquifer Evaluation. Illinois
State Water Bulletin 49.
Witt, G.M., and Andrews, L.J. 1993. Reverse Osmosis Membrane Technology Water Chemistry
and IndustrzalApplications.Edited by 2.Amjad. New York: Van Nostrand Reinhold.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Design
All well projects go through a series of steps: predesign, field testing, regulatory
criteria, design, construction, and testing and operations issues. The issues involved
with predesign, field testing, and design include the required demands for water
supply, measuring the impacts of competing users, and optimizing efficient and
reliable operations that may limit groundwater opportunities. It should be noted
that most testing occurs once some form of construction has begun-usually via a
test well. Results from this testing provide engineers and hydrogeologists with the
information needed to define the appropriate zones in the formation in which to
place a casing and those to leave open.
Installing wells to provide water supplies are feasible from a technical perspective
provided that certain subsurface conditions exist. These conditions include a
formation that is areally extensive and porous enough to permit water flow to the well.
Initial data to be collected at a potential well site was discussed in previous chapters.
After the initial investigation and confirmation of the presence of water-bearing
materials, the amount of water that can be withdrawn must be determined. The
basic aquifer parameters that must be evaluated are hydraulic conductivity1
transmissivity and storage coefficient. In addition, drawdown, the extent of the cone
of influence, flow, and specific yield must be defined. Aquifer testing provides data
on the response of the aquifer to step-drawdown tests and other pump tests. Specific
well design issues regarding up-hole velocity, screen size, well losses, casing burst
strength, and other parameters must be determined so casings and screens can be
properly placed.
The most significant aquifer parameters for predesign purposes are porosity,
transmissivity, specific yield and specific retention, hydraulic head, and gradient.
The first three describe the rock formation and quantities of water existing in the
formation. Head and gradient determine how water moves through the formation
Copyright (C) 2007 American Water Works Association All Rights Reserved
120 Siting, Drilling, and Construction of Water Supply Wells
and represent the mechanics of horizontal and vertical recharge to a well being
pumped. Head and gradient are also used to analyze the transport of pollutants that
may migrate to a well (AWWA, 2003). Hydraulic conductivity and transmissivity
indicate how easily water will move in the formation. Hydraulic conductivity is the
basic, three-dimensional parameter required for modeling purposes, but
transmissivity is the most commonly used term by hydrogeologists.
Porosity
Porosity is the ratio of openings (voids) to the total volume of a soil or rock. Porosity
is expressed either as a decimal fraction or as a percentage as follows:
(Eq. 5-1)
Where:
n = porosity, as a decimal fraction
yt = the totaLvolume of a soil or rock sample
V , = the volume of solids in the sample
& = the volume of openings (voids).
If the porosity determined using the above equation is multiplied by 100, the result
is porosity expressed as a percentage.
Table 5-1 outlines the porosity of various formation materials. Soils are highly
porous materials that are caused by loose soil particles, root holes, and animal
burrows. The porosity of unconsolidated sand and gravel depends on the range in
grain size, degree of sorting, and on the shape of the rock particles. Fine-grained
materials tend to be better sorted and have the highest porosity values. Clay has a
high percentage of voids, but because the voids are so small, clay transmits virtually
no water.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Design 121
sr = Vr
- (El. 5-3)
V,
Where:
S, = specific retention
J$ = the volume of water retained in a total volume of yt
f i = total volume of a soil or rock sample.
Table 5-2 lists selected values of specific yield.
Copyright (C) 2007 American Water Works Association All Rights Reserved
122 Siting, Drilling, and Construction of Water Supply Wells
_II "I
to the surface during wet weather, making the area unsuitable for development
without some form of drainage (as is commonly found in part of the southeastern
US and particularly south Florida). Where the water table is at a great depth, the
cost of constructing wells and pumping water for domestic needs may be
prohibitively expensive.
Potentiometric head is the water surface in a confined aquifer. As noted in
chapter 1, this is the point above the confining unit to which the water level rises.
In either case, the highest head occurs where the aquifer is recharged. The change in
head over the distance between the point of recharge and the point where a well is
proposed to be installed is the gradient. These water levels are determined from a
fixed measuring point. Typically, the referenced standard is the National Geodetic
Vertical Datum (NGVD) of 1929, also commonly referred to as sea level.
The gradient between any two observation points is found as follows:
Copyright (C) 2007 American Water Works Association All Rights Reserved
z = elevation of the water table or the potentiometric head, whichever applies
I = distance between measuring points 1 and 2
The hydraulic gradient can be determined if the following data are available for
three wells located in any triangular arrangement:
0 Relative geographic position of the wells
Distance between the wells
0 Total head at each well
Total head is the sum of elevation head, pressure head, and velocity head. Because
groundwater moves relatively slowly, velocity head can be ignored. Therefore, the
total head at an observation well involves only two components: elevation head and
pressure head. Groundwater moves in the direction of decreasing total head, which
may or may not be in the direction of decreasing pressure head.
h, = z + h p (Eq. 5-5)
Where:
z = elevation head, the distance from the datum plane to the point where
the pressure head, hp, is determined.
Copyright (C) 2007 American Water Works Association All Rights Reserved
124 Siting, Drilling, and Construction of Water Supply Wells
_ x
Soils
Clean Clean sand or Very fine sand, silt,
gravel sand and gravels loess, loam, solonetz
Stratified
Peat Unweathered clay
clay
Good Breccia-
Rocks Oil rocks Sandstone limestone
granite
dolomite
-log,,R(cmZ) 3 4 5 6 7 8 9 10 11 12 13 14 15 16
I I I I I I I I I I I I I I
log,,k(md) 8 7 6 5 4 3 2 1 0 -1 -2 -3 -4 -5
the individual water particles tend to follow discrete streamlines and not to mix
with particles in adjacent streamlines. As a result, the quantity ofwater, Q, is directly
proportional to the hydraulic gradient, db/dl.
If Equation 5-6 is rearranged to solve for K, the following is obtained:
-_
-
K - Qd'? - ( m 3 / d > ( m > (Eq. 5-7)
( m2)(m ) d
The units of hydraulic conductivity are those of velocity (or distance divided by
time). However, the velocity units are less obvious in Darcy's law because the
definition of hydraulic conductivity includes the volume of water, Q, that will move
in a unit of time (gpd) assuming a unit hydraulic gradient (such as ft/mile) through
a unit area (such as ft2). Expressing hydraulic conductivity in terms of a unit
gradient rather than an actual gradient at some place in an aquifer allows values of
hydraulic conductivity for different rocks to be compared.
Table 5-3 outlines the ranges of hydraulic conductivity through 12 orders of
magnitude. Hydraulic conductivity will vary by type of rock and likely will be
different from place to place in the same rock (see Table 5-4). If the hydraulic
conductivity is essentially the same throughout an area, the aquifer is considered to
be homogeneous. If the hydraulic conductivity differs from one part of the aquifer
to another, the aquifer is considered to be heterogeneous.
Water typically flows preferentially in one direction. As a result, the hydraulic
conductivity may be different along different axes in an aquifer. If it varies by
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Design 125
T = Kb (Eq. 5-8)
Where:
T = transmissivity
K = hydraulic Conductivity
b = aquifer thickness
Copyright (C) 2007 American Water Works Association All Rights Reserved
126 Siting, Drilling, and Construction of Water Supply Wells
Storage Coefficient
The storage coefficient is the ability of a formation to store and transmit water.
These are the formation's most important hydraulic properties. These properties are
given either in terms of a unit cube of the material or in terms of a unit prism of an
aquifer, depending on the intended use. These abilities, as they relate to the two
units of measurement, are shown in Table 5-5 (AWWA, 2003).
The storage coefficient, S, is defined as the volume of water an aquifer releases
from or stores per unit surface area of the aquifer per unit change in head. The
storage coefficient is a dimensionless unit, as the following equation shows, in which
the units in the numerator and the denominator cancel:
volume of water
S = (Eq. 5-9)
(unit area)(unit bead change)
The size of the storage coefficient depends on whether the aquifer is confined
or unconfined. If the aquifer is confined, the water released from storage when the
head declines comes from expansion of the water and from compression of the aquifer.
In a confined aquifer having a porosity of 0.2 and containing water at a temperature
of about 59°F (15"C),expansion of the water alone releases about 3 x m3 of
water per cubic meter of aquifer per meter of decline in head. To determine the storage
coefficient of an aquifer caused by expansion of the water, the aquifer thickness must
be multiplied by 3 x If only the expansion of water is considered, the storage
coefficient of an aquifer 300-ft (100-m) thick would be 3 x lop5. The storage
coefficient of most confined aquifers ranges from about to The
difference between these values and the value caused by expansion of the water is
attributed to compression of the aquifer (AWWA, 2003).
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Design 127
most pores in granular materials are of capillary size, water is pulled upward into a
capillary fringe above the water table to a height, hc, above the water level. In a
steady- state condition or conditions in which the moisture content remains
constant, flow of water in the unsaturated zone can be determined from a modified
form of Darcy’s law, as shown in the following equation:
(Eq. 5-10)
Where:
Q = the quantity of water
Ke = the hydraulic conductivity under the degree of saturation existing in
the unsaturated zone
A = the cross-sectionalarea through which flow occurs
(b, - z)/z = the gradient caused by capillary (surface tension) forces
dh/dl= the gradient caused by gravity
The plus/minus sign accounts for the direction of movement: plus for downward
and minus for upward. For movement in a vertical direction, either up or down, the
gradient caused by gravity is 1. For lateral (horizontal) movement in the unsaturated
zone, the gravitational gradient can be eliminated.
Because transmissivity depends on both K and b, its value differs between
aquifers and from place to place in the same aquifer. Estimated values of
transmissivity for principal aquifers the vs range from less than 1 gpd for some
fractured sedimentary and igneous rocks to over 1,OOO,OOO gpd for cavernous
limestones and lava flows (AWWA, 2003).
In a related issue regarding transmissivity, Nuzman (1989) accepted that the field
coefficient of permeability represents the limit of laminar flow through the
formation at a given temperature and viscosity of the water (AWWA, 2003). The limit
of laminar flow through the borehole wall is defined by the following equation:
This equation assumes uniform vertical flow that does not actually occur in
wells. It has been found by field experience that the beginning of turbulent flow
through the formation borehole was is approximately 2.35 times the laminar flow
limit (AWWA, 2003). Williams (1985) defined the point where the flow transitions
from predominately turbulent flow to predominately laminar flow, as
(Eq. 5-12)
Copyright (C) 2007 American Water Works Association All Rights Reserved
128 Siting, Drilling, and Construction of Water Supply Wells
Where:
re = critical radius (in.)
Q/L = specific aquifer discharge (gpm/ft)
Q = discharge rate (gpm)
L = length of screen (ft)
d = mean grain diameter (in.)
8 = effective porosity
It should be noted that Williams (1985) defined the Reynolds number at the point
where the flow regime changes from laminar to turbulent as being 30.
Flow volumes can be derived for design purposes from monitoring wells and
drawdown information for equilibrium conditions from one of two formulas
developed by Theim. For water table aquifers
Q = K(H2-h2) (Eq. 5-13)
R
1,055log-
r
Where:
Q = discharge rate (gpm)
r = distance to observation well (ft)
R = borehole diameter (ft)
K = hydraulic Conductivity (gpd/ft)
H = drawdown at the borehole
h = drawdown at observation well (ft)
For confined aquifers
Q = K6W-b) (Eq. 5-14)
R
5281og-
Where: r
Q = discharge rate (gpm)
r = distance to observation well (ft)
R = borehole diameter (ft)
K = hydraulic conductivity (gpd/ft)
b = formation thickness (ft)
H = drawdown at the borehole
h = drawdown at observation well (ft)
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Design 129
Wellfield Interference
Possible interference between wells should be determined before locating multiple
wells in a well field. Determining interference between pumping wells will allow the
design engineer and/or hydrogeologist to optimize spacing and pump capacity to
determine the most efficient placement pattern and pumping rates. The total
interference drawdowns estimated for various pumping rates are as shown in Figure 5-1.
Pumping Rates
When numerical values have been assigned to transmissivity and the storage
coefficient, the drawdown effects of pumping can be determined. These effects are
Copyright (C) 2007 American Water Works Association All Rights Reserved
130 Siting, Drilling, and Construction of Water Supply Wells
for any quantity of water at any reasonable distance from the pumping well. A
graphic representation should be plotted of water levels against the logarithm of
distance from the center of pumping for a given time period. A minimum
continuous pumping period of 100 days is usually used as a conservative safety factor.
WELL DESIGN
Once the wellfield spacing and pumping rates are determined, the proper design of
wells and specification of materials are made. Decisions regarding materials,
screened interval length, screen openings, casing and column pipe diameter, and the
need for sand or silt removal can be made once the field parameters are understood.
A series of calculations must be made to ensure the proper size borehole, casing,
screen, and screen spacing are designed. Typically, the client has a need for a specific
water yield and well. The designer must bring these inputs together to design a cost
effective and efficient well.
Up-hole Velocity
The maximum velocity criteria imposed on withdrawal wells is 10 ft/sec, which
affects casing diameters. However, this velocity is too high for many wells because it
tends to entrain sand and other particles if proper screening is not provided (see
Entrance Velocity section). High velocity will also exert wear on the casing.
Theoretical withdrawal velocities and pressures can be calculated for a maximum
day flow rate using the following equation (Heald, 1994, p. 3-6):
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Design 131
hf = 0.002083 x L x 8655
(Eq. 5-16)
Where:
hf= head loss due to friction (ft)
L = length of pipe
C = friction factor for Hazen-Williams (dimensionless)
gpm = flow (gpm)
d = inside diameter of the pipe (in.)
(Eq. 5-17)
Where:
z(x,y~= depth to the saltwater interface below sea level at location (xg)(ft)
pf= density of fresh water (g/cm3)
ps= density of salt water (g/cm3)
hfx,y)= elevation of the water table above sea level at location (x,y) (ft)
This equation can be converted into the following, more practical, form:
(Eq. 5-18)
Where:
hd = head due to density differential (ft)
ps = density of salt water (g/cm3)
pf= density of fresh water (g/cm3)
L = length of column of ftesh/salt water (ft)
In this equation, L is comparable to z of the Ghyben-Herzberg equation.
Copyright (C) 2007 American Water Works Association All Rights Reserved
132 Siting, Drilling, and Construction of Water Supply Wells
(Eq. 5-19)
Where:
hA = bottom-hole driving pressure at the injection rate
hB = bottom-hole driving pressure at the injection rate of QB (psi)
QA = injection rate (gpm)
QB = injection rate, equation variable (gpm)
psi = h
~
SPgr (Eq. 5-21)
2.31
Where:
psi = pressure (psi)
h = head (ft)
spgr = specific gravity of fluid (water is assumed 1.00)
h = head (ft)
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Design 133
(Eq. 5-22)
Where:
Pa= critical collapse pressure (psi)
E = modulus of elasticity for steel pipe (30,000,000)
,a = Poisson's ratio (usually taken as 0.30 for steel)
d = outside diameter of the pipe (in.)
t = wall thickness of the pipe (in.)
Table 5-6 outlines the collapse strength of steel pipe. Similar tables can be found for
PVC and fiberglass.
(Eq. 5-23)
Where a can be reduced to:
4,660
a = (Eq. 5-24)
and:
a = wave velocity
h = pressure rise above normal (ft ofwatet)
d = inside diameter of the pipe (in.)
e = thickness of pipe wall (in.)
e = velocity of flow (fps)
e = acceleration due to gravity (32 ft/sec)
Copyright (C) 2007 American Water Works Association All Rights Reserved
Table 5-6 Collapse strength of steel well casing
Outside Inside
Nominal Diameter Wall Thickness Diameter Diameter Weight Collapsing Strength
in. (mm) in. in. (mm) in. (mm) in. (mm) lb/ft (kg/m) psi ft water (kg/cm2)(m water)
8 Y4 0.250 (6.35) 8.625 (219.08) 8.125 (206.38) 22.36 (33.28) 755.54 1,745.29 (53.20) (531.96)
8 5/16 0.3125 (7.94) 8.000 (203.20) 27.74 (41.29) 1,191.21 2,751.70 (83.87) (838.72)
10 Y4 0.250 (6.35) 10.750 (273.05) 10.250 (260.35) 28.04 ( 41.72) 461.08 1,065.10 (32.46) (324.64)
10 5/16 0.3125 (7.94) 10.125 (257.18) 34.84 (51.84) 760.25 1,756.18 (53.53) (535.28)
12 Y4 0.250 (6.35) 12.750 (323.85) 12.250 (311.15) 33.38 (49.67) 306.09 707.06 (21.55) (215.51)
12 5/16 0.3125 (7.94) 12.125 (307.98) 41.514 (61.78) 520.68 1,202.78 (36.66) (366.61)
14 Y
4 0.250 (6.35) 14.00 (355.60) 13.500 (342.90) 36.71 (54.64) 242.43 560.02 (17.07) (170.69)
14 5/16 0.3125 (7.94) 13.375 (339.73) 45.68 (67.98) 418.68 967.15 (29.48) (294.79)
14 z/s 0.375 (9.53) 13.250 (336.55) 54.57 (81.21) 636.10 1,469.39 (44.79) (447.87)
14 Y4 0.250 (6.35) 14.50 (368.30) 14.000 (355.60) 38.05 (56.62) 221.82 512.41 (15.62) (156.18)
14 5/16 0.3125 (7.94) 13.875 (352.43) 47.35 (70.47) 385.11 889.59 (27.11) (271.15)
14 w 0.375 (9.53) 13.750 (349.25) 56.57 (84.19) 588.19 1,358.72 (41.41) (414.14)
16 % 0.250 (6.35) 16.00 (406.40) 15.500 (393.70) 42.05 (62.58) 172.25 397.90 (12.13) (121.28)
16 %6 0.3125 (7.94) 15.375 (390.53) 52.36 (77.92) 303.15 700.27 (21.34) (213.44)
16 w 0.375 (9.53) 15.250 (387.35) 62.58 (93.13) 469.53 1,084.62 (33.06) (330.59)
16 Y4 0.250 (6.35) 16.625 (422.28) 16.125 (409.58) 43.72 (62.58) 155.89 360.11 (10.98) (109.76)
16 736 0.3125 (7.94) 16.000 (406.40) 54.44 (81.02) 275.69 636.84 (19.41) ( 194.1 1 )
16 w 0.375 (9.53) 15.875 (403.23) 65.08 (96.85) 429.18 991.40 (30.22) (302.18)
Copyright (C) 2007 American Water Works Association All Rights Reserved
Table 5-6 Collapse strength of steel well casing (continued)
~~~ ~~~
Outside Inside
Nominal Diameter Wall Thickness Diameter Diameter Weight Collapsing Strength
in. (mm) in. in. (mm) in. (mm) in. (mm) lb/ft (kg/m) psi ft water (kg/cm2)(m water)
18 0.250 (6.35) 18.00 (457.20) 17.500 (444.50) 47.39 (70.53) 126.48 292.16 (8.90) (89.05)
18 0.3125 (7.94) 17.375 (441.33) 59.03 (87.85) 225.76 521.49 (15.90) (158.95)
18 0.375 (9.53) 17.250 (438.15) 70.59 (105.05) 354.92 819.86 (24.99) (249.89)
18 0.250 (6.35) 18.625 (473.08) 18.125 (460.38) 49.06 (73.01) 115.51 266.84 (8.13) (81.33)
18 0.3125 (7.94) 18.000 (457.20) 61.12 (90.96) 206.95 478.05 (14.57) (145.71)
18 0.375 (9.53) 17.875 (454.03) 73.09 (108.77) 326.64 754.54 (23.00) (229.98)
20 0.250 (6.35) 20.00 (508.00) 19.500 (495.30) 52.73 (78.48) 95.46 220.52 (6.72) (67.21)
20 0.3125 (7.94) 19.375 . (442.13) 65.71 (97.79) 172.25 397.90 (12.13) (121.28)
20 0.375 (9.53) 19.250 (488.95) 78.60 (116.97) 273.98 632.89 (19.29) (192.90)
20 0.4375 (11.11) 19.125 (485.78) 91.41 (136.03) 399.05 921.82 (28.10) (280.97)
20 0.250 (6.35) 20.625 (523.88) 20.125 (511.18) 54.40 (80.96) 87.86 202.96 (6.19) (61.86)
20 0.3125 (7.94) 20.000 (508.00) 67.79 (100.89) 159.00 367.28 (11.19) (111.95)
20 0.375 (9.53) 19.875 (504.83) 81.10 (120.69) 253.68 586.00 (17.86) 178.61
20 0.4375 (11.11) 19.750 (501.65) 94.33 (140.38) 370.69 856.3 1 (26.10) (261.00)
22 0.250 (6.35) 22.00 (558.80) 21.500 (546.10) 58.07 (86.42) 73.75 170.37 (5.19) (51.93)
22 0.3125 (7.94) 21.375 (542.93) 72.38 (107.72) 134.22 310.05 (9.45) (94.50)
22 0.375 (9.53) 21.250 (539.75) 86.61 (128.89) 215.46 497.71 (15.17) (151.70)
22 0.4375 (11.11) 21.125 (536.58) 100.75 (149.94) 316.88 732.00 (22.3
. 1), (223.11)
.
Table continued next page.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Table 5-6 Collapse strength of steel well casing (continued)
Outside Inside
Nomind Diameter Wall Thickness Diameter Diameter Weight CollapsingStrength
in. (mm) in. in. (mm) in. (mm) in. (mm) Ib/ft (kg/m) psi ft water (kg/cmz) (m water)
22 (559) Yi 0.250 (6.35) 22.50 (571.50) 22.000 (558.80) 59.41 (88.41) 69.37 160.25 (4.88) (48.84)
22 0.3125 (7.94) 21.875 (555.63) 74.05 ( 1 10.20) 126.48 292.16 (8.90) (89.05)
22 0.375 (9.53) 21.750 (552.45) 88.61 (131.87) 203.44 469.94 (14.32) (143.24)
22 0.4375 (11.1 1) 21.625 (549.28) 103.09 (153.41) 299.84 692.62 (21.11) (211.11)
24 0.250 (6.35) 24.00 (609.60) 23.500 (596.90) 63.41 (94.37) 58.13 134.28 (4.09) (40.93)
24 0.3125 (7.94) 23.375 (593.73) 79.06 ( 1 17.65) 106.51 246.04 (7.50) (74.99)
24 0.375 (9.53) 23.250 (590.55) 94.62 (140.81) 172.25 397.90 (12.13) (121.28)
24 0.4375 (11.11) 23.125 (587.38) 110.10 (163.84) 255.34 589.84 (17.98) (179.78)
24 0.250 (6.35) 24.50 (622.30) 24.000 . (609.60) 64.75 (96.36) 54.92 126.88 (3.87) (38.67)
24 0.3125 (7.94) 23.875 (606.43) 80.73 (120.14) 100.79 232.82 (7.10) (70.96)
24 0.375 (9.53) 23.750 (603.25) 96.62 (143.79) 163.26 377.13 (11.49) ( 1 14.95)
24 0.4375 ( 1 1.1 1 ) 23.625 (600.08) 112.43 (167.32) 242.43 560.02 (17.07) (170.69)
26 0.250 (6.35) 26.00 (660.40) 25.500 (647.70) 68.75 (102.32) 46.61 107.67 (3.28) (32.82)
26 0.3125 (7.94) 25.375 (644.53) 85.73 (127.59) 85.88 198.38 (6.05) (60.47)
26 0.375 (9.53) 25.250 (641.35) 102.63 (152.73) 139.73 322.78 (9.84) (98.38)
26 0.4375 (11.11) 25.125 (638.18) 119.44 (177.75) 208.48 481.59 (14.68) (146.79)
26 (660) Y4 0.250 (6.35) 26.50 (673.10) 26.000 (660.40) 70.09 (104.30) 44.21 102.13 (3.11) (31.13)
26 (660) %6 0.3125 (7.94) 25.875 (657.23) 87.40 (130.07) 81.56 188.41 (5.74) (57.43)
26 (660) 34 0.375 (9.53) 25.750 (654.05) 104.63 (155.71) 132.89 306.97 (9.36) (93.56)
26 (660) 7/16 0.4375 (11.11) 25.625 (650.88) 121.78 (181.23) 198.55 458.66 (13.98) (139.80)
Copyright (C) 2007 American Water Works Association All Rights Reserved
Table 5-6 Collapse strength of steel well casing (continued)
Outside Inside
Nominal Diameter Wall Thickness Diameter Diameter Weight CollapsingStrength
in. (mm) in. in. (mm) in. (mm) in. (mm) lb/ft (kg/m) psi ft water (kg/cm2)(m water)
28 Yi 0.250 (6.35) 28.00 (711.20) 27.500 (698.50) 74.09 (110.26) 37.94 87.63 (2.67) (26.71)
28 %6 0.3125 (7.94) 27.375 (695.33) 92.41 (137.52) 70.22 162.21 (4.94) (49.44)
28 % 0.375 (9.53) 27.250 (692.15) 110.64 (164.65) 114.83 265.25 (8.08) (80.85)
28 7/16 0.4375 (11.11) 27.125 (688.98) 128.79 (191.66) 172.25 397.90 (12.13) (121.28)
28 ?4 0.250 (6.35) 28.50 (723.90) 28.000 (711.20) 75.43 (112.25) 36.1 1 83.41 (2.54) (25.42)
28 %6 0.3125 (7.94) 27.875 (708.03) 94.08 (140.00) 66.91 154.55 (4.71) (47.11)
28 z/s 0.375 (9.53) 27.750 , (704.85) 112.64 (167.63) 109.53 253.02 (7.71) (77.12)
28 7/16 0.4375 (11.11) 27.625 (701.68) 131.12 (195.14) 164.51 380.01 (11.58) (115.83)
30 % 0.250 (6.35) 30.00 (762.00) 29.500 (749.30) 79.43 (118.21) 3 1.28 72.26 (2.20) (22.02)
30 5/16 0.3125 (7.94) 29.375 (746.13) 99.08 (147.45) 58.13 134.28 (4.09) (40.93)
30 % 0.375 (9.53) 29.250 (742.95) 118.65 (176.57) 95.46 220.52 (6.72) (67.21)
30 7/16 0.4375 (11.11) 29.125 (739.78) 138.13 (205.57) 143.85 332.20 (10.13) (101.28)
30 ?4 0.500 (12.70) 29.000 (736.60) 157.53 (234.44) 203.44 469.94 (14.32) (143.24)
30 % 0.250 (6.35) 30.50 (774.70) 30.000 (762.00) 80.77 (120.20) 29.86 68.99 (2.10) (21.03)
30 5/16 0.3125 (7.94) 29.875 (758.83) 100.75 (149.94) 55.55 128.31 (3.91) (39.11)
30 z/s 0.375 (9.53) 29.750 (755.65) 120.65 (179.55) 91.31 210.91 (6.43) (64.29) '
30 7/16 0.4375 (11.11) 29.625 (752.48) 140.47 (209.04) 137.73 318.15 (9.70) (96.97)
30 % 0.500 (12.70) 29.500 (749.30) 160.20 (238.41) 194.99 450.43 (13.73) (137.29)
Copyright (C) 2007 American Water Works Association All Rights Reserved
138 Siting, Drilling, and Construction of Water Supply Wells
Well losses
Drawdown values obtained for a single pumping well using the Theim formulas
represent only the head losses suffered by water movement through the formation
under laminar flow conditions. The actual pumping level of a particular well cannot
be calculated without considering high velocities and turbulence losses during
pumping. At and near the well face, fluid velocities may become large enough that
turbulent flow conditions exist. The magnitude of turbulence losses varies with each
well because of differences in formation characteristics, screen slot sizes required,
degree of well development, well diameter, and quantity of water being pumped.
There are so many unknown quantities involved in the calculation of these
individual factors that they are usually lumped together under the heading of welllosses.
One method of approximating the well losses for a particular well is to use the
step-drawdown equation as defined by Equation 4-5. The values of B and C
(formation and well losses) may be calculated if proper test data are available. To
collect such data, the finished well must be pumped at three to five increasing rates
for equal periods of time and the drawdown measured for each pumping rate. When
a full-scale aquifer performance test is not conducted, however, a step-drawdown
test can differentiate the observed losses in the pumping well. Additionally, this test
makes it possible to quickly compare the magnitude of well losses to determine
when a well needs cleaning or other repair work. Irregular increasing well loss with
increasing pumping rates indicates unsatisfactory development of a new well, or
deteriorating aquifer or well conditions in an old well. Small regular increases in well
loss or decrease in well specific capacity as a result of transition to turbulent flow in
the aquifer are normal.
Entrance Velocity
Water entrance velocities through the screen openings should be between 0.1 and
0.2 ft/sec (0.03 and 0.06 m/sec). Such velocities will minimize head losses and
chemical precipitation. For design of well screens installed in a radial collector well,
an average velocity of about 0.033 ft/sec (0.01 m/sec) is used. Screen entrance
velocities are computed by
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Design 139
development. The total open area required must be determined by adjusting either
the length or diameter of the screen, because the slot size is not arbitrary.
A significant factor in well loss for sand and gravel wells is an open screen area
when the percentage of open area is substantially less that the specific yield of the
aquifer. Research by Williams (1985) has shown that when the open area of the
screen is greater than the specific capacity of the formation, the actual head loss
across the well screen is insignificant until the velocity through the screen exceeds
2 ft/sec (0.6 m/sec). In an attempt to limit turbulent flow losses around the well
borehole, many regulatory agencies have prescribed screen velocities between 0.1
and 0.2 ft/sec (0.03 and 0.06 m/sec) and a minimum thickness of gravel pack
resulting in large-diameter well construction. High velocity turbulent flow through
the formation borehole results in higher pumping and maintenance costs. In this
case, velocity is a function of quantity and area and is easily approximated in the
design stage. For membrane applications where sand may become an operational
problem, the velocity should be reduced.
Copyright (C) 2007 American Water Works Association All Rights Reserved
140 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Design 141
Copyright (C) 2007 American Water Works Association All Rights Reserved
142 Siting, Drilling, and Construction of Water Supply Wells
REFERENCES
AWWA (American Water Works Association). 1964. Manual M1 1-Steel Pipe Design and
Installation. Denver, Colo.: AWWA.
AWWA (American Water Works Association). 1998. ANSIIAWWA A100-06-Standard
f . r Water Wells. Denver, Colo.: AWWA.
AWWA (American Water Works Association). 2003. Manual M2 1-Groundwater. Denver,
Colo.: AWWA.
Bear, J., Zaslavsky, D., and Irmay, S. 1968. Physical Principals of Water Percolation and
Seepage. Paris: United Nations Educational, Scientific and Cultural Organization
(UNESCO).
Bloetscher, F., Muniz, A., and Witt, G.M. 2005. Groundwater Injection: Modeling, Risks and
Regulations. New York: McGraw-Hill.
Davis, S.N. 1969. Porosity and Permeability in Natural Materials. In Flow Through Porous
Media. Edited by R.J.M. Dewiest. New York: Academic Press.
Domenico, P.A., and Schwartz, F.W. 1990. Physical and Chemical Hydrogeology. New York:
John Wiley & Sons.
Fetter, C.W., Jr. 1994.Applied Hydrogeoloa,3rd ed. New York: Macmillan College Publishing.
Heald, C.C., ed. 1994. Cameron Hydraulic Data. Liberty Corner, N.J.: Ingersoll-DresserPumps.
Johnson, A.I. 1967. SpeciJic Eeld-Complication of Speczfc Eelds for Various Materials. US
Geological Survey, Water Supply Paper 1662-D. Washington, D.C.: USGS.
Johnson, A.I., and Morris, D.A. 1962. Physical and Hydrologic Properties of Water Bearing
Depositsfrom Core Holes in the Los Banos-Kettleman City Area, Cali&rnia. USGS Open
File Report. Denver, Colo.: USGS.
Nuzrnan, C.E. 1989. Well Hydraulic Flow Concept. In Recent Advances in Groundwater
Hydrology. Minneapolis, Minn.: American Institute of Hydrology.
Rorabaugh, M.I. 1953. Graphical and Theoretical Analysis of the Step Drawdown Test of
Artesian Wells. ASCE Proceedings, 362:79.
Williams, D.E. 1985. Modern Techniques in Well Design.Jour. AWWA, 77(9): 68-74.
Witt, G.M., and Ameno, J.J. 1989 City ofplantation Northwest TreatmentPlant: R.O. Reject
Injection WellPreliminary Design. Plantation, Fla.: Camp, Dresser & McKee.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Construction and Development
The components common to most wells include well casings, cementing or grouting
of wells, well screens, gravel packs, and sanitary seals. Considerations for these
components include material specifications, sizing, and most important, the depth
of the casing/screen to allow the appropriate water source into the well. Once the
well is completed, it must be developed. Development may be the most overlooked
issue in well construction, but good development practices will provide an efficient
well with long life and low maintenance costs.
CASINGS
Purpose of Casings
There are two main purposes for the casing. The first is to provide structural
reinforcement and stabilization for the borehole. Casings also serve to seal out
contaminated water from the land surface and undesirable water from formations
above the aquifer. A third benefit of the casing is to identify construction parameters
(i.e., well diameter, screen length, etc.) that are used to establish baseline data for
determining the optimum pumping rates given other aquifer parameters and
logging results. This initial information is used to establish baseline conditions for
future evaluation of pump and well performance.
Copyright (C) 2007 American Water Works Association All Rights Reserved
144 Siting, Drilling, and Construction of Water Supply Wells
__
Driving the casing has the benefit of not requiring grouting, but it is limited to
softer rock and soil formations and limited depth. Jetted wells or well-points are
such examples. When drilling a well using the cable-tool method, the casing should
be driven when the ground formation could begin caving. A drive shoe, attached to
the lower end of the casing, keeps the hole from collapsing. Drive shoes are threaded
or machined to fit the pipe or casing, and the inside shoulder of the shoe butts
against the end of the pipe. Drive shoes are forged of high-carbon steel, without
welds, and are hardened at the cutting edge to withstand hard driving. Some
regulatory agencies do not accept casings that are not cemented in place because
they do not positively seal the borehole. Table 6-1 shows casing sizes and pump
types for small wells.
Casings are driven using drilling tools, drive clamps, and a drive head. Where
the well penetrates water-bearing rock underlying unconsolidated material, the
casing is driven into the rock to obtain a good seal. Unfortunately, a tight seal that
will prevent pollution or unconsolidated material from entering the well from above
is not guaranteed, so a grouted seal is usually required. A length of casing is attached
to the casing previously installed by threaded coupling or welding. A drive head is
then attached to the upper end of the casing to protect it from the driving blows of
the drive clamp, which is attached to the drill stem. When the drill is lowered into
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Construction and Development 145
the length of casing and subsequently raised and lowered, the action of the dropping
clamp on the drive head forces the casing into the drill hole. The concept is similar
to drilling the well and uses the same drilling rigs. Additional protection can be
gained by driving the casing down to stable rock and under-reaming the borehole
beneath the casing to a diameter 2 in. (50 mm) larger than the outside diameter of
the shoe for a depth of 10 ft (3 m) below the casing.
The under-reamed portion of the drill hole is filled with cement grout, and the
casing driven to the bottom of the hole. Before drilling is resumed, the cement grout
is allowed to set for several days, providing a good seal. Once drilling is restarted, the
cement inside the casing is drilled out. An open, uncased hole is constructed in the
water-bearing rock below this point. Vibrating the casing into the aquifer does not
require cementing; however, the same limitations that apply to driven casings also
apply to vibrating casings into place.
While cable-tool methods limit data collection on the formation because the
casing is immediately installed, dual tube and rotary methods minimize disruption
of the aquifer when setting the casing. For collection of geophysical data, rotary
methods are the preferred method for setting the casing. Wells constructed using
rotary methods are not usually cased until drilling is completed. Because the casing
is smaller than the drilled hole, no driving is required. In some instances, a casing is
installed concurrently with drilling, such as with the use of dual-rotary drilling
methods.
Types of Casings
The well casing is a lining for the drilled hole that maintains the open hole from the
land surface to the water-bearing formation. For the casing to be entirely effective, it
must be constructed of suitable materials and be properly installed so as to be
watertight for its entire depth. If the formation could likely cave over the full depth
of the well, a single casing is usually sufficient. In these situations, the sand and
gravel caves in around the outside of the casing and closes the space between the drill
hole and the casing. However, single casings are usually restricted to smaller, surficial
wells. In deeper wells, it is preferable to have multiple casings as this makes drilling
easier in formations that may collapse. Likewise, using multiple casings may be
desirable in aquifers that are corrosive or polluted.
If one or more outer casings are installed in a well, the annular space between
the casings is filled with cement grout. With this type of installation, the outer
casing may be either left in place or withdrawn completely. Ifwithdrawn, the grout is
placed as the temporary casing is removed. Each outer casing is generally one pipe-
size larger in diameter than the outside diameter of the couplings of the protective
casing. This type of grouted installation may also be used where the water-bearing
formation underlies clay, hardpan, or other stable formations.
Copyright (C) 2007 American Water Works Association All Rights Reserved
146 Siting, Drilling, and Construction of Water Supply Wells
.+
I- +34
I I tZ4
42
-1 1 1
Casing Diameter (in.)
50
_ I l l
JLandSurface
z:1 yj
3,000
3,100
3,400
3,500 - Total Depth Approx. 3,499 ft.
Injection Well No. 2
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Construction and Development 147
There are several types of casing (pit, surface, intermediate, final, and tubing).
A pit casing is the initial casing installed at the surface to prevent the introduction of
contaminants from the surface and provide containment for the drilling operation
at the surface. The pit casing should be steel and extend through the surface soils.
The surface casing is the next casing installed. The surface casing typically seals the
surficial formation from the rest of the well. The surface casing is not used for water
table aquifers because the surface formation is the aquifer. A series of intermediate
casings may be installed to seal off successive formations where the water is not
desired or not available. Each successive casing is 6 in. smaller than the prior casing.
Figure 6-1 shows an example of a well with a series of casings. This concept is
referred to as telescoping. The final casing string is the one that seals off all
formations except the one where the water is desired. The final casing will be filled
with the water to be withdrawn. The column pipe and pump is installed inside the
final casing.
In fractured formations, care should be taken to identify where there are
connections to poorer quality water sources than those desired for water supply or
polluted water as a result of vugs and fractures in the formation. It is preferable to
use these formations only where a competent layer of low-permeability rock overlays
the aquifer. Under such circumstances, the well can be protected if it is watertight to
a depth greater than that of the deepest existing well of questionable construction in
the area and substantially below the lowest anticipated water level. The watertight
construction is achieved by drilling the hole in the fractured rock 2 in. (50 mm)
larger than the outside diameter of the casing couplings and filling the annular space
between the drill hole and the outside of the casing with cement grout. In some
areas, such construction may not be realistic because available water is cased-off.
Other methods of assuring adequate water quality protection may be necessary.
Casing Materials
Casings are usually one of four materials: carbon steel, stainless steel, fiberglass, or
PVC. Fiberglass and PVC have been used extensively in recent years for installations
in shallow wells or where corrosion and/or bacteria may be an issue. Ingot iron is
used in constructing gravel-wall wells or other large-diameter wells. In selecting a
suitable material, the stress that the casing experiences during installation and the
corrosiveness of the water and soil must be considered. All casings will provide
satisfactory service given the correct groundwater and stress environment.
Many grades of casings are available, so specifying casings must include more
than the nominal diameter of the casing. Tables 6-2 through 6-6 show examples of
the standard casing sizes for steel, fiberglass, and PVC as outlined in AWWA
Standard Al00-06. Carbon and stainless steel are the most common casing
materials (see Figure 6-2).Carbon steel has a number of benefits that make it useful:
Copyright (C) 2007 American Water Works Association All Rights Reserved
148 Siting, Drilling, and Construction of Water Supply Wells
ability tos weld, high yield and tensile strength, and high burst strength. Carbon
steel provides the most amount of protection against borehole collapse because the
strength of the material is greater than fiberglass and PVC. However, carbon steel is
subject to corrosion from galvanic and microbial contamination. Therefore, careful
consideration to the materials used in the well must occur to limit galvanic action.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Construction and Development 149
Copyright (C) 2007 American Water Works Association All Rights Reserved
150 Siting, Drilling, and Construction of Water Supply Wells
Aquifers with high microbial populations or high chlorides may not be appropriate
for steel casings.
Stainless steel has the same benefits as carbon steel. Stainless steel is an upgrade
that attempts to solve the corrosion problems but is still subject to both galvanic and
microbial contamination. In some cases, the stainless steel may be more susceptible
to microbial contamination. It is also significantly more expensive that the other
options.
Fiberglass is lightweight and corrosion resistant (see Figure 6-3)-neither
galvanic nor microbiological activity will damage it. Fiberglass is less expensive than
steel. However, fiberglass has less burst, tensile, and yield strength than steel, so
deeper wells are unlikely to use fiberglass casings (column pipes may also be
fiberglass).
PVC is the least costly and lightest weight of the potential casing options (see
Figure 6-4). Its use is becoming the more common in shallow wells as it is not
subject to corrosion or microbiological attack. Galvanic activity is not a factor. PVC
has less burst, tensile, or yield strength than steel or fiberglass. Care must be taken
during construction of wells with PVC as the heat created during the grouting
operation may buckle PVC casings.
The lighter materials (PVC and fiberglass) may be used for test wells or
temporary casings. Temporary casings may be used as forms when a grout seal is
placed around the outside of the permanent casing. The temporary casing is
withdrawn as the grout seal is placed.
Joints for permanent casings should have threaded couplings or should be
welded (in the case of steel-see Figure 6-5) to ensure water-tightness from the
Copyright (C) 2007 American Water Works Association All Rights Reserved
Source: John Largey
Figure 6-3 Fiberglass casing materials
Copyright (C) 2007 American Water Works Association All Rights Reserved
152 Siting, Drilling, and Construction of Water Supply Wells
bottom of the casing to a point above grade. This precaution will prevent surface
contamination or undesirable groundwater from entering the well from formations
above the water-bearing formation through the casing.
SCREENS
Once the casing is placed and grouted in place, the column pipe and screen, if
required, are placed. Screens are needed in most wells, especially where sand and
fine materials may enter the borehole. The screen is designed to eliminate fine
particulates that may damage downstream pumps and treatment equipment, while
allowing the maximum amount of water from the aquifer to enter the well with a
minimum of resistance. Generally, wells completed in unconsolidated formations,
such as sands and gravels, are equipped with screens. In competent rock that will not
release fines, such as limestone or granite, screens may not be required. Screens are
sometimes installed in fractured formations that may collapse into the borehole and
trap equipment.
Although a screen prevents sand from entering the well during pumping, a
screen may allow fine formation particles to enter the well during the development
process so they may be removed by bailing. At the same time, the large particles of
sand are held back, forming a permeable, graded natural-gravelpack around the well
screen itself. In this way, the hydraulic conductivity of the water-bearing formation
around the well screen is greatly increased, resulting in lower velocity head loss and
higher capacity per foot of drawdown.
Proper screen selection is extremely important in the design of a well drawing
from unconsolidated aquifers. Selection is often a complicated matter that demands
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Construction and Development 153
Copyright (C) 2007 American Water Works Association All Rights Reserved
154 Siting, Drilling, and Construction of Water Supply Wells
The design criteria for water entering through the screen opening that has been
adopted by many regulatory agencies for well construction is between 0.1 and
0.2 ft/sec (0.03 and 0.06 m/sec). The very low screen velocity criteria promoted the
use of large-diameter well screens and more efficient well construction. However,
research indicates that the actual head loss across the screen is minimized as long as
the thickness of the well screen and the percentage of open area in the screen is equal
to or greater than the specific yield of the aquifer, until the flow velocity through the
screen exceeds 2 ft/sec (0.6 m/sec) (Williams, 1985). Therefore, the most
important factor is the degree of turbulent flow that may be generated in the water
flow through the formation and gravel-pack material surrounding the well screen.
Turbulent flow head losses around the borehole increase by the velocity
squared. In laminar flow conditions, the head loss is linear with the velocity. In
properly constructed and properly developed wells of high capacity, the well loss in
head can be quite significant because of the turbulent flow in the well screen.
Turbulent flow causes movement of sand particles, mechanical plugging of the
gravel pack, as well as mechanical blockage and chemical precipitation of minerals
around the outside of the well screen.
GRAVEL PACKS
All gravel-packed wells have screens. A gravel pack is included to act as a filter to
permit the use of larger slot sizes in the well screen than would be possible if the area
surrounding the screen were not gravel-packed.When a well screen is surrounded by
an artificial gravel wall, the size of the openings is controlled by the size of gravel
used and by the types of openings.
A gravel-wall well must be carefully designed. Table 6-7 outlines the typical
grain sizes used in gravel packs. Selection of the gravel pack material is dependent on
the aquifer formation. The material used in the gravel filter must be clean, washed
gravel composed of well-rounded particles. Like the screen, the intent of the gravel
pack is to prevent fines from plugging the screen or entering the borehole in large
quantities. Gravel packs can consist of pea gravel, sand, or other rock. The filter size
depends on the size of the natural formation and the intended slot openings of the
well screen. Without proper gravel size, fine sand will not be prevented from
entering the well, and the yield of the well will be reduced. The size of individual
grains of gravel filter material should be four to six times larger than the median size
of the natural material. At the same time, the uniformity coefficient of the gravel
treatment should be similar to that of the formation material. The slot size for the
screen should retain 90 percent of the pack material. An artificial gravel-pack filter
can also be installed around the lateral well screens in a radial collector well to match
finer-grained formation materials. Figure 6-7 shows a grain size curve for two
materials Material A is much more uniform than Material B and preferable in a
gravel pack.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Construction and Development 155
The gravel pack is placed between the outside of the well screen and the
borehole. After the outer casing is in place, the screen is lowered to the bottom of
the well and centered. Selected gravel is added to the annular space between the
screen and the casing through a small-diameter tremie pipe. The gravel is placed
evenly around the screen in 2- to 4-ft (0.6- to 1.2-m) layers. As the gravel is added,
the casing and tremie are slowly raised. The procedure continues until the entire
screen is surrounded with gravel and the pack extends several feet (0.5 to 1 m) above
the top of the screen. The outer casing is pulled back high enough to expose the
entire screen section. As a rule, the screen is attached to an inner casing, extending to
the land surface, into which the pump is placed. About 25 ft (8 m) of the outer
casing is required to provide a seal against contamination by surface water. If the
entire casing is removed, the gravel treatment must not extend to the land surface.
Copyright (C) 2007 American Water Works Association All Rights Reserved
156 Siting, Drilling, and Construction of Water Supply Wells
Slot Number
(thousandth of an inch) Gauze Number
.,.,
8 70
10 60
12 50
14
16
18 40
25 30
30
35 20
40
50
125 118 in
The annular space between the working casing and undisturbed earth must be
sealed with cement grout or puddled clay to prevent contamination from seeping
into the formation. After the gravel filter has been placed, a pipe is often installed in
the finished pump base or foundation to allow additional filter materials to be
added if the gravel filter settles as a result of normal pumping operations, well
development processes, or well rehabilitation procedures (AWWA, 2003).
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Construction and Development 157
grout also provides some protection to the casing from potential deterioration from
microbiological activity. Grout material should be placed uniformly into the
annular space after water or drilling fluids have been circulated sufficiently to ensure
any obstructions in the annular space have been cleared. In shallow wells, grout can
be placed by dropping it from the surface (rude and crude-see Figure 6-8) or a
bailer. The rude-and-crude methods should only be employed when the interval to
be grouted can be seen from the surface. This generally limits usage of this method
to intervals of less than 30 ft.
The dump-bailer method is perhaps the simplest method for grout placement.
The cement grout is lowered in a dump bailer that discharges its load when it
reaches the bottom of the hole. The bailer is placed in the annular space 1 ft above
the bottom of the hole. After the grout is placed in the well, the casing is pulled up
so that the shoe is above the grout. A plug is placed in the bottom of the casing,
which is then driven to the bottom of the hole, displacing the grout into the annular
space around the outside of the casing. Bailer methods permit the grout to be placed
in stages. The elapsed time between dumps should not be more than 10 min.
However, in deeper wells, grouting the casing in place can be a challenge. If the
annular space outside the casing is large enough to accommodate a grout (tremie)
pipe, an air- or water-pressure drive is used. The tremie pipe should extend from the
Copyright (C) 2007 American Water Works Association All Rights Reserved
158 Siting, Drilling, and Construction of Water Supply Wells
~ ii ~ ~x - ___
_ _ i
surface to the bottom of the annular space. Grout is then pumped into the tremie
pipe (see Figure 6-9). As the grout is placed, the pipe is slowly withdrawn to the
surface, circulating around the casing to ensure a smooth and consistent pour all the
way around the casing. The tremie pour should be continuous, and the tremie pipe
discharge should be submerged in the grout at all times. The tremie method requires
a minimum annular space of 3 in. (7.6 cm) between casings. The minimum tremie
pipe diameter is generally 2 in. (5.1 cm), although concrete grout tremie pipes
should be a minimum 3 in. (7.6 cm) to prevent clogging. Grout material placed
using the tremie method should occur after water or drilling fluid have been
circulated to clear obstructions.
A variety of pumping methods can be used but may be limited to site-specific
applications. Pressure grouting involves forcing grout into the annular space. Grout
pumping methods begin with the installation of a pipe inside the casing. The casing
Copyright (C) 2007 American Water Works Association All Rights Reserved
Next Page
Well Construction and Development 159
Drill Rig
Drill Tube
Drill Hole
Drill Mud
Pumped
Underground
-
Figure 6-10 Pumping grout (above ground and below ground methods)
is suspended slightly .above the bottom of the borehole, and a suitable packer
connection is provided at the bottom of the casing. The packer allows removal of
the grout pipe, and prevents grout leakage into the interior of the casing.
The continuous injection method requires the grout to be placed with a float
shoe with a back-pressure valve. Tubing is run to a float shoe to carry the grout.
When the annular space is deemed clean and free of obstructions, the grout is
pumped down the tube into the bottom of the annular space (see Figure 6-10).
When the space is filled, the grout pipe is removed. Work on the well is not resumed
for at least 7 2 hr, after which time the packer connection and plug are drilled out
(AVVWA, 2003). Pumping should be continuous until the entire annular space is
filled with grout. Concrete grout cannot be used with this method. As the tubing
and shoe are not withdrawn, they must be drilled out, a complicating factor with
this method. Pressure grout has the potential problem of exceeding the burst
strength of the casing pipe if not monitored.
After grouting, an acoustic sonic log (i.e., cement bond log) should be run in
the well to determine the competency of the cement bond to the casing and
formation (or second casing, whichever is appropriate). The log should be run from
the top of the casing to the bottom at least 7 2 hr after the grouting operation but
before further construction commences.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Previous Page
CEMENT GROUTING
Water wells are cemented, or grouted, and sealed for the following reasons:
To protect the water supply against pollution,
To seal out water of an unsatisfactory chemical quality,
To increase the life of the well by protecting the casing against exterior corrosion,
To stabilize soil or rock formations of a caving nature, and
To prevent entry of stormwater run-off around the casing.
As noted in previous sections, an annular space normally surrounds the casing.
The annular space is the most likely source of contamination from the surface if not
properly sealed. Unless this space is sealed, a channel exists for the downward
movement of water. In loose caving formations, such as sand, the opening may be
self-sealing, but in stable formations, this space must be cemented to prevent
contamination from the land surface or porous formations connecting with the
surface.
Three materials are commonly used for grouting: concrete, sand cement, and
neat cement grout. Concrete grout is a mixture of portland cement (ASTM 15),sand,
coarse aggregate, and water in the proportion of at least 5 bags of cement (94 lbs/cf)
per cubic yard of concrete, and not more than 7 gal of water per sack of cement.
Bentonite and other admixtures (ASTM C 4 9 4 ) are commonly used to reduce
shrinkage, increase viscosity, and reduce permeability (Lehr, et al., 1988). A
minimum of 2 percent and a not-to-exceed maximum of 12 percent, by weight, of
bentonite clay should be added to neat cement grout to compensate for shrinkage.
Regardless of the materials used, cement, additives, and water must be mixed
thoroughly.
Sand cement grout consists of sand, portland cement, and water. The sand to
cement ratio is 2:l. Water content remains the same as do admixtures. Neat cement
is made of only portland cement and water in the ratio of 7 gal of water per sack of
cement ( 9 4 lbs/cf in each bag). Admixtures are similar to those used in concrete
grout (Lehr, et al., 1988). Curing time before further construction is based on the
type of portland cement used. Type I cement has a minimum curing time of 72 hr.
Type 11 portland cement has a curing rime of 36 hr and is preferred for many
installations as a result.
When formations located below the depth of the protective casing are known
to yield water of an unsatisfactory chemical quality, these formations may be sealed
off with liners set in cement grout for their entire length, which may be several
hundred feet deep. When a casing is extended to a consolidated formation lying
below an unconsolidated formation, the most effective way to prevent sand or silt
from entering the well at the bottom of the casing is cementing. The casing exterior
is protected against corrosion by encasing it in cement grout, as described earlier in
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Construction and Development 161
WELL DEVELOPMENT
Well development may be the most important part of the well drillingprocess and is
often underestimated with regard to the time required to properly develop the well.
As a result, many wells suffer from incomplete development from the start, which
makes them less efficient and less productive than they were designed to be. In the
long-term, this causes additional client time and both capital and operating expense
that are unnecessary.
The goals of well development are
To clear fine materials from the face of the borehole;
To clean and stabilize the formation by removing drilling mud, sand, and other
foreign materials that are pushed into the formation by the drilling process
(thereby improving porosity);
To correct damage caused by the drilling process; and
To improve ease ofwell disinfection.
The well development procedure includes all steps necessary to accomplish
these goals, including subjecting the aquifer to high levels of energy and pressure to
dislodge and remove materials that may clog the formation and reduce well
efficiency. Not all wells are developed in exactly the same way. Gravel-pack wells and
open-hole wells require different approaches, and the material moved in the open-
hole well are far different than those of the gravel-pack. The rotary and cable-tool
drilling methods have different impacts on the aquifer during construction.
Copyright (C) 2007 American Water Works Association All Rights Reserved
162 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Construction and Development 163
Copyright (C) 2007 American Water Works Association All Rights Reserved
164 Siting, Drilling, and Construction of Water Supply Wells
Improve Disinfection
Clean boreholes will have a minimum amount of surface contamination and a
limited amount of colonization of native or surface bacteria in the well. As a result,
disinfection of the well can be accomplished more easily and more quickly than in wells
that are not clean or that have not removed the biological component of the aquifer.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Construction and Development 165
and not appropriate for most installations. It requires a deeper aquifer to get enough
back-siphonage to dislodge formation materials.
Pump surging involves turning the pump on and off for short periods. This
develops a mild water hammer in the well to dislodge the cuttings and other
materials that need to be removed. Surging may also involve pumping water into the
formation and then reversing the pump to draw it out. This method solves two
problems with over-pumping-it breaks up the bridging of small particles and is less
likely to pull sands and fines to the well. However, surging does create pressure and
may damage friable formations, creating more fines and sediments that need to be
removed. Fines will continue to migrate toward the well once pumping starts so
development may be incomplete.
Air purging and mechanical block surging are essentially the same concept
using different materials. With air purging, the air pumped into the borehole
through a drop pipe or air line is replaced by water. With mechanical blocks,
specific parts of the borehole are purged as opposed to the entire borehole. The
same benefits and concerns apply to air purging and mechanical block surging as to
pump surging.
High-velocity jetting is a means to scour the borehole and remove particles.
The jetting occurs as the well is being pumped, so loose materials are moved to the
surface. Jetting has advantages in hard formations where it may quickly remove
materials on the borehole wall and screen. Soft formations should not be subjected
to jetting because the formation could be damaged.
Double-flanged swabbing can be used to develop the well and to scrub the well
to remove materials on the borehole wall. A typical swab consists of two rubber discs
sandwiched between three wood or steel discs. The swab is constructed so that the
outside diameter of the rubber disc is equal to the inside diameter of the screen,
fitting closely to the inner surfaces of the well screen and casing. The swab is
mechanically raised and lowered along the casing and well screen to draw drilling
fluids and fines through the gravel pack and into the borehole. An air-lift may be
used in conjunction with the swab to clear the borehole, or the swab may be fitted
with a one-way valve allowing removal of development water and fines.
A variety of chemicals can be used to help in well development. Acidization is
common to remove materials that cannot be swabbed or scoured off. Dispersing
agents can also be used, but most chemical action is unnecessary for initial
development. Chemical use is more appropriate for well maintenance (see chapter 7).
Copyright (C) 2007 American Water Works Association All Rights Reserved
166 Siting, Drilling, and Construction of Water Supply Wells
Redevelopment
Periodically, the well will need to be redeveloped to remove accumulated
precipitants in the screen, biological masses, and sediment buildup. Redevelopment
Copyright (C) 2007 American Water Works Association All Rights Reserved
Well Construction and Development 167
will restore much of the initial aquifer efficiency. The same basic procedure is used
to redevelop a well as was used to initially develop it. Further discussion is found in
chapter 7.
SANITARY PROTECTION
Once the well has been constructed and developed fully, the final sanitary
protection should be provided along with disinfection of the borehole, pump,
casing, pipe, and fittings. Where the minimum depth for withdrawal varies with soil
formations and surrounding conditions, the well casing should extend at least to the
depth where protection from surface contaminants is anticipated. The screen
should be set below that point. The sanitary seal prevents contamination from
migrating downward to the screen from the surface.
The sanitary seal is usually constructed of neat cement. Every well casing should
be grout sealed from land surface to the full depth. Many regulatory agencies require
a minimum of a 6-ft-square concrete pad around the well casing, sloped at 1 in. per
yard away from the well. Where a well is installed to a depth less than where
protection can be assured, the well needs to be located in a wellhead protection zone
as defined in chapter 2. It is suggested that in the immediate vicinity of the well, an
impervious layer of well-compacted clay or neat cement at least 2-ft (0.6-m) deep
should be placed on the land surface around the well. This barrier will minimize
percolation from surface water to the withdrawal point.
Another means of protection is to submerge the well screen below the pumping
level of water in the well. The pumping level of the well should never be allowed
below the top of the screen as aeration of the well screen may promote aerobic
bacteriological activity. The cascading water causes air entrainment and possible
cavitation to the pump.
Copyright (C) 2007 American Water Works Association All Rights Reserved
168 Siting, Drilling, and Construction of Water Supply Wells
pumped into the well should be thoroughly mixed with the water in the well casing
and must come in contact with the pump and discharge piping.
A gravel-pack well may prove difficult to disinfect. The material used for gravel
treatment, even though washed and clean, still carries contamination. To resolve the
problem, a tablet or powdered calcium hypochlorite can be occasionally added by
hand to the gravel-filling tube as the gravel is placed.
Even with disinfection, the water pumped from a well may still show evidence
of contamination. Under such circumstances, a chlorinator can be installed at the
well to treat all the water discharged to the system. In time (perhaps as long as three
or four months), normal pumpingwill usually rid the well of contamination. During
this period, a free chlorine residual will make it possible to use the water. Additional
information on disinfection is available in AWWA Standard A100-06.
SURFACE EQUIPMENT
The final piece of well construction is the installation of the surface equipment.
Surface equipment for wells is generally limited to some piping, a meter, and some
sample taps or probes to monitor water quality. Figure 6-14 shows an engineering
drawing for a wellhead that includes the well (top only), an air release valve, meter,
butterfly valves for flow control, a check valve to prevent backflow, piping, and pipe
supports. This installation is above ground and is shown in different perspectives.
Figure 6-15 shows an example of an installed wellhead similar to the drawing shown
in Figure 6-14. Surface equipment should be designed by a competent professional
engineer. The design should include
Lightning and transient voltage surges protection, including lightning arrestors,
surge capacitors, or other similar protection devices, and phase protection;
Access for repair and maintenance purposes that will not cause interrupted
operation;
Protection against surge and water hammer to protect the integrity of the
well system;
Operational reliability and flexibility in the event of damage to or failure of the
pipeline or a well;
Access to the well for geophysical loggingwithout disruption of operations;
Necessary screening for floatable solids prior to withdrawal to avoid plugging of
the injection horizon; and
Vandalism protection.
Copyright (C) 2007 American Water Works Association All Rights Reserved
W e l l Construction and Development 169
NOTES:
1 . Furnish and instail flange isolation kit consisting of isolating and sealing gasket,
bait isolating sleeves and isolating washers. Kits shall be manufactured by
Pipeline Seal and insulator, Inc. Houston,Texas or qual.
2. Harness dresser coupling shall have an interior coating of novocoat SP-ZOOOW
;,:\
in accordance with section 15006.
3. Restrained MJ gland shall be ebba iron or equal. Eye bolts shall be used to
connect the harness dresser coupling tie-rods to the restrained MJ gland.
b
- -
rump Lonrroi
. ,
Meter
Pressure Sustaining
Hydraulic Check Vaiw
6' 90" FL Bend 7 ,-3 90" FL Bend
112" Threaded Penetration r f
in Flange for Automatic~ ?/. ~ 6" Pipe to R
Depressurization System
Transmission System
Surface Plate 112" Stainless Stell
Ball Valve, (Typ. of 3)
Well Casing
NOTE:
1. Field run piping with assistance of engineer.
Provide linings and pipe support as required.
Copyright (C) 2007 American Water Works Association All Rights Reserved
170 Siting, Drilling, and Construction of Water Supply Wells
REFERENCES
AWWA (American Water Works Association). 2003. Manual M21-Groundwater. Denver,
Colo.: AWWA.
AWWA (American Water Works Association). 2006. Al00-06 Standardfor Water Wells.
Denver, Colo.: AWWA.
Bloetscher, F., Muniz, A., and Witt, G.M. 2005. GroundwaterInjection:Modeling, Risks and
Regulations.New York: McGraw-Hill.
Lehr, J., Hurlburt, S., Gallagher, B., and Voytek, J. 1988. Design and Construction of Water
Wells: A Guide for Engineers, National Water Well Association. New York: Van
Nostrand Reinhold.
National Groundwater Association. 1998. Manual of Water Well Construction Processes.
Westerville, Ohio: National Groundwater Association.
Williams, D.E. 1985. Modern Techniques in Well Design.Jour. AWWA, 77(9): 68-74.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Operation of Wells
WELL PERFORMANCE
Once the well is designed and constructed, two issues must be monitored on a
regular basis: well performance and water quality. Well performance issues include
the routine maintenance of pumps and motors and record-keeping of withdrawals.
Water quality monitoring and record-keeping are generally straightforward and
often dictated by regulatory agency requirements. However, ongoing issues with
fouling and microbiological activity appear to be common with wells, so those
topics will be covered in more detail.
Copyright (C) 2007 American Water Works Association All Rights Reserved
172 Siting, Drilling, and Construction of Water Supply Wells
,.".".,."" ",,", ,"
shut off the pump or sound an alarm if the flow or water level dropped below a safe
minimum level. Routine maintenance is often specified by the manufacturer and
will include greasing bearings, polarity checks, and alignment checks.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Operation of Wells 173
Gravel-packmaterial,
The depths (settings) of the casing and screen, and
The total depth of the well.
Pump data should include
The type (and make) of the pump installed,
The type and horsepower of the motor (driver),
The pump setting (depth to the pump intake),
The setting of the air line or other device for measuringthe water level in the well,
Notation for the point (and reference elevation) used for measurement of the
water level, and
All information provided by the pump and motor manufacturer, such as
capacity and efficiency data.
The total pumpage for each well is generally required by permit to be recorded
daily and reported monthly on operating reports. These numbers can be graphed to
illustrate the seasonal and yearly production rates. This data can be used for future
projection of water withdrawal rates and to monitor the actual volume of water
produced from each well. Data can usually be recorded from a totalizer on
flowmeters installed in the discharge piping for each well.
Records of water levels in the well during periods of nonuse (static) and during
pumping should be recorded to provide a baseline for determining the amount of
drawdown. The static levels can identify changes in the amount ofwater that may be
available in the aquifer with time or at any given time.
Because temperature is often indicative of changes in flow regimes in aquifers,
the groundwater temperature should be recorded and plotted. As the temperature of
the groundwater varies, the capacity of the well fluctuates as a result of the viscosity
of the water. In projects where recharge to the aquifer may come from infiltration of
surface water, the temperature of the adjacent surface water body should also be
recorded.
Operations personnel should evaluate any well failure or long-term decline in
performance to determine if physical or mechanical problems are causing the
decline. Specific capacity is a method to monitor well performance. As noted in
chapter 5, specific capacity or the ratio of the yield of each well to its drawdown is
used to plot the operational trend of each well. The specific capacity of a well should
be calculated annually to identify the potential need for maintenance, plugging
problems, or water supply concerns as outlined in chapter 4.
If specific capacity decreases, it may be the result of a drop in pumping water
levels or a reduction in pumping yield caused by microbiological fouling, chemical
precipitation, formation, well screen or gravel-pack plugging, pump corrosion, or
Copyright (C) 2007 American Water Works Association All Rights Reserved
174 Siting, Drilling, and Construction of Water Supply Wells
biofouling. Water level declines can be caused by regional water level declines or
reduced hydraulic efficiency in the well, most commonly plugging or incrustation of
the borehole, screen, or gravel pack. Other specific yield problems may relate to
Changes in the water-bearingzone,
Insufficient development of the well at time of drilling,
Pump wear; and
0 Impeller detachment from the shaft.
Proper study and comparison of data enable the operator (or consultant) to
anticipate maintenance and repair needs. Comparative data pertaining to the physical
condition of the pump unit should also be collected. This data should include
0 Water level measurements made before, during, and after the (drawdown)
pumping test,
A record of the pumping rate,
0 Hydrographs generated during the test, and
0 Any raw data collected (manual or computer generated).
Well maintenance activities should also be recorded. This data can be used to
predict times when maintenance needs to be performed, identify possible causes of
well decline, and plan for annual budgets for wellfield management when compared
to the initial test data. These records should include
0 Dates that maintenance was performed;
0 Results of pre- and postmaintenance pumping tests;
0 Methods (and materials) used in the maintenance procedures; and
0 Other factors such as the coloration of the pumped water, amounts of sand
removed, odors, and water quality analyses.
It is recommended that similar tests be rerun after any repair or maintenance work.
Design problems become evident from several operational conditions: over-
pumping (which results in lowering of the water table), clogging or collapse of a
screen or perforation of a screen section, corrosion, incrustation, and wear
aggravated by excessive intake velocities. Other problems include poor selection of
well materials (that lead to significant corrosion or collapse),incorrect specification
of pumps and poor construction (casing damage, breaches in the grout,
misplacement of screens and gravel pack, and misalignment).
Over-pumping can damage the well by reducing the storage and production
capacity of a groundwater system as described in chapter 6. In granular formations,
the water-bearingformation may consolidate. Where this occurs, it results in a lower
water table, less water storage space, reduced yield from individual wells, and can
Copyright (C) 2007 American Water Works Association All Rights Reserved
Operation of Wells 175
collapse the well casing. Wear in the screens or pumps may be a result of entrance
velocity, as water passes through the well screen (or the edge of the formation
depending on the type of well). As the entrance velocity increases, sand, silt, and
colloidal matter can enter the flow stream.
Other problems include suction breaks and electrical surges. No pump should
operate at a rate at which it breaks suction as it may cause severe damage to both the
pump and the aquifer as a result ofwater hammer (see chapter 5). Surgingin the well
may collapse the well if it was not properly stabilized. Surging can stimulate sand,
silt, and colloidal activity or dislodge corrosion and precipitates. Air bubbles may be
entrained into the wells, which can damage the distribution system piping by
causing air pockets. The solution is to remove a bowl or slow the motor speed, not to
close the valves to reduce pumping. Lightning strikes and poor grounding may cause
electrical surges that damage motors and pumps. Appropriate lightning attenuation
should be installed where required.
Well Abandonment
Regulatory agencies generally require utilities to abandon wells no longer in use.
The well must be abandoned in accordance with the regulatory guidelines. The
following is a general outline of a well abandonment plan. The plan is subject to
modification based on the nature and cause of the abandonment.
The head in the well will be suppressed by pumping a solution of sodium
chloride (salt) and/or barium sulfide (barite) into the well (if required). Blow-
out prevention equipment will be on site, should it be necessary for controlling
the well.
The well will be geophysically logged and television surveyed prior to
abandonment. The nature and extent of the geophysicalloggingwill depend on
the value and cause of the well being abandoned. The following are logs that
may be used:
- Electric logs: single-point resistivity, long- and short-normal resistivity,
and spontaneous potential,
- Gammaray,
- Caliper,
- Fluid conductivity,
- Temperature,
- Flowmeter,
- Dual induction,
- 3-D velocity log (sonic log), and
- Cement bond log (if necessary).
Copyright (C) 2007 American Water Works Association All Rights Reserved
176 Siting, Drilling, and Construction of Water Supply Wells
All geophysical logs should be performed from the bottom of the borehole to
land surface (for those logs that can be effectively performed in the cased
portions of the well). All logs that can be performed only in open holes should
be run from the bottom of the borehole to the bottom of the casing.
The bottom of the borehole should be filled with clean, washed, and
chlorinated (disinfected) gravel. The gravel should be tapped periodically to
ensure proper placement. A bentonidsand cap should be placed on top of the
gravel 5 ft below the bottom of the casing. The hole is then filled with neat
cement grout from the bentonite/sand cap to land surface.
All fluid displaced during cementing must be contained and disposed of in an
environmentallysafe manner.
A final well abandonment plan should be submitted to the appropriate
regulatory agencies at the time of application for a well abandonment permit,
subject to field modification based on logging and conditions encountered
during the abandonment.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Operation of Wells 177
Particulate Plugging
Plugged screens increase the entrance velocity of the raw water, which can increase
particle movement as well as drawdown. Sand, silt, and other particulates may clog
the screen, providing less area to draw the water. When this happens, the capacity of
the well decreases, the pumps become less efficient, and operations costs for
electricity increase. Figure 7-1 shows a borehole with sand entering a pumping weIl.
Sand will also increase wear on pumps and settle in large pipelines. Sand is
problematic for membrane processes.
Removal of sand can be a delicate process because it is possible to damage the
screen. Water samples from wells developed in sand aquifers should also be
periodically inspected for the presence of sand. The presence of sand in a well may
be an indication of eventual collapse of the well, collapse of the formation and, in
extreme cases, sinkholes. These problems are generally repairable but require
appropriate expertise to review the situation.
In most cases, particulate plugging is caused by poor well design or
construction, including insufficient development of the well or inadequate
formation sampling leading to poor screen selection and/or location. In some cases,
the logging may not have been sensitive to thin layers of sand, silt, or colloidal
matter that may be exposed with time. In wells with gravel packs, incomplete
development or over-pumpingmay be indicated by plugging of the gravel pack and
the screens.
Copyright (C) 2007 American Water Works Association All Rights Reserved
178 Siting, Drilling, and Construction of Water Supply Wells
Calcium Carbonate
One of the most common well problems is incrustation of the well screen or of the
gravel pack around the screen. This may be caused by the release of dissolved
minerals from the native water, geochemical reactions, or microbiological activity.
Calcium carbonate forms a scale on the screen and cements together particles of
sand and gravel. Calcium carbonate incrustation can usually be removed by a
chemical process.
Corrosion
Three general types of corrosion involved in water wells are hydraulic, chemical, and
galvanic. Hydraulic corrosion is caused by turbulent flow, hard particulates, and/or
wearing flow velocities, which abrade well components. Hydraulic corrosion
enlarges screens and opens holes in the casing that allow larger particles into the
casing. As deterioration accelerates, the casing material diminishes and potentially
collapses.
Hydraulic corrosion is generally caused by particulate matter from incomplete
well development or fine material within the formation that is not screened out.
Cavitation caused by turbulent flow will aggravate corrosion by flaking off pieces of
metal. Pumping at rates higher than design flow is the primary cause of hydraulic
corrosion.
Chemical corrosion is a problem in older wells because of materials used in the
past. Chemical corrosion is caused by ionization of metallic elements, typically zinc
or iron, through carbonation or oxidation reduction (redox) reactions. Chloride
ions that exist in raw water can form weak acids that react with metallic ions or
attack metals. Sulfide ions also create acids in certain environments that may attack
metal surfaces. Oxidation and reduction reactions occur in groundwater
environments and can accelerate corrosion in a well. The presence of high
concentrations of dissolved oxygen may accelerate desiccation of brass or other pipe.
Galvanic corrosion is caused by the generation of electric currents in dissimilar
metals. Galvanic corrosion is often a problem with stainless steel pumps that are
connected to steel column pipes with bronze centralizers in a steel casing. Newer
technologies and the use of stainless steel, bronze, and plastics over standard steel
Copyright (C) 2007 American Water Works Association All Rights Reserved
Operation of Wells 179
Magnesium
Magnesium Alloys
Zinc
Aluminum 25
Cadmium
Aluminum 17ST
Steel or Iron
Cast Iron
Chromium-Iron (active)
Niresist
18-8 Chromium-Nickel-Iron (active)
18-8-3 Chromium-Nickel-Molybdenum-Iron (active)
Lead-Tin Solders
Lead
Tin
Nickel (active)
Brasses
Copper
Bronzes
Copper-Nickel Alloys
Monel
Silver Solder
Nickel (passive)
18-8 Chromium-Nickel-Iron (passive)
18-8-3 Chromium-Nickel-Iron (passive)
Silver
Gold
Platinum
grades have reduced galvanic corrosion, although stainless steel grades may have
some of the same inherent problems in high chloride waters (Bloetscher, et al., 2001,
2OO2a, 2002b). Figure 7-2 shows the galvanic series. The higher the conductance
that exists between two metals, the greater the potential for galvanic action. This
corrosion is typically found where casing screen is joined, where the submersible
pumps are joined to the column pipes, or where bronze spiders exist. Poor pump
alignment, stressed threads as a result of poor assembly, or poor welds may
encourage this type of corrosion.
Copyright (C) 2007 American Water Works Association All Rights Reserved
180 Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Operation of Wells 181
Copyright (C) 2007 American Water Works Association All Rights Reserved
182 Siting, Drilling, and Construction of Water Supply Wells
Isolated From
South County
Isolated From Regional Isolated From
Bacteria Biscayne Wellfield Wellfield Floridan Wellfield
Kluyvera sp. d
Micrococcus luteus d d
Micrococcussp. d d
Plesiomonas shigelloides d
Pseudomonasaeruginosa d d d
Pseudomonasalcaligenes d J d
PseudomonasJluorescens d d d
Pseudomonaspickettii d
Pseudomonas pseudoalcaligenes d
Pseudomonasputida d
Pseudomonasstutzeri d d
Rhodococcus equi d
Runyon Group Ivmycobacterium d
Salmonella sp. d
Serratia marcescens J
Shewanella (pseudomonas)putrefaciem d
Sphaerotilus natans d
Sphingomonaspaucimoblis d
Staphylococcus aureus d
Staph-coagulase negative d d
Stenotrophomonas (xanthomonas) d d d
maltophilia
Source: Bloetscher, e t al., 2000a
Copyright (C) 2007 American Water Works Association All Rights Reserved
Operation of Wells 183
Copyright (C) 2007 American Water Works Association All Rights Reserved
184 Siting, Drilling, and Construction of Water Supply Wells
sealants can lead to physical deterioration of the well. The improper application of
certain chemical reagents, especially chlorine, and sequestering reagents or those
used during redevelopment, may exacerbate deterioration. Overly aggressive
pumping for redevelopment, over-pumping of the system, or the improper use of
surging may cause structural damage to the well in the long term.
Many older wells were installed using methods and materials no longer in use
and do not meet current standards. In these cases, the problems probably cannot be
fully corrected. For many older wells, acidification, typically using sulfamic acid, can
improve performance. Sulfamic acid solution will remove or loosen incrustation in
the screens or the column pipe, although it will not remove much biofouling.
Physical agitation or surging is a method that often removes incrustation or
reduces fine material entering the well screen or gravel pack. Tools are used that
push water down into the well and pull it out, just as old hand-pumped well systems
worked. Initially, the surge device is operated at less than 3 strokes per minute at 6 in.
to 10 in. per stroke. Over time, the frequency and the stroke should be increased,
which increases the surging. Care must be taken: if the casing or the formation is weak,
or the screens damaged, the well structure can collapse during surging.
The addition of chemicals to the well is the most common treatment. Chlorine
is used as a biocide for microbiological fouling, although in most cases it does not
kill all the bacteria, it only serves to control the biofilm. A 12 percent sodium
hypochlorite solution or commercial calcium hypochlorite provides the chemical
strength needed for chlorination of the bacteria. In some cases hydrogen peroxide
may be used to address biofouling problems, but certain bacteria, such as the
Pseudomoms species, may be able to use the oxygen to their benefit, increasing
rather than decreasing biological activity.
Another option is acidification, dropping the pH to less than 2. Hydrochloric,
sulfuric, and nitric acid are used, but these chemicals must be used carefully.
Sulfamic acid is preferred by some hydrogeologists for this reason. Deterioration of
the well materials must be weighed against the removal of the biofilm or the
incrustation. The addition of phosphates has been used, as it makes water “more
slippery” and increases total well capability. However, phosphates provide a nutrient
for biofilm. In all cases with chemical use, a plan for handling hazardous material
and disposal must be made. None of these chemicals should be discharged to the
ground: they must be hauled to an approved disposal site.
Another method, carbon dioxide injection (also hydraulic fracturing), uses
gaseous carbon dioxide and liquid carbon dioxide under 100 psi of pressure. This
technique causes the carbon dioxide to enter the formation, dropping the pH
through a conversion of the CO;?to carbonic acid. The water freezes, cracking and
loosening incrustation. The formation may also crack and loosen, which can free the
fractured zones or crack the bedrock formations and potentially increase yield. After
the carbon dioxide is injected, the well is surged and redeveloped.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Operation of Wells 185
"-
Sonar jetting is a relatively new method used to remove incrustations and may
reduce biofilms. A sequence of small blasting caps is suspended and exploded,
sending shock waves through the casing. Incrustations generally are blasted off the
well screen, formation, and casing. After sonar jetting, surging and full
redevelopment of the well must occur to remove all of the excess debris.
Acidification improves the process to remove the encrustration to some extent. The
problem with this process may be the inability to get permits to do the blasting, and
the potential damage to the casing, cement seal, and/or the screens that may occur.
Other methods that show some promise in certain specific cases are sectional flow
control devices and inner sleeve installations within the casing, using entrained air
to reduce fouling.
Owners and operators of wells that have increasing levels of contamination
should immediately begin assessing their alternatives for correcting the problem.
The major choices that may be considered in attempting to locate the source of
contamination are to
Determine if correction or removal of the source will allow the aquifer to return
to normal;
Determine whether the plume of contamination flowing toward the well can be
blocked or intercepted;
Determine if it is economically feasible to treat the water to remove the
contamination;
0 Investigate whether altering the well to draw water from a different aquifer
is possible;
Investigate the feasibility of drilling a replacement well at another location
where there is no contamination:
0 Investigate whether water from the contaminated well can be blended with
water from an uncontaminated source to bring the finished water-level below
the MCL;
Investigate changing to a surface water source; OK
Investigate purchasingwater from another water system.
Although groundwater quality does nor vary much with time, certain quality
features do gradually change.
Copyright (C) 2007 American Water Works Association All Rights Reserved
186 Siting, Drilling, and Construction of Water Supply Wells
REFERENCES
AWWA (American Water Works Association). 2003. Manual M21-Groundwater. Denver,
Colo.: AWWA.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Operation of Wells 187
Bloetscher, F., Bullock, R.J., Fergen, R.E., Witt, G.M., and Fries, G.D. 2002a. Is It Time for
Water Plant Engineers to Revisit the Selection of Stainless Steel Grades in Water and
Wastewater Treatment Environments, Part 1. Water Engineering and Management,
149(5):36-44.
Bloetscher, F., Bullock, R.J., Fergen, R.E., Witt, G.M., and Fries, G.D. 2002b. Is It Time for
Water Plant Engineers to Revisit the Selection of Stainless Steel Grades in Water and
Wastewater Treatment Environments, Part 2. Water Engineering and Management,
149(6):12- 15.
Bloetscher, F., Bullock, R.J., and Witt, G.M. 2001. Brackish Water Supply Corrosion
Control Issues Using 316L Stainless Steel. In Proc. of the ASCE-EWRI Annual
Conference, Orlando, Fla. Reston, Va.: ASCE.
Bloetscher, F., Fergen, R.E., Witt, G.M. 2000a. Biofouling Concerns from Raw Waters
Sources in Membrane Water Treatment. In Proc. of the American DesaltingAssociation,
Lake Tahoe, Nev. Stuart, Fla.: American Membrane Technology Association.
Bloetscher, F., Muniz, A., and Witt, G.M. 2005. Groundwater Injection:Modeling, Risks and
Regulations. New York: McGraw-Hill.
Bloetscher, F., and Witt, G.M. 1996. Well Plugging Problems: Case Studies in Collier
County, the City of Venice and the City of Hollywood, Florida. In Proc. of the A W A
Annual Conference.Denver, Colo.: AWWA.
Bloetscher, F., and Witt, G.M. 2000. Effects of Silt, Salt and Other Fouling Mechanisms
Affecting Groundwater Treatability. In Proc. of the A W A Annual Conference.Denver,
Colo.: AWWA.
Bloetscher, F., Witt, G.M., Dodd, A.E., and Dodd, C.P. 2000. Brackish Water Supply
Corrosion Issues Using 316L Stainless Steel. In Proc. of the Florida Section A W A
Annual Conference.
Bloetscher, F., Witt, G.M., Dodd, C.P., and Dodd, A.E. 1998. Prevention of Biofouling in
Membrane Water Treatment Plants. In Proc. of the A W A Annual Conference. Denver,
Colo.: AWWA.
Chapelle, F.H. 1993. GroundwaterMicrobiology and Geochemistry, New York: John Wiley
& Sons.
Gerba, C.P., and Bitton, G. 1984. Groundwater Pollution andMicrobiology.New York: John
Wiley & Sons.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Summary
Groundwater is water that flows downward by gravity until it contacts a layer of rock
or other impenetrable material, creating, an aquifer. This water may have entered the
soil as a result of rainfall or snow melt, or it may be an ancient source found well
below the surface. Groundwater moves downhill, taking the path of least resistance
to the flow. Therefore, if underground conduits or channels (i.e., voids and/or
fractures that lead to high permeability) are present, the water will tend to flow in
these pathways. These formations may yield substantial quantities ofwater to wells.
Groundwater can' have significant advantages over more traditional surface
water uses. These advantages include:
0 Less exposure to contamination (assuming not a surficial aquifer);
0 Water quality is stable;
Water temperature is stable;
Water quality changes are slow to occur;
0 Evapotranspirationlosses are insignificant; and
Less treatment typically is required.
However, groundwater sources have the following disadvantages:
Difficult to clean up once contaminated;
No early warning of contamination-unseen plumes of contaminants can
migrate into a wellfield without warning unless sentinel wells are constructed;
Competing uses from urban industrial, commercial, agricultural, irrigation, and
ecosystem users in the same area;
Determining the safe yields of material often is uncertain;
0 Water levels are not obvious;
Copyright (C) 2007 American Water Works Association All Rights Reserved
190 Siting, Drilling, and Construction of Water Supply Wells
Supplies are often limited in basins, which is why most large utility systems rely
on surface supplies, not groundwater.
Well siting considerations include four issues: site availability, water supply,
water quality, and wellhead protection limitations. Many small water systems also
include land costs as a prime consideration when selecting sites for public water
supply wells; however, this may overlook significant water quality or water quantity
issues. Selecting suitable water quantity and quality are intertwined. The water
system must balance factors including well depth, geology of the area, characteristics
of the rock formations, and dissolved minerals in the aquifer.
The SDWA and its associated amendments are focused on protecting the
public health from various contaminants in potable water supplies. This has impacts
on groundwater use- the groundwater rules, wellhead protection programs, and
water quality requirements all have impacts on the selection and treatment of
groundwater supplies. Whether surface waters, groundwaters, or via operation and
treatment, SDWA has basic requirements that must be met.
There are many drilling methods and many methods of well construction that
have been developed for wells. The following are a variety of wells that serve many
purposes:
Water production (the focus of this'document)
Oil and gas wells
Geothermal wells
Injection/disposal wells
Aquifer storage and recovery wells
Environmental remediation wells
Environmental remediation wells are the shallowest of this group, often less
than 10 ft deep, while oil and gas wells may be thousands of feet deep. Water supply
wells fall somewhere in between. The following are the primary drilling methods for
water supply wells:
Cable tool
0 Hollow stem auger
Hydraulic rotary
Mudrotary
Reverse-air circulation
Dual tube
All well projects go through a series of steps: predesign, regulatory criteria,
design, construction and testing, and operations issues. Most testing occurs once
Copyright (C) 2007 American Water Works Association All Rights Reserved
Summary 191
some form of construction has begun-usually with a test well. Once the
exploratory or test well is complete, geophysical logging can commence.
Appropriate drilling, geologic, geophysical, and video logs and other tests, such as
caliper and packer tests, must be conducted during the drilling and construction of
new wells. Results for this testing permit engineers and hydrogeologists to define
the appropriate zones in the formation to case, and those to leave open. When
construction is complete, well development may be the most important part of the
well drilling process and is often underestimated with regard to the time required to
properly develop the well.
Once the well is designed and constructed, two issues must be monitored in a
wellfield on a regular basis: well performance and water quality. Well performance
issues include the routine maintenance items for pumps and motors and record-
keeping of withdrawals. Groundwater withdrawal wells provide good service to
most utilities for many years, but all wells are subject to fouling and other
performance problems. These concerns include
Mechanical failures, including failures of electrical motors and pumps, and
failures of valves,
Poor operating and maintenance procedures,
Poor well design and construction practices, including insufficient placement of
grout; improper design of pumps, valves, and fittings; and excessive drawdown
allowances,
Hydrogeologic constraints that cannot be evaluated at the time of design or
change over time, such as:
- sand, clay, or rock layers that are unstable and collapse into the borehole;
- naturally occurring or induced fracturing and faulting;
- long-term water quality changes caused by changes to the hydraulic regime,
such as dams;
- water hammer to the aquifer;
- effects caused by mining of the water or introduction of chemicals and
microorganisms; and
- naturally occurring phenomena (such as sinkholes, karst terrain features,
or faults).
High silt or sand content caused by failure to develop the wells fully, or
intercepting sand or silt layers that have not or cannot be sealed off in the
borehole or corrected in well design.
All of these problems may exist in conjunction with, or as a result of,
microbiological fouling problems in wells. As treatment technologies advance, the
Copyright (C) 2007 American Water Works Association All Rights Reserved
192 Siting, Drilling, and Construction of Water Supply Wells
need to review and correct well performance problems, especially fouling concerns,
has taken on greater significance.
All wells can plug or foul because of hydrogeologic, geologic, engineering, and
construction factors. The problems are usually physical, mechanical, or
environmental in nature. For example, performance problems are typically caused by
fouling or sand and silt production in wells. These problems and their likely causes
are outlined below.
Water level decline in the well
- reduced hydraulic efficiency in the well, most commonly plugging or
incrustation of the borehole, screen, or gravel pack
- regional water level declines
- well interference or plugging of a gravel pack by sand, silt, or clay
Lower specific capacity
- drop in pumping water level
- reduction in pumping yield caused by incrustation, formation plugging,
pump corrosion, and biofouling
Lower yield
- dewateringor caving in of a major fracture or other water-bearing zone
- insufficient development of the well
- lack of connection to water-bearingfractures
- pumpwear
- impeller detachment from shaft
- incrustation, plugging, or corrosion and perforation of column pipe
Sand/silt pumping
- presence of sand or silt in fractures intercepted by well completed open-hole
- leakage around casing bottom
- inadequate screen and filter-pack selection or installation
- screen corrosion
- collapse of filter pack caused by excessive vertical velocity and wash-out
Silt/clay infiltration
- inadequate seal around the well casing or casing bottom
infiltration through filter pack
- mud seams in rock
Copyright (C) 2007 American Water Works Association All Rights Reserved
Summary 193
-"
Copyright (C) 2007 American Water Works Association All Rights Reserved
About the Authors
Mr. Albert Muniz is currently a vice president with Hazen and Sawyer, P.C.,
managing their Boca Raton office. Hazen and Sawyer is one of the top
Copyright (C) 2007 American Water Works Association All Rights Reserved
Siting, Drilling, and Construction o f Water Supply Wells
Mr. John Largey is currently a hydrogeologist with Hazen and Sawyer, P.C.,
based in Boca Raton, Fla., managing field operations for diverse drilling programs.
Hazen and Sawyer is one of the top environmental engineering firms in the western
hemisphere, involved in water resources, water supply, water treatment, wastewater
treatment, and injection programs. Mr. Largey has over 20 years experience
involving all aspects of drilling wells for a variety of applications including water
supply; Class I, Class 111, and Class V injection wells; oil and gas; geotechnical
investigation; environmental investigation; and environmental remediation. Mr.
Largey can be reached at 2101 N.W. Corporate Boulevard, Suite 301, Boca Raton,
FL 3343 1-7343.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Dedication
Dr. Bloetscher dedicates this work to his parents, Frederick and Virginia Bloetscher
in Tamarac, Fla. They are the initial (and continuing) proofreaders of all of the
documents.
Mr. Muniz dedicates this work to his family, especially his wife, Dr. Lori S.
Muniz, who has supported his efforts throughout his career, and to his children
Natalie, Albert0 (Tony), and Alexis.
Mr. Largey dedicates this work to his wife, Diane Mason-Largey, who has
lovingly endured the many long days and nights in the life of a field geologist, and to
Alice B. Largey, a true rock hound.
...
Xlll
Copyright (C) 2007 American Water Works Association All Rights Reserved
Figures
vi i
Copyright (C) 2007 American Water Works Association All Rights Reserved
...
Vlll Siting, Drilling, and Construction of Water Supply Wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
4-18 Example of Alternative Solution for Drawdown Response100
4-19 Example of Drawdown Response at Impermeable Boundary 106
4-20 Example of Drawdowns Response at Recharge Boundary 107
5-1 Interfering Drawdown Between Wells 129
6-1 Telescoped Well 146
6-2 Steel Casing Materials 150
6-3 Fiberglass Casing Materials 151
6-4 PVC Casing Being Installed 151
6-5 Welding a Casing Pipe 152
6-6 Well Screen 153
6-7 Well Screen Size Chart 156
6-8 Dump Methods for Grouting 157
6-9 Tremie Pipe 158
6-10 Pumping Grout (above ground and below ground methods) 159
6-11 Cube Packing >40%Porosity 163
6-12 Rhombohedra1 Packing >25%Porosity 163
6-13 Formation Collapse 163
6-14 Drawing of Wellhead 169
6-15 Photograph of Wellhead 170
7-1 Sand Entering a Borehole 177
7-2 Galvanic Series 179
7-3 Bacterial Quantities in a Well 183
Copyright (C) 2007 American Water Works Association All Rights Reserved
Tables
xi
Copyright (C) 2007 American Water Works Association All Rights Reserved
INDEX
Note: f. indicates figure; t. indicates table.
Acidification 184
Acoustic logging 88 88f. 88t.
in conjunction with caliper logs 89 89f.
Aerial maps 6f. 7 7f.
Air-line devices 96
Aquifer testing 71 91
and casing depth 94
and cone of depression 94
and cuttings 95
drawdown method of calculation 98 99f. 100f.
identification of aquifer boundaries 105 106f. 107f.
monitor wells 95
Packer tests 93 191
and pump depth 94
ratios between transmissivity and specific
capacity for different aquifer types 107
recovery method of calculation 99
reverse-air method 91
specific capacity method 101
step-drawdown testing 101
and storage coefficient 93 95
and transmissivity 93 95
transmissivity equation 97
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Bacteria 22 23 113
coliform 115
found in South Florida aquifers 180 181t. 182t.
This page has been reformatted by Knovel to provide easier navigation.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Bacteria (Cont.)
iron 114
monitoring 180 183f.
presence in aquifers 180
removal by soil 25
slime-producing 114
speciation 115
survival time 25 25t.
Walkerton (Ontario) E. coli case study 26
See also Biofilm; Microbiological fouling
Bacteriophages 24
Biofilm 114 180
See also Bacteria;
Microbiological fouling
Biological Activity Reaction Test (BART) 183
Boreholes
clearing fines from 161
geophysical logging 71 73 75f.
photography 91 94f.
plugging 177 177f.
thickness 139
Boron 116
Bottom-hole pressure 131
Broward County (Florida) wellhead
protection zones 17 18f.
Bucket-type drilling method 41 42f.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Casings (Cont.)
surface 147
telescoped 146f. 147
types 145
welding 150 152f.
Chemical corrosion 178
Clay
causes of infiltration 192
gamma log response to 83 84 84f. 85f.
Clogging potential 109
Coliform bacteria sampling 115
Collapse strength 133
of steel casing 133 134t.
Colloids 109
testing 112
Cone of depression 94
Cone of influence 119
Confined aquifers 2
flow equation 128
ratio between transmissivity and specific
capacity 107
storage coefficient 126
Confining units 1
Construction
casings 143
gravel packs 154
grouting 156
installation of surface equipment 168 169f. 170f.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Construction (Cont.)
screens 152
See also Sanitary protection; Well
development
Contaminants 22
See also Dissolved
inorganic salts; Endocrine disruptors;
Maximum contaminant levels;
Pathogens; Pesticides; Synthetic
organic compounds; Volatile organic
compounds; Waterborne diseases
Coring 65
boxed cores 65 65f.
core barrels 65 66f.
core samples 65 65f.
Corrosion 178
Cryptosporidium 15 22 183
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Disinfection 167
improving 164
Disinfection By-Products Rule 16
Dissolved inorganic salts 20
Down-the-hole hammer drilling method 63 64f.
Drawdown 119
and impermeable barriers 105 106f.
method of calculation 98 99f. 100f.
and recharge barriers 105 106 107f.
and specific capacity method 101
wellfield 18 21f.
See also Step-drawdown testing
Drilling methods 37 190
air rotary 58
bucket-type 41 42f.
cable-tool 42 43f. 44f.
caissons 45
California (stovepipe) method 40
comparison 68t.
down-the-hole hammer (DTHH) 63 64f.
drive points 39 39f. 40f.
driven wells 39 39f. 40f.
dual-tube (reverse-air) 61 61f. 62f.
foam 58
hand digging 38
hollow stem auger 45 46f. 47f.
hydraulic rotary 47 48f. 49f. 50f.
51f. 52f. 53f. 55f.
56f. 57f.
jetting 41
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
E. coli 26
Electric tape 96
Electrical conductivity (EC) logs 82 83f.
in conjunction with neutron logs 87
in conjunction with temperature logs 89
Electrical resistivity
log adjustments for temperature 81 81f.
of selected aquifer materials 80t.
single-point log 79 79f.
subsurface 79 79f. 80t. 81f.
surface 75 76f.
This page has been reformatted by Knovel to provide easier navigation.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Gallionella 23 114
Galvanic corrosion 178
Galvanic series 179 179f.
Gamma logs 82
in conjunction with caliper logs 84 85f.
in conjunction with neutron logs 87
energy for 83 84t.
response to clay and silt 83 84 84f. 85f.
Gamma-gamma logs 86
Geophones 76
Geophysical logging 71 73 191
See also Lithologic logging; Subsurface
geophysical methods; Surface
geophysical methods
Ghyben-Herzberg principle 131
Giardia lamblia 15 16 22 183
Gradient 119 121
defined 122
equation 122
Gravel packs 140 154 155
grain sizes 154 155t.
materials and selection 154
and screens 154 156f.
Ground Water Rule 16
Groundwater 1 189
advantages and disadvantages of use 4 189
aquifer types 1
defined 189
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Groundwater (Cont.)
flow velocity and direction 2
and hydrologic cycle 1 2f.
information sources 5
and pollution from underground fuel
tanks 13
water quality 3
Grout 140 145 156
acoustic sonic log to determine
competency 159
cement 160
concrete 160
continuous injection 159
dump-bailer method 157
materials 160
neat cement 160
pumping 158 159f.
purpose 160
rude and crude 157 157f.
sand cement 160
tremiepipes 157 158f.
Hand digging 38
Head. See Head loss; Head-to-pressure
conversion; Hydraulic head; Total
dynamic head; Total head
Head loss, and screens 154
Head-to-pressure conversion 132
Heterotrophic plate counts 115
This page has been reformatted by Knovel to provide easier navigation.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Jetting 41
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Managanese 178
Maximum contaminant levels (MCLs) 15
Microbiological fouling 179
chemical treatment 184
and electrical potential and pattern of
well casing 180
and sonar jetting 185
treatment by acidification 184
treatment by carbon dioxide injection 184
See also Bacteria; Biofilm
Microbiological issues 113
and sampling 115
Mineral pollutants 20
Mining of the aquifer 94
Monitor wells. See Sentinel monitor wells
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Ohm’s law 79 80
Over-pumping
problems caused by 174 193
in well development 164
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Screens (Cont.)
selection 152
slot size 153
SDI. See Silt density index
SDWA. See Safe Drinking Water Act
Sea level 122
Secondary drinking water standards 13 15t.
Seismic refraction and reflection 76
shots 76
thumpers 76
Semiconfined aquifers (ratio between
transmissivity and specific capacity) 107
Sentinel monitor wells 9
for aquifer observation 95
for water quality sampling 115
Silt 109
causes of infiltration 192
causes of pumping 192
gamma log response to 83 84 84f. 85f.
SDI testing and equation 112
Silt density index
equation 113
testing 112
SOCs. See Synthetic organic compounds
Sodium 116
Solid tool drilling method. See Cable-tool
drilling method
Sonar jetting 185
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Specific capacity
calculation 103
causes of decline in 192
as indicator of well performance 173 193
method of drawdown calculation 101
ratios with transmissivity for different
aquifer types 107
and water quality monitoring 176
Specific retention 119
definition 121
equation 121
values for various geologic materials 121 122t.
Specific yield 119 126t.
definition 120
and drawdown equation 102
equation 120
Spontaneous potential (SP) logging 81 82f.
Springs 1
Spudder drilling method. See Cable-tool
drilling method
Step-drawdown testing 11 101 119
equation 102
procedure 101
Storage coefficient 93 95 119 126
126t.
and confined aquifers 126
defined 126
and drawdown equation 102
drawdown method of calculation 98 99f. 100f.
equation 126
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Tape measures 96
Telescoping 45
Temperature
logs 89
record-keeping 173
Test wells 129 190
Total dynamic head 132
Total head
defined 123
equation 123
Transmissivity 93 95 119 120
126 126t.
defined 125
difference in values from place to place 127
and drawdown equation 102
drawdown method of calculation 98 99f. 100f.
equation 97 125
ratios with specific capacity for different
aquifer types 107
recovery method of calculation 99
and water level 95
Tremie pipes 157 158f.
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Velocity
entrance 138
up-hole 130
Viruses 22 24
removal by soil sorption 25 27t.
sensitivity to UV light and temperature 26
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Viruses (Cont.)
survival time 24
travel distances in groundwater 26 26t.
Volatile organic compounds (VOCs) 14
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Waterborne diseases 15 22
and microorganisms 22
Well abandonment 175
Well development 161
air purging 165
chemical additives 165
cleaning and stabilizing formation 162 163f.
clearing fines from borehole 161
correction of damage caused by drilling 162
double-flanged swabbing 165
goals 161
high-velocity jetting 165
improving disinfection 164
mechanical block surging 165
methods 164
over-pumping 164
protocol 165 185
pump surging 165
raw-hiding 164
redevelopment 166 185 193
See also Construction
Well efficiency 105
Well loss 138
constant 103
defined 103
in feet 105
and well efficiency 105
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Copyright (C) 2007 American Water Works Association All Rights Reserved
Index Terms Links
Yield
casing sizes for based on 144 144t.
causes of decline 192
Copyright (C) 2007 American Water Works Association All Rights Reserved