Geographical Information System and Its Application To Project Management in Construction Industry
Geographical Information System and Its Application To Project Management in Construction Industry
Geographical Information System and Its Application To Project Management in Construction Industry
VIJAY KOLAGOTLA
Assistant Manager-Planning
Gammon India Ltd., Mumbai.
E-mail: vijay.kolagotla@gammonindia.com
Abstract:
The construction industry is huge and it involves a large number of activities. Various
traditional techniques for scheduling and controlling are still being used in the construction
industry which fail to provide the spatial (layouts, drawings) and non-spatial
(specifications, cost estimates etc) aspects of information in a construction project. So it
was considered that integration between the Project Management and GIS (Geographic
Information System) would be a key part of the solution. This integration would show
visualisation of construction progress w.r.t. time. In this integration the drawings were
drafted using a computer – aided drafting (CAD) program (AutoCAD), the construction
schedule was prepared using Project Management Software (MS Project 2003), the
updated schedule information (which mainly includes percent complete) which is updated
in the Geodatabase (Arc Info). As the updating is being done, a custom application (.net
with C# language) had been prepared to automatically update the Geodatabase. Thus the
project management software is updated and simultaneously the Geodatabase is also
updated and 3-D view of the progress of view can also been seen. The Integrated GIS-
Project Management system would help all the parties involved in the construction project
(especially for decision making) as they would be able to see all the spatial aspects of
project in one system.
Introduction:
The Construction Industry has a huge number of tasks involved and cost involved in these projects is
also very large. The Project Managers have a hard time monitoring the projects between site and
office. They have to come on site to know the progress of work and decide the sequence of work.
They are generally confused on what to do next or what would be the changes faced by them in
future. So the cost involved is large and it varies w.r.t. to the completion of the project i.e. time. The
traditional approach for scheduling and progress control techniques such as bar charts and the critical
10th ESRI India User Conference 2009 Geography in Action
path method are still being used by the project managers for planning which a serious disadvantage
for the decision is making purpose as the spatial aspects fail to provide the required information.
There is pressure on the project managers to shorten the delivery times and thus the current
scheduling and progress reporting practices are in need of substantial improvements in quality and
efficiency. Integration of Geographical Information System (GIS) and project management software’s
with visualization was recognized as one of the most important tools for achieving this goal.
It should be seen perception of a project as well as in the integration of other parties’ activities in the
planning process. Furthermore, in large scale projects, a visual representation of the schedule can be
extended to monitoring not only the construction process itself, but also all the auxiliary activities,
including onsite plant and equipment. In addition, the practical and educational benefits of being able
to visualize construction at a fine level of detail are significant. The application of geographic
information system in project management will be new in the Indian Construction industry. GIS will
allow construction managers and different people involved in project with different backgrounds to
get the information about the progress of the project and support Decision Making. GIS will provide a
common basis of understanding and communication among these people. Many people think of GIS
as a presentation tool. A GIS does in fact create high quality maps that communicate considerable
amounts of information in an efficient and attention-getting manner. GIS is both a database system
with specific capabilities for spatially referenced data, as well as a set of operations for working with
the data.
Visualizing construction progress in three dimensions provides the construction project manager with
a more intuitive view of the construction sequence. 3-D visualization allows the construction manager
to view the construction activities during any stage of the construction process. The objective of this
paper is to demonstrate that GIS can be integrated with project management software for
construction progress visualization and an integrated information system.
Project Management
The term Project management is defined as:
“The application of knowledge, skills, tools and techniques to project activities to meet project
requirements." (PMBOK)
"The planning, monitoring and control of all aspects of the project and the motivation of all those
involved in it to achieve the project objectives on time and to the specified cost, quality and
performance.” (PRINCE2)
In the past twenty-five years, a host of professions have been in the process of developing
automated tools for efficient storage, analysis and presentation of geographic data. These efforts
have apparently been the result of increasing demands by users for the data and information of a
spatial nature. This rapidly evolving technology has come to be known as “Geographic Information
Systems (GIS)”. Geographic information system goes beyond description; it also includes analysis,
modeling, and pre¬diction. According to the Environmental Systems Research Institute (ESRI), a GIS
is defined as “an organized collection of computer hardware, application software, geographic data,
and personnel designed to efficiently capture, store, update, manipulate, analyze, and display all
forms of geo¬graphic referenced information.” Kang Tsung Chang describes GIS is a computer
system for capturing, storing, querying, analyzing and displaying geographically referenced data. GIS
is essentially a marriage between computerized mapping and database management systems. Thus,
GIS is both a database system with specific capabilities for spatially referenced data, as well as a set
of operations for working with the data.
Fig 1: Flow Chart showing the Integration of Project Management and GIS
The objective of this paper is to display the progress and sequence of construction work in 3-D while
synchronizing this information with a formal CPM work schedule. This would help all parties involved
in a construction project to visualize the progress in a natural way, hence minimizing delays and cost
overruns. In addition to monitoring the schedule, the system can also be extended to monitor
quantities of materials, costs, and resources. Fig.1. shows the path of the paper among the various
applications in the system. It also shows the procedure that needs to be used in using the system. A
building of G+20 storey building is selected as the study area. The progress reports are described in
the following sections.
different groups (GRP). According to the groups the numbers of piles are decided after the piles have
been laid, Pile caps have to be put on these piles simultaneously. On these pile caps a PCC Slab is to
be laid which would make the pile foundation complete .i.e. the substructure activities would be
completed. After the completion of substructure activities, superstructure activities have to be
started. The type of formwork used is Mivan formwork i.e. the concreting work is done at the same
time for all columns, walls, beams and slab. Superstructure is divided into different floors, and then it
is further divided into 2 types i.e. wings (Type B, Type A).The two wings are then further divided into
two parts i.e. in total 4 parts (Part I, Part II, Part III, and Part IV). Each and every part is again
divided into structural parts i.e. BLDGColumn, Wall, Beam, and Slab. It is then planned that
Shuttering and Reinforcement will be done simultaneously for BLDGColumn and Wall and then after
that Staging for Beam and Slab will be done. Only after the whole of Shuttering and Reinforcement is
done one can start the Concreting activity. And after concreting is over one has to do De-shuttering
of the formwork.
Activity
Information and MS
Project Schedule of
the Building
Fig.2. Floor plan with elevation, WBS and Activity information with MS Project Schedule
10th ESRI India User Conference 2009 Geography in Action
Fig.3.
MS Project Schedule
Activity for Wall and Column Activity for Wall and Column
Starter Completed Starter, Shuttering and
Reinforcement Work Completed
Summary Report Summary Report
DAY 7 DAY 5
CONCLUSION
This system will benefit project managers, site engineers and clients in the following manner:
PROJECT MANAGER
• Up-to date information about the progress of work
• Helps in controlling big project sites
• Comes to know about the Cost incurred/Spent and the quantity of materials used on site
• Reduces time for decision making as all information is in one system
SITE ENGINEER
• Controlling the project site by knowing the progress of work
• Helps in easy decision making for procurement of funds or materials
• Helps in informing the contractors beforehand about the start of their work
• Helps in knowing how much more material is required
• Helps in reducing wastage of materials
• Helps in ordering the ideal quantity of materials thus by reducing over ordering of
materials
CLIENT
• Helps in knowing the exact status of the project
• Has a 3-D view of the progress of work thus knowing where large cost has been
incurred
Because of the limitations of this version of Integration of Project Management with GIS, the
interfaces between ArcGIS, AutoCAD, and MS Project, only one database should be available and that
is the one that is essential to the operation of the system (i.e., percent completion information), and
10th ESRI India User Conference 2009 Geography in Action
the system is designed for use in single-user desktop environments. The database of the study area
was prepared for columns, walls, beams, slabs, doors, and windows. The database of staircase, site
layout, reinforcement detailing, drainage, plumbing, electrical and gas pipelines can also be added for
further detailed knowledge of the progress of work. The scheme of integration of GIS with project
management software can be further improved by core software professionals. Links of Photographs
showing the present status of work can also be added. It should be further explored to integrate GIS
with ERP (Enterprise Resource Planning) analysis, billing software’s and SAP (System Applications
Product).
REFERENCES:
Abeid, J., Allouche, E., Arditi, D., and Hayman, M. (2003). “Photo-Net II: A Computer based monitoring
system applied to project management.” Autom. Constr., 12(5), 603-616.
Adjei-Kumi, T., Retik, A., and Shapira, A. (1996). “Integrating on-site tasks into planning and scheduling of
construction projects.” Proceedings of the International Symp. on Organization and Management of
Construction, Shapping Theory and Practice, Managing the Construction Project and Managing Risk: D.A.
Langford and A.retik, eds., E & FN Spon, Glasgow, U.K., 283-292.
Anbazhagan.S, Dept.of Earth Sciences, IIT Bombay, “GIS and Its Applications” edited in 2003
Cheng, M.Y., and Chen, J.C. (2000). “Integrating barcode and GIS for monitoring construction projects.”
Autom. Constr., 11(1), 23-33
Cheng, M.Y., and Yang, S.C. (2001). “GIS- based cost estimates integrating with material layout planning.”
J. Constr. Eng. Manage. 127(4), 291-299
Cheng, M.Y., and O’Connor, J.T. (1996). “ArcSite: Enhanced GIS for Construction site layout.” J. Constr.
Eng. Manage., 122(4), 329-336.
Dr.F.Escobar, Assoc. Prof. G. Hunter, Assoc. Prof. I.Bishop, Dr.A.Zeger, “Introduction to GIS”,
http://www.sli.unimelb.edu.au/gisweb
Dr. G.S. Rao, Ajita Kini, Saumyagjit Roy, Anwar Hussan, “IT and GIS – a complementary technology blend”
ESRI 2005. “ArcGIS Solutions for Civil Engineering GIS—the Intelligent Platform for Civil IT”.
Geoff Zeiss, Director of Technology, Autodesk, Inc., “Convergence: Integrating Geospatial Technology and
Architectural and Engineering Design.”
Geoff Zeiss, Director of Technology, Autodesk, Inc., “Worldwide Challenges facing the Construction
Industry.”
Harold Kerzner, Ph.D, Project Management – A Systems Approach to Planning, Scheduling and Controlling
J.Patrick Moore, “Building a Baseball Stadium using GIS”, A Case study of IntegralGIS Company
10th ESRI India User Conference 2009 Geography in Action
Kamat, V.R., and Martinez, J.C. (2002). “Comparison of Simulation-driven construction operations
visualization and 4D CAD.” Exploring New Frontiers: Proc:., 2002 Winter Simulation Conf., E. Yucesan,
C.H. Chen, J.L. Snowdon, and J.M. Charnes, eds., Institute of Electricity and Electronics Engineers, New
York, 1765-1770
KLG Systel, Course Material on Primavera Enterprise Project Management (P6), 3-8
Koo, B., and Fischer, M. (200). “Feasibility study of 4D CAD in commercial construction.” J. Constr. Eng.
Manage., 126(4), 251-260
P.Venkatachalam, B.Krishna Mohan , GRAM++ -Indigenous GIS Software Suite, CSRE, IIT Bombay.
http://www.csre.iitb.ac.in/gram++/Publications.htm.
P.Venkatachalam, Principles of GIS, gram++ GIS Package Development and Applications, CSRE, IIT
Bombay http://www.csre.iitb.ac.in/gram++/Publications.htm
PMBOK, Project Management -- Body of Knowledge as defined by the Project Management Institute — PMI
Retik, A., and Shapira, A. (1999). “VR based planning of Construction projects.” IEEE Comput. Graphics
Appl., 24(1), 6-12
Retik, A. (1997). “Planning and monitoring of construction projects using virtual reality.” Proj. Manage.J.,
97(1),28-31
Research Futures: Academic responses to industry challenges. (1997), Construct IT Center of Excellence,
Salford, U.K.
Stephen E. Poku and Prof. David Arditi, M.ASCE, “Construction Scheduling and Progress Control Using
GIS”, Journal of Computing in civil engineering, Vol.20,No.5 ,Sept.1 2006
Shankar Bagale (2006), “Planning and Management of Irrigation projects using Remote Sensing and GIS
Technology.” NRSA,15-22
Spatial India ESRI India News, Noida, Friday, December 2, 2005, Special supplement on Eight Annual India
ESRI User Conference. “ From Pilots to enterprise Deployments.”, 1-2
Vijay K. Bansal, Mahesh Pal, “GIS Based Projects Information System for Construction Management”, Asian
Journal of Civil Engineering (Building and Housing) Vol.7, No.2(2006) Pages 115-124
GIS Software used: ESRI ArcGIS Desktop 9.2 (ArcMap, ArcScene, ArcCatalog)