Insulation Works
Insulation Works
Insulation Works
1. Distribution is centralized - in this case through ACONEX. Any improvement suggestions should be forwarded to the
Quality Control Engineer
2. Each copy is issued to a particular person or organization.
3. Copy holders will be automatically issued with any amendments through ACONEX.
4. Photocopies of this document are uncontrolled and users should confirm validity inACONEX prior to use.
TWJO-ITP-E&M-0012 revA
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101&CP102 Inspection and Test Plan
Approval:
Jakarta Mass Rapid Transit Project CP101&CP102 Inspection and Test Plan
Contents
Cover Sheet
Revision History
Contents
Covered Scope Activity
Flow Chart
Inspection and Test Plan for Insulation Works (CP101-CP102)
2. Checklist
TWJO-ITP-E&M-0011-CHK-0001 rev A Insulation Ducting Works
TWJO-ITP-E&M-0011-CHK-0002 rev A Insulation Pipe Works
TWJO-ITP-E&M-0012 revA Contents
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101&CP102 Inspection and Test Plan
Scope of this Inspection and Test Plan Material check and Visual check. The inspection work by QC
Engineer of subcontractor for Internal Inspection, checked by QC Engineer of TWJO and JMCMC
Engineer as the Acceptance for the Result of Inspection. Inspection and test plan for duct work
insulation cunducted by unit ,and pipe work insulation work shall be conducted zone by zone (sample
schematic drawing is attached).
Flow Chart
Start
Submit
Material Sample Approval (MSA), Revise
Method Statement (MS),
Inspection & Test Plan (ITP)
OK
Material Preparation
1. Spesification of material Insulation
2. Surface Cleaning Repair
Not OK
OK
Installation insulation work Not OK
OK
OK
Not OK
Submit Request For Inspection (RFI)
OK
JMCMC and TWJO
Joint Inspection (material & Visual, Check)
OK
End
TWJO-ITP-E&M-0012 revA
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project
Subcont QC
Material sample Approval
Once Before Personnel &
1 Approval For Material Insulation (TWJO-MSA-0129, TWJO- Approved Material Supplier Certificate P R R A
Procurement TWJO QC
MSA-0141 )
Engineer
2 Preparation Before Installation
Subcont QC TWJO-ITP-E&M-
Once Before Insulation No Spatter, Mill Scale, Oil, Personnel & 0012-CHK-
- Surface Preparation NA P W I A
work Process Grase and rust TWJO QC 0001,0002, Insulation
Engineer Works Checklist
Subcont QC TWJO-ITP-E&M-
Material sample Approval
Once Before Insulation Personnel & 0012-CHK-
- Material Insulation Check (TWJO-MSA-0129, TWJO- ASTM C-533-13 P W I A
work Process TWJO QC 0001,0002, Insulation
MSA-0141 )
Engineer Works Checklist
3 Check After Installation
Subcont QC TWJO-ITP-E&M-
Once After Insulation Good For Construction Personnel & 0012-CHK-
- Visual Installation Check As Per Drawing P W W A
Work Drawing TWJO QC 0001,0002, Insulation
Engineer Works Checklist
Legends P: Perform R: Review I: For Information only H: Hold point W: Witness point NA: Not Applicable RW: Random Witness
Name: Name:
Signature: Signature:
All approved ITPs and related records shall be stored on TWJO server under Quality Assurance folder with a hard copy in office file.
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project