ICTSAD609 Project Portfolio - GBC220051
ICTSAD609 Project Portfolio - GBC220051
ICTSAD609 Project Portfolio - GBC220051
Student Version
ICTSAD609
Plan and monitor business analysis
activities in an ICT environment
CONTENTS
Section 1: Establish business analysis approach
Section 2: Plan business analysis activities and communication
Section 3: Manage business analysis
Student name & ID: QUANG THANH NGUYEN
Date: 18/09/2022
description of
what the
business
does.
o a improved security
descripti fewer issues with compliance
on of
the The continuation of business is assured
initiative less internal IT staff is required
an lower expenses
explanation
of how each rapid expansion across borders
initiative Rapid scalability with on-demand access to extra resources
supports the
organisation’ 2. Implementing artificial intelligence technology
s vision and Artificial intelligence technology that can monitor each child's development, adapt
strategy to their needs as they learn, and Digital Assistance that is available around-the-
an clock will create the best possible learning environment.
appropriate The simulation of human intelligence functions by machines, particularly
Faster Decisions
Daily Applications
New Inventions:
Swot Analysis:
Strengths Weaknesses
hospitable organizational
culture.
Level of investment-ready
financing .
Opportunities Threats
Opportunities for
collaboration between all
goods and services.
Legislative and To ensure everyone's safety and the success of the business or organization,
organisational standards, legislation, and organizational policies/procedures are put in place.
requirements They also give instructions on how things should be done, which will affect the
method we decide to use for business analysis. Legislation is the process or
Establish the
product of enrolling, enacting, or promulgating law by a legislature, parliament, or
a summary Standards
of the
Information about recommended practices can be found in ISO standards.
associated
They are a collection of best practices guidelines that experts from around
organisation
the world have agreed upon for a variety of professions, workplaces, and
al policies
sectors. For instance, Worlducation complies to ISO standards:
and
procedures Standards for quality management to increase productivity and decrease
product failures.
Attach any
relevant policies Environmental management guidelines to help with waste reduction,
to your portfolio. environmental impact reduction, and sustainability.
Food contamination can be avoided with the use of food safety regulations.
Identify Using the Worlducation case study: a sample answer for ONE initiative may
stakeholders include:
Produce a Stakeholders may be identified using an Affinity diagram and may include:
complete list of
End-users and teachers
everyone involved
in, affected by or board of directors (guide decision-making and represent share-holders)
responsible for
CEO (reports to the board, ultimately responsible for cashflow)
each initiative. In
explain how
you will
identify and
deal with
new
stakeholders
Establish process Using the case study, a sample answer for ONE initiative may include:
needs
Relevant personnel:
Use standards
Software developers to develop the cloud based and artificial intelligence
and (email to request outline of work to be completed)
policies/procedur
es to establish o developing a cloud-based solution where customers can access the
organisational software remotely on their own devices (estimated cost of $2 million)
process needs o implementing artificial intelligence technology that can follow up on
applicable to each each child’s progress and adjust to their needs as they learn, creating
business analysis the optimal path learning experience.
initiative,
including: Finance manager (meeting request for information on financing)
System Developer
Worducation,
Dear Sir/Madam,
Financing Request
Laws and rules regarding privacy that vary by country
Regulation of content
criteria for regional languages
Having conversations with important parties
management tool for projects
requirements for management and storage
Kind Regards
Plan execution of Business analysis activities for each initiative.may include:
activities
Create a business analysis plan
Plan the
Conduct stakeholder analysis and form a stakeholder management plan
execution of
business analysis Engage with stakeholders
activities
Establish software adaptation requirements, in accordance with ISO
according to
standards
organisational
requirements for Identification of technology solution patterns
each initiative.
Training requirements
Legislation ☒
Software protection and licensing UML use case diagram example for Sentinel License
Development Kit. (uml-diagrams.org)
Determine business With the exception of those that have already been budgeted for, the
analysis scope business analysis will be carried out with the use of previously available
resources. Two weeks after the meeting, the work will be finished.
Scope business analysis
Deliverables required include:
activities for each
initiative, considering: • Business analysis plan
Develop estimates for Uisng the case study, a sample answer for ONE initiative may include:
business analysis work
A PERT value for each element and calculate the estimate as a weighted
Use an appropriate average:
technique to estimate (Optimistic + Pessimistic + (4 times Most Likely))/6.
business analysis work,
Time elements to consider:
including the use of
numeric and financial Optimistic Pessimisti Most likely PERT
information and c Value
mathematical
calculations. Business 80 hours 90 hours 82 hours 83 hours
analyst
Cost
Total $12715
Plan internal and external Communication constraints may include time zone differences and
stakeholder conflicting policies for communication platforms used by various
communication for each stakeholders (e.g. MS Teams vs Zoom).
initiative, considering for
o CEO (tactic change)
each stakeholder:
o Sales manager (responsible to sell and promote new software)
how to:
o ICT manager (responsible to develop new software)
o receive
information o Business analyst (responsible to analyse requirements and
communicate with stakeholders)
o distribute
information External:
o access o Teachers in different countries (provide requirements)
information
Receive Distribute Access Update Escalate
o update
information CEO Executive ICT Cloud ICT Board
team based
Social media
post
Plan business analysis Business Analysis Performance Metrics: Actual performance measures
performance are captured, analyzed, and become the basis for taking corrective or
management preventive action. Capturing actual performance metrics is a process that
occurs through the business analysis effort and is implicitly a potential
Plan business analysis
output from every business analysis task.
performance. Include:
Performance metrics:
at least three metrics
to measure work deliverable due dates,
performed by
number of review cycles,
business analyst
frequency of changes to requirements,
reporting format.
stakeholder feedback.
Develop a requirements An MS Excel spreadsheet will be used to capture requirements due to the
management process. short notice of the project.
Develop a requirements Attributes will include: unique requirement identifier, requirement name,
management process by requirement description, version number, requirement type, change
establishing a history, requirement status, requirement priority, trace information.
requirements repository,
Traceability is required, particularly for requirements of end-users. Due to
including:
Requirements
change process
Prepare for stakeholder Using the case study, they may for example choose to update the project
meeting schedule to show progress.
Prepare for the
Meeting minutes template:
stakeholder meetings
(e.g. by updating the
project schedules).
Attach proof.
Minutes of Meeting
Date: 10/09/2022
frequency of
3 Discuss 15/09/2022
changes to
and identify the
requirements frequency of
changes to
METRICS:
1: deliverable due dates
4: stakeholder feedback
OVERALL PERFORMANCE
Rate the employee’s general performance in relation to their
continuous improvement efforts
IMPROVEMENT OPPORTUNITIES
Attach: Proof of requirements tool/technique used in stakeholder ☒
meeting
Summarise business analyst Using the case study, a sample answer may include:
meeting
The business analyst approved with their performance assessment
Summarise what was and was ready to take communication training. They expressed
discussed at the business gratitude for the compliments on their attention to detail and indicated
analyst performance that they had put in extra effort to achieve high-quality deliverables.
management meeting. In you
answer include:
A summary of the
discussion
Corrective actions
required
Dear Sir/Madam,
● Our legal team asked for at least for 5 weeks for the negotiation
with local educational structures. It will be done by October 7th.
● We also plan to add three extra weeks for all processes to fix bugs
and mistakes with the team.
Regards,
Business analyst
Problem solving The student must explain how they used existing experience to solve
problems during the problem analysis initiative.
Explain how you managed
problem solving for business For example, they may mention that previous experience with
analysis activities drawing on communication across different time zones helped them choose
your existing experience. alternative forms of communication (e.g., email as opposed to
conference call).
Performance Review
Team member: Business Analyst Project:
Worducation Date: 05/09/2022
Overall performance
Rate the employee’s general performance in relation to their
continuous improvement efforts
1 X
IMPROVEMENT OPPOrtunities
Strengths: Well,
defined
Improvements
required: Internet
speed
Training needs:
Email writing skill