Net Present Value
Net Present Value
Net Present Value
Contents
[hide]
1 Formula 2 The discount rate 3 NPV in decision making 4 Example 5 Common pitfalls 6 History 7 Alternative capital budgeting methods 8 References
Formula
Each cash inflow/outflow is discounted back to its present value (PV). Then they are summed. Therefore NPV is the sum of all terms,
i - the discount rate (the rate of return that could be earned on an investment in the financial markets with similar risk.)
Rt - the net cash flow (the amount of cash, inflow minus outflow) at time t. For educational purposes, R0 is
commonly placed to the left of the sum to emphasize its role as (minus) the investment. The result of this formula if multiplied with the Annual Net cash in-flows and reduced by Initial Cash outlay will be the present value but in case where the cash flows are not equal in amount then the previous formula will be used to determine the present value of each cash flow separately. Any cash flow within 12 months will not be discounted for NPV purpose.[2]
To some extent, the selection of the discount rate is dependent on the use to which it will be put. If the intent is simply to determine whether a project will add value to the company, using the firm's weighted average cost of capital may be appropriate. If trying to decide between alternative investments in order to maximize the value of the firm, the corporate reinvestment rate would probably be a better choice. Using variable rates over time, or discounting "guaranteed" cash flows differently from "at risk" cash flows may be a superior methodology, but is seldom used in practice. Using the discount rate to adjust for risk is often difficult to do in practice (especially internationally), and is difficult to do well. An alternative to using discount factor to adjust for risk is to explicitly correct the cash flows for the risk elements using rNPV or a similar method, then discount at the firm's rate.
If...
It means...
Then...
the investment NPV would add value to the project may be accepted >0 the firm the investment NPV would subtract value the project should be rejected <0 from the firm the investment NPV would neither gain =0 nor lose value for the firm We should be indifferent in the decision whether to accept or reject the project. This project adds no monetary value. Decision should be based on other criteria, e.g. strategic positioning or other factors not explicitly included in the calculation.
Example
A corporation must decide whether to introduce a new product line. The new product will have startup costs, operational costs, and incoming cash flows over six years. This project will have an immediate (t=0) cash outflow of $100,000 (which might include machinery, and employee training costs). Other cash outflows for years 16 are expected to be $5,000 per year. Cash
inflows are expected to be $30,000 each for years 16. All cash flows are after-tax, and there are no cash flows expected after year 6. The required rate of return is 10%. The present value (PV) can be calculated for each year:
Yea r T=0
Cash flow
T=1
$22,727
T=2
$20,661
T=3
$18,783
T=4
$17,075
T=5
$15,523
T=6
$14,112
The sum of all these present values is the net present value, which equals $8,881.52. Since the NPV is greater than zero, it would be better to invest in the project than to do nothing, and the corporation should invest in this project if there is no mutually exclusive alternative with a higher NPV. The same example in Excel formulae:
NPV(rate,net_inflow)+initial_investment PV(rate,year_number,yearly_net_inflow)
More realistic problems would need to consider other factors, generally including the calculation of taxes, uneven cash flows, and Terminal Value as well as the availability of alternate investment opportunities.
Common pitfalls
If, for example, the Rt are generally negative late in the project (e.g., an industrial
or mining project might have clean-up and restoration costs), then at that stage the company owes money, so a high discount rate is not cautious but too optimistic. Some people see this as a problem with NPV. A way to avoid this problem is to include explicit provision for financing any losses after the initial investment, that is, explicitly calculate the cost of financing such losses.
Another common pitfall is to adjust for risk by adding a premium to the discount
rate. Whilst a bank might charge a higher rate of interest for a risky project, that does not mean that this is a valid approach to adjusting a net present value for risk, although it can be a reasonable approximation in some specific cases. One reason such an approach may not work well can be seen from the following: if some risk is incurred resulting in some losses, then a discount rate in the NPV will reduce the impact of such losses below their true financial cost. A rigorous approach to risk requires identifying and valuing risks explicitly,e.g. by actuarial or Monte Carlo techniques, and explicitly calculating the cost of financing any losses incurred.
Yet another issue can result from the compounding of the risk premium. R is a
composite of the risk free rate and the risk premium. As a result, future cash flows are discounted by both the risk-free rate as well as the risk premium and this effect is compounded by each subsequent cash flow. This compounding results in a much lower NPV than might be otherwise calculated. The certainty equivalent model can be used to account for the risk premium without compounding its effect on present value.[citation needed]
Another issue with relying on NPV is that it does not provide an overall picture of
the gain or loss of executing a certain project. To see a percentage gain relative to the investments for the project, usually,Internal rate of return or other efficiency measures are used as a complement to NPV.
History
Net present value as a valuation methodology dates at least to the 19th century. Karl Marx refers to NPV as fictitious capital, and the calculation as capitalising, writing:[4]
The forming of a fictitious capital is called capitalising. Every periodically repeated income is capitalised by calculating it on the average rate of interest, as an income which would be realised by a capital at this rate of interest.
In mainstream neo-classical economics, NPV was formalized and popularized by Irving Fisher, in his 1907 The Rate of Interest and became included in textbooks from the 1950s onwards, starting in finance texts.[5][6]
Adjusted present value (APV): adjusted present value, is the net present value of
a project if financed solely by ownership equity plus the present value of all the benefits of financing.
savings.
Accounting rate of return (ARR): a ratio similar to IRR and MIRR Cost-benefit analysis: which includes issues other than cash, such as time
Internal rate of return: which calculates the rate of return of a project while
Modified internal rate of return (MIRR): similar to IRR, but it makes explicit
assumptions about the reinvestment of the cash flows. Sometimes it is called Growth Rate of Return.
Payback period: which measures the time required for the cash inflows to equal
NPV Ambiguity
Net present value is used in two different contexts in finance. The term NPV may be referred to as net present worth of series of payments or receipts such as in case of an annuity. The second term refers to the net present value for a series of net cash flows that have an outgoing cash expense at the beginning of the cash streams. This latter definition provides an investor with insights in to the financial viability of an investment such as replacement decision, extension of products and services.
Here we discount each of the amounts of the annuity with the interest rate, the time period starts at 1 and ends at n the last period at which the annuity receipt or payment is due.
Here each payment or receipt is discounted at interest rate i for time period t-1
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
$1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000
0.636 0.567 0.507 0.452 0.404 0.361 0.322 0.287 0.257 0.229 0.205 0.183 0.163 0.146 0.130 0.116 0.104 NPV
$636,000 $567,000 $507,000 $452,000 $404,000 $361,000 $322,000 $287,000 $257,000 $229,000 $205,000 $183,000 $163,000 $146,000 $130,000 $116,000 $104,000 $7,471,000
NPV Formula
You may visit this page that explains NPV Formula and NPV Equation in detail
NPV Example
Let us examine finding Net Present Value or NPV with an example investment proposal. Let us say we were offered a series of cash inflows at the end of each of the next four years as $5000, $4000, $3000, and $1000. And the initial cash outlay for this proposal is $10,000 and weighted average cost of capital orWACC is 12%.
NPV at 12%
Year 1 2 3 4
NPV at 15%
Year 1 2 3 4 Net Cash Flows 5000 4000 3000 1000 PVIF @ 15% 0.870 0.756 0.658 0.572 NPV =-$80 Present Value $4,350 $3,024 $1,974 $572 $9,920-$10,000
XNPV at 9%
Date 01/01/2010 04/01/2010 07/30/2010 12/15/2010 01/31/2011 N Net Cash Flows PVIF @ 9% 1 0.979 0.9516 0.9211 0.911 NPV = Present Value $-10,000 $2,937 $2,854.8 0 $2,763.3 0 $2,733 1,288.10
get a rate i, given annual rate r, for a period x, where x is a fraction (e.g., six months = 0.5) or a multiple of the number of years: i + 1 = (r + 1)x To use discount rates that vary over time (so r1 is the rate in the first period, r2 = rate in the second period etc.) we would have to resort to a more basic form of the calculation: NPV = CF0 + CF1/(1+r1) + CF2/((1+r1) (1+r2)) + CF3/((1+r1) (1+r2) (1+r3)) ... This would be tedious to calculate by hand but is fairly easy to implement in a spreadsheet.
Weaknesses of NPV
The NPV calculation is very sensitive to the discount rate: a small change in the discount rates causes a large change in the NPV. As the estimate of the appropriate discount rate is uncertain, this makes NPV numbers very uncertain (see CAPM and WACC). An NPV also often relies on uncertain forecasts of future cash flows. How much of a problem this is obviously depends on how uncertain the forecasts are. One solution to both problems is to calculate a range of NPV numbers using different discount rates and forecasts, so that one can generate, for example, best, worst and median case NPV numbers, or even a probability distribution for the NPV (possibly using something like a Monte-Carlo approach).