Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Chimoio Water Supply Project FinalDesign

Download as pdf or txt
Download as pdf or txt
You are on page 1of 124

Chimoio Water Supply 

Project 
FinalDesignReport 

ADVENTIST  DEVELOPMENT  AND RELIEF  AGENCY 


MAPUTO  ­ MOZAMBIQUE 

1LZ  ­0f,­ 11 

CHIMOIO WATER  SUPPLY  PROJECT  

FINAL DESIGN  REPORT  

Financed  by:  On behalf of:  


USAID  National  Directorate  of Water  
Rua Faria  de  Sousa  107  Ministry  of Construction  and  Water  
Maputo  Republic  of Mozambique  

SHELADIA  Associates  Inc.  


15825  Shady  Grove Road, Suite  100  
Rockville,  Maryland 20850  
USA  

JULY  1994  
Chimoio Water Supply Project 
FinalDesign Report 

TABLE  OF CONTENTS 

Page 

1. INTRODUCTION  I  

1.1.  Background  I  

1.2.  Project  Area  2  

1.3.  Climaiic Conditions  2  

1.4.  Project  Objectives  2  

1.5.  Report  Objectives  3  

1.6.  Report  Structure  3  

2. EXISTING  DATA  4  

2.1  Topographic  Maps  4  

2.2.  Topographic  Surveys and  Way­leaves  4  

2.3.  Soil  Surveys  4  

2.4.  Hydrology  Information  5  


2.4. 1. Storage  Capacity  of Chicamba  Lake  5  
2.4.2.  Design Levels of Chicamba  Lake  5  
2.4.3.  Historical Water Levels  in Chicamba  Lake  6  

3.  FIELD  SURVEY  7  

3.1.  Topographical  Survey  7  

3.2.  Soil Investigation  7  


3.2.1.  General  7  
3.2.2.  Soil Types  8  
3.2.3.  Test  Results  8  
3.2.3.1.  Sieve  analyses  8  
3.2.3.2.  Compaction  analyses  8  
3.2.4.  Implications of Soil Types  for Excavation  and Structures  9  
Chimoio Water Supply Project
FinalDesignReport 

4.COMPONENTS  OF THE PROJECT  10

4.1.   General  10

4.2.   Intake  Tower  10  


4.2.1.  Location and  intake  level   10  
4.2.2.  Civil work  brief description   11  
4.2.3.  Structural  calculation   11  
4.2.4.  Mechanical  equipment   12  
4.2.5.  Electrical  equipment   12  
4.2.6. Alarms   13  

4.3.   Access  Bridge  to the  Intake Tower  13  


4.3.1.  General   13  
4.3.2.  Method  of construction   14  
4.3.3.  Structural  calculation   14  
4.3.4.  Other ancillary   14  

4.4.   Transportable  Punp  14  


4.1.1.  General   14  
4.4.2.  Civil work   14  
4.4.3.  Electro  / mechanical  work   15  

4.5.   Guard  ­ Store  House  15  


4.5.!.  General  15  
4.5.2.  Civil  work   15  

4.6.   Intake  Site  and  Transformer  Tower  16  


4.6.1.  Ganeral   16  
4.6.2.  Intake  Site   16  
4.6.3.  Transformer  Tower   16  
4.6.3.1.  Structural  Calculation  16  
4.6.3.2.  Size  of transformer   16  

4.7.   At  ess  Road  16  


4.7.1.  General   16  
4.7.2.  Method  of Construction   17  
4.7.3.  Culverts   17  

ii 
Chimoio Water Supply Project 
FinalDesign Report 

4.8.  Pressure  Pipeline  17  


4.8. 1.General  17  
4.8.2.  Earthworks  17  
4.8.3.  Pipe  Laying  18  
4.8.4.  Concrete Works  18  
4.8.4. 1. Valve  Chamberr,  19  
4.8.4.2.  Anchor  Blocks  19  
4.8.4.3.  Marker  Posts  19  
4.8.5.  Valves  and  Accessories  19  
4.8.6.  Hydraulic  analyses  20  
4.8.6. 1. Water  Hammer  / Surge Pressure  20  
4.8.7.  Pipe Material­Steel  Pipes  22  
4.8.8.  Testing  of the Pipelines  22  
4.8.9.  Cleansing and  Disinfection  of the  Pipeline  22  

4.9.  Header Reservoir  23  


4.9.1. General  23  
4.9.2.  Civil  Work  23
4.9.3.  Structural  Calculation  23  
4.9.4. Electro­Mechanical  work  23  

4.10  Gravity Main  24  


4. 10.1. General  24  
4.10.2. Earthworks  24  
4.10.2. 1. River­Stream  Crossings  24  
4.10.3.  Pipe  Laying  24  
4.10.4.  Concrete  Works  24  
4.  10.5.  Valves  and  Accessories  24  
4.10.6.  Hydraulic  analyses  24  
4.10.6. 1. Water Hammer  / Surge Pressure  26  
4.10.7.  Pipe Material  ­ uPVC Pipes  and  Fittings  28  
4.10.8.  Testing of the  Pipelines  28  
4.109.  Cleansing and  Disinfection  of the  Pipelines  28  

5.  OPERATION  & MAINTENANCE  29  

5.1  Present  0  & M  Situation  29  

5.2.  0  & M  for Extended  system  29  

6.  CONSTRUCTION  PROGRAMME  AND  CASH  FLOW  31  

6.1.  Construction  Programe  31/1 

6.2.  Cash  Flow  31/2 


Chimoio Water Supply Project 
Final Design Report

7. CONFIDENTIAL  COST  ESTIMATE  32

7.1.  Summary  Cost  Estimate­Phase  II  36 

8.  LIAISON  37

9.  PROJECT RISKS AND  CONST  IAINTS  38  

9.1.  General  38  

9.2.  Major Risks  38  


9.2. 1. Delays to  Project Execution  38  
9.2.1.1.  Delay  in obtaining  finance  on time  38  
9.2.1.2.  Delay  in obtaining  land  acquisition  approval  38  
9.2.1.3.  Delay  due to  possible presence  of mines on the site  38  
9.2.2.  Unsustainabillity of the  installed system  39  

9.3.  Minor  Risks  39  


9.3.1.  Inability  to  construct  system components  as designed  39  
9.3.2.  Failure  of the  system  to  provide  required  capacity  39  

iv 
Chimoio Water Supply Project
Final Design Report

ABBREVIATIONS  

The following  general  abbreviations  are used  in  this  Report: 

F.D.R.  Final Design  Report 


USAID  United  States Agency  for Int,, national  Development 
AdC  Agua  d,­ Chimoio 
DNA  National  Directorate  of Water  Affairs 
DINAGECA  National  Directorate  for  Mapping 
SIER  Chimoio  Energy  Company 
DNEP  National  Directorate  for  Roads and  Bridges 
DPCA  Provincial  Directorate  for Construction  and  Water 
CPMZ  Companhia  do Pipeline  Mocambique­Zimbabwe 
masl  Metres  above  sea  level 
m  Metres 
m3 Cubic metres 
m3  Ih Cubic metres  per hour 
No.  Number 
Vs  Litres per second 
mm  Millimetres 
Chimoio Water Supply Project 
FinalDesign Report 

CHAPTER  1  

INTRODUCTIOY 
Chimoio Water Supply Project 
Final Design Report
1. INTRODUCTION 

1.1.  Background 

This  report  relates  to  Water  Sector  Study  (  Draft  Report,  Sept.  93  ) by  the 
Consultant  DHV  and  Feasibility  analysis  and  cost  estimate,  Pipe  line  from 
Chicamba  Dam  to Chimoio  ( Apr. 94  ) by  Consultant  Sheladia  Ass. 

The  city of Cumoio  is the  capital  of Manica  Province.  In  1993  the  Chimoio 
City Council  estimates the total  urban  / peri­urban  population at  about  190,000 
inhabitants. 

The  normal  source  of  raw  water  for  the  town  of Chimoio  is  the  Mezingaze 
river  where  water  is  pumped  out  of two  interconnected  reservoirs  to  a water 
treatment  plant  and  then  distributed  through  distribution  network.  The 
upstream  of  these  two  reservoirs  has  been  destroyed  in  a flash  flood.  The 
distribution network is not  a part  of this  F.D.R.  but  it is worth  mentioning  that 
about  30%  of total  water  pumped  in  distribution  network  is lost  due  to  the 
leakage's 'i  the  reticulation  pipes through the  City. 

Only 50%  of the  100,000 or  so  residents of the  urbanised  part  of Chimoio  are 


connected  to  the  water  distribution  network  of  "Agua  de  Chimoio".  The 
remainders,  and  some  of peri­urban  community,  are  served  by  public  taps  or 
more  often by a system  of individual  wells  unrelated  to  the urban  water  supply 
system. 

Due  to  the  drought  of  1990/1991,  the  Mezingaze  River  has  dried  with  hardly 
any real  storage  capacity  in  the  reservoir  This  situation is  nov,  repeated  every 
summer  and  AdC  must completely  cease  operating six months  a year. 

During  that  period  increasing pressure  has  been  placed  on  boreholes  wells  to 
support  the  entire  community.  Further  attempts  by  the  AdC  to  supply 
additional  water  through  drilled  wells  have  not  proved  satisfactorily.  Capacity 
of these  sources  is very  limited  and  in  no  way  can  be  considered  as  having 
potential to  supply the entire  City. 

This  drought  has  highlighted  very  clearly  the  extremely  low  security  and the 
insufficiency of the two  present  sources  of water  supply  (Mezingaze  River  and 
underground). 

In  response  to  this  emergency,  US  Agency  for  International  Development 
(USAID­Mozambique)  agreed  to  provide  finds  to  develop  and  construct  an 
alternative  source  of water  supply  which  would  better  safeguard  the  water 
supply  of Chimo'o.  The  adequate  source  of raw  water  has  been  found  in 
Chicamba  dam  reservoir located  41  km from  the City. 
Chimoio Water Supply Project 
FinalDesign Report 

1.2.  Project Area 

The  town  of Chimoio  is located  in the  Beira  corridor  which  contains  major 
infrastructures  such  as the  railway and  the  EN6  national  road  that  link the port 
of Beira  with Zimbabwe.  The  distance  between  Chimoio  and  the port  of Beira 
is approximately  200  km. 

The town  of Chimoio  lies  at an altitude  of between  630 and  710.  The treatment 


plant,  where  the  water  must  be  discharged  is located  in  the  lowest  part  of 
Chimoio at  635  m of altitude. 

The project  area  is situated  in the Province  of Manica  in  Central  Mozambique. 


The  installations  will  be  constructed  between  the  reservoir  of the  Chicamba 
dam,  where  the intake is located,  and  the existing  water  treatment  plant  located 
to the  north  of Chimoio. 

1.3.  Climatic  Conditions 

The minimum  and  maximum  monthly  average temperatures  are  18  C and  25  C 


respectively. Monthly average rainfall precipitations are: 

January  240 mm 
February  199 mm 
March  183  mn 
April  53  mm 
May  14 mm 
June  18 mnn 
July  13  mm 
August  15  mm 
September  12  mm 
October  36 mm 
November  120 mm 
December  218  mm 

1.4.  Project Objectives 

The objectives of the Consultancy Services  for phase I of the Project are: 

­ To develop  aconcept  for the supply  ofraw water  to the city of 


Chimoio 
­ To  prepare  afinal design for  the accepted  alternative 
­ To prepare and  issue the tender documents 
­ To prepare a tender evaluation and  give recommendation  to the client 


Chimoio Water Supply Project 
FinalDesignReport 

In  developing  the  raw  water  supply  concept,  alternative  sources  have  been 

studied and  the accepted  alternative issupply from  Chicamba  dam. 


1.5.   Report Objectives 

In particular the following engineering  details shall be  provided in this Report: 

­ General layout  ofthe  scheme showing  all main  components 

­ Longitudinal  sections of the pipeline 

­ Hydraulic  analysis of the pipeline 

­ Structural analysis  of the structures 

­ Plans and  sections  of important details  and the dimensions  of the 


major components  of the system  such  as intake tower, storage 
reservoir, small structures on the  pipeline, all  necessary electrical 
and  mechanical  equipment,  etc. 

1.6.   Report  Structure 

This report  issubmitted  in three  volumes,  9chapters  in Volume  I, Appendices 


in Volume II,and  drawings  in Volume IIl.  

Volume  I:  

Chapter  1.  Introduction  

Chapter  2.  Existing  data  

Chapter 3.  Field survey  

Chapter 4.  Components of the project 

Chapter  5.'  Operation & Maintenance 

Chapter  6.  Confidential  cost estimate 

Chapter  7.  Construction  programme  and  cash flow 

Chapter 8.  Liaison 

Chapter  9.  Project Risks  and  Constrains 


Chimoio Water Supply Project 
Final Design Report 

Tables  and  figures  in  this  Report  are  numbered  according  to  the  Chapter  in 
which  they  appear.  They  are  numbered  consecutively  according  to mention  hi 
the text. Environmental  and  baseline studies are  subjects  of separate  reports. 

4
Chimoio Water Supply Project 
FinalDesign Report

CHAPTER 2  

EXISTING  DATA 
Chimoio Water Suvply Project
Final Design Report

2.  EXISTING  DATA 

2.1  Topographic  Maps 

Three  principal  series  of topographic  maps  have  been  consulted.  These  are 
available  through  the  National  Directorate  of  Water  Affairs  (DNA),  the 
National  Directorate  for  Mapping  (Dinageca),  and  the  Chimoio  Energy 
Company  (SHER/EdM). 

1:50.000  (1958­1960),  sheets 837  and  838 


1:10.000  (1953),  Bacia  Hidrografica  do Revue 
1:10.000  (1980),  DNGC,  Chimoio 
The  1:10.000  maps cover  the  whole project  area,  except  for  one  section  along 

the  EN6  road of about  8 km. 

2.2.  Topographic  Surveys  and Way­leaves 

Both  the  National  Directorate  for Roads  and  Bridges  (DNEP)  in  Maputo  and 
the  Provincial  Directorate  for  Construction  and  Water  (DPCA)  in  Chimoio 
have  been  consulted.  Both  organisations  were  most  helpfiul.  However,  neither 
were  able  to provide  topographic  surveys of the EN6  between  Chimoio  and  the 
Messica  River  nor  of  the  road  from  the  EN6  and  the  Chicamba  Dam. 
Apparently  there  was  a  serious  fire  in the  technical  archives  of DNEP  some 
years  ago  which  destroyed  the  records. 

Services  should  be  at  least  15  metres  from  the  centre  line  of a  major  road. 
However,  permission  may  be  granted  for closer  passage  in  special  cases. 
Route  of the pipeline  is crossing  the  major  road  EN6  only  one  place,  therefore 
way­leave  is  required  only  for that  road  crossing. 

The  Companhia  do  Pipeline  Mocambique­Zimbabwe  (CPMZ),  were  also  most 


helpful.  They  have  provided  copies  of  topographic  survey  carried  out  in 
1964/65  along  the  pipeline  between  Chimoio  and  Messica  River.  The  way-
leave  of oil  pipeline  has  a  width  of 60  m.  CPMZ  have  indicated  that  it  is  not 
acceptable  to  install the water  pipeline  within  their way leave. 

2.3.  Soil  Surveys 

Relatively  little  information  about  soils  along  the  pipe  routes  has  been  found. 
The  CPMZ  topographic  surveys  carries  some  general  notes  about  surface  soil 
conditions.  Therefore  it  was  necessary  to  execute  the  soil  investigation  along 
the  pipe route. 


Chimoio Water Supply Project 
Final Design Report

2.4.   Hydrology  Information 

The  following  information  has  been  provided  by  the  Hydrology  Section  of 
SHER, Chimoio,  the operators  of Chicamba darn. 

2.4.1.  Storage Capacity  of Chicamba  Lake 

Chicamba  dam  has  storage capacity  for  full  turbine  operation  (50  cubic  metres 
per  second)  during  a  period  of three  years.  Water  availability  has  not  limited 
power  generation  since  the  dam  crest  was  increased  in  1973,  despite  two 
periods  of serious  drought.  The  water  consumption  of  Chimoio  is  less  than 
0,5% of the turbine  flow,  a  value  which  can be  considered  insignificant. 

The  long  term  plans  for  power  generation  in the  Manica/Sofala  region  include 
the  construction  of a  sub­station  on  the  Cahora  Bassa  power  line  to  provide 
power  to  the  region.  This  will  be  cheaper  than  up­grading  turbine  capacity  at 
Chicamba/Mavuzi  power  scheme.  There  is therefore  likely to  be  a  lower  water 
consumption  for  electricity  generation  in the  future  and  more  storage  capacity 
will  be available  to  secure the  water  supply for Chimoio. 

2.4.2.  Design  Levels of Chicambu  Lake 

Important  levels  (metres  above  sea  level,  masl)  relevant  for the  design  of the 
intake  tower are:  

Description  Level  (masl)  

Dam  crest  626  

Maximum  operational  level  625  

Flood  protection  level,  January  622  

Flood  protection  level,  February  620  

Designed  minimum  operational  level  590  

Actual  minimum operational  level  582  

Bottom  discharge  565  

River  bed  548  


Chimoio Water Supply Project 
FinalDesign Report 

2.4.3.  Historical Water Levels  in Chicamba  Lake 

The  observed  minimum  in  the  Chicamba  Lake since  the  dam  crest was  raised  in 
1973  are: 

Yeal  Level  (masl) 

1973/74  591 
1974/75  613  
1977/78  618  
1984/85  615  
1991/92  611  
1992/93  609  
1993/94  610  

A  study  has  been  carried  out  of  'e  probability  of the  occurrence  of low  water 
levels  in  the  Lake,  this  is  included  in  the  Environmental  Study  Report.  A 
resonable  design  level for the  intake  tower is  605msi. 


Chimoio Water Supply Project 
Final Design Report

CHAPTER 3 

FIELD  SURVEY 

7k  
Chimoio Water Supply Project 
FinalDesign Report 

3.  FIELD  SURVEY 

Field  survey  has  been  executed  for  the  various  aspects  of the  Project.  Due  to 
lack of topographic  and  sub­soil  information  both  investigation  were  executed. 
The  Baseline  study and  Environmental  study  are  subject  of separate  reports 

3.1.  Topographical  Survey 

The  route  of  the  transmission  pipeline  has  been  surveyed  to  establish 
longitudinal  sections  for  hydraulic  design.  The  levels  along  the  route  of  the 
pipeline  have  been  established  on  every  50  m,  and  along  river  and  stream 
crossings  every  5­10  m.  Site  surveying  on  the  locations  of  the  structures 
(reservoir,  intake  tower and  bridge  and  intake  site)  established  the  levels  on the 
grid  5 m  x  5 m. Concrete  bench  marks  are  established  every  500  m  along  the 
pipe  route  and  on  every  bend. 

The  surveying  carried  out  under  the  Project  is sufficient  for  detailed  design  to 
be prepared.  The total  quantities  of topographical  surveying  are: 

Longitudinal  section  levelling of transmission  pipeline  route  42  km 


Bush clearing  for  longitudinal  levelling  42  km 
Site  surveying (reservoir,  intake  site)  0,4 ha 
Bench mark  establishing  92 No. 

All  topographical  survey  work  has  been  plotted  and  is shown  on  the  drawings, 
either  as  longitudinal  section  (transmission  pipeline)  or  site  plans  (intake  site, 
reservoir). 

3.2.  Soil  Investigation 

3.2.1.  General 

The  sub­soil  conditions  for  transmission  pipeline  route  and  major  structures 
have  been investigated. 

For  the  transmission  pipeline,  sub­soil  conditions  have  been  investigated  at  a 
frequency  of roughly  500 m.  On  each  river,  stream  crossing  three trial  pits have 
been  investigated,  one in the  middle  and one  on the each  bank of the crossing. 

Seismic  investigation  has  been  done  on  the  intake  sites.  First  location  of the 
intake site  proved  difficult  for foundation  construction.  The  alternative  location 
proved  to be  suitable  for  required type of structure 

A  total of 86  trial  holes  have  been made,  with the  total  excavation  depth  of 172 
m. The  full  results of investigations  are available  in  Volume  II of this report. 


LnImoio  water auppiy rrojecl 
FinalDesign Report

3.2.2  Soil  Types 

The main soil  and ground  types  encounterLd  by  the investigation  are: 

­ Sand 

­ Silt 

­ Gravel 

­ Boulders 

-Gneiss 

The  majority  of  trial  holes  encountered  sand  with  varying  degrees  of 
intermixed gravel  and  gneiss. 

Rock outcrop  has been encountered  in only two  holes, there  will be  some  cases 


where  large  boulders  will  have  caused  refusal  and  where  such  a boulder  is 
classified as  rock. 

Standing  ground  water  has  been  encountered  in  all  the  holes  at  the  river 
crossings and some  of the stream  crossings. 

3.2.3.  Test Results 

3.2.3.1.  Sieve  analyses 

Sieve  analyses  were  carried  out  on  samples  taken  at  sites  for  structures,  and 
additionally, for selected  transmission pipeline route. 

The results  of the  sieve  analyses  show  acceptable  material  for backfilling  pipes 


and  structures.  Considering  the  presence  of ground  water  on  every  river 
crossing there  is a need  for  special  dewatering  equipment  during construction 
and  special protection  of the  pipes  along the river  and stream  crossings. 

3.2.3.2.  Compaction  analyses 

Compaction  analyses  indicate  a  general  suitability  of  all  materials  for 


compaction. 


Chimoio Water Supply Project 
FinalDesign Report 

3.2.4.  Implications of Soil Types  for Excavation  and Structures 

An  assessment  has  been  made  of  the  material  to  be  excavated  along  the 
transmission  pipeline  route  , based  on  the  analysis  of the  results  of the  trial 
holes. The material  to  be  excavated  has been classified  into: 

­ normally  excavatable  material  (soft material) 


­ hard  material,  rippable 
­ rock  requiring  blastirg 

Based  on  typical  trench  dimensions  of 600  mm  width,  and  1150  mn  to  2500 
mm  depth,  the  following  indicates  the  percentage  of each  type  of  material 
required to  be  excavated  for transmission  pipeline  and intake  site: 

Description  Soft  Hard  Rock 

Transmission  pipeline  89%  90/0  2% 

Intake  site  410%  31%  28% 

The  above  percentages  have  been  used  to  estimate  volumes  of  and  cost  16r, 
hard  material  and  rock  excavation.  However,  it  must  be  stressed  that  the 
frequency of test  holes  (every  500  m) prevents  an  accurate  assessment  and  the 
above percentages  will vary during  construction. 

10 
Chimoio Water Supply Project 
FinalDesign Report

CHAPTER  4 

COMPONENTS  OF THE PROJECT 

iOt* 
Chimoio Water Supply Project
FinalDesignReport 

4.COMPONENTS  OF THE PROJECT 

4.1.  General 

Raw water  will  be  pumped  from  C,'icamba  Lake  to  header  reservoir  on  the  hill 
overlcoking  the  Lake.  From  the  reservoir  the  water  will  be  transported  by 
gravity  to  the  treatment  plant  of  the  Water  Company  of  Chimoio.  In 
accordance  with  the  originul  Terms  of  Reference  the  rehabilitation  of the 
existing  treatment  plant  was  not  in  the  scope  of this  Project.  However  it  was 
agreed  that  if the  funds  are  available  the  rehabilitation  of  the  plant  will  take 
place pending  on the available  budget.  

The  following  components  are  forming  the  system  and  will  be built  under  this  
Project:  

­ Intake tower with  high lifting  pumps on  the Chicamba  Lake 

­ Access  bridge  to the intake  tower 

­ Transportable  pump,  which  will  be  used  when  the  water  level  in the 
Lake  falls  under  605  m 

­ Guard,  store  house  incorporating  office,  accommodation  facilities  and 


storage 

­ Fenced  Intake  site  incorporated  Guard,  store house,  transformer tower 


etc. 

­ Access  road 

­ Pressure pipeline  including  valves  and  fittings 

­ Header reservoir  of 100  m3  located  on the  hill  overlooking  the  Lake 

­ Gravity pipeline  including  valves and  fittings 

­ Radio  communication 

4.2.  Intake Tower 

4.2.1.  Location  and intake  level 

The  location  of the  intake  tower  has been  chosen  in  the  bay of the  Lake  about 
800m  from  the  dam  to  reduce  the  impact  of the  power  generation  and  waves. 
Also  it  has  been  considered  the  sub­soil  conditions  in  order  to  minimise  the 

11 
Chimoio Water SupplyProject
FinalDesignReport 

cost  of  foundation  for  the  tower.  Based  on  the  available  data  about  design 
levels  and  historical  water  levels  of Chicamba  Lake  the  intake  level  for  the 
tower has  been chosen to be 605  m. 

4.2.2.  Civil  wo:k  brief description 

The  dimensions  of the  tower  are  calculated  to accommodate  three  submersible 


pumps.  One duty  and  one stand­by are in  the scope  of this Project,  third one  is 
for  future extension.  The  height  of the  tower  from  the  bottom  of the  sump  to 
the  top ofthe  top slab  is 23.20 m. 

The  material  for construction of the  tower  will  be  reinforced  concrete  class 25 


with  high  tensile  bars  as  reinforcement.  Construction  of  the  tower  can  be 
executed  with sliding  formwork, depending on the  contractors equipment. 

As  a protection  of the  mechanical  and  electrical  equipment  a house  will  be 
constructed on the  top  ofthe  tower. 

Material  used  for  the  cunstruction  of the  house  will  be  230  mm.  bricks 
plastered inside. Roof sheeting will be corrugated  galvanised  iron sheets. 

Delivery  pipes will be  two  steel  pipes 300  mm  Diameter  encased  in  concrete  to 
prevent  floating of the pipes  . The  slope  of the  pipes  will  be  3% in  direction  of 
the  Lake  to  enable  back  washing  of the  pipes.  Back  washing  of the  delivery 
pipes  can  be  executed  whenever  the  water  level  in  the  lake  is lower  than 
maximum  level  in the  Lake by closing  the valves on the  delivery pipes,  pumping 
the  water  in  the  tower  using  a mobile  pump  and  opening  the  valves  on  the 
delivery  pipes.  Gate  valve  with  19  m mild  steel  spindle,  gear  box,  bevel  and 
hand  wheel  shall be  installed  on the delivery pipes  to  allow opening  and  closing 
from  the top slab. 

Minimum  flow through  two  300  mm  steel  pipes  is 450m3,.  Which is more  than 
adequate even  for future extension. 

Intake head  structure isdesigned  to allow required  quantity of water  in delivery 


pipes.  Material  will  be  concrete  class  15.  To  prevent  debris,  fishes  and 
crocodiles  from  entering  the  intake  tower  intake  head  structure  will  be 
equipped with  the grid 20  mm  bars at  100  mm  centres. 

4.2.3. Structural calculation 

Structural  calculation are enclosed  in Annex  No.  1 

12 
Chimoio Water Supply Project 
FinalDesign Report 

4.2.4.  Mechanical  equipment 

The  intake  tower  shall  be  equipped  with  two  submersible  pumps  (I  duty,  1 
stand­by). The  pumps  shall  be  with the  following characieristics: 

Q=lOOm'1h,  H=180m. 

Calculation of the pump

Required capacity  2000 m' / day = 100  m3  /h  (woridng  time 20  hours/day)  

level  difference: 

header  reservoir  764  m 

intake level  ­605  m 
159  m 

friction losses +  6.61  m  


(L=2050  m, 250 mm  dia steel  pipe)"  165.61  m  

The pumps were  chosen  KSB BPN  374/6+10A  733/2 

The  outlet  pipe  of each  pump  shall  be  provided  with  allnecessary  non­return 
and  isolating valve.  Pumps and  vertical  ID  250  mm  steel  double flanged  pipes 
3000 mm  long will be  supported  with 600  mm  plate welded  support on the top 
slab. 

The  intake tower  house  shall  be  equipped  with a hand  operated  hoist, working 


weight  2000  kg  to  permit  removal  of  equipment  from  the  tower. 
Transportation  of the equipment over the access  bridge  shall be by trolley. 

4.2.5.  Electrical  equipment 

The  intake  site  will be  electrically supplied  from  a distribution  sub  ­ station  to 
be constructed  by the  Electricity Company.  Electricity will be  available with the 
following characteristics: 

380 V ; 50 Hz; 315 KVA

Distribution board and motor control panel will be installed inside the house.
The  house  will  be  equipped  with  2  x  36  W  1200  mm  long  surface  mounted 
batten type  fluorescent luminaires  with  single metal  reflector. 

13 
Chimoio Water Supply Project 
FinalDesign Report 

The  lightning  protection  system  will  be  installed  with  4  earth  electrodes  to 
protect the  equipment  from  lightning. 

Level  switches  shall  be  provided  in  the  intake  tower  and  header  reservoir  for 
the  following  functions: 

i)  Water protection against  dry running  of pumps­intake  tower 

ii) High  level  cut­out­header  reservoir 

iii)Low  level  cut­in­header  reservoir 

Level  switches  shall  be floating  mercury  switches, enclosed  in  watertight  plastic 


casing,  FLYGT  Type  ENH­10.  The  switches  shall  be  freely  suspended  and 
adjustable  to  the  required  level. 

A  pressure  switch  shall  be  installed  on  the  discharge  manifold  to  provide  cut-
out  of the  pumps.  The  pressure  switch  shall  be  adjustable  and  shall  be  set,  on 
commissioning,  at  the  field  established  "closed  valve"  pressure  for  the  pump 
sets. 

4.2.6.  Alarms 

The following  visual and  audible alarms  shall be  provided: 

­ Electricity  supply­mains  failure  ( battery operated) 

­ Header  reservoir­overflow 

­ Operation  of any electrical  protective  device  or safety  cut­out 

­ Failure of any duty motor 

Visual  indication  of alarms  shall  be  located  on  the  appropriate  switchboard  or 
instrument  panel.  Audible  indication  of  alarms  shall  be  located  both  in  the 
Intake  Tower  and  in  the  Office  of the  Guard­store  house.  A  siren  shall  also  be 
installed  on the outside of transformer  tower. 

4.3.  Access  Bridge to the  Intake Tower 

4.3.1.  General 

Access  bridge  shall be  constructed  as  a  link  between  intake  site  and  the  tower. 
Material  shall  be  reinforced  concrete  class  40.  Reinforcement  shall  be  high 
tensile reinforcement  bars. 

14 
Chimoio Water Supply Project
Final Design Report

4.3.2.  Method  of construction 

First,  the  I1  183  n embankment  shall be  constructed  using excavated  rock. On 


the  embankment  shall  bc  placed  precast  concrete  deck.  Reinforced  concrete 
upstand  restraint  shall  be  constructed  after  next  11. 183  m.  Upstand  restraint 
shall  be  based  on  natural  stone masonry  pier with  class  20  concrete  core.  Next 
precast  concrete  deck  shall  be  placed  between  embankment  and  a  pier.  Third 
precast  concrete  deck  shall  be  placed  between  the  pier  and  tower.  After  the 
precast  deck  is  placed  in  the  position  and  to  required  level  reinforced  concrete 
bridge  deck  shall  be  cast  insitu.  Every  11  Im movement  joints  shall  be 
constructed  using  Malthold  DPC. 

4.3.3. Structural calculation 

Structural  calculation  are  enclosed  in Annex No.  2. 

4.3.4.  Other ancillary 

Steel  pipes  I) 250  mm  length  4000  mm  internally  lined  and  externally 
protected  shall be placed  on  the  bridge  fixed to  bridge  deck  using  brackets  and 
support  brackets. 

Electrical  cables  shall  be  fixed  to a bridge beam  on the galvanised  cable tray. 

Metal  fence  shall  be  constructed  700  mm  high  using  20  mm  Dia.  bars  at  125 
mm  central.  The handrail  shall  be  protected  with  thermoplastic cover. 

4.4.  Transportable  Pump 

4.4.1.  General 

The  water  in  the  Chicamba  Lake  might  fall  below  the  elevation  605  m  which 
corresponds  to  the  inlet  of the  intake  tower.  It  might  eventually  reach  585  m,
the  minimum  level  of operation  of the hydro­electric plant. 

4.4.2.  Civil work 

The  reinforced  ramp,  on  which  the  pump  shall  be  transported  will  be 
constructed  from  the  store  room  to  the  existing  ,,'ater  level  in  the  Lake  while 
the  execution  of the  Project  is  going  on.  Any  extension  of the  ramp  will  be 
constructed  separately  from  this  Project  according  to  necessity  and  when  the 
water falls  below  this level. 

4.4.3. Electro  /mechanical  work 

15 
Chimoio Water Supply Project
FinalDesign Report 

The  pump  shall  be  mounted  on  the  non  roadworthy  trailer.  The  pump  shall  be 

following  characteristics: 

Q=110m3 /h,  H=30m 

The  pump has  been  chosen KSR  ELK/ELB  40. 

Flexible  reinforced  rubber  pipes  100  mm  Dia  shall  be  connected  to  the  pump. 
The  pump  shall  pump  the  water  from  the Lake  to  the  tower  sump  during  low 
water  levels  in  the  Lake.  To  enable  operation  of the  pump  a  hand­winch  with 
the  stainless  steel  cable shall  be  mounted  in  the store room. 

4.5.  Guard  ­ Store  House 

4.5.1.  General 

The  Guard,  store house  shall  include the following  facilities: 

­ I  office 
­ 2 bedrooms  with  the  lounge  for the  guards off duty 
­ I sl.,wer  and toilet 
­ I storage room  for the transportable  pump and  pipes 

The house  shall  be furnished  with the  hard  furniture  as follows: 

­ Metallic  cushioned  armed chair  No. 2 


­ Metallic  office  desk  No.  I 
­ 4 tier steel  file cabinet  No.  I 
­ 3 seater  wooden  settee with foamed  cushions  No.  I 
­ Metallic  single bed  with  foam  mattress  No.  2 
­ Storage  cupboard  No.  2 
­ Kitchen  table with  4  chairs  No.  1 
­ Storage  cupboard ( lounge)  No.  1 
­ Key  storage  No.  1 

4.5.2.  Civil  work 

Material  shall  be  brickwork  plastered  both  sides.  Roof shall  be  galvanised  iron 
sheeting.  Sanitary  waste  from the toilet  and  shower shall  be  disposed  in  a  septic 
tank  and  soakaway.  Water  supply  for  the  house  shall  be  connected  to  the 
Chicamba  Township  water  main which  crosses the  intake site  access road. 

Sanitary  wastes  from  the  bathroom  shall  be  disposed  in  a  septic  tank  which  is 
connected  to  a  soakaway. 

16 
Chimoio Water Supply Project 
FinalDesign Report

4.6.  Intake Site and Transformer Tower 

4.6.1.  General 

In order to provide efficient operation of the intake  tower  as well  as security of 


the equipment,  an  intake site shall be built  at the  entrance of the bridge. 

4.6.2.  Intake Site 

Intake  site  shall  consist  of Guard­store  house,  transformer  tower,  sufficient 


turning  area  for  the  truck  in  case  of  any  operational  or  maintenance 
requirements. 

The  level of the  intake  site  shall  be 625.20m.  To  prevent  soil  erosion  due  to 
wave  activity the edge  of the site shall be protected  with 500 mm  free drainage 
rockfill.  The  wire fence  1800 mm  high  shall be  built around  the  site because of 
security  reasons.  The  erosion  of the  slope  (if it  isnot  rock)  shall be  protected 
with adequate vegetation. 

4.6.3. Transformer Tower 

To  provide the  adequate  power  supply  transformer  tower  shall be  built  as per 
requirements  of EdM/SHER. 

4.6.3.1.  Structural  Calculation 

Structural calculation are enclosed  in Annex No 3. 

4.6.3.2.  Size of transformer 

The  size  of transformer  has  been  calculated  for  the  worst  loading  case.  The 
adequate transformer  shall be 315KVA. 

Detailed  calculation of loading are  enclosed in  Annex No 4. 

4.7.  Access Road 

4.7.1.  General 

Access  road  shall  be  constructed  from  existing  road  to  Chicamba  Dam  to 
Intake site. Total length shall be  1850 m. 

17
Chimoio  Water Supply Project 
FinalDesign Report

4.7.2.  Method  of Construction 

The  route  of the  road  shall  follow  the  existing  dirt  track  to  the  "restaurante",  
after  that  it  shall  follow  a  direct  path  to  the  intake  site.  The  potholes  on  the  
existing  dirt track  shall  be  filled  with  adequate  material  and compacted  to  93%  
MOD  AASITO.  Material  for  wearing  course  shall  be  selected  gravel  
compacted  to  95%  MOD  AASHTO.  
To  prevent  erosion  of the  road  on  the  edge  of  the  road  shall  be  placed  free  
drainage  rockfill  60­250  mm  compacted  to  95%  MOD  AASHTO.  Drainage  
channels  100  nm  deep  shall  protect  the  road  from  water  flow  on  the  slopes.  
Ground  slopes  shall be protected  from  erosion  uy vegetation.  

4.7.3.  Culverts 

Water  from  the  slopes  shall  be  controlled  by  4  culverts  which  shall  be 
constructed  on every  stream,  crossing  the  road.  Culverts  shall be class  S  culvert 
pipes  with  100  mam.  bed  and  haunch  placed  below  subgrade  layer  with  1:100 
fall. 

4.8.  Pressure  Pipeline 

4.8.1.  General 

First  2153  m  of the  transmission  main  from  the  intake  to  the  header  reservoir 
shall be  steel  pipes  longitudinal  welded,  internally  lined,  externally  coated,  6  m 
length,  working pressure 22  bars. 

4.8.2.  Earthworks 

The  pipes  shall  be  laid  in  the  trenches  600  mm  wide,  with  the  minimum  cover 
of  800 mm  above  the top  of the pipe.  When  crossing the streams,  including the 
portion  of the  pipe  which  is  going  to  be  laid  under  the  maximum  level  of the 
Lake,  the  invert  level  shall  be  2.0  m  deep.  Below  the  invert  of the  pipe  100 
mm  of  sand  shall  be  placed.  First  200  mm  above  the  pipe  shall  be  sand  or 
screened  granular  material  compacted  to  88%  MOD  AASHTO. 
The  reminder  of  trenches  shall  be  backfilled  with  selected  granular  material 
compacted  to  96%  MOD  AASIITO.  Excavation  shall  be  protected  with  all 
necessary  planking and  strutting to  ensure  the safety  of workmen. 

Material  to  be  excavated  shall  be  divided  into  three  classes,  Rock,  Hard 
Material  and Soft Material. 

Rock shall  be defined  as: 

(i)  Solid  undecomposed  boulders exceeding  0. 10 cubic  metres; or 

18 
Chimoio Water Supply Project 
FinalDesign Report 

(ii)  Solid unweathered  crystalline material  in bulk or in banks or ledges, 


which  can  ,ot be  broken  up or removed  except  by  the use of 
explosives. 

Hard  Material  shall  be defined  as: 

Material,  not rock, which  requires  the use  of pneumatic tools,  mechanical 


breakers, or special  cutting tools to mechanical  excavators for its practical 
removal. 

Excavation  for  concrete structures  such  as  inspection  chambers  and  for thrust 


and  anchor  blocks  shall  be  to  required  depth  and  as  near  as  possible  to  the 
external  dimensions  of the structure. 

The  excavation  must  be  free  of water  at  any  time  during  the  pipe  laying  and 
construction of concrete  structures. 

Marker  tape  shall  be  placed  300  mm  above  the  pipeline.  The  material  for 
Marker tape shall be  blue PVC  or  polyethylene mesh  or ribbon  at  least  50 mm 
wide,  incorporating  a corrosion resistant  tracing system. 

4.8.3.  Pipe Laying 

Laying  instruction  of the  manufacturer  shall  be  explicitly  followed.  All  pipes 
shall be sound  and clean before laying. When  laying  .j  not in  progress the  open 
ends of the  pipes  shall be  closed by  water tight  plugs  or other  approved  means. 
Good alignment  shall be preserved  in laying. 

4.8.4. Concrete  Works 

All  coicrete  and  reinforced  concrete  works  shall  comply  wit  the  following 
standard  specification as appropriate: 

BS  8110  The structural  use of concrete 


BS  8007  Code  of practice for  "Design of concrete structures  for retaining 
aqueous  liquids  
BS  12  Ordinary Portland cement  
BS  882  Aggregates for concrete  
BS  812  Water absorption of aggregate  
BS  3148  Water for washing  aggregates  
BS  ­rj75 Admixtures  of concrete  
BS  1881  Strength test  ofconcrete  
BS  4449  Carbon  steel bars  
BS  4482  Cold  reduced  steel wires  
BS  4483  Steel fabric  
BS  1052  Finally  annealed mild  steel wire  

19 
Chimoio Water Supply Project 
Final Design Report 

BS 4466  Cutting  and  bending of reinforcement 


BS  8100  Tolerances of placement  of reinforcement 
BS  8110  The  minimum  concrete cover of reinforcement 
BS 2499  Hot  poured joint sealants 
BS  5212  Cold  poured  polymer­based  joint  sealant 
BS 4254  Two­part  polysilphide­based  sealants 
BS 5889  Silicone based  building  sealants 
BS  903  Rubber  waterstops 

4.8.4.1.  Valve  Chambers 

Washout  chamber's  and  air  valve  chambers  shall  be  placed  as  per  longitudinal 
sections.  The  exack  position  shall  be  indicated  on  site.  All  concrete  chambers 
shall  be  painted  outi;de  with  two  layers  of  bitumen.  All  chambers  shall  be 
lockable. 

4.8.4.2.  Anchor  Blocks 

Anchor,  thrust  blocks  shall  be  placed  on  all  the  bends  and  at  the  slopes  as 
follows: 

gradient spacing ( m) 

up to  I in  2  6 
from  1:2 to  1:4 12 
from  l:4to 1:5 18 
from  1:5 to  1:6 24 
flatter  than  1:6  not required 

4.8.4.3.  Marker Posts 

Marker  posts  shall  be  made  of precast  reinforced  concrete  and  placed  1.0  m 
from  central  line  of  pipes.  They  shall  be  positioned  on  every  bend  of the 
pipeline,  on  the straight  portion  every  500  m. 

4.8.5.  Valves  and  Accessories 

All  valves  and  accessories  are  designed  for  a  pressure  at  least  equal  to  two 
times  the  normal  working  pressure  where  they  will  be  installed.  As  far  as 
possible  all  equipment  of  the  same  type  shall  be  from  one  manufacturer  and 
they  must  be  clearly  marked  with  the  name  of manufacturer,  flow  direction 
arrows  and  the  pressure  for  which  they  are  designed.  All  valves  shall  be 
manually  operated  and  open left  ( counter  clockwise). 

20 
Chimoho Water Supply Project 
Final Design Report 

4.8.6. Hydraulic analyses 

Hydraulic  calculations  of friction  losses  for  the  steel  pipe  have  been  calculated 
based  on Hazen­Williams  formula as  follows: 

4, 7
J=  10,708  x(Q  LIS2XD­

Where:   J  =  Friction losses  (m)  


Q = Flow (/s)
C  =  140 (Hazen­Williams  coefficient)  
D  =  Pipe diameter  (mm)  

For the Q  =  2000  m'/d ay; D  =


250  mm and  C  =  140  = 

J  =  6,61  m 

Water  hammer  /  surge  pressure  is  the  crucial  factor  in  the  design  of  this 
pressure  pipeline,  therefore  the  calculations  are  given below  inclusive  of water 
hammer / surge  pressure. 

4.8.6.1.  Water  Hammer / Surge  Pressure 

This  phenomenon  occurs  frequently  in  pressure  pipelines  and  is  defined  as  the 
periodic  pressure  oscillation  which  move  back  and  forth  along  a  pipeline.  The 
phenomenon  occurs  when  closing  and  opening  valves,  starting  and  stopping 
pumps or when any  other operating condition  changes in the pipeline. 

The example  of calculation  of water  hammer  /  surge  pressure  is  shown  below. 


The  determining  factor  of  the  size  of water  hammer  /  surge  pressure  is  the 
speed  with  which  the  pressure  wave  travels  along  the  pipeline.  The  following 
formula  has been  used: 
Cp=Cwx 1 
1+I Ew  dm 
(Ep  I/ 

Where  Cp  =  Wave  celerity  (m/s) 


Cw  =  Wave  celerity in  a column of water (1425  m/s) 
Ew  =  Elasticity  modus of water  (2070  N/mm 2  ) 
Ep  =  Elasticity  modus of pipe  material (N/mm)  uPVC  Ep =  3000; 
Steel  Ep  =  210000 
dm  =  mean diameter of pipeline  which  is equal  to  internal  pipe 
diameter  di  plus pipe  wall thickness  t ( dm=di+t) 
t  =  Pipe  wall  thickness  ( mm) 

21 
Chimoio Water Supply Project 
FinalDesign Report 

The  size  of pressure  oscillation  after  a  valve  closure  depends  on  the  time  it 
takes  to  close  the  valve,  and  on the  so  called  reflection  time  of the  pipeline.  If 
the  flow  is  cut  during  a  period  shorter  than  this  reflection  time  the 
maximum  pressure  increase  may be  calculated  by  use of the  following  formula: 

H  =  Cp  xx

Where:H  = Maximum  pressure increase  (+) or decrease  (­)  (mhw)  


Cp  =  Wave celerity  as calculated  by use  ofthe  above  formula  (m/s)  
g  =  Acceleration  of gravity (;­ 9,81  m/s')  
Vo  =  Flow velocity just  before valve  closure  (m/s)  

The  reflection  time is calculated  as follows: 

To  2L
Cp 

Where: To  =  Reflection  time (s) 


L  =  Length of pipeline (m) 
Cp  =  Wave  celerity (m/s) 

In  the  case  of having  a  longer valve  closing  time than  the  reflection  time  of 
the  pipeline,  the  pressure  increase  is  lower  than  the  calculated  in  the  above 
formula. 

Calculation  of water hammer / surge  pressure: 

Steel  pipe ID  250  mm  Wall  thickness  4,8  mm;  Q  = 27,78  Vs; 
Vo  = 0,7  ­Js; Static  head  = 159  m;  Friction losses = 6,61  m; 
Length  L  = 2050 m  => 

Cp  =  1027,26  m/s  


H  =  73,30 m (mhw)  
To  =  4,00s  

Ah  =  159 + 6,61  +  73,30 


Ah = 238,91  m 

In order to  avoid  installation  of  some  form  of water  hammer  protective  device 
to  reduce  pressure,  because  of high  operational  and  maintenance  cost,  steel 
pipe  is  accepted.  The  reflection  time  is  very  short  therefore  the  pressure 
increase  should be  lower  than calculated  in  the above  formula. 

22 
Chimoio Water Supply Project 
FinalDesign Report

4.8.7.  Pipe  Material­Steel  Pipes 

Due  to high  risk  of water  hammer  and  to  avoid  installation  of  water  hammer 
protective  device  to  reduce  pressure,  the  material  for  pressure  main  has  been 
designed  to  be  GRW  longitudinal  welded  pipe  to  SABS  719  Gr.  B.  250  mm 
internal  diameter, wall  thickness  of 4.8  mm. 

The  main  concern  regarding  the  use  of steel  pipe  is  corrosion.  The  long 
continuous  lengths  of  welded  steel  pipelines  increase  the  opportunities  for 
corrosion  to  develop.  Welded  joints  are  a  potential  source  of  increased 
corrosion  risk  due  to  difficulty  in applying  protection  after  welding.  Corrosion 
of  steel  pipelines  does  not  generally  cause  catastrophic  failure,  rather  a 
progressively  increasing  loss of water  through  leakage. 

To  protect  steel  pipe  from corrosion  pipes  shall  be internally  lined  with  smooth, 
dense,  centrifugally  spun  cement  mortar  lining.  External  corrosion  protection 
shall  be  with fusion  bonded  low  density  polyethylene  in  thicknesses  from 2.0  to 
3.0  mm  or  similar approved  by  the Engineer on  Site. 

4.8.8.  Testing  of (he  Pipelines 

The  pressure  in  the  pipeline  shall  be raised  steadily  until a  pressure  of 1,5  times 
the  operating  pressure  is reached  in  the  lowest  part  of the  section,  and  the 
pressure  shall  be  maintained  at  this level  for  a  period  of one  hour.  The  pumps 
shall  than  be  disconnected  and  no  fuither  water  shall  be  permitted  to enter  the 
pipeline  for the  further  period  of one  hour. At  the end  of this  period  the  original 
pressure  shall  be  restored by  pumping  and  the loss  measured. 

The  permissible  loss  in  all  welded  steel  pipeline  shall  not  exceed  0.1  litres  per 
mm  of pipe  diameter  per kilometre  of pipe  per  24  hours  for each  30  m  of test 
head.  In  uPVC  pipe  the  permissible  loss  shall  not  exceed  2.0  litres  per  metre 
nominal  bore  per  kilometre  length  per  metre  head  ( calculated  as  the  average 
head  applied  to  the section  ) per 24  hours. 

4.8.9.  Cleansing  and  Disinfection  of the Pipeline 

At  the  conclusion  of  pipelaying  flushing  out  of the pipeline  shall  be  executed. 
Disinfection  of  the  pipeline  shall  be  carried  out  using  chlorinated  raw  water 
from Chicamba  Lake.  Residual  of not  less  than 20  mg/l of free  chlorine  shall  be 
acceptable  for  the structures.  For  the pipeline  a residual  of at least  20  mg/I  for  a 
period  of 2  hours  shall  be acceptable. 

23 
Chimoio Water Supply Project 
FinalDesign Report 

4.9  Header Reservoir 

4.9. 1. General 

The  header  reservoir  will  be  located  on  the  hill  overlooking  the  Chichamba 
Lake  at  the  elevation  762  m.  The  head  will  be  enough  to  carry  the  water  by 
gravity  to  the  treatment  plant  of  Chimoio.  It  is  not  going  to  be  a  storage 
3
reservoir  only a pressure  break tank,  therefore  the  capacity  will  be  100  m . 

The  primary  function  of  this  reservoir  is  to  protect  the  gravity  main  from 
overpressure  by  breaking  the  head  created  by  the  submersible  pumps  in  the 
Intake  Tower.  This  head  depends  on  the  water  level  in  the  Chicamba  Lake, 
which  can vary  by  20 m. The  secondary  function  of the  reservoir  is  to protect 
the gravity  main  from  water  hammer  caused by  intake  pumps and  to  reduce  the 
effect  of water  hammer  at the pressure  main. 

4.9.2.  Civil  Work 

The reservoir  shall  be  built  in  the  ground  1.0  m  below  original ground  level.  At 
the  bottom  level  of the  reservoir  sludge  disposal  pipe  with  the  valve  shall  be 
installed.  Raw  water  has  been  taken  from  the  Lake  so  settlement  already  took 
place.  The  quantity  of sludge  will  be  minor.  Sludge  shall  be  disposed  in the 
channel  filled  with  free  drainage  rockfill  to  allow  soaking  of the  sludge  in the 
ground. 

On  the  top  slab  three  ventilation  pipes  shall  be  installed  and  entrance  for 
maintenance  of the  reservoir.  Entrance  shall  be  covered  with  cast  iron  manhole 
lockable  cover. 

To  prevent unauthorised  entry  in the reservoir  area  it shall  be fenced  with  1.8  m 


high  wire  mesh  fence  with  lockable  gates.  Access  road  to  the  reservoir  area 
shall be  constructed  as a dirt  track  3.0  m  wide. 

4.9.3. Structural  Calculation 

Structural  calculation  are  enclosed  in Annex  No. 5. 

4.9.4.  Electro­Mechanical  work 

Level  switches  shall  be  installed  in  the  reservoir  to  control  the  intake  pumps. 
Item 4.2.4.  refers. The  outlet  pipe  shall  be  equipped  with the gate valve  in  case 
of maintenance  of the gravity  main. 

24 
Chimoio Water Supply Project 
FinalDesign Report 

4.10  Gravity Main 

4.10.1.  General 

The  pipeline  between  header  reservoir  and  the  treatment  plant  will  be 
constructed  in 200  mm  and  250  mm  diameter  unplasticized  PVC  pipe  in  class 
6,9,12,16  and 20  according  to hydraulic gradient  and  altitude. 

4.10.2.  Earthworks  

Item 4.8.2.  is  applicable.  

4.10.2.1.  River­Stream  Crossings 

The  banks  of all  the  river­stream  crossings  shall  be  protected  with wire  mesh 
gabions  400  mm  thick.  The  pipes  crossing  the  rivers  and  streams  shall  be 
encased  in concrete  to prevent  possible erosion  during  rainy season. 

4.10.3. Pipe  Laying  

Item  4.8.3.  is  applicable.  

4.10.4.  Concrete  Works  

Item  4.8.4.  is applicable  

4.10.5. Valves  and Accessories  

Item  4.8.5.  is  applicable.  

4.10.6. Hydraulic  analyses 

Hydraulic  calculation  are  based  on  the  formula  first  developed  by  Blasius  for 
smooth pipes,  based  on  the  premise  that  for smooth  pipes  the  friction  factor  is 
solely dependent  on the Reynolds  number.  The formula is  as follows: 

p   158.2  L  V, 


Re  D 

Where   P  =  Pressure  loss in  pascals  (Pa)  per  metre  of pipe  


Re =  Reynolds  number  
L  =  Pipe length in metres (m)  
D  =  Pipe diameter  in  metres (m)  
V  =  Velocity  of flow in  metres per second  (m/s)  

25 
Chimoio Water Supply Project 
Final Design Report

Vxd
Re=-
q18 

Where   Re  =  Reynolds number 


V  =  Velocity of flow  in metres per  second  (m/s) 
d  =  Inside  pipe  diameter (mm) 
7l 8 =  Kinematics  fluid  viscosity (m2  / s) 

From  the  flow  chart  which  is  based  on  the  above  mentioned  formula  friction 
losses  for  different  classes  of pipes  for  the  required  flow  Q=27,78  Vs  are  as 
follows: 

pipe  diameter  classof the  pipe  friction  losses 


(ram)  (m/100m) 
250  6  0,15 
250  9  0,17 
250  12  0,19 
250  16  0,24 
250  20  0,32 
200  9  0,46 
200  _12  0,50 

The highest  point  ( level  691.99  m ) on  the  gravity  main  is  at  km  28.675  from 
the  header  reservoir.  In the  table  below  is shown  the friction  losses  from  the 
reservoir  to  that  critical  point  on  the  entire gravity  main.  When  considering  the 
classes  of the  pipes  in  addition  to  the  level  difference  between  high  and  low 
points on  the  pipeline  the  possible  water  hammer  is taken  into  account. 

pipe  class  of  the  length  friction  total  friction 


diameter  pipe  (M)  losses  losses (m) 
(MM)  (m/lOOm) 
250  6  2678  0,15  4,05 
250  9  5697  0,17  9,69 
250  12  10500  0,19  19,95 
250  16  9200  0,24  22,08 
250  20  600  0,32  1,92 
total  friction  57,69 
losses  (m) 
decrease  of  2.88 
characteristi 
cs  with  age 
+ 5% 
TOTAL  60,57 

26 
Chinoio Water Supply Project 
Final Design Report

of the  header  reservoir: 


of  the  required level 
Calculation 
on  the  pipeline  691,99  m
Level  of the highest  point 
752,56 m 
Total  friction  losses, 
pipeline,  the
water  supply,  in case of  some  minor  lekageS  of  the 
To  secure 
minimeur  water  level  in  the  reservoi 
shall  be 761,80  m.  
inimum  ater levl  he resr tthe  inlet  at  the  treatment  plant  3050  m  of the 
mm  diameter.  The  pressure
be  200  ridioethe u re
reduct pressure  at  plant  shall  be 2'
in  order  to  the  treatment  of the  
gravity  main before pipeline  shall  be  41,91  in. Depending  on  the  quality 
at  the  inlet 
existing  of  the  at  the  treatment 
reservoir  plant  it  might  be  necessay  to  construct
pressure  break  chamber  before  inlet  to  the  existing  reservoir.  During  the
necessry  investigation  of  the  existing  reservoir 
construction  of  the  project 
should  be  executed. 

4.10.6.1.  Water  Hammer  /Surge  Pressure 


pipelines 
in pressure and  and  is defined 
a  pipeline.  the 
as The 
This  phenomenon  occurs  frequently moveback  forth  along 
peiodic  pressure  oscillation  which 
closing  and  opening  valves,  starting  and  stopping
phenomenon  occurs  when operating  condition  changes  in the  pipeline. 
pumps  or  when  any  other 
due  to  level 
through  the  pipeline  by  gravity 
The  example  of 
is transported 
dn  will  be  under  pressure. 
Although  the  water  below  for  the  biggest 
cicull  nc  water  h morlsurgO  prelsure  is  show  factor 
The  determining 
on  the  gravity  main  between  two  points.  speed  with  which  the 
level  difference  /  surge  pressure  is  the  used: 
of  the  size  of  water  hammer  pipeline.  The  following  formula  has  been 
along  the 
pressure  wave  travels 
Cp=CWX 

= Wave  celerity  (m/s)


Where  Cp  n/s) 
Cw  Wave  celerity  in a column  ofwater  (1425  2  ) 
Ew  = Elasticity  modus  ofwater  (2070  N/mm
material  ( N mm  ) uPVC  Ep  3000; 
I 2
Ep  = Elasticity = modus  of pipe 
Steel  Ep  210000 
which  is equal  to  internal  pipe 
dm=  mean  diameter  of pipeline thickness  t (dm  = di+t) 
diameter  di  plus  pipe  wall 
t  Pipe wall thickness  ( mm ) on  the  time  it 
of  pressure  oscillation  after  a valve  closure  depends  the  pipeline.  If 
The  size  time  of 
and  on  the  so  called  reflection 
takes  to  close  the  valve, 

27 
Chimoio Water Supply Project 
Final Design Report 

than  this   reflection  time  the 


the  flow  is  cut  during  a  period   shorter 
by use  of the  following formula:  
maximum  pressure  increase  may  be  calculated 
Vo 
(±)Cp x 
­g

=  Maximum  pressure  increase  (+) or  decrease  (­)  (mhw)


Where:  H 
ofthe  above  formula  (m/s) 
Cp =  Wave  celerity as calculated  by use 
closure  (m/s) 
Vo  =  Flow  velocity  just before  valve 
mis 2) 
g  =  Acceleration  ofgravity  (=  9,81 

The  reflection  time  is  calculated  as  follows:


2L
2
To  =
Cp 

Where:To  =  Reflection  time  (s)  


L  =  Length  of pipeline  (m)  
Cp =  Wave  celerity  (m/s)  
of 
closing time  than  the  reflection  time 
In the  case  of having  a longer valve  the  above 
lower  than  the  calculated  in 
the  pipeline,  the  pressure  increase  is 
formula. 

Calculation  of water  hammer/surge  pressure:  


=  27,78  /s  ; Vo  =  0.6 mis; 
PVC  250  mm  class  16 (assumption);  Q 
96 m;
Static  head  =  182,25  m; Friction  losses  = 32, 
=  7 3 50m 
Length  L  1

Cp  = 433,52  m/s  


H  =   26,51  m(mhw) 
To  =  80,04s 

Ah  =  182,25  ­ 32,96  + 26,51 


Ah = 175,8  m 

of a  high  pressure.  Due  to  very 


PVC  class  20 is  accepted  for that  area 
pressure  increase  at  the  critical 
long  distance  between  two  points  the 
sufficient,  but  because  it is  a 
point  will be  lower  even  class  16  will  be 
the  river  crossing   class  20  is 
short  section  of  the  pipeline  and  in 
designed. 
Fittings
4.10.7.  Pipe  Material  ­ uPVC  Pipes  and 
it  to  be  used  instead  of  steel,  cast  iron 
The  properties  of  uPVC  pipes  allow 
highest  stiffness  per  unit  cost  of  the 
asbestos  cement,  etc.  pipes.  It  has  the 

28 
Chimoio Water Supply  Project 
FinalDesignReport 

engineering  plastics  and  is  therefore  most  commonly  used  in  load  bearing 
applications  such  as  pressure  pipes.  !. has  other  features  such  as:  low  specific 
gravity,  good  chemical  and weather  resistance,  very smooth  bores  and  the long 
term  flow  characteristics  vary very little  from  those of newly  laid  pipes. 

Unplasticized  polyvinyl  chloride  (uPVC)  pressure pipes, joints and  fittings  shall 


comply with  relevant  provisions  of standards as  set out below: 

uPVC pipes:  BS  3505 


uPVC joints and  fittings:  BS  4346 
uPVC  solvent  cements:  BS  4346 

Storage  of pipes  must  be  executed  strictly  in  accordance  with  manufacturer 
recommendation.  It  is  essential  that  pipes  are  stacked  with  the  socket  and 
spigot  ends  alternating  and  with the  sockets  projecting  so  that there  is  a  barrel 
to  barrel  contact  along  the  lengths  of pipe.  During  storage  all  pipes  must  be 
protected  from  ultraviolet  light. 

4.10.8.  Testing  of the  Pipelines 

Item  4.8.8.  is  applicable. 

4.10.9. Cleansing  and  Disinfection  of the Pipelines 

Item  4.8.9. is  applicable 

29 
Chimoio Water Supply Project 
FinalDesign Report 

CHAPTER  5  

OPERATION  & MAINTENANCE 
Chimoio Water Supply Project 
FinalDesign Report 

5.  OPERATION & MAINTENANCE 

5.1  Present  0  & M  Situation 

Agua  de  Chimoio  is  responsible  for  all  water  supply  system  in  Chimoio.  The 
water  supply  scheme  is  uncomplicated  and  easy  to  operate  and  little  planning  is 
done. Even  when there  is  enough raw  water ( only  6 months  a year  )  operation 
of existing  equipment  is  complicated  due to  lack  of spare  parts  and  necessary 
tools.  The  major  problems  for  operation  and  maintenance  can  be  summarised 
as follows: 

­ Shortage  of  skilled  staff 

­ Shortage  of transport  for staff and  materials 

­ Shortage  of  spare  parts for the equipment 

­ Purchasing  procedures  entail  delays  in the  supply  of spare  parts and 


materials  and  so  prevent  the  prompt  and  efficient  execution  of 
repairs 

­ Missing  system  drawings,  preventing  proper  maintenance  planning 


and execution 
­ Lack of communication  between  intake,  treatment  plant,  workshop 
and main  office 

These and  other problems  are  reflected  in  the  actual  condition  of system.  About 
40  %  of the  pipe  network  is  estimated  to  be  in  poor  condition.  Although  the 
distribution  network  is  not  in  the  scope  of this  Project  rehabilitation  work  is 
required. 

5.2.  0  & M  for Extended  system 

Based  on  the  existing  0  & M  problems  proposal  for  efficient  0  & M  for the 
extended  system relate  mainly  to: 

­ More effective  planning  and  execution  of 0  &M  activities;  

­ The  provision of necessary  vehicles  and equipment;  

­ The  adjustment of staffing  requirements  and  working  procedures  to  


match  major features  of the extended  system notably: 

­ Intake site at  Chicamba Lake 
­ Pressure  main 

30 
Chimoio Water Supply Project 
Final Design Report 

­ Head  r reservoir  site 

­ Gravity main 

­ Communication  system  to be  established 

­ Continuous  monitoring of the efficient operation of the system 

­ Change  in emphasis  from  ad­hoc repairs to routine (preventive) 


maintenance  in order  to lengthen service life of the  system 

­ Appropriate training  to be  provided, to  operate the  new equipment 


Detailed operation  and  maintenance manuals  shall be  prepared  by the 
contractor. The manuals  should cover the testing,  operation, 
maintenance,  dismantling  and  repair  of all  equipment  and  should  include 
explanations of the function  and  purpose of each item supplied. 

­ Long term training  needs should  be analysed and converted into  long-


term training plans.  Training plans for each job category should be  
developed,  including a plan for senior management.  A consultant could  
assist  in  developing the plans.  

31 
Chimoio Water Supply Project
FinalDesign Report 

CHAPTER 6  

CONSTRUCTION  PROGRAMME  AND  CASH  FLOW 


Chimoio Water Supply Project
FinalDesign Report 

6. CONSTRUCTION  PROGRAVLME  AND  CASH  FLOW 

Construction  programme  and  cash  flow are  based  on  the  commencement  date 
15/09/1994.  The  Christmas  Holidays  have  been  included  in the  Construction 
programme  from  16/12/1994  to  02/01/1995.  If the  project  implementation 
starts  on any later date the construction  programme  has to  be  modified. 

32 
6.1.  Construction  Programme 
DESCRIPTION  15/09/94  15/10/94  15/11/94  16/12/94  02/01/95  15/01/95  15/02/95  15/03/95 

Mobilisation 

Access  Road 

Excavation  Intake  Site 

Intake  Tower 

Access  Bridge 

Transformer  Tower  0 

Guard­Store  House 

Excavation  Pressure  Mair  a



Pipeloying  Pressure  Main 

Reservoir  Site 

Excavation  Gravity  Main  E 


Pipelaying  Gravity  Main  .­

River  Crossings 

Structures  on  the  Pipelines 

Electro­Mechanical  Works 

Testing 

.  LoCommisiorning 
­ / 
,  ..  :  31/11 
6.2  Cash  Flow  iE m o n t hl yT 
M cumulative 

6000000-
5072013
5000000- 4566253
3790220
4000000- 3238330

3000000-

2000000-
97369 7741174779490 760
1000000- 46109251255

15.9.94  15.10.94  15.11.94  15.12.94  15.1.95  15.2.95  15.3.95 

99  31/2 

t7"Tc: 
Chimoio Water Supply Project 
FinalDesign Report 

CHAPTER 7  

CONFIDENTIAL  COST ESTIMATE  
Chimoio Water Supply Project
Final Design Report 

7. CONFIDENTIAL  COST  ESTIMATE 

item  description  unit  provis.  unit rate  total 


Iquant.  (US$)  (US$) 
1.  PRELIMNARY  & GENERAL  L.S.  1  505,000  505,000 

total 1  505,000 

item  description  unit  provis,  unit  rate  total 


I  quant.  (US$)  (US$) 
2.  PIPELNE 
2.1.  Excavation of trenches  inany material 
including  backfill and removal  of surplus 
material.  m  42,269  9.76  412,545 
2.2.  Supply  steel  pipes and  fittings longitudinal 
welded,  internally  coated,  externally 
protected,  6m  length, working  pressure 22  m  2153  70  150,710 
bars. 
2.3.  Lay pips  and fittings including testing, 
flushing and disinfection  m  2153  15  32,295 
2.4.  Supply uPVC  pipes  with  rubber sealing 
rings, 6m  length all  classes  m  40,116  23.74  952,354 
2.5.  Supply fittings  for uPVC pipes with  rubber 
rings  No  235  138.83  32,625 
2.6.  Lay  uPVC pipes and  fittings including 
testing,  flushing  and disinfection  m  40,116  1.5  60,174 
2.7.  Construct  all  the chambers  on  the pipeline 
including supply of all  materials, valves and 
fittings  No  88  3,400  299,200 
2.8.  Provide  all material  and  construct  anchor 
and  trust blocks, marker  posts,  road  and 
railway crossings  L.S.  1  41,950  41,950 
2.9.  Previde and  construct all  river and  stream 
crossings  L.S.  1  46,080  46,080 

total  2  2,027,933 

33  
Chimoio Water Supply Project
FinalDesign Report 

item  description  unit  provis.  unit  rate  total 


quant.  (US$)  (US$) 
3.  INTAKE  TOWER AND  BRIDGE 
3.1.  Excavation  in any material  and  placement  of 
rock  material  L.S.  1  96,935  96,935 
3.2.  Grouting  of all  fractures  L.S.  1  20,000  20,000 
3.3.  All  concrete work  for  intake  tower and 
bridge including  supply  of all  material  for 
concrete  and  reinforcement  bars  L.S.  1  231,441  231,441 
3.4  Supply  and installation  of all 
electromechanical  work for  intake  tower 
and bridge including  all the  testing and 
commissioning  L.S.  1  367,550  367,550 
3.5.  House  on  the  intake tower  L.S.  1  12,000  12,000 

total 3  727,926 

item  description  unit  I  provis.


quant.  unit 
(US$) 
rate total
(US$) 
4.  TRANSFORMER  TOWER  L.S.  1  15,000  15,000 

total  4  15,000 

item  description  unit  provis.  unit  rate  I total 


quant.  (US$)  (USS) 
5.  GUARD  AND  STORE  HOUSE 
5.1.  Construction  of guard,  store house  L.S.  1  75,000  75,000 
5.2.  Construction  of septic tank  and  soakaway 
including  all  drain  pipes  L.S.  1  8,075  8,075 
5.3.  Connection to  existing  water  pipe  m  1,200  12  14,400 
5.4.  Furniture  L.S.  1  20,000  20,000 

total 5  117,475 

34 
Chimoio Water Supply Project 
Final Design Report

item  description  unit  provis.  unit rate  total 


quant.  (US$)  (US$) 
6.  INTAKE  SITE  AND ACCESS  ROAD 
6.1.  Excavation  in  any material  and backfill 
around  the  structures  for intake  site  L.S.  1  114,018  114.018 
6.2.  Construction  of ramp,  free  drainage  rockfill 
and  fence  L.S.  1  7,756  7,756 
6.3.  Construction  of access road  L.S.  1  71,705  71,705 
6.4.  Supply  and  installation  of all 
electromechanical  work  at the  intake site 
including  all  testing  and  commissioning  L.S.  1  84,200  84,200 

total  6  277,679 

item  description  unit  provis.  unit  rate  total 


quant.  (US$)  (USS) 
7.  STORAGE  RESERVOIR 
7.1.  Excavation  in  any  material,  backfilling  and 
construction  of dirt track  L.S.  1  5,752  5,752 
7.2.  All  concrete  work  for the  reservoir 
including  supply  of the material  for  concrete 
and  reinforcement  bars  L.S.  1  12,812  12,812 
7.3.  Supply  and  installation  of all  pipes  and 
fittings,  wire  fence  and  construction  of 
chambers  L.S.  1  8,290  8,290 
7.4.  Supply and  installation  of float  switches 
including  2050m  of cable  L.S.  1  22,000  22,000 

total  7  48,854 

item  description  unit  provis.  unit  rate  total 


quant.  (US$)  (US) 
8.  SUNDRY  ITEMS 
8.1.  Calculation,  construction  and  as­built 
drawings,  operational  manuals  and  30 days 
instruction  period  L.S.  1  36,800  36,800 
8.2.  Construction and  removal  of coffer  dam  L.S.  1  23,000  23,000 
8.3.  Notice  boards  No.  2  1,000  2,000 
8.4.  Spare  pipes  and  fittings  L.S.  1  28,044  28,044 
8.5.  Supply  and  install  radio  communication 
including  all permissions  L.S.  1  35,000  35.000 

total 8  124.844 

35
Chimoio Water Supply Project 
Final Design Report 

item  description  unit  provis.  unit rate  total 


quant.  (USS)  CUSS) 
9.  PROVISIONAL  SUMS 
9.1.  Additional  soil  investigation  L.S.  1  9,280  9,280 
9.2.  Connection  and  installation of power supply  L.S.  1  40,000  40,000 
9.3.  Miscellaneous  plumbing and electrical 
works,  accounts  certified by the Engineer  L.S.  1  31,930  31,930 

total  9  81,210 

item  description  unit  provis.  unit  rate  total 


quant.  _USS_  CUSS) 
10.  DAYWORK  AND  DE­MINING 
10.1.  Daywork  L.S.  1  10,000  10,000 
10.2.  De­mining survey  and  de­mining  L.S.  1  50.000  50,000 

total  10  60,000 

item  description  unit  provis.  unit  rate  total 


quant.  (US$)  (US) 
1 I.  MANAGEMENT,  SUPERVISION  AND 
FACILITIES  FOR  ENGINEER  L.S.  1  555,000  555,000 

total  11  555,000 

item  description  unit  provis.  unit rate  total 


quant.  (USS)  (US$) 
12  SUPPLY  AND  INSTALLATION  OF 
TREATMENT  PLANT  2000m'/day  L.S.  1  70,000  70,000 

total  12  70,000 

36  
Chimoio Water Supply Project 
Final Design Report

7.1.  Summary Cost Estimate­Phase  II 

ITEM   DESCRIPTON  TOTAL 


(USS) 
1.  Preliminary and General   505,000 

2.  Pipe  line   2,027,933 

3.  Intake  tower  and  bridge   727,926 

4.  Transformer  tower   15,000 

5.  Guard  and store  house   117,475 

6.  Intake  site and  access road   277,679 

7.  Storage reservoir   48,854 

8.  Sundry  items   124,844 

9.  Provisional  sums   81,210 

10.  Daywork and  De­mining   60,000 

11.  Management,  Supervision  and  facilities for Engineer   555,000 

12.  Supply  and installation of treatment  plant  70,000 


SUB­TOTAL  item  1to  item  12  4,610,921 
Contingencies  ( 10% or sub­total)  461,092 

TOTAL  5,072,013 

37  
Chimoio Water Supply Project 
Final Design Report 

CHAPTER 8 

LIAISON 

1?)
Chimoio Water Supply Project
FinalDesignReport 

8. LIAISON 

During  the  design  stage  of the  project  (phase  I) Consultant  maintained  close 
contact  with  the  relevant  Officers  of the  following  National  and  Provincial 
Directorate: 

­ National Directorate  of Water  Affairs (DNA)­Maputo 

­ National Directorate  for Roads  and Bridges (DNEP)­Maputo 

­ National Directorate  for Mapping (DINAGECA)­Maputo 

­ Ministry  of Finance­Maputo 

­Ministry of Health­Maputo 

­ Provincial Directorate  for Construction and  Water (DPCA)­Chimoio 

­ Agua  de  Chimoio­Chimoio 

­ Chimoio  Energy  Company  (SHER)­Chimoio 

­ City Council­Chimoio 

­ Companhia  do  Pipeline Mocambique­Zimbabwe  (CPMZ)­Beira, 


Mutare 

­ Manica  Provincial Government 

­ Rural Water  Programme,  Manica 

­ CFM­Centro  ( Central  Region, Mozambican  Railways) 

­ Empresa  de Tobaccos de  Manica 

­ Semoc­Mozambique 

38 
Chimoio Water Supply Project 
FinalDesign Report 

CHAPTER 9  

PROJECT RISKS AND  CONSTRAINS 
Chimoio Water Supply Project 
Final Design Report

9.  PROJECT RISKS  AND  CONSTRAINS 

9.1.  General 

As  apart  of the  services  offered  under  this  Project,  the Consultant  will  assess 
the possible  risks to and  constrains on Project  execution and  sustainability. 

At  this  point  in the  Project  some  general  risks  and  constrains  are  foreseen. 
These  are  listed  below  and  shown  the  reasons  for  the  existence  of the  risk  (or 
constrain)  ,ndthe  measures  for avoidance or reduction. 

9.2.  Major  Risks 

9.2.1.  Delays  to Project  Execution 

9.2.1.1.  Delay in  obtaining  finance  on  time 

Water  level  in the  Chicamba  Lake  isat  the moment  the  lowest  for  the  last  20 
years,  therefore  the  construction  of the  intake  tower,  delivery  channel  and 
intake  head  strutue will  be  cheaper  and  should  be  finished  before  the  rainy 
season starts. 

To  avoid  this  delay  the  finance  construction  should  be  closed  as  soon  as 
possible  to  enable  the  Contractor  to  start  construction  immediately  after  letter 
of commencement  isissued. 

9.2.1.2.  Delay  in obtaining  land  acquisition  approval 

The  Consultant  strongly  recommends  that  DNA,  DPCA,  AdC  and  Chimoio 
Town  Council acquaints  itself with the  respective sites and  required  way­leave, 
and  formally  approaches  the Land Boards  with a view to  securing  the  required 
sites  and way­leave. 

9.2.1.3.  Delay due  to  possible presence  of mines  on  the site 

Although  no  official  information  received  by  the  Employer  indicates  the 
presence  ofmines  on  the  Site, the  Consultant  recommends  that due  precautions 
and  investigation  to  be  taken  before  commencement  of work  specially  on  the 
hills  overlooking  the  Lake  where  the  header  reservoir  shall  be  built  or  in the 
area  around  that location. 

Such  precaution  and  investigation  may  include  obtaining  local  information, 


carrying  out  a mine  survey,  de­mining,  or  clearance  of the  site  by  scoring  the 
surface  with  bulldozer  equipped  with  a high  blade  as  a protection  in case  of 
blast (where  it ispossible because  ofthe  high slope of the ground  level). 

39 
Chimoio Water Supply Project 
FinalDesign Report

9.2.2.  Unsustainability  of the  installed system 

The  inadequate  system  maintenance  can  cause  the  unsustainability  of  the 
installed  system. 

To  avoid  that  it  is  essential  to  establish  the  realistic  operational  and 
maintenance  requirements  and  appropriate tehnology. 

9.3.  Minor Risks 

9.3.1.  Inability  to construct  system  components  as designed 

During  soil  investigation  trial  pits  were  excavated  500  m  spaced,  there  is  a 
possibility  of occurrence  of the  different  material  between  the  investigated  trial 
pits, which might  caused  the  re­design  of some  components  of the  system. 

Close  monitoring  of sub­soil  conditions  is  required  by  the  Engineer  on  Site 
during  the  excavation  in order  to  do  the  necessary  amendments  of drawings  if 
conditions  differs from  original  design. 

9.3.2.  Failure  nfthe system  to  provide  required  capacity 

The  failure  might  occur  if there  is  inadequate  system  maintenance  leading  to 
high  losses. 

To reduce  or avoid  possible  high  losses  of the  system  it is essential  to  establish 
realistic  operational  and  maintenance  requirement  as  well  as  to  equip  the  AdC 
to  fulfil  their  obligations. 

40 
Chimoio Water Supply Project
FinalDesign Report 

ANNEX  No.  1  

INTAKE TOWER  

STRUCTURAL  CALCULATION  

/AZ
Consulting  Engineers  and  Project  Managers 
Telephone  +263­4­750775/9  Telefax  +263­4­750780 
­Sheet  NO:  4007194;C'104
Made  by:  AP
Bending  Schedule  Checked by: ,,P
CHIMOIO  WATER  SUPPLY  PROJECT  Date:  JULY  1994  
INTAKE  TOWER  Drawine  Reference:  14007/94JC.2.  1.t  

Bar Size  N  in  Total  Length  Shape 


Member/  Section  Mark  each  M  [mm  Code  A  B  C  D  E 
INTAKE  TOWER  01  ........ 
T12  ....... 
600  .  . ..... 
600  .......  1975  .......... 
.......  .......... .......  38  915: .............. 
200i,..............  , ..............  ............. 
.
S02.  T12  336  -- 336 2275 38  10151 300:
.. . 
. .. .
... 
. .....  ...............  ..............  ....................  ...........  I....... 
.............  .............. ,..............  ..............  .............. 
T2
103  ...........
....... ....
300  ......
.....
.............  ........... .......... .......  ...............  ..............  ..............  ..............  i..............  
300  4400 20  STRi
064  T12  300  300  3000  2O  STR! 
05 .... T12 
.......  168 
...  ... ... .. ....... ...  ......  ......  ..  .   ................  20...  . STR 
168 ...........  4400 ......  .  ..............  , ..............  ..............  ............... 
S06  T12  168  168  30001  20  STR  i 
S07 T16... ... ... .... ... ...180
.. .. 
... . .. ... 
.. ..  ...  ...  ..  ...  .. ...  ..  ...  . 
180 5150 ..  ..  ...  ..  ... 
37 .. 4340i
........ . .  ........  :...............  _............................. 

08 ........ ................... 90............... 90 ..................... 


.. T16 2125 ..............  38 . ................... 
965 : i..............  ..............  i..............  
0  T16  90  90  5950  41  1Q40 
.....i'..i.. '.............. 
.. ..........  .. .d.................................  ............
..............  i..............  ..............  i.............  
0..
16
.......
i'
....... 90  90
........... 5925
' I .......... 20  STR:
......
6 6..........
...............
....... 'f..............
ii..............
..........
i....
.......
11 T16  180 180 8225 20  STR: 
y'i..... 
.... S2 T6 '  .........

i,...... 18 .. .... .....  ..... '   g  i.............. i..............  i..............  .............. 
.......
i.......i,............. 180.........
.......... ....
.. 7325 .. 20 ..............
.............
.. STR: 
....
".i.
. ............. ........... ........ i
..........  20  "6 3 
T16  16 8225 STR: 
1
.........  . . ......  16... 
..............  . .... ' /  ............  . ............  .............. i....... 
14 T16 0 9 20 3 1065: 
Intake  Tower  Top  Slab  15  T12 38 38  3000 20  STR  i 
16 T12 63 63 1975 39 945; 160:
I# thus 17
i'T12
...
.. ...
. 44 44
'.......... 1925

.f6............ 39 925
i6..........
f' 150
b...............
...........
...........
i.............
..........
.......
.. ....
ST2
. ............. 
0 10 3 0 39  1505:  175: 
T12  ............... 
10  . ............... 
10  .. . ............... 
1600 .. . ................ . 
82 495 . .125 . . . ..............  ..............  ,.... ...  .
... .
ST2
.... 
i'.... . . .   i'8 ii  . . . . . . i'. ..... 
18 
~  i~......  ... ...
4700 
. . . . . . .   i..............  {.. . . . . . .  i.. . . . . . . 
".'..-'..
20  STR: 
21 ... .
.... 
...T12
.....  .............  8 ... ............ 8..............3425
.....  ............... 20 .  .STR 
... . ..............  {...............  . ... ... ........... 
... ........... b ............
6 ............
6 ...........205
...................
..............
..............
..........
2  T1 2  9  9  1975 20  STR 
...
a...
.:i i........... Y 
i5  ..........
i. ..........
i6.............
.. i :3
........
.........
...
...........
{...
......
{......
... ......
..........
..............
................... 
..........
ST2
....................
...................

..............
10 
i.............. 
!............
...........
39  1005:  165:

Intake  Tower  17 T12  23 69 1925 39  925:.  150::


Interm 
C ediate
antilever  ...... i'8....  ... ~{
..............'  ............. 7  .5.................
.. ..............  ..........
i'"i'7i..............{........
....... ....  i....... 
Intermediate  Cantilever  8 12 25 75 3100 39  1505:  175:
S~
b i...
.....fi5....... i6...... 5 ....... i .............. . ...... .............................
Slabs T2 .... 10 Y 30. 1600... 82'   g~f~i.............. 
495
2...... 
...... ig........
6  12 ......
20.
.{ 
 ..  ,i.........:i~  .........  125:
..............  i.............. {.............. 
S15..... 45 ...... 47-0 0 2 T
3  #  thus  22 T12 25  75 1350 20  STR  i 
cont'd on next page
...'T12
...... . . . . . .16 8.....  48' ..................... 
 .. 1825 37 925
'.'"'"
.. ...
g.. . . . . . .  i.. . . . . . .  i.. . . . . . . 
.'.."i'
Al  . 16 8 24 2450 39 117566 05
All  Bending  Dimensions  are  in  accordance  with  BS4466 
*  Consulting  Engineers  and  Project  Managers 
* Telephone  ­263­4­750775i9  Telefax  ­263­4­750780 
Sheet  N*:  4007,94;C,'105 
Made  by:  AP
Bending  Schedule  Checked  by:  A.,. 
CHLIOIO WATER  SUPPLY  PROJECT  Date:   1994 
,TAI­WE TOWER  SLABS  Drawine  Reference:  4007,94,C.2.14 

Bar  Size  W  in  Total  Length  Shape  


Member/  Section  Mark  each  N'  [mm]  Code  A  .  B  C  D   E 
Intake  Tower  27  T16  8  24  4500  20  str; 
Inter.  Cantilever  28  T6  8  24  3400  20  sr..............
.idiate 
Slabs  (Conc'd  from  29  R8  116  348  1250  61  210: 360: 
previous  page) 

...............  ........  ...................  ..........  .... ....................  ..................  ...........................  .............................  .............  


................  ..............   ..............  ...............  ....................  ..................   ............  ...............  ..............  ...............  ,..............  

. . . . . . . .  . . . . . . .   . . . . . . .   . . . . . . . .  . . . . . . . . . .   . . . . . . . . .   . . . . . .   i. . . . . . . .i  . . . . . . .   . . . . . . .   i. . . . . . .  
. . . . . . . .  . . . . . . .   . . . . . . .   . . . . . . . .  . . . . . . . . . .   . . . . . . . . .   . . . . .   . . . . . .   . . . . . . .   ;  . . . . . . .   ............. .
. . . . . . . .  . . . . . . .   . . . . . . .   . . . . . . . .  . . . . . . . . . .   . . . . . . . . . . . . . .  ... . . . . . .  . . . . . . .   . . . . . . .  . . . . . . .  
..................... ............................ ............... ................. .............. ............
! i......... i...... .....
. . . . . . .  ...........  ................  ...............  ....................  . . . . . . . . .   . . . . . .   ... . . . . . .  . . . . . . .   i..............  . . . . . . .  
............... ....... .................... ............... .................. ............... ............ ........... ......... ....... i....
. . . . . . . .  . . . . . . .   . . . . . . .   . . . . . . . .  ....................  . . . . . . . . .   . . . . . .   . . . . . . .   . . . . . . .   . . . . . . .   i..............  
...............
..............
..............
...............
..................
...............
.........
............
.........
i......
i....
................
..............
..............
...............
. ;.........
..................
...............
............
...........
.......
i.....
. . . . . . . .  ..............
..............  
. . . . . . . .  . . . . . . . . . .   . . . . . . . . .   ............ 
i. . . . . . .   i. . . . . . .   i. . . . . . .   . . . . . . . . 
. . . . . . . .  . . . . . . .   . . . . . . .   . . . . . . . .  ....................  . . . . . . . . .   . . . . . .   . . . . . . .   . . . . . . .   . . . . . . .   . . . . . . .  
...............
..............
.............
...........
..........
.........
.......
......
.....
....
...
...............  ..............  ..............  ...............  ....................  ..................  ............  ..............  ..............  ..............  ..............  
...............
..............
..............
...............
...............
.............
...........
.........
!.......
!.....
i...
......
.............
............
.........
...........
..............
S........I........6.......
........
........
Consulting  Engineers  and Project  Managers 
•  ]  Telephone  +263­4­75077519  Telefax  +263­4­750780 
Sheet  NI:  BS  106 
Bending  Schedule  Made  by: 
Checked by:
R.S.B.
RSB. 
AP. 
CH.IJOIO  WATER  SUPPLY  PROJECT 
Date:  JUNE  1994
INTAWE  HOUSE  ABOVE  INTAKE  TOWER 
Drawing  Reference:  007,94,C  :.13 

Bar Size  N'  in  Total  Length Shape


Member/  Section  Mark  each  N'  [mmJ  Code  A  B  i  C  : D  i  E 
BEAM  2  19  T16  3  6  3150 20  S'rRf 
2# THUS2#THS  20 T12 2
20 I2
...............  ............................  2  4  3150
315U  2'0 STR:
20......................................................... 
......
''
.........
...
'..........
21 "............
............
...............
.. ..'
....
T16 ............
T ""o ..........
...
....... 4 
.  ............................. 

.................. 
1950  39  86  43 
22 R8 54 108 1400  61  195
.............. ............... 45
............. ...................................................
.......... ......... ..............
.. ..........
BEAM  3  21  TI6  4  8 1950 39 865: 430 !
2# THUS  23  T16  2 4  4550
24...........0........................................................ 20  SrR.
.....
.....
......................
...
24 T16 ........... 
.........
o  ............
R!.......... 
.. ....
..............

..............
.........
4 4550 
............................  .............  ...............  ..................  
20 STR: 
. . ......... 
22  RB  32  64  1400  61  1951  445:
............................................ .......... i.......
.... .... 
2 3 ............. T16..............  .............. 
2 ............... 
4 ...... 
4500.............  .................
20  STR  ;............ ........
. 5..............  ..............  ......
i......  
27..0..............................................................

...... ....................................................... 
................... 
...............  ............  ...............  ................ 
............  .... 
.......  .... . . . ................  ................. 
............................. 
. . ............ 
. ............ 
27  T20  3  6 
.............
.............. 
. ..............l ....-
..
... i............. 
:: 
............. 
1400  99C  4 
...............
.........  .  ... .  ..........  . . . .  

..............
............. 
26
................ 
.............
....................
.................
T16
.........
...............
I  ...........
..............
A.B­C  0­ZOO20  7.5.d i.......
2 4  ...........
............ 120 60 200:  2750: i i:k:L C

...............
...............
........
..........
.................
........
.......... ..........
.......  T12 
2)8  ........   2 
..  ..................... 
4  ......
1550  60  200;  450: 
..............
29  ...........................
T12 1  ...... ........ ..........................
......
2  1200  60  2CC: 2'75S 
.........
......
..............
............ ..........  . ......................
................ ............
..............
1..............
..............
..........
COLUMN  29  T16  4 16  4825  37  4700iU
4# THUS  30  RB  32  128  775 60  150:  150:

.. 
..............
.......
....... 
................
............ 
....................
.......
.............
..................
.......
............ ......................
............. 
...............  .................
i.............. 
...........
...............  ..............  .............  .... . . . . ...  
.............. .............. .............. ..........
.........  ...................  .............  .............................  .............  
.....
........
.... .................
.................. .......... ................... ..............

...............
...........
........ .................... .................. .......................... .............. ...............
...............  .............  .............   ..............  ........  ..........  ...............................  ..........................................   ............  

...............  .............   . ............  ...............  .... . . . . . ............................   .. ..............  ..............  ..............  ..............  


...............  .............  . ............  ...............  . .........  . ..  ......................  .........  ..............  .........  .................  .............  
..............
. . . .. . . ........
................
.......
h I  .

All  liel.......................
........... cu.................446

dA  
-,r Nicholas  O'Dwyer  & Partners  
Consulting  Engineers 

2  Robert  M ugaba Road  Sle  t  No  ....... ......................


P 0  Box UA  424.  Unioni  Avenue,  Harato
Telephone  702531.5  Made  By  .................
Tol013s  702538 
J...  2345 C ZW .R Checked By . . ........................
Jo e  ...........................................................................................
.......
...........
....... Damo ... .. . . .............
..... ...............

SELCfON  .. ..-..-.-. ..-. R.. 

­ ­ iI  ,_

______~~~~  ­Lgpjd  01  & 


-2 pjf

J  ­­­­ I  ~  ______I____

' i.  jirzLV 


I  F  F--_-

-'-
--
i---;--- , ­ ­ ­­ ­­­ ­ ­ ­ ­ ­ ­ ­ -.... __,,_..__ ..  ______  ___.._ 
,__

zzzz  111  uf 


tA.;
.. I  4t  _-
1%  ~
TIM,,. __________ 

71__  i ­.  ______


lr,

*  ­ ­ ­ ­____ 
-____
____  ____  __T 

_  _  _  ! [ . . - !_.-J:

iz~itzti~ziz~
1  ~ ­~I  ________________________7__
.lr Nicholas  O'Dwyer  & Partners 
Consulting Engineers  &  Parners 

2  Rober  Mugabe  Road  Sheel  No  ..........................................


P.O.  Box  UA 424,  Union Avenue,  Hatafe
Telephone 702531.5  Made By ......................
Telefsx:  702536  
Telex:  22345  CODWYR  ZW   Checked  By  ...  ....................

.Joe ................................ ........ .... ............. Date......

.. . . ...... Ref .  .. ...................


S ECTIO N  ......................................................................................


IT7 

,  l"- ----- -2

­­­­­ ­­­ ­ 1

_4­­_  _ -.
_--___-__-- _____ 
t-L -

-1-1

I  I 
LAMONT Consulting Engineers

Page :
Job No.:
10.1/20 
Chimoio Water Supply project Made by: ap
rc cant. slab Date
30 /07/94
rc design checked:

beam/slab design acc. BS 81:0

REINFORCEMENT DESIGN for a slab


for Cross Section: SUPPORT - cantilever

Width: b = 1000 mm, bw = 1000 mm


Depth: h =  200 mm, hf =  0 mm
d = 144 mm, d' = 60 mm
Cover: top 40 mm, bot. 50 mm, sides 0 mm
Span: 1 = 1.600 m, Width of Support 300 mm

Materials:
Concrete fcu =  40 N/mxn2, Steel fy = 460 N/mm2

Moments and Forces:

Bending: M = 26.6 kNm


Shear: V = 33.2 kN, UDL =  0.00 kN/m

REINFORCEMENT:
Bending:
Bottom:

requ.: As = 485 mm 2 ­­ > 


provide 8 T12 at 200 mm c/c with As =  904 mm 2 (0.28%)

Shear:
Shear Stress: v = 0.23 N/mm2, vc =  0.82 N/mm 2
No Shear reinforcement required !
Design at 294 mm from Cl for 0.0 kN, v  =  0.00 N/mm2
Asv = 0 mm2/m
Provide 0 legs R 0 at 0 mm --> Asv =  0 mm2/mCurtailment:
j< 0 mm >j<--- 0 Links R 0 --->
­­­­­­­­­­ 0  mm  ----------- >1
l  r  Nicholas  O'Dwyer  & Partners  
Consulting  Engineers 

2  Robe'i  Mugebe  Road  Sheet  No  .  ..........................  


P 0.  Box  UA  424.  Unon  Avenue,  Herare 
Telephone  702531.5 
;Jade  By "  ..........................
Teletae.  702536
Telex,  22345  COOWYR  ZW  Ch­cked  By
JOB......  ...................
..... , . . 
...................................
.,  ,.  .........  .  ... 
SECTIO N  .....................  .  .  ­ .  ..  .....  .....

-- __ 

­:­'[..  1.l  ­ __  _ 

'C 

_  ' frTcTzz  .  ­ ­ =­­_  __  __  _ 

~~~L  /G_ -. __ 

­_  __  _  _  _  _ 
Nicholas O'Dwyer  & Partners  
Consulting  Engineers 

2  Roben  Mugabe  Road  'heel  NO 


P.O.   Box UA  424,  Union  Avenue,  Harate
Telephone  702531.5   de By.  ......
Telefaox 702536  .
Telox:22345  COOW YR ZW  ,  ,, By  ................................

SEO  N 
SECT ION  ...
­.­ oe 
V~>
......
...................
.......
.........
.
­ ,­ ."..
. ..........................................
... .
..... m  . . . .
...
.......
............ ............

S-.
..... _-

Tt  I  I

_  ._ . ,,_-,_ _  -_ _, L-~
_.,,

ffI  I  1  1  _ _  _  _  _  _  __,..r L
! .__t_ - "_--__ _. _,,_,. _ 

,- !- --

-!-
--- ­ ­ -,- - -!- ,. ,.-

!!iT
]IlI--f7..... .. - ­ " .....- -
I . 
Nicholas  O'Dwyer  & Partners
Uf  Consulting  Engineers 

2 Robert  Mugabe  Rood  Sheet  No 


P.O.  Box  UA  424.  Union  Avenue,  Harare  
Telephone  702531.5   a?de  By...... 
Telefax:  702536  .................................
Telex:  22345  COOW YR  ZW  krd  8,  .......................................  

JOB  ......  a ...................................  

SECTIO N  .......   .........  ...  ..I.  ..  .......................  

I  -

4j  i  _,___,  _____  t  1  !


;  '­ ___  __  ___  __  ___  __  _ 

­ ­" 

7)'  .Fv2
­


­ ­ ­­ ­­  ­ _  _­ ­ _  _  _  _  _  _  _  _  _ 
­ ­­ i­­ I­­..  _  ­ ,,  a...jj! 
­ ­­

K
_

­ ~~­ - __
r- __ _  __  __  

­ ­­ .  ,.I  

­ ­­ ­ il  h  CY L ___  ____  ____  _  ­_ 


­mur  Nicholas  O'Dwyer  &  Partners  
Consulting  Engineers 

2  RobertMugabe  Rood  51,hel  No  .... 


P.O  Box  UA  424.  Union  Avenue.  Hirate 
Telephone  702531.5  ;..ode  By  .. ..................................
Telefax  702536 
Telex  22345  CODWYR  ZW  I  k.hJ  Byt.  .  . 

JO B  ...  ................  . ........  .  ....................................... 


SECTION  ....................................................................  .....  .................  ...  MCI 

I  I  i  _  _  _  _  _  _  _ 

­~~~~~~~  q1T~zrI­ ______ 

IT­ I­ !_  _  __  _  _  __  _  _  _ 

­ ~  ~  ~  ~  K______  ­

­ ­_  ._  _  _ _  __­ _ 

L  I  ­ ­:  I  ­ ______________________________ 

~I  I  I  F  I_  _  __  _  __I__  _ 

1 !2

Kt  _  _  _  __/_­­

.... 
I  _ _ .___ _  _  __--
*­tr  Nicholas  O'Dwyer  & Partners:  
Consulting  Engineers 
2  Robert  Mugabe  Road  + 0 
,........ ..
P.O.  Box UA 424.  Union  Avenue,  Harare  
Telephone  702531.5   ,,A e  By  .. ..................................
Telefax: 702536 
Telex:  22345  COOWYR  ZW  -cked Bv .................................

JOB ........................................................................
.....

SECTION­.  A-......! .

... . . . .A-

___k~ ~  '~fi~  _______ 

~i~f  3T- ­ .-.--.


'­_____­___
_,__.__ 
_-_--..........-
,_
.......
._......
. ,-_.....

II  I_'_, _  _  _  _  _  __ 

isV, ___  __ 

­­ +--

c­ ­­ ­ - _  _  _  _  _ 

IC­~  INA_"
I  ______ 

P~  ~  ~  .­
L"L _  ____ 
• ir Nicholas  O'Dwyer  & Partners  
Consulting  Engineers 

2  Robert Mugabe Road  No 


o,"_I . . .................................
P.O.  Box UA 424.  Union Avenue,  Harare
Telelphone  702531­5 By.......
M,,dce ...... 
Telephone7025  1 ­5M  de  B  ....
.............................................
Telefax!  702536  
Telex:  22345  COD WYR  ZW   r7,.-h'd Oy .......................................

JOB ...............................................
.....................  ...  

SECTION  . . <­ ­ .... .. . .

...............................................

Jh­ _ 

­ 4A  (P 

,.  o___  _  _  _  _  _  _  _ 

) i .N

"~ C 
J[  i i -

A/

i  tz­ i  zz  .  i
L

U71  __i

­ _  -,___ _  _________. 

--- 1j


Nicholas  O'Dwyer  & Partners  
Consulting  Engineers 

2  Rober,  Mugabe  Road  SfheetNo  ....  ...................................


P  0.  Box  UA  424.  Un  on  Avenue,  Haitre 
Telephone  702531.5  ; ,, By  .  ..........................
Telelax  702536 
Te e.:  22345  COOW YR ZW  L.­ked  aY  .................................

JOB ............ ......................


...... ,. .

SECTION  f..................  

__ I.  _  _  _  _ 

1  ­ --
[_ _  _ 

­ ~~~.,  _  IG

II  ­ I _  _  _  _  _  _  _  _  _  _  _

LI2~If~~7II(Do I  ___"__ 

o -- I 
"---,--_-

~ijI  IT-
, i­­­­­­­­­­­­­­­­..  __  __ _•

I  lo  I C,  c  er 

.  _ _ 
_  __  _  _  _  _  _j  T 
Nicholas O'Dwyer  & Partners 
Consulting  Engineers 

2Roben  Mugabe  Road  Shet  No  , . ,..


P 0  Box UA  424.  Union  Avenue,  Hari re
Telephone  702531.5  .1.  By 
Telefax702536 
Tell%.  22345 CODWYR  ZW  I.*.tkvd  By  .................................
JOBO  ......................................
...........................................
......  U,  . 

...
.... ............ .....
SECTION  ...................................................................
.............

*I~K ' r_75 ___________ 

1C 

1 ­1+ 

,I L!
Nicholas O'Dwyer  & Partners 
Consulting  Engineers 

2  Robert  M ugabe  Road  shxiel  No  ...  ........................................  


P  0.  Box  UA  424.  Union  Avenue.  Harare 
Telephone  702531.5  ;rde  By  .... 
Telefam.  702536  ..................... 
Telex:  22345  CODW YR  W 
Cheicked  By  ........................................ 
JO B .....  , . . . . . . ...........................................................  .... .  .  . .  .  .  . .  .  . .  .  .  ....  .. .......... 
L) I .......  .......  ...... 

SECTION  ..........................  ............. 

~­ I  J  _  _  _  _ 

4>'  i­t -
_  ___I  _ 

7-

7__  - _  _  _  _  _ 

-I--.. ____ _  __  _  __  _ 

I .. 
Nicholas  O'Dwyer  &  Partners 
Consulting  Engineers 
Shee No  ..........................................
2  Robert  Mug a  e Road  Avenue.  Hartre 
Union
P 0.  Bo  xUA  424  Made  By  .......  .......
........
Telephone  702531  .5 
702536 ........................
Y  .. . . ..........
Telefax  e
Ch  ockB
x :  2 2345 CC DWY R  Z  W 
Te le
X;( 0 ...........
8  ..... .. .....
.....
..............
......
.............................. ......
. .... ... ...
...... ......
r . ... ...........

SECTION 
~r 

I  F  _________....___

_  _  _  _ 
_  _  _  _ 
W'  e,  ­ e  _  I  ____________
SI

________________ 
, CJ
• i

I  A  ­r, YEI , • _________ 

i;~ ~i re  i Jei- ll

I  1  T
__"

4I

__________'_J 
-,

*  T-
;
' .' ' ____  __  I  ' __  _ __  _  _ _  __  _  __  _  __  _  __ 

- , ' I  ___  ______________ 

____,_,__________  

i  , i I 1,1 i- --

H ____________  

___  _  _  _  _  _ 

u'  i  _  _  _  _ _  _  _  _ 

77 

1AJ  I~ ____________ 

L , !JZ! I
+  /  7  x­ J a'J

*  IF  _______­7__
Nicholas  O'Dwyer  & Partners  
Consulting  Engineers 

2  Rober  Mugabe  Road  Sheet  No  ....  ................................  


P.O  Box  UA  424.  Un,on  Avenue.  Harare  
Telephone  702531.5   Made  By  ...........  ....... 
Teleiex.  702536 
Telex:  22345 COOWYR  ZW  Checked  By  ..................................  .  
JOB  ..  ..................................  ......  ....  ......  ......  ... ..................  .  . .  ......  ......
......  .....  Date  ..... ...  .  . .  .  .  .....  . . .  . .....  .. ......
SE  7  c N  ........................................  ...........  ............................  Rae.  

"  I 

_  _  _  _  _  _  _  __­-

.. i 

I
ia:~ {~  
....  ____ 
i! I  ~  t'-~ ­-
___ 
___  ___  ~  ~  ___  ___  ___  ___ 

]  I  L .!~i  ~  ___  ~-
'  2'  C  _________ 
I  I  ­.-

1  I  l  '  I
77.i  m  V  T  ]__  _  _  _  _ 
9  I  [ r]- .. . .

I ,  ­'  ­ ­ '­i­­­'Pi  ..  ­­ I­ _____-

_  _  _  _  ~  j 2 
~t~v I_  _  _  _  _  _  _  _  _  _  _  _  _ 
Nicholas O'Dwyer  & Partners  
Consulting  Engineers 

2 ROberitM ugabe  Road  Sheet  No  .................................................... 


P 0.  Box  UA  424.  U.,en  Avenue  Hlrae
Telephone  702531.5  Made  By 
Telefsx:  702536 
Telex:  22345  COOWYR ZW  .  .  Chcka.  ................................... 
.....  .Date  ...  ......................................................... 
SECTION  .......................................................  .

;  L  '  '  ,4.7iJ 

;  :  IL_ _2  I 

-------------- 0_  I­Al  T  i r!i 


Ii. ' 
­1 

I  ~ 
)~ 
:  ''  t  ,''/  L  S­-
__:_ _ ____________ 

__  _  __  I  A1  13I  A  cO 

1~2­CCe 
*Nicholas  O'Dwyer  & Partners  
Consulting  Engineers 

2  Robert  Mugabe  Rood  Shee  No  .........................................


P0.  Box  UA 424.  Union Avenue.  Harare 
Telephone  702531­5  M ade By .........................................
Telefax:  702536 
Telex:  22345  CODW YR ZW  Checked  By .......................................

J O B  0.............................................................
...... ............
...............
..............
........... Date  ...............
... ..............................

.. .....  ........ Ref 


SECTION  .................................................................................

... q  ­,
V ­77
"V;­ iA 

________,  , I 111i II I  II  _  __  _____________ 

11
, ,I ,IP,4  I J I
I , . 
T____ i" II 1
=1r  Nicholas  O'Dwyer  & Partners  !  
Consulting  Engineers 

2 Rober  Mugabe  Road  Sheel  No  .........................................


P  0  Box  UA  424.  Union  Avenue.  Harare 
Telephone  702531.5  Made  By  ........................ 
Telefax.  702536 
Teiex:  22345  CODWYR  ZW  Checked  Bv  ..........................................  

JOB  ......  ..  .....................................  ..............  ....   ........   ......................................  


O N  
SEC TI ......................  .. ..............................................................   ........   . ..............  ...  ...........  ..  ............................................  

'  I  I  ______________________________ 
~i I  _  _  _  _  _  _  _  _ 

I  iI 


ip,  ,  _  _  _
I u  ­
;  r_ 
_______  ­

,  i  t­.' 0  . 4 ­57c 

_  _  _  _  _  _  _  _  _  _  _  _  !IL  I  I  _  _  _  _  _  _  _  _  _  _  _  _ 

.­.i i
1 1_ 7L 

r­7.' 
­!r  I 
_  A _ 

AAA
.  " 
_  _ 

c~xi/.'/­ ,g c  ,  1­ , 

'  Ii 

_____________________________
0; 
_._,_.  PcZ 
­­ ­

Ii___________________ 

____  o7',c­i­i  PA  .


'  ­I  ,,,..  i" 7  r..,  II?  F  ­q­i7.E­­ ­.­ .  . 
Nicholas  O'Dwyer  & Partners  
Consulting  Engineers 

2 Roben  Mugabe  Road  SICe No  .. ....................................


P.O.  Box UA  424, Union  Avenue.  Harare 
Telephone  702531.5  ;Aade  By  ...............
...........................
Teleia:  702536 
Tle  x  22345  COOWYR  ZW  h  d  By  ......................................

J OB  ...
......
............ ..... .  .....................................

SECTION  . 

Wi I  

I -_L _ _  _  _  _ 

15  ­7 

ff

­~~  1.1 ­­ ~ 1;i.  __  _  __  _ 


Nicholas  O'Dwyer  &  Partners  
Consulting  Engineers 
2  Robert  Mugabe  Road  Sheet  No  .................................................... 
P.O.  Boe  UA  424.  Union  Avenue,  Harare 
Telephone  702531­S 
Made  By  ........................................... 
Telefax:  702536 
Telex:  2345  COOWYR  ZW  Cheded  By  ......................................... 

SECTION 
JOB  .,.. ......................
. .y............
.. .  ­­..................... g 
0.)......................Dae  ..................... .....
.......
R  ........................... 

­ :  izi 
­­  ­ __  _  _  _  _ 

CC 

Ij  ____ 

'[,­ ­­­­ Q,-

- - - ~­ ­ ­ ­
Chimoio WaterSupply Project 
FinalDesignReport 

ANNEX  No.  2  

ACCESS  BRIDGE  

STRUCTURAL  CALCULATION  
Consulting  Engineers  and  Project  Managers
Telephone  +263.4­75M75S9Tclefu  +2634­75750 

Sheet  N2:  BS  103  


Bending  Schedule  Made  by: 
Checked  by: 
S.B.
R.
A.P.  
CHIMOIO  WATER  SUPPLY  PROJECT  
Date:  JUNE  
BRIDGE  & INTAKE  HOUSE  R.C.  DETAILS.  
Drawing  Reference:  4007/94/C/2.13 

Bar  Size  W  In  Total  Length  Shape


Member/  Section  Mark  each  N  [mm]  Code  A  B  C  i  D  E 
BRIDGE  06  T16  4  12  11000  20  STR!  
3#  SE'TIONS   07  T12  4  12  11000  20  SI'R  !  
(IN  11#  PANELS  OF   08  ........ 
......
SIZE  1017mm) 
RIO  ....... 
138  ......... 
414......... 
.......
....
................... 6 
2000  6.  ........
.  .....  ....... 
220  .. . . .
09  RI2  238  714   2000  60  670,  2001....
22#  IN  EACH  PANEL  ................... 
10  ..RI2  .........  . 
122  366  .  050  81   3351  351  
11  R12  242 726 1125  83 900!  150 
..... 
...  6151  
"  ......  ......
12 
.................  2.."...  .. 
R  ­...  ­. . 39  . 750. 
5.....0.... 9.0  . .  ..........   i 
.......  .................   ......................  .  
13  T25  10   30  11000  20OSTR  
.  .....  ........  .............  .......................  ...............................   ............  ............................ 
15  T12  162  486  1975  20  STR
. ... -.........
. . ......... ................ ...
1  T16  32  972  2200  2  STR  I 
........  .....................   .  ...  .
F  .....
..
.­ ...
.iii .......
..  .......
6.  ..  ....  ..................
I  I.  ...................  ........... 
STR ......  .....  . "..............  ..............  .. . . 
18  T12  22 66 2050 39 1015i  751  

CORBEL  STUB  COLUMN   01  T25  3  6  3375  99A  


2#TIIUS..   . .  ...............  ......  ............. 
. . 
....... "'"  ;  ,  ... 
.................................  "  . ............  ............ 
.  ".............:........4  ........  .............  
.............   .  ........  ...   "  !  s. \ 
...............  ..........................
..................  ....  ...........  ...  .
"...... 
.. .5 ......................  
S.  .  . .  .  .  .. ....................
.............. ......... .....
......  .....................................  
2T5 
.....  ................  
2  4  1900 
..................................... 
... 

60  200 50......:


.
.
:.................  
...... ....
............. 
03  ...  .  .......................... 
T12  4  8...  ..................................... 
1650  60  "'200:"'500......1'.......i....  
~....... .............  ..............  ...............
........ ...................  ....
.....
........ .............  .........
......... . ........... 

MAIN  CORBEL  04  T20  21  21  3375  99B  


....  .............   ..................
....... ........
. . ....................
............... 
.........  . ................   .............   ..... ..
..
................
.............
.............
...............
....................
..................
............
.............
..
* .................
. ..........
05  2  7  7C  ­5
60  33 
.  ..........  
..........................................   .......   . 
"  .
JO  X5X4SU  05 T20  6  6  350  .38  84  30  ['
COLUM  AT  MVEA 
M  ETH  314 
...............  ....RIO  20 
.........  ..............  ..... ........ 20 ................... 
•..........................................................  25009  ................ 60 ...........  
300 84i  400 
...................... 
..
OINT.  "  .... .:.
32  RI0  6  6   2400 
2...TH U  S................. 6..840......
.. ... "..  ...  .........  

T.U .......
.......
.......
I....
....
.. ...  ........... ....  . ...............  ...... ...  . ... :...  . 

All  Bending  Dimensions  ­are In  accordance  ivth  BS4466 


Mop=  Nicholas  O'Dwyer  & Partners
Consulting  Engineers 

2 Robert  Mugabe  Road  Sheet  No  ...................................


P.O. Box  UA  424,  Union Avenue,  Herare  
Telephone  702531.5  Made By .........................
..............
Telefax:  702536 

.....
o,.....
.......
.............
Telex:  22345  CODWYR  ZV
...........
wc ...........
......
......
.........
t:h.cked  By .......... . ..................

m.n o 
Ci+6"Z"
03..........~ t ­c­ v­. 

.............................. ...... ... ,~


. .......
.­ .. 

. . .........................................

FT  I 

­ ­­­­­­­­­­­­ I­I  _-.

. r  .­­­ ,-- -

IF -T

­~­
J!4A 

LL ­­ ­ -a. ge

'­I 
I.

­ ­ ­­ ­_  _  _  _  _  _  _ 

__ ­­ .  --. ­­ ­­ N 7 - _  __  __  __ 


vi 
Nicholas O'Dwyer  & Partners
F  Consulting  Engineers 

2 Robet  Mugsb  Rood 


Hirer.
Sheet  No  .. >
:...
P.O.  Box  UA 424.  Union Avenue, 
Telephone  702531­5  d.B*  -
Te::ex:  2
Telefx:  36
7253CO  Y  W Wl*LeIB  MaWd  By  ........................
,.~el ...
..............

.......
. .  ..........
... .............
R. .................
.

A  I___ 

W  ,  y1

Ntt

[t. .___.. __
-Mir= Nicholas  O'Dwyer  &  Partners 
Consulting  Engineers 
2  Robert  Mugabe  Ro4.d No  ....... 
.;I,!el .................................
P.O.  Box  UA  424.  Union Avenue.  Herare  
Telephone  702531.5   Made By ... ......................................
Telefax:  702538  
Telex:  22345 CODWYR  ZW Ch,.thedBV ...  ..................................

JO B . ...............................................................................................................
. ae ..............................  

SECTION  ....  ...... . ....................................... Rel

Sr

~1,4 

.4A.
..

Aik
-_ _  _  _  _  _  _ 

_  _. ___  _  _  __  _  _ 

---------------

vfi4zi
­ur­ Nicholas O'Dwyer  &  Partners 
Consulting  Engineers 

2 Robert  Mugabe  Road  Sheet  No  ............................  ............. 


P.O. Box  UA  424,  Union Avenue,  Harare 
Telephone  702531.5  MadeB V.........................................
Telefax:  702536 
Telex:  22345  COOW YRZW  Checked  By  ........  .  ................................ 

JOB  .......  .  ...............................  .........................................................................  ...  .  e  ...........  .................... 

SECTION  ..................................................  ............. 

I  ­ _ 

­­ ­ ­ ­­ ­ ­­ ­ ­­ ­

__  ~~  ~  ~  ~  ~ 4 ~  ~  ~  ~  ~  _ 


________________________ 
0  A_

­ ­ ­­­­ ­­­ ­ ­ .  ­ ­__________________

­­­­­­­­­­­­
­eir Nicholas O'Dwyer  & Partners 
Consulting  Engineers 

2  Roben  Mugeb.  Rood  Sheet  No  ....................................................... 


P 0.  Box  UA  424.  Union  Avenue,  HireSe 
Telephone  702531.5  ade  y ............... 
Telefax:  702530  .......... 
Telex:  22345 CODWrYR  ZW  Checked  By  ............................................... 

JOB  ........  .................  ae.............. 


SECTION  ..  ..  ...........  ................  .

p  5 

T--

­ ­ ­ ­ ­ ­ ­ ­ T  ~  ­" 

­ ­ ­ ­T  ­"  J  . . 
IL~O  ILO~ 

O,4O~ 


/ I K

'I  ­,  ­. 

-A ~<  ­

O(cc ­ ____________________ 

I.  ­ LI.  cr~.~z ~C'


S~-p~

Scd4r
LAMONT Consulting Engineers
Page
.11,)  No.  :  1031/20 
Chimoio Water Project Made by: jf 
Bridge Date : 06/07/94
nax field moment checked:

bemelab d.aign .cc. 9J  oil* 

REINFORCEMENT DESIGN for a rectangular beam


for Cross Section: SPAN - simply supported
Width: b - 300 mm, bw - 300 mm
Depth:  h  ­ 750  mm, hf ­ 0  mm 
td - 698 mm, d' - 60 mm
Cover: top 40 mM, bot. 40 mm, si des 41) mm 
Span: 1 .12.000 m, Width of Support 300 ,nm
matrials :
Concrete fcu - 25 N/mm', Steel fy - 410 N/mm'

Moments and Forces;


Bending: M ­ 504.0 kNm
Shear: V ­ 168.0 kN, UDL =  28.00 kN/m

REINFORCEMENT:
Bending:
Bottom: requ.: As ­ 2529 mm' ­-

provide 5 X25 with As *  3125 am'  (1.39%)

Shear:
Shear Stress: v =  0.81 N/mm', vc  ­ 0.72  N/mm'
Design  at  %6000  mm  from  Cl for  144.4  kN,  v  ­ 0.7U  {1/mrO'  
Minimum Links:' Asv =  552 mm'/m
Provide 2 legs RI0 at 275 mm ­­ Asv  =  571 mm'/m

2  ..
i...  ,  ... 

7-S !/ 
Jimicnolas  u'uwyer  &  Fartners 
Consulting Engineers 
2  Robert  Mugabe  Road 
Shevl  No  ...........................................  
P.O.  Box  702531.5
Telephone 
Telephon  UA 424.  Union  Avenue,  Haaie
70253  1.  aM,e  B  ....
.  .......................................
. . . .  .  . . 
Talefax  702536 
Telem­ 22345  CODWYR  ZW 
CI  nh  By  ........................ 
JO B ......................................   .... . ...................   . 
...........  ......  Date  ............   ............  .......................   .  
SECTION'........  ..  t  ...............   .......  .................. 
..  '  ......  ....  ..... ...  .. ...

-'- .~i  r  ' 


l[
­­ ­­­ ­Jl ­­­
:
­ -

___ _

____  ___

KIz 
­l­ .. 
_  __,_,_,_,_­._.... 

SI 
it% 
tlt  __  La__. 
I ­ ­ .  "-
-,WF Nicholas  O'Dwyer  & Partners  
Consulting  Engineers 

2  Roben  Mugabe  Road  Shee No ...........................................


P­O.  Box UA  424.  Union  Avenue. HariSe
T  e:Phone  702531.5  Made By  .... ..........................................
TlOefa.,  702536 
Tele.  22345  COOWYR  ZW  Chpcked  By ..  ........................................

o '
JOB  ...........................
......
.... .... .... ... . . .................. .................
u,,e  . ...... ............
.........

S ECT ION  ................................ . .....


.............
RC1 .. .......
. .. ..................
....

L  1__ ___

Tr9

­ci: 

I  4  _  _  _  _  _  _ 

z~I9I~~T  z~:  4". 


____  ___ 

r  41k

WI

I  I  ­ _________________________" 

II~iKT  ~  i  ____­___ 

,, -C;., --

­ 7  iIi

..
.....
"
*  INicholas  O'Dwyer  & Partners  Consulting  Engineers 

2 Robert  Mugabe  Road  Sheet  No.


P.O.  Box  UA 424,  Union Avenue,  Harare  
Telephone  702531.5  Made By ..............  ..  .........................  
Telefax:  702536  
Telex:  22345  CODVYR  ZW  Checked  By  ....................................................  
JOB  .......  ...........................................................................  .  ........................  . . . .  . . .  O  ...................  ....... .....................................  
D ate  
J E  No. . ...........  . . . . . ... .... e .  . .  . .  ......  

I  I  L  o  ­ 1 

zlz)  I  .u 

'  L  iz  A  l'  W­Ltr 14  C41k  ___ 

I  II I 
_____  ____  ____  ____ 

C
a*2 
0"t
I  I

Ti,, ­­ A  ­__ 

I_ I  _  _  __  _____  __  _ 

i  ­­ ,  N I-_  _  __  _  __  _  __ 


K:'  jr~00~tA 
­­ ,1'L  ­ T­q'  ­ ­' ­
­ ­ ­ ­
_ _  _  __ 
Nicholas  O'Dwyer  & Partners 
Consulting  Engineers 

2  Rob  n Mugabe Road  SheuoNo  ..........................................


P.O.  Box  UA  424.  Union  Avenue,  Hrre ....................
.....
Telephone  702531  5 M ide  By  .........................
Telefax:  702536  
Telex:  22345  COOWYR  ZW  Chocked By  ........................................

...... Date.......................................
.......................
JO B .................................................................................................
.......
................
...............................................
S EC TION  ......................................... .
.................................
Ref...................

-- ­

___  I  ________  I.+ Io ,./,

1%1 

I  I  i iI

f  i'
zv  !12i
.... , 
'
,

1  t  j­ ­­­ t­I  _ __  __  __  __ 

'~~~  C?, -D

I  t'  IL'  I  I i J  T
' !Jj 

il~Te I ;!"

SIl- ­ ­-
­TM 
!A  I  !
Chimoio Water Supply Project 
Final Design Report

ANINEX  No.  3 

TRANSFORMER  TOWER 

STRUCTURAL  CALCULATION 
Consulting  Engineers  and  Project  Managers 
- Telephone  +263­4­750775/9  Telefax  +263­4­750780 
Shcul NO:  4007/94/C/lu2

Bending  Schedule  %lade by: 


Chucked  by: 
R.S.B.
A.P.
CHIMOIO  WATER  SUPPLY  PROJECT  Date:  JULY  1994 
TRANSFORIER  TOWER  Drawing  Reference:  4007/941C/2.12

Bar Size  N  in  Total Length  Shape 


Member/  Section  Mark  each NO  [mm]  Code A  B  C  D E 
BASES  01  T16  10  40  1025  38  215:  670:

BEAM  1  02 TI2 4  24 1900  38  865i 230i


.... ...............
..
.............
..............
....
..........
........
...........
......
............
o............
,.......
..
..............
.. .............
;
6#  03 T16  2  12  2000 20 2000;: 

04 .....
.........
T12 .......
2  ............
12  2000  ...... 20 
.............
"."...................
2000:   ................
....................

..............
...............
05  ...............
..............
..............
............
R8 ........
..........
.......
.....
,.. 11  66 1000 60 230; 180:: 

BEAM  2  02 TI2 4  24 1900  38 865i 230:


6#
......
.....
.....
....
05
....
...........
..............
................
R8
,..
.......
....
.I,;,
...........
i.......
......
14
!...84 10OW  60  230:  180.
06  TI2 2  12  2500)  2(0  25o00 
7 .............
............... .......
..........
.......... . ...
....... ..............
..............
..............
..........

SLAB I !1 TI2 18 18 3025 33 2830:"


i....... i.....
......
... ...
.......
.. ...............
.... ... .. 6..............
.................
......... i...........
i.....
........
1#12 TI?
....... I.
i........
..I5
.. I5 4025
i6.............
............ 33  ............
...........
.....'...
..............
3830:.............
i..........
I........
.....
13  TIO  18  ..............
18  ..................
3025  ......
33 ..
2830: .............
..
!....
..
.
i .....
.....
:.....
....... ................ ....... ...
.........
....i
..
14  TIO I5 15  4025  33  3830:.

COLUMN 1 08 T16 4  16 60001 42 690: 305: 4885i 65i


4# 4 . .
09 ...............
T16 ............
............... 16
....
.. 2250 51 .............
.................
... 265i...
2030: ............
.................. :............
.............. 100
........
...............
..............
10....
..
...
..
............
..
...
...........
R8...........
...
.........
..........
i.......
36i.....
i...
144 9001 60 180 1801

...............
..............
..............
...............
...............
........
........
...........
..........
.......
........
i.....
..
...............
..............
..............
...............
...................
...
..............
.............
...........
i........
......
.i.
....
..
........
...................
................
........
........................
.........
...... i......
....i.........
.........
i i....
....
...............
............
...............
.I.....
........ .
..........
..............i
........
......
............... ....
.................
.... ...............
..... ......
i....
...
................
...........
..............i........
...................
...............
..............
...............
.............
...........................
..............
.....................
. ...
.......... i..........
i......
..............
i.............

...............
..............
............ ............
..............
........ i..............
............ .............
i..........
.................. :......

All  Bending  Dimeiois  are  in  accordance  %i%h J|S4466


­ Nicholas  O'Dwyer  &  Partners 
Consulting  Engineers 

. .................................
Sheet  No  .............
2 Rober  Mugabe  Road 
P.O.  Box UA  424.  Union Avenue.  Harare 
Made  By ...........................................
Telephone  702531­5 
T  lelax:  702536 
CheckefBy  ........................................
Telex:  22345  CODW YR Z W

.  ­
J oe  ......... ....... 
..............................................
................................

_..Ct.C 

­ X­­C  . . 

117r 
­­ ­ ­­ ­­ ­ _12___ __  _4s
­­
.c  ­ ­­  ­­  ­­­ 

p'V A____________cc,
I  Ifi Ct  r'­tiC  M­ ­ F 

15;C4, 

i=  4­ S4  L&


.  .ATE  P ............

* ~  -Th
3Ihrz

1  ­

R­ ­ ­­

­ ~  J~­~ 
T8e ­­Ina 

I­­ ­1  ­ . . ­ .  . .  * 
­ ..................

­ ,­.  . 
.
­.. ­ .  ­... 
:  . 

­­
..  . . ­­'  .  ­­.­
44.
... ..Z  ... .  ..  ._.. 
­
.  ..  ... 

*  1,.  7> 

a  r 
{j  I 

/Ili  u  b:(r 

12  31 
Jl.rn  i­ o  I"u  .
E4)  v*I  A 

IG  

.4t.^-a~
f

­,K.e  1O&
/1  ­+ 

­IADr­l>) 

II  oI 

Dt­LI 
4
.­ .- -- - - -
ocz  ,C  >  ­-
I - __-- _  _____
........ .~

­­­­­­ -
,­ .  _  I!  ; 
Chimoio Water Supply Project 
FinalDesign Report 

ANNEX  No. 4  

CALCULATION  FOR SIZE OF TRANSFORMER 
"L', 

­i 

r ,  :.  ,v  ­­

L,  WJ, 

­ o  ,  .  .,.  . 
Chimoio Water Supply Projec! 
FinalDesign Report 

ANNEX  No.  5 

HEADER  RESERVOIR 

STRUCTURAL  CALCULATION 
­ i  Consulting  Engineers  and  Project Managers 
Telephone  +263­4­750775/9  Telefax  ­263­4­750780 
Sheet  NO:  4007/94iC/l0l 
Made  by:  R.S.B.
Bending  Schedule  Checked  by:  A.P. 

C010  WATER  PROJECT  Date:  JULY  1994 


RESERVOIR  Drawing  Reference:  4007,'94,C'4.2 

Bar  Size  W  in  Total  Length  , Shape  ­ ­ i  ­

Member/  Section  Mark  each  N  [mm]  Code  A  B  C  D  E 


RESERVOIR  01  T12  152  152  2400  39  l170:  125::
S02  T12  307  307  2925i  20  STRi 
.. .... 
. . .. . .. . 
. .. .  . ..... ...........  .............  .... .  ............... .  . . . . . ..............  ...............  ..............  ..............  
03
.. ..  Tl2
. .  .....  ..... 253 , .  .  .......................... 
......  .............. 253 1525 ...........  .......  51
......  440
.....  ".
.............  ..............  ..............  ..............  

04 ... ....
. T12 172 .......... 172
...........  . .. . .  2525
.......  .............  . .  ...  ..  .52
. .  . . 950i
. . . .:. ..  .3751
. . .  ..  .950:
.  ... ..............  ..............  
05 T12 190 190 5675 65 5675.....
...' 06.i  ............  6............. 
fT2
..... 6 16 ...........  325
i ;  .............  4 i 6...
10:i .............. 
305; ................  60: ..........  .
2240; ............ 
. . . . .   T12.............
.....
07 16 .......... 
.....
....
16 ..........
........37...... 
1425 16 .............. 
................
...1 
....i 
... .......
SR8
. . . . .  I 
5.. ............... 88 ................ 775..
....
88
............... 61."'.....
... ..............  ...............  . . . . . . .   i.............. 
165: 165:
S ~  12 48 8 00 35 700:
10 T12  96 96 15%0 61 46i 210
11 T12 15 15 2650 61 695 550. :
....
.. .. . ... ..
12 T12.. ............ 
........  15
...  15................
............... 2875
.... ................ 61 ...... 
4001 ....... 
......... 
960 ....  ............  .............. 
. . . 
.  ...
... 
.Tl2..  14 ............... 
13...................  14 .................... 
3100 ..................  39 ............ 
1775i;.............. 
150:..............  ,..............  .............. 
....... 14 .......  .............. 
T12 
.............. 
28 
............... 
28 
..................... 
6975 
.. ....20 ................. 
STR 
. .. .. . . . .. .............. 
. ..  ..........  . 
15 . .. . ... .. . TI2
.....  ...  ..........  .I ...............  ....................  ..................  .. ..........  ..............  ,  . .  . 
96 96 1725 39 810! 175:: ....  ..............  ............. 

....... 16.......  . ......
T12. ......  ........... 
96 I.............. 
96  ... ............. 
2475 .. .  ...............  .......... 
82 810 . .;. . . . . .
210. .  . . . . . . .i.. . . . . . IF  . . . . . . 
........ 17.......  ....
.........  . ............. 
T12 16 .................... 
16 ...............  2050 ........  .......... 
35 ............ 
1850:: ;..............  .............  i .............  ............. 
18.......
...  ..  ..  ...  ... 
T12 .............  ...............  ...  .................. 
7 7 2700 .............. 
38 .  .  .  . .  .  .......  .. .....  ..............  ..............  .............. 
44 51850
....i... 
9 T12
... .............. g...... 
.......  ..................
.............  ..... .  ~  .............  ............  ..............  
15 15 3200 61 685 83
... "'................... 
S2 12
.. 16 ...............:.......... 
16
............  38
.'......
2400
'"' 
" '..
.. .....
'..
"i'..
305: 1850: 
...........  i... 
...  ...........  i... 
..... . 
.......
.. f.....
..  .............. 
.... ....... .................. 
'  .................
............  '6
i  ..
..
................................ 
...........
.. 12 14 14 3700 55 1350 . 1910;.
150:; . 150 . 
22  T12  24 24 2150 33 1860 
... 3...
. T ....... 
2  .............. 90................ 
90  ....................
2  0. ......................  ...  ...... .  ..... ..... ...... " ...............   o .........
2 T12
.... .... . T12 190 190 2000
...................56............... 56.................... 65
..................  19805 .............  ... .
.............
1650 39 810: 751. . . . .  . . . . . . .;.. . . . . . 
............... 
25 ............. 
T12 . .............. 
56 ............... 
56 .................... 
6600 .................. 
20 ............ 
STR .........  .....j..............  :
1.. ..  . . .;.. ..  . . . 
2 ....
.......... T2
.... ... 
16 . ............ 
156 ............... 
156 .................... 
1050 .. ............. 85 .  . 720
.  . .  .  ........ 185:
...... ;.............. 
50:;..............  .'.............. 
...
•...
..
1
...]
............
.. 20  20 
..................
.............
1775 
..............
g
8~  65 
6............
..........
50:
i........
......
28  TI0  4  4  1350  20  STR 
.
.  ..... ..............  ... ...........  ...............  ...................  ..................  ............  . ..............  ..............  •..............  i..............  
........ .......... 
29 
30 
TI
T12 
20
8  .......  .................. 
20
8  i........ 
1150
2300  . .........
..............  ......:. .........  i.............. ............. 
39 545i
20  STR  i.............. 
95::

...............  ..............  ..............  ...............  ........  ...........  ..................  ..........  ..............  ..............  ..............  
...............  ..............  ..............  ...............  ....................  ..................  ............  . . ... .. . ... ... .. .... . .. ... ... .  

All  Bending  Dimensions  are  in  accordance  with  BS4466 


c n;
o 0sDwyer.,&'Partners 

2 Robint  MugatI#  Road  Shiai  Noa  ......... ...........


P.O.8o0 UA  424,  Union  Aveius, Ha 
Telephone  702531.5  Madc  By  ... ..  .............
Telefee.;  107536 
: .  ...............................
. .......
:,'JOB...
....
.:.
L.
.......
..;. ......
.....
... .........
i.:. ........
.. ... .....
....
.... Ot ..........................
SECTION  .. ­­­ "-.....

....  ......  ........

v  ,1 ,  v_ T .  2  ­ .  ... 

L.  .­ R  ItsCS~~,i(£L 

---

f  1.4. 
fi­t  ' i

'F  .-.
TI 7
...  ..... . .. 
.,=p= Nicholas  O'Dwyer  & Partners 
Consulting  Eiiincei s 

2  Ro h  ­ A, , lo d 
ht S h I"  N o ­........
...... .......
...............
P 0  [l.l UA  124 0.,II  u  ­ . 11.11.0. 
r h j j 
IU,  M  ILloB y ............................
Telclai
n02!'G
Telex.  22345  COO W YR ZW  Checked  By .......................................

JO B  .. . ...
.................
.....
.........
....
......
.......
.. .. .....
......
... .. . ... Date  ............... . ....
SEC:TION  .......
kc,
......
.2., 5%  ., ,,r., ,,.,tL, ........
;.i -

J--- - -.-.

I  - "[Vt
±r~U­
j  ',.n 

47_i.­_
-kJA - _ _ _  _  _  _  _  _ 

11tt~titt ­4v­ I 

I.  _ _ _  i ,_ ,!

­ -- -. L IL
_z  iz..
. ,  .......

. . ... ..... ' S  d  __  _ 


.­ g­=  Nicholas  O'Dwyer  &  Partners 
Consulting  Engineers 
RoI
en  Mugabe  Road  Sleet  No ...  ......................... 

P 0  Son  UA  424.  Unon  Avenue,  Hifie 


T.Icyallo­,  702531.5  1..0  0D  . 
70253G 
Tcletjs 22345 
Telea  COOVW 
YR  ZW   CheCked  By  ..  ............................

JO B  ........  .q .....  ..........  Date  ...........  

T  O 
SE  ........ L.y~,  .  "'  4­l'.._____________________  
­1,

I~~~~~~  I 
__­_
~__________ 
S  jy,__  ,  .; 

F  L 

­­­­ 
­
_  IU t  5:4i J ! , , ,--
i  n   4. 
­­­....
<__  __._ 

___ 
_­I__-
­­ _ __­_­­_ 
i  i­­i­­i­L­. 
_ ­)_  _  _­f 
7?_  ­_ 
__  1__  4­
I  vI­.
_  I 
-.  . . ­_!­_..  
..  . _   1 
­

­
I _  _ [jL__._ r,
­­
-
_,.,.., 

r  ­ ­,  ­­ . ­ I 
i  i~  ­ Z 
!t  t  ­ ­ u  k~  .Z 
.) 
_____  
________.____

I  if  ,'t.,u­­..­.
-

i  I   I  i 
I ,  ,­ 

4~:1 

I l"l/  i  t 
i  / 
i l I­I­I  ......... 
_

... __._ 

L;

Nicholas  O'Dwyer  & Partners 
Consuling  Elgineers 

2 Roberi  Muq,'lhe
Road  Shect  No  . .............................
P 0  Ro.  UA  424 Unof,  Avosiuo.  Hvi"ain
1 02h'I.II  M,,,Inl|y
Tel
0 3JGl~ z ..... ....................
Te  ,:  221345
COOW YI-l
ZW  Ch, 08diksI 
By .. ... ............................

JOB ....
.......   . . .....
SECTION.....................SECION
.. ... ...
. ......
.....
.....
........ .. . .. .. . . ..... .. . . . ... .. . .... .1 . . ... .. . " ." .'
.... .... ... ......

I' I  -- _ _  __  _  _  _ 

2  ~  ~  jit ~  L  LW~ 

!.J, i 
+-" _  _-

! i! t i  x2 . ­LI­. .. -.L)C  ----- ­­ ­.-

....
._L____ . ._, _____..

T-_l-
- --_-r- - - - - I,(!t 
- I5­J  - I ....
. . ..­A 
-

, ; I - _k IL
:]-...
.L),_
L-. .. 24 
mt--i- 1,7
, /JI/1~ 11­­c. 

- '  m - -ILl,,c
- --
1 -j4  -
­..  ­ _  _  _  _  ____! 
_ _ L'L~'  _', <rL_ i

L  ­4 
I  '% ­ .  ­ ­.  -- ____-

. -
7
I,.
- ...! ,__1. ....... . .__ ... . ....
_  _ 

'i­I­­.­ o- . -
i .,....-
i i,-li l-,-rn ­.  ­ ­ -k _. _  _.
Nicholas  O'Dwyer  & Partners 
Consulting  Engineers 

2  Robet  Mugabe  Road  Sheet  No  ............................ 


P.O.  Oix UA  424.  Union  Avenuo.  Halia  
Teiephonm  702531­5  M  .do  By  ...  ..................................
...........
ToleInx  Mf25J11 
1  22:14't,  COLL)WYII  ZW Ch cked  By  ..............................................

..................... ..... ........ .


O ats .. ... ... ..
...... .... ...
JO B .......................................................................................... ...
JOB....................  .....  ....................  t  

­­­­­
1~~  ~  ~ ­ 4­ Le  ­­ -

Zic 

t  ______ 
. ­ ­_  _  _  tl ____ 

_-- ­ ­ ­ __ _  _  _  _  _  _  _  _  _  _  _  _  _

j.  7 

­ ­lii  i­F_ VT  _ 


3-, ~  _  _  _ _ 

ii~~  ~  ~  ~~~i  i  ­ iL  _  __  _  _  _  _  _  _ 

_
. T.  K  L  ­ - ­ ­ - ...... _  _  _  _  _  _  _ 

- 22_ 

L;  I  ­ _ 

L  i,  1.  1  IX  .:

­­'Ti 1iii_"­­ v  1_____  


Nicholas  O'Dwyer  &  Partners  
Consulting  Engineers 

2  Robeft Muuabo  Road  sheal No .. .


P 0.  Box UA  421,  Unon  AvosiuO.  Har3a3n
T kph o.  70 231-5 M.,do  Gy ............................................
Toicrh.  )o?2G3 
TZ e'7 22245  CODWYR  ZW  Checked  By .........................................

JO B ...................
.................................................
............................
.......................
...... D  le................
.. .............................
....
SECTION  ......
C  CI  ­ ­"4,  tv­ "A  C>.(6%  I 1 
flul ...........  . . . ................

I  hill

--0l '

_  _  'A  ­

7_1,,. .. .

­­­­­­­ .­ +  ­ cr  --
-__ _ __ 

ill~~  __  ~~I.5,4  ,1 

(­L  Li'  i  ->


...  ...  ............
Nicholas  O'Dwyer  & Partners 
Consulting  Engineers 

2 Robert  Mugabe Road  Sheel  No  ...........


.... .............................
P.O  Box UA  424.  Union  Avenuo,  Hafare  
Telephoile  702531­5   M ado By  .............................................
Toilf,,i  . 7 53
Tulux.22345 COOW Yn  ZW Checked By ...........................................

JOB  ...................................
SEC TIO N
SCTON~
~  SCV
~  ~ ¢ ~ V0
~  ~~~~....
........................
........
..... ' ..... ,...
.....-
..
...............
. . te :
..... .,,.....
l
L.) ; I  .................
r IA :  .
v  ~.

uI.. 

I I 

L!L

00A­) 

-- J . . . .. _  __...
._ _ 

­.  '
LCA­

Ji-_-

_I . ­ .  ,,.,__ __  ___  __  ___.  ___. 

-_ _  ft 
Nicholas  O'Dwyer  & Partners  
Consulting  Engineers
2  Rob  n  Muabe  loodSht  No  ......................
2  Robeil  Mugab.  RoadShaN.  ................
OF  ........
P.O.  Box  UA  424.  Union  Avenue.  Harare 
Telephone  702531.5  Miade By  .................................................

T  .a.:  22345  CODW'YFR


ZW  clhackod  By  ........................................
JOB  ........ .....
....................................................
......................... .................. .
..... Date ............................ /.,.
SECTION ".  ...... ...
......... i
a... .........................
. ....
.  -~
­
.  KC'

­
­­­­­  ­ ­  -
zL IJi
., _  ___ _  __  _  _

___________ 

;j~tzl or-F=-?
C  ­ -- r
L%­ ­ ­_  _"_ - --

.
.- . ', 10  - ­ " 
____________ 
__  _ 

-"- " ­r 

_,
iOA  W_ _, _,_______.
LA. 

1__11%  __  _____._ 

_  A___  _  _  _  _  _ 
4•

_  ~ _  _  ____  ____  ___ 


,icholas  O'Dwyer  &  Partners 
Consulting  Engineers 

2  Robett  M u3abc Road $heclNo .........................................
P0  Box  UA  424. Union  Ave nue,  Harve 
Tricphon e  70253115  Made By  .... ..............................
7elefa  x 702536 
Telex:  22345  COOWYR  ZW  Checked By ...............................................

JO .................  ... ................ W.,............

Ii  z­ i2_W  _"'$.AS___ 

_ Oz  P_  _____

.iij117iiji­i~
­­ ­

SWj
­"­­
..  _ .  . .......  
"+--

L - VI  INe~_
­ i  ­.  ­ - . . . . .  . . . .  . . . . .  . . . _  _  _  _  _ 
Nicholas  O'Dwyer  & Partners 
Consulting  Engineers 
Sheet  No  ................................
2 Robert  Mugabe  Road 
Avenue, Harare
P.O.  Box UA  424. Union 
Made  By  ............................................
Telephone 
T:I:16.:  702531­5
702536  

T  xee:22345  CODW YR  ZW   Chelked  By  .............................................

JOB ..
............... 
..........................
....................................
.. .. ...
......
....
r..,<
...........................
........
... ..... ......
........
......
..................
SECTION  ..................... iL,

_­ m  . -ffi---J"-
IA --

__
m .. 

- ­ I " - .­

,.,,/ ! 

--- ­ ­­­­­­­­­­­­­­

LiII~KI•ITIL  :m/I 

­­­­­­­­­.. _...... _:!_.__-_-__-

----
­ Nicholas 
Consulting  O'Dwyer  & Partners
Engineers 

Sheet  No  ..  ...........................................  


2 Robert  M ugabe  Road 
.f  By  . .  . . 
P 0  Bo% UA  424.  Union Avenue.  HIim
702531­S 
Taieph,or 
ChP.ked  fy ..................................  
Tele. 
JoB 22345  CODVVYR 
.....
...
J  o e  .....
ZW 
.....
......
......... ......
...........
.....
.....
.......
.....
...........
0  ,1
...... ..........
...
....
.............

"  .. .  .  .. .  .....  .......   .  ,.......................  


S  EC TION  ......  ,­ :  .... 

­.­..........  . 

CRet 

­ ___._a_. 
­ ,,  ­ "  .  ­ .  _r  ,  . 

i  i  i­­ ­t  
­ ­ ­ ­­.  -
.77±.  .. ._  __
Nicholas O'Dwyer  & Partners 
Consulting  Engineers 

2 Rol>be Mugnbe  Road  Siee  NO


p 0  Box  UA  424.  Union Avenue,Miie
Te  rphone  702531.5  .4.,d  eBy  . . .....................................
Telero. 102536  

Tlol  ZW 
2345  CO  W'VYR Ihecked  By . ................................

...
SECTION .......
. .
............... ......................
. .... ...
............. ....
.....
. I..

I  I  J 

4:­ -

­­­­­­­­­ 1-

/ .  .  ''

K 44 

_,,-____.___..,,!__
. .. __._ _

-- ,/# ­*  .i ________ 

­ .  .  - I,~~.­
._.-.. 'I ________________ 

.. . .. J .

i ii i i i -- i . . . . 1  . / _  _..

I ,,*­~­ -I _  _  __  _  _  __  _  _ 

,  /  '  / - -- * -+ - - .- s-
i. .

­ ­­­­­ ­­­­­­­ --.- t- ­ --- ,-- - ____________ 

.17i  7;  ). ., I ___ _  _ 

i -i
zi  .f...
-I----
I-
---
.- _ __--
-r Nicholas  O'Dwyer  &  Partners 
Consufting  Engineers 

2  Robefl  Mugabo  Road  5Ieyt  No  . .. ................................


P 0.  Box  U A  424.  Unon Avenue,  Hrtae
Telephone  702531.5  7.,Io  By .  
TIe:aef  702536  
T  lex:  22345  COOWYR  ZW Ch,,Ced By ..........................

JOB .............. .... ..........


... .. I.-
SECTION  i.. 
............... .. ......
..... M .  ,

- . .. . .. .. .....

[.:.-T1--I:-:t...' O 4l­.  .I~  ­ ___ 

.AV ..  " . . .

rot . 
;. .  ­ . , ,.....
Valve  .

R  "I:. "
E'. .....
,E :

6  20

­ 18a~700 

~1W. 
r  ut_ block 
1 ....'
"I I  '
INLET  PIPE­ DETAIL 
_  _  _  __.

ate  1:  5 

­H. • ' "_


­

I(
_  __,

­, .  t.
, . .. . .. . ,.....
j  Nicholas  O'Dwyer  &  Partners 
Consulting  Engineers 
A,
2  Roh.,l  M  ,  .,o  n  d  ,  No  .  ..................................  
P0  Box  UA  424  Unon  Avenuo.  HasIaje  
T.Icphorno  702531  5  .4.  yv.....................  
T.lfax  70'536  
Tel.,. 22345  COOW YR  ZW  Lh,'­c  od  By  ....  ...................................  

SECTIO N... . . . . . . .  ..  . . . . . . .   -.
JOB  .........................  .......  . .  .......................... 
..  ,.... 
1 f ' 
................. 
.........

0  .  1  I.  Overflow/Scour  pipe.­ .... 

1  ....  _  _  _  __  _  _  _  __  _  _  __  _  _  _ 

,  150  100 

25mm  4 

2 Layers  _t.Ithoid/ 

­ 4 250  ,  '"­ "  " 

S­­­­I~  DETAIL  . 
­ ­Ft­P  Scnh,,  _.__,__,_•__•
­ ­ Nicholas  O'Dwyer  & Partners 
Consulting  Engineers 

2 Roberl  Mugabe  Red 


Sheer  No  ...........  
P 0.  Box  UA 
Teieohone  424.  Union  Avenue. Hirare 
702S3l.r, 
Telepo  ne7025  311,B   Mi.  l y  .. 
................................
TeleIo.  702536 
Tela.  22345 COU)WYn  ZW 

JO 8  ............. 
SECTIO N  ...........  ..... . ­ '  ...r.   .  .........  .. . .  ....  .............  ......  . 
,,  I  '  :   ......  .  ..................  
SZC  TION-----i ­­-

.  7TWL1_ 0 

Note:   Roof  to  be  screeded  to  a 


maximum  of  75mm  and  to  12  
a  minimum  of  25mm  on  
perimeter.  

RESERVOIR  -

1  88 0c 

1186j7001 

,,0o  
oo  15   I­ Vi 21  
M"Nicholas  O'Dwyer  &  Partners  
Consulting  Engineers 

2  Robel  Mugabe  Road  SI­eet  No .  .  ............................  


P 0  8o4  UA  424.  Union  Aven.e. Hirai, 
Telephone  70253 1.5 
f.4 de By  . . ..................................
T  feoi 702536 
Tejo:.  22345  COOWYR  ZW 
(.I.... y  .d
JOB  ..........   . . . . .
... ............... 

I  C 
N  .........................   . . .  .  . .  .. . . .......... 
.  .  .  .  ..... . .....  ... .....  .  l110  .......................  .......... 
,A­­N..  .  ..  ............ 
I  I TI  I 

K­­­  ­­­­­­­­­­­­­­­,  ....  _ 

OUTLET  PIPE  DETAIL 


Sce  1::25 

- Slonr20do­­
­I  i  ­ ­

­
­

K_ 
1­, 
.-­­ ­­.
- ­ __  ­
­'  ­ ­ ­ ­_  _ 

___________________
­ _  _  _  _  _ 


_  _  _ 
~u~Nicholas  O0'Dwyer:&Rartner. 
Consu6lting!Enigineers. 
2ntihvi  M1i11tM  IOAd  ........ 
P0  IUv.IA  424.  Ur~on  Avenue,  Har14' 
TSIIVI)onp  .V 
YO53
.I..  Iif  ..........
Talefi,  7(n36
T*­1c2315C
D.l(qZ  jB 
JO  02 .. a
.............
....... J  ......
....... v

....
....
SEC  16
........

I  .  ...­- ___________________________L:__ 

I  ~~~X1
i  ~­ _  _  _ 

.  T  ____ 

1e'OF
16I­K­SFAIK  Cm  Cf  /,u  ­t.  ,  LI

c3 vI A  "'41.
­a-

wezl~o
­.  L  10 MU:4 

ACIFA
U04 ­ Sf(  1  - ­

I1.~t 

flA~. 
­I  -
_  _  _ 

1­ At(  _  _  _  _ 

k0___________ 

li­io__  I  _  _ 

%~~~~~~~AUA 
444  C 
CL AA :PO  ?44:.  Z4Z4 
­ <,  1 

7  7  7 
NihlsOT~werZ  Partners  ~~  
~ConuiIng Engineers  
ob.i.
2. ,'ad M.ug... .be :. u  .. ......................
P0  Box  UA4.24  Union  Avenue,  Hurerq 

B -JO
. . ......
. ......
SECTION  ....... ..
........ .  j.........

TThT_ 
i00mm  dec ' 
Pipe  ­ SSl
i !:l TO.. ­ ­­ ______DETA_______­­____ 
Ilosquito  gauize  ti4.  
Root  stob  .  strap  bc.!e, 
M­'vt
roud  pipe.  . 

VENTILATOR'  DETAIL­­ _  _  __ 


Scale  1:10 

I  *.. ­ ___________
___­_____

Straine~r  200 di  i4 


*~

, :
i)[i:
::,::11
::,, :..;I\
---:. : ' i].0..AC.Ppe  __.. ..
___. .....
_ ;
­4U  .

~OUTLET  PIPE  DETAIL__  __ 


Scale1  5_  _  _  _  _  _  _ 
U..Nicholaso,'wyer,
y Cansulting  Engineers  
&Part  nesK 
2  ?Y 
2 Rotwri M ugnble R  ad   ' .............................
.
P0. flue  UA474.  Usison Avenuo,  Hao  
Tolo o  702531.5  I  i  ........
Telefac  702536C)Y,  
T  x 
CO  2234 
W ...
...' ..........
....

JO 
B......
A,.......
..................S. ...........

­ 7.

p+4 L0CKlIO  DA  @EV


I1 '"  IAT P 

L  f INe
O0P  _-OA 'A  A'OL  ~j
LIGHT  DUTY  p ECTANI.~ 
H   ­L,

.L.4 OE COVER  CAST  INO  ROOF  SLA

ItoI   - _4  ­& 

*  ELEVATI[ON  OF  STAPL E._   _  _  _  _  _  _ 

PAIN  Mt.  I  EL  ANO  CAST  IRON  WORK 10  BE  ­IREC­ ­  ________________ 

COAIS SIAC9  (FOXY  
PAUSMEO  AUO l'AIMILO  TW~O
PII1  AFTE  1C  ALAItO 
AtW  . 

LJ  I  1­ t­ 4-

r  "' 

L  ­
. t"j1I 
­­­
. . .  . . . . . . . . . . .  .  . 

.  .  .. 
____ 

You might also like