93doc04 0
93doc04 0
93doc04 0
PAPERS
ALTERNATIVES FOR
THE U.S. TANK
INDUSTRIAL BASE
February 1993
ALTERNATIVES FOR
THE U.S. TANK
INDUSTRIAL BASE
February 1993
The U.S. military has no plans to purchase new tanks after 1992. Without
U.S. sales, tank production in this country might cease, leaving in question the
ability of U.S. tank manufacturers to produce tanks should they be needed
during a crisis. This paper, prepared at the request of the House Committee
on Armed Services, explores various options for maintaining the U.S. tank
industrial base. The options differ widely in terms of their cost and the
insurance they provide against an unforeseen need for new U.S. tanks. This
information may be useful to the Congress as it debates the fate of the
defense industrial base in this time of fiscal constraint. In keeping with the
Congressional Budget Office's (CBO's) mandate to provide objective analysis,
the paper makes no recommendations.
Robert D. Reischauer
Director
February 1993
CONTENTS
SUMMARY 1
CONCLUSION 36
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE
TABLES
FIGURES
The shrinking of the U.S. military, coupled with the disappearance of a long-
time foe and the unprecedented peacetime investment in modern weapons
that occurred in the 1980s, has led to sharp reductions in the planned
purchases of military weapons. In particular, the Bush Administration did not
plan to buy any new tanks for U.S. forces for the next 15 or more years.
Without U.S. purchases, the U.S. industrial base dedicated to producing tanks
could close and would eventually atrophy.
With no further purchases of new tanks, one alternative would be to lay away
and preserve the physical portions of the tank industrial base after all orders
for tanks have been filled. Taking into account the Bush Administration's
plan submitted in February 1992, Congressional action on the fiscal year 1993
budget, and current orders, this layaway process could begin in 1994 and could
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE
The Abrams tank fleet envisioned for 1995 will not only be very capable
but also relatively young; the oldest Abrams tank will be only 15 years old.
Given that the useful service life of a tank is typically assumed to be 30 years,
the United States should not need to produce new tanks to replace aging
vehicles until 2010 or later, again confirming the Bush Administration's plan
to buy no new tanks for at least 15 years.
Laying away the tank line would be the least costly alternative examined
in this paper, requiring a total of $340 million for the five years from 1994
through 1998 (see Summary Table 1). (All costs in this paper are expressed
in 1993 dollars of budget authority.) These funds would be used to preserve
the physical portions of the tank industrial base~the plants, machines, and
assembly lines~and for personnel costs associated with ceasing production of
tanks. Thereafter, maintaining facilities in mothballed status and providing
security would cost about $40 million a year. The Army estimates that a line
that has been laid away for more than two years would take about 72 months
and $1.1 billion to start producing tanks again at surge rates (defined as 120
tanks a month). Moreover, based on historical evidence, the first vehicles off
a restarted tank line might not be of high quality.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE
Cost to Reach
Annual Surge Caoacitvc
Cost, Cost After Time
1994-1998a 1998b (Months) Funds
Alternative I:
Lay Away Tank Line 340 40 72 1,110
Alternative II:
Produce at Low Rate 3,830d 740d 47 600
Alternative III:
Convert Older Models 2,210 d - e 650d-f 56 530
a. Does not include $15 million to lay away the assembly line at the Detroit Arsenal Tank Plant.
c. Surge capacity is 120 tanks per month and would require two assembly lines operating on multiple shifts.
d. Assumes additional production of 120 tanks per year to fill orders from foreign governments.
e. The proposed budget revisions submitted by then Secretary of Defense Dick Cheney in January 1993 include
an estimate of $720 million as a minimum sustaining level.
f. According to the proposed budget revisions submitted in January 1993, a minimum annual investment of $250
million would sustain the program, but would convert only 60 tanks per year rather than the 198 funded in
the alternative.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE
45-year empire in Eastern Europe, this may not be an auspicious time for the
United States to be without the capability to produce tanks. Continuing to
maintain the tank industrial base, at least until the new world order becomes
more certain, might be a sound insurance policy.
To reduce both the risk of losing the ability to make tanks in the near term
and the time needed to start producing tanks in large numbers at some time
in the future, should they be needed, the United States could keep the entire
industrial base active by producing new tanks at a low rate of 10 per month.
Maintaining production at a low rate would ensure that workers trained in
each of the skills critical to building tanks would be available at all times,
though not necessarily in large numbers. Keeping the base warm would
appreciably shorten the time needed to start producing new tanks at surge
rates, from as much as 72 months from layaway to 47 months from low-rate
production. Contractors would need this time to hire and train the additional
personnel required to operate two assembly lines on multiple shifts. Although
47 months would still be longer than the duration of the most probable future
contingencies, the shorter response time could be significant if a major new
threat emerges that would require an increase in the size of the Abrams tank
fleet.
This alternative would also provide the Army with 120 additional new
tanks every year-tanks that the Army does not need to support the force
planned for 1995. Because they would be a more recent and capable version,
newly produced tanks could replace some of the older Abrams tanks in the
inventory. The overall improvement in capability resulting from new tanks
delivered to the Army by the year 2000 would be small, however~on the order
of 2 percent.
The major disadvantage of this alternative is its high cost, which could
total $3.8 billion from 1994 through 1998~more than 10 times the cost of
laying away the line (see Summary Table 2). In 1998 and thereafter, annual
costs to produce 120 tanks each year would be more than $700 million,
compared with $40 million for the previous alternative.
As a compromise between producing tanks at a low rate and laying away the
tank industrial base, the United States could convert older and less capable
models of the Abrams tank to the newest, most sophisticated configuration.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE
This latest model, designated the M1A2, has a bigger, more powerful cannon
than the Abrams tanks produced in the early 1980s, as well as better armor
protection, digital electronics, better electro-optics, and a system for
preventing harmful nuclear, biological, or chemical contaminants from
reaching the crew. Converting an original Ml to an M1A2 involves taking the
tank almost totally apart and replacing all of the major components except for
the engine and transmission. Thus, conversion would involve all parts of the
industrial base except those that produce engines and transmissions. The
Army currently plans to fund a program to upgrade 210 Ml tanks from 1993
through 1995. The converted M1A2 tanks, in addition to new M1A2 tanks
already purchased, would equip one division in the Army's contingency force,
which would fight in regional wars such as Operation Desert Storm. To equip
the entire contingency force, the Army would need to upgrade a total of 1,002
Five-
Year
1994 1995 1996 1997 1998 Total
Alternative I:
Lay Away Tank Line 50 30 140 80 40 340
Alternative II:
Produce at Low Rate* 780 800 760 740 750 3,830
Alternative III:
Convert Older Models
Phase I 80 130 0 0 0 210
Phase H a - b 0 150 550 650 650 2,000
SOURCE: Congressional Budget Office based on Army data and Congressional action on the 1993 budget
request.
NOTE: Costs do not include about S15 million to lay away the assembly line at the Detroit Arsenal Tank Plant.
b. According to then Secretary of Defense Dick Cheney's proposed budget revisions submitted in January 1993,
a minimum annual investment of $250 million would sustain the program after 1995, but at 60 conversions per
year rather than the 198 conversions funded in the alternative.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE
Ml tanks. Although the Army would like to convert an additional 792 tanks
to the M1A2 configuration, it is not yet sure how it will structure or fund such
a program.
By other measures, this approach lies between the previous two. About
56 months would be needed to start producing new tanks at surge rates from
a line dedicated to conversion. This period falls between the delays
associated with the other two options and is sufficiently long so that large
numbers of additional new tanks would not be available for short-notice
contingencies. The costs would also fall between those of the previous two
options. In 1994 and 1995, the Army plans to spend at least $220 million on
conversion, three times the cost of layaway but about one-seventh the cost of
low-rate production. Beyond 1995, costs would still fall between those of the
other two options, but the level of funding would depend on how the
conversion program is structured. Under the Army's plan as of fall 1992,
annual costs might total $650 million, which would sustain the tank line and
convert 198 tanks a year to the M1A2 configuration. Under the budget
revisions submitted by then Secretary of Defense Dick Cheney in January
1993, conversion costs might amount to as little as $250 million a year beyond
1995. This lower funding would sustain the tank line (assuming foreign sales
of 120 tanks a year), but the Army has indicated informally that it is not clear
how many tanks could be converted.
The Congress has directed that funds appropriated for fiscal year 1992 be
used in 1993 to convert older tanks to newer models. The question it must
now address is whether the conversion program should continue and, if so, at
what pace and for how long.
If the overriding criterion is to limit costs, then the option to lay away
the tank base should be pursued instead. In the next two years, 1994 and
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE
Closing down and laying away the tank line, especially during the next
two years, involves risks that a program that sustains the tank base would
avoid. Inability to respond to an unforeseen threat to U.S. security is one
such risk. Russia could again become a highly militarized society, but that
seems unlikely. The emergence of a developing nation equipped with
sophisticated tanks obtained on the global arms market is perhaps a more
likely scenario. U.S. responses to such threats could require additional tanks
or upgraded versions of the Abrams tank in order to ensure that U.S. forces
retain their superiority.
The time and effort needed to resurrect a tank line that has been laid
away are also uncertain. If restarting production takes longer than is currently
estimated, the risk of failure to meet an unanticipated threat is greater. Risks
also increase if the ability of a reopened line to produce quality tanks has
been overestimated. The risks associated with restarting the line may be
greater than currently estimated because the planned shutdown is likely to be
at least 15 years, a rather long time. A conversion program, or one that
maintains low-rate production, would ensure the availability of quality
components as long as it continued. Programs that maintained most of the
base in active status might avoid the problems of quality associated with
producing tanks from a restarted production line that had been long idle.
Even if these programs were continued for only a few years, they would also
provide additional time to study the issues related to closing down the tank
line completely.
Although the lack of need for an active tank line may be welcome news
in an age of constrained military budgets, it also causes concern about the
possibility that the United States could, in the near future, be unable to
produce tanks. This inability may be particularly troubling in a world that
recently witnessed a major war in the Persian Gulf that featured the use of
tanks and other armored vehicles. Questions have been raised regarding the
continued ability of the United States to produce modern tanks in response
to changing world conditions, should an unforeseen threat emerge. In
response to these concerns, members of industry and the Congress have
suggested options for maintaining all or part of the tank industrial base.
This paper describes the U.S. industrial base for producing tanks,
outlines the tank requirements of the U.S. Army, and then presents and
examines options for preserving the tank industrial base in either an active or
a stored mode.
Private Corporations
Government Facilities
Subcontractors
The major contractor for the Abrams tank is General Dynamics, Land
Systems Division (GDLS). As operator of the government-owned tank plants
at Lima, Ohio, and Warren, Michigan, it is responsible for delivering finished
tanks to the Department of the Army.1 In addition, several other firms have
contracts with the Army to produce major components such as engines or
transmissions, which the Army then turns over to GDLS for incorporation into
the finished tank. Some producers in this category are private companies such
as Textron Lycoming, which supplies the tank engines. Others are Army
installations such as Rock Island Arsenal, which provides the gun mounts, and
Watervliet Arsenal, which makes the cannons. The facility that manufactures
armor inserts out of depleted uranium is operated by DOE. Most of these
facilities also produce other items or perform other services. A few, the DOE
armor facility being one example, are supported solely by work related to tank
production.
To fully support its fighting forces, the Army needs many tanks in addition to
those that equip its armored units. The Army must provide tanks for the
Armor School to train tank crews, it must have sufficient spare tanks on hand
to replace those that need repair, and it must maintain reserve stocks to be
1. The tank plant at Warren, Michigan, is also known as the Detroit Arsenal Tank Plant.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 11
SOURCE: Congressional Budget Office based on U.S. Anny, Tank Industrial Base Briefing* (February 20,
1992).
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 12
Michigan 561 18
Connecticut 550 18
Ohio 419 14
Indiana 392 13
California 314 10
New York 142 5
Pennsylvania 128 4
Illinois 93 3
South Carolina 83 3
New Jersey 58 2
Alabama 57 2
Canada 50 2
Massachusetts 45 1
Florida 34 1
North Carolina 23 a
Maine 16 a
Texas 16 a
Virginia 12 a
Oregon 12 a
Missouri 8 a
Iowa 4 a
Minnesota 4 a
Arizona 4 a
New Hampshire 2 a
Wisconsin 2 a
Remaining States _68 _2
SOURCE: Congressional Budget Office based on U.S. Army, Tank Industrial Base Briefing" (February 20,
1992).
used in the event of war. Finally, the Army maintains extra sets of tanks
overseas, primarily in Europe, that would be available for immediate use by
combat units stationed in the United States. These additional requirements
approximately double the number of tanks that the Army needs solely to
equip its armored units in order to support its forces fully.2
Current Inventory. The U.S. Army now has almost 16,000 tanks of all types,
about double the size of its tank fleet in 1974 (see Figure 2). This increase
in the number of tanks was not necessitated by any increase in the size of the
Army's armored forces. Rather, the Army needed the increased inventory
primarily because the United States decided to preposition several divisions'
worth of tanks in Europe, a policy designed to speed the deployment of U.S.
forces in the event of a major war. Additional tanks were also needed to
provide war reserves that were stored in Europe and would be used to replace
tanks lost in combat.
In addition to expanding its tank inventory during the last 20 years, the
Army was purchasing better tanks—specifically, the Abrams, regarded by many
as the best tank in the world.3 The Army's procurement of the Abrams,
which started in 1979, ended in 1992. The Army's current inventory includes
about 7,700 Abrams tanks, the oldest of which is 13 years old. The Army also
has many older and less capable tanks, including about 7,300 M60 tanks that
range in age from 10 to 27 years old, and slightly less than 900 M48s that are
over 30 years old and obsolete (see Table 3).
Smaller Inventory Needed for 1995 and Thereafter. The Army estimates that
it will have 7,780 Abrams tanks in its inventory in 1995. The Congressional
Budget Office calculates that this number of tanks will suffice to equip the
force proposed by the Bush Administration for 1995. Reflecting changed
circumstances in the world, the Bush Administration proposed reducing the
size of the Army so that by 1995 it would be about 30 percent smaller than
it was in 1990. As a consequence, the number of tanks needed to equip the
Army would also be reduced. CBO's analysis assumed current levels for
equipping forces, and proportional requirements—based on current levels—for
tanks needed for training, spares, and war reserves. Based on the Bush
Administration's plans, CBO also assumed the need for 2% divisions' worth of
prepositioned stocks. Using these assumptions, CBO calculated that the
Army's need for tanks will decrease from approximately 11,100 to support
2. This estimate does not include tanks needed by the Marine Corps, which are not addressed in this paper.
3. In his testimony before the Senate Committee on Armed Services, General Colin Powell, the Chairman of
the Joint Chiefs of Staff, stated that the Army's M1A1 tank is unmatched in the world.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 14
1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992
Fiscal Year
SOURCE: Congressional Budget Office based on John M. Collins, U.S.-Soviet Military Balance: Concepts and
Capabilities, 1960-1980 (New York: McGraw-Hill Publications, 1980); International Institute for
Strategic Studies, The Military Balance (London: Brassey's, various editions); and Army data.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 15
28 divisions in 1990, to about 9,600 for the current force. By 1995, the Army
would need fewer than 8,000 tanks to support the 20 divisions that it plans to
retain in its force structure, which includes 12 active, six reserve, and two
cadre divisions.
Total Inventory
Required Inventory
SOURCE: Congressional Budget Office based on Army data and on The Analytic Sciences Corporation, The
TASCFORM Methodology: A Technique for Assessing Comparative Force Modernization, 4th ed., rev.
(Arlington, Va.: TASC, July 1991).
Comparison with Tank Fleets from Other Countries. Even though the U.S.
tank inventory may be shrinking during the next three years, it will still be
more capable than the inventories of most other countries (see Figure 3).
This advantage stems in part from the fact that each tank in the U.S.
inventory will be highly capable, but also from the significant changes that are
expected in the tank inventories of other countries. Just as the United States
must reduce its European tank holdings to comply with the Conventional
Forces in Europe (CFE) Treaty, so too must other European countries. Thus,
for example, the size of Ukraine's and Russia's tank holdings in Europe will
decrease significantly by 1995. And Germany will have to dispose of most of
the equipment it inherited from the East German army.
Russia will be the only country to possess a tank fleet that will be larger
and more capable than the U.S. Abrams fleet. In 1995, Russia could have
35,000 tanks, whose combined capability would be twice that of the U.S. fleet.
This fleet will be dispersed over the entire Russian expanse, however, which
stretches more than 5,000 miles from the Baltic countries to Siberia.
4. The Analytic Sciences Corporation, The TASCFORM Methodology: A Technique for Assessing Comparative
Force Modernization, 4th ed., rev. (Arlington, Va.: TASC, July 1991).
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 17
SOURCE: Congressional Budget Office based on data from the International Institute for Strategic Studies, The
Military Balance, 1992-1993 (London: Brassey's, Autumn 1992); The Analytic Sciences Corporation,
The TASCFORM Methodology: A Technique for Assessing Comparative Force Modernization, 4th ed.,
rev. (Arlington, Va.: TASC, July 1991); and Army data.
The U.S. Army therefore does not have an immediate need for new
tanks. It can equip and support the planned forces with Abrams tanks that
have already been purchased. Furthermore, the Abrams fleet is composed of
new tanks; the oldest will be just 30 years old in 2010. Because the Army has
retained tanks in its inventory for 30 years or longer, production to meet
inventory requirements can, in theory, be delayed until 2010 or later. Finally,
the superiority of these tanks was well established by their performance in the
Persian Gulf War.
Future Trends and Their Potential Impact on the U.S. Tank Fleet. Two types
of threat could emerge during the next decade that could compel the Army
to buy new tanks before 2010, although neither seems probable. The first
would be the reemergence of a military entity capable of fielding a large
armored force similar to that of the former Soviet Union. The second would
be the fielding, in significant numbers, of a tank that would be technologically
superior to the Abrams tank. Either occurrence could force the United States
to build and field more sophisticated tanks to counter those of a potential
adversary.
and must contend with the combined forces of the North Atlantic Treaty
Organization.
Moreover, building many new tanks would not be the only way for the
United States to respond to such a threat. A cheaper and more timely
response would be to retain or reconstitute some of the forces scheduled to
be eliminated in the next few years. Such units could be equipped with tanks
currently in the U.S. inventory, such as the M60A3. Unless they are sold,
given away, or destroyed, several thousand surplus M60A3 tanks, which are
not part of the required inventory, will remain in the U.S. inventory for many
years to come. Though not as capable as the Abrams, these tanks are
nonetheless a match for many tanks currently fielded by the former Soviet
Union and almost all tanks fielded by developing countries.
The question that needs to be answered, then, is will the United States need
more than 7,780 capable tanks in the period before a successor to the Abrams
is produced, probably sometime after 2010? Largely as a result of the
diminished threat from the Warsaw Pact and the Soviet Union, the
overwhelming need that motivated many Army programs for so long no longer
exists. However, inasmuch as no one could have predicted the collapse of the
Warsaw Pact and the Soviet Union two years ago, no one can say with
certainty that no new or rejuvenated threat will emerge in their place in the
next 15 years. Maintaining the ability to produce tanks, should they be
needed, can be viewed as an insurance policy for these uncertain times.
Whether it is worth the cost of the premium in this time of fiscal constraint
and how long it is needed are questions that both the Administration and the
Congress need to address. To help in this debate, CBO examined three
options of various costs for maintaining some parts of the tank industrial base
for the foreseeable future.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 20
The options for preserving the tank industrial base range from putting it in
mothballs after completing currently planned tank production to continuing
tank production at a low rate. CBO examined both of these options but also
considered an intermediate alternative that would modify tanks in the current
inventory to make them more capable. The options would add similar
capability to the active inventory, but they differ in their cost and in the
amount of insurance they provide in retaining the ability to produce tanks if
a crisis arises.
The options also vary in the impact that they would have on the jobs of
people employed in the tank industrial base. Although this issue is of great
concern to all involved, it was not the focus of this paper and so was not
analyzed.
Realizing that the Army has no near-term need for new tanks, the United
States drastically reduced its annual purchases of Abrams tanks for the Army
from a total of 481 tanks in 1990 to 18 in 1992. After 1992, the Bush
Administration's budget, as submitted in February 1992, includes no funds to
buy new tanks. Following the pattern of declining purchases, the annual
production of tanks has fallen significantly from the 718 produced in 1990 to
the 484 produced in 1992. Assembly of tanks for the United States will
continue through 1993. After that time, no new tanks will be produced to fill
U.S. orders until the next generation is needed. At the Congress's direction,
the Army will modify 54 older Abrams tanks to a more capable configuration
starting in 1993.
Plans for the tank program during the next five years are uncertain. The
Army has proposed a conversion program in two phases, the first of which
would upgrade 210 tanks and would require funding in 1994 and 1995. The
second phase would upgrade almost 800 additional tanks and would require
funding for several years after 1995. The revised budget submitted by then
Secretary of Defense Dick Cheney in January 1993 fully funded the first
phase, but provided only minimal funds for the second. Furthermore, the
Bush Administration did not set a firm date for when the Army will start
producing its next tank, although the current inventory of Abrams tanks will
begin to reach the end of its estimated useful life in 2010.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 21
Should the United States cease producing tanks in 1997, one option
would be to lay away the additional major facilities associated with tank
production that would no longer be needed. The manufacturing equipment
unique to tank production would be stored in place and protected from the
elements, if necessary. Government-owned buildings would be closed and
guarded. Leased facilities would continue to be rented so that they would be
available if needed. In short, the physical portions of the tank production
base would be stored for future use. While preserving the production
5. The Bush Administration proposed this course of action in its February 1992 budget submission. The proposed
budget revisions submitted in January 1993 by then Secretary of Defense Dick Cheney include funds for the
tank conversion program described earlier. The Clinton Administration is currently considering its plans for
the tank program.
6. Without the program to convert 54 tanks in fiscal year 1993, the DOE facility would have closed in December
1992. Because the facility can produce 20 armor sets per month, it could be ready for shutdown sometime in
fiscal year 1993.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 22
facilities, the Army could continue to develop a tank to replace the Abrams
fleet starting in 2010.
Time and Cost to Restart Production. When production resumes and the
industrial base is needed again, time will be needed to take it out of
mothballs and to find and train the people to run it. If the line remains shut
for more than two years, restarting it could take a long time. First of all,
some skilled personnel in jobs that require extensive training would, according
to the Army, have to be retrained to regain their skills.7 Retraining for some
tasks, such as armor welding, could take six months, according to Army
estimates.
Second, the Army claims that, after a hiatus of two or more years, the
DOE facility could take two years to be recertified and start producing special
armor. (Of course, if an urgent need arose for tanks to meet a national
emergency, this recertification requirement could be waived or expedited.)
After certification, producing the first set of armor would take another 18
months, for a total delay of 42 months. According to the Army's analysis, the
special armor is responsible for the longest delays when restarting an inactive
tank line. Thus, all the other components should be available when the armor
is ready.
Finally, another nine months would be needed to assemble all the parts
into the first tank. In all, it could take up to 51 months to rejuvenate the
industrial base and produce the first tank. In a time of crisis, however, the
Army will need tanks in large numbers. Increasing production rates takes
time because more trained workers are needed and shifts are added. In fact,
attaining a production rate of 120 tanks per month could take an additional
21 months. Thus, a total of six years might elapse before tanks would be
produced in large numbers.
7. Retraining time might be minimized if the government developed and maintained an up-to-date list of the
addresses of personnel with skills critical to the manufacture of tanks. Such a list might be maintained by
offering people with critical skills a modest remuneration in return for keeping the government informed of
their whereabouts. Alternatively, the contractors or the Army could establish schools to maintain the critical
skills of people who would no longer be involved in tank production.
8. The estimate of $1.1 billion includes only training and start-up costs. Production would require additional
funds.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 23
Cost to Lay Away. The Army estimates that laying away and storing the tank
industrial base will cost $340 million in 1993 dollars over the next five years
(see Table 4). That amount includes $200 million to meet the one-time costs
associated with ceasing tank production and laying away the tank facilities
(see Table 5). One-time costs would cover personnel separation, laying away
facilities and equipment, managing the layaway, and environmental cleanup.
Costs associated with management and personnel separation form the largest
component of one-time costs (45 percent); the remaining 55 percent would be
devoted to layaway and cleanup. The Army admits, however, that its analysis
of potential environmental costs is not complete and that those costs could be
much higher.
Laying away the tank production base would also create annual recurring
costs for as long as the lines are in storage. From 1994 through 1998,
recurring costs for security and maintenance of the laid-away facilities
1993 Total
and 1994-
Before 1994 1995 1996 1997 1998 1998
Alternative I:
Lay Away Tank Line 0 50 30 140 80 40 340
Alternative II:
Produce at Low Rate* 0 780 800 760 740 750 3,830
Alternative III:
Convert Older Modelsb
Phase I 680 80 130 0 0 0 210
Phase II a ' c 0 0 150 550 650 650 2,000
NOTE: Costs do not include about $60 million to lay away the assembly line at the Detroit Arsenal Tank Plant.
a. Assumes additional production of 120 tanks per year to fill orders from foreign governments.
b. Includes estimates for research and development, procurement, and operations and maintenance costs to
convert Ml tanks to the M1A2 configuration.
c. According to then Secretary of Defense Dick Cheney's proposed budget revisions submitted in January 1993,
a minimum annual investment of $250 million would sustain the program after 1995, but at 60 conversions per
year rather than the 198 conversions funded in the alternative.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 24
TABLE 5. COSTS FROM 1994 THROUGH 1998 FOR ALTERNATIVE I (LAY AWAY THE
TANK LINE), BY FUNCTION AND FACILITY (In millions of 1993 dollars)
Detroit Lima
Arsenal Army Allison
Tank Tank Trans-
Function Planta Plant GDLSb mission Other0 DOE Total
One-Time Costs
Management and
Personnel Separation 20 40 30 90
Layaway of Facilities
and Equipment 10 30 20 d 10 0 70
Environmental Cleanup 10 J2 _d d _0 JO JO
Subtotal 40 80 50 d 10 20 200
Recurring Costs
Security and
Maintenance 20 10 20 90 140
Total
One-Time and
Recurring Costs 40 100 60 20 10 110 340
SOURCE: Congressional Budget Office based on U.S. Army Tank-Automotive Command, Austere Abrams Closure
Study (August 1991); and personal communication with Tank-Automotive Command, March 1992.
NOTES: GDLS = General Dynamics, Land Systems Division; DOE = Department of Energy.
a. Cost associated with laying away component machining only. Excludes an additional $15 million associated
with laying away the assembly line.
b. Includes Central Office Complex, Scranton Plant, Sterling Plant, subcontractors, and vendors.
c. Includes specific product lines operated by Textron Lycoming at the Stratford Army Engine Plant and other
lines at Hughes Aircraft Company, Computing Devices of Canada, Rock Island Arsenal, Watervliet Arsenal,
Kollmorgen, Plessey, and Singer-Kearfott.
would amount to $140 million, or 41 percent of the total five-year costs. After
1998, and until facilities would be needed to start producing parts for the next
generation of Army tanks, annual costs for maintaining and preserving the
base would total about $40 million (in 1993 dollars).
The costs for closing and storing the remaining dedicated lines would be
spread over several facilities. The major remaining facilities include the
GDLS facilities (the Scranton castings plant and the plant at Sterling Heights,
Michigan), the transmission line at Allison Transmission Division, and the
engine line at the Stratford Army Engine Plant operated by Textron
Lycoming. Finally, some smaller lines that produce parts that the government
supplies to GDLS for incorporation into the tank, such as laser range finders
from Hughes, would also have to be closed, stored, and maintained.
because tanks sold to foreign customers do not contain the special armor that
the DOE facility produces.
Description. In this option, the Army would buy 120 of the latest model
Abrams tank (the M1A2) per year for the U.S. military, starting in 1994.
Production at the rate envisioned in this option will not guarantee that all
parties currently producing tanks or their parts will continue to do so. For
some of the 18,000 vendors who now supply or have supplied components for
tanks, the low volume of business that would result from this option may not
be sufficiently profitable to keep them in the tank business, particularly
because many tank parts must meet exacting government standards.9 In fact,
because the rate of tank production has decreased over the past two years,
several vendors have already ceased their involvement in the tank program,
and GDLS expects that several more will follow. Nevertheless, producing
tanks at a low rate will sustain all major parts of the industrial base.
9. The government-owned tank assembly facility at Lima, Ohio, has the capacity to produce 75 tanks a month
(900 tanks a year)—much more than the number of tanks envisioned in this alternative.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 27
out. Neither the Bush Administration nor the Army included such a program
in the budget submitted in February 1992 or advocated conversion during
subsequent hearings on the fiscal year 1993 budget request. In the fall of
1992, however, the Army began to evaluate a program that would upgrade
1,002 Abrams tanks and has since submitted its proposed program to the
Office of the Secretary of Defense for approval. The Bush Administration
had approved only the first phase of the program by the end of its tenure, and
the Clinton Administration has not yet made its position on this program
known. This alternative would carry out the Army's plan.
Description. Four models of the Abrams tank have been produced since
1979. In chronological order and order of increasing capability, they are the
Ml, the IPM1, the M1A1, and the M1A2. The first two models have a
105mm cannon, and the last two a 120mm cannon with longer range. Other
improvements have been added over the years, including armor made with
depleted uranium (see Table 6). All M1A2 tanks and about half of the
MlAls have this special armor.
10. GDLS's analysis identified the processes that are unique to tank production and not easily transferred to
civilian application. Those processes would not include engine and transmission work that, though different
for use in tanks, is not sufficiently different to make it unique.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 28
Number in Army
Inventory in 1995 2,374 894 4,430 62
Weight (Tons) 60 61 67 69
Stored Rounds
(Main gun) 55 55 40 40
SINCGARS
Radiob
Improvement in
Capability over
Ml Model0 (Percent) n.a. 4 7d 22
SOURCE Congressional Budget Office based on Christopher F. Foss, ed., Jane's Armour and Artillery Systems
(Surrey, England: Jane's Information Group, various editions); Association of the U.S. Army, Army,
1991 Greenback (October 1991); data from General Dynamics, Land Systems Division; and The
Analytic Sciences Corporation, The TASCFORM Methodology: A Technique for Assessing
Comparative Force Modernization, 4th ed., rev. (Arlington, Va.: TASC, July 1991).
NOTES: NBC = nuclear, biological, chemical; SINCGARS = Single Channel Ground and Airborne Radio
System; n.a. = not applicable.
The Army has broken its proposed program into two phases. The first
phase would provide enough M1A2 tanks to equip and support one division
within the contingency force and would be funded from 1993 through 1995
(see Table 7). The Army needs almost 300 tanks to equip one mechanized
division and provide tanks for training. The Army has already bought 81 new
M1A2 tanks and plans to convert 210 tanks to the M1A2 configuration in the
first phase of its conversion program. The Army's second phase would
convert an additional 792 tanks and would require funds beginning in 1995.
The length of the second phase depends on the rate at which tanks would be
upgraded. The earliest completion date likely is 2000, which requires
conversion of 198 tanks a year from 1996 through 1999. A less ambitious
program would take longer. Upon completion of both phases, the Army
would have enough M1A2 tanks to equip its planned contingency force (which
includes five divisions plus one brigade afloat) and to provide extra tanks for
training.
Time to Restart Production. The time required to start producing new tanks
from a line that had been engaged in upgrading Mis to MlA2s would be
between the requirements of the previous two alternatives. All portions of the
industrial base would be active except those that produce engines and
transmissions. Of these two, engine production would take longer to restart,
with a delay of 20 months before the first engine could be delivered. Delivery
of the first tank could occur nine months later, for a total delay of 29 months
to produce the first tank. About one year later, production rates of 60 tanks
a month could be expected, and surge rates of 120 tanks could be achieved
about two years after the first tank rolled off the production line. All in all,
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 30
it could take 56 months to reach surge-rate production from a line that had
been engaged in upgrading Mis to MlA2s.
Costs. Because the conversion of Ml tanks to the M1A2 model requires such
extensive reworking of each tank, this upgrade would be expensive. In fact,
the total cost of the 210 upgrades in the Army's first phase is $890 million
(see Table 7). If the Army pursues the second phase at a rate of 198
upgrades per year, then the cost for the conversion program from 1994
through 1998 would be about $2.2 billion, with annual costs as high as $650
million (see Tables 4 and 7). Additional annual costs after 1998, if the
program were continued indefinitely at a rate of 198 tanks a year, would be
about $650 million. (As with the previous alternative, these costs are based
on assumed sales to foreign governments of 120 tanks per year. Without
these sales, costs could increase.)
1993
and
Before 1994 1995 1996 1997 1998 Total
SOURCE: Congressional Budget Office based on Department of the Army, "Abrams Upgrade Program"
(September 10, 1992); Congressional action on the 1993 budget request; and proposed budget
revisions submitted by then Secretary of Defense Dick Cheney in January 1993.
a. Does not include about $60 million to lay away the assembly line at the Detroit Arsenal Tank Plant. Includes
costs of research and development, procurement, and operations and maintenance to convert Ml tanks to the
M1A2 configuration. The costs of the tanks that will be converted in 1994 and 1995 and perhaps 1996 will
include some of the funds provided in Congressional appropriations from 1993 and prior years. Also, the
Army assumed that it can sell 120 new tanks to foreign customers every year and that producing these tanks
will lower U.S. costs. CBO estimates that if no additional new production from foreign sales occurs after 1995,
total costs could increase by 10 percent to 25 percent.
b. According to then Secretary of Defense Dick Cheney's proposed budget revisions submitted in January 1993,
the conversion program could be maintained with minimum funding of $250 million per year—enough to
convert 60 tanks, assuming that foreign military sales account for 120 new tanks produced annually.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 31
The costs of the conversion program could be lower if the Army pursues
the second phase of the program at a slower pace. In then Secretary of
Defense Dick Cheney's proposed budget revisions, submitted in January 1993,
only $250 million a year is set aside for tank conversion beyond 1995.
Coupled with sales of 120 tanks per year to foreign governments, this funding
should sustain the tank line. The pace of conversion might, however, be quite
slow. The Army indicates informally that it has not yet determined how many
tanks it could convert with $250 million while it also pays the overhead and
other costs necessary to sustain the tank production line.
During the next few years, some of the costs of the conversion program
may be financed using either funds from past appropriations or proceeds from
sales of military weapons to foreign countries. For example, the Army
proposes using almost $200 million from the sale of surplus tanks and other
equipment to help pay for the first phase of its conversion program. This
financing approach would reduce the additional funds that the Congress would
have to appropriate to carry out the conversion program. If the conversion
program were not carried out, however, the funds used to finance it would be
available to pay for other needs. The method used to finance the program
therefore does not alter the true costs of converting tanks, which are the focus
of this paper.
The three alternatives vary little in the amount of capability they would add
to the Army's tank force. They differ significantly, however, in their costs and
in the amount of insurance each would provide against uncertainty about
future threats to U.S. security.
Laying away the tank line offers some significant advantages, especially with
regard to cost.
Least Expensive. Closing and laying away the tank line would require $340
million in funding from 1994 through 1998, much less than the requirements
for maintaining low-rate production ($3.8 billion) or a conversion program (as
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 32
much as $2.2 billion) (see Table 8). Annual costs after 1998 would also be
much lower; those associated with layaway would amount to $40 million a
year compared with more than $700 million a year for low-rate production
and from $250 million to $650 million for conversion.
Cost to
Cost, Time to Reach Surge
1994-1998* Restart Capacity
(Millions of (Months) (Millions of
1993 dollars) First Tank Surgefc 1993 dollars)
Alternative I:
Lay Away Tank Line 340 51 72 1,110
Alternative II:
Produce at Low Rate 3,830C 22 47 600
Alternative III:
Convert Older Models 2,210 c>d 29 56 530
a. Does not include about $15 million to lay away the assembly line at the Detroit Arsenal Tank Plant.
c. Assumes additional production of 120 tanks per year to fill orders from foreign governments.
d. The proposed budget revisions submitted by then Secretary of Defense Dick Cheney in January 1993 include
an estimate of $720 million as a minimum sustaining level.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 33
Improvements in Capability May Not Be Needed. Laying away the tank line
would, of course, preclude making any improvements to the capability of the
Army's tank fleet for the foreseeable future. Low-rate production or
conversion would result in increased capability, but the improvements would
be small and may not be needed to meet future threats to U.S. security.
But does the Army really need to improve the overall capability of its
tank fleet? Many defense analysts contend that the United States already has
enough tanks to equip its planned forces and that the MlAl is the most
capable tank in the world. There is some basis for this assertion. First, as
mentioned above, U.S. tank forces enjoy a substantial advantage when
compared with tank forces of almost any other country (see Figure 3).
Moreover, by its performance in the Persian Gulf War, the Abrams tank
Composition Total
Ml IPM1 MlAl M1A2 Capability a
Alternative I:
Lay Away Tank Line 2,374 894 4,453 62 42,900
Alternative II:
Produce at Low Rate 1,774 894 4,453 662 43,700
Alternative III:
Convert Older Models 1,372 894 4,453 1,064 44,200
SOURCES: Congressional Budget Office based on Army data and on The Analytic Sciences Corporation, The
TASCFORM Methodology: A Technique for Assessing Comparative Force Modernization, 4th ed., rev.
(Arlington, Va.: TASC, July 1991).
Restart Times May Be Acceptable. If the tank line is laid away, the time and
investment required to restart production and reach production at surge rates
of 120 new tanks a month would be substantial—a full six years and more than
$1 billion (see Table 8). The delays and initial investments associated with
the other two alternatives would be smaller~56 months and $530 million to
achieve surge-rate production from a line upgrading tanks, and only 47
months and $600 million from low-rate production.
Although laying away the tank line has advantages, particularly relating to
cost, low-rate production or conversion provides a hedge against uncertainty
about future threats and other factors. Of the two approaches, conversion
may be preferable because it would maintain much of the industrial base but
would cost at least 40 percent less during the 1994-1998 period. The
remainder of this discussion therefore focuses on a program to convert Ml
tanks to the M1A2 configuration.
11. Testimony of Donald Atwood before the House Committee on Armed Services, April 28, 1992.
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 35
no one can be sure if or when a serious new threat to Western security might
emerge. If a new threat emerges, a relatively rapid return to production of
high-quality tanks could be important, especially if considerable time elapses
before the United States recognizes the emergence of and acts to counter a
new military power. A conversion program would require less time to achieve
production of new tanks than would a line that had been laid away.
Compared with these developing nations, the United States will almost
certainly maintain a large numerical advantage in terms of total tank
inventories. The United States might not, however, be able to bring its entire
tank inventory to bear. In regions of the world where the United States does
not maintain a significant forward presence, small units with limited numbers
of U.S. tanks might have to oppose an adversary who threatens U.S. security
interests. Alternatively, the United States might need to split its forces in
order to deal with two or more contingencies simultaneously. In such a
scenario, having U.S. tanks that are superior on a tank-for-tank basis may be
important. U.S. actions in Operation Desert Storm-in which the U.S. military
tried to ensure that its forces used the latest model M1A1, equipped with
special armor-underscore the importance of such superiority.
The uncertainty concerning the ability to resurrect the tank base will
certainly increase the longer the base is shut down. Inasmuch as the United
States will probably not be building new tanks before 2010, the hiatus between
shutdown and reopening may be very long. If restart takes longer than the
Army estimates, then the risks of failing to meet a future threat are greater
than the Administration currently acknowledges.
CONCLUSION
In its defense authorization act for 1993, the Congress approved the use of
$225 million-funds that had been appropriated for 1992 but not spent-for
converting older Abrams Ml tanks to the newer A2 version. Thus, at least
through 1993, the Congress opted to insure against possible future threats to
U.S. security by sustaining most of the tank industrial base.
This decision, however, raises the question of how long the United
States should continue to buy insurance. Should it continue until it needs to
ALTERNATIVES FOR THE U.S. TANK INDUSTRIAL BASE 37
produce a new tank, which might not be until 2010 or even later? Or will this
insurance be needed for only a few years until the international climate,
particularly the situation in the former Soviet republics, becomes clearer?
If costs are the key criterion, the tank line should be allowed to close
as soon as all foreign orders are filled. The Army's planned conversion
program would require more than four times as much funding over the next
two years as layaway. Subsequently, depending on the pace of conversion,
upgrading tanks could cost from as little as two to more than 10 times as
much as layaway costs in a given year. Indeed, annual costs for conversion
after 1995 could be as high as $650 million. The Army estimates that the
one-time cost of restarting and reaching surge-rate production from a line that
has been laid away is only slightly more than $1 billion. Thus, if conversion
is pursued at a high pace after 1995, the United States would spend in two
years as much to convert tanks as it would to restart a line that had been laid
away.
After 1995, annual costs for the conversion program could rise to
between $250 million and $650 million. Such costs would represent a small
fraction of the Army's total budget. Sustaining the capacity to produce tanks
through conversion or low-rate production provides some insurance against
an unforeseen event—the emergence of a major new threat to U.S.
security~and other risks associated with closing the tank line. Continuing this
program may therefore be reasonable, particularly until uncertainty about the
situation in Eastern Europe and other parts of the world diminishes.
In the years to come, however, the risks incurred by ending support for
the tank base should continue to be weighed against the costs. This judgment
may be particularly important if external factors, such as a decline in the
volume of foreign sales of tanks, cause the price of the conversion program
to increase.