Employer:: 250mm Thick Filter Material
Employer:: 250mm Thick Filter Material
Employer:: 250mm Thick Filter Material
Filter Material
5.0
8.5 1.0 8.5
300mmX300mm Geotextile
Attached to Wall at Wephole
3.3 10.3
13.5
CH:46+730 to CH:46+740
5
0.10m PCC
10
ELEVATION OF MASONRY BREAST WALL
250mm Thick
Filter Material
5.0
300mmX300mm Geotextile
Attached to Wall at Wephole
3.3 10.3
13.5
NOTE:
1.ALL DIMENSIONS ARE IN M UNLESS NOTED OTHERWISE.
2.THIS DRAWING ARE USED IN MASONRY WALL CONSTRUCTION.
EMPLOYER: CONSULTANT: CONTRACTOR: PROJECT: SASEC Mugling–Pokhara Highway Improvement Phase-I Designed By : SCALE As shown
Government of Nepal Project – (SMPHIP) MASONRY BREAST WALL DETAILS
Renardet S.A., Switzerland Checked By : DATE: Mar.2022
Ministry of Physical Infrastructure and Transport China Communications Construction Company Ltd. ADB Loan No. 3846 NEP KM46+720 TO KM46+760
in association with Mugling – Anbukhaireni – Pokhara Road (Section-1)
Department of Roads Verified By : DRG NO :
Soil Test (P) Ltd., Nepal and
Project Directorate (ADB)
CEMAT Consultants (P) Ltd., Nepal
(C.C.C.C) Contract No: SMHIP/OCB/MAP/01
Bishalnagar, Kathmandu, Nepal (Km 8+250 to Km 49+700) Approved By : SHEET NO :