Appendix 1 - Scope of Work Bayuran Gate Construction
Appendix 1 - Scope of Work Bayuran Gate Construction
Appendix 1 - Scope of Work Bayuran Gate Construction
A. SCOPE OF WORK
The Contractor shall construct the Bayuran Gate based on the design as shown in Attachment 1
by performing following works:
2. Dismantle of the existing facility, as necessary according to site condition and construction
drawing (Concrete Fence, CCTV, etc, as required)
3. Concrete structure works (f’c : 30 Mpa), including foundation, column, beam and tie beam.
- Formwork fabrication.
- Rebar fabrication.
- Lean concrete (f’c : 10 Mpa).
- Formwork installation.
- Concrete poured, grouting, anchor setting.
7. Sanitary works
- Kitchen sink installation
- Wastafel installation
- Toilet installation
- Shower installation
- Accessories installation such as Kran, accessories etc.