Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Chapter 11 Steel Structures

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

3/25/2022

Steel Structure
Chapter 11

Steel structures used for :


Multistory Building
Theaters
Industrial Building
Roof Truss
Stadium
Bridges
Others

1
3/25/2022

Materials in Steel Structures


Usually steel structures given in standard form such as:

W – section
C – channel
Tubes
Plates
Angles

Note: Standard forms in steel structures is more economical than a


built sections.

Unit of measurement
Weight is usually used as unit of measurement
in steel structures:

$/ton

2
3/25/2022

Steel structures cost includes:


1. Cost of standard Structural Shapes
2. Cost of preparing drawing
3. Cost of Fabricating the steel shapes into finished members
4. Cost of transporting the steel
5. Cost of erecting the steel
6. Cost of field painting the steel structures
7. Cost of job overhead. General overhead, insurances, taxes
and profit

Cost of standard Structural Shapes


Materials cost is function of:
1. Steel grade
2. Shape
3. Weight
4. Total Quantity

3
3/25/2022

Cost of preparing shop drawing


 The engineer or architect does not furnish drawing in
sufficient details

 The steel suppliers must prepare shop drawing before


the steel can be fabricated

 Steel supplier maintain engineering and drafting


departments which prepare shop drawing in sufficient
details to enable their shops to fabricate the members

Cost of fabricating structural steel


Fabricating includes:
Cutting
Punching
Milling
Panning
Marking

fabricating structural steel function of operational performed


Size of member
Operations that can be duplicated on similar members

4
3/25/2022

Cost of transporting steel to the job


The estimator should determine the fright or
truck cost per unit weight for the particular
project to include the correct amount in the
estimate

Erection Structural Steel


1. The columns are erected first
2. The beams are installed in the building

Equipment for Erection structural steel depends on:


o Type of structure
o Size
o Height
o Location

10

5
3/25/2022

Types of Connection
Types of connection and how to install connection
depend on the design criteria

Bolted Connections:
It is more easy but increase construction cost

Welded Connection:
More difficult and needs experience

11

Field Painting Structural Steel


Sometimes necessary to perform limited field
painting

The cost will vary depending of


 Type of structure
 Size
 Access to member

12

6
3/25/2022

Rate of applying a field coat of paint in steel


structures
Member of Structure square ft/ton
Beam 200 – 250
Girder 125 – 200
Column 200 – 250
Roof Truss 275 – 350
Bridge 200 – 250

13

Example
Structural steel consisting of beams, columns, angles, and plates, is used for a
framed building. All members are to be fabricated at a shop for a high-
strength bolted connections. Wide flange beams will be used for beams and
columns.

A list of members and details is given in accompanying table. The small size
beams are used for short spans and longer size beams will be used for longer
spans. The larger columns size will be used for the lower floor. Where the
smaller column sizes are used for the upper floor. Angles are used as seats
and clips for beam to column connections for joining together the structural
members. Steel plates are used for columns base plates and splicing of
column members

14

7
3/25/2022

Example
 Based on the current economical condition, the base price of steel
quoted from the supplier is 24.96/cwt for beams and columns.
28.43/cwt for plates and 22.17/cwt for angles.
 The steel will be delivered by 20-T trucks from the steel supplier a
distance of 134 mi to the job at a rate of 2.75$/mi.
 An illustrative breakdown of the base, fabrication and delivery cost
of the steel is shown in the example. The percentage values given in
the preceding of the reference book are used for fabrication, shop
drawings and painting

15

Example

16

8
3/25/2022

The Total cost will be :


Basic Cost of Steel: Shop painting: 7.5% x 60 256.62 = $4
Columns: 1 123.87 cwt @ 24.96$/cwt = $28 051.80 519.25
Beams: 1 173.93 cwt @ 24.96$/cwt = $29 301.29 Shop drawing: 10.0% % x 60 256.62 = $6
Plates: 60.30 cwt @ 28.43$/cwt = $29 301.29 025.66
Angles: 3 in. 47.87 cwt @ 22.17$/cwt = $1 061.28 Shipping steel to job:
Angles: 21/2 in. . 5.77 cwt @ 22.17$/cwt = $127.92 Number of trucks needed:
Total base cost of steel: = $60 256.62 120.59 T/(20 T/truck) = 6 trucks required
Total Cost: 6 trucks x 134 mi @ $2.75/mi = $2 211.0
Fabricating Costs:
Columns: 1 123.87 cwt @ 85% x 24.96$/cwt = $23 884.03 Subtotal of direct costs:
Beams: 1 173.93 cwt @ 85% x 24.96$/cwt = $24 906.10 Basic Cost of Steel: $60 256.62
Plates: 60.30 cwt @ 95% x 28.43$/cwt = $1 628.04
Fabricating Costs: $51 435.39
Angles: 3 in. 47.87 cwt @ 85% x 22.17$/cwt = $902.09
Shop painting: $4 519.25
Angles: 21/2 in. . 5.77 cwt @ 90% x 22.17$/cwt = $115.13
Shop drawing: $6 025.66
Totl base cost of steel: = $51 435.39
Shipping Costs: $2 211.0
Total Direct Cost:=$ 124 447.92

17

The Total cost will be :


Overhead and Profit:
12% x $ 124 447.92 = $14 933.75
Total cost of fabricated steel delivered to job:
$124 447.92 + $14 933.75 = $139 441.67

Summary of cost:
Cost per pound:$139 441.67 / 241.174lb = 0.58/lb
Cost per hundredweight: $139 441.67 /2 411.74 = $57.79/cwt
Cost per ton: $139 441.67 / 120.59 T = $ 1 156/T

18

You might also like