Detailed Cost Estimates: Demolition and Removal Building Material Off From The Site
Detailed Cost Estimates: Demolition and Removal Building Material Off From The Site
Detailed Cost Estimates: Demolition and Removal Building Material Off From The Site
DEPARTMENT OF AGRICULTURE
Regional Field Unit No. 02
Tuguegarao City
II EARTHWORKS
1. Excavation(Labor) 122.98 cu-m 300.00 36,893.25
2. Backfill and Compaction(Labor) 78.18 cu-m 300.00 23,454.48
3. Mixed Gravel & Sand Fill and Compaction 139.61 cu-m 300.00 41,883.00
4.Solignum 22.00 liter 600.00 13,200.00
Material Cost 55,083.00
Labor Cost(35%of 3 +1+2) 84,246.78
Direct Cost 139,329.78
Indirect Cost
OCM 20,899.47
TAXES 19,227.51
Total Cost(Earthworks) 179,456.76
III CONCRETE WORKS V= 115.67 cu.m.
A. Column Footing 13.50 cu.m.
Portland Cement 145.80 bags 230.00 33,534.00
16mm.Øx 6.0 m. R.S.B. 60.00 pcs. 350.00 21,000.00
Fine Aggregates 6.75 cu.m. 350.00 2,362.50
Coarse Aggregates 13.50 cu.m. 500.00 6,750.00
#16 Annealed Wire 5.71 kgs. 80.00 456.45
64,102.95
B. Tie Beam 7.92
Portland Cement 85.54 bags 230.00 19,673.28
16mm.Øx 6.0 m. R.S.B. 75.00 pcs. 350.00 26,250.00
10mm.Øx 6.0 m. R.S.B. 200.00 pcs. 145.00 29,000.00
Fine Aggregates 3.96 cu.m. 350.00 1,386.00
Coarse Aggregates 7.92 cu.m. 500.00 3,960.00
#16 Annealed Wire 9.00 kgs. 80.00 720.00
80,989.28
C. Wallfooting 3.00
Portland Cement 27.00 bags 230.00 6,210.00
12mm.Øx 6.0 m. R.S.B. 30.00 pcs. 210.00 6,300.00
Fine Aggregates 1.50 cu.m. 350.00 525.00
Coarse Aggregates 3.00 cu.m. 500.00 1,500.00
#16 Annealed Wire 5.00 kgs. 80.00 400.00
14,935.00
D. Column 18.00
Portland Cement 194.40 bags 230.00 44,712.00
16mm.Øx 9.0 m. R.S.B. 120.00 pcs. 570.00 68,400.00
10mm.Øx 6.0 m. R.S.B. 200.00 pcs. 145.00 29,000.00
Fine Aggregates 9.00 cu.m. 350.00 3,150.00
Coarse Aggregates 18.00 cu.m. 500.00 9,000.00
#16 Annealed Wire 61.13 kgs. 80.00 4,890.57
159,152.57
E. Beam 37.25
Portland Cement 402.28 bags 230.00 92,524.03
16mm.Øx 9.0m. R.S.B. 55.00 pcs. 570.00 31,350.00
16mm.Øx 6.0m. R.S.B. 30.00 pcs. 350.00 10,500.00
12mm.Øx 6.0 m. R.S.B. 17.00 pcs. 210.00 3,570.00
10mm.Øx 6.0 m. R.S.B. 500.00 pcs. 145.00 72,500.00
Fine Aggregates 18.62 cu.m. 350.00 6,518.40
Coarse Aggregates 37.25 cu.m. 500.00 18,624.00
#16 Annealed Wire 49.81 kgs. 80.00 3,984.91
239,571.34
F. Ground Floor Slab Flooring 36.00
Portland Cement 388.80 bags 230.00 89,424.00
10mm.Øx 6.0 m. R.S.B. 250.00 pcs. 145.00 36,250.00
Fine Aggregates 18.00 cu.m. 350.00 6,300.00
Coarse Aggregates 36.00 cu.m. 500.00 18,000.00
#16 Annealed Wire 20.00 kgs. 80.00 1,600.00
Note: includes FRONT PORCH,RAMP AND STEPS 151,574.00
F. Stair 0.86
Portland Cement 15.00 bags 230.00 3,450.00
16mm.Øx 6.0 m. R.S.B. 20.00 pcs. 370.00 7,400.00
12mm.Øx 6.0 m. R.S.B. 20.00 pcs. 210.00 4,200.00
10mm.Øx 6.0 m. R.S.B. 50.00 pcs. 145.00 7,250.00
Fine Aggregates 0.43 cu.m. 350.00 151.20
Coarse Aggregates 0.86 cu.m. 500.00 432.00
#16 Annealed Wire 15.00 kgs. 80.00 1,200.00
24,083.20
G. Parapet Walls 79.20 sq.m.
Cement 50.00 bags. 230.00 11,500.00
Sand 39.60 cu.m 300.00 11,880.00
10 mm dia. X 6 m RSB 100.00 pcs. 145.00 14,500.00
Tie Wire 1.00 roll 1,650.00 1,650.00
39,530.00
V MASONRY WORKS
1. CHB Wall, A = 346.50 sq-m (Exterior)
A = 136.38sq-m (Interior)
TOTAL AREA 724.32 sqm.
CHB 6"(Rear main wall) 6,306.30 pcs 13.00 81,981.90
CHB 4" 2,304.82 pcs 11.00 25,353.04
Portland Cement 378.10 bags 230.00 86,961.86
Sand 31.51 cu-m 300.00 9,452.38
12 mm dia x 6 m RSB 80.00 pcs 210.00 16,800.00
10 mm dia x 6 m RSB 60.00 pcs 140.00 8,400.00
Tie Wire #16 2.00 roll 1,650.00 3,300.00
232,249.18
VI STEELWORKS
A. TRUSS
2"X 2" THK Angle Bar Bottom Chord 30.00 pcs. 940.00 28,200.00
2"X 2" THK Angle Bar Top Chord 32.00 pcs. 940.00 30,080.00
1 1/2"X 1 1/2"THK Angle Bar Web Members 25.00 pcs. 700.00 17,500.00
Metal C - Purlins G.A 14, 2" x 6" x 1.2 mm 88.00 pcs 770.00 67,760.00
2" x 4 "Channel Bar (Heavy Duty) 12.00 pcs. 3,850.00 46,200.00
Plain Round Bar Sag Rod - 12 mm x 6 m 20.00 pcs 210.00 4,200.00
Plain Round Bar Cross Bracing - 16 mm x 6 m 25.00 pcs 380.00 9,500.00
Steel Plate, 0.30 x 0.60 x 1"thk 1.00 pc 2,500.00 2,500.00
Turn Buckle, 16 mm 24.00 pcs 180.00 4,320.00
Epoxy Primer Gray 4.00 gal 560.00 2,240.00
Lacquer Thinner 10.00 gal 180.00 1,800.00
Paint Brush, 2 1/2" 5.00 pcs 40.00 200.00
Welding Rod 6.00 boxes 500.00 3,000.00
Davies Metal Primer 1.00 pail 2,200.00 2,200.00
Hacksaw Blade 10.00 pcs. 50.00 500.00
220,200.00
B. STEEL RAILINGS
1"X 1" Square Bar 6.00 pcs. 300.00 1,800.00
1"X 1"Tubular Bar 20.00 pcs. 400.00 8,000.00
2" dia. Stainless Steel 10.00 pcs. 2,500.00 25,000.00
34,800.00
c. ACCENT SCREENS
1" X 3" Tubular Bars 20.00 pcs. 500.00 10,000.00
2" x 2" X 1/4 " thk Angle Bar 10.00 pcs. 940.00 9,400.00
Welding Rod 1.00 box 500.00 500.00
19,900.00
Material Cost 274,900.00
Labor Cost(40%M.C.) 109,960.00
Direct Cost 384,860.00
Indirect Cost
OCM 57,729.00
TAXES 53,110.68
Total Cost(Steel Truss) 437,970.68
VII TINSMITHRY WORKS, A= 414.00
0.40mm x 3.70m Pre-painted 414.00 sq.m. 1,000.00 414,000.00
APO Rib-Type,
Complete with Accessories ,Provide Double
Bubble Insulation
d. Others
Septic Tank 1.00 lot 30,000.00 30,000.00
Catch Basin 12.00 sets 1,000.00 12,000.00
42,000.00
D-5 0.80 x 2.10 Flush Hollow Core Door 4.00 set 6,000.00 24,000.00
with 6mm thk Marine plywood on Inner Face and Ribbon
Grain Plywood on Outer Surface
D-6 Solid Compact Laminate Toilet 6.00 sets 8,000.00 48,000.00
Compartment Door 187,000.00
Windows
W-1 Powdered Coated Aluminum Fixed Windows 13.50 sqm 2,300.00 31,050.00
with 6 mm thk Tempered Glass-Tinted Bronze
W-2 Powdered Coated Aluminum Fixed Windows 7.02 sqm 2,300.00 16,146.00
with 6 mm thk Tempered Glass-Tinted Bronze
W-3 Powdered Coated Aluminum Fixed Windows 5.60 sqm 2,300.00 12,880.00
with 6 mm thk Tempered Glass-Tinted Bronze
W-4 Powdered Coated Aluminum Fixed Windows 32.50 sqm 2,300.00 74,750.00
with 6 mm thk Tempered Glass-Tinted Bronze
W-5 Powdered Coated Aluminum Fixed Windows 8.64 sqm 2,300.00 19,872.00
with 6 mm thk Tempered Glass-Tinted Bronze
W-6 Powdered Coated Aluminum Fixed Windows 2.88 sqm 2,300.00 6,624.00
with 6 mm thk Tempered Glass-Tinted Bronze
161,322.00
6. Ceiling
Davies Gypsum Putty 6.00 gal
Davies Concrete Primer and Sealer 2.00 pails
Davies Megacryll Flat Latex(3 coats) 5.00 gal
3 28
16 16
0.8 0.2
demolition C1F1
COLUMN 5.76
WALLS
Thickness
No.
89.60 Depth
VOLconc
VOLex
VOLfill
F1 F2 F3 16 mm RSB
5.43 4.66667 2.13333 1.5
14 8 1 pcs
65.3333 17.0667 1
83.4 total
12.00
4.00
60.00
73.33
1.00
1,100.00
1,100.00
183.33
1.60
80.00
200.00 1,200.00
1.40
2,026.67
472.89
1.77777777777778 66 60
38
799 0.2 500 16.6667
2.55
0
0
10 mm
Footing Column
DESCRIPTION F1(1.75x1.75x.40) C1(0.4x0.4) C2(0.45x0.45)
16 mm 10 mm 16 mmx9 10 mm 16 x 7.5
Width/Ht. 1.50 0.4
Length/base 1.50 0.4
Thickness/Length 0.40 7.5
Depth(Footing-NGL) 1.50 1.50
No. Of pcs. RSB 14.00 2.22
No. of Pcs 15.00 15
Vol, Concrete 13.50 18
vol. Of excavation 50.63
Backfill
Reinforcement 65.3333333
65.3333333
TOTAL, Vol of Conc. 13.50 18
5.14285714
9.7
28
99
27.049180328
256.82
2.00
207.25 Front entrance CR
14.00 158.98
4.60
128.80 128.80 152.15 19.56 74.1
495.03 12.864 3.36
masonry 1.44
392.00 45.50 346.50 2.16
151.50 15.12 136.38 3.36
139.286 63.78
2.4
210.00
57 79 3.9 23
5 79 21.36 23
60.00 158 46
540
LENGHT OVERALL SETS
22.25 10 12.4 24.8 4 7 29
13 26 4.33333 7 30
9 18 3 7 21
88
100.8
8
3.66666666666667
71 11.833333333
32.541666667
300.00 1,111.11
0.04 88.888888889
26.666666667
168
22.22 246.91 283.55555556
6.67 74.07
13.86 3.47
13.86 3.47
22.13
C2F2 ROOF BEAM CONC. PAVE'T
#REF! #REF!
0
12
16
16
33.5
wt no of Pcs Total wt
304
31.04 20
COLUMN WF TOTAL
0.25
31
0.4
#REF! #REF!
#REF! #REF!
Floor Stair Tie Beam CHB WALL
Second Floor .02 x .30 m CHB 6" CHB 4"
20 16 6.6
6.6
12.6
17.6 58.667
20 0.864 0.12 880
Republic of the Philippines
DEPARTMENT OF AGRICULTURE
Regional Field Unit No. 02
Tuguegarao City
S U M M A R Y
ITEM NO. WORK DESCRIPTION % WEIGHT AMOUNT
2,099,219.62 1,800,000.00 15
702,967.41 480,000.00 4
679,096.31 1,440,000.00 12
683,514.00 480,000.00 4
1,296,059.13 960,000.00 8
648,169.47 720,000.00 6
376,095.01 600,000.00 5
543,153.60 720,000.00 6
545,543.48 480,000.00 4
242,812.45 480,000.00 4
37,531.85 240,000.00 2
432,000.00 360,000.00 3
72,000.00
ommending Approval
ELYN P. BOSITO
n. Officer V
roved:
REINFORCEMENTS
LEFT SUPPORT MID SPAN
GRID LENGTH
MARK BOTTOM
LINE (M) TOP (MM) TOP (MM)
(MM)
MENTS
MID SPAN RIGHT SUPPORT
BOTTOM BOTTOM DIMENSION
TOP (MM)
(MM) (MM)
S U M M A R Y
ITEM %
NO. WORK DESCRIPTION WEIGHT AMOUNT
S U M M A R Y
ITEM
WORK DESCRIPTION % WEIGHT AMOUNT
NO.
I EARTHWORKS #REF! #REF!
II CONCRETE & RSB WORKS #REF! #REF!
III FORMWORKS #REF! #REF!
IV MASONRY WORKS #REF! #REF!
V ELECTRICAL WORKS #REF! #REF!
VI PLUMBING AND DRAINAGE SYSTEM #REF! #REF!
VII FENESTRATIONS #REF! #REF!
VIII FLOOR FINISHES #REF! #REF!
IX CEILING WORKS #REF! #REF!
X PAINTING WORKS #REF! #REF!
XI CARPENTRY WORKS #REF! #REF! SPECIFICATION
XII STEEL WORKS #REF! #REF!
TOTAL PROJECT COST #REF! #REF! "PROPOSED TWO STOREY
Sps. DR. RICHMOND VERGARA & MRS. KAT
SLAB CONCRETING
STAIR CONCRETING
2ND FLOOR COLUMN CONCRETING
2F CHB LAYING
2ND FLOOR BEAM CONCRETING
STEEL TRUSSES
ROOFING
GF CHB LAYING
GF CHB PLASTERING
2ND FLOOR CHB PLASTERING
ELECTRICAL ROUGH-IN
PLUMBING ROUGH-IN
DOOR JAMB INSTALLATION
CEILING WORKS (GF)
CEILING WORKS (2F)
TILING (GF)
TILING (2F)
EXTERIOR PAINTING
INTERIOR PAINTING WORKS
CARPENTRY WORKS
ELECTRICAL FIXTURES
PLUMBING FIXTURES
CLEARING
DEMOBILIZATION
V ELECTRICAL WORKS
CONDUITS AND BOXES
Plastic Junction Box with Cover 4 x 4 65.00 pcs. 30.00 1,950.00
Utility Box 2x4 100.00 pcs. 30.00 3,000.00
20 mm Dia. PVC Adoptor , Poly 200.00 pcs. 20.00 4,000.00
50 mm Dia. PVC Adoptor , Poly 40.00 pcs. 80.00 3,200.00
20 mm Dia. Pvc Long Elbow ,thickwall ,poly 150.00 pcs. 10.00 1,500.00
25 mm Dia. Pvc Long Elbow ,thickwall ,poly 80.00 pcs. 40.00 3,200.00
50 mm Dia. Pvc Long Elbow ,thickwall ,poly 30.00 pcs. 120.00 3,600.00
20 mm Dia. PVC , pipe , thickwall,poly 180.00 pcs. 70.00 12,600.00
25 mm Dia. PVC , pipe , thickwall,poly 80.00 pcs. 90.00 7,200.00
50 mm Dia. PVC , pipe , thickwall,poly 25.00 pcs. 230.00 5,750.00
Solvent cement, 400 cc 20.00 can 200.00 4,000.00
electrical tape , armak 40.00 roll 27.00 1,080.00
rubberized tape 20.00 roll 120.00 2,400.00
3/4 by 10 ft Grounding Rod with Clamp 1.00 set 1,200.00 1,200.00
50 mm Dia. RSC Pipe 1.00 set 1,100.00 1,100.00
50 mm Dia. Entrance Cap 1.00 pcs. 500.00 500.00
WIRES
2.0 mm sq. THHN/THWN Stranded Wire, 600V 7.00 boxes 2,400.00 16,800.00
3.5 mm sq. THHN/THWN Stranded Wire,660 V,RED 3.00 boxes 3,600.00 10,800.00
3.5 mm sq. THHN/THWN Stranded Wire,660 V Yellow 3.00 boxes 3,600.00 10,800.00
5.5 mm sq. THHN/THWN Stranded Wire,660 v 1.00 box 6,000.00 6,000.00
14 mm sq. THHN/THWN Stranded Wire ,660 v 35.00 m 100.00 3,500.00
80 mm sq. THW, Stranded , 660V 30.00 m 450.00 13,500.00
Dropwire 1.00 lot 10,000.00 10,000.00
FIXTURES
One Gang Switch , Panasonic Wide Series 16A,250V 7.00 sets 130.00 910.00
Two Gang Switch , Panasonic Wide Series , 16A,250V 7.00 sets 250.00 1,750.00
Three Gang Switch , Panasonic Wide Series,16A,250V 6.00 sets 400.00 2,400.00
Three Way, Two Gang Switch, Panasonic Wide Series 3.00 sets 400.00 1,200.00
Duplex Convenience Outlet with Grounding
Universal , Panasonic Wide Series,20A 250V 30.00 sets 330.00 9,900.00
Weatherproof plate Cover, Royu Wide Series, 5.00 sets 450.00 2,250.00
Aircon Outlet , Panasonic Wide Series , 20A ,250V 4.00 sets 500.00 2,000.00
12 watts ,LED , 3 way pinlights 30.00 sets 500.00 15,000.00
8 watts CFL,in 4 inches Dia. Pinlight 22.00 sets 350.00 7,700.00
Striplights 40.00 m 200.00 8,000.00
Centerlight 8.00 sets 1,500.00 12,000.00
Wall Lamp 4.00 sets 1,200.00 4,800.00
Exhaust Fan 4.00 sets 1,500.00 6,000.00
Emergency Light 2.00 sets 1,100.00 2,200.00
breakers and panel board 1.00 lot 30,000.00 30,000.00
Metering
cl200, kilowatthour meter , digital 1.00 set 2,500.00 2,500.00
# 1/10 service drop wire 50.00 m 100.00 5,000.00
LABOR CONTRACT
Prepared by:
Received by:
2x4 c purlins 40 30
2x6 channel bar 15 5
red oxide
paint thinner
welding rod
angle bar 10
1st CONTRACT
STRUCTURAL WORKS, ELECTRICAL & PLUMBING ROUGHINS
2ND CONTRACT
CHB LAYING AND PLASTERING
3RD CONTRACT
ELECTRICAL WORKS
5TH CONTRACT
CEILING WORKS
PREPARED BY:
RECEIVED BY: