Fundamentals of Building Costs
Fundamentals of Building Costs
Fundamentals of Building Costs
BUILDING COSTS
CONSTRUCTION COST
➢ are anything that is required for the delivery of the project and that cannot be included in the
direct costs. Generally, overhead costs are 8% to 10% of the contract value. Few overhead costs are;
• Salaries and benefits
• Insurance policy – Group workmen policy, Contractors all risk (CAR) policy, equipment policy, provident fund, premium
etc.
• Financing cost – Interest, guarantees, warranties, bonds, penalties etc.
• Progress photographs and videos
• Conveyance cost – Cost for the transportation of labours to and from the site, senior engineers for their site inspection,
employees transportation cost etc.
• Travel and transfer cost
• Visit of headquarter personnel.
• Temporary site installations and facilities like labour colonies, parking, site offices etc.
• Client and consultant requirements for their office space, office staff etc.
• Utilities like electricity, water, drainage etc which are temporary for the site offices, labour colonies etc.
• Taxes and Duties
• Miscellaneous expenses
RISK
IS THE PROBABILITY OF ANY HAPPENING
CONTINGENCY
IS THE BACKUP MONEY OR FUTURE
MONEY THAT WE KEEP ASIDE.
RISK AND CONTINGENCY
• For example, if 100% is the bid price, 10% Markup, 90% as Total cost,
then 10/90 will be the markup (Ontop) and 10/100 will be Offtop.
• Markups are loaded in different ways in different projects.
The types of markup loading are:
• Uniform distribution of markups (For eg; 15% for all components)
• Front loading of markup (Here more percentage of markup will be charged at the initial stages of
the project for initial works since major works come in this time and later the markup percentage
will be reduced.)
• Backloading of markup (This is the reverse of front-loading where more loading of markup will be
given to the last stages. This is to protect the project from any escalation, uncertainties etc.)
• Uneven loading of markup (This loads markup only to those work packages that are going to incur a
loss in a project)
ACTIVITY