Cost Calculation Program For Productivity in Welding
Cost Calculation Program For Productivity in Welding
Cost Calculation Program For Productivity in Welding
In an increasingly competitive marketplace, every firm should set itself two main objectives:
recover productivity and reduction of costs.
This program allows costs calculation and welding times on the basis of incorporated operating
economic parameters, and also can make comparisons with a different solutions by simulating
the use of a different process, for example changing from manual electrode welding to a process
using continuous solid or cored wire so as to reach a strategic decision as to the performance
of the current situation, or the need to change. Increased deposition speed allows large cost
reductions and time savings to be achieved, as can be easily checked by means of the program.
It is even possible to assess the impact on costs reduction and increased productivity following
the introduction of automatic, automated and/or robot stations taking into account cost and
time of the new investment too. In this case, the winning factor is the increase in intermittency,
i.e. the time during which the welding arc is at work compared to the total welding time, which
translates into an increase in productivity.
If we look at the total costs of an industrial welded product (figure 1), with a large approximation
we can see that the composition of costs is as follows :
• design and engineering, approx. 5%;
• raw materials, approx. 35%
• labour, approx. 43%
• general services, approx. 10%
• depreciation, approx. 5%
• welding consumables, approx. 2%
1
PRODUCTIVITY IN WELDING
Just the fact of adopting a semiautomatic wire process instead of using the electrodes – to go
back to the above example – often allows a significant reduction in costs per metre of welding.
At the same time, and irrespective of cost, a reduction in welding times is achieved and that
means increased productivity.
The issue connected to productivity is perhaps the most important. It is therefore of fundamental
importance to clarify better this issue.
Achieving savings in welding costs is certainly a positive feature, but as can be seen from
the diagram shown above, any impact on the total cost of the artefact is going to be of small
significance in the overall economy of the firm. Not only, sometimes more expensive unit cost
of the new brought in material – above all in situations where the cost of labour is especially low
as it is in less industrialised countries – could result in greater cost per meter of welding and
discourage the potential user to change to a new welding process/welding consumable.
2
COST CALCULATION PROGRAM
Areas of improvement
The first question users must ask is: “Are we using the fastest welding process suited to the
work we do?” The fundamental factors that have a bearing on cost and productivity are:
- Deposition rate (kg/h) of the brought in material.
- Intermittency in the welding process used.
As regards the brought in material, in the diagrams shown in the following pages typical values
of deposition rates are indicated for various products:. Increasing the deposition rate speed, a
corresponding reduction in welding cost are achieved, indicatively as follows
- Manual electrode welding MMA
- Welding with solid wire MIG/MAG
- Welding with cored wire FCAW
- Welding with submerged arc SAW
As regards as of the welding processes, every increase in intermittency generates a reduction
in welding cost, indicatively as follows:
- Manual electrode welding
- Semi automatic or automatic welding with solid or cored wire
- Automatic welding with submerged arc
- Automated and/or robot welding processes
A shining example of synergy in the factors shown above, coming from the market itself, was
the change of route taken by industry over the last decades, and is still going on, that made
great use of manual electrode welding, in favour of cored wire which was the only alternative
that could meet the need as to quality, flexibility and capabilities offered by the electrode. In
this case, the greater speed of deposition rate and the change from a manual process to a
semiautomatic one with improvements in intermittency, brought enormous savings in costs
and productivities increases , even considering the more expensive unit cost of cored wire
as compared with the electrode, and even bearing the investments needed in wire welding
equipment.
3
PRODUCTIVITY IN WELDING
As first operation, type in a comment (name, type of joint, date etc.) that will later appear on
the printout.
The procedure is fully guided so we do not need to go into the modes of operation.
It is important however to give certain information as to the selection of parameters, so that the
final result will be reliable.
1.0) In phase one, the program requests a series of economic and financial data as well as
operating variables, so as to calculate the cost of welding per time unit ( /hour).
The data requested are:
1.1) Type of material to be welded – Choose from the options offered. In the event of
material not in memory, its specific weight can be forced in (kg/dm3)
1.2) Welding process – Choose from the options offered.
1.3) Flux efficiency – This concerns only the so-called high recovery fluxes, i.e. those that
have been enhanced with iron powder and where there is an increased output. In all other
cases, if normal agglomerate or pre-fused fluxes are used, input 100
1.4) Consumption Kg/flux per Kg/wire or Ratio (Kg Flux/Kgwire):
If the data are known: input these.
If they are not known, find the manufacturer’s indications or in any event keep the following
table in mind:
Approximate values for submerged arc welding:
Fused fluxes: 1.1 – 1.4 Kg./per Kg. wire
Agglomerate fluxes: 0.6 – 0.9 Kg./per Kg. wire
High recovery fluxes: 1.4 – 1.7 Kg./per Kg. wire
Approximate values for welding in protective atmosphere:
Solid wire/C02: 0.3 – 0.4 m3/Kg
Solid wire/mixture: 0.25 – 0.50 m3/Kg
Cored wire/C02: 0.20 – 0.25 m3/Kg
Cored wire/mixture: 0.2 - 0.3 m3/Kg
4
COST CALCULATION PROGRAM
1.5) There is an option between CO2 (commercially sold at /Kg) and Argon mix or pure Argon
(commercially sold at /m3).
1.6) Consumable name
Insert as brief description, or the AWS Classification
If an ESAB product is chosen, the more usual ones appear listed on the screen.
In this case just digit the relative no. (in the event of change in type – remember to clean
the line and go back with the cursor!).
1.7) Deposition rate
This means the theoretical amount of metal deposited, i.e. at 100% of intermittency.
In other words they are the Kgs that would be deposited if it were possible to weld
uninterruptedly, without detaching the arc, for one hour. If there are values known in the
workshop; use these. Otherwise, ask the supplier (see too, the attached diagrams). These
values are influenced essentially by the intensity of current and it is therefore necessary to
take the applicable parameters concerning welding type be performed and the welding
position into account too (which does not always allow the productivity of the electrode
used to be exploited to the maximum).
1.8) Net efficiency
Indicates as a percentage the quantity of metal actually deposited (e.g. 67 means that
one Kg of consumable materials deposit 67% of its weight in weld).
For various products in the ESAB catalogue these values are indicated.
In other cases:
Coated electrodes: I = 350 mm.: 63% approx.
Coated electrodes: I = 450 mm.: 68% approx.
MAG wire: 95%
METALCORED Cored wire: 95% approx.
Rutili-basic cored wire: 85% - 90%
Submerged Arc Welding: 98% approx.
5
PRODUCTIVITY IN WELDING
10
8
D
7
0
33.8
OK
5 C
4
B
3 D
OK 48.60
C OK 43.39
OK 43.32
A OK 48.50
OK 33.80
2
B
A
1
6
COST CALCULATION PROGRAM
D
4
OK 61.30
KG/hour
C
3
B
2
A = DIA. 2,50
B = DIA. 3,25
C = DIA. 4
D = DIA. 5
7
PRODUCTIVITY IN WELDING
8
KG/hour
6
1.6
7
1.2
5
1
4
0,8
3
0
0 50 100 150 200 250 300 350 400
AMPERE
16
KG/hour
14
7
3.9 .76
12 4
7
3.1
6
10 5.5
8
2.3
8 8
1.9
1.6
6
0
0 200 300 400 500 600 700 800 900 1000
AMPERE
8
COST CALCULATION PROGRAM
8
1,2
6
KG/hour
STICK-OUT
4 15 - 20 mm
1,2
8
6
KG/hour
STICK-OUT
4 1,20 mm - 15/20 mm
9
PRODUCTIVITY IN WELDING
6
1.
6
KG/hour
2
1.
STICK-OUT
1,20 mm - 20 mm
4 1,60 mm - 20 mm
10
COST CALCULATION PROGRAM
11
PRODUCTIVITY IN WELDING
12
COST CALCULATION PROGRAM
UPPER ANGLE
DEPTH OF FUSION
GAP
GAP S
DIU
RA
US ER
I W ROOT THICKNESS
AD LO
R
P ER LOWER CHANFER
UP HEIGHT
LOWER ANGLE
Note : for single U joint reply 0 to the questions “Lower radius.” - “lower angle” - “lower joint : height”.
ROOT
THICKNESS
LOWER
CHAMFER
GAP HEIGHT
LOWER ANGLE
Note: K Joint
13
PRODUCTIVITY IN WELDING
THICKNESS
ROOT
GAP
Note: Fillet weld joint (where angle =90°, thickness = throat, Root = 0)
T) T
EN EN
ES EM
PR RC
(IF FO
90
N
°
EI
R
TH
THICKNESS
GAP
14
COST CALCULATION PROGRAM
Note
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
15
PRODUCTIVITY IN WELDING
Note
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
.................................................................................................................................................
16
COMEX-T-02k-0307