LIFTING PLAN REV Approved 2
LIFTING PLAN REV Approved 2
LIFTING PLAN REV Approved 2
PACKAGE: UAA-04
Revision: B
General
DISCIPLINE Civil Mechanical Electrical (MATERIAL
HANDLING)
Approved by
GC :
Submitted by:
L & T - SUCG JV
INDEX
1 INTRODUCTION 04
2 PURPOSE 04
3 PROJECT DESCRIPTION 04
4 SCOPE OF WORK 04
5 ORGANIZATION CHART 05
6 RESPONSIILITIES 06
6.1 LIFT CO-ORDINATOR 06
6.2 BANKS MAN/SIGNAL MAN 06
6.3 SLINGER/RIGGER 07
6.4 CRANE OPERATOR 07
7 USE OF LIFTING TOOLS AND TACKLES 07
8 GENERAL CRANE OPERATIONS & PREPRATION BEFORE CAGE LIFTING 09
8.1 CONTROL OF LIFTING OPERATIONS- COMMUNICATIONS 09
8.2 STANDARD SIGNALS 10
9 OPERATOR CHECKS 10
10 ADVERSE WEATHER CONDITION 11
10.1 ELECTRIC STORM AND STRONG WIND 11
11 RE-BAR CAGE LIFTING AND POSITIONING 11
ANNEXURE – A ( LIFTING PROCEDURE- TANDEM LIFTING )
ANNEXURE – B (CRANE OPERATOR TRAINING CERTIFICATE)
ANNEXURE – C (CRANE OPERATOR EYE VISION CERTIFICATE)
ANNEXURE – D (CRANE OPERATOR COMPETENT CERTIFICATE)
ANNEXURE – E (LIFT PERMIT,PRETASK CHECK LIST)
ANNEXURE – F (LIFT PLAN)
ANNEXURE – G (CRANE THIRD PARTY CERTIFICATE)
ANNEXURE – H (CRANE DETAILS AND LOAD CHARTS)
ANNEXURE – I (THIRD PARTY CERTIFICATE OF LIFTING TOOLS AND
TACKLES)
1. INTRODUCTION
L&T SUCG -JV
METRO TUNNELLING CHENNAI
CHENNAI Reinforcement cage METRO RAIL
LIMITED
lift plan for d-wall
CONTRACT UAA-04
Page 4 of 12
2. PURPOSE
3. PROJECT DESCRIPTION
4. SCOPE OF WORK:
This lift plan is intended to lift single 22.58m reinforcement cage manoeuvring and lowering for
diaphragm wall at Nehru Park.
5. ORGANIZATION CHART
L&T SUCG -JV
METRO TUNNELLING CHENNAI
CHENNAI Reinforcement cage METRO RAIL
LIMITED
lift plan for d-wall
CONTRACT UAA-04
Page 5 of 12
SIGNAL MAN/BANKS
MAN
PHANI KUMAR
SLINGER/RIGGER
RAJ RAO
6. RESPONSIBILITIES
L&T SUCG -JV
METRO TUNNELLING CHENNAI
CHENNAI Reinforcement cage METRO RAIL
LIMITED
lift plan for d-wall
CONTRACT UAA-04
Page 6 of 12
• Stand clear while a load is lifted clear of the deck and landed, while slack is
taken up with or without a load on the hook, and must confirm to the Banksman
that he is clear.
• Not touch a load being landed until it is below his/her waist height and never
attempts to manually stop a swinging load
• Be easily identifiable and distinct from the Banksman.
QUY-80
1) Master Ring-55t SWL
2) D shackle
a) 2 nos-17.5t SWL
b) 2 nos-25t SWL
3) Slings
a) 3 nos-1mx28mm=8t SWL
b) 2 nos-1.5mx28mm=12t SWL
TATA TFC-280
1) Master Ring- 40t SWL
2) D shackle
a) 2 nos-25t SWL
b) 2 nos-17t SWL
c) 2 nos 13.5t
3) Slings
1) Hand signal shall be used between lift co-ordinator and crane operators.
2) Cranes shall be placed in levelled unfirms ground
3) Approach for crane movement will be maintained towards the excavated
trench.
4) Cranes condition shall be checked before starting the tandem lifting
operation.
5) Crane operators and lift co-ordinator will be briefed about the lift plan.
6) Cordoning the area of in and around the area.
7) All foreign material shall be removed from the cage before lifting.
8) All lifting tools and tackles which are used for lifting operations shall be
inspected before commencing the job.
9. Operator Checks
At the commencement of each shift, carry out a function check of the
boom minimum radius cut-out and the hook block (main/auxiliary) over hoist
cut-outs. These checks shall be extended to include maximum radius and
maximum pay-out limits, when they are fitted.
L&T SUCG -JV
METRO TUNNELLING CHENNAI
CHENNAI Reinforcement cage METRO RAIL
LIMITED
lift plan for d-wall
CONTRACT UAA-04
Page 11 of 12
Lifting and placing of cage will be done with the help of 2 nos of Cranes
and the Cage Lifter. The Cage Lifter will be fixed directly to the lifting
hooks of the cage with D’ shackles and slings of the 80 MT crane. The
bottom end of the cage shall be fixed to the second crane (minimum 75
MT capacity Service Crane) with two slings. Now the Cage shall be lifted
slowly with 80 MT Crane operating both the wires and bottom shall be
lifted by the supporting second crane which will swing at a synchronized
speed with the movement of the cage. When the cage is fully lifted, the
load in service crane shall be freed so that the entire load of the cage will
come on the 80Mt crane. The sag control supports from the75T crane will
be freed so that the cage can be held by the Lifter from the top. After
completion of lifting, the cage shall be lowered slowly in-to the panel and
the sag control support/slings will be removed when the supporting
locations of the cage comes down to the ground level. The cage shall be
L&T SUCG -JV
METRO TUNNELLING CHENNAI
CHENNAI Reinforcement cage METRO RAIL
LIMITED
lift plan for d-wall
CONTRACT UAA-04
Page 12 of 12
lowered up to the desired level and shall be rested with the help of resting
hooks. The Cage Lifter, lifting positions and lifting procedure are shown in
the attached sketch as per Annexure A.