SCOPE OF WORK

BAYURAN GATE CONSTRUCTION OF TANJUNG JATI B UNIT 5&6


PT. BHUMI JATI POWER

A. SCOPE OF WORK
The Contractor shall construct the Bayuran Gate based on the design as shown in Attachment 1
by performing following works:

1. Preparation works and procurement of equipment and materials


- Site office preparation (including accommodation and transportation for Contractor’s
personnel).
- Mobilization and demobilization.
- Procurement of equipment and materials.

2. Dismantle of the existing facility, as necessary according to site condition and construction
drawing (Concrete Fence, CCTV, etc, as required)

3. Concrete structure works (f’c : 30 Mpa), including foundation, column, beam and tie beam.
- Formwork fabrication.
- Rebar fabrication.
- Lean concrete (f’c : 10 Mpa).
- Formwork installation.
- Concrete poured, grouting, anchor setting.

4. Roof and Cladding works


- Roof and cladding truss fabrication.
- Roof and cladding installation.
- Ridge installation.
- Flashing installation.
- Roof plank installation.

5. Wall, Floor and Ceiling Works


- Brick wall installation.
- Mortar and skin smooth finishing.
- Ceramics installation (wall + floor).
- Ceiling frame and acoustic panel installation.

6. Door and window works


- Alumunium door/window installation
- Steel door / window installation
- Stainless / carbon pipe door installation include gate, turnstile and wooden sliding gate.

7. Sanitary works
- Kitchen sink installation
- Wastafel installation
- Toilet installation
- Shower installation
- Accessories installation such as Kran, accessories etc.

8. Steel structure work (fabrication)

PT. Bhumi Jati Power


Scope of Work for Bayuran Gate Page 1 of 6
Volume of steel structure fabrication for Gate front security and parking roof for motorcycle
is estimated 3 ton.
Detail of scope of steel structure fabrication works:
- Fabrication (marking, cutting, drilling, assembling, welding and painting).

9. Steel structure works (erection)


The contractor shall provide at least 1 crane and 1 manlift machine for install steel frame
and roof include man cage considering the volume of steel structure erection (est. 3 ton)
for Gate front security and parking roof for motorcycle.
Detail of scope of steel structure erection works:
- Erection and installation steel structure (main structure, frame roof).

10. Rigid Pavement works


Detail of Scope of rigid pavement works as follows:
- Preparation work (clearing, elevation survey, subgrade compaction with CBR test result
requirement min 15%.
- Lean concrete (f’c = 10 Mpa)
- Concrete structure works (f’c = 30 Mpa), grooving finished
- Concrete cub pre-cast installation (K-225)

11. Road Pavement


- Provide 20 T Vibrator roller.
- Preparation work (clearing, elevation survey, subgrade compaction with CBR test result
requirement min 15%).
- Laying Sub Base Course type C, 250mm thickness with CBR test result requirement
min 30%.
- Laying Base Course type B, 250mm thickness with CBR test result requirement min
80%.
- Concrete curb precast installation (K225).
- Construct Skirting for asphalt perimeter (K175).

12. Asphalting works


- Provide Asphalt Paver, Steel Wheel Roller / Tandem, Tyre Roller, Baby roller.
- Preparation work (cleaning, survey elevation, surface preparation).
- Prime coat application (asphalt emulsion cationic rapid setting-1, CRS-1) and
equipment to be used for spraying prime coat should refer to Bina Marga 2018 with
range of material consumption is 0,4-1,3 l/m2.
- Tack Coat application (asphalt emulsion cationic rapid setting-1, CRS-1) and
equipment to be used for spraying prime coat should refer to Bina Marga 2018 with
range of material consumption is 0,2 l/m2 applied above asphalt surface first layer.
- Placement HMA / Asphalt concrete.
This shall be divided into two layers (50mm thickness AC-WC, and 50mm for AC-WC).
The temperature production of the Hot Mix Asphalt (HMA) mixing in AMP shall follow
Table 6.3.5.1 BM-SU-2018 of Bina Marga 2018 as shown in below.
Work Item Temperature
Marshall sample mixing 155 C + 1 C
Compaction marshall sample 145 C + 1 C
Mixing Work 145 C – 155 C
Loading HMA to Truck 135 C – 150 C
Loading HMA to the paver (onsite) 130 C – 150 C

- Compaction HMA / Asphalt concrete.

PT. Bhumi Jati Power


Scope of Work for Bayuran Gate Page 2 of 6