Flowchart Work Piping in Shop and Site Area
Flowchart Work Piping in Shop and Site Area
Flowchart Work Piping in Shop and Site Area
5) (1) From cutting plan. Mark the required length 5) (1) Dimention
CUTTING
(2) Mark the line no, Drawing no, and party no on (2) Size
the spool piesce (3) Material code
(3) Cut
TRANSPORT 11) Final inspection before delivery 11) Confirm the spool No, and piece No.
TO SITE
12) Transportation to site for Installation
WORK FLOW SITE INSTALATION CARBON STEEL SITE INSTALATION ALLOY STEEL CHECK LIST
CHART
SITE 1) Site Inspection & confirmation Check & confirm 1) Daily Hot Work Permit
INFIRMATION a) Equipment Instalation & Alignment
b) Nozzle location and orientation
c) Support location, type, guide, etc 2) Line number and spool part
d) Alignment no.
e) Valve location, material, size 3) Vehiicle entry permit
f) Bolt length, material, size
g) Hot Work Permit
4)Dimension on site condition
2) Collecttion of fabricated spool pieces
COLLECTION * Fitting etc
SPOOL PIECES 3) Shifting & Unloading on site 5) Edge preparation & fit-up
4) Installation of piping * Angles, foot gap
* Mis allignment
FIT-UP
Carbon Steel fit-up Alloy fit-up * Fitting valve, etc
* Pre heating temp & area
5) But Joint Socket 5) Socket But Joint * Material check
PRE-HEAT * Gap 1,6 mm-3.2 mm * Expansion gap 1.6 mm * Expansion gap 1.6 mm * Gap 1,6mm-3,2mm * Cleanness of edge
* Bridge bracket * Direct tack weld by qualified * Preheat 150-300 C * Bridge bracket * Joint No
* Tack weld by qualifed welder * Direct tack weld by * Preheat 150-300 C
welder qualified welder * 18” & over heater coil or 2” 6) Welding
by propane torch * Qualification of welder
* Below 18” by propane burner * Welding rod material
*Tack weld by qualified welder * Electrode (Amp & Volt)
* Preheating Temp & area
6) Root pass 6) Root pass * Root pass
WELDING
* GTAW – ER70SG or equiv * GTAW – ER70SG or Equiv * GTAW–ER 80SG or Equiv * SMAW – 7016 B2 or Equiv a) Penetration
* SMAW – E7016 or Equiv * SMAW–E8016 or Equiv * Post heat 594 C – 15 min b) Crack, Inner cut
* Liquid penetrant check c) Beed
* Preheat 150 – 300 C d) Pin hole etc
* Post weld temp & area
Cover pass Cover pass * PT check
* SMAW - E8016 B2 or equivalent * SMAW – E8016 B2 or Equiv Cover pass
a) Nunder cut
While weld joint number & welder
b) Beed overlap
nomber to weld seam c) Pin holes
d) Crack
FINISHNG
7) Finishing
* Spatter, tack weld work etc 7) Finishing cleaneses of joint
WORK FLOW CHART SITE INSTALATION CARBON STEEL SITE INSTALATION ALLOY STEEL CHECK LIST