Chapter 6 Answer Key (1 15)
Chapter 6 Answer Key (1 15)
Chapter 6 Answer Key (1 15)
lOMoARcPSD|18274103
CHAP 6
a. Compute the incremental net income of the investment for each year.
b. Compute the incremental cash flows of the investment for each year.
c. Suppose the appropriate discount rate is 12 percent. What is the NPV of the project?
lOMoARcPSD|18274103
We will use the bottom-up approach to calculate the operating cash flow for each year.
We
also must be sure to include the net working capital cash flows each year. So, the net
income and total cash flow each year will be:
4. Calculating Project Cash Flow from Assets: In the previous problem, suppose the
project requires an initial investment in net working capital of $250,000 and the
fixed asset will have a market value of $230,000 at the end of the project. What is the
project’s Year 0 net cash flow? Year 1? Year 2? Year 3? What is the new NPV?
The cash outflow at the beginning of the project will increase because of the spending on
NWC. At the end of the project, the company will recover the NWC, so it will be a cash
inflow. The sale of the equipment will result in a cash inflow, but we also must account
for
the taxes which will be paid on this sale. So, the cash flows for each year of the project
will
be:
5. NPV and Modified ACRS: In the previous problem, suppose the fixed asset actually
falls into the 3-year MACRS class. All the other facts are the same. What is the
project’s Year 1 net cash flow now? Year 2? Year 3? What is the new NPV?
First, we will calculate the annual depreciation for the equipment necessary for the
project. The depreciation amount each year will be:
So, the book value of the equipment at the end of three years, which will be the initial
investment minus the accumulated depreciation, is:
To calculate the OCF, we will use the tax shield approach, so the cash flow each year
is:
Remember to include the NWC cost in Year 0, and the recovery of the NWC at the
end of the project. The NPV of the project with these assumptions is:
6. NPV and Bonus Depreciation: In the previous problem, suppose the fixed asset
actually qualifies for 100 percent bonus depreciation. All the other facts are the
same. What is the project’s Year 1 net cash flow now? Year 2? Year 3? What is the
new NPV?
The book value of the asset is zero, so the gain on the sale is taxable.
To calculate the OCF, we will use the tax shield approach, so the cash flow each year
is:
Remember to include the NWC cost in Year 0, and the recovery of the NWC at the
end of the project. The NPV of the project with these assumptions is:
lOMoARcPSD|18274103
First, we will calculate the annual depreciation of the new equipment. It will be:
Now we can find the project IRR. There is an unusual feature that is a part of this
project. Accepting this project means that we will reduce NWC. This reduction in
NWC is a cash inflow at Year 0. This reduction in NWC implies that when the
project ends, we will have to increase NWC. So, at the end of the project, we will
have a cash outflow to restore the NWC to its level before the project. We also must
include the aftertax salvage value at the end of the project. The IRR of the project is:
IRR = 17.70%
8. Project Evaluation: Dog Up! Franks is looking at a new sausage system with an
installed cost of $375,000. This cost will be depreciated straight-line to zero over the
project’s 5-year life, at the end of which the sausage system can be scrapped for
$25,000. The sausage system will save the firm $95,000 per year in pretax operating
costs, and the system requires an initial investment in net working capital of
$15,000.
lOMoARcPSD|18274103
If the tax rate is 24 percent and the discount rate is 10 percent, what is the NPV of
this project?
First, we will calculate the annual depreciation of the new equipment. It will be:
Now, we calculate the aftertax salvage value. The aftertax salvage value is the market
price minus (or plus) the taxes on the sale of the equipment, so:
Very often, the book value of the equipment is zero as it is in this case. If the book
value is zero, the equation for the aftertax salvage value becomes:
We will use this equation to find the aftertax salvage value since we know the book
value is zero. So, the aftertax salvage value is:
Using the tax shield approach, we find the OCF for the project is:
Now we can find the project NPV. Notice that we include the NWC in the initial
cash outlay. The recovery of the NWC occurs in Year 5, along with the aftertax
salvage value.
9. NPV and Bonus Depreciation: In the previous problem, suppose the fixed asset
actually qualifies for 100 percent bonus depreciation. All the other facts are the
same. What is the new NPV?
The book value of the asset will be zero at the end of the project, so the aftertax
salvage value is:
lOMoARcPSD|18274103
Using the tax shield approach, we find the OCF for the first year of the project is:
Now we can find the project NPV. Notice that we include the NWC in the initial
cash outlay. The recovery of the NWC occurs in Year 5, along with the aftertax
salvage value.
10. Calculating Salvage Value: An asset used in a 4-year project falls in the 5-year
MACRS class for tax purposes. The asset has an acquisition cost of $7.6 million and
will be sold for $1.4 million at the end of the project. If the tax rate is 21 percent,
what is the aftertax salvage value of the asset?
To find the book value at the end of four years, we need to find the accumulated
depreciation for the first four years. We could calculate a table with the depreciation
each year, but an easier way is to add the MACRS depreciation amounts for each of
the first four years and multiply this percentage times the cost of the asset. We can
then subtract this from the asset cost. Doing so, we get:
We will begin by calculating the initial cash outlay, that is, the cash flow at Time 0.
To undertake the project, we will have to purchase the equipment and increase net
working capital. So, the cash outlay today for the project will be:
Equipment –$4,100,000
NWC –150,000
Total –$4,250,000
Using the bottom-up approach to calculating the operating cash flow, we find the
operating cash flow each year will be:
Sales $2,350,000
Costs 587,500
Depreciation 1,025,000
EBT $737,500
Tax 184,375
Net income $553,125
To find the NPV of the project, we add the present value of the project cash flows.
We must be sure to add back the net working capital at the end of the project life,
since we are assuming the net working capital will be recovered. So, the project NPV
is:
NPV = $536,085.37
12. Calculating EAC: You are evaluating two different silicon wafer milling machines.
The Techron I costs $265,000, has a 3-year life, and has pretax operating costs of
$41,000 per year. The Techron II costs $330,000, has a 5-year life, and has pretax
operating costs of $52,000 per year. For both milling machines, use straight-line
depreciation to zero over the project’s life and assume a salvage value of $25,000. If
your tax rate is 21 percent and your discount rate is 9 percent, compute the EAC for
both machines. Which do you prefer? Why?
We will need the aftertax salvage value of the equipment to compute the EAC. Even
though the equipment for each product has a different initial cost, both have the same
salvage value. The aftertax salvage value for both is:
To calculate the EAC, we first need the OCF and PV of costs of each option. The
OCF and PV of costs for Techron I is:
EAC = –$284,782.49/(PVIFA9%,3)
EAC = –$112,504.68
EAC = –$423,040.16/(PVIFA9%,5)
EAC = –$108,760.43
The two milling machines have unequal lives, so they can only be compared by
expressing both on an equivalent annual basis, which is what the EAC method does.
Thus, you prefer the Techron II because it has the lower (less negative) annual cost.
lOMoARcPSD|18274103
lOMoARcPSD|18274103
Intermediate
The book value of the equipment at the end of the project is:
The asset is sold at a loss to book value, so this creates a tax refund. The aftertax
salvage value will be:
Now we have all the necessary information to calculate the project NPV. We need to
be careful with the NWC in this project. Notice the project requires $20,000 of NWC
at the beginning, and $2,500 more in NWC each successive year. We will subtract
the
$20,000 from the initial cash flow and subtract $2,500 each year from the OCF to
account for this spending. In Year 4, we will add back the total spent on NWC,
which is $27,500. The $2,500 spent on NWC capital during Year 4 is irrelevant.
Why? Well, during this year the project required an additional $2,500, but we
would get the
lOMoARcPSD|18274103
money back immediately. So, the net cash flow for additional NWC would be zero.
With all this, the equation for the NPV of the project is:
14. NPV and Bonus Depreciation: In the previous problem, suppose the fixed asset
actually qualifies for 100 percent bonus depreciation. All the other facts are the
same. What is the new NPV?
The book value of the asset is zero, so the aftertax salvage value will be:
Now we have all the necessary information to calculate the project NPV. We need to
be careful with the NWC in this project. Notice the project requires $20,000 of NWC
at the beginning, and $2,500 more in NWC each successive year. We will subtract
the
$20,000 from the initial cash flow and subtract $2,500 each year from the OCF to
account for this spending. In Year 4, we will add back the total spent on NWC,
which is $27,500. The $2,500 spent on NWC capital during Year 4 is irrelevant.
Why? Well, during this year the project required an additional $2,500, but we would
get the money back immediately. So, the net cash flow for additional NWC would be
zero. With all this, the equation for the NPV of the project is:
their lives and will have zero salvage value. Whichever system is chosen, it will not
be replaced when it wears out. If the tax rate is 23 percent and the discount rate is
7.5 percent, which system should the firm choose?
If we are trying to decide between two projects that will not be replaced when they
wear out, the proper capital budgeting method to use is NPV. Both projects only have
costs associated with them, not sales, so we will use these to calculate the NPV of
each project. Using the tax shield approach to calculate the OCF, the NPV of System
A is:
If the system will not be replaced when it wears out, then System A should be chosen,
because it has the less negative NPV