Abbreviation:
N/A/E: Normal, Abnormal, Emergency S/NS: Significant, Not significant
R/NR: Routine, Non routine SOP: Standard Operating Procedures
MP: Management Programs (Site shall take management programs applicable only for specific issues contributing to High Risk
Severity :-
0.5 Minor (Injury without time/work restriction - FAC)
1 Major (Injury with time/work restriction - MTC RWC)
2 Serious (Irreversible effect handicap-LWC)
3 Critical (One fatality, instantly or afterwards)
6 Disaster (more than one fatality, instantly or afterwards)
10
4.00
3.00
2.00
1.00
ION, RISK ASSESSMENT (HIRA)
ISSUED BY :
Additional controls
Residual risk with additional controls
Priority
E S P TR
1.00 4.00 3.00 12.00 4.00
1.00 4.00 3.00 12.00 4.00
1.00 1.00 3.00 3.00 4.00
1.00 4.00 3.00 12.00 4.00
1.00 4.00 3.00 12.00 4.00
1.00 1.00 3.00 3.00 4.00
1.00 4.00 3.00 12.00 4.00
1.00 1.00 3.00 3.00 3.00
1.00 1.00 3.00 3.00 4.00
Probability :-
ut time/work restriction - FAC) 1.00 Virtually Impossible: only theoretical case (once in a life ti
me/work restriction - MTC RWC) 4.00 Conceivable but improbable: once in a career (once in 20
effect handicap-LWC) 7.00 Improbable/borderline case (1/10Y)
one fatality, instantly or afterwards) 40.00 Possible (once every six months)
Can be expected (once per week)
Note:-
1. Only R<20 can result in acceptable situation. R=>20, If no action is taken, the reason should be documented
2. If S(Severity score is 15) is critical or more( one or more Fatality Potential) Treat the Priority as 1, even if the Ris
Effective Date: 27.10.2019
Doc No : MA01/MECH/HIRA/056
Rev No :
Page No :
Effective Date : 01.10.2019
Form #
N NS
N NS
N NS
N NS
N NS
N NS
N NS
N NS
N NS
cumented
t the Priority as 1, even if the Risk score is <200