Chimoio Water Supply Project FinalDesign
Chimoio Water Supply Project FinalDesign
Chimoio Water Supply Project FinalDesign
Project
FinalDesignReport
FINAL DESIGN REPORT
JULY 1994
Chimoio Water Supply Project
FinalDesign Report
TABLE OF CONTENTS
Page
1. INTRODUCTION I
4.COMPONENTS OF THE PROJECT 10
4.1. General 10
ii
Chimoio Water Supply Project
FinalDesign Report
i
Chimoio Water Supply Project
Final Design Report
8. LIAISON 37
iv
Chimoio Water Supply Project
Final Design Report
ABBREVIATIONS
CHAPTER 1
INTRODUCTIOY
Chimoio Water Supply Project
Final Design Report
1. INTRODUCTION
1.1. Background
This report relates to Water Sector Study ( Draft Report, Sept. 93 ) by the
Consultant DHV and Feasibility analysis and cost estimate, Pipe line from
Chicamba Dam to Chimoio ( Apr. 94 ) by Consultant Sheladia Ass.
The city of Cumoio is the capital of Manica Province. In 1993 the Chimoio
City Council estimates the total urban / periurban population at about 190,000
inhabitants.
The normal source of raw water for the town of Chimoio is the Mezingaze
river where water is pumped out of two interconnected reservoirs to a water
treatment plant and then distributed through distribution network. The
upstream of these two reservoirs has been destroyed in a flash flood. The
distribution network is not a part of this F.D.R. but it is worth mentioning that
about 30% of total water pumped in distribution network is lost due to the
leakage's 'i the reticulation pipes through the City.
Due to the drought of 1990/1991, the Mezingaze River has dried with hardly
any real storage capacity in the reservoir This situation is nov, repeated every
summer and AdC must completely cease operating six months a year.
During that period increasing pressure has been placed on boreholes wells to
support the entire community. Further attempts by the AdC to supply
additional water through drilled wells have not proved satisfactorily. Capacity
of these sources is very limited and in no way can be considered as having
potential to supply the entire City.
This drought has highlighted very clearly the extremely low security and the
insufficiency of the two present sources of water supply (Mezingaze River and
underground).
In response to this emergency, US Agency for International Development
(USAIDMozambique) agreed to provide finds to develop and construct an
alternative source of water supply which would better safeguard the water
supply of Chimo'o. The adequate source of raw water has been found in
Chicamba dam reservoir located 41 km from the City.
Chimoio Water Supply Project
FinalDesign Report
1.2. Project Area
The town of Chimoio is located in the Beira corridor which contains major
infrastructures such as the railway and the EN6 national road that link the port
of Beira with Zimbabwe. The distance between Chimoio and the port of Beira
is approximately 200 km.
January 240 mm
February 199 mm
March 183 mn
April 53 mm
May 14 mm
June 18 mnn
July 13 mm
August 15 mm
September 12 mm
October 36 mm
November 120 mm
December 218 mm
1.4. Project Objectives
2
Chimoio Water Supply Project
FinalDesignReport
In developing the raw water supply concept, alternative sources have been
Longitudinal sections of the pipeline
Hydraulic analysis of the pipeline
Structural analysis of the structures
Volume I:
Chapter 3. Field survey
Chapter 4. Components of the project
Chapter 8. Liaison
3
Chimoio Water Supply Project
Final Design Report
Tables and figures in this Report are numbered according to the Chapter in
which they appear. They are numbered consecutively according to mention hi
the text. Environmental and baseline studies are subjects of separate reports.
4
Chimoio Water Supply Project
FinalDesign Report
CHAPTER 2
EXISTING DATA
Chimoio Water Suvply Project
Final Design Report
Three principal series of topographic maps have been consulted. These are
available through the National Directorate of Water Affairs (DNA), the
National Directorate for Mapping (Dinageca), and the Chimoio Energy
Company (SHER/EdM).
Both the National Directorate for Roads and Bridges (DNEP) in Maputo and
the Provincial Directorate for Construction and Water (DPCA) in Chimoio
have been consulted. Both organisations were most helpfiul. However, neither
were able to provide topographic surveys of the EN6 between Chimoio and the
Messica River nor of the road from the EN6 and the Chicamba Dam.
Apparently there was a serious fire in the technical archives of DNEP some
years ago which destroyed the records.
Services should be at least 15 metres from the centre line of a major road.
However, permission may be granted for closer passage in special cases.
Route of the pipeline is crossing the major road EN6 only one place, therefore
wayleave is required only for that road crossing.
Relatively little information about soils along the pipe routes has been found.
The CPMZ topographic surveys carries some general notes about surface soil
conditions. Therefore it was necessary to execute the soil investigation along
the pipe route.
5
Chimoio Water Supply Project
Final Design Report
The following information has been provided by the Hydrology Section of
SHER, Chimoio, the operators of Chicamba darn.
Chicamba dam has storage capacity for full turbine operation (50 cubic metres
per second) during a period of three years. Water availability has not limited
power generation since the dam crest was increased in 1973, despite two
periods of serious drought. The water consumption of Chimoio is less than
0,5% of the turbine flow, a value which can be considered insignificant.
The long term plans for power generation in the Manica/Sofala region include
the construction of a substation on the Cahora Bassa power line to provide
power to the region. This will be cheaper than upgrading turbine capacity at
Chicamba/Mavuzi power scheme. There is therefore likely to be a lower water
consumption for electricity generation in the future and more storage capacity
will be available to secure the water supply for Chimoio.
Important levels (metres above sea level, masl) relevant for the design of the
intake tower are:
6
Chimoio Water Supply Project
FinalDesign Report
The observed minimum in the Chicamba Lake since the dam crest was raised in
1973 are:
1973/74 591
1974/75 613
1977/78 618
1984/85 615
1991/92 611
1992/93 609
1993/94 610
A study has been carried out of 'e probability of the occurrence of low water
levels in the Lake, this is included in the Environmental Study Report. A
resonable design level for the intake tower is 605msi.
7
Chimoio Water Supply Project
Final Design Report
CHAPTER 3
FIELD SURVEY
7k
Chimoio Water Supply Project
FinalDesign Report
Field survey has been executed for the various aspects of the Project. Due to
lack of topographic and subsoil information both investigation were executed.
The Baseline study and Environmental study are subject of separate reports
The route of the transmission pipeline has been surveyed to establish
longitudinal sections for hydraulic design. The levels along the route of the
pipeline have been established on every 50 m, and along river and stream
crossings every 510 m. Site surveying on the locations of the structures
(reservoir, intake tower and bridge and intake site) established the levels on the
grid 5 m x 5 m. Concrete bench marks are established every 500 m along the
pipe route and on every bend.
The surveying carried out under the Project is sufficient for detailed design to
be prepared. The total quantities of topographical surveying are:
All topographical survey work has been plotted and is shown on the drawings,
either as longitudinal section (transmission pipeline) or site plans (intake site,
reservoir).
3.2.1. General
The subsoil conditions for transmission pipeline route and major structures
have been investigated.
For the transmission pipeline, subsoil conditions have been investigated at a
frequency of roughly 500 m. On each river, stream crossing three trial pits have
been investigated, one in the middle and one on the each bank of the crossing.
Seismic investigation has been done on the intake sites. First location of the
intake site proved difficult for foundation construction. The alternative location
proved to be suitable for required type of structure
A total of 86 trial holes have been made, with the total excavation depth of 172
m. The full results of investigations are available in Volume II of this report.
8
LnImoio water auppiy rrojecl
FinalDesign Report
Sand
Silt
Gravel
Boulders
-Gneiss
The majority of trial holes encountered sand with varying degrees of
intermixed gravel and gneiss.
Standing ground water has been encountered in all the holes at the river
crossings and some of the stream crossings.
3.2.3. Test Results
Sieve analyses were carried out on samples taken at sites for structures, and
additionally, for selected transmission pipeline route.
9
Chimoio Water Supply Project
FinalDesign Report
An assessment has been made of the material to be excavated along the
transmission pipeline route , based on the analysis of the results of the trial
holes. The material to be excavated has been classified into:
Based on typical trench dimensions of 600 mm width, and 1150 mn to 2500
mm depth, the following indicates the percentage of each type of material
required to be excavated for transmission pipeline and intake site:
The above percentages have been used to estimate volumes of and cost 16r,
hard material and rock excavation. However, it must be stressed that the
frequency of test holes (every 500 m) prevents an accurate assessment and the
above percentages will vary during construction.
10
Chimoio Water Supply Project
FinalDesign Report
CHAPTER 4
COMPONENTS OF THE PROJECT
iOt*
Chimoio Water Supply Project
FinalDesignReport
4.COMPONENTS OF THE PROJECT
4.1. General
Raw water will be pumped from C,'icamba Lake to header reservoir on the hill
overlcoking the Lake. From the reservoir the water will be transported by
gravity to the treatment plant of the Water Company of Chimoio. In
accordance with the originul Terms of Reference the rehabilitation of the
existing treatment plant was not in the scope of this Project. However it was
agreed that if the funds are available the rehabilitation of the plant will take
place pending on the available budget.
The following components are forming the system and will be built under this
Project:
Transportable pump, which will be used when the water level in the
Lake falls under 605 m
Access road
Radio communication
4.2. Intake Tower
The location of the intake tower has been chosen in the bay of the Lake about
800m from the dam to reduce the impact of the power generation and waves.
Also it has been considered the subsoil conditions in order to minimise the
11
Chimoio Water SupplyProject
FinalDesignReport
cost of foundation for the tower. Based on the available data about design
levels and historical water levels of Chicamba Lake the intake level for the
tower has been chosen to be 605 m.
As a protection of the mechanical and electrical equipment a house will be
constructed on the top ofthe tower.
Material used for the cunstruction of the house will be 230 mm. bricks
plastered inside. Roof sheeting will be corrugated galvanised iron sheets.
Delivery pipes will be two steel pipes 300 mm Diameter encased in concrete to
prevent floating of the pipes . The slope of the pipes will be 3% in direction of
the Lake to enable back washing of the pipes. Back washing of the delivery
pipes can be executed whenever the water level in the lake is lower than
maximum level in the Lake by closing the valves on the delivery pipes, pumping
the water in the tower using a mobile pump and opening the valves on the
delivery pipes. Gate valve with 19 m mild steel spindle, gear box, bevel and
hand wheel shall be installed on the delivery pipes to allow opening and closing
from the top slab.
Minimum flow through two 300 mm steel pipes is 450m3,. Which is more than
adequate even for future extension.
4.2.3. Structural calculation
12
Chimoio Water Supply Project
FinalDesign Report
The intake tower shall be equipped with two submersible pumps (I duty, 1
standby). The pumps shall be with the following characieristics:
Q=lOOm'1h, H=180m.
Calculation of the pump
level difference:
intake level 605 m
159 m
The outlet pipe of each pump shall be provided with allnecessary nonreturn
and isolating valve. Pumps and vertical ID 250 mm steel double flanged pipes
3000 mm long will be supported with 600 mm plate welded support on the top
slab.
The intake site will be electrically supplied from a distribution sub station to
be constructed by the Electricity Company. Electricity will be available with the
following characteristics:
Distribution board and motor control panel will be installed inside the house.
The house will be equipped with 2 x 36 W 1200 mm long surface mounted
batten type fluorescent luminaires with single metal reflector.
13
Chimoio Water Supply Project
FinalDesign Report
The lightning protection system will be installed with 4 earth electrodes to
protect the equipment from lightning.
Level switches shall be provided in the intake tower and header reservoir for
the following functions:
A pressure switch shall be installed on the discharge manifold to provide cut-
out of the pumps. The pressure switch shall be adjustable and shall be set, on
commissioning, at the field established "closed valve" pressure for the pump
sets.
4.2.6. Alarms
Header reservoiroverflow
Failure of any duty motor
Visual indication of alarms shall be located on the appropriate switchboard or
instrument panel. Audible indication of alarms shall be located both in the
Intake Tower and in the Office of the Guardstore house. A siren shall also be
installed on the outside of transformer tower.
4.3.1. General
Access bridge shall be constructed as a link between intake site and the tower.
Material shall be reinforced concrete class 40. Reinforcement shall be high
tensile reinforcement bars.
14
Chimoio Water Supply Project
Final Design Report
4.3.3. Structural calculation
4.3.4. Other ancillary
Steel pipes I) 250 mm length 4000 mm internally lined and externally
protected shall be placed on the bridge fixed to bridge deck using brackets and
support brackets.
Metal fence shall be constructed 700 mm high using 20 mm Dia. bars at 125
mm central. The handrail shall be protected with thermoplastic cover.
4.4.1. General
The water in the Chicamba Lake might fall below the elevation 605 m which
corresponds to the inlet of the intake tower. It might eventually reach 585 m,
the minimum level of operation of the hydroelectric plant.
4.4.2. Civil work
The reinforced ramp, on which the pump shall be transported will be
constructed from the store room to the existing ,,'ater level in the Lake while
the execution of the Project is going on. Any extension of the ramp will be
constructed separately from this Project according to necessity and when the
water falls below this level.
15
Chimoio Water Supply Project
FinalDesign Report
The pump shall be mounted on the non roadworthy trailer. The pump shall be
following characteristics:
Flexible reinforced rubber pipes 100 mm Dia shall be connected to the pump.
The pump shall pump the water from the Lake to the tower sump during low
water levels in the Lake. To enable operation of the pump a handwinch with
the stainless steel cable shall be mounted in the store room.
4.5.1. General
I office
2 bedrooms with the lounge for the guards off duty
I sl.,wer and toilet
I storage room for the transportable pump and pipes
Material shall be brickwork plastered both sides. Roof shall be galvanised iron
sheeting. Sanitary waste from the toilet and shower shall be disposed in a septic
tank and soakaway. Water supply for the house shall be connected to the
Chicamba Township water main which crosses the intake site access road.
Sanitary wastes from the bathroom shall be disposed in a septic tank which is
connected to a soakaway.
16
Chimoio Water Supply Project
FinalDesign Report
4.6. Intake Site and Transformer Tower
4.6.1. General
4.6.2. Intake Site
The level of the intake site shall be 625.20m. To prevent soil erosion due to
wave activity the edge of the site shall be protected with 500 mm free drainage
rockfill. The wire fence 1800 mm high shall be built around the site because of
security reasons. The erosion of the slope (if it isnot rock) shall be protected
with adequate vegetation.
4.6.3. Transformer Tower
To provide the adequate power supply transformer tower shall be built as per
requirements of EdM/SHER.
Structural calculation are enclosed in Annex No 3.
4.6.3.2. Size of transformer
The size of transformer has been calculated for the worst loading case. The
adequate transformer shall be 315KVA.
4.7. Access Road
4.7.1. General
Access road shall be constructed from existing road to Chicamba Dam to
Intake site. Total length shall be 1850 m.
17
Chimoio Water Supply Project
FinalDesign Report
The route of the road shall follow the existing dirt track to the "restaurante",
after that it shall follow a direct path to the intake site. The potholes on the
existing dirt track shall be filled with adequate material and compacted to 93%
MOD AASITO. Material for wearing course shall be selected gravel
compacted to 95% MOD AASHTO.
To prevent erosion of the road on the edge of the road shall be placed free
drainage rockfill 60250 mm compacted to 95% MOD AASHTO. Drainage
channels 100 nm deep shall protect the road from water flow on the slopes.
Ground slopes shall be protected from erosion uy vegetation.
4.7.3. Culverts
Water from the slopes shall be controlled by 4 culverts which shall be
constructed on every stream, crossing the road. Culverts shall be class S culvert
pipes with 100 mam. bed and haunch placed below subgrade layer with 1:100
fall.
4.8.1. General
First 2153 m of the transmission main from the intake to the header reservoir
shall be steel pipes longitudinal welded, internally lined, externally coated, 6 m
length, working pressure 22 bars.
4.8.2. Earthworks
The pipes shall be laid in the trenches 600 mm wide, with the minimum cover
of 800 mm above the top of the pipe. When crossing the streams, including the
portion of the pipe which is going to be laid under the maximum level of the
Lake, the invert level shall be 2.0 m deep. Below the invert of the pipe 100
mm of sand shall be placed. First 200 mm above the pipe shall be sand or
screened granular material compacted to 88% MOD AASHTO.
The reminder of trenches shall be backfilled with selected granular material
compacted to 96% MOD AASIITO. Excavation shall be protected with all
necessary planking and strutting to ensure the safety of workmen.
Material to be excavated shall be divided into three classes, Rock, Hard
Material and Soft Material.
18
Chimoio Water Supply Project
FinalDesign Report
The excavation must be free of water at any time during the pipe laying and
construction of concrete structures.
Marker tape shall be placed 300 mm above the pipeline. The material for
Marker tape shall be blue PVC or polyethylene mesh or ribbon at least 50 mm
wide, incorporating a corrosion resistant tracing system.
4.8.3. Pipe Laying
Laying instruction of the manufacturer shall be explicitly followed. All pipes
shall be sound and clean before laying. When laying .j not in progress the open
ends of the pipes shall be closed by water tight plugs or other approved means.
Good alignment shall be preserved in laying.
4.8.4. Concrete Works
All coicrete and reinforced concrete works shall comply wit the following
standard specification as appropriate:
19
Chimoio Water Supply Project
Final Design Report
Washout chamber's and air valve chambers shall be placed as per longitudinal
sections. The exack position shall be indicated on site. All concrete chambers
shall be painted outi;de with two layers of bitumen. All chambers shall be
lockable.
Anchor, thrust blocks shall be placed on all the bends and at the slopes as
follows:
gradient spacing ( m)
up to I in 2 6
from 1:2 to 1:4 12
from l:4to 1:5 18
from 1:5 to 1:6 24
flatter than 1:6 not required
4.8.4.3. Marker Posts
Marker posts shall be made of precast reinforced concrete and placed 1.0 m
from central line of pipes. They shall be positioned on every bend of the
pipeline, on the straight portion every 500 m.
All valves and accessories are designed for a pressure at least equal to two
times the normal working pressure where they will be installed. As far as
possible all equipment of the same type shall be from one manufacturer and
they must be clearly marked with the name of manufacturer, flow direction
arrows and the pressure for which they are designed. All valves shall be
manually operated and open left ( counter clockwise).
20
Chimoho Water Supply Project
Final Design Report
4.8.6. Hydraulic analyses
Hydraulic calculations of friction losses for the steel pipe have been calculated
based on HazenWilliams formula as follows:
4, 7
J= 10,708 x(Q LIS2XD
J = 6,61 m
Water hammer / surge pressure is the crucial factor in the design of this
pressure pipeline, therefore the calculations are given below inclusive of water
hammer / surge pressure.
This phenomenon occurs frequently in pressure pipelines and is defined as the
periodic pressure oscillation which move back and forth along a pipeline. The
phenomenon occurs when closing and opening valves, starting and stopping
pumps or when any other operating condition changes in the pipeline.
21
Chimoio Water Supply Project
FinalDesign Report
The size of pressure oscillation after a valve closure depends on the time it
takes to close the valve, and on the so called reflection time of the pipeline. If
the flow is cut during a period shorter than this reflection time the
maximum pressure increase may be calculated by use of the following formula:
H = Cp xx
g
To 2L
Cp
In the case of having a longer valve closing time than the reflection time of
the pipeline, the pressure increase is lower than the calculated in the above
formula.
Steel pipe ID 250 mm Wall thickness 4,8 mm; Q = 27,78 Vs;
Vo = 0,7 Js; Static head = 159 m; Friction losses = 6,61 m;
Length L = 2050 m =>
In order to avoid installation of some form of water hammer protective device
to reduce pressure, because of high operational and maintenance cost, steel
pipe is accepted. The reflection time is very short therefore the pressure
increase should be lower than calculated in the above formula.
22
Chimoio Water Supply Project
FinalDesign Report
Due to high risk of water hammer and to avoid installation of water hammer
protective device to reduce pressure, the material for pressure main has been
designed to be GRW longitudinal welded pipe to SABS 719 Gr. B. 250 mm
internal diameter, wall thickness of 4.8 mm.
The main concern regarding the use of steel pipe is corrosion. The long
continuous lengths of welded steel pipelines increase the opportunities for
corrosion to develop. Welded joints are a potential source of increased
corrosion risk due to difficulty in applying protection after welding. Corrosion
of steel pipelines does not generally cause catastrophic failure, rather a
progressively increasing loss of water through leakage.
To protect steel pipe from corrosion pipes shall be internally lined with smooth,
dense, centrifugally spun cement mortar lining. External corrosion protection
shall be with fusion bonded low density polyethylene in thicknesses from 2.0 to
3.0 mm or similar approved by the Engineer on Site.
The pressure in the pipeline shall be raised steadily until a pressure of 1,5 times
the operating pressure is reached in the lowest part of the section, and the
pressure shall be maintained at this level for a period of one hour. The pumps
shall than be disconnected and no fuither water shall be permitted to enter the
pipeline for the further period of one hour. At the end of this period the original
pressure shall be restored by pumping and the loss measured.
The permissible loss in all welded steel pipeline shall not exceed 0.1 litres per
mm of pipe diameter per kilometre of pipe per 24 hours for each 30 m of test
head. In uPVC pipe the permissible loss shall not exceed 2.0 litres per metre
nominal bore per kilometre length per metre head ( calculated as the average
head applied to the section ) per 24 hours.
At the conclusion of pipelaying flushing out of the pipeline shall be executed.
Disinfection of the pipeline shall be carried out using chlorinated raw water
from Chicamba Lake. Residual of not less than 20 mg/l of free chlorine shall be
acceptable for the structures. For the pipeline a residual of at least 20 mg/I for a
period of 2 hours shall be acceptable.
23
Chimoio Water Supply Project
FinalDesign Report
4.9 Header Reservoir
4.9. 1. General
The header reservoir will be located on the hill overlooking the Chichamba
Lake at the elevation 762 m. The head will be enough to carry the water by
gravity to the treatment plant of Chimoio. It is not going to be a storage
3
reservoir only a pressure break tank, therefore the capacity will be 100 m .
The primary function of this reservoir is to protect the gravity main from
overpressure by breaking the head created by the submersible pumps in the
Intake Tower. This head depends on the water level in the Chicamba Lake,
which can vary by 20 m. The secondary function of the reservoir is to protect
the gravity main from water hammer caused by intake pumps and to reduce the
effect of water hammer at the pressure main.
The reservoir shall be built in the ground 1.0 m below original ground level. At
the bottom level of the reservoir sludge disposal pipe with the valve shall be
installed. Raw water has been taken from the Lake so settlement already took
place. The quantity of sludge will be minor. Sludge shall be disposed in the
channel filled with free drainage rockfill to allow soaking of the sludge in the
ground.
On the top slab three ventilation pipes shall be installed and entrance for
maintenance of the reservoir. Entrance shall be covered with cast iron manhole
lockable cover.
4.9.3. Structural Calculation
Level switches shall be installed in the reservoir to control the intake pumps.
Item 4.2.4. refers. The outlet pipe shall be equipped with the gate valve in case
of maintenance of the gravity main.
24
Chimoio Water Supply Project
FinalDesign Report
4.10 Gravity Main
4.10.1. General
The pipeline between header reservoir and the treatment plant will be
constructed in 200 mm and 250 mm diameter unplasticized PVC pipe in class
6,9,12,16 and 20 according to hydraulic gradient and altitude.
4.10.2. Earthworks
The banks of all the riverstream crossings shall be protected with wire mesh
gabions 400 mm thick. The pipes crossing the rivers and streams shall be
encased in concrete to prevent possible erosion during rainy season.
4.10.3. Pipe Laying
4.10.5. Valves and Accessories
4.10.6. Hydraulic analyses
Hydraulic calculation are based on the formula first developed by Blasius for
smooth pipes, based on the premise that for smooth pipes the friction factor is
solely dependent on the Reynolds number. The formula is as follows:
25
Chimoio Water Supply Project
Final Design Report
Vxd
Re=-
q18
From the flow chart which is based on the above mentioned formula friction
losses for different classes of pipes for the required flow Q=27,78 Vs are as
follows:
The highest point ( level 691.99 m ) on the gravity main is at km 28.675 from
the header reservoir. In the table below is shown the friction losses from the
reservoir to that critical point on the entire gravity main. When considering the
classes of the pipes in addition to the level difference between high and low
points on the pipeline the possible water hammer is taken into account.
26
Chinoio Water Supply Project
Final Design Report
27
Chimoio Water Supply Project
Final Design Report
H
28
Chimoio Water Supply Project
FinalDesignReport
engineering plastics and is therefore most commonly used in load bearing
applications such as pressure pipes. !. has other features such as: low specific
gravity, good chemical and weather resistance, very smooth bores and the long
term flow characteristics vary very little from those of newly laid pipes.
Storage of pipes must be executed strictly in accordance with manufacturer
recommendation. It is essential that pipes are stacked with the socket and
spigot ends alternating and with the sockets projecting so that there is a barrel
to barrel contact along the lengths of pipe. During storage all pipes must be
protected from ultraviolet light.
29
Chimoio Water Supply Project
FinalDesign Report
CHAPTER 5
OPERATION & MAINTENANCE
Chimoio Water Supply Project
FinalDesign Report
5. OPERATION & MAINTENANCE
Agua de Chimoio is responsible for all water supply system in Chimoio. The
water supply scheme is uncomplicated and easy to operate and little planning is
done. Even when there is enough raw water ( only 6 months a year ) operation
of existing equipment is complicated due to lack of spare parts and necessary
tools. The major problems for operation and maintenance can be summarised
as follows:
These and other problems are reflected in the actual condition of system. About
40 % of the pipe network is estimated to be in poor condition. Although the
distribution network is not in the scope of this Project rehabilitation work is
required.
Based on the existing 0 & M problems proposal for efficient 0 & M for the
extended system relate mainly to:
Intake site at Chicamba Lake
Pressure main
30
Chimoio Water Supply Project
Final Design Report
Gravity main
31
Chimoio Water Supply Project
FinalDesign Report
CHAPTER 6
Construction programme and cash flow are based on the commencement date
15/09/1994. The Christmas Holidays have been included in the Construction
programme from 16/12/1994 to 02/01/1995. If the project implementation
starts on any later date the construction programme has to be modified.
32
6.1. Construction Programme
DESCRIPTION 15/09/94 15/10/94 15/11/94 16/12/94 02/01/95 15/01/95 15/02/95 15/03/95
Mobilisation
Access Road
Intake Tower
Access Bridge
Transformer Tower 0
GuardStore House
Reservoir Site
River Crossings
ElectroMechanical Works
Testing
. LoCommisiorning
/
, .. : 31/11
6.2 Cash Flow iE m o n t hl yT
M cumulative
6000000-
5072013
5000000- 4566253
3790220
4000000- 3238330
3000000-
2000000-
97369 7741174779490 760
1000000- 46109251255
99 31/2
t7"Tc:
Chimoio Water Supply Project
FinalDesign Report
CHAPTER 7
CONFIDENTIAL COST ESTIMATE
Chimoio Water Supply Project
Final Design Report
total 1 505,000
total 2 2,027,933
33
Chimoio Water Supply Project
FinalDesign Report
total 3 727,926
total 4 15,000
total 5 117,475
34
Chimoio Water Supply Project
Final Design Report
total 6 277,679
total 7 48,854
total 8 124.844
35
Chimoio Water Supply Project
Final Design Report
total 9 81,210
36
Chimoio Water Supply Project
Final Design Report
TOTAL 5,072,013
37
Chimoio Water Supply Project
Final Design Report
CHAPTER 8
LIAISON
1?)
Chimoio Water Supply Project
FinalDesignReport
8. LIAISON
During the design stage of the project (phase I) Consultant maintained close
contact with the relevant Officers of the following National and Provincial
Directorate:
National Directorate for Mapping (DINAGECA)Maputo
Ministry of FinanceMaputo
Ministry of HealthMaputo
City CouncilChimoio
Manica Provincial Government
SemocMozambique
38
Chimoio Water Supply Project
FinalDesign Report
CHAPTER 9
PROJECT RISKS AND CONSTRAINS
Chimoio Water Supply Project
Final Design Report
9.1. General
As apart of the services offered under this Project, the Consultant will assess
the possible risks to and constrains on Project execution and sustainability.
At this point in the Project some general risks and constrains are foreseen.
These are listed below and shown the reasons for the existence of the risk (or
constrain) ,ndthe measures for avoidance or reduction.
Water level in the Chicamba Lake isat the moment the lowest for the last 20
years, therefore the construction of the intake tower, delivery channel and
intake head strutue will be cheaper and should be finished before the rainy
season starts.
To avoid this delay the finance construction should be closed as soon as
possible to enable the Contractor to start construction immediately after letter
of commencement isissued.
The Consultant strongly recommends that DNA, DPCA, AdC and Chimoio
Town Council acquaints itself with the respective sites and required wayleave,
and formally approaches the Land Boards with a view to securing the required
sites and wayleave.
Although no official information received by the Employer indicates the
presence ofmines on the Site, the Consultant recommends that due precautions
and investigation to be taken before commencement of work specially on the
hills overlooking the Lake where the header reservoir shall be built or in the
area around that location.
39
Chimoio Water Supply Project
FinalDesign Report
The inadequate system maintenance can cause the unsustainability of the
installed system.
To avoid that it is essential to establish the realistic operational and
maintenance requirements and appropriate tehnology.
9.3. Minor Risks
During soil investigation trial pits were excavated 500 m spaced, there is a
possibility of occurrence of the different material between the investigated trial
pits, which might caused the redesign of some components of the system.
Close monitoring of subsoil conditions is required by the Engineer on Site
during the excavation in order to do the necessary amendments of drawings if
conditions differs from original design.
The failure might occur if there is inadequate system maintenance leading to
high losses.
To reduce or avoid possible high losses of the system it is essential to establish
realistic operational and maintenance requirement as well as to equip the AdC
to fulfil their obligations.
40
Chimoio Water Supply Project
FinalDesign Report
INTAKE TOWER
STRUCTURAL CALCULATION
/AZ
Consulting Engineers and Project Managers
Telephone +2634750775/9 Telefax +2634750780
Sheet NO: 4007194;C'104
Made by: AP
Bending Schedule Checked by: ,,P
CHIMOIO WATER SUPPLY PROJECT Date: JULY 1994
INTAKE TOWER Drawine Reference: 14007/94JC.2. 1.t
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i. . . . . . . .i . . . . . . . . . . . . . . i. . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ; . . . . . . . ............. .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ... . . . . . . . . . . . . . . . . . . . . . . . . . . .
..................... ............................ ............... ................. .............. ............
! i......... i...... .....
. . . . . . . ........... ................ ............... .................... . . . . . . . . . . . . . . . ... . . . . . . . . . . . . . i.............. . . . . . . .
............... ....... .................... ............... .................. ............... ............ ........... ......... ....... i....
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i..............
...............
..............
..............
...............
..................
...............
.........
............
.........
i......
i....
................
..............
..............
...............
. ;.........
..................
...............
............
...........
.......
i.....
. . . . . . . . ..............
..............
. . . . . . . . . . . . . . . . . . . . . . . . . . . ............
i. . . . . . . i. . . . . . . i. . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
...............
..............
.............
...........
..........
.........
.......
......
.....
....
...
............... .............. .............. ............... .................... .................. ............ .............. .............. .............. ..............
...............
..............
..............
...............
...............
.............
...........
.........
!.......
!.....
i...
......
.............
............
.........
...........
..............
S........I........6.......
........
........
Consulting Engineers and Project Managers
• ] Telephone +263475077519 Telefax +2634750780
Sheet NI: BS 106
Bending Schedule Made by:
Checked by:
R.S.B.
RSB.
AP.
CH.IJOIO WATER SUPPLY PROJECT
Date: JUNE 1994
INTAWE HOUSE ABOVE INTAKE TOWER
Drawing Reference: 007,94,C :.13
...... .......................................................
...................
............... ............ ............... ................
............ ....
....... .... . . . ................ .................
.............................
. . ............
. ............
27 T20 3 6
.............
..............
. ..............l ....-
..
... i.............
::
.............
1400 99C 4
...............
......... . ... . .......... . . . .
..............
.............
26
................
.............
....................
.................
T16
.........
...............
I ...........
..............
A.BC 0ZOO20 7.5.d i.......
2 4 ...........
............ 120 60 200: 2750: i i:k:L C
...............
...............
........
..........
.................
........
.......... ..........
....... T12
2)8 ........ 2
.. .....................
4 ......
1550 60 200; 450:
..............
29 ...........................
T12 1 ...... ........ ..........................
......
2 1200 60 2CC: 2'75S
.........
......
..............
............ .......... . ......................
................ ............
..............
1..............
..............
..........
COLUMN 29 T16 4 16 4825 37 4700iU
4# THUS 30 RB 32 128 775 60 150: 150:
..
..............
.......
.......
................
............
....................
.......
.............
..................
.......
............ ......................
.............
............... .................
i..............
...........
............... .............. ............. .... . . . . ...
.............. .............. .............. ..........
......... ................... ............. ............................. .............
.....
........
.... .................
.................. .......... ................... ..............
...............
...........
........ .................... .................. .......................... .............. ...............
............... ............. ............. .............. ........ .......... ............................... .......................................... ............
All liel.......................
........... cu.................446
dA
-,r Nicholas O'Dwyer & Partners
Consulting Engineers
iI ,_
J I ~ ______I____
-'-
--
i---;--- , -.... __,,_..__ .. ______ ___.._
,__
_ _ _ ! [ . . - !_.-J:
iz~itzti~ziz~
1 ~ ~I ________________________7__
.lr Nicholas O'Dwyer & Partners
Consulting Engineers & Parners
4
IT7
, l"- ----- -2
1
_4_ _ -.
_--___-__-- _____
t-L -
-1-1
I I
LAMONT Consulting Engineers
Page :
Job No.:
10.1/20
Chimoio Water Supply project Made by: ap
rc cant. slab Date
30 /07/94
rc design checked:
Materials:
Concrete fcu = 40 N/mxn2, Steel fy = 460 N/mm2
REINFORCEMENT:
Bending:
Bottom:
Shear:
Shear Stress: v = 0.23 N/mm2, vc = 0.82 N/mm 2
No Shear reinforcement required !
Design at 294 mm from Cl for 0.0 kN, v = 0.00 N/mm2
Asv = 0 mm2/m
Provide 0 legs R 0 at 0 mm --> Asv = 0 mm2/mCurtailment:
j< 0 mm >j<--- 0 Links R 0 --->
0 mm ----------- >1
l r Nicholas O'Dwyer & Partners
Consulting Engineers
-- __
'C
_ __ _ _ _ _
Nicholas O'Dwyer & Partners
Consulting Engineers
SEO N
SECT ION ...
. oe
V~>
......
...................
.......
.........
.
, ."..
. ..........................................
... .
..... m . . . .
...
.......
............ ............
S-.
..... _-
Tt I I
_ ._ . ,,_-,_ _ -_ _, L-~
_.,,
ffI I 1 1 _ _ _ _ _ _ __,..r L
! .__t_ - "_--__ _. _,,_,. _
,- !- --
-!-
--- -,- - -!- ,. ,.-
!!iT
]IlI--f7..... .. - " .....- -
I .
Nicholas O'Dwyer & Partners
Uf Consulting Engineers
I -
"
7)' .Fv2
r
_ _ _ _ _ _ _ _ _ _ _
i I.. _ ,, a...jj!
I
K
_
~~ - __
r- __ _ __ __
. ,.I
I I i _ _ _ _ _ _ _
~ ~ ~ ~ K______
L I : I ______________________________
1 !2
Kt _ _ _ __/_
....
I _ _ .___ _ _ __--
*tr Nicholas O'Dwyer & Partners:
Consulting Engineers
2 Robert Mugabe Road + 0
,........ ..
P.O. Box UA 424. Union Avenue, Harare
Telephone 702531.5 ,,A e By .. ..................................
Telefax: 702536
Telex: 22345 COOWYR ZW -cked Bv .................................
JOB ........................................................................
.....
SECTION. A-......! .
... . . . .A-
+--
c - _ _ _ _ _
IC~ INA_"
I ______
P~ ~ ~ .
L"L _ ____
• ir Nicholas O'Dwyer & Partners
Consulting Engineers
JOB ...............................................
..................... ...
...............................................
Jh _
4A (P
,. o___ _ _ _ _ _ _ _
) i .N
"~ C
J[ i i -
A/
i tz i zz . i
L
_
U71 __i
_ -,___ _ _________.
--- 1j
T
Nicholas O'Dwyer & Partners
Consulting Engineers
SECTION f..................
__ I. _ _ _ _
1 --
[_ _ _
~~~., _ IG
II I _ _ _ _ _ _ _ _ _ _ _
LI2~If~~7II(Do I ___"__
o -- I
"---,--_-
~ijI IT-
, i.. __ __ _•
. _ _
_ __ _ _ _ _ _j T
Nicholas O'Dwyer & Partners
Consulting Engineers
...
.... ............ .....
SECTION ...................................................................
.............
1C
1 1+
,I L!
Nicholas O'Dwyer & Partners
Consulting Engineers
~ I J _ _ _ _
4>' it -
_ ___I _
7-
7__ - _ _ _ _ _
I ..
Nicholas O'Dwyer & Partners
Consulting Engineers
Shee No ..........................................
2 Robert Mug a e Road Avenue. Hartre
Union
P 0. Bo xUA 424 Made By ....... .......
........
Telephone 702531 .5
702536 ........................
Y .. . . ..........
Telefax e
Ch ockB
x : 2 2345 CC DWY R Z W
Te le
X;( 0 ...........
8 ..... .. .....
.....
..............
......
.............................. ......
. .... ... ...
...... ......
r . ... ...........
SECTION
~r
I F _________....___
_ _ _ _
_ _ _ _
W' e, e _ I ____________
SI
________________
, CJ
• i
I 1 T
__"
4I
__________'_J
-,
I
* T-
;
' .' ' ____ __ I ' __ _ __ _ _ _ __ _ __ _ __ _ __
____,_,__________
i , i I 1,1 i- --
I
H ____________
___ _ _ _ _ _
u' i _ _ _ _ _ _ _ _
77
1AJ I~ ____________
L , !JZ! I
+ / 7 x J a'J
* IF _______7__
Nicholas O'Dwyer & Partners
Consulting Engineers
" I
_ _ _ _ _ _ _ __-
.. i
I
ia:~ {~
.... ____
i! I ~ t'-~ -
___
___ ___ ~ ~ ___ ___ ___ ___
] I L .!~i ~ ___ ~-
' 2' C _________
I I .-
1 I l ' I
77.i m V T ]__ _ _ _ _
9 I [ r]- .. . .
_ _ _ _ ~ j 2
~t~v I_ _ _ _ _ _ _ _ _ _ _ _ _
Nicholas O'Dwyer & Partners
Consulting Engineers
; : IL_ _2 I
4
Ii. '
1
I ~
)~
: '' t ,''/ L S-
__:_ _ ____________
1~2CCe
*Nicholas O'Dwyer & Partners
Consulting Engineers
J O B 0.............................................................
...... ............
...............
..............
........... Date ...............
... ..............................
... q ,
V 77
"V; iA
11
, ,I ,IP,4 I J I
I , .
T____ i" II 1
=1r Nicholas O'Dwyer & Partners !
Consulting Engineers
' I I ______________________________
~i I _ _ _ _ _ _ _ _
I iI
1
ip, , _ _ _
I u
; r_
_______
f
, i t.' 0 . 4 57c
_ _ _ _ _ _ _ _ _ _ _ _ !IL I I _ _ _ _ _ _ _ _ _ _ _ _
..i i
1 1_ 7L
r7.'
!r I
_ A _
AAA
. "
_ _
c~xi/.'/ ,g c , 1 ,
_
' Ii
_
_____________________________
0;
_._,_. PcZ
Ii___________________
J OB ...
......
............ ..... . .....................................
SECTION .
Wi I
I -_L _ _ _ _ _
15 7
ff
SECTION
JOB .,.. ......................
. .y............
.. . ..................... g
0.)......................Dae ..................... .....
.......
R ...........................
: izi
__ _ _ _ _
CC
Ij ____
- - - ~
Chimoio WaterSupply Project
FinalDesignReport
ACCESS BRIDGE
STRUCTURAL CALCULATION
Consulting Engineers and Project Managers
Telephone +263.475M75S9Tclefu +263475750
T.U .......
.......
.......
I....
....
.. ... ........... .... . ............... ...... ... . ... :... .
.....
o,.....
.......
.............
Telex: 22345 CODWYR ZV
...........
wc ...........
......
......
.........
t:h.cked By .......... . ..................
m.n o
Ci+6"Z"
03..........~ t c v.
. . .........................................
FT I
. r . ,-- -
IF -T
~
J!4A
LL -a. ge
'I
I.
_ _ _ _ _ _ _
.......
. . ..........
... .............
R. .................
.
A I___
W , y1
Ntt
[t. .___.. __
-Mir= Nicholas O'Dwyer & Partners
Consulting Engineers
2 Robert Mugabe Ro4.d No .......
.;I,!el .................................
P.O. Box UA 424. Union Avenue. Herare
Telephone 702531.5 Made By ... ......................................
Telefax: 702538
Telex: 22345 CODWYR ZW Ch,.thedBV ... ..................................
JO B . ...............................................................................................................
. ae ..............................
Sr
~1,4
.4A.
..
Aik
-_ _ _ _ _ _ _
_ _. ___ _ _ __ _ _
---------------
vfi4zi
ur Nicholas O'Dwyer & Partners
Consulting Engineers
I _
eir Nicholas O'Dwyer & Partners
Consulting Engineers
p 5
T--
T ~ "
T " J . .
IL~O ILO~
O,4O~
8
I
/ I K
-A ~<
O(cc ____________________
Scd4r
LAMONT Consulting Engineers
Page
.11,) No. : 1031/20
Chimoio Water Project Made by: jf
Bridge Date : 06/07/94
nax field moment checked:
REINFORCEMENT:
Bending:
Bottom: requ.: As 2529 mm' -
Shear:
Shear Stress: v = 0.81 N/mm', vc 0.72 N/mm'
Design at %6000 mm from Cl for 144.4 kN, v 0.7U {1/mrO'
Minimum Links:' Asv = 552 mm'/m
Provide 2 legs RI0 at 275 mm Asv = 571 mm'/m
2 ..
i... , ...
7-S !/
Jimicnolas u'uwyer & Fartners
Consulting Engineers
2 Robert Mugabe Road
Shevl No ...........................................
P.O. Box 702531.5
Telephone
Telephon UA 424. Union Avenue, Haaie
70253 1. aM,e B ....
. .......................................
. . . . . . .
Talefax 702536
Telem 22345 CODWYR ZW
CI nh By ........................
JO B ...................................... .... . ................... .
........... ...... Date ............ ............ ....................... .
SECTION'........ .. t ............... ....... ..................
.. ' ...... .... ..... ... .. ...
KIz
l ..
_ __,_,_,_,_._....
SI
it%
tlt __ La__.
I . "-
-,WF Nicholas O'Dwyer & Partners
Consulting Engineers
o '
JOB ...........................
......
.... .... .... ... . . .................. .................
u,,e . ...... ............
.........
L 1__ ___
Tr9
I
ci:
I 4 _ _ _ _ _ _
r 41k
WI
I I _________________________"
II~iKT ~ i _______
,, -C;., --
7 iIi
..
.....
"
* INicholas O'Dwyer & Partners Consulting Engineers
I I L o 1
zlz) I .u
I II I
_____ ____ ____ ____
C
a*2
0"t
I I
Ti,, A __
...... Date.......................................
.......................
JO B .................................................................................................
.......
................
...............................................
S EC TION ......................................... .
.................................
Ref...................
--
1%1
I I i iI
f i'
zv !12i
.... ,
'
,
'~~~ C?, -D
I t' IL' I I i J T
' !Jj
il~Te I ;!"
SIl- -
TM
!A I !
Chimoio Water Supply Project
Final Design Report
ANINEX No. 3
TRANSFORMER TOWER
STRUCTURAL CALCULATION
Consulting Engineers and Project Managers
- Telephone +2634750775/9 Telefax +2634750780
Shcul NO: 4007/94/C/lu2
04 .....
.........
T12 .......
2 ............
12 2000 ...... 20
.............
"."...................
2000: ................
....................
..............
...............
05 ...............
..............
..............
............
R8 ........
..........
.......
.....
,.. 11 66 1000 60 230; 180::
...............
..............
..............
...............
...............
........
........
...........
..........
.......
........
i.....
..
...............
..............
..............
...............
...................
...
..............
.............
...........
i........
......
.i.
....
..
........
...................
................
........
........................
.........
...... i......
....i.........
.........
i i....
....
...............
............
...............
.I.....
........ .
..........
..............i
........
......
............... ....
.................
.... ...............
..... ......
i....
...
................
...........
..............i........
...................
...............
..............
...............
.............
...........................
..............
.....................
. ...
.......... i..........
i......
..............
i.............
...............
..............
............ ............
..............
........ i..............
............ .............
i..........
.................. :......
. .................................
Sheet No .............
2 Rober Mugabe Road
P.O. Box UA 424. Union Avenue. Harare
Made By ...........................................
Telephone 7025315
T lelax: 702536
CheckefBy ........................................
Telex: 22345 CODW YR Z W
.
J oe ......... .......
..............................................
................................
_..Ct.C
XC . .
117r
_12___ __ _4s
.c
p'V A____________cc,
I Ifi Ct r'tiC M F
15;C4,
* ~ -Th
3Ihrz
1
R
~ J~~
T8e Ina
I 1 . . . . . *
..................
"
,. .
.
.. . ...
: .
.. . . ' . .
44.
... ..Z ... . .. ._..
. .. ...
"
* 1,. 7>
a r
{j I
/Ili u b:(r
12 31
Jl.rn i o I"u .
E4) v*I A
IG
.4t.^-a~
f
1
,K.e 1O&
/1 +
IADrl>)
II oI
DtLI
4
. .- -- - - -
ocz ,C > -
I - __-- _ _____
........ .~
-
, . _ I! ;
Chimoio Water Supply Project
FinalDesign Report
ANNEX No. 4
CALCULATION FOR SIZE OF TRANSFORMER
"L',
i
r , :. ,v
L, WJ,
o , . .,. .
Chimoio Water Supply Projec!
FinalDesign Report
ANNEX No. 5
HEADER RESERVOIR
STRUCTURAL CALCULATION
i Consulting Engineers and Project Managers
Telephone +2634750775/9 Telefax 2634750780
Sheet NO: 4007/94iC/l0l
Made by: R.S.B.
Bending Schedule Checked by: A.P.
04 ... ....
. T12 172 .......... 172
........... . .. . . 2525
....... ............. . . ... .. .52
. . . . 950i
. . . .:. .. .3751
. . . .. .950:
. ... .............. ..............
05 T12 190 190 5675 65 5675.....
...' 06.i ............ 6.............
fT2
..... 6 16 ........... 325
i ; ............. 4 i 6...
10:i ..............
305; ................ 60: .......... .
2240; ............
. . . . . T12.............
.....
07 16 ..........
.....
....
16 ..........
........37......
1425 16 ..............
................
...1
....i
... .......
SR8
. . . . . I
5.. ............... 88 ................ 775..
....
88
............... 61."'.....
... .............. ............... . . . . . . . i..............
165: 165:
S ~ 12 48 8 00 35 700:
10 T12 96 96 15%0 61 46i 210
11 T12 15 15 2650 61 695 550. :
....
.. .. . ... ..
12 T12.. ............
........ 15
... 15................
............... 2875
.... ................ 61 ......
4001 .......
.........
960 .... ............ ..............
. . .
. ...
...
.Tl2.. 14 ...............
13................... 14 ....................
3100 .................. 39 ............
1775i;..............
150:.............. ,.............. ..............
....... 14 ....... ..............
T12
..............
28
...............
28
.....................
6975
.. ....20 .................
STR
. .. .. . . . .. ..............
. .. .......... .
15 . .. . ... .. . TI2
..... ... .......... .I ............... .................... .................. .. .......... .............. , . . .
96 96 1725 39 810! 175:: .... .............. .............
....... 16....... . ......
T12. ...... ...........
96 I..............
96 ... .............
2475 .. . ............... ..........
82 810 . .;. . . . . .
210. . . . . . . . .i.. . . . . . IF . . . . . .
........ 17....... ....
......... . .............
T12 16 ....................
16 ............... 2050 ........ ..........
35 ............
1850:: ;.............. ............. i ............. .............
18.......
... .. .. ... ...
T12 ............. ............... ... ..................
7 7 2700 ..............
38 . . . . . . ....... .. ..... .............. .............. ..............
44 51850
....i...
9 T12
... .............. g......
....... ..................
............. ..... . ~ ............. ............ ..............
15 15 3200 61 685 83
... "'...................
S2 12
.. 16 ...............:..........
16
............ 38
.'......
2400
'"'
" '..
.. .....
'..
"i'..
305: 1850:
........... i...
... ........... i...
..... .
.......
.. f.....
.. ..............
.... ....... ..................
' .................
............ '6
i ..
..
................................
...........
.. 12 14 14 3700 55 1350 . 1910;.
150:; . 150 .
22 T12 24 24 2150 33 1860
... 3...
. T .......
2 .............. 90................
90 ....................
2 0. ...................... ... ...... . ..... ..... ...... " ............... o .........
2 T12
.... .... . T12 190 190 2000
...................56............... 56.................... 65
.................. 19805 ............. ... .
.............
1650 39 810: 751. . . . . . . . . . . .;.. . . . . .
...............
25 .............
T12 . ..............
56 ...............
56 ....................
6600 ..................
20 ............
STR ......... .....j.............. :
1.. .. . . .;.. .. . . .
2 ....
.......... T2
.... ...
16 . ............
156 ...............
156 ....................
1050 .. ............. 85 . . 720
. . . . ........ 185:
...... ;..............
50:;.............. .'..............
...
•...
..
1
...]
............
.. 20 20
..................
.............
1775
..............
g
8~ 65
6............
..........
50:
i........
......
28 TI0 4 4 1350 20 STR
.
. ..... .............. ... ........... ............... ................... .................. ............ . .............. .............. •.............. i..............
........ ..........
29
30
TI
T12
20
8 ....... ..................
20
8 i........
1150
2300 . .........
.............. ......:. ......... i.............. .............
39 545i
20 STR i..............
95::
............... .............. .............. ............... ........ ........... .................. .......... .............. .............. ..............
............... .............. .............. ............... .................... .................. ............ . . ... .. . ... ... .. .... . .. ... ... .
v ,1 , v_ T . 2 . ...
L. . R ItsCS~~,i(£L
---
f 1.4.
fit ' i
'F .-.
TI 7
... ..... . ..
.,=p= Nicholas O'Dwyer & Partners
Consulting Eiiincei s
2 Ro h A, , lo d
ht S h I" N o ........
...... .......
...............
P 0 [l.l UA 124 0.,II u . 11.11.0.
r h j j
IU, M ILloB y ............................
Telclai
n02!'G
Telex. 22345 COO W YR ZW Checked By .......................................
JO B .. . ...
.................
.....
.........
....
......
.......
.. .. .....
......
... .. . ... Date ............... . ....
SEC:TION .......
kc,
......
.2., 5% ., ,,r., ,,.,tL, ........
;.i -
J--- - -.-.
I - "[Vt
±r~U
j ',.n
47_i._
-kJA - _ _ _ _ _ _ _ _
11tt~titt 4v I
I. _ _ _ i ,_ ,!
-- -. L IL
_z iz..
. , .......
T O
SE ........ L.y~, . "' 4l'.._____________________
1,
I~~~~~~ I
___
~__________
S jy,__ , .;
F L
.
_ IU t 5:4i J ! , , ,--
i n 4.
....
<__ __._
_
___
_I__-
_ ____
i iiiL.
_ )_ _ _f
7?_ _
__ 1__ 4
I vI.
_ I
-. . . _!_..
.. . _ 1
_
I _ _ [jL__._ r,
-
_,.,..,
r , . I
i i~ Z
!t t u k~ .Z
.)
_____
________.____
I if ,'t.,u...
-
i I I i
I , ,
4~:1
I l"l/ i t
i /
i l III .........
_
... __._
L;
I
Nicholas O'Dwyer & Partners
Consuling Elgineers
2 Roberi Muq,'lhe
Road Shect No . .............................
P 0 Ro. UA 424 Unof, Avosiuo. Hvi"ain
1 02h'I.II M,,,Inl|y
Tel
0 3JGl~ z ..... ....................
Te ,: 221345
COOW YI-l
ZW Ch, 08diksI
By .. ... ............................
JOB ....
....... . . .....
SECTION.....................SECION
.. ... ...
. ......
.....
.....
........ .. . .. .. . . ..... .. . . . ... .. . .... .1 . . ... .. . " ." .'
.... .... ... ......
I' I -- _ _ __ _ _ _
2 ~ ~ jit ~ L LW~
!.J, i
+-" _ _-
....
._L____ . ._, _____..
T-_l-
- --_-r- - - - - I,(!t
- I5J - I ....
. . ..A
-
, ; I - _k IL
:]-...
.L),_
L-. .. 24
mt--i- 1,7
, /JI/1~ 11c.
.
- ' m - -ILl,,c
- --
1 -j4 -
.. _ _ _ _ ____!
_ _ L'L~' _', <rL_ i
L 4
I '% . . -- ____-
. -
7
I,.
- ...! ,__1. ....... . .__ ... . ....
_ _
'iI. o- . -
i .,....-
i i,-li l-,-rn . -k _. _ _.
Nicholas O'Dwyer & Partners
Consulting Engineers
1~~ ~ ~ 4 Le -
Zic
t ______
. _ _ _ tl ____
_-- __ _ _ _ _ _ _ _ _ _ _ _ _ _
j. 7
_
. T. K L - - ...... _ _ _ _ _ _ _
- 22_
L; I _
JO B ...................
.................................................
............................
.......................
...... D le................
.. .............................
....
SECTION ......
C CI "4, tv "A C>.(6% I 1
flul ........... . . . ................
I hill
--0l '
_ _ 'A
7_1,,. .. .
. + cr --
-__ _ __
JOB ...................................
SEC TIO N
SCTON~
~ SCV
~ ~ ¢ ~ V0
~ ~~~~....
........................
........
..... ' ..... ,...
.....-
..
...............
. . te :
..... .,,.....
l
L.) ; I .................
r IA : .
v ~.
uI..
I I
L!L
00A)
-- J . . . .. _ __...
._ _
. '
LCA
Ji-_-
-_ _ ft
Nicholas O'Dwyer & Partners
Consulting Engineers
2 Rob n Muabe loodSht No ......................
2 Robeil Mugab. RoadShaN. ................
OF ........
P.O. Box UA 424. Union Avenue. Harare
Telephone 702531.5 Miade By .................................................
-
zL IJi
., _ ___ _ __ _ _
___________
;j~tzl or-F=-?
C -- r
L% _ _"_ - --
.
.- . ', 10 - "
____________
__ _
_,
iOA W_ _, _,_______.
LA.
_ A___ _ _ _ _ _
4•
.iij117iijii~
SWj
"
.. _ . . .......
"+--
L - VI INe~_
i . - . . . . . . . . . . . . . . . . . _ _ _ _ _
Nicholas O'Dwyer & Partners
Consulting Engineers
Sheet No ................................
2 Robert Mugabe Road
Avenue, Harare
P.O. Box UA 424. Union
Made By ............................................
Telephone
T:I:16.: 7025315
702536
JOB ..
...............
..........................
....................................
.. .. ...
......
....
r..,<
...........................
........
... ..... ......
........
......
..................
SECTION ..................... iL,
_ m . -ffi---J"-
IA --
__
m ..
- I " - .
A
,.,,/ !
---
LiII~KI•ITIL :m/I
.. _...... _:!_.__-_-__-
----
Nicholas
Consulting O'Dwyer & Partners
Engineers
........... .
CRet
___._a_.
,, " . . _r , .
i i i t
. -
.77±. .. ._ __
Nicholas O'Dwyer & Partners
Consulting Engineers
Tlol ZW
2345 CO W'VYR Ihecked By . ................................
...
SECTION .......
. .
............... ......................
. .... ...
............. ....
.....
. I..
I I J
4: -
1-
/ . . ''
K 44
_,,-____.___..,,!__
. .. __._ _
. . - I,~~.
._.-.. 'I ________________
.. . .. J .
i ii i i i -- i . . . . 1 . / _ _..
, / ' / - -- * -+ - - .- s-
i. .
i -i
zi .f...
-I----
I-
---
.- _ __--
-r Nicholas O'Dwyer & Partners
Consufting Engineers
- . .. . .. .. .....
.AV .. " . . .
rot .
;. . . , ,.....
Valve .
R "I:. "
E'. .....
,E :
6 20
18a~700
~1W.
r ut_ block
1 ....'
"I I '
INLET PIPE DETAIL
_ _ _ __.
ate 1: 5
I(
_ __,
, . t.
, . .. . .. . ,.....
j Nicholas O'Dwyer & Partners
Consulting Engineers
A,
2 Roh.,l M , .,o n d , No . ..................................
P0 Box UA 424 Unon Avenuo. HasIaje
T.Icphorno 702531 5 .4. yv.....................
T.lfax 70'536
Tel.,. 22345 COOW YR ZW Lh,'c od By .... ...................................
SECTIO N... . . . . . . . .. . . . . . . . -.
JOB ......................... ....... . . ..........................
.. ,....
1 f '
.................
.........
, 150 100
25mm 4
2 Layers _t.Ithoid/
SI~ DETAIL .
FtP Scnh,, _.__,__,_•__•
Nicholas O'Dwyer & Partners
Consulting Engineers
JO 8 .............
SECTIO N ........... ..... . ' ...r. . ......... .. . . .... ............. ...... .
,, I ' : ...... . ..................
SZC TION-----i -
. 7TWL1_ 0
RESERVOIR -
1 88 0c
1186j7001
,,0o
oo 15 I Vi 21
M"Nicholas O'Dwyer & Partners
Consulting Engineers
- Slonr20do
I i
K_
1,
.- .
- __
' _ _
___________________
_ _ _ _ _
_
_ _ _
~u~Nicholas O0'Dwyer:&Rartner.
Consu6lting!Enigineers.
2ntihvi M1i11tM IOAd ........
P0 IUv.IA 424. Ur~on Avenue, Har14'
TSIIVI)onp .V
YO53
.I.. Iif ..........
Talefi, 7(n36
T*1c2315C
D.l(qZ jB
JO 02 .. a
.............
....... J ......
....... v
....
....
SEC 16
........
I . ...- ___________________________L:__
I ~~~X1
i ~ _ _ _
. T ____
1e'OF
16IKSFAIK Cm Cf /,u t. , LI
c3 vI A "'41.
a-
wezl~o
. L 10 MU:4
ACIFA
U04 Sf( 1 -
I1.~t
x
flA~.
I -
_ _ _
1 At( _ _ _ _
k0___________
liio__ I _ _
%~~~~~~~AUA
444 C
CL AA :PO ?44:. Z4Z4
<, 1
4
7 7 7
NihlsOT~werZ Partners ~~
~ConuiIng Engineers
ob.i.
2. ,'ad M.ug... .be :. u .. ......................
P0 Box UA4.24 Union Avenue, Hurerq
B -JO
. . ......
. ......
SECTION ....... ..
........ . j.........
TThT_
i00mm dec '
Pipe SSl
i !:l TO.. ______DETA___________
Ilosquito gauize ti4.
Root stob . strap bc.!e,
M'vt
roud pipe. .
I *.. ___________
________
, :
i)[i:
::,::11
::,, :..;I\
---:. : ' i].0..AC.Ppe __.. ..
___. .....
_ ;
4U .
JO
B......
A,.......
..................S. ...........
7.
L f INe
O0P _-OA 'A A'OL ~j
LIGHT DUTY p ECTANI.~
H L,
PAIN Mt. I EL ANO CAST IRON WORK 10 BE IREC ________________
COAIS SIAC9 (FOXY
PAUSMEO AUO l'AIMILO TW~O
PII1 AFTE 1C ALAItO
AtW .
LJ I 1 t 4-
r "'
L
. t"j1I
. . . . . . . . . . . . . . . .
.
. . ..
____