Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Concurrent Delays

Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

CHAPTER

2. LITERATURE REVIEW

2.1. Introduction

Many articles and studies conducted on causes of delay in construction projects

have been reviewed either locally or internationally. To achieve this study few

articles published during the last 20 years were reviewed concerning delays and time

management used like.

The study Sugiharto Alwi and Keith Hampson (2006) showed that in Indonesia

(Bali) there is no agreement between the two groups of contractors (small and large

contractors). In their result, it stipulates that those contractors generally agree on the

importance ranking of the individual delay variables. Recently contractors tried to

overcome delay problems; the main reason is because the contractors have no ability

to identify the important causes of delay occurring during the construction process.

2.2. Fundamentals of construction contracts

In construction contract there are two (2) types of risk either contractual or

construction itself.

6
2.2.1. Contractual Risk
In case there is no damage for delay, “Contractor‟s sole remedy for delay, loss

of productivity, impact damages or other similar claims shall be an extension of time

in which to complete the work. In no event in which to complete be entitle to

additional compensation or damages for delay. The owner shall not be liable in

monetary damages for the cost of delays which arise from acts or omissions for which

the owner is responsible.

In case of Limited delay damages the contractor shall be entitled to an

increase in the General Conditions if the Contractor‟s General Condition has actually

been increased as a result of a delay to the critical path of the Project Schedule caused

by the improper acts or omissions of the Owner.

Finally in case of Delay Damages, “In the event that Contractor's performance is

delayed or hindered , through no fault of its own Contractor through no fault of its

own, Contractor shall be entitled an extension of time corresponding to the number of

days its performance was delayed, and shall be entitled to additional costs related to

such delay or hindrance."

2.2.2. Extension of time

According to Tony Farrow (2007) Extensions of time clauses in construction

contracts do not assist the parties because they are not prescriptive; they are drafted in

a general way and it is not industry practice to predetermine how delays should be

7
analyzed, either in terms of methodologies or in dealing with such factors as float and

concurrency.

Adding to that if the Contractor is delayed at any time in the commencement

or progress of the work by an act or neglect of the Owner or Architect, or of an

employee of either, or a separate contractor employed by the owner, or by changes

ordered in the work, or by labor disputes, fire, unusual delay in deliveries,

unavoidable causalities or other causes beyond the Contractor‟s control, or by delay

authorized by the Owner pending mediation and arbitration, or by other causes which

the Architect determines may justify delay, them the Contract Time shall be extended

by Change Order for such reasonable time as the Architect may determine.

2.3. Construction schedule delays

The task of investigating the events that led to project delay for the purpose of

determining the financial responsibilities of the contracting parties arising from the

delay is called “delay analysis” or DA.

2.3.1. Types of delays

Terry Williams (2001) revealed that there are three basic ways to group delays

which are excusable delay with compensation, excusable delay without compensation

and non-excusable delay. Therefore Trauner et al, 2009 has specified that delay might

be groups in four main groups which are critical or non-critical, excusable or non-

excusable, compensable or non-compensable, concurrent or non-concurrent delays

can be classified by their origin (Caused Delays or CD), compensability (Excusable

8
Delays / ED and Non-Excusable Delays / NED), and timing (Non-Concurrent Delays

/ NCD and Concurrent Delays / CD).

Project Delays'

Classification

(PDC)

Origin Compensability Timing

Third Non-excusable
Owner Contractor Excusable Non-concurrent Concurrent
Party (NED)

(OCD) (CCD) (TPCD) (ED) Non-compensable (NCD) (CD)

Compensable Non-compensable

(ECD) (ENCD)

Figure 2-1: Project Delays Classification

(Source: Trauner et al, 2009)

2.3.1.1. Excusable versus non-excusable delays

All delays are either considered as excusable or non-excusable. According to

Callahan et al. (1992) and Trauner et al. (2009), it depends on the clauses in the

contract. Excusable Delays are further subdivided into two categories. They are Non-

Compensable Delays and Compensable Delays.

An excusable delay is a delay that is due to an unforeseeable event beyond

the contractor‟s or the subcontractor‟s control for instance general labor strikes, fires,

9
floods, acts of god, owner-directed changes, errors and omissions in the plans and

specifications, differing site conditions or concealed conditions, unusually severe

weather, intervention by outside agencies, lack of action by government bodies

(building inspection). In addition to that, Levy (2006) adds two more excusable

delays to the above list as illness or death of one or more of the contractors,

transportation delays over which the contractor has no control. In another study,

Kelleher (2005) added two more conditions which are epidemics, quarantine

restrictions.

Non-excusable delays are events that are within the contractor‟s control or

that are foreseeable. Mubarak (2005) defines non-excusable delays as “delays that are

either caused by the contractor or not caused by the contractor but should have been

foreseen by the contractor”. Furthermore Trauner et al. (2009) point out some

examples which are late performance of sub-contractors, untimely performance by

suppliers, faulty workmanship by the contractor or sub-contractors, a project-specific

labor strike caused by either the contractor‟s unwillingness to meet with labor

representative or by unfair labor practices. Moreover Mubarak (2005) added some

more examples as Contractor cash-flow problems, accidents on the site caused by the

contractor‟s negligence or lack of preparations, late delivery of the contractor‟s

furnished materials and equipment.

Obviously, the distinction between these two is significant in that it

determines which party is liable for the delay. It dictates whether or not a contractor

10
would be entitled to a time extension and possibly if the contractor would be entitled

to compensation for that time extension.

DELAY
CATEGORIES

NON
EXCUSABLE EXCUSABLE

BEYOND CONTRACTOR
CONTROL WITHIN CONTRACTOR CONTROL

OWNER CHALLENGES CONTRACTOR SLOW

UNFORCESEEABLE PROGRESS
SUB CONTRACTOR
WEATHER SLOW

DIFFERING SITE PROGRESS

CONDITIONS BROKEN EQUIPMENT

STRIKES NO TIME EXTENSION / LD RELIEF

COMPENSABLE NON COMPENSABLE

POSSIBLY $ FOR DELAY NO $ FOR DELAY BEYOND

WITHIN OWNER CONTROL OWNER CONTROL

OWNER CHANGES UNFORCESEEABLE

DIFFERING SITE CONDITIONS WEATHER

STRIKES

Figure 2-2: Delay Categories

(Source: Trauner et al, 2009)

11
2.3.1.2. Critical versus Non-critical delays

Several studies classify delays only into three groups as Excusable and Non-

excusable, Compensable and Non-compensable and Concurrent and Non-concurrent.

Therefore certain authors (Trauner et al., 2009; Callahan et al., 1992) added one more

category which is critical and Non-critical delays.

According to them, delays that affect the project completion, or in some cases

a milestone date, are considered as critical delays, and delays that do not affect the

project completion, or a milestone date, are noncritical delays.

Trauner et al. (2009) also notified that the issue of critical delays emerges

from the Critical Path Method (CPM) scheduling. The determining which activities

truly control the project completion date depends on the following criteria which are

the project itself, the contractor‟s plan and schedule (particularly the critical path), the

requirement of the contract for sequence and phasing, the physical constraint of the

project.

2.3.1.3. Compensable versus Non-compensable Delays

According to Callahan (1992), an excusable delay can be classified either

“excusable compensable” or “excusable non-compensable”. Some studies notified

that excusable non-compensable delays are normally beyond the control of either

owner or contractor such as unusual weather conditions, natural disasters, wars,

national crises, floods, fires or labor strikes. There is a general lack of understanding

concerning the Non-Compensable Delay for weather. It should be noted that a Non-

12
Compensable Delay is for unusually severe weather. That is weather which is not

anticipated at that time of year in that part of the country.

On one hand "Non-compensable delays" are excusable delays which are

actual delays to the project schedule but are within the parties' contemplation and not

the fault of either the contractor or the owner. These include delays caused by unusual

weather, other acts of God, and even some forms of labor disputes. Essentially, these

types are beyond the control of the parties and, therefore, will neither be compensated

nor penalized to any particular party to the construction project. Although the

contractor is not entitled to extra compensation for non-compensable delays, in most

instances it is entitled to an extension of contract time.

"Compensable delays," on the other hand, are excusable delays to the

construction schedule which are allegedly within the control of the parties and are

caused by the fault of one party or the other or even a combination of forces. In these

instances, the parties to the contract undoubtedly have incurred cost impacts to their

extended performance due to an extended period of time that the project covers.

2.3.1.4. Concurrent delays

According to Callahan et al. (1992) too concurrent delay is “more than one

delay contributed to the project delay, not that the delays necessarily occurred at the

same time”. Mubarak (2005) states that a concurrent delay includes a combination of

two or more independent causes of delay occurring within the same time frame. For

Levy (2006), it is known as overlapping delays.

13
Furthermore Mark Boe, P.E. stated in the Capital Project Management, Inc

that concurrent delay occurs when a contractor and an owner have both caused

independent critical path delays — delays that affect the completion date of a project

— during the same approximate time period. Consequently, barring a contract

provision to the contrary, neither can recover damages without a clear allocation of

each party‟s delay and expense.

Concurrent delay refers to the complex situation where more than one event

occurs at the same time, but where not all of those events enable the contractor to

claim an extension of time or to claim loss and expense.

2.3.2. Causes of delay

The result of the study of Alwi and Keith Hampson (2003) concerning the

main causes of delay in Indonesia is poor design, user changes, weather, site

conditions, late deliveries, economic conditions and increases in quantity. In addition

to that, Hampson et al. (2001) stated that destructive conflict resolution leads to

additional costs and delays to a project.

Also Chan and Kumaraswamy (1997) found that the five principal and

common factors of delays to be poor risk management and supervision, unforeseen

site conditions, slow decision making involving all project teams, client-initiated

variations, and necessary variations of works.

In the study of Murali Sambasivan and Yau Wen Soon (2006) the most

important causes were contractor‟s improper, planning, contractor‟s poor site

14
management, inadequate contractor experience, inadequate client‟s finance and

payments for completed work, problem with subcontractors, shortage in material,

labor supply, equipment availability and failure, lack of communication between

parties and mistakes during the construction stage.

According to Sugiharto Alwi and Keith Hampson the delay factors were

divided into six (6) major groups which are People, Professional Management,

Design and Documentation, Materials, Execution and External. Their research

stipulates that the main causes of delay are poor design, user changes, weather, site

conditions, late deliveries, economic conditions and increases in quality.

Kaming et al. (2006) studied influencing factors on 31 high-rise projects in

Indonesia and found out that cost overruns occur more frequently and are more severe

problem than time overruns. They stated the majors factors influencing cost overrun

are material cost increase due to inflation, inaccurate material estimation and degree

of complexity.

Al-Barak discussed the main causes of failure in Construction industry in

Saudi Arabia by surveying 68 contractors and about 34 different causes of failure.

The study concluded that lack of experience, poor estimation practices, bad decisions

in regulating company‟s policy, and national slump in the economy are the severe

factors.

15
Figure 2-3: Factors of delays in construction project
(Source: Assaf et al, 2006)

- 16 -
2.3.3. Effects of delays in construction

Gene Wortham has presented in his study that construction delays has for

effects acceleration, schedule change or inefficiency, delayed project completion,

missed intermediate completion dates, liquidated damages, frustrations of the parties

(claims) and last but not the least increased costs of the projects.

In the research about the problems of projects and effects of delays in the

construction industry of Pakistan, 2011, it stipules that mostly delay problems are

cause of dispute, negotiation, lawsuit, total desertion, litigation and abandonment.

The parties included in contract through claims agree on the additional capital and

extra time linked with construction delay. The general consequences are the loss of

wealth, time and capacity. For owner, delay means the loss of income and

unavailability of facilities. For contractor, delay means the loss of money for extra

spending on equipment and materials and hiring the labor and loss of time.

Delays on a project will have different contractual consequences depending on the

cause of the delay. First when impacts on the completion date is caused by the

contractor, the contractor will be liable to pay Liquidated and Ascertained Damages

(LAD's) to the client. Second if the impacts the completion date is not caused by

either party, the contractor may be entitled to an extension of time. And third when

the delay is caused by the client, the contractor may be able to claim an extension of

time and loss and expense.

- 17 -
2.4. Methods of Delay Analysis

To identify delays and to measure the effects on a construction projects, it is

primordial to use the appropriated methods. In delays construction, bar charts and

Critical Path Method are the basic tools to identifying them. To make sure that the

agreed construction duration is done on time, a planned schedule should be given by

the contractor. With that they will maintain and upload any changes on the project

(unexpected conditions). A basic premise of schedule delay analysis is that delay is

measured from the project‟s completion rather than from any interim activity date

(Bramble and Callahan 2002). When a schedule delays occurs, the as-planned and as-

built schedules are the basic data source for delay analysis (Bubshait and

Cunningham, 1998).The main idea is that the as-planned versus as-built method

compares two schedules, which is why it is also called “the total time method or net

impact method”. The hypothesis is that the contractor is not responsible of the delay

and the owner causes all delays.

In the theory of Nguyen (2007), the method displays the net impact of all claimed

delays on project‟s finish date. There are three kinds of activity in as-built schedules

which are the delayed activity, actual duration activity and actual time-shortened

activity.

- 18 -
*As-planned by Contractor

*As-built by owner

Figure 2-4: As-planned and As-built schedule


(Source: Delay Analysis Method Using Delay Section)

2.5. Planning sequences in construction industry

According to C. Hendrickson (1998), construction planning is a fundamental

and challenging activity in the management and execution of construction projects. It

involves the choice of technology, the definition of work tasks, the estimation of the

required resources and durations for individual tasks, and the identification of any

- 19 -
interactions among the different work tasks. A good construction plan is the basis for

developing the budget and the schedule for work.

2.6. Methods of minimizing construction delays

Based on several studies of project success factors and rectification of delays in

construction project, several recommendations were given to all parties. First owners

should pay progress payment to the contractor on time, minimize change orders

during construction to avoid delays, avoid delay in reviewing and approving of design

documents than they anticipated, and check for resources and capabilities, before

awarding the contract to the lowest bidder (Assaf. and Al-Hejji, 2006).

Secondly these are the recommendations from Majid, 2006: frequent progress

meeting, use up-to-date technology utilization, use proper and modern construction

equipment, use appropriate construction methods, effective strategic planning, roper

material procurement, accurate initial cost estimates, clear information and

communication channels, frequent coordination between the parties involved, proper

emphasis on past experience and proper project planning and scheduling.

- 20 -

You might also like