Commisioning Plant Course
Commisioning Plant Course
Commisioning Plant Course
Commissioning And
Troubleshooting Course
Initial Operation:
• The phase in a project after start-up of the complete plant in order to adjust
and optimize and prepare the plant for the performance testing phase.
Hot Commissioning / Live Commissioning:
• Design process fluids are introduced in the systems and sub-
systems.
Performance Testing:
• Check if the plant meets the specifications under normal operating
condition.
Post Commissioning:
• Solving of outstanding punch points after the plant has been
handed over to the client.
De-Commissioning:
• Means taking out of active use and dismantling of an industrial
plant.
Safety and Environmental Considerations
During Commissioning stages there are hazard that could cause damage
to the Newly installed equipment, Injury People , Impact Environment .
All the steps within each stage should be considered for any project, of any
size, to ensure all of the commissioning activities required are included in
the management system to get successful plant start-up.
The Commissioning Phases
Prepare:
Activities to be taken to set commissioning up, gather information, select the
commissioning team, develop the schedule and create documentation.
Implement:
This phase, is “commissioning”, examines the facets that address the installation,
checking and start-up of the new equipment.
Close out:
The final stage of the commissioning process: ensuring that all paperwork systems and
trials are complete, and that the plant or equipment has met its acceptance criteria,
enabling the plant to be handed to the ongoing operations group.
• The commissioning team upon agreement With the Project Manager and Commissioning
Managers Will attend the following reviews:
P&ID, Piping isometric, Plant Layout, Constructability, 3-D model, Schedule, SIL, LOPA and
action upon alarm
• Compile the Commissioning Schedule