Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Estimation

Download as pdf or txt
Download as pdf or txt
You are on page 1of 102

ESTIMATION

Estimation is the scientific way of


working out the approximate cost of
an engineering project before
execution of the work.

 It is totally different from calculation of the


exact cost after completion of the project.
 Estimation requires a thorough Knowledge
of the construction procedures and cost of
materials & labour in addition to the skill ,
experience, foresight and good judgment.
ESTIMATE
An estimate of the cost of a construction
job is the probable cost of that job as
computed from plans and specifications.

 For a good estimate the, actual cost of the


proposed work after completion should not
differ by more then 5 to 10 % from its
approximate cost estimate, provided there
are no unusual, unforeseen circumstances.
NEED FOR ESTIMATE
1. It help to work out the approximate cost of the
project in order to decide its feasibility with
respect to the cost and to ensure the financial
resources, it the proposal is approved.

2. Requirements of controlled materials, such as


cement and steel can be estimated for making
applications to the controlling authorities.

3. It is used for framing the tenders for the works


and to check contractor’s work during and after
the its execution for the purpose of making
payments to the contractor.

4. From quantities of different items of work


calculated in detailed estimation, resources are
allocated to different activities of the project and
ultimately their durations and whole planning and
scheduling of the project is carried out.
SITE CONDITIONS AFFECTING THE OVERALL COST
1 = Each type of work requires a different
method of construction. Construction may be of
an ordinary house or office and it may also be
of a Dam, Tunnel, Multistory building, Airport,
Bridge, or a Road, already in operation. Each of
these works requires totally different
construction techniques, type of machinery,
and formwork.

2 = Quality of labour and labour output varies in


different localities.

3 = Weather conditions greatly affect the output


and, hence, the overall cost.
SITE CONDITIONS AFFECTING THE OVERALL COST (-ctd-)

4. Ground conditions vary and change


the method of construction. For
example, excavation may be dry, wet,
hard, soft, shallow or deep requiring
different efforts.

5. The work may be in open ground such


as fields or it may be in congested
areas such as near or on the public
roads, necessitating extensive
watching, lightening, and controlling
efforts, etc.
SITE CONDITIONS AFFECTING THE OVERALL COST (-ctd-)

6. The source of availability of a


sufficient supply of materials of good
quality is also a factor.

7. The availability of construction


machinery also affects the method of
construction.

8. Access to the site must be


reasonable. If the access is poor,
temporary roads may be constructed.
ESSENTIAL QUALITIES OF A GOOD ESTIMATOR
• In preparing an estimate, the Estimator must
have good knowledge regarding the important
rules of quantity surveying.

• He must thoroughly understand the drawings


of the structure, for which he is going to
prepare an estimate.

• He must also be clearly informed about the


specifications showing nature and classes of
works and the materials to be used because
the rates at which various types of works can
be executed depend upon its specifications.
ESSENTIAL QUALITIES OF A GOOD ESTIMATOR (-ctd-)
A good estimator of construction costs should possess the
following capabilities, also:-

1 = A knowledge of the details of construction work.

2 = Experience in construction work.

3 = Having information regarding the materials required,


machinery needed, overhead problems, and costs of all
kinds.

4 = Good judgment with regard to different localities,


different jobs and different workmen.
5 = Selection of a good method for preparing an estimate.

6 = Ability to be careful, thorough, hard working and


accurate.

7 = Ability to collect, classify and evaluate data relating to


estimation.

8 = Ability to visualize all the steps during the process of


construction.
ESSENTIAL QUALITIES OF A GOOD ESTIMATOR (-ctd-)
 Before preparing the estimate, the estimator should visit
the site and make a study of conditions, there. For
example, if the construction of a large building is
planned, the estimator or his representative should visit
the site and:

 Note the location of the proposed building.


 Get all data available regarding the soil.
 Make a sketch of the site showing all important details.
 Obtain information concerning light, power, and water.
 Secure information concerning banking facilities.
 Note conditions of streets leading to railway yards and
to material dealers, and
 Investigate general efficiency of local workman.
TYPES OF ESTIMATES

 There are two main types of estimates:-


1 = Rough cost estimate.
2 = Detailed estimate.

 Depending upon the purpose of estimate,


some types of detailed estimate are as
follows:-
a) Contractor's estimate

b) Engineer's estimate

c) Progress estimate
I = Rough cost estimate

• Estimation of cost before construction from


plans or architectural drawings of the
project scheme, when even detailed or
structural design has not been carried out, is
called Rough cost estimate.

• These estimates are used for obtaining


Administrative Approval from the
concerning Authorities.

• Sometimes, on the basis of rough cost


estimates, a proposal may be dropped
altogether.
Rough cost estimate (-ctd-)
• Unit cost is worked out for projects similar to the project
under consideration carried out recently in nearly the same
site conditions.

• Unit cost means cost of execution of a unit quantity of the


work.
Rough cost estimate (-ctd-)
• To find rough cost of any project, this worked
average unit cost is multiplied with total quantity
of the present work in the same units.

• For example, in case of a building, plinth area (sq.


ft.) of the proposed building is worked out, which
is then multiplied by the cost per unit area (Rs.
/ft2) of similar building actually constructed in the
near past in nearly the same site conditions, to
find out the rough cost estimate of the building.

• This cost is sometimes adjusted by the average


percentage rise in the cost of materials and
wages.
Rough cost estimate
 The rough cost estimate may be prepared on the
following basis for different types of projects:

1. Cost per square foot of covered area (plinth area) is


the most commonly adopted criterion for preparing
rough cost estimate for most of the residential
buildings.

2. For public buildings, cost. Per person (cost per


capita) is used. For example,

Students hostel———————-—cost per student

Hospitals————————————Cost per bed

Hotel—————————————Cost per Guest


Rough cost estimate (-ctd-)
3. Cost per cubic foot is particularly suitable for
commercial offices, shopping centers, and
factory buildings, etc.

4. For water tank/reservoir, cost may be worked out


on the basis of capacity in gallons of water stored.

5. For roads and railways, cost may be found out


per mile/kilometer of length.

6. For streets, cost may be per hundred feet/meters of


length.

7. In case of bridges, cost per foot/meter of clear span


may be calculated.
EXAMPLE

 Calculate the total rough cost

estimate and cost per Flat for a

multi-storey (4-storeyed) block

consisting of 40 residential flats.

Other details are given in the table:


Sr. No PORTION AREA UNIT COST (Rs./sq.ft.)
(sq. ft)
Building Sanitory Electric Sui Gas
Works Works Services Services

1 Main Flat Area

(i) Ground Floor 20030 1800 130 100 60


(ii) Ist Floor 20030 1500 130 100 60
(iii) 2nd Floor 20030 1650 130 100 60
(iv) 3rd Floor 20030 1800 130 100 60

2 Park Area at G. Floor 75,800 800 -------- 40 -------

3 Circulation Area in all 1936 1050 -------- 70 -------


4 floors

4 Covered Shopping 920 950 -------- 70 -------


Area at G. Floor

5 Attached Servant 2112 1150 55 70 40


Quarters
Add the following costs as Lump Sum :
1- Road and Walkways = 15,00,000/-
2- Land Scapping = 12,00,000/-
3- External Sewerage = 7,00,000/-
4- External Water Supply, Overhead and
Underground Water Tanks with pumping
machinery for each set of Flats = 19,00,000/-
5- External Electricity = 3,00,000/-
6- Boundary Wall = 6,00,000/-
7- Miscellaneous unforeseen items
= 8,00,000/-
8- Add 6 % development charges.
9- Add 3 % consultancy charges
DETAILED ESTIMATE

• Detailed estimates are prepared by carefully


and separately calculating in detail the costs of
various items of the work that constitute the
whole project from the detailed working
drawings after the design has been finalized.

• The mistakes, if any, in the rough cost estimate are


eliminated in the detailed estimate.

• Detailed estimates are submitted to the competent


authorities for obtaining technical sanction.
DETAILED ESTIMATE
 The whole project is sub-divided into different
items of work or activities. The quantity for each
item is then calculated separately from the
drawings as accurately as possible. The procedure
is known as "taking out of quantities".

 The quantities for each item may be estimated and


shown in the pattern which is called "Bill of
quantities."

 The unit, in which each item of the wok is to be


calculated, should be according to the prevailing
practice as followed in various departments of the
country.
BILL OF QUANTITIES
Description No Measurements Quantity Total Remarks
Sr. No
of item Quantity

Length Breadth Height


PRICED BILL OF QUANTITIES

Sr. No. Description of Item Unit Quantity Rate Cost Remarks


DETAILED ESTIMATE

 Each item of the work is then multiplied by its


estimated current rate calculated by a fixed procedure
to find out cost of the item.

 At the end, a total of all items of the work are made to


get the total estimated cost.

 The rates are usually as per Schedule of Rates for the


locality plus a premium to allow for rise in labor and
material rates over and above the schedule of rates.

 A percentage, usually 5% is also provided on the total


estimated cost for the work to allow for the possible
contingencies due to unforeseen items or expenditure
or other causes, besides 2% establishment charges.
DETAILED ESTIMATE

 Besides drawings and details of measurements and


calculation of quantities (Bill of Quantities), the following
documents are also usually submitted with the detailed
estimate for obtaining Technical Sanction:

1. A report explaining History, necessity, scope and main


features of the project, its design, and estimate, etc.

2. Specifications lying down the nature and class of work


and material to be used in various parts of the work.

3. The abstract of cost (priced Bill of Quantities) showing


the total quantities under each sub-head, rate per unit of
measurement, and cost.

4. Calculation sheets showing calculations for important


parts of the structure. In fact, in estimating the art and
skill lies only in the computation of details without any
omissions, of all parts of the building or work.
CLASSIFICATION DEPENDING UPON
PURPOSE OF DETAILED ESTIMATE
1- CONTRACTOR ESTIMATE
It is made by the contractor for determining
the price or prices to be bid.
It is usually a carefully prepared detailed
estimate.

2- ENGINEER’S ESTIMATE

This type of estimate is made by the Engineer


(Consultant) usually for the purposes of
financing the work and for checking bids and
running bills submitted by contractors.
3- PROGRESS ESTIMATES
• These are made by the Engineer at
regular intervals for the completed parts
of the project during the progress of the
work for determining the amounts of
partial payments to be made to the
contractor.

• On large contracts, such estimates are


commonly made each month and, hence,
are frequently called monthly estimates.
UNFORESEEN ITEMS IN DETAILED ESTIMATE
• While preparing a detailed estimate, one had to
be very careful to see that all items of the work
are incorporated.
• It is likely that a few Items, though
unimportant in nature, might have been
overlooked and which may result in raising the
estimate of the project.
• There may be also certain unforeseen
circumstances affecting the project.
• Hence, a certain allowance usually 5 to 10% of
the total cost, is made in the estimation which
will take care of all these items that are
unforeseen or are overlooked and are known as
"Contingencies".
METHODS OF DETAILED ESTIMATE
 The dimensions, length, breadth and height or depth
are to be taken out from the working drawings (plan,
elevation and section).

 Junctions of walls, corners and the meeting points of


walls require special attention.

 For symmetrical footings, which is the usual case,


earthwork in excavation in foundations, foundation
concrete, brickwork in foundation and plinth, and
brickwork in superstructure may be estimated by either
of the two methods:

(1) SEPARATE OR INDIVIDUAL WALL METHOD


(2) CENTER LINE METHOD
SEPARATE OR INDIVIDUAL WALLS METHOD
• The walls running in one direction are termed as
"long walls” and the walls running in the
transverse direction, as "Short waLls", without
keeping in mind which wall is lesser in length
and which wall is greater in length.
• Lengths of long walls are measured or found
"Out-to out" and those of short walls as "In-
to-in".
• Different quantities are calculated by multiplying
the length by the breadth and the height of the
wall.
• The same rule applies to the excavation in
foundation, to concrete bed in foundation,
D.P.C., masonry in foundation and super
structure etc.
SEPARATE OR INDIVIDUAL WALLS METHOD
• For symmetrical footing on either side, the
center line remains same for super structure,
foundation and plinth. So, the simple method is
to find out the centre-to-centre lengths of long
walls and short walls from the plan.
• Long wall length out-to-out
= Center to center length + half breadth on
one Side + half breadth on other side.

= Center to center length + one breadth

• Short wall length in-to-in = Center to Center


length - one breadth.
SEPARATE OR INDIVIDUAL WALLS METHOD
This method can also be worked out in a quicker way., as follows:

 For long walls


• First of all, find the length of the foundation trench of the long
wall “out-to-out” in the same manner as explained above.
• The length of the foundation concrete is the same.
• For the length of the first footing or first step of the brick wall,
subtract two offsets (2x6"=12") in foundation concrete from the
length of the trench or concrete.
• For the second footing subtract from the length of the 1st footing
two offsets (2x2.25"= 4.5"), for 3rd footing subtract from the
length of the 2nd footing 2 offsets (4.5") and in this way deal
with the long walls up to the super-structure.

 For short walls


Follow he same method but instead of subtracting add two
offsets to get the corresponding lengths in-to-in.
12 Breadth 12 Breadth

Foundation
Trench
CENTRE LINE METHOD
 In this method, total length of centre lines of walls,
long and short, has to be found out.
 Find the total length of centre lines of walls of same
type, having same type of foundations and footings and
then find the quantities by multiplying the total centre
length by the respective breadth and the height.
 In this method, the length will remain the same for
excavation in foundations, for concrete in foundations,
for all footings, and for superstructure (with slight
difference when there are cross walls or number of
junctions).
 This method is quicker but requires special attention
and considerations at the junctions, meeting points of
partition or cross walls.
CENTRE LINE METHOD
 For rectangular, circular polygonal (hexagonal,
octagonal etc) buildings having no inter or cross
walls, this method is quite simple.

 For buildings having cross or partition walls, for


every junction, half breadth of the respective
item or footing is to be deducted from the total
centre length.

 Thus in the case of a building with one partition


wall or cross wall having two junctions, deduct
one breadth of the respective item of work from
the total centre length.
CENTRE LINE METHOD
 For buildings having different types of walls, each set of
walls shall have to be dealt separately.

 Find the total centre length of all walls of one type and
proceed in the same manner as described above. Similarly
find the total centre length of walls of second type and deal
this separately, and so on.

 Suppose the outer walls (main walls) are of A type and


inner cross walls are of B type.

 Then all A type walls shall be taken jointly first, and then all
B type walls shall be taken together separately.

 In such cases, no deduction of any kind need be made for A


type walls, but when B type walls are taken, for each
junction deduction of half breadth of A type walls (main
Walls) shall have to be made from the total centre length of
B type walls.
CENTRE LINE METHOD

 At corners of the building where two walls


are meeting, no subtraction or addition is
required.

 In the figure, the double cross-hatched


areas marked P,Q,R, & S come twice,
while blank areas, A,B,C, & D do not come
at all, but these portions being equal in
magnitude, we get the correct quantity.
DESCRIPTION AND UNITS OF
MEASUREMENT FOR
COMMON ITEMS
1 = SITE CLEARANCE WORKS

• This item is described in detail but


the price of this item is usually
indicated as lump sum (LS).

• The cost of this item is provided in


the estimate by judgment, according
to the description of the item and is
indicated as Lump sum (L.S).
2 = EXCAVATION FOR FOUNDATION TRENCHES

• Earthwork in excavation for foundation


trenches is calculated by taking the
dimensions of each trench as length X
breadth X depth.

• It is measured in cubic ft, cubic yard or


cubic meter, according to the prevailing
practice.

• The payment for this item is generally


done as Rs. per hundred cubic ft.
FILLING IN TRENCHES
 Filling in trenches after the
construction of foundation
masonry is ordinary neglected. If
the trench filling is, also taken in
account, it may be calculated by
deducing the volume of masonry
in trenches from that of the
volume of excavation.
3 = FOUNDATION CONCRETE (P.C.C.)
• The type of concrete must be clearly
mentioned. The mix proportions and the type of
cement, sand and coarse aggregate must be
specified.

• This item is measured in cubic ft and the


unit for measurement is, generally Rs. per
100 cubic ft.

• When the soil is soft or weak, one layer of dry


bricks or stone soling is applied below the
foundation concrete. The soling layer is
computed in sq.ft (length X breadth), specifying
the thickness in description of item.
4 = BRICKWORK IN FOUNDATION UP TO PLINTH

 Care must be taken, while taking dimensions


from the drawings in the bill of quantities
because the walls in this part of the structure
are in the form of steps with changing
dimensions.

 This item is calculated in cft and the unit for


payment is Rs. per 100 cft.

 In the description of work, the quality of bricks


and mortar ratio must be specified. For example,
"Brickwork in foundation and plinth using first
class bricks laid in (1:4) or (1:6) cement-sand
(c/s) mortar———————“
5 = BRICKWORK IN SUPER STRUCTURE
Important considerations are:

a = Measurements of walls shall be taken in the


same order and in the same manner as for
brickwork in foundations and plinth.

b = In the first measurements, all openings


such as doors, windows, veranda openings etc.
shall be neglected. However, deductions shall
be made for all openings in the walls, at the
end of the item.
BRICKWORK IN SUPER STRUCTURE (ctd)
c = In the description of the work, the quality
of bricks and mortar ratio have to be specified.

d = Masonry for arches shall be paid separately,


at a different rate.

e = The height of super structure is very


important. Generally the quantities are
worked out for each storey separately and
rates would be different for different storeis
because of additional labor work, scaffolding
and shuttering.

f = The item is worked out in cft and the


standard unit for payment is Rs. Per 100 cft.
6 = DAMP PROOF COURSE (D.P.C.)
 Horizontal D.P.C. shall extend the full width of
the super structure walls, however, it shall not
be provided across doorways and veranda
openings. It is also provided in roof and floors.

 Vertical D.P.C. is provided in external walls,


especially, in the walls of basements.

 The quantity of D.P.C. is estimated in square ft.


(on area basis) and standard unit for payment
is Rs. per 100 sft.
7 = ROOFING & RCC WORKS
 Area of the Roof slab is calculated by taking inside
dimensions of the room plus a bearing of the roof slab
on the walls, on all sides.

 For R.C.C. Roof slabs and beams, the total quantities


of concrete and steel are estimated, separately.

 The quantity of plain concrete is estimated in cft and


the standard unit for payment of concrete is Rs. per
100 cft.

 Volume of Reinforcing Steel is not deducted , while


estimating the volume of plain concrete for payment.

 c= R.C.C. lintels over wall openings such as doors


and windows are also included in R.C.C. work.
ROOFING & RCC WORKS (ctd)
• Roof consisting of beams, battens, and tiles or wooden
planks is estimated for each part, separately.

Steel beam is estimated by weight, whereas, wooden


beam is measured in cft. Battens are estimated by
numbers indicating there size and lengths. Tiles are
also estimated by size and numbers.

• Roof finishing may consist of bitumen coating and/or


Polythene sheets (water proofing) , earth filling (heat
proofing) and brick tiles, etc.

Dimensions are taken from inner face to inner face of


parapet walls.

This item is estimated in sft and a composite rate for


payment is taken as Rs. per 100 sft of the roof area.
8 = REINFORCEMENT STEEL /
GENERAL STEEL WORK
 Steel is provided separately from R.C.C.
per ton, per Kg, or per cwt (standard
weight also called Quintal or century
weight equal to 112 Ibs = 50Kg).

 Quantity of steel can either be worked


out by rules of thumb practice or by
intensive calculations taking the length
and diameter of steel bars from the
working drawings showing reinforcement
details and bar-bending schedules. In
taking length of bars, due margin of
hooks, bends and overlapping is given
REINFORCEMENT STEEL / GENERAL STEEL
WORK (-ctd-)

 As a Rule Of Thumb Practice,


for ordinary beams and slabs for residences,
assume 6.75 Ibs of steel per cft of R.C.C. work.
However, for R.C.C. columns, it varies from 8
to 10 Ibs per cft., because normally, we use
2% of steel in columns.

 Percentage of steel means, area of steel divided


by total area of the column multiplied by 100
and 1% of steel in columns corresponds to a
quantity of 4.5 Ibs/cft.
9 = FLOORS
 Cement concrete floors. Mosaic floors, and brick
floors are most commonly used.

 Payments are made separately for different


layers, like, topping, lean concrete, sand filling,
earth filling, etc.

 Earth filling, sand filling and lean concrete are


paid by volume, whereas, topping is paid on
area basis, mentioning thickness in the
description.

 Standard unit for payment of topping is, usually,


Rs. per 100 sft.

 The skirting is estimated in running ft.


10 = PLASTERING
 The type of plaster, proportioning of materials
and minimum thickness of plaster have to be
specified.

 The quantity is calculated for total wall surface


without deduction for openings such as doors
windows, ventilators, etc. However, if the wall is
being plastered on both the faces, the deductions
for opening areas are made from one side only.

 Standard unit for payment is Rs. per 100 sft.

 Height is also specified for plastering because, for


greater heights, labor cost increases. The rate
varies according to the number of the storey
11 = WOODWORK/CARPENTRY
 The type of material used and the quantity of
finish required should be clearly indicated in the
description of the item.

 The rate for any type of woodwork includes


cutting of timber to required sizes, joinery
work, fittings and fastenings, three coats of oil
paints or varnish, bolts, locks, handles, etc.

 The measurements are taken for the overall


area of doors, windows, etc. If volume of
timber required for these items is to be finding
out, the computed area is multiplied with the
nominal thickness and an allowance of 25% is
made for wastage of timber.
WOODWORK/CARPENTRY (-ctd-)
 Rectangular wooden beams, vertical
columns, trusses, etc., are measured in
cft.

 Wooden stairs are measured in number


of steps and description of the item
includes the riser, tread, and width of the
steps.

 Wooden shelves are measured in running


ft (RFT).
12 = PLUMBING WORK/SANITARY FITTINGS

 For water supply and drainage works in a


building, the pipe lines and sewer lines are
measured in RFT, while other items are
measured in numbers.

 These items include wash hand basins


(W.H.B.), kitchen basins (which may be of
glazed ceramic, mosaic, or stainless steel),
water closets (W.C., which may be of European
type, or local type), flushing tanks (also
known as flushing cisterns), shower rose, and
all type of water tapes.
PLUMBING WORK/SANITARY FITTINGS (-ctd-)
 Within sewer lines, man holes or inspection chambers are
to be provided at every corner and also at a distance, not
exceeding every 50 ft inside the house and every 100 ft
outside the house.

 The size of man hole may be 2.5ft X 2,5ft for low depths
and 3ft X 3ft, 4ft X 4ft or 5ft X 5ft for deep depths.

 Drainage pipe lines outside the covered area but inside the
boundary wall are, usually, of R.C.C. with minimum
diameter 4 in, however, these are available in different
sizes.

 Inside the building, drainage pipe is, usually, of C.I. with


minimum diameter 3 in.

 Water supply pipes are, usually, G.I. pipes., estimated in


RFT in different dias.

 Other accessories, like sockets, elbows, tees, reducers,


unions, etc., are estimated in numbers.
13 = ELECTRIC FITTINGS

• All the accessories used in electric


fittings are described in detail and
payment is done in numbers or RFT.

• All wires and pipes are taken in RFT


while other items are taken in No’s.
SOME COMMON RELATIONS
USED IN BUILDING
ESTIMATES
1- MORTARS

(a) Cement-Sand Mortars


120 cft dry yields 100 cft wet

(b) Lime-Sand Mortars


113 cft dry yields 100 cft wet

(C) Cement-Lime-Sand Mortars


112 cft dry yields 100 cft wet

(d) Dry mortar required for 100 sft of ½” thick cement


plaster =6 cft
2- CEMENT CONCRETE
154 cft dry yields 100 cft wet

3- BRICKWORK
(a) 100 cft Brick masonary Bricks ------------1350
Dry Mortar ------- 30 cft
Wet Mortar ------- 25 cft

(b) 100 sft surface area using bricks on bed


Bricks --------------360
Mortar ------------- 9 cft

(b) 100 sft surface area using bricks on edge


Bricks --------------540
Mortar ------------- 13 cft
4- POINTING PER 1000 SFT AREA

Ingredient 1:1 1:2 1:3


Cement 8 cft 5 cft 3.8 cft
Sand 8 cft 10 cft 11.4 cft

5- EARTHWORK
Output of labor assuming one man working 8 hours per day with lift up to
5 ft or less

TYPE OF SOIL EXCAVATION PER DAY


Medium Soil 75 – 100 cft
Hard / Stiff Soil 50 – 75 cft
Rocky Soil 25 – 30 cft
6- BITUMEN

Bitumen for 100 sft of DPC (first coat) = 15 Kg

Bitumen for 100 sft of DPC (second = 10 Kg


coat)

7- CEMENT
1 Bag ------------- 50 Kg (Weight), 1.25 cft (Volume)

8- SPECIFIC WEIGHTS
RCC --------------- 150 lbs / cft

PCC --------------- 145 lbs / cft

Aggregate ------- 166 lbs / cft


9- TIMBER

Timber for 100 sft of Panelled Doors and


Windows = 13 cft

Timber for 100 sft of Glazed windows and


Ventilators = 8 cft

10- WHITE WASH

Lime for 100 sft of white wash (one coat) = 1.00 Kg


ESTIMATION OF A SIMPLE
BUILDING
PLAN
FOUNDATIONS
SPECIFICATIONS
 Clear height of rooms: 12’
 Clear height of Verandah: 10’-0”
 Plinth level: 1’-6”
 Thickness of roof slab: 4”
 Thickness of RCC shade: 3”
 Depth of RCC Beams in Verandah: 1’-6” below verandah slab
 Parapet wall: 1’-0” (Clear height above roof tiles)
 Ventilators (4 No.): 2’-6” x 1’-6”
 RCC lintel: 6” in depth
 Damp proof coarse: 1 ½”thick PCC (1:2:4) + 2 coats of hot
bitumen + polythene sheet
 Full foundation up to plinth level along verandah periphery is
provided
 Internal finishes: Three coats of white wash/distemper paint
 External finishes: Three coats of Weather shield paint
Center to Center Lengths

 L1 = (10’-0”) + (12’-0”) + (0’-4 ½”) + (0’-4 ½”) +


(0’-4 ½”) = 23’-1 ½”

 S1& S2 = (12’-0”) + (0’-4 ½”) + (0’-4 ½”) = 12’-9”

 S3 = (8’-0”) + (0’-4 ½”) - (0’-4 ½”) = 8’-0”


BILL OF QUANTITIES
1- CIVIL WORKS
S. Description of item No Measurement Quantity Total Quantity Remarks
No
Length Breadth Depth

1 Earthwork for
excavation
in
foundation
trenches
L1 3 25’-7 ½ //
2’-6” 3’-6” 224.22 cft 672.66 cft L = 23’-1 ½”+2’-6” = 25’-7 ½”

S1 2 10’-3” 2’-6” 3’-6” 89.69 cft 179 .38 cft L = 12’-9”-(2’-6)” = 10’-3”

S2 1 10’-3” 2’-1 ½ ” 3’-6” 76.23 cft 76.23 cft L = 12’-9”-(2’-6)” = 10’-3”

S3 2 5’-6” 2’-6” 3’-6” 48.13 cft 96.25 cft L = 8’-0”-(2’-6)” = 5’-6”

Total = 1024.52 cft


2
Earth work in
filing under
floors
Room No.1 1 12’-0” 12’-0” 0’-6 ½ ” 78.00 cft 78.00 cft D = 1’-6”-(0’-11 ½”) = 6 1/2”

Room No.2 1 10’-0” 12’-0” 0’-6 ½ ” 65.00 cft 65.00 cft

Veranda 1 22’-4 ½ ” 7’-3” 0’-6 ½” 87.87 cft 87.87 cft L = 10’-0”+(0’-4½”)+(12’-0”)


= 22’-4 ½”
B = 8’-0”-(0’-9)”= 7’-3”

Total = 230.87 cft

3
P.C.C (1:4:8) in Length & Breadth
foundation using same as for
crushed or Foundation trenches
broken stones (Item No. 1)

L1 3 25’-7 ½ ” 2’-6” 0’-6” 32.00 cft 96.00 cft

S1 2 10’-3” 2’-6” 0’-6” 12.81 cft 25.63 cft

S2 1 10’-3 2’-1 ½” 0’-6” 10.89 cft 10.89 cft

S3 2 5’-6 2’-6” 0’-6” 6.87 cft 13.75 cft

Total= 146.27 cft


4
Burnt brick work
in foundation and
plinth using first
class bricks in
(1:6) cements
sand mortar.
(a) L1

1st step 3 24’-7 ½ ” 1’-6” 0’-6” 18.47 cft 55.40 cft L = 23’-1½”+(1’-6”) = 24’-7½”

2nd step 3 24’-3” 1’-1 ½ “ 0’-6” 13.64 cft 40.92 cft L = 23’-1½”+(1’-1½”) = 24’-3”

3rd step up to plinth 3 23’-10 ½” 0’-9” 3’-4 ½” 60.43 cft 181.30 L = 23’-1½”+(0’-9”) =
level cft 23’-10½”
D = 2’-0” +(1’-6”) –(0’-1 ½”)
= 3’-4 ½”

Total= 277.62
cft
(b) S1

1st step 2 11’-3” 1’-6” 0’-6” 8.44 cft 16.88 cft L = 12’-9”-(1’-6”) = 11’-3”

2nd step 2 11’-7 ½ ” 1’-1 ½ ” 0’-6” 6.54 cft 13.08 cft L = 12’-9”-( 1’-1½”) = 11’-7½”

3rd step up to plinth 2 12’-0” 0’-9” 3’-4 ½ ” 30.37 cft 60.75 cft L = 12’-9”-( 0’-9”) = 12’-0”
level

Total= 90.71 cft


(c) S2

1st step 1 11’-3” 1’-1 ½ ” 0’-6” 6.33 cft 6.33 cft L = 12’-9”-(1’-6 ”) = 11’-3”

2nd step 1 11’-7 ½ ” 0’-9 ” 0’-6” 4.36 cft 4.36 cft L = 12’-9”-( 1’-1½”)= 11’-7½”

3rd step up to plinth 1 12’-0” 0’-4 ½ ” 3’-4 ½ ” 15.19 cft 15.19 cft L = 12’-9”-( 0’-9”) = 12’-0”
level
Total= 25.88 cft

(d)S3

1st step 2 6’-6” 1’-6” 0’-6” 4.87 cft 9.75 cft L = 8’-0”-(1’6”) = 6’-6’

2nd step 2 6’-10 ½ ” 1’-1 ½” 0’-6” 3.86 cft 7.73 cft L = 8’-0”-(1’-1½”) = 6’-10½”

3rd step up to plinth 2 7’-3” 0’-9” 3’-4 ½ ” 18.35 cft 36.70 cft L = 8’-0”-(0’-9”) = 7’-3”
level
Total= 54.18 cft

(e) steps in front of


verandah

1st step 1 23’-10 ½” 2’-0” 0’-6” 23.88 cft 23.88 cft L = 23’-1½”+(0’-4½”) +
(0’-4½”) =23’-10½”

2nd step 1 23’-10 ½” 1’-0” 0’-6” 11.94 cft 11.94 cft

Total= 35.82 cft

G.Total= 484.21 cft


5
1-1/2” thick P.C.C Length &
(1:2:4) in DPC Breadth same
including two as for plinth
wall
coats of hot
bitumen & 2
layers of
Polythene sheet

L1 2 23’-10 ½” 0’-9” - 17.9 sft 35.81 sft

S1 2 12’-0” 0’-9” - 9.00 sft 18.00 sft

S2 1 12’-0” 0’-4 ½” - 4.5 sft 4.50 sft

Verandah columns 3 0’-9” 0’-9” - 0.56 sft 1.69 sft

Total = 60.00 sft

Deduction of Door sills 1 4’-0” 0’-9” - 3.00 sft 3.00 sft

1 4’-0’ 0’-4 ½” - 1.50 sft 1.50sft

Total= 4.50 sft

Net Total = 55.50 sft


6
Brick work in Length & Breadth
super structure same as for plinth
using first class wall
bricks in (1:4)
cement sand
mortar
L1 2 23’-10 ½” 0’-9” 13’-10 ½” 248.45 cft 496.90 cft H = 12’-0” (Room height) +
0’-4” ( Slab) + 0’-4’’ (Earth
filling) + 0’-1”(Mud plaster)
+ 0’-1½” (Tiles) + 1’-0”
(P. wall)
= 13’-10½”

S1 2 12’-0” 0’-9” 13’-10 ½” 124.87 cft 249.75 cft

S2 1 12’-0” 0’-4½ ” 12’-0” 54.00 cft 54.00 cft No Parapet Walls

Verandah columns 3 0’-9” 0’-9” 8’-6” 4.78 cft 14.34 cft H=10’-0”- (1’-6”)=8’-6”

Verandah parapet walls

(i) L1 1 23’-10 ½” 0’-9” 1’-6 ½” 27.60 cft 27.60 cft H = 0’-4” (Earth filling) + 0’-
1” (Mud plaster) +
0’-1½” (Tiles) + 1’-0” (P.
walls) = 1’-6½”

(ii) S3 2 7’-3” 0’-9” 1’-6 ½ ” 8.38 cft 16.76 cft

Total= 859.35 cft


Deduction
Doors 1 4’-0” 0’-9” 7’-0” 21.00 cft 21.00 cft
1 4’-0” 0’-4 ½ ” 7’-0” 10.5 cft 10.50 cft

Windows 3 4’-0” 0’-9” 4’-0” 12.00 cft 36.0 cft


Ventilators 4 2’-6” 0’-9” 1’--6” 2.81 cft 11.25 cft

Shelves 2 4’-0” 0’-6” 5’-0” 10.00 cft 20.00 cft


RCC lintels over
(i)doors 1 5’-0” 0’-9” 0’-6’ 1.87 cft 1.87 cft
1 5’-0” 0’-4 ½ ” 0’-6’ 0.93 cft 0.93 cft

(ii)Windows 3 5’-0” 0’-9” 0’-6’ 1.87 cft 5.62 cft


(iii)Ventilators 4 3’-6” 0’-9” 0’-6’ 1.31 cft 5.25 cft
(iv)Shelves 2 5’-0” 0’-9” 0’-6’ 1.87 cft 3.75 cft
Total = 116.18 cft
Net Total = 743.17 cft
7 Reinforced There is 4½”
cement bearing of both
concrete slabs on all walls
(1:2:4) as in
roof slab,
lintels,
columns,
beams etc.,
(reinforcement
will be
measured
separately)

Roof slab of 1 23’-1 ½” 12’-9” 0’-4” 98.28 cft 98.28 cft L = 10”-0” + 12’-0” +
rooms 0’-4½” + 0’-9” (2
bearings) = 23’-1½”
B = 12’-0” + 0-
4½”(bearing) + 0’-
4½”(bearing) = 12’-9”
Roof slab of 1 23’-10 ½ ” 8’-4 ½ ” 0’-4” 66.65 cft 66.65 cft B = 8’-0” + 0’-4½”
Verandah (bearing) = 8’-4½”
Verandah
beam
Long beam 1 23’-1 0½” 0’-9” 1’-6” 26.86 cft 26.86 cft
Short beam 2 7’-7 ½ ” 0’-9” 1’-6” 8.59 cft 17.18 cft L=8’-0”-(0’-9”) + (0’-
4½”) = 7’-7½”
Lintels
Doors 1 5’-0” 0’-9” 0’-6’ 1.87 cft 1.87 cft
1 5’-0” 0’-4½ ” 0’-6’ 0.93 cft 0.93 cft
Windows 3 5’-0” 0’-9” 0’-6’ 1.87 cft 5.62 cft
Ventilators 4 3’-6” 0’-9” 0’-6’ 1.31 cft 5.25 cft
Shelves 2 5’-0” 0’-9” 0’-6’ 1.87 cft 3.75 cft
Shades 2 5’-0” 1’-6” 0’-3” 1.87 cft 3.75 cft
Total= 226.39 cft
8 Mild steel round 6.75 lbs/cft
bars as steel of
reinforcement 226.39 cft
including cutting, concrete
bending, binding
and placing =1528.13
reinforcement in lbs
position

Total= 1529.00 lbs


9 Roof insulation
comprising of 2
coats of hot
bitumen, 4” thick
earth filling, 1”
thick mud plaster
and 1-1/2” thick
brick tiles jointed
and pointed in
cement sand mortar
(1:3)

Rooms (1 & 2) 1 22’-4 ½ ” 12’-0” - 268.50 268.5 sft L = 10’-0”+ (12”-


sft 0”) + (0’-4½”)
= 22’- 4-½”
Verandah 1 22’-4 ½ ” 7’-3” - 162.22 162.22 cft B = 8’- 0”- (0’-9”) =
cft 7’-3”
Total = 430.72 sft
10 Sand under floors
Room No.1 1 10’-0” 12’-0” 0’-6” 60.00 cft 60.00 cft
Room No.2 1 12’-0” 12’-0” 0’-6” 72.00 cft 72.00 cft
Verandah 1 22’-4½ ” 7’-3” 0’-6” 81.11 cft 81.11 cft
Total = 213.11 cft
11 Cement concrete
(1:4:8) as under
layer of floors
Room No.1 1 10’-0” 12’-0” 0’-4” 40.00 cft 40.00 cft
Room No.2 1 12’-0” 12’-0” 0’-4” 48.00 cft 48.00 cft
Verandah 1 22’-4 ½ ” 7’-3” 0’-4” 54.07 cft 54.07 cft
Total = 142.07 cft
12 1-1/2” thick
cement
concrete
(1:2:4) as top
layer of floor,
finished
smooth

Room No.1 1 10’-0” 12’-0” - 120.00 120.00 sft


sft
Room No.2 1 12’-0” 12’-0” - 144.00 144.00 sft
sft
Verandah 1 23’-10 ½” 8’-0” - 191.00 191.00 sft L = 10’-0” + (12’-0”) +
sft (0’-4 ½ ”) + (0’-9”) +
(0’-9”) = 23’-10 ½ ”
Door sill 1 1 4’-0’ 0’-9” - 3.00 sft 3.00 sft
Door sill 1 1 4’-0” 0’-4 ½ - 1.50sft 1.50sft

Total= 459.5 sft
Deduction
Columns 3 0’-9” 0’-9” - 0.56 sft 1.68sft
Net 457.80 sft
Total=
13
½” thick (1:3)
cement sand
plaster to walls
finished smooth
Inner side

Room No.1 (Long wall) 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
Room No.1(Short wall) 2 10’-0” - 12’-0” 120.00 sft 240.00 sft
Room No.1 (Ceiling) 1 10’-0” - 12’-0” 120.00 sft 120.00 sft
Room No.2 (Long wall) 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
Room No.2(Short wall) 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
Room No.2 (Ceiling) 1 12’-0” - 12’-0” 144.00 sft 144.00 sft
Verandah wall 1 23’-10 ½” - 10’-0” 238.75 sft 238.75 sft L = (10’-0”) + (12’-0”) +
(0’-4½ “) +(0’-9”)+ (0’-9”)
= 23’-10 ½ “
Verandah ceiling 1 22’-4 ½” - 7’ –3” 162.26 sft 162.26 sft L = (10’-0”)+(12’-0”)

+(0’-4 ½ “) = 22’-½“
Columns 3 3’-0” - 8’-6” 25.50 sft 76.5 sft L = (0’-9”) + (0’-9”) +
(0’-9”) + (0’-9”) = 3’-0 ”
Long beam (internal 1 22’-4 ½” - 1’-6” 33.55 sft 33.55 sft
side)
Long beam (soffit) 2 10’-9 ¾” - 0’-9” 8.10 sft 16.21 sft L={(22’-4 ½”)-(0’-9”)}/2
=10’-9¾”
Short beam (internal 2 7’-3” - 1’-6” 10.87 sft 21.74 sft L={(8’-0”)-(0’-9”)}
sides) = 7’-3”

Short beam (soffit) 2 7’-3” - 0’-9” 5.43 sft 10.87 sft


Door jambs 2 0’-9” - 7’-0” 5.25 sft 10.50 sft

2 0’-4½” - 7’-0” 2.63 sft 5.25 sft

1 0’-9” - 4’-0” 3.0 sft 1.50 sft

1 0’-4½” - 4’-0” 1.50 sft 3.00 sft

Window jambs 6 0’-9” - 4’-0” 3.00 sft 18.00 sft

6 0’-9” - 4’-0” 3.00 sft 18.00 sft

Ventilator jambs 8 0’-9” - 2’-6” 1.88 sft 15.00 sft

8 0’-9” - 1’-6” 1.19 sft 9.00 sft

Shelves 4 0’-6” - 5’-0” 2.5 sft 10.00 sft

4 0’-6” - 4’-0” 2.0 sft 8.00 sft

Outer side
Rear wall 1 23’-10 ½” - 15’- 379.00 379.00 sft H = (0’-6”) + (1’-6”) +
10½” sft (12’-0”) + (0’-4”) + (0’-
(From 6” below 4’’) + (0’-1”) + (0’-1½”)
G.L. to Parapet + (1’-0”)
walls) = 15’-10½”
Left & Right side 2 13’-6” - 15’- 214.32 428.64 sft L= (12’-0”) + (0’-9”) +
wall 10½” sft (0’-9”)
= 13’-6”
Front side (above 1 23’-10 ½” - 3’-0” 71.63 sft 71.63 sft H = (12’-0”) + 0’-10½”)
verandah roof) + (1’-0”) - (10’-10 ½” )
= 3’-0”
Left & Right side 2 8’-0” - 2’-0” 16.00 sft 32.00 sft H = (1’ – 6’’) + (0’ – 6’’)
plinth of verandah = 2’ – 0’’
Parapet wall
Inner side of rooms 2 22’-4 ½” - 1’-0” 22.37 sft 44.70 sft L = (10’-0”)+(12’-0”)
+(0’-4 ½ “)
= 22’-4 ½ “
2 12’-0” - 1’-0” 12.00 sft 24.00 sft
Inner side of 1 22’-4 ½” - 1’-0” 22.37 sft 22.37 sft
Verandah
2 7’-3 “ - 1’-0” 7.25 sft 14.50 sft
Outer side of 1 23’-10 ½” - 3’- 67.66sft 67.66 sft H = (1’-6”)+(0’-4”)
Verandah 4 ½” +(0’-6 ½”) + (1’-0 “)
= 3’-4 1/2//

2 8’-0” - 2’-10” 22.67 sft 45.33 sft


Top of parapet wall 2 23’-10 ½” - 0’-9” 17.9 sft 35.80 sft
(Rooms)
2 12’-0” - 0’-9” 9.00 sft 18.00 sft
Top of parapet wall 1 23’-10 ½” - 0’-9” 17.90 sft 17.90 sft
(Verandah)
2 7’-3” - 0’-9” 5.43 sft 10.87 sft
Steps
Tread 2 23’-10 ½” - 1’-0” 23.87 sft 47.74 sft
Riser 3 23’-10 ½” - 0’-6” 11.93 sft 35.80 sft
Sides 2 2’ – 00’’ 0’-6” 1.00 sft 2.00 sft
2 1’ – 00’’ 0’-6” 0.5 sft 1.00 sft
Total= 3316.07 sft
Deduction
Doors 2 4’-0’ - 7’-0” 28.00 sft 56.00 sft
Windows 3 4’-0’ - 4’-0” 16.00 sft 48.00 sft
Ventilators 4 2’-6” - 1’-6” 3.75 sft 15.00 sft
Total= 119.00 sft
Net Total= 3197.07 sft
14 Wood work as
in
(i) 1 ½” thick 2 4’-0’ - 7’-0” 28.00 sft 56.00 sft
wooden doors
with chowkat,.
Total = 56.00 sft
(ii) Glazed and 3 4’-0’ - 4’-0” 16.00 sft 48.00 sft
gauzed windows
and ventilators.
4 2’-6’ - 1’-6” 3.75 sft 15.00 sft
Total = 63.00 sft
G.Total 119.00 sft
=
15 Three coats of - - - - - .(2 x Qty of item
painting to No.14)
doors , = 238.0 sft
windows and
ventilators
Total 238.00 sft
16 Three coats of
distempering/
white washing to
walls (Internal
Side)
Room No.1 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
(Long wall)
Room No.1 2 10’-0” - 12’-0” 120.00 sft 240.00 sft
(Short wall)
Room No.1 (Ceiling) 1 10’-0” - 12’-0” 120.00 sft 120.00 sft
Room No.2 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
(Long wall)
Room No.2 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
(Short wall)
Room No.2 (Ceiling) 1 12’-0” - 12’-0” 144.00 sft 144.00 sft
Verandah wall 1 23’-10 ½” - 10’-0” 238.75 sft 238.75 sft
Verandah Ceiling 1 22’-4 ½” - 7’ –3” 162.26 sft 162.26 sft
Columns 3 3’-0” - 8’-6” 25.50 sft 76.50 sft
Long beam (sides) 1 22’-4 ½” - 1’-6” 33.55 sft 33.55 sft
Long beam (soffit) 2 10’-9 ¾” - 0’-9” 8.10 sft 16.21 sft L= {(22’-4 ½”)-(0’-9”)}/2
= 10’-9¾”
Short beam (sides) 2 7’-3” - 1’-6” 10.87 sft 21.74 sft
Short beam (soffit) 2 7’-3” - 0’-9” 5.43 sft 10.87 sft
Door jambs 2 0’-9” - 7’-0” 5.25 sft 10.50 sft
2 0’-4½” - 7’-0” 2.63 sft 5.25 sft
1 0’-9” - 4’-0” 3.0 sft 1.50 sft
1 0’-4½” - 4’-0” 1.50 sft 3.00 sft
Window jambs 6 0’-9” - 4’-0” 3.00 sft 18.00 sft
6 0’-9” - 4’-0” 3.00 sft 18.00 sft
Ventilator jambs 8 0’-9” - 2’-6” 1.88 sft 15.00 sft
8 0’-9” - 1’-6” 1.19 sft 9.00 sft
Shelves 4 0’-6” - 5’-0” 2.5 sft 10.00 sft
4 0’-6” - 4’-0” 2.0 sft 10.00 sft
Total = 2017.16 sft
Deduction
Doors 4 4’-0’ - 7’-0” 28.00 sft 112.00 sft
Windows 4 4’-0’ - 4’-0” 16.00 sft 64.00 sft
Ventilators 6 2’-6” - 1’-6” 3.75 sft 22.50 sft
Total= 142.5 sft
Net 1874.66 sft
Total =
17 Three coats of
Weather shield
paint to walls.
(External side)
Rear wall 1 23’-10 ½” - 15’-4½” 367.07 sft 367.07 sft H = ={(15’-10 ½”)-
(0’-6”) = 15’-4 1/2”
Left & Right side wall 2 13’-6” - 15’-4½” 207.5 sft 415.13 sft
Front side (above 1 23’-10½” - 3’-0” 71.63 sft 71.63 sft
verandah roof)
Left & Right side wall 2 8’-0” - 2’-0” 16.00 sft 32.00 sft
of verandah
Parapet wall
Inner side of rooms 2 22’-4 ½” - 1’-0” 22.37 sft 44.70 sft
2 12’-0” - 1’-0” 12.00 sft 24.00 sft
Inner side of 1 22’-4 ½” - 1’-0” 22.37 sft 22.37 sft
Verandah
2 7’-3” - 1’-0” 7.25 sft 14.50 sft
Outer side of 1 23’-10½” - 2’-10½ ” 67.66 sft 67.66 sft
Verandah
2 8’-0” - 2’-10½ ” 22.67 sft 45.32 sft
Top of parapet wall 2 23’-10 ½” - 0’-9” 17.9 sft 35.80 sft
(Rooms)
2 12’-0” - 0’-9” 9.00 sft 18.00 sft
Top of parapet wall 1 23’-10 ½” - 0’-9” 17.90 sft 17.90 sft
(Rooms)
2 7’-3” - 0’-9” 5.43 sft 10.87 sft
Total= 1186.95 sft
Deduction

Windows 2 4’-0’ - 4’-0” 16.00 sft 32.00 sft


Ventilators 2 2’-6” - 1’-6” 3.75 sft 7.50 sft
Total= 39.50 sft
Net 1147.45 sft
Total=
ABSTRACT OF QUANTITIES
1- CALCULATIONS

1. Excavation in Medium soil

Quantity from BOQ item No. 1 = 1024.52 cft

Output of one labourer working 8 hrs = 75 cft

04 labourers are required for 3 ½ days to


excavate 1050 cft earth.
2. PCC (1:4:8)
Quantity of BOQ item No.3 (Foundations) = 146.27 cft
Quantity of BOQ item No.11 (Floors) = 142.07 cft
Total = 288.34 cft
Dry material for 100 cft of cement concrete = 154 cft

Note:
Materials
(i) Cement=154x1x288.34/(100x13) = 34.15cft
(ii) Sand=154x4x288.34/(100x13) = 136.62 cft
(iii) Coarse aggregate
=154x8x288.34/(100x13) = 273.25 cft
3. Ist Class Burnt brick work in foundation
in cement sand mortar (1:6)
Quantity of BOQ item No.4 = 484.21 cft

Note: Bricks for 100 cft of brick work = 1350 Nos.


Dry mortar for 100 cft of brik work = 30 cft

Material
(i) Bricks=1350x484.21/100 = 6537 Nos.
(ii) Cement=30x1x484.21/(7x100) = 20.75 cft
(iii) Sand=30x6x484.21/(7x100) = 124.51cft
4. 1 ½” thick PCC (1:2:4) in DPC including
two coats of hot bitumen & 2 sheets of
Polythene.
Quantity of BOQ item No.5=55.50x0.125 = 6.93 cft

Note: (i) Dry material for 100 cft of cement concrete = 154 cft
(ii) Bitumen for 100 sft of DPC (first coat) = 15 Kg
(iii) Bitumen for 100 sft of DPC (second coat) = 10 Kg

Material
(i) Cement=154x1x6.93/(100x7) = 1.52 cft
(ii) Sand=154x2x6.93/(100x7) = 3.04 cft
(iii) Coarse aggregate=154x4x6.93/(100x7) = 6.09 cft
(iv) Bitumen =25x55.50/100 = 13.87 Kg
(v) Polythene Sheet (2 x 55.5) = 111.0 sft
5. Ist Class Burnt brick work in Super
structure in cement sand mortar (1:4)

Quantity of BOQ item No.6 = 743.17 cft

Note: (i) Bricks for 100 cft of brick work = 1350 Nos.

(ii) Dry mortar for 100 cft of brik work = 30 cft

Material

(i) Bricks=1350x743.17/100 = 10033 Nos.

(ii) Cement=30x1x743.17/(5x100) = 44.59 cft

(iii) Sand=30x4x747.13/(5x100) = 178.36 cft


6. Reinforced cement concrete (1:2:4)
Quantity of BOQ item No.7 = 226.39 cft

Note: Dry material for 100 cft of cement = 154 cft


concrete

Materials
(i) Cement=154x1x226.39/(100x7) = 49.80 cft
(ii) Sand=154x2x226.39/(100x7) = 99.61 cft
(iii) Coarse aggregate
=154x4x226.39/(100x7) = 199.22 cft
(iv) Mild steel round bars = 1529 lbs
= 693.55 Kg
(Note: 1 Kg = 0.454 lbs)
7. Roof insulation
Quantity of BOQ item No.9 = 430.72 sft

Note: (i) Brick tiles for 100 sft roof insulation = 360 Nos.
(ii) Dry mortar for 100 sft = 9.00 cft
(iii) Bitumen for 100 sft of DPC (first coat) = 15 Kg
(iv) Bitumen for 100 sft of DPC
(second coat) = 10 Kg
Material
(i) 1 ½” thick brick tiles = 1551 Nos.
(ii) Cement=9x1x430.72/(4x100) = 9.69 cft
(iii) Sand=9x4x430.72/(4x100) = 29.07 cft
(iv) Bitumen =430.72/100 = 107.68 Kg
(v) Mud /Earth filling=430.72x0.42 = 180.90 cft
(Vi) Polythene sheet (2 x 430.72) = 862 sft
8. Sand under floors
Quantity of BOQ item No.10 = 213.11 cft
Material
Sand = 213.11 cft
9. 1 ½” thick cement concrete (1:2:4) in
floors
Quantity of BOQ item No.12=457.80x0.125 = 57.23 cft

Note: (i) 1 ½” = 0.125 ft = 154 cft


(ii) Dry material for 100 cft of cement
concrete
Materials
(i) Cement=154x1x57.23/(100x7) = 12.59 cft
(ii) Sand=154x2x57.23/(100x7) = 25.18 cft
(iii) Coarse aggregate
=154x4x57.23/(100x7) = 50.36 cft
10. 1/2” thick cement plaster in cement sand
mortar (1:3)
Quantity of BOQ item No.13 = 3197.07 sft

Note: Dry mortar for 100 sft of ½” thick cement plaster = 6 cft

Material
(i) Cement=6x1x 3197.07/(4x100) = 47.96 cft
(ii) Sand=6x3x 3197.07/(4x100) = 143.87 cft

11. Wood work in door, windows ventilators


Quantity of BOQ item No.14 (i) Doors = 56.00 sft
Quantity of BOQ item No.14 (ii) Windows = 63.00 sft

Note: (i) Timber for 100 sft of Panelled Doors = 13 cft


(ii) Timber for 100 sft of Glazed windows and
Ventilators = 8 cft

Material
(i) Timber for doors =13x56/100 = 7.28 cft
(ii) Timber for windows and Ventilators = 5.04 cft
=8x63/100
Total = 13.32 cft
12. White wash / Distemper
Quantity of BOQ item No.16 = 1872.9 sft
Note: Lime for 100 sft of white wash (one coat) = 1.00 Kg

Material
Lime for three coats=1x3x1872.9/100 = 56.24 Kg

13. Weather Shield


Quantity of BOQ item No.17 = 1143.45 sft

14. Earth filling under floors


Quantity of BOQ item No.2 = 230.87 cft

Material
Earth for filling = 230.87 cft
2- SUMMARY
S.No. Description of material Quantity

1. Cement 220.68 cft or


(From 2,3,4,5,6,7,9,10) 177 Bags
2. Sand 740.26 cft
(From 2,3,4,5,6,7,9,10)
3. Coarse aggregate 528.92 cft
(From 2,4,6,9)
4. Mild steel round bars (item No: 6) 693.55 Kg
5 Burnt bricks 1st class 16570 Nos.
(From 3,5)
6 1/2” thick Brick tiles (item No: 7) 1551 Nos.
7 Bitumen 121.55 Kg
(From 4,7)
8 Polythene sheet 973 sft
(From 4,7)
9. Timber 13.32 cft
(item No: 11)
10. Lime 56.24 Kg
(item No: 12)

11. Mud/Earth filling 411.77 cft


(From 7,13)

You might also like