NPTEL Assignment 3 Overcurrent
NPTEL Assignment 3 Overcurrent
Assignment -3
TYPE OF QUESTION:MCQ
QUESTION 1: Mark: 2
Select the most suitable pickup setting for a ground overcurrent relay (51N) protecting a rural distribution
feeder with rated current of 120 A,
Correct answer:(B) 40 A
Detailed Solution:
Pickup setting of a ground overcurrent relay for rural feeder is selected as,𝐼𝑝𝑖𝑐𝑘𝑢𝑝 ≥ 0.3𝐼𝑟𝑎𝑡𝑒𝑑 .
Considering the above factor, (B) 40 A is the most suitable option for pickup setting of the relay.
NPTEL Online Certification Courses
QUESTION 2: Mark: 2
What will be the operating time of an overcurrent relay following IEEE very inverse characteristic for a fault
current of 600 A?Consider the pickup setting and TMS setting of the relay as 150 A and 1.5 respectively.
Detailed Solution:
𝛽
Operating time, 𝑡 = ( 𝛼 + 𝐿) × 𝑇𝑀𝑆
(𝐼 ⁄𝐼𝑝𝑖𝑐𝑘𝑢𝑝 ) −1
For IEEE very inverse characteristic, α = 2, β=19.61, L = 0.491
Substituting I = 600 A and Ipickup = 150 A and TMS = 1.5, operating time is calculated as, t = 2.7 s
NPTEL Online Certification Courses
QUESTION 3:
Mark: 3
C B A
RC RB
Relay RB coordinates with RC. Both relays have CTs of 100:5. Maximum fault current at bus B is 1000 A.
Pickup current of both relays is 10 A. If the coordination time interval required is 0.3s. Obtain the TMS
value of RCfrom the given relay characteristics.
Detailed Solution:
Relay RBis to be set with lowest TMS value available in the characteristics, which is 0.1.
From the relay characteristics, operating time of RBwith TMS = 0.1 and PSM = 5 is close to 0.15s.
With coordinating time interval of 0.3s, operating time for RC should be should be (0.15+0.3 = ) 0.45s.
For this operating time with PSM = 5, TMS of RCwill be 0.4 (as shown below).
NPTEL Online Certification Courses
0.45
0.15
QUESTION 4-6:
D C B A
11kV, RD RC RB
50 Hz
Relays CT ratio Maximum load current Minimum fault current Maximum fault current
RB 50:5 46 A 540 A 1220 A
RC 100:5 96 A 980 A 2160 A
RD 200:5 170 A 1552 A 3880 A
A 11kV, 50 Hz distribution feeder is shown in the figure. All the overcurrent relays shown in the system are
set with IEEE standard moderately inverse characteristics. Maximum and minimum fault currents observed
by the relays are provided in the Table withthe maximum load currents and CT ratios at the corresponding
buses.
Available TMS settings = 0.025, 0.05, 0.1, 0.25, 0.5 and 1
Throughout calculation, consider values up to 2 decimal points.
QUESTION 4: Mark: 3
Different sets of pickup settings (A) for relay RB, RC and RD are provided below. Which set violates the
security and dependability constrain of the overcurrent relay?
Correct answer:(C)
NPTEL Online Certification Courses
QUESTION 5: Mark: 5
Considering the pickup setting for all the relays to be the next higher integer of the 2 times of maximum load
current at the corresponding buses and a coordination time interval (CTI) of 0.3s, which is the correct set of
TMS settings for the relays RB, RC and RD respectively?
Correct answer:(C)
QUESTION 6: Mark: 3
Considering pickup and TMS settings of the relays as calculated in Question 5, what will be the operating
times (in second) of the relays RB, RC and RDfor maximum fault current at bus B?
Correct answer:(D)
NPTEL Online Certification Courses
Detailed Solution:(4 to 6)
For Question4: pickup setting of RCin (C) is above minimum fault current level i.e. 40 A> 38.8 A
For Question5: As mentioned above, TMS settings for relays RB, RC and RD are 0.025, 0.25 and 0.5.
For Question6:
𝛽
For maximum fault current at B, operating time of the relay RB, = (((1220 ⁄ + 𝐿) × 0.025= 0.03 s
10)⁄10)α −1
𝛽
For maximum fault current at B, operating time of the relay RC, = (((1220 ⁄20)⁄10)α−1 + 𝐿) × 0.25 = 0.38 s
𝛽
For maximum fault current at B, operating time of the relay RD, = (((1220 ⁄40) ⁄10)α−1 + 𝐿) × 0.5= 1.2 s
QUESTION 7: Mark: 2
For the system shown consider all the relays are of directional overcurrent type. For fault at F, which relays
will operate the circuit breakers in case of failure of primary relay from A end.
D C
RDC RCD RCB
RDA
F
RAD RAB RBA RBC
A B
Detailed Solution:
For fault at F, primary protection is provided by R AB at bus A and RBA at bus B. In case of failure of relay at
bus A, back-up protection will be provided by RDA at bus D. So the isolation will be provided by the
decision of RDA and RBA.