CBE Approved ROB-55 Launching 8.06.21
CBE Approved ROB-55 Launching 8.06.21
CBE Approved ROB-55 Launching 8.06.21
NOTES
(1) ALL THE DIMENSION & LEVEL ARE IN METER UNLESS OTHERWISE SPECIFIED.
(2) DIMENSIONS ARE NOT TO BE SCALED & ONLY WRITTENDIMENSION SHALL BE FOLLOWED.
0
37280 c/c of exapansion joint BE DECIDED BY SITE ENGG. SITE ENGG SHALL ENSURE AVAILABILITY OF STAND - BY CRANE OF SAME
70
37280 c/c of exapansion joint 30000 c/c of bearing
31
36000 c/c of bearing
36000 c/c of bearing OR HIGHER CAPACITY.
26380
(4). THE RAILWAY TRACK IS BG LINE.
31700
(5) SPAN - 1 STEEL GIRDER ERECTION SHALL BE CARRIED OUT UNDER POWER & TRAFFIC BLOCK
C/L UP TRK
C/L UP TRK
(6) SIGNAL MAN TO BE ENGAGED AT THE BOTH THE SIDE OF TRACK AT PROPER DISTANCE AS DIRECTED
C/L DN TRK
C/L UP TRK
P5 P4 P3 P2 BY RAILWAY AUTHORITY TO PROTECT THE TRACK.
CRANE
CRANE (7) SAFETY NET TO BE PROVIDED DURING ALL CONSTRUCTION OPERATION TILL REMOVAL OF DECK
SHUTTERING DURING THE TRAFFIC BLOCK. TRACK WILL BE PROTECTED BY RAILWAY STAFF AS PER G
37280 & S RULES AND IRPWM
2700 6560 4470 31.28 37.28
31280 6560 4470 26250 (8) ALL THE WORK ON RAILWAY PORTION SHALL BE CARRIED OUT UNDER CLOSE SUPERVISION OF
P5
RAILWAY ENGG.
P4 P3
P5 P4 P3 (9) CGM/ENGG/DFCCIL TO ENSURE THE FEASIBILITY OF ERECTION SCHEME BEFORE COMMENCING THE WORK.
9.55 6.56 4.91 25.82
5 (10) CGM/ENGG./DFCCIL TO TAKE ALL THE PRECAUTION AND TAKE NECESSARY TEMPORARY SIGNALING
3 ARRANGEMENT DURING LINE BLOCK AND DURING CASTING OF DECK SLAB.
(11) THE SPECIFIED CRANE SHOULD BE TESTED AND CERTIFIED AFTER REASSEMBLING AT SITE BEFORE
4.86
COMMENCEMENT OF LAUNCHING WORK
STAGE - II 6.57 4.93 25.78
STAGE - II (12) THE POSITION OF CRANE FOR LIFTING OF GIRDER SHALL BE PLANNED IN SUCH MANNER THAT IT IS NOT
TO TARAPUR INFRINGING EXISTING TRACK
WESTERN RAILW
C/L OF EXIST. TRACK-1
STAND BY CRANE WILL ALSO BE ENSURE OF SIMILAR CAPACITY . ALL SLINGS, SHACKLES & LIFTING HOOKS
C/L UP TRK
C/L UP TRK
C/L DN TRK
C/L UP TRK
DFCC BOUNDARY
(16) PRIOR TO LAUNCHING OF ACTUAL GIRDER IT MUST BE ENSURED TO DEMONSTRATE THE CAPACITY OF THE
AY BOU
CRANE
CRANE
CRANE TO LIFT THE REQUIRED WEIGHT CORRESPONDING TO REQUIRED RADII & BOOM LENGTH AT MOCK
LOCATION IN PRESENCE OF RAILWAY/DFCCIL ENGINEER IN-CHARGE
NDARY
37280 (17) ANY GIRDER SHOULD NOT BE LEFT UN BRACED AFTER ERECTION . INCLINED SUPPORTS SHOULD BE FIXED AS
2700 6560 4470 SHOWN TILL END DIAPHRAGMS ARE FIXED PROPERLY.
31280 6560 4470 26250
(18) SITE INCHARGE SHALL ENSURE THAT ACTUAL WEIGHT OF GIRDER TO BE LIFTED BY CRANE DOES NOT
P5 P4 P3 EXCEED THE VALUE GIVEN IN CRANE EFFICIENCY CHART.
P5 P4 P3 (19) PATHWAY FOR CRANE MOVEMENT CROSSING THE EXISING TRACK SHALL BE PREPARED WITH GUNNY BAGS
TO FACE AN EMERGENCY WHICH SHALL BE CLEARED OFF THE TRACK AFTER LAUNCHING OPERATION
15530
18030
187 0
18030
PROVIDE REMAINING BRACING BETWEEN COMPLETE BRACING BETWEEN G4
1820
17800 GIRDER G3 & G4 OVER TRACK PORTION AND G5 IN PORTION OF GIRDER (5) REPEAT STEPS ABOVE TO LAUNCH GIRDER G2. PROVIDE END & CENTRAL BRACINGS, DIAPHRAGM
13030
10530
NOT AFFECTED BY TRACK START BETWEEN G1 & G2 AS SHOWN.
C/L DN TRK
C/L UP TRK
8040
SHUTTERING ACTIVITY OF SLAB (6) REPEAT STEPS 1 TO 5 ABOVE FOR REMAINING GIRDERS G3,G4,G5
DIAPHRAGM & CENTRAL BRACING BRACING
0 BETWEEN G4 & G5 REQUIREMENTS
36900
75
16
2700
30000 (1) SHORT DURATION TRAFFIC AND POWER BLOCK SHALL BE REQUIRED AT LEAST 12 HRS. PRIOR TO
36900
24000
MAJOR BLOCK FOR ENTRANCE OF CRANE INTO WORKING AREA
LAUNCH GIRDER G1,G2,G3,G4 & G5 AND NOT REQUIRED
PROVIDE END & CENTRAL BRACING AND POWER & TRAFFIC (2) SHORT DURATION TRAFFIC AND POWER BLOCK SHALL BE REQUIRED AS FEASIBLE AFTER MAJOR BLOCK
SPAN - 2
15000
DIAPHRAGMS BETWEEN GIRDER BLOCK FOR FIXING OF BRACING OF GIRDER ALREADY LAUNCHING
45000 (3) THE NECESSARY NUMBER OF TRAFFIC WARDEN TO BE DEPLOYED TO GUIDE PEDESTRIANS.
C/L DN TRK
C/L UP TRK
SLING DETAILS :- (4) FLAG MAN AND LAMP MAN TO BE DEPLOYED ON THE TRACK PROTECTION
4000 (5) SINCE THE ERECTION WILL BE DONE IN TRAFFIC BLOCK ALL THE AREA WILL BE ILLUMINATED BY
TOTAL WEIGHT TO BE LIFTED :- 37MT.
30000 LOAD ON CRANE :- 37 MT. FLOOD LIGHT FOR WHICH GENERATOR WILL BE KEPT AS STAND BY ARRANGEMENT FOR LIGHTING.
SAFE CAPACITY OF ONE SLING :- (6) THE TOTAL HOUR OF MAJOR (TRAFFIC / POWER ) BLOCK IN A DAY CAN NOT BE SPLIT IN TO SEPARATE BLOCK
NO.OF SLING USED :- 2 NO. (7) DURING CASTING OF DECK SLAB SPEED RESTRICTION OF 20 KMPLON THE RAILWAY TRACK IS REQUIRED
STAND BY CRANE
6340 MAXIMUM FORCE IN ONE SLING :-
STAND BY CRANE
DIA OF SLING :- 60 MM IMPORTANT NOTES :
TYPE OF SLING TO BE USED :- 6 x 37 M (18/12/6-1) 1570 GRADE STEEL
DETAILS OF SITE PLAN OF LAUNCHING OF SPAN -1 DETAILS OF SITE PLAN OF LAUNCHING OF SPAN-2 CORE AS PER TABLE 3 OF IS 2266:2002 (1) AS PER RAILWAY BOARD LETTER NO. 2015/CE-IV/RUB/206 DATED - 15.02.2016 & 11.08.2016, BASED ON SITE
CONDITION i.e. FOR MAXIMUM BOOM LENGTH AND OPERATING RADIUS, SAFE WORKING LOAD OF CRANE
SHALL BE ASSESSED WHICH SHALL BE MORE THAN 1.5 TIME FOR LOAD TO BE HANDLED
PLAN (2) PATHWAY FOR CRANE MOVEMENT CROSSING EXISTING TRACK SHALL BE TEMPORARILY PREPARED
ADDITIONAL STIFFENERS TO BE PROVIDED AT 1 NO OF 6 x 37 M (18/12/6-1) GIRDER WITH GUNNY BAGS TO FACE AN EMERGENCY WHICH SHALL BE CLEARED OFF THE TRACK AFTER THE
BOTH ENDS TO FIX TEMPORARY SUPPORTING 25 @ BOLT 25 @ BOLT
ISMC - 100 1570 GRADE STEEL CORE OPERATION OF LAUNCHING
(600 x 600 x 20) ARRANGEMENT TO GIRDER (TYP.) ISMC - 250 400 ISMC - 250
PLATE (TYP.) ISMC - 100 CAPACITY = MT BACK TO BACK
50
BACK TO BACK (3) FOR LAUNCHING OF STEEL GIRDER USING ROAD CRANE ALL THE NECESSARY PRECAUTION AS
ISMC - 250
BACK TO BACK (600 x 600 x 20) STIPULATED VIDE HQ LETTER NO. W65/0/BRIDGE (W3) DATED 25.02.2016 SHOULD BE OBSERVED IT
WOODEN PLATE 25 @ BOLT
SLEEPER WOODEN SHOULD BE ENSURE THAT NO CRANE OPERATION IN UNDER TAKEN UNLESS A STAND BY CRANE OF
12 MM THK .PLATE SLEEPER GIRDER ADEQUATE CAPACITY IS AVAILABLE WHICH CAN HANDEL THE JOB IN CASE OF FAILURE OF DESIGNATED
2000
°
>45
DURING LAUNCHING OPERATION.
>45
PIER CAP
45
850
SIDE SUPPORTS ARRANGEMENT WHEN
°
SINGLE GARDER IS PLACED IN POSITION SIDE SUPPORTS ARRANGEMENT WHEN CROSS SECTION OF GIRDER (5) REFER HQ LETTER NO. W65/11/SAFETY DATED 18.06.2019 FOR GUIDELINES FOR TAKING TRAFFIC & POWER
TWO GIRDERS PLACED IN POSITION FIX END DIPHARAMGM BETWEEN FIRST AND SECOND GIRDER BEFORE REMOVING THE SIDE (36.90 M ) BLOCK.
SUPPORT OF 1st & 2nd GIRDER AND PROVIDE SEPARATE SIDE SUPPORTS TO THE NEXT GIRDER
CONTINUE IN SIMILAR WAY FOR NEXT GIRDER.
REFERENCE DRAWINGS :
L/4 L/4
30900 1. GENERAL ARRANGEMENT DRAWING : DRM (B) 24853/14-F, PCE NO.24078-DRM/1-D
°
>45
>45
32 65Ø HOLE
°
80 140 80
220
220 X 80 X 16
DRM(B) 26817/14-F LAUNCHING SCHEME OF ROB IN
GIRDER
32
10 MM THICK PLATE 220 X 300 X 32
LIEU OF LC 55 AT KM 110/14-16
350
SIDE VIEW
Date: 2021.06.07 16:37:15 +05'30'
G1
LIFTING & PLACING
OF GIRDER 1
37.0 MT 19.98 20 31.7 58 63.79 %
AXEN-DESIGN-CCG N K Chaudhary Digitally signed by N K Chaudhary VR-ST SECTION
Date: 2021.06.07 13:11:44 +05'30'
92
32.05 %
VANGAON
11. ERECTION TOOLS AS REQUIRED OF GIRDER 3
25 MT 13.03 14 31.7 27.17 %
LIFTING & PLACING
LIFTING HOOK ARRANGEMENT 12. CHAIN PULLEY 2 NOS G4
OF GIRDER 4
LIFTING & PLACING
25 MT 10.53 12 31.7 110 22.73 %
DRG. NO. CCG/N/MUM/LC-55 LAUNCHING SCHEME/BOR-VGN/2021/008
13. DG SET 2 NOS G5
OF GIRDER 5
25 MT 8.04 10 31.7 130 19.23 %