Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Chapter 6 Answer Key (1 15)

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 15

lOMoARcPSD|18274103

lOMoARcPSD|18274103

Solutions to Questions and Problems

CHAP 6

1. Calculating Project NPV: Paul Restaurant is considering the purchase of a


$9,300 soufflé maker. The soufflé maker has an economic life of five years and
will be fully depreciated by the straight-line method. The machine will produce
1,400 soufflés per year, with each costing $1.97 to make and priced at $4.95. The
discount rate is 14 percent and the tax rate is 21 percent. Should the company
make the purchase?

Using the tax shield approach to calculating OCF, we get:

OCF = (Sales – Costs)(1 – TC) + TCDepreciation


OCF = [($4.95 × 1,400) – ($1.97 × 1,400)](1 – .21) + .21($9,300/5)
OCF = $3,686.48

So, the NPV of the project is:

NPV = –$9,300 + $3,686.48(PVIFA14%,5)


NPV = $3,355.98

2. Calculating Project NPV: The Best Manufacturing Company is considering a


new investment. Financial projections for the investment are tabulated here. The
corporate tax rate is 22 percent. Assume all sales revenue is received in cash, all
operating costs and income taxes are paid in cash, and all cash flows occur at the
end of the year. All net working capital is recovered at the end of the project.

Year 0 Year 1 Year 2 Year 3 Year 4


Investment $26,30
0
Sales revenue $13,40 $15,00 $16,40 $12,90
0 0 0 0
Operating 2,900 3,100 4,200 2,800
costs
Depreciation 6,575 6,575 6,575 6,575
NWC spending 300 200 225 150 ?

a. Compute the incremental net income of the investment for each year.
b. Compute the incremental cash flows of the investment for each year.
c. Suppose the appropriate discount rate is 12 percent. What is the NPV of the project?
lOMoARcPSD|18274103

We will use the bottom-up approach to calculate the operating cash flow for each year.
We
also must be sure to include the net working capital cash flows each year. So, the net
income and total cash flow each year will be:

Year 1 Year 2 Year 3 Year 4


Sales $13,400 $15,000 $16,400 $12,900
Costs 2,900 3,100 4,200 2,800
Depreciation 6,575 6,575 6,575 6,575
EBT $3,925 $5,325 $5,625 $3,525
Tax 864 1,172 1,238 776
Net income $3,062 $4,154 $4,388 $2,750

OCF $9,637 $10,729 $10,963 $9,325



Capital spending $26,300
NWC –300 –200 –225 –150 875
Incremental cash –
flow $26,600 $9,437 $10,504 $10,813 $10,200
lOMoARcPSD|18274103

The NPV for the project is:

NPV = –$26,600 + $9,437/1.12 + $10,504/1.122 + $10,813/1.123 + $10,200/1.124


NPV = $4,376.86

3. Calculating Project NPV: Down Under Boomerang, Inc., is considering a new 3-


year expansion project that requires an initial fixed asset investment of $1.42
million. The fixed asset will be depreciated straight-line to zero over its 3-year tax
life, after which it will be worthless. The project is estimated to generate $1.09
million in annual sales, with costs of $475,000. The tax rate is 25 percent and the
required return is 12 percent. What is the project’s NPV?

Using the tax shield approach to calculating OCF, we get:

OCF = (Sales – Costs)(1 – TC) + TC .Depreciation


OCF = ($1,090,000 – 475,000)(1 – .25) + .25.($1,420,000/3)
OCF = $579,583.33

So, the NPV of the project is:

NPV = –$1,420,000 + $579,583.33(PVIFA12%,3)


NPV = –$27,938.63

4. Calculating Project Cash Flow from Assets: In the previous problem, suppose the
project requires an initial investment in net working capital of $250,000 and the
fixed asset will have a market value of $230,000 at the end of the project. What is the
project’s Year 0 net cash flow? Year 1? Year 2? Year 3? What is the new NPV?

The cash outflow at the beginning of the project will increase because of the spending on
NWC. At the end of the project, the company will recover the NWC, so it will be a cash
inflow. The sale of the equipment will result in a cash inflow, but we also must account
for
the taxes which will be paid on this sale. So, the cash flows for each year of the project
will
be:

Year Cash Flow


0 – $1,670,000 = –$1,420,000 – 250,000
1 579,583.33
2 579,583.33
3 1,002,083.33 = $579,583.33 + 250,000 + 230,000 + (0 –
230,000)(.25)
lOMoARcPSD|18274103

And the NPV of the project is:

NPV = –$1,670,000 + $579,583.33(PVIFA12%,2) + ($1,002,083.33/1.123)


NPV = $22,788.53

5. NPV and Modified ACRS: In the previous problem, suppose the fixed asset actually
falls into the 3-year MACRS class. All the other facts are the same. What is the
project’s Year 1 net cash flow now? Year 2? Year 3? What is the new NPV?

First, we will calculate the annual depreciation for the equipment necessary for the
project. The depreciation amount each year will be:

Year 1 depreciation = $1,420,000(.3333) =


$473,286 Year 2 depreciation = $1,420,000(.4445)
= $631,190 Year 3 depreciation =
$1,420,000(.1481) = $210,302

So, the book value of the equipment at the end of three years, which will be the initial
investment minus the accumulated depreciation, is:

Book value in 3 years = $1,420,000 – ($473,286 + 631,190 + 210,302)


Book value in 3 years = $105,222

The asset is sold at a gain to book value, so this gain is taxable.

Aftertax salvage value = $230,000 + ($105,222 – 230,000)(.25)


Aftertax salvage value = $198,805.50
lOMoARcPSD|18274103

To calculate the OCF, we will use the tax shield approach, so the cash flow each year
is:

OCF = (Sales – Costs)(1 – TC) + TCDepreciation

Year Cash Flow


0 – = –$1,420,000 – 250,000
$1,670,000
1 579,571.50 = ($615,000)(.75) + .25($473,286)
2 619,047.50 = ($615,000)(.75) + .25($631,190)
3 962,631.00 = ($615,000)(.75) + .25($210,302) + $198,805.50 +
250,000

Remember to include the NWC cost in Year 0, and the recovery of the NWC at the
end of the project. The NPV of the project with these assumptions is:

NPV = –$1,670,000 + $579,571.50/1.12 + $619,047.50/1.122 + $962,631.00/1.123


NPV = $26,157.16

6. NPV and Bonus Depreciation: In the previous problem, suppose the fixed asset
actually qualifies for 100 percent bonus depreciation. All the other facts are the
same. What is the project’s Year 1 net cash flow now? Year 2? Year 3? What is the
new NPV?

The book value of the asset is zero, so the gain on the sale is taxable.

Aftertax salvage value = $230,000 + ($0 – 230,000).(.25)


Aftertax salvage value = $172,500

To calculate the OCF, we will use the tax shield approach, so the cash flow each year
is:

OCF = (Sales – Costs).(1 – TC) + TC .Depreciation

Year Cash Flow


0 – = –$1,420,000 – 250,000
$1,670,000
1 816,250 = ($615,000)(.75) + .25($1,420,000)
2 461,250 = ($615,000)(.75)
3 883,750 = ($615,000)(.75) + $172,500 + 250,000

Remember to include the NWC cost in Year 0, and the recovery of the NWC at the
end of the project. The NPV of the project with these assumptions is:
lOMoARcPSD|18274103

NPV = –$1,670,000 + $816,250/1.12 + $461,250/1.122 +


$883,750/1.123 NPV = $55,536.11

7. Project Evaluation: Your firm is contemplating the purchase of a new $575,000


computer-based order entry system. The system will be depreciated straight-line to
zero over its 5-year life. It will be worth $60,000 at the end of that time. You will
save
$176,000 before taxes per year in order processing costs, and you will be able to
reduce working capital by $80,000 (this is a one-time reduction). If the tax rate is 23
percent, what is the IRR for this project?

First, we will calculate the annual depreciation of the new equipment. It will be:

Annual depreciation charge = $575,000/5


Annual depreciation charge = $115,000

The aftertax salvage value of the equipment is:

Aftertax salvage value = $60,000(1 – .23)


Aftertax salvage value = $46,200

Using the tax shield approach, the OCF is:

OCF = $176,000(1 – .23) +


.23($115,000) OCF = $161,970

Now we can find the project IRR. There is an unusual feature that is a part of this
project. Accepting this project means that we will reduce NWC. This reduction in
NWC is a cash inflow at Year 0. This reduction in NWC implies that when the
project ends, we will have to increase NWC. So, at the end of the project, we will
have a cash outflow to restore the NWC to its level before the project. We also must
include the aftertax salvage value at the end of the project. The IRR of the project is:

NPV = 0 = –$575,000 + 80,000 + $161,970(PVIFAIRR%,4)


+ [($161,970 + 46,200 – 80,000)/(1+ IRR)5]

IRR = 17.70%

8. Project Evaluation: Dog Up! Franks is looking at a new sausage system with an
installed cost of $375,000. This cost will be depreciated straight-line to zero over the
project’s 5-year life, at the end of which the sausage system can be scrapped for
$25,000. The sausage system will save the firm $95,000 per year in pretax operating
costs, and the system requires an initial investment in net working capital of
$15,000.
lOMoARcPSD|18274103

If the tax rate is 24 percent and the discount rate is 10 percent, what is the NPV of
this project?

First, we will calculate the annual depreciation of the new equipment. It will be:

Annual depreciation = $375,000/5


Annual depreciation = $75,000

Now, we calculate the aftertax salvage value. The aftertax salvage value is the market
price minus (or plus) the taxes on the sale of the equipment, so:

Aftertax salvage value = MV + (BV – MV)TC

Very often, the book value of the equipment is zero as it is in this case. If the book
value is zero, the equation for the aftertax salvage value becomes:

Aftertax salvage value = MV + (0 – MV)TC


Aftertax salvage value = MV(1 – TC)

We will use this equation to find the aftertax salvage value since we know the book
value is zero. So, the aftertax salvage value is:

Aftertax salvage value = $25,000(1 – .24)


Aftertax salvage value = $19,000

Using the tax shield approach, we find the OCF for the project is:

OCF = $95,000(1 – .24) + .24($75.000)


OCF = $90,200

Now we can find the project NPV. Notice that we include the NWC in the initial
cash outlay. The recovery of the NWC occurs in Year 5, along with the aftertax
salvage value.

NPV = –$375,000 – 15,000 + $90,200(PVIFA10%,5) + ($19,000 + 15,000)/1.105


NPV = –$26,959.71

9. NPV and Bonus Depreciation: In the previous problem, suppose the fixed asset
actually qualifies for 100 percent bonus depreciation. All the other facts are the
same. What is the new NPV?

The book value of the asset will be zero at the end of the project, so the aftertax
salvage value is:
lOMoARcPSD|18274103

Aftertax salvage value = $25,000(1 – .24)


Aftertax salvage value = $19,000

Using the tax shield approach, we find the OCF for the first year of the project is:

OCF = $95,000(1 – .24) + .24($375,000)


OCF = $162,200

And the OCF for Years 2 to 5 is:

OCF = $95,000(1 – .24)


OCF = $72,200

Now we can find the project NPV. Notice that we include the NWC in the initial
cash outlay. The recovery of the NWC occurs in Year 5, along with the aftertax
salvage value.

NPV = –$375,000 – 15,000 + $162,200/1.10 + $72,200/1.102 + $72,200/1.103 +


$72,200/1.104
+ ($72,200 + 19,000 + 15,000)/1.105
NPV = –$13,375.69

10. Calculating Salvage Value: An asset used in a 4-year project falls in the 5-year
MACRS class for tax purposes. The asset has an acquisition cost of $7.6 million and
will be sold for $1.4 million at the end of the project. If the tax rate is 21 percent,
what is the aftertax salvage value of the asset?

To find the book value at the end of four years, we need to find the accumulated
depreciation for the first four years. We could calculate a table with the depreciation
each year, but an easier way is to add the MACRS depreciation amounts for each of
the first four years and multiply this percentage times the cost of the asset. We can
then subtract this from the asset cost. Doing so, we get:

BV4 = $7,600,000 – 7,600,000(.2000 + .3200 + .1920 +


.1152) BV4 = $1,313,280

The asset is sold at a gain to book value, so this gain is taxable.

Aftertax salvage value = $1,400,000 + ($1,313,280 – 1,400,000).(.21)


Aftertax salvage value = $1,381,789
lOMoARcPSD|18274103

11. Calculating NPV: Thurston Petroleum is considering a new project that


complements its existing business. The machine required for the project costs $4.1
million. The marketing department predicts that sales related to the project will be
$2.35 million per year for the next four years, after which the market will cease to
exist. The machine will be depreciated to zero over its 4-year economic life using the
straight-line method. Cost of goods sold and operating expenses related to the
project are predicted to be 25 percent of sales. The company also needs to add net
working capital of $150,000 immediately. The additional net working capital will be
recovered in full at the end of the project’s life. The corporate tax rate is 25 percent
and the required return for the project is 13 percent. Should the company proceed
with the project?

We will begin by calculating the initial cash outlay, that is, the cash flow at Time 0.
To undertake the project, we will have to purchase the equipment and increase net
working capital. So, the cash outlay today for the project will be:

Equipment –$4,100,000
NWC –150,000
Total –$4,250,000

Using the bottom-up approach to calculating the operating cash flow, we find the
operating cash flow each year will be:

Sales $2,350,000
Costs 587,500
Depreciation 1,025,000
EBT $737,500
Tax 184,375
Net income $553,125

The operating cash flow is:

OCF = Net income + Depreciation


OCF = $553,125 + 1,025,000
OCF = $1,578,125

To find the NPV of the project, we add the present value of the project cash flows.
We must be sure to add back the net working capital at the end of the project life,
since we are assuming the net working capital will be recovered. So, the project NPV
is:

NPV = –$4,250,000 + $1,578,125(PVIFA13%,4) + $150,000/1.134


lOMoARcPSD|18274103

NPV = $536,085.37

12. Calculating EAC: You are evaluating two different silicon wafer milling machines.
The Techron I costs $265,000, has a 3-year life, and has pretax operating costs of
$41,000 per year. The Techron II costs $330,000, has a 5-year life, and has pretax
operating costs of $52,000 per year. For both milling machines, use straight-line
depreciation to zero over the project’s life and assume a salvage value of $25,000. If
your tax rate is 21 percent and your discount rate is 9 percent, compute the EAC for
both machines. Which do you prefer? Why?

We will need the aftertax salvage value of the equipment to compute the EAC. Even
though the equipment for each product has a different initial cost, both have the same
salvage value. The aftertax salvage value for both is:

Aftertax salvage value = $25,000(1 – .21)


Aftertax salvage value = $19,750

To calculate the EAC, we first need the OCF and PV of costs of each option. The
OCF and PV of costs for Techron I is:

OCF = –$41,000(1 – .21) + .21($265,000/3)


OCF = –$13,840

PV of costs = –$265,000 + –$13,840(PVIFA9%,3) + ($19,750/1.093)


PV of costs = –$284,782.49

EAC = –$284,782.49/(PVIFA9%,3)
EAC = –$112,504.68

And the OCF and PV of costs for Techron II is:

OCF = – $52,000(1 – .21) + .21($330,000/5)


OCF = –$27,220

PV of costs = –$330,000 – $27,220(PVIFA9%,5) + ($19,750/1.095)


PV of costs = –$423,040.16

EAC = –$423,040.16/(PVIFA9%,5)
EAC = –$108,760.43

The two milling machines have unequal lives, so they can only be compared by
expressing both on an equivalent annual basis, which is what the EAC method does.
Thus, you prefer the Techron II because it has the lower (less negative) annual cost.
lOMoARcPSD|18274103
lOMoARcPSD|18274103

Intermediate

13. Cost-Cutting Proposals: Starset Machine Shop is considering a 4-year project to


improve its production efficiency. Buying a new machine press for $670,000 is
estimated to result in $245,000 in annual pretax cost savings. The press falls in the
5- year MACRS class, and it will have a salvage value at the end of the project
of
$55,000. The press also requires an initial investment in spare parts inventory of
$20,000, along with an additional $2,500 in inventory for each succeeding year of
the project. If the shop’s tax rate is 23 percent and the discount rate is 8 percent,
should the company buy and install the machine press?

First, we will calculate the depreciation each year, which will

be: D1 = $670,000(.2000) = $134,000


D2 = $670,000(.3200) = $214,400
D3 = $670,000(.1920) = $128,640
D4 = $670,000(.1152) = $77,184

The book value of the equipment at the end of the project is:

BV4 = $670,000 – ($134,000 + 214,400 + 128,640 + 77,184)


BV4 = $115,776

The asset is sold at a loss to book value, so this creates a tax refund. The aftertax
salvage value will be:

Aftertax salvage value = $55,000 + ($115,776 – 55,000)(.23)


Aftertax salvage value = $68,978.48

So, the OCF for each year will be:

OCF1 = $245,000(1 – .23) + .23($134,000) = $219,470.00


OCF2 = $245,000(1 – .23) + .23($214,400) = $237,962.00
OCF3 = $245,000(1 – .23) + .23($128,640) = $218,237.20
OCF4 = $245,000(1 – .23) + .23($77,184) = $206,402.32

Now we have all the necessary information to calculate the project NPV. We need to
be careful with the NWC in this project. Notice the project requires $20,000 of NWC
at the beginning, and $2,500 more in NWC each successive year. We will subtract
the
$20,000 from the initial cash flow and subtract $2,500 each year from the OCF to
account for this spending. In Year 4, we will add back the total spent on NWC,
which is $27,500. The $2,500 spent on NWC capital during Year 4 is irrelevant.
Why? Well, during this year the project required an additional $2,500, but we
would get the
lOMoARcPSD|18274103

money back immediately. So, the net cash flow for additional NWC would be zero.
With all this, the equation for the NPV of the project is:

NPV = –$670,000 – 20,000 + ($219,470 – 2,500)/1.08 + ($237,962 – 2,500)/1.082


+ ($218,237.20 – 2,500)/1.08 3 + ($206,402.32 + 27,500 +
68,978.48)/1.084
NPV = $106,654.44

14. NPV and Bonus Depreciation: In the previous problem, suppose the fixed asset
actually qualifies for 100 percent bonus depreciation. All the other facts are the
same. What is the new NPV?

The book value of the asset is zero, so the aftertax salvage value will be:

Aftertax salvage value = $55,000 + ($0 – 55,000)(.23)


Aftertax salvage value = $42,350

So, the OCF for each year will be:

OCF1 = $245,000(1 – .23) + .23($670,000) = $342,750


OCF2 = $245,000(1 – .23) = $188,650
OCF3 = $245,000(1 – .23) = $188,650
OCF4 = $245,000(1 – .23) = $188,650

Now we have all the necessary information to calculate the project NPV. We need to
be careful with the NWC in this project. Notice the project requires $20,000 of NWC
at the beginning, and $2,500 more in NWC each successive year. We will subtract
the
$20,000 from the initial cash flow and subtract $2,500 each year from the OCF to
account for this spending. In Year 4, we will add back the total spent on NWC,
which is $27,500. The $2,500 spent on NWC capital during Year 4 is irrelevant.
Why? Well, during this year the project required an additional $2,500, but we would
get the money back immediately. So, the net cash flow for additional NWC would be
zero. With all this, the equation for the NPV of the project is:

NPV = –$675,000 – 20,000 + ($342,750 – 2,500)/1.08 + ($188,650 – 2,500)/1.082


+ ($188,650 – 2,500)/1.083 + ($188,650 + 27,500 + 42,350)/1.084
NPV = $122,417.01

15. Comparing Mutually Exclusive Projects: Hagar Industrial Systems Company


(HISC) is trying to decide between two different conveyor belt systems. System A
costs $265,000, has a 4-year life, and requires $73,000 in pretax annual operating
costs. System B costs $380,000, has a 6-year life, and requires $64,000 in pretax
annual operating costs. Both systems are to be depreciated straight-line to zero over
lOMoARcPSD|18274103

their lives and will have zero salvage value. Whichever system is chosen, it will not
be replaced when it wears out. If the tax rate is 23 percent and the discount rate is
7.5 percent, which system should the firm choose?

If we are trying to decide between two projects that will not be replaced when they
wear out, the proper capital budgeting method to use is NPV. Both projects only have
costs associated with them, not sales, so we will use these to calculate the NPV of
each project. Using the tax shield approach to calculate the OCF, the NPV of System
A is:

OCFA = –$73,000(1 – .23) + .23($265,000/4)


OCFA = –$40,973

NPVA = –$265,000 – $40,973(PVIFA7.5%,4)


NPVA = –$402,230.27

And the NPV of System B is:

OCFB = –$64,000(1 – .23) + .23($380,000/6)


OCFB = –$34,713

NPVB = –$380,000 – $34,713(PVIFA7.5%,6)


NPVB = –$542,939.06

If the system will not be replaced when it wears out, then System A should be chosen,
because it has the less negative NPV

You might also like