Well Decommissioning Guidelines: June 2018
Well Decommissioning Guidelines: June 2018
Well Decommissioning Guidelines: June 2018
Issue 6
June 2018
Acknowledgments
In preparing and publishing this document, Oil & Gas UK gratefully acknowledges the contribution of
members of the Well Decommissioning Guideline Task Finish Group, namely:
• Chris Barrett, INEOS E&P Holdings Limited
• Dillan Perras, Repsol Sinopec Resources UK Ltd
• James Richards, CNR International (U.K.) Ltd
• Jim Keenan, Halliburton Energy Services Group
• Matt Jenkins, ConocoPhillips (UK) Limited/Well-Safe Solutions
• Mike Brandie, Schlumberger Oilfield UK Plc
• Niki Mackenzie, Maersk Oil a company of Total
• Nick Lucas, Shell Upstream International
• Ted Hibbert, Apache North Sea Limited
While every effort has been made to ensure the accuracy of the information contained in this
publication, neither Oil & Gas UK, nor any of its members will assume liability for any use made of this
publication.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or
transmitted in any form or by any means, electronic, mechanical, photocopying, recording or otherwise,
without prior written permission of the publishers.
Crown copyright material is reproduced with the permission of the Controller of Her Majesty’s
Stationery Office.
Copyright © 2018 The UK Oil and Gas Industry Association Limited trading as Oil & Gas UK
London Office:
6th Floor East, Portland House, Bressenden Place, London, SW1E 5BH
Tel: 020 7802 2400 Fax: 020 7802 2401
Aberdeen Office:
Exchange 2, 3rd Floor, 62 Market Street, Aberdeen, AB11 5PJ
Tel: 01224 577250 Fax: 01224 577251
info@oilandgasuk.co.uk
www.oilandgasuk.co.uk
These guidelines have been previously published as the Guidelines for the Abandonment of Wells, and
“well abandonment” is now referred to as “well decommissioning” where appropriate.
Within these guidelines the word “shall” is only used when the instruction is explicit in legislation or
physical laws. Otherwise the word “should” indicates the workgroup’s understanding of current good
practice. “May” is used where there are alternatives available to the well-operator and either, or any
one, of those alternatives is acceptable; in these instances the well-operator will have to use its best
technical judgement to decide which is preferable in the particular situation.
This document provides industry recommendations and good practice for well decommissioning based
on recent North Sea experience. The contents of the document have been developed by an Oil & Gas
UK Workgroup who have reviewed the existing literature and have identified areas where current
practice and experience has moved beyond the published guidance to a sufficient degree, or is not
covered in existing guidance that it was deemed necessary to record the changes in this publication.
This document is aimed at the well engineer but contains information relevant to all disciplines and
management involved in well decommissioning.
These guidelines are relevant to all oil and gas well operators working in the following areas:
• External waters, that is, the territorial sea adjacent to Great Britain (GB) and any designated
area within the United Kingdom continental shelf (UKCS);
• Internal waters of Great Britain, such as estuaries; and
• Onshore Great Britain, where appropriate.
While every effort has been made to produce a useful and comprehensive document, these guidelines
do not represent legal, regulatory or technical advice by Oil & Gas UK or any workgroup members. No
liability is accepted for errors or omissions, or for the consequences of any actions taken with reference
to or in reliance on these guidelines.
Oil & Gas UK Guidelines are subject to regular review. Feedback and comments are welcome, please
contact info@oilandgasuk.co.uk
Good cement: Cement that has been verified as to quantity and quality as stated in Section 4 of these
guidelines.
Impermeable: A formation or material is considered impermeable when it has sufficiently low
permeability so as to prevent flow, i.e. it is impermeable to flow.
Maximum Anticipated Pressure: Maximum pressure expected in the wellbore or formation in the future
following permanent well decommissioning. This may include the possible effects of future
developments or the recharge of the reservoir.
Permanent well decommissioning: The permanent isolation from surface and from lower pressured
zones, of penetrated zones with flow potential in any well that will not be re-entered.
Permanent barrier: A verified barrier that will maintain a permanent seal. A permanent barrier must
extend laterally across the full cross section of the well and include all annuli. When considering isolation
from surface, the first barrier above the point of potential influx is referred to as the primary barrier; the
next barrier above the point of potential influx is referred to as the secondary barrier.
Well: A well is a single wellbore or aggregation of wellbores from a single well origin. It includes the
original wellbore, any side-track from it and any hole section as defined by Regulation 2, DCR (SI
1996/913), and Regulation 2, SCR2015 (SI 2015/398).
Zone with flow potential: Sequence of rock that is capable of flow of fluids. See section 2.
Furthermore, the guidelines help well-operators to comply with the Offshore Installations and Wells
(Design and Construction, etc) Regulations 1996 (SI 1996/913), hereafter referred to as DCR. The
regulations in DCR that are relevant to well decomissioning are 13, 15 and 16 and cover well integrity,
design for decommissioning and materials. The regulations are goal-setting in nature and set out what
the regulator requires of the duty holder
so far as is reasonably practicable, there can be no unplanned escape of fluids from the well; …
…ensure that a well is so designed and constructed that, so far as is reasonably practicable:
after its suspensions or abandonment there can be no unplanned escape of fluids from it or from the
reservoir to which it led.
...The well operator shall ensure that every part of the well is composed of material which is suitable for
achieving the purposes described in Regulation 13 (1).
Objectives
To provide guidelines for the isolation of formations with flow potential when a well is decommissioned
or sidetracked.
Scope
• These guidelines apply to all exploration, appraisal and development wells that are being
decommissioned or sidetracked.
• It should be recognised that each well is unique and should be considered on an individual basis.
• Whilst primarily aimed at offshore wells, these guidelines are equally applicable onshore.
Flow potential originates mostly from formations with permeability and a pressure differential with
other formations or surface. Formations with low or no permeability, like shales and chalk, may however
also exhibit flow potential (e.g. if fractured), in which case these may require isolation; fractures may be
natural or induced by well activities or production.
The assessment of flow potential should include scenarios such as zones that become charged during
the life of the well, re-charging of reservoirs, movement of fluids post-decommissioning, re-
development for hydrocarbon extraction (possibly with enhanced recovery techniques), use for
geothermal projects, or storage of energy or CO2.
Indications of flow potential are based on drilling records (gains/losses/gas levels), log evaluation
(including from adjacent wells), well annuli pressures, well annuli bleed down history, fluid/gas sampling
and subsurface modelling. Evidence of flow potential may only become apparent during
decommissioning operations. Precautions are required for adequate pressure control during such
operations.
Formations may be grouped into zones of similar fluids and/or pressures where inter-zonal isolation has
been assessed as not required, or where the consequences of cross flow are deemed acceptable. Such
a group of formations can be isolated by a common barrier or dual barrier if required.
The level of acceptable flow potential, post-decommissioning, will require an assessment of the risk of
harm to people or the environment. Considerations should include outflow at surface and underground
flow from one formation into another (including into usable water aquifers where applicable). The
assessment will typically consider formation fluids, pressures, formation strength, potential flow rates,
sustainability of potential flow, environmental impact, feasibility of remedial activities and response
time.
Overview
The underlying principle on which these guidelines are based is restoration of the cap rock.
The material, number, position, length and placement method of barriers should be based on
assessment of well condition, formation fluids, pressures, formation strength, potential flow rates,
sustainability of potential flow, environmental impact.
Separate guidelines have been compiled for the qualification of barrier materials which are to be placed
(see Oil & Gas UK Guidelines on qualification of materials for the abandonment of wells, Issue 2, 2015).
The condition and suitability of existing materials in the well should be considered when forming part
of a permanent barrier, e.g. scale, corrosion, mud solids, plastic coated tubulars, GR lined tubulars,
encapsulation, control lines and cable.
The actual number of barriers required should be determined by risk assessment and they may differ
from the numbers below. When considering the number of barriers for water-bearing zones, a single
barrier has been specified as a minimum. This approach should be risk assessed and operators should
consider increasing this requirement based on, but not limited to, the following considerations:
Generally;
• One permanent barrier from surface or seabed may be considered if a zone requiring isolation is
water-bearing.
• Two permanent barriers from surface or seabed are recommended if a zone requiring isolation is
hydrocarbon-bearing OR water bearing and significantly over-pressured.
The two permanent barriers may be combined into a single large permanent barrier (combination
barrier), provided it is as effective and reliable as the two barriers and is an appropriate method to
achieve the objectives that two barriers would otherwise have provided.
3.4.1 Cement
• A cement column of typically a minimum 100 ft measured depth (MD) of good cement to constitute
a permanent barrier whether inside or outside the casing.
• Typically 100 ft MD of good cement above the zone with flow potential.
Note: Where distinct zones with flow potential are less than 100 ft MD apart, then the maximum
practical column of good cement should be placed between the zones.
A reduction in the lengths stated above should only be used if a rigorous risk assessment process has
been followed and it robustly demonstrates that the additional time, trouble and cost required to set a
100 / 200 ft barrier are grossly disproportionate to the further risk reduction achieved in setting these
barriers. Thereby demonstrating that the risks associated with a barrier less than 100 / 200 ft are as low
as is reasonably practicable (ALARP).
Certain formations (e.g. certain shales or certain salts) are known to move as a result of stress
differences. These formations are able to close an annulus space where cement is absent or incomplete.
Typically, such moving formation is a geological feature that is observed field-wide and is not an isolated
well related feature. To be considered for use as a barrier, the formation should be impermeable and
have adequate strength; these properties should be lasting at the prevailing conditions.
The internal barrier material should be adjacent to the annular isolation providing sufficient cumulative
length above the zone with flow potential.
It is acknowledged that existing annular materials have been used to form an annulus barrier where the
verification has been carried out as per a sealing formation. This approach should not be considered a
primary design option. Guidance on verification can be found in section 4.
For existing annular materials, if it can be demonstrated that the cumulative length of the resulting seal
of the formation against the casing is adequate to prevent flow of the present fluids at the maximum
anticipated pressures, then such a seal is acceptable as a replacement for a good annulus cement bond.
However, unlike sealing formations, existing annular sealing materials will be well specific and the
following could be considered:
• Mud density
• Weighting agent
• Well inclination
• Annular clearance
• Fluid properties
• Age of the well
• Pressure and contents of zone to be isolated
The internal barrier material should be adjacent to the annular isolation providing sufficient cumulative
length above the zone with flow potential.
It is recognised that different barrier materials are in development and will emerge as alternatives to
cement. These materials will require assessment and it is anticipated that required lengths of these
materials will be different to those of cement.
If it can be demonstrated that the cumulative length of the resulting seal provided by the alternative
material is adequate to prevent flow of the present fluids at the maximum anticipated pressures, then
such a seal is acceptable as a replacement for a good annulus cement bond.
The internal barrier material should be adjacent to the annular isolation or can itself form the annular
isolation providing there is sufficient cumulative length above the zone with flow potential.
Separate guidelines have been compiled for the qualification of barrier materials which are to be placed
(See Oil & Gas UK Guidelines on qualification of materials for the abandonment of wells, Issue 2, 2015).
• Be set above the zone with flow potential across a suitable cap rock.
• Extend across the full cross section of the well and include all annuli.
• Have formation fracture pressure at the base of the barrier in excess of the maximum
anticipated pressure from the zone being isolated.
A suitable cap rock is impermeable, laterally continuous and has adequate strength and thickness to
contain the maximum anticipated pressure from the zone being isolated.
Note 1: Consideration should be given to the location of the barrier and fracture pressure along the
length of the barrier.
Note 2: Consideration should be made of needing to repeat a barrier placement without needing to
remove the failed barrier material
Note 3: The secondary barrier of one zone with flow potential can be the primary barrier for another,
shallower positioned, zone with flow potential (Figure 3). The bottom of the secondary barrier should
be placed in an area of suitable fracture strength.
Note 4: Two barriers are shown per zone with flow potential in Figure 4. This will be the case if barriers
cannot be shared, i.e. cap rock L is not capable of containing the maximum anticipated pressure from
the main reservoir, or cap rock K is not capable to contain the pressure of sandstone B.
This section covers barrier position where the zone with flow potential is not behind the casing.
For open hole isolations, it is recommended to set a permanent barrier in cased hole (Figure 6) or to
extend sufficiently into cased hole (Figure 5). The barrier across cased hole is to fully isolate the open
hole and allow for a pressure test.
Zones with flow potential that belong to different pressure regimes should be separated by one
permanent barrier unless cross-flow is acceptable (see Figure 7).
Where the pressure from a zone with flow potential is anticipated to exceed the formation fracture
pressure anywhere in the open hole, it should be isolated by two permanent barriers or a combination
barrier (See Figure 8).
Figure 6. Example Open Hole Permanent Barriers (If open hole strength is sufficient for maximum
pressure from Zone A)
The original wellbore should be permanently decommissioned, unless there is confidence that
permanent barriers can be placed and verified during the final permanent decommissioning of the well.
Where an open hole has been sidetracked and subsequently cased across the kick-off point without
achieving a top of cement into the previous shoe (see Figure 9), a suitable barrier should be set above
the sidetrack point.
If the kick-off plug is being used as a permanent barrier, then the remaining barrier, after kick-off, should
conform to the minimum requirements of a permanent barrier (see also Figure 9).
Isolation needs to be considered to ensure adequate well control in subsequent drilling operations. For
deep sidetracks in the reservoir, isolation from the original wellbore, across the sidetrack point, may be
required for reservoir management during production life.
• Future decommissioning in the well design, since in some cases it will be very difficult to regain
access to the original wellbore;
• Possibly different pressure regimes in the lateral branches of the well; and
• Cementing off annuli above the laterals.
A full lateral barrier in cased hole consists of annulus isolation and overlapping internal casing isolation.
Cemented casing alone is not considered to constitute a permanent barrier to flow laterally into or out
of the wellbore. (refer to figure 10).
Similarly to Figure 10, inside cased hole, a permanent barrier requires both a cement plug or equivalent
inside the casing, and overlapping good annular cement or equivalent as per Figure 11. The internal
barrier should be attempted whether the casing is perforated or not. In this example zones A & B have
flow potential, and belong to different pressure regimes, so should be separated by one permanent
barrier internally.
Note 1: The barrier in Figure 11 is placed on a firm support to prevent slumping of the cement slurry
down the well. Consideration should also be given to gas migrating upwards as the cement is thickening.
These considerations are equally appropriate in open hole.
To achieve the required barrier length, allowances will have to be made on volumes to cater for
uncertainties during placement. It may be necessary to place up to 500 ft MD of cement to achieve 100
ft of good cement. Similarly, it may be necessary to place up to 800 ft MD of cement to achieve 200 ft
good cement. Optimisation of barrier placement may allow reduction of length from the values noted
above whilst considering some of following during engineering:
• Hole conditions
• Inclination
• Fluid density hierarchy
• Stinger geometry
• Verification method
• Offset experience
Generally, the additional cost of placing more cement is far outweighed by the implications of a leaking
barrier. However, circumstances may arise where it is impractical to place such a typically sized barrier.
When well completion tubulars are left in hole and permanent barriers are installed through and around
the tubulars, reliable methods and procedures to install these barriers should be established.
See figure 12 as an example of Through-Tubing Cased Hole Decommissioning.
• Cement slumping
• Channelling
• Lack of centralisation
• Small radial clearances
• Tubing integrity
• Full annular coverage
• Contamination
• Tubing debris, such as wax and scale
• Cables and control lines
• Modelling.
Provided the isolations outlined in these guidelines are achieved, cables and control lines can form part
of permanent barriers. Assessment of potential leak paths and the plugging thereof should be
conducted. A rigorous risk assessment process should be followed and documented and should
consider:
• Penetration type e.g. ESP cable, gauge cable, chemical injection line, control line.
• Potential leak paths e.g. encapsulation, cable material, hydraulic line, bonding of barrier material.
• Encapsulation material e.g. plastic type, damage during installation, interfaces between materials.
• Degradation e.g. plastic encapsulation shrinkage, metal corrosion, barrier material interface, with
consideration of temperature and fluid environment.
• Leak path failure modes, and well specific risk profile, which may include cross-flow modelling.
• Alternative isolation material requirements including seal-healing properties.
Bull-heading of cement into perforations can form a permanent barrier, provided the principle of cap
rock restoration still applies.
In principle, the decommissioning of a horizontal well is no different from a standard well. The only
difference is in the means of ensuring a satisfactory isolation, which is in general more difficult to
achieve, see figure 13 below.
• Isolation of zones with flow potential from each other at high angle
• The final vertical thickness of installed barriers
• Wireline access depth for tagging cement.
Overview
Any permanent barrier should be verified to ensure the barrier is placed at the required depth and will
have the required sealing capability.
• Tagging
• Pressure testing
• Inflow testing
• Pumping Records
• Well history
• Modelling
• Lab testing
• Field experience
• Logs
• Sampling
Verification requirements are dependent upon the individual well, job design, barrier material used and
placement method.
Wellbore Barrier
The cement barrier should be verified by an appropriate combination of the following:
• The barrier installation should be documented, including records from the cement operation
(volumes pumped, returns during cementing, water-wetting pills, etc).
• The strength development of the cement slurry should be confirmed. This is primarily done using
pre-job testing with representative component samples cured at anticipated downhole
temperature and pressure.
• The position of a barrier should be verified by tagging, calculation or measurement to confirm the
depth of the firm cement plug.
o Tagging with drillpipe this is typically 10 to 15 klbs.
o Tagging with wireline, coiled tubing or stinger; the weight will be limited by tools and
geometry.
• A pressure test should:
o be a minimum of 500 psi above the leak off pressure below the barrier (e.g. into
perforations or open formation below the casing shoe); but
o not exceed the casing strength minus wear allowance or damage the primary casing
cement, whichever is lower.
• Inflow test should consider the maximum pressure differential to be experienced by the barrier.
In cased hole, if a pressure tested and tagged mechanical plug or previous cement plug is used as a
foundation for the barrier, then
Note: It is acknowledged that alternative materials may be used. The verification method should prove
the barrier is adequate to prevent flow of the present fluids at the maximum anticipated pressures in
the direction of flow.
Annular Barrier
The annular barrier should be verified by an appropriate combination of:
• Evidence that the formation has the required fracture strength to withstand the maximum
anticipated pressures.
• The length of the resulting seal of the formation against the casing is adequate to prevent flow of
the present fluids at the maximum anticipated future pressures, for example differential pressure
testing across a suitable length.
And/or
• Validation that the bond log response can be interpreted as adequate for the maximum anticipated
future pressures. This can be achieved by means of a combination of logging and differential testing
experience. Log interpretation should be performed by a senior onshore qualified and trained
cement log specialist and documented.
Once sufficient field experience is gained, it may be possible to use only one of the above verification
techniques (logging or differential testing) when accepting a barrier; such a decision should be
documented. Sealing formation verification can potentially be extrapolated to other wells that are
geologically similar.
In addition to 4.2, there can be less available accurate methods of determining cement quality and
quantity in both tubing and annulus after through tubing or bull-headed barriers are placed. No single
verification method should be relied on exclusively. Additional considerations for verification of bull-
headed or through-tubing barriers could include:
Cement across a liner lap should not be part of a permanent barrier unless it has been verified. If the
cement quality in the liner lap is uncertain, the cement barrier should be placed above and/or below
the liner lap.
HPHT Wells
The placement and number of barriers (section 3) also apply to the decommissioning of HPHT wells.
However, with the increased complexity and criticality of these wells, there should also be consideration
of the following as a minimum:
Overburden formations may be prone to increase of flow potential, e.g. chalks, as a result of induced
fractures during production. The pressure profile may have changed during well life and should be
considered for the number and depths of barriers required.
This assessment may allow a shallower cap rock to be acceptable for isolation of the group, with a
consequent reduction in decommissioning complexity.
Note: In this case then throughout the guidelines the group should be interpreted as a single zone with
flow potential, and with no need to place a permanent isolation barrier between the zones within the
group.
Note: Future CCS may be identified as an option for the reservoir in a decommissioning programme, if
this is the case, the well decommissioning should be designed accordingly.
The barriers placed in a well with significant concentrations of CO2 should be chosen and designed to
withstand the potential effects of the gas on cement, and steel components of the well and on
subsurface formations. CO2 may degrade cement in the presence of water, in particular Portland
cement, increasing its permeability. CO2 will also accelerate corrosion of steel and can increase the
permeability of subsurface formations, for example by (thermal) fracturing of shales.
Any cement designs should take account of the presence of zones containing magnesium salts.
Annular Fluids
Fluids that are positioned above the uppermost barrier in a well and cannot be legally discharged should
be removed or contained before wellhead removal. This is the part of the well which will be exposed to
the environment after wellhead removal. The depth of annular fluid removal should be determined on
a well-by-well basis. An environmental plug may also be set in the well to contain annular fluids.
It is seen as good practice to retrieve all casing strings to a depth of 10 ft below seabed. This requirement
mainly exists to accommodate fishing activities in the area after the well has been decommissioned.
As per the Oil & Gas UK Guidance on Liaison with the Fishing Industry it is seen as good practice that
depth of 10 ft below seabed has to be reviewed on a well-by-well basis, taking into account the
prevailing local conditions with respect to sand dunes and scouring.
Where subsea equipment and debris has been retrieved at decommissioning a seabed clearance
certificate is issued. The certificate should clearly identify any objects / debris left at the site. The
minimum recommended radius of search is 70 metres from the well.
There is no requirement to inspect the well location once a seabed clearance certificate has been issued.
For platform wells, requirements for conductor and drill string removal will be different compared to
open-water wells and should be specified on a well-by-well basis and in discussion with OPRED.
Appendices
The following link also provides useful references on legislation, notification and guidance for well
decommissioning.
See [Ref. 1]
The BEIS guidance notes on Decommissioning of Offshore Oil and Gas Installations and Pipelines can be
found at:
See [Ref. 2]
Oil & Gas UK’s Guidelines on Liaison with the Fishing Industry on the UKCS can be found at:
See [Ref. 3]
Consent to Flare
Marine Licence
Consent to Locate
Incident Reporting
• For guidance: See [Ref. 15]
• E.g. PON1 for spills of oil or chemicals, PON2 for loss of materials, OPPC non-compliance, OCR non-
compliance or non-compliance with Consent to Locate.
New to this issue is reference to Licencing regulations which require well decommissioning to be
performed in line with the Licence under which it was drilled. Attention is drawn especially to Clauses
19- Commencement and abandonment and plugging of Wells,
23- Avoidance of harmful methods of working,
29- Licensee to keep records,
25 & 45- Relating to the fishing industry,
The Petroleum Act 1998 as modified by the Energy Act 2016 requires operators to detail and minimise
costs of decommissioning. As part of a decommissioning programme (DP) assessment process, OGA on
behalf of BEIS / OPRED review the cost of well P&A and cost optimisation that may be achieved in
delivering a technically competent well decommissioning.
Notification of Well Operations in internal waters (NOTE: Internal waters are handled by the Health and
Safety Executive, not OSDR)
o There is a 21 or 10 day notification period under Regulation 17(1), 17 (2) of the Offshore
Installations (Safety Case etc) Regulations 2005
o For wells in internal waters there is no requirement to submit a report from the well
examiner with the well notification. The requirement to have a well examination scheme is
as per the requirements of Regulation 18 of DCR.
• Weekly reports should be sent to the Health and Safety Executive for ongoing Well Operations
under Regulation 19, DCR: See [Ref. 20]
There is a 21 day notification period under Regulation 6(1) of the Borehole Sites and Operations
Regulations 1995.
For wells onshore UK there is no requirement to submit a report from the well examiner with the well
notification. The requirement to have a well examination scheme is as per the requirements of
Regulation 18 of DCR.
Petroleum Operations Notice 9 sets out the Oil & Gas Authority specific reporting and retention
obligations with respect to well data: See [Ref.25]
CDA members should ensure that details of well decommissioning operations and final well status
diagram are uploaded to CDA (www.cdal.com) for future reference.
1. Well configuration (original, intermediate and present), including depths and specification of
permeable formations and zones with flow potential, casing strings, primary cement behind-casing
status, wellbores, installed completion, sidetracks, etc.
2. Stratigraphic sequence of each wellbore showing reservoir(s) and information about their current
and future production potential, where reservoir fluids and pressures (initial, current and with an
eternal perspective) are included.
3. Logs, data and information from primary cementing operations in the well.
4. Estimated formation fracture gradient.
5. Specific well conditions such as scale build-up, casing wear, collapsed casing, fill, or similar issues.
Field name:
Date of information:
Information required
What and where are the zones with flow potential? (any rock that is capable to cause flow of fluid
into the well; consider effects of induced fractures)
What are the contents of each zone?
Are they hydrocarbon-bearing or water-bearing?
A zone is considered hydrocarbon-bearing if any moveable hydrocarbons are present or likely to be
in future.
Is crossflow acceptable between these zones?
If not, which zones need to be permanently isolated?
Unknown well conditions (more than two years from last well entry, or well has scale / asphalting
problems or hydrate formation potential exists)
What is the quality of the annulus isolation at the depths of the cap rocks? Assess cementing
records (slurry recipe/volumes, losses), casing centralisation, casing cement logs, records of
annulus pressure or flow.
Well history summary:
• current well schematic, including all annuli fluids;
• previous well decommissioning activities, including sidetracks;
• tubular records, pressure tests.
• Wellhead and X-tree installation and maintenance records. Tool requirements to safely access
the well.
What is the lightest fluid gradient between each permeable zone and its permanent barrier?
What is the current operational and integrity status of the well? e.g. flowing, injecting, plugged or in
poor mechanical condition (e.g. leaking x-mas tree valve, leaking tubing, casing integrity or annular
pressure anomalies).
Is the well operating under dispensation from policy?
Information on the type of service the well has seen during its life cycle (e.g. production, gas lift,
water injection, gas injection, cuttings injection, ESP, production histories, etc.).
The following key is used in the tables to show whether the potential issue is:
Cement strength not developing due • Slurry designed and tested in lab, preferably with rig
to poor materials or erroneous samples of materials before job.
mixing procedures • Consider actual slurry tested in surface sample.
• Quality control of materials.
• Supervision by cementing specialist.
• Consider temperature log as input to design.
x Unable to seal annulus by • Select depth where no or little cement is present in the casing
perforate and annulus or where there are low risks of pack off due to fill by solids.
circulate/squeeze • Size and phasing (high side) of perforations adequate to prevent
blockage.
• Unable to circulate, which • Hold squeeze pressure as cement sets or consider using a
may result in accepting cement retainer. If minimal circulation is achieved, extend
annulus fill as a permanent circulation time at increasing rate.
barrier. • Cleaning of debris, mud, grease from annulus requires circulation
• Suboptimal displacement of and cleaning fluids.
resident fluids may leave a • Consider use of a wash tool designed to allow circulation between
channel. perforations prior to cementing.
• Fluid contamination and • Use of computer modelling to predict fluid interfaces and risk of
cement slumping into the mud channels. Optimise key variables such as pump rates,
void below perforations. spacer volumes ahead and behind, and fluid rheology.
• Perforation damage of • If a sump below perforations is significant, consider placing a
adjacent casings. viscous fluid base such as a VRP via additional perforations below
• The well may have been the planned cement plug depth.
drilled with a different type • Consider punchers or pipe cutters as an alternative to perforating
of mud that the one used guns if the next bigger casing is to be protected. A quarry test may
for washing the perforations be considered.
and the remedial cement
• Abrasive jetting is an alternative for wireline perforating, creating
operation.
larger holes in casing and washing behind casing to enhance
• Pack off and losses. cleaning and circulation rates. Perforation washing over an
extended length is another technique to achieve this.
• Use surfactants in the spacer for the cement squeeze remedial
job.
• Use of a swivel to be able to rotate the pipe while washing behind
the perforations.
x Unable to repair annulus • Consideration should be given to milling inside previous casing.
casing cement by section This allows an expandable packer to be set in the bottom of a
window as a support for the cement slurry.
milling
• Achieving window length is optimized by milling cemented casing
• Unable to achieve adequate without centralisers and minimise number of collars to be milled.
window length. Roundtrips may result in losing the hole.
• Lose access to the hole. • Avoid pack-off and stuck pipe by keeping the hole clean and be
• Fluid contamination as a prepared for swarf handling. Milling rate is controlled by hole
result of small slurry cleaning and ability to handle large volumes of swarf.
volumes and cement • Where a second section is milled, the loose pipe may start rotating
slumping into the void and prevent further progress.
outside below the casing • The milled section should be cleaned out to remove debris, e.g.
stub. by means of underreaming if against formation or by side jetting.
• Losses during placement. • Sealing capability, length of window and number of barriers will
depend on type and pressures of fluids, and height of cap rock.
The basis for selection is to be documented, i.e. the effectiveness
Note: As a precaution, avoid of the operation through long-term monitoring if possible.
milling RA pip tags.
For details on further terms (Constructing, Operating, Plugged and Shut-in, Suspended) please refer to
the Well Integrity Guidelines based on the OGA's WONS user guidelines available from OGA website.
Well Decommissioning Phase 1 – the reservoir has been permanently isolated. This requires that
permanent barrier material is placed to fully isolate all reservoir producing or injecting zones from the
wellbore. The tubing may be left in place, partly or fully retrieved.
Well Decommissioning Phase 2 – all intermediate zones with flow potential have been permanently
isolated. This may require the tubing to be partly retrieved if still present, isolating liners, milling and /
or retrieving casing, and setting cement or permanent barrier material to isolate intermediate zones
with flow potential from each other, and communication within the wellbore. The phase is complete
when no further permanent barriers are required.
Not fully decommissioned E&A wells should be the exception rather than rule and be in accordance with
Well Decommissioning Phase 2 requirements.
Well Decommissioning Phase 3 – Well is considered fully decommissioned after removing the wellhead
and conductor. The well origin at surface is removed. The well will never be used or re-entered again.
The well will be removed from the well examination scheme.
Phase 3 may require setting of environmental plugs. An environmental plug is not a pressure barrier
but is placed to ensure that any contaminated fluids in the annuli (e.g. OBM or cuttings reinjection fluids)
are not released to sea.
For all acceptable barriers other than permanent barriers, refer Well Integrity Guidelines (Oil & Gas UK).
The previously defined “UKOOA/Oil & Gas UK category” is used for subsea Phase 3 well
decommissioning, hence only applicable for subsea Phase 2 decommissioned wells.
The scope of work to decommission a well can be represented by a code that commences with two
letters indicating the location of the well, followed by 3 digits representing the complexity of each of
the 3 phases of well decommissioning, e.g. PL 1-3-3 or SS 0-4-3.
The two letters simply define the physical location of the well.
• PL – platform well
• SS – subsea well
• LA – land well
The three digits represent three distinct decommissioning phases, whereas their value reflects the work
scope and equipment required.
The P&A code is a high level indication and does not need to finesse subdivisions of work, e.g. diagnostic
and preparatory operations. Allowance for such tasks should be included within the most appropriate
phase.
For each phase, a digit is chosen (0 to 4) that best reflects the complexity type of the decommissioning
work, according to the following:
TYPE 0: No work required – a phase or phases of well decommissioning work may already have
been completed
TYPE 1: Simple rigless decommissioning – using wireline, pumping, crane, jacks. Subsea will use
a well intervention vessel and be riserless
TYPE 3: Simple rig-based decommissioning – requiring retrieval of tubing and casing using a rig.
TYPE 4: Complex rig-based decommissioning – may have poor access and poor cement
requiring retrieval of tubing and casing, milling and cement repairs
The complexity type of a phase can be determined through a set of questions as described in the
Guideline on well abandonment cost estimation, available through Oil & Gas UK.
The P&A code can be used to record the decommissioning complexity and methodology for the three
phases for a well at a location in a table. See examples 1 and 2.
For a platform well, of which the reservoir will be decommissioned by a coiled tubing unit, then requiring
the tubing to be pulled and shallow barriers placed by a rig and the conductor removed by a rig as well,
the P&A Code would be PL 2-3-3.
Decommissioning complexity
TYPE 4
Platform well TYPE 0 TYPE 1 TYPE 2 TYPE 3
Complex
No work Simple Complex Simple
rig-
required rigless rigless rig-based
based
Reservoir
1 x
decommissioning
Phase
Intermediate
2 x
decommissioning
Wellhead conductor
3 x
removal
For a platform well, already decommissioned across the reservoir, then a complex intermediate P&A
using a rig and standard conductor removal by a rig, the P&A Code would be PL 0-4-3
Decommissioning complexity
TYPE 4
Platform well TYPE 0 TYPE 1 TYPE 2 TYPE 3
Complex
No work Simple Complex Simple
rig-
required rigless rigless rig-based
based
Reservoir
1 x
decommissioning
Phase
Intermediate
2 x
decommissioning
Wellhead conductor
3 x
removal
Guidelines on qualification of materials for the abandonment of wells, Issue 2 Sept 2015, Oil & Gas UK,
ISBN 1 903 004 56 X
Guideline on well abandonment cost estimation, Issue 2, 2015, Oil & Gas UK, ISBN 1 903 003 69 3
Well integrity guidelines, Issue 3, March 2016, Oil & Gas UK, ISBN 1 903 004 71 6
The Offshore Installations and Wells (Design and Construction, etc) Regulations 1996, SI 1996/913, ISBN
0 22 054451 X
L154, The Offshore Installations (Offshore Safety directive) (Safety Case etc.) Regulations 2015, ISBN 978
0 7176 6325 5
API 65-2, Isolating Potential Flow Zones During Well Construction, Second Edition/December 2010
Guidelines for High Pressure, High Temperature Wells October 2016, Oil & Gas UK
WONS guidelines
Guidelines on Liaison with the Fishing Industry on the UKCS, Issue 6 2015, Oil & Gas UK, ISBN 1 903 004
40 3
BEIS Decommissioning of Offshore Oil and Gas Installations and Pipelines Guidance
BEIS Environmental Alerts and Incident Reporting Including Anonymous Reporting Guidance
Aberdeen Office:
Exchange 2, 3rd Floor, 62 Market Street, Aberdeen, AB11 5PJ
Tel: 01224 577250 Fax: 01224 577251
info@oilandgasuk.co.uk
www.oilandgasuk.co.uk