MAIN CHEMICAL BUILDING

CABLE TRAY ROUTING

Reference Drawings
Drawing Number
. ·
. ·

Engineer's Stamp Contractor's Stamp

. . . . .
. . . . .
. . . . .
0 ISSUED FOR CONSTRUCTION JAM RPM 15/10/2021
Rev. Description Drawn Checked Date
Employer Project
AL-KHOBAR 2 SEAWATER REVERSE
OSMOSIS DESALINATION PLANT

Engineer Contractor
- 0001 -R 0 .1

POx No:
Drawing Title
Cod.: SA05C2 - 02 - 65 - R900

MAIN CHEMICAL BUILDING


CABLE TRAY ROUTING
COVER
Scale: Drawing No: Sheet: Rev.
- KRO2-WE80-U-0001 01 0
MAIN CHEMICAL BUILDING
DOCUMENT SHEET DESCRIPTION REVISION
KRO2-WE80-U-0001 1 COVER 0
KRO2-WE80-U-0001 2 INDEX 0
KRO2-WE80-U-0001 3 PLAN VIEW 1 0
KRO2-WE80-U-0001 4 PLAN VIEW 2 0
KRO2-WE80-U-0001 5 SECTION 1 0
KRO2-WE80-U-0001 6 SECTION 2 0
KRO2-WE80-U-0001 7 SECTION 3 0
KRO2-WE80-U-0001 8 SECTION 4 0
KRO2-WE80-U-0001 9 CABLE TRAY SUPPORTS 1 0
KRO2-WE80-U-0001 10 CABLE TRAY SUPPORTS 2 0

Reference Drawings
Drawing Number
. ·
. ·

Engineer's Stamp Contractor's Stamp

. . . . .
. . . . .
. . . . .
0 ISSUED FOR CONSTRUCTION JAM RPM 15/10/2021
Rev. Description Drawn Checked Date
Employer Project
AL-KHOBAR 2 SEAWATER REVERSE
OSMOSIS DESALINATION PLANT

Engineer Contractor
- 0001 -R 0 .1

POx No:
Drawing Title
Cod.: SA05C2 - 02 - 65 - R900

MAIN CHEMICAL BUILDING


CABLE TRAY ROUTING
INDEX
Scale: Drawing No: Sheet: Rev.
- KRO2-WE80-U-0001 02 0
Plant North
NOTES
- ALL DIMENSIONS ARE IN mm. ELEVATIONS ARE IN m.

N
- CABLE TRAYS TO FINAL CONSUMERS SHALL BE DEFINED ON SITE ACCORDING TO
STANDARDS DRAWINGS.
- IN ORDER TO UNDERSTAND CABLE TRAYS ROUTING, 3D MODEL CAN HELP TO AVOID
CONFUSIONS.
- THE TOP TRAY OF A GROUP OF OUTDOOR CABLE TRAYS WILL BE PROVIDED WITH
49
° COVER.
- CABLE TRAYS HAVE AT LEAST 20% SPARE SPACE.
- INDOOR CABLE LADDER TRAYS AND CONDUIT NOT SUBJECT TO CORROSIVE
ENVIRONMENT SHALL BE OF HOT DIP GALVANIZED STEEL. IN ALL OUTDOOR AREAS, IN
SEMI CLOSED BUILDINGS AND IN AREAS WITH CORROSIVE CHEMICALS, THE HOT-DIP
GALVANIZED MATERIAL (TRAYS, CONDUITS AND SUPPORTS).
- THE LOCATION OF THE TRAY SUPPORTS REPRESENTED IN THIS DRAWING HAVE TO BE
TAKEN AS REFERENCE. THE FINAL POSITION WILL DEPEND ON THE CABLE TRAY
MANUFACTURER RECOMMENDATION.
- LEVEL CODIFICATION IS NOT APPLICABLE FOR THE CONDUITS IDENTIFICATION

I&C CABLES LV - BUS DUCT

LV - CONTROL VOLTAGE MV - POWER SUPPLY


- POWER SUPPLY
GALVANIZED STEEL SUPPORT HV - POWER SUPPLY
1 2 3 4 5 6 7 8 9 10 11

LEVEL
A
RACEWAY DIMENSIONS
2645 2645
GDN035-QC001 TAG

GDN044-QC001

GDN045-QC001
GDN014-QC002

GDN065-QC001
GDN050-AP001 GDN063-QC001

GDN034-QC001
GDN052-QC001

GDN030-BB001 GDN030-BB002 GDN030-BB003


TRAY IDENTIFICATION

Tray ID Service Tray ID Service Tray ID Service

GDN041-QC001

GDN043-QC001
GDN013-QC001

GDN064-QC001
A I&C G LV N MV
B
GDN010-BB002 GDN050-BB002 GDN060-BB002 GDN030-BB005 B I&C H LV O MV

GDN032-QC001
GDN053-QC001

C I&C I LV P MV
GDN030-AP002

14235
14085
D I&C J LV Q MV

GDN040-QC001

GDN042-QC001
GDN012-QC002

GDN062-QC001

+2.90
16425

16425
E I&C K LV R MV
GDN030-AP001
F I&C L LV S MV

GDN010-BB001 GDN050-BB001 GDN060-BB001 GDN030-BB004 M LV T MV


GDN051-QC001

GDN031-QC001
C
GDN011-QC001

GDN061-QC001

GDN020-QC001

2190GDN021-QC001
U MV

V MV
DOWN
DOWN DOWN DOWN DOWN DOWN DOWN

2780
2190

3550
770

3595 14605 5095 14555 5780 5535 13170 1515

63850

Reference Documents

CONCRETE STRUCTURE DETAILS, SEE DRAWING: KRO2-ZC80-S-0300

Reference Drawings
Drawing Number
. ·
. ·

Engineer's Stamp Contractor's Stamp

. . . . .
. . . . .
. . . . .
0 ISSUED FOR CONSTRUCTION JAM RPM 15/10/2021
Rev. Description Drawn Checked Date
Employer Project
AL-KHOBAR 2 SEAWATER REVERSE
GROUND LEVEL +2.90 OSMOSIS DESALINATION PLANT
SCALE 1:150
Engineer Contractor
- 0001 -R 0 .1

POx No:
Drawing Title
Cod.: SA05C2 - 02 - 65 - R900

MAIN CHEMICAL BUILDING


CABLE TRAY ROUTING
PLAN VIEW 1
Scale: Drawing No: Sheet: Rev.
1:150 KRO2-WE80-U-0001 03 0
Plant North
NOTES
- ALL DIMENSIONS ARE IN mm. ELEVATIONS ARE IN m.

N
- CABLE TRAYS TO FINAL CONSUMERS SHALL BE DEFINED ON SITE ACCORDING TO
STANDARDS DRAWINGS.
- IN ORDER TO UNDERSTAND CABLE TRAYS ROUTING, 3D MODEL CAN HELP TO AVOID
CONFUSIONS.
- THE TOP TRAY OF A GROUP OF OUTDOOR CABLE TRAYS WILL BE PROVIDED WITH
49
° COVER.
- CABLE TRAYS HAVE AT LEAST 20% SPARE SPACE.
- INDOOR CABLE LADDER TRAYS AND CONDUIT NOT SUBJECT TO CORROSIVE
ENVIRONMENT SHALL BE OF HOT DIP GALVANIZED STEEL. IN ALL OUTDOOR AREAS, IN
SEMI CLOSED BUILDINGS AND IN AREAS WITH CORROSIVE CHEMICALS, THE HOT-DIP
GALVANIZED MATERIAL (TRAYS, CONDUITS AND SUPPORTS).
- THE LOCATION OF THE TRAY SUPPORTS REPRESENTED IN THIS DRAWING HAVE TO BE
TAKEN AS REFERENCE. THE FINAL POSITION WILL DEPEND ON THE CABLE TRAY
MANUFACTURER RECOMMENDATION.
- LEVEL CODIFICATION IS NOT APPLICABLE FOR THE CONDUITS IDENTIFICATION

I&C CABLES LV - BUS DUCT


KRO2-CT-WE80-002-A300x100 EL.+6.250 KRO2-CT-WE80-004-A300x100 EL.+6.250 KRO2-CT-WE80-006-A300x100 EL.+6.250
KRO2-CT-WE80-002-G300x100 EL.+5.950 KRO2-CT-WE80-004-G300x100 EL.+5.950 KRO2-CT-WE80-006-G300x100 EL.+5.950 LV - CONTROL VOLTAGE MV - POWER SUPPLY
- POWER SUPPLY
KRO2-CT-WE80-002-H300x100 EL.+5.650 KRO2-CT-WE80-004-H300x100 EL.+5.650 KRO2-CT-WE80-006-H300x100 EL.+5.650
GALVANIZED STEEL SUPPORT HV - POWER SUPPLY
1 2 3 4 5 6 7 8 9 10 11
KRO2-CT-WE80-003-A300x100 EL.+7.000 KRO2-CT-WE80-005-A300x100 EL.+6.250 KRO2-CT-WE80-007-A300x100 EL.+6.250
KRO2-CT-WE80-003-G300x100 EL.+6.700 KRO2-CT-WE80-005-G300x100 EL.+5.950 KRO2-CT-WE80-007-G300x100 EL.+5.950
KRO2-CT-WE80-003-H300x100 EL.+6.400 KRO2-CT-WE80-005-H300x100 EL.+5.650 KRO2-CT-WE80-007-H300x100 EL.+5.650

A LEVEL

RACEWAY DIMENSIONS
GDN035-QC001

GDN044-QC001

GDN045-QC001
GDN014-QC002

GDN065-QC001
GDN050-AP001 GDN063-QC001 TAG

GDN034-QC001
GDN052-QC001

GDN030-BB001 GDN030-BB002 GDN030-BB003


TRAY IDENTIFICATION

Tray ID Service Tray ID Service Tray ID Service

GDN041-QC001

GDN043-QC001
GDN013-QC001

GDN064-QC001
B A I&C G LV N MV
GDN010-BB002 GDN050-BB002 GDN060-BB002 GDN030-BB005
B I&C H LV O MV

GDN032-QC001
GDN053-QC001

C I&C I LV P MV
GDN030-AP002

GDN040-QC001

GDN042-QC001
GDN012-QC002

GDN062-QC001
D I&C J LV Q MV
+2.90
GDN030-AP001 E I&C K LV R MV

ELECTRICAL F I&C L LV S MV
GDN010-BB001 GDN050-BB001 GDN060-BB001 GDN030-BB004 PIT
GDN051-QC001

GDN031-QC001
M LV T MV
C
GDN011-QC001

GDN061-QC001

GDN020-QC001

GDN021-QC001
U MV

V MV
DOWN
DOWN DOWN DOWN DOWN DOWN DOWN

KRO2-CT-WE80-001-A300x100 EL.+7.900
KRO2-CT-WE80-001-G300x100 EL.+7.600
KRO2-CT-WE80-001-H300x100 EL.+7.300
KRO2-CT-WE80-001-I 300x100 EL.+7.000
KRO2-CT-WE80-001-J300x100 EL.+6.700

Reference Documents

CONCRETE STRUCTURE DETAILS, SEE DRAWING: KRO2-ZC80-S-0300

Reference Drawings
Drawing Number
. ·
. ·

Engineer's Stamp Contractor's Stamp

. . . . .
. . . . .
. . . . .
0 ISSUED FOR CONSTRUCTION JAM RPM 15/10/2021
Rev. Description Drawn Checked Date
Employer Project
AL-KHOBAR 2 SEAWATER REVERSE
GROUND LEVEL +2.90 OSMOSIS DESALINATION PLANT
SCALE 1:150
Engineer Contractor
- 0001 -R 0 .1

POx No:
Drawing Title
Cod.: SA05C2 - 02 - 65 - R900

MAIN CHEMICAL BUILDING


CABLE TRAY ROUTING
PLAN VIEW 2
Scale: Drawing No: Sheet: Rev.
1:150 KRO2-WE80-U-0001 04 0
NOTES
- ALL DIMENSIONS ARE IN mm. ELEVATIONS ARE IN m.
- CABLE TRAYS TO FINAL CONSUMERS SHALL BE DEFINED ON SITE ACCORDING TO
STANDARDS DRAWINGS.
- IN ORDER TO UNDERSTAND CABLE TRAYS ROUTING, 3D MODEL CAN HELP TO AVOID
CONFUSIONS.
- THE TOP TRAY OF A GROUP OF OUTDOOR CABLE TRAYS WILL BE PROVIDED WITH
COVER.
- CABLE TRAYS HAVE AT LEAST 20% SPARE SPACE.
- INDOOR CABLE LADDER TRAYS AND CONDUIT NOT SUBJECT TO CORROSIVE
ENVIRONMENT SHALL BE OF HOT DIP GALVANIZED STEEL. IN ALL OUTDOOR AREAS, IN
SEMI CLOSED BUILDINGS AND IN AREAS WITH CORROSIVE CHEMICALS, THE HOT-DIP
GALVANIZED MATERIAL (TRAYS, CONDUITS AND SUPPORTS).
- THE LOCATION OF THE TRAY SUPPORTS REPRESENTED IN THIS DRAWING HAVE TO BE
A A
TAKEN AS REFERENCE. THE FINAL POSITION WILL DEPEND ON THE CABLE TRAY
MANUFACTURER RECOMMENDATION.
- LEVEL CODIFICATION IS NOT APPLICABLE FOR THE CONDUITS IDENTIFICATION

I&C CABLES LV - BUS DUCT

LV - CONTROL VOLTAGE MV - POWER SUPPLY


- POWER SUPPLY
GALVANIZED STEEL SUPPORT HV - POWER SUPPLY

1 2 3 4 5 6 7

LEVEL

RACEWAY DIMENSIONS

TAG
KRO2-CT-WE80-004-A 300 x 100 EL. +6.250
KRO2-CT-WE80-004-G 300 x 100 EL. +5.950
KRO2-CT-WE80-004-H 300 x 100 EL. +5.650 KRO2-CT-WE80-001-A 300 x 100 EL. +7.900 TRAY IDENTIFICATION
KRO2-CT-WE80-001-G 300 x 100 EL. +7.600 Tray ID Service Tray ID Service Tray ID Service
KRO2-CT-WE80-002-A 300 x 100 EL. +6.250 KRO2-CT-WE80-003-A 300 x 100 EL. +7.000 KRO2-CT-WE80-001-H 300 x 100 EL. +7.300 KRO2-CT-WE80-005-A 300 x 100 EL. +6.250
A I&C G LV N MV
KRO2-CT-WE80-002-G 300 x 100 EL. +5.950 KRO2-CT-WE80-003-G 300 x 100 EL. +6.700 KRO2-CT-WE80-001-I 300 x 100 EL. +7.000 KRO2-CT-WE80-005-G 300 x 100 EL. +5.950

SEE DRAWING KRO2-WE80-U-0001 SHEET 06


KRO2-CT-WE80-002-H 300 x 100 EL. +5.650 KRO2-CT-WE80-003-H 300 x 100 EL. +6.400 KRO2-CT-WE80-001-J 300 x 100 EL. +6.700 KRO2-CT-WE80-005-H 300 x 100 EL. +5.650 B I&C H LV O MV

C I&C I LV P MV

D I&C J LV Q MV

E I&C K LV R MV

F I&C L LV S MV

M LV T MV

U MV

V MV
4950
4650
4350
4050
3750

3435
2685

2685

2685
+2.90

GDN011-QC001 GDN010-BB001 GDN050-BB001 GDN051-QC001 GDN061-QC001 GDN060-BB001 GDN030-BB004 GDN030-BB001 GDN031-QC001 GDN020-QC001
3595 14605 5095 14555 5780

Reference Documents

CONCRETE STRUCTURE DETAILS, SEE DRAWING: KRO2-ZC80-S-0300

Reference Drawings
Drawing Number
. ·
. ·

Engineer's Stamp Contractor's Stamp

. . . . .
. . . . .
. . . . .
0 ISSUED FOR CONSTRUCTION JAM RPM 15/10/2021
Rev. Description Drawn Checked Date
Employer Project
AL-KHOBAR 2 SEAWATER REVERSE
SECTION A-A OSMOSIS DESALINATION PLANT
SCALE 1:75
Engineer Contractor
- 0001 -R 0 .1

POx No:
Drawing Title
Cod.: SA05C2 - 02 - 65 - R900

MAIN CHEMICAL BUILDING


CABLE TRAY ROUTING
SECTION 1
Scale: Drawing No: Sheet: Rev.
1:75 KRO2-WE80-U-0001 05 0
NOTES
- ALL DIMENSIONS ARE IN mm. ELEVATIONS ARE IN m.
- CABLE TRAYS TO FINAL CONSUMERS SHALL BE DEFINED ON SITE ACCORDING TO
STANDARDS DRAWINGS.
- IN ORDER TO UNDERSTAND CABLE TRAYS ROUTING, 3D MODEL CAN HELP TO AVOID
CONFUSIONS.
- THE TOP TRAY OF A GROUP OF OUTDOOR CABLE TRAYS WILL BE PROVIDED WITH
COVER.
- CABLE TRAYS HAVE AT LEAST 20% SPARE SPACE.
- INDOOR CABLE LADDER TRAYS AND CONDUIT NOT SUBJECT TO CORROSIVE
ENVIRONMENT SHALL BE OF HOT DIP GALVANIZED STEEL. IN ALL OUTDOOR AREAS, IN
SEMI CLOSED BUILDINGS AND IN AREAS WITH CORROSIVE CHEMICALS, THE HOT-DIP
GALVANIZED MATERIAL (TRAYS, CONDUITS AND SUPPORTS).
- THE LOCATION OF THE TRAY SUPPORTS REPRESENTED IN THIS DRAWING HAVE TO BE
A A
TAKEN AS REFERENCE. THE FINAL POSITION WILL DEPEND ON THE CABLE TRAY
MANUFACTURER RECOMMENDATION.
- LEVEL CODIFICATION IS NOT APPLICABLE FOR THE CONDUITS IDENTIFICATION

I&C CABLES LV - BUS DUCT

LV - CONTROL VOLTAGE MV - POWER SUPPLY


- POWER SUPPLY
GALVANIZED STEEL SUPPORT HV - POWER SUPPLY

6 7 8 9 10 11

LEVEL

RACEWAY DIMENSIONS

TAG
KRO2-CT-WE80-007-A 300 x 100 EL. +6.250
KRO2-CT-WE80-007-G 300 x 100 EL. +5.950
KRO2-CT-WE80-007-H 300 x 100 EL. +5.650 KRO2-CT-WE80-001-A 300 x 100 EL. +7.900 TRAY IDENTIFICATION
KRO2-CT-WE80-001-G 300 x 100 EL. +7.600 Tray ID Service Tray ID Service Tray ID Service
KRO2-CT-WE80-005-A 300 x 100 EL. +6.250 KRO2-CT-WE80-006-A 300 x 100 EL. +6.250 KRO2-CT-WE80-001-H 300 x 100 EL. +7.300
A I&C G LV N MV
KRO2-CT-WE80-005-G 300 x 100 EL. +5.950 KRO2-CT-WE80-006-G 300 x 100 EL. +5.950 KRO2-CT-WE80-001-I 300 x 100 EL. +7.000
SEE DRAWING KRO2-WE80-U-0001 SHEET 05

KRO2-CT-WE80-005-H 300 x 100 EL. +5.650 KRO2-CT-WE80-006-H 300 x 100 EL. +5.650 KRO2-CT-WE80-001-J 300 x 100 EL. +6.700 B I&C H LV O MV

C I&C I LV P MV

D I&C J LV Q MV

E I&C K LV R MV

F I&C L LV S MV

M LV T MV

U MV

V MV

4950
4650
4350
4050
3750
2685

2685

2685
+2.90

1275
GDN030-BB004 GDN030-BB001 GDN031-QC001 GDN020-QC001 GDN021-QC001

300 300
300
14555 5780 5535 13380
300 300
300 300

ELECTRICAL
PIT

Reference Documents

CONCRETE STRUCTURE DETAILS, SEE DRAWING: KRO2-ZC80-S-0300

Reference Drawings
Drawing Number
. ·
. ·

Engineer's Stamp Contractor's Stamp

. . . . .
. . . . .
. . . . .
0 ISSUED FOR CONSTRUCTION JAM RPM 15/10/2021
Rev. Description Drawn Checked Date
Employer Project
AL-KHOBAR 2 SEAWATER REVERSE
SECTION A-A OSMOSIS DESALINATION PLANT
SCALE 1:75
Engineer Contractor
- 0001 -R 0 .1

POx No:
Drawing Title
Cod.: SA05C2 - 02 - 65 - R900

MAIN CHEMICAL BUILDING


CABLE TRAY ROUTING
SECTION 2
Scale: Drawing No: Sheet: Rev.
1:150 KRO2-WE80-U-0001 06 0
NOTES
- ALL DIMENSIONS ARE IN mm. ELEVATIONS ARE IN m.
B - CABLE TRAYS TO FINAL CONSUMERS SHALL BE DEFINED ON SITE ACCORDING TO
STANDARDS DRAWINGS.
- IN ORDER TO UNDERSTAND CABLE TRAYS ROUTING, 3D MODEL CAN HELP TO AVOID
CONFUSIONS.
- THE TOP TRAY OF A GROUP OF OUTDOOR CABLE TRAYS WILL BE PROVIDED WITH
COVER.
- CABLE TRAYS HAVE AT LEAST 20% SPARE SPACE.
- INDOOR CABLE LADDER TRAYS AND CONDUIT NOT SUBJECT TO CORROSIVE
ENVIRONMENT SHALL BE OF HOT DIP GALVANIZED STEEL. IN ALL OUTDOOR AREAS, IN
SEMI CLOSED BUILDINGS AND IN AREAS WITH CORROSIVE CHEMICALS, THE HOT-DIP
GALVANIZED MATERIAL (TRAYS, CONDUITS AND SUPPORTS).

B - THE LOCATION OF THE TRAY SUPPORTS REPRESENTED IN THIS DRAWING HAVE TO BE


TAKEN AS REFERENCE. THE FINAL POSITION WILL DEPEND ON THE CABLE TRAY
MANUFACTURER RECOMMENDATION.
- LEVEL CODIFICATION IS NOT APPLICABLE FOR THE CONDUITS IDENTIFICATION

I&C CABLES LV - BUS DUCT

LV - CONTROL VOLTAGE MV - POWER SUPPLY


- POWER SUPPLY
GALVANIZED STEEL SUPPORT HV - POWER SUPPLY

A B C D

LEVEL

RACEWAY DIMENSIONS

TAG

TRAY IDENTIFICATION
KRO2-CT-WE80-001-A 300 x 100 EL. +7.900
KRO2-CT-WE80-001-G 300 x 100 EL. +7.600 Tray ID Service Tray ID Service Tray ID Service
KRO2-CT-WE80-001-H 300 x 100 EL. +7.300 A I&C G LV N MV
KRO2-CT-WE80-001-I 300 x 100 EL. +7.000
B I&C H LV O MV
KRO2-CT-WE80-001-J 300 x 100 EL. +6.700
C I&C I LV P MV
300
300 D I&C J LV Q MV
KRO2-CT-WE80-002-A 300 x 100 EL. +6.250
KRO2-CT-WE80-002-G 300 x 100 EL. +5.950 E I&C K LV R MV

KRO2-CT-WE80-002-H 300 x 100 EL. +5.650 F I&C L LV S MV

M LV T MV

U MV

V MV

4950
4650
4350
4050
3750
3285
2985
2685

+2.90

GDN014-QC002 GDN013-QC001 GDN012-QC002 GDN011-QC001


14910 1515 770

Reference Documents

CONCRETE STRUCTURE DETAILS, SEE DRAWING: KRO2-ZC80-S-0300

Reference Drawings
Drawing Number
. ·
. ·

Engineer's Stamp Contractor's Stamp

. . . . .
. . . . .
. . . . .
0 ISSUED FOR CONSTRUCTION JAM RPM 15/10/2021
Rev. Description Drawn Checked Date
Employer Project
AL-KHOBAR 2 SEAWATER REVERSE
SECTION B-B OSMOSIS DESALINATION PLANT
SCALE 1:75
Engineer Contractor
- 0001 -R 0 .1

POx No:
Drawing Title
Cod.: SA05C2 - 02 - 65 - R900

MAIN CHEMICAL BUILDING


CABLE TRAY ROUTING
SECTION 3
Scale: Drawing No: Sheet: Rev.
1:75 KRO2-WE80-U-0001 07 0
NOTES
- ALL DIMENSIONS ARE IN mm. ELEVATIONS ARE IN m.
C - CABLE TRAYS TO FINAL CONSUMERS SHALL BE DEFINED ON SITE ACCORDING TO
STANDARDS DRAWINGS.
- IN ORDER TO UNDERSTAND CABLE TRAYS ROUTING, 3D MODEL CAN HELP TO AVOID
CONFUSIONS.
- THE TOP TRAY OF A GROUP OF OUTDOOR CABLE TRAYS WILL BE PROVIDED WITH
COVER.
- CABLE TRAYS HAVE AT LEAST 20% SPARE SPACE.
- INDOOR CABLE LADDER TRAYS AND CONDUIT NOT SUBJECT TO CORROSIVE
ENVIRONMENT SHALL BE OF HOT DIP GALVANIZED STEEL. IN ALL OUTDOOR AREAS, IN
SEMI CLOSED BUILDINGS AND IN AREAS WITH CORROSIVE CHEMICALS, THE HOT-DIP
GALVANIZED MATERIAL (TRAYS, CONDUITS AND SUPPORTS).

C - THE LOCATION OF THE TRAY SUPPORTS REPRESENTED IN THIS DRAWING HAVE TO BE


TAKEN AS REFERENCE. THE FINAL POSITION WILL DEPEND ON THE CABLE TRAY
MANUFACTURER RECOMMENDATION.
- LEVEL CODIFICATION IS NOT APPLICABLE FOR THE CONDUITS IDENTIFICATION

I&C CABLES LV - BUS DUCT

LV - CONTROL VOLTAGE MV - POWER SUPPLY


- POWER SUPPLY
GALVANIZED STEEL SUPPORT HV - POWER SUPPLY

D C B A

LEVEL

RACEWAY DIMENSIONS

TAG

TRAY IDENTIFICATION
KRO2-CT-WE80-001-A 300 x 100 EL. +7.900
KRO2-CT-WE80-001-G 300 x 100 EL. +7.600 Tray ID Service Tray ID Service Tray ID Service
KRO2-CT-WE80-001-H 300 x 100 EL. +7.300 A I&C G LV N MV
KRO2-CT-WE80-001-I 300 x 100 EL. +7.000
B I&C H LV O MV
KRO2-CT-WE80-001-J 300 x 100 EL. +6.700
C I&C I LV P MV

D I&C J LV Q MV
KRO2-CT-WE80-007-A 300 x 100 EL. +6.250
KRO2-CT-WE80-007-G 300 x 100 EL. +5.950 E I&C K LV R MV

KRO2-CT-WE80-007-H 300 x 100 EL. +5.650 F I&C L LV S MV

M LV T MV

U MV

V MV
4950
4650
4350
4050
3750

3285
2985
2685
+2.90
1225

GDN021-QC001 GDN042-QC001 GDN043-QC001 GDN045-QC001


300 300

2780
300

ELECTRICAL
PIT

Reference Documents

CONCRETE STRUCTURE DETAILS, SEE DRAWING: KRO2-ZC80-S-0300

Reference Drawings
Drawing Number
. ·
. ·

Engineer's Stamp Contractor's Stamp

. . . . .
. . . . .
. . . . .
0 ISSUED FOR CONSTRUCTION JAM RPM 15/10/2021
Rev. Description Drawn Checked Date
Employer Project
AL-KHOBAR 2 SEAWATER REVERSE
SECTION C-C OSMOSIS DESALINATION PLANT
SCALE 1:75
Engineer Contractor
- 0001 -R 0 .1

POx No:
Drawing Title
Cod.: SA05C2 - 02 - 65 - R900

MAIN CHEMICAL BUILDING


CABLE TRAY ROUTING
SECTION 4
Scale: Drawing No: Sheet: Rev.
1:75 KRO2-WE80-U-0001 08 0
Plant North
NOTES
- ALL DIMENSIONS ARE IN mm. ELEVATIONS ARE IN m.

N
- CABLE TRAYS TO FINAL CONSUMERS SHALL BE DEFINED ON SITE ACCORDING TO
STANDARDS DRAWINGS.
- IN ORDER TO UNDERSTAND CABLE TRAYS ROUTING, 3D MODEL CAN HELP TO AVOID
CONFUSIONS.
- THE TOP TRAY OF A GROUP OF OUTDOOR CABLE TRAYS WILL BE PROVIDED WITH
49
° COVER.
- CABLE TRAYS HAVE AT LEAST 20% SPARE SPACE.
- INDOOR CABLE LADDER TRAYS AND CONDUIT NOT SUBJECT TO CORROSIVE
ENVIRONMENT SHALL BE OF HOT DIP GALVANIZED STEEL. IN ALL OUTDOOR AREAS, IN
SEMI CLOSED BUILDINGS AND IN AREAS WITH CORROSIVE CHEMICALS, THE HOT-DIP
GALVANIZED MATERIAL (TRAYS, CONDUITS AND SUPPORTS).
- THE LOCATION OF THE TRAY SUPPORTS REPRESENTED IN THIS DRAWING HAVE TO BE
TAKEN AS REFERENCE. THE FINAL POSITION WILL DEPEND ON THE CABLE TRAY
MANUFACTURER RECOMMENDATION.

1 2 3 4 5 6 7 8 9 10 11

GALVANIZED STEEL SUPPORT

SPECIAL SUPPORTS DEFINED ON SITED


SPECIAL SUPPORTS ( AS PER REFERENCE DRAWINGS )

A
SP-046
GDN035-QC001

GDN044-QC001

GDN045-QC001
GDN014-QC002

GDN065-QC001
GDN050-AP001 GDN063-QC001

GDN034-QC001
GDN052-QC001

GDN030-BB001 GDN030-BB002 GDN030-BB003


SP-045

GDN041-QC001

GDN043-QC001
GDN013-QC001

GDN064-QC001
B
GDN010-BB002 GDN050-BB002 GDN060-BB002 GDN030-BB005

GDN032-QC001
DEFINE ON SITE GDN053-QC001
SP-045 SP-046
GDN030-AP002
SP-045

GDN040-QC001

GDN042-QC001
GDN012-QC002

GDN062-QC001
+2.90
GDN030-AP001
13

GDN010-BB001 GDN050-BB001 GDN060-BB001 GDN030-BB004


GDN051-QC001

GDN031-QC001
C
GDN011-QC001

GDN061-QC001

GDN020-QC001

GDN021-QC001
D

10 12 11 XX 10 10

01 01 14 03 03 04 04 04 04 09 09 05 05 05 05 06 06 07 07 08 08 08 02 Reference Documents

FOR SUPPORT DETAILS, SEE DRAWING: KRO2-WE00-U-0900

Reference Drawings
Drawing Number
. ·
. ·

Engineer's Stamp Contractor's Stamp

Reference Documents Special Supports

01 KRO2-WE80-S-1801
. . . . .
02 KRO2-WE80-S-1802 . . . . .
03 KRO2-WE80-S-1803 . . . . .
04 KRO2-WE80-S-1804 0 ISSUED FOR CONSTRUCTION JAM RPM 15/10/2021
Rev. Description Drawn Checked Date
05 KRO2-WE80-S-1805
Employer Project
06 KRO2-WE80-S-1806
AL-KHOBAR 2 SEAWATER REVERSE
07 KRO2-WE80-S-1807 GROUND LEVEL +2.90 OSMOSIS DESALINATION PLANT
08 KRO2-WE80-S-1808 SCALE 1:125
09 KRO2-WE80-S-1809 Engineer Contractor
- 0001 -R 0 .1

10 KRO2-WE80-S-1810
11 KRO2-WE80-S-1811
12 KRO2-WE80-S-1812 POx No:
Drawing Title
Cod.: SA05C2 - 02 - 65 - R900

13 KRO2-WE80-S-1813
MAIN CHEMICAL BUILDING
14 KRO2-WE80-S-1814
CABLE TRAY ROUTING
CABLE TRAY SUPPORTS 1
Scale: Drawing No: Sheet: Rev.
1:125 KRO2-WE80-U-0001 09 0
Plant North
NOTES
- ALL DIMENSIONS ARE IN mm. ELEVATIONS ARE IN m.

N
- CABLE TRAYS TO FINAL CONSUMERS SHALL BE DEFINED ON SITE ACCORDING TO
STANDARDS DRAWINGS.
- IN ORDER TO UNDERSTAND CABLE TRAYS ROUTING, 3D MODEL CAN HELP TO AVOID
CONFUSIONS.
- THE TOP TRAY OF A GROUP OF OUTDOOR CABLE TRAYS WILL BE PROVIDED WITH
49
° COVER.
- CABLE TRAYS HAVE AT LEAST 20% SPARE SPACE.
- INDOOR CABLE LADDER TRAYS AND CONDUIT NOT SUBJECT TO CORROSIVE
ENVIRONMENT SHALL BE OF HOT DIP GALVANIZED STEEL. IN ALL OUTDOOR AREAS, IN
SEMI CLOSED BUILDINGS AND IN AREAS WITH CORROSIVE CHEMICALS, THE HOT-DIP
GALVANIZED MATERIAL (TRAYS, CONDUITS AND SUPPORTS).
- THE LOCATION OF THE TRAY SUPPORTS REPRESENTED IN THIS DRAWING HAVE TO BE
TAKEN AS REFERENCE. THE FINAL POSITION WILL DEPEND ON THE CABLE TRAY
MANUFACTURER RECOMMENDATION.

1 2 3 4 5 6 7 8 9 10 11

GALVANIZED STEEL SUPPORT

SPECIAL SUPPORTS DEFINED ON SITED


SPECIAL SUPPORTS ( AS PER REFERENCE DRAWINGS )

2850
3200 15400 4300 720 2170 9570 2170 720 5380 5535
3975

3975
GDN035-QC001

GDN044-QC001

GDN045-QC001
GDN014-QC002

GDN065-QC001
GDN050-AP001 GDN063-QC001

GDN034-QC001
GDN052-QC001

GDN030-BB001 GDN030-BB002 GDN030-BB003


2500

2500
GDN041-QC001

GDN043-QC001
GDN013-QC001

GDN064-QC001
B
GDN010-BB002 GDN050-BB002 GDN060-BB002 GDN030-BB005
2500

2500
GDN032-QC001
GDN053-QC001

GDN030-AP002
2500

2500
GDN040-QC001

GDN042-QC001
GDN012-QC002

+2.90
GDN062-QC001
GDN030-AP001
2500

2500
GDN010-BB001 GDN050-BB001 GDN060-BB001 GDN030-BB004
GDN051-QC001

GDN031-QC001
C 2170
GDN011-QC001

GDN061-QC001

GDN020-QC001

GDN021-QC001
2710
2500

2500

690
2805
1830

2310
1730

1870
1745

1600

1600

1600
1470

1000 2170 1170 2030

900
265

D 545

265
1375 1450 1375 3000 2000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000
1000 Reference Documents

FOR SUPPORT DETAILS, SEE DRAWING: KRO2-WE00-U-0900

Reference Drawings
Drawing Number
. ·
. ·

Engineer's Stamp Contractor's Stamp

. . . . .
. . . . .
. . . . .
0 ISSUED FOR CONSTRUCTION JAM RPM 15/10/2021
Rev. Description Drawn Checked Date
Employer Project
AL-KHOBAR 2 SEAWATER REVERSE
GROUND LEVEL +2.90 OSMOSIS DESALINATION PLANT
SCALE 1:125
Engineer Contractor
- 0001 -R 0 .1

POx No:
Drawing Title
Cod.: SA05C2 - 02 - 65 - R900

MAIN CHEMICAL BUILDING


CABLE TRAY ROUTING
CABLE TRAY SUPPORTS 1
Scale: Drawing No: Sheet: Rev.
1:125 KRO2-WE80-U-0001 10 0