Estimation
Estimation
Estimation
b) Engineer's estimate
c) Progress estimate
I = Rough cost estimate
2- ENGINEER’S ESTIMATE
Foundation
Trench
CENTRE LINE METHOD
In this method, total length of centre lines of walls,
long and short, has to be found out.
Find the total length of centre lines of walls of same
type, having same type of foundations and footings and
then find the quantities by multiplying the total centre
length by the respective breadth and the height.
In this method, the length will remain the same for
excavation in foundations, for concrete in foundations,
for all footings, and for superstructure (with slight
difference when there are cross walls or number of
junctions).
This method is quicker but requires special attention
and considerations at the junctions, meeting points of
partition or cross walls.
CENTRE LINE METHOD
For rectangular, circular polygonal (hexagonal,
octagonal etc) buildings having no inter or cross
walls, this method is quite simple.
Find the total centre length of all walls of one type and
proceed in the same manner as described above. Similarly
find the total centre length of walls of second type and deal
this separately, and so on.
Then all A type walls shall be taken jointly first, and then all
B type walls shall be taken together separately.
The size of man hole may be 2.5ft X 2,5ft for low depths
and 3ft X 3ft, 4ft X 4ft or 5ft X 5ft for deep depths.
Drainage pipe lines outside the covered area but inside the
boundary wall are, usually, of R.C.C. with minimum
diameter 4 in, however, these are available in different
sizes.
3- BRICKWORK
(a) 100 cft Brick masonary Bricks ------------1350
Dry Mortar ------- 30 cft
Wet Mortar ------- 25 cft
5- EARTHWORK
Output of labor assuming one man working 8 hours per day with lift up to
5 ft or less
7- CEMENT
1 Bag ------------- 50 Kg (Weight), 1.25 cft (Volume)
8- SPECIFIC WEIGHTS
RCC --------------- 150 lbs / cft
1 Earthwork for
excavation
in
foundation
trenches
L1 3 25’-7 ½ //
2’-6” 3’-6” 224.22 cft 672.66 cft L = 23’-1 ½”+2’-6” = 25’-7 ½”
S1 2 10’-3” 2’-6” 3’-6” 89.69 cft 179 .38 cft L = 12’-9”-(2’-6)” = 10’-3”
3
P.C.C (1:4:8) in Length & Breadth
foundation using same as for
crushed or Foundation trenches
broken stones (Item No. 1)
1st step 3 24’-7 ½ ” 1’-6” 0’-6” 18.47 cft 55.40 cft L = 23’-1½”+(1’-6”) = 24’-7½”
2nd step 3 24’-3” 1’-1 ½ “ 0’-6” 13.64 cft 40.92 cft L = 23’-1½”+(1’-1½”) = 24’-3”
3rd step up to plinth 3 23’-10 ½” 0’-9” 3’-4 ½” 60.43 cft 181.30 L = 23’-1½”+(0’-9”) =
level cft 23’-10½”
D = 2’-0” +(1’-6”) –(0’-1 ½”)
= 3’-4 ½”
Total= 277.62
cft
(b) S1
1st step 2 11’-3” 1’-6” 0’-6” 8.44 cft 16.88 cft L = 12’-9”-(1’-6”) = 11’-3”
2nd step 2 11’-7 ½ ” 1’-1 ½ ” 0’-6” 6.54 cft 13.08 cft L = 12’-9”-( 1’-1½”) = 11’-7½”
3rd step up to plinth 2 12’-0” 0’-9” 3’-4 ½ ” 30.37 cft 60.75 cft L = 12’-9”-( 0’-9”) = 12’-0”
level
1st step 1 11’-3” 1’-1 ½ ” 0’-6” 6.33 cft 6.33 cft L = 12’-9”-(1’-6 ”) = 11’-3”
2nd step 1 11’-7 ½ ” 0’-9 ” 0’-6” 4.36 cft 4.36 cft L = 12’-9”-( 1’-1½”)= 11’-7½”
3rd step up to plinth 1 12’-0” 0’-4 ½ ” 3’-4 ½ ” 15.19 cft 15.19 cft L = 12’-9”-( 0’-9”) = 12’-0”
level
Total= 25.88 cft
(d)S3
1st step 2 6’-6” 1’-6” 0’-6” 4.87 cft 9.75 cft L = 8’-0”-(1’6”) = 6’-6’
2nd step 2 6’-10 ½ ” 1’-1 ½” 0’-6” 3.86 cft 7.73 cft L = 8’-0”-(1’-1½”) = 6’-10½”
3rd step up to plinth 2 7’-3” 0’-9” 3’-4 ½ ” 18.35 cft 36.70 cft L = 8’-0”-(0’-9”) = 7’-3”
level
Total= 54.18 cft
1st step 1 23’-10 ½” 2’-0” 0’-6” 23.88 cft 23.88 cft L = 23’-1½”+(0’-4½”) +
(0’-4½”) =23’-10½”
Verandah columns 3 0’-9” 0’-9” 8’-6” 4.78 cft 14.34 cft H=10’-0”- (1’-6”)=8’-6”
(i) L1 1 23’-10 ½” 0’-9” 1’-6 ½” 27.60 cft 27.60 cft H = 0’-4” (Earth filling) + 0’-
1” (Mud plaster) +
0’-1½” (Tiles) + 1’-0” (P.
walls) = 1’-6½”
Roof slab of 1 23’-1 ½” 12’-9” 0’-4” 98.28 cft 98.28 cft L = 10”-0” + 12’-0” +
rooms 0’-4½” + 0’-9” (2
bearings) = 23’-1½”
B = 12’-0” + 0-
4½”(bearing) + 0’-
4½”(bearing) = 12’-9”
Roof slab of 1 23’-10 ½ ” 8’-4 ½ ” 0’-4” 66.65 cft 66.65 cft B = 8’-0” + 0’-4½”
Verandah (bearing) = 8’-4½”
Verandah
beam
Long beam 1 23’-1 0½” 0’-9” 1’-6” 26.86 cft 26.86 cft
Short beam 2 7’-7 ½ ” 0’-9” 1’-6” 8.59 cft 17.18 cft L=8’-0”-(0’-9”) + (0’-
4½”) = 7’-7½”
Lintels
Doors 1 5’-0” 0’-9” 0’-6’ 1.87 cft 1.87 cft
1 5’-0” 0’-4½ ” 0’-6’ 0.93 cft 0.93 cft
Windows 3 5’-0” 0’-9” 0’-6’ 1.87 cft 5.62 cft
Ventilators 4 3’-6” 0’-9” 0’-6’ 1.31 cft 5.25 cft
Shelves 2 5’-0” 0’-9” 0’-6’ 1.87 cft 3.75 cft
Shades 2 5’-0” 1’-6” 0’-3” 1.87 cft 3.75 cft
Total= 226.39 cft
8 Mild steel round 6.75 lbs/cft
bars as steel of
reinforcement 226.39 cft
including cutting, concrete
bending, binding
and placing =1528.13
reinforcement in lbs
position
Room No.1 (Long wall) 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
Room No.1(Short wall) 2 10’-0” - 12’-0” 120.00 sft 240.00 sft
Room No.1 (Ceiling) 1 10’-0” - 12’-0” 120.00 sft 120.00 sft
Room No.2 (Long wall) 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
Room No.2(Short wall) 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
Room No.2 (Ceiling) 1 12’-0” - 12’-0” 144.00 sft 144.00 sft
Verandah wall 1 23’-10 ½” - 10’-0” 238.75 sft 238.75 sft L = (10’-0”) + (12’-0”) +
(0’-4½ “) +(0’-9”)+ (0’-9”)
= 23’-10 ½ “
Verandah ceiling 1 22’-4 ½” - 7’ –3” 162.26 sft 162.26 sft L = (10’-0”)+(12’-0”)
+(0’-4 ½ “) = 22’-½“
Columns 3 3’-0” - 8’-6” 25.50 sft 76.5 sft L = (0’-9”) + (0’-9”) +
(0’-9”) + (0’-9”) = 3’-0 ”
Long beam (internal 1 22’-4 ½” - 1’-6” 33.55 sft 33.55 sft
side)
Long beam (soffit) 2 10’-9 ¾” - 0’-9” 8.10 sft 16.21 sft L={(22’-4 ½”)-(0’-9”)}/2
=10’-9¾”
Short beam (internal 2 7’-3” - 1’-6” 10.87 sft 21.74 sft L={(8’-0”)-(0’-9”)}
sides) = 7’-3”
Outer side
Rear wall 1 23’-10 ½” - 15’- 379.00 379.00 sft H = (0’-6”) + (1’-6”) +
10½” sft (12’-0”) + (0’-4”) + (0’-
(From 6” below 4’’) + (0’-1”) + (0’-1½”)
G.L. to Parapet + (1’-0”)
walls) = 15’-10½”
Left & Right side 2 13’-6” - 15’- 214.32 428.64 sft L= (12’-0”) + (0’-9”) +
wall 10½” sft (0’-9”)
= 13’-6”
Front side (above 1 23’-10 ½” - 3’-0” 71.63 sft 71.63 sft H = (12’-0”) + 0’-10½”)
verandah roof) + (1’-0”) - (10’-10 ½” )
= 3’-0”
Left & Right side 2 8’-0” - 2’-0” 16.00 sft 32.00 sft H = (1’ – 6’’) + (0’ – 6’’)
plinth of verandah = 2’ – 0’’
Parapet wall
Inner side of rooms 2 22’-4 ½” - 1’-0” 22.37 sft 44.70 sft L = (10’-0”)+(12’-0”)
+(0’-4 ½ “)
= 22’-4 ½ “
2 12’-0” - 1’-0” 12.00 sft 24.00 sft
Inner side of 1 22’-4 ½” - 1’-0” 22.37 sft 22.37 sft
Verandah
2 7’-3 “ - 1’-0” 7.25 sft 14.50 sft
Outer side of 1 23’-10 ½” - 3’- 67.66sft 67.66 sft H = (1’-6”)+(0’-4”)
Verandah 4 ½” +(0’-6 ½”) + (1’-0 “)
= 3’-4 1/2//
Note:
Materials
(i) Cement=154x1x288.34/(100x13) = 34.15cft
(ii) Sand=154x4x288.34/(100x13) = 136.62 cft
(iii) Coarse aggregate
=154x8x288.34/(100x13) = 273.25 cft
3. Ist Class Burnt brick work in foundation
in cement sand mortar (1:6)
Quantity of BOQ item No.4 = 484.21 cft
Material
(i) Bricks=1350x484.21/100 = 6537 Nos.
(ii) Cement=30x1x484.21/(7x100) = 20.75 cft
(iii) Sand=30x6x484.21/(7x100) = 124.51cft
4. 1 ½” thick PCC (1:2:4) in DPC including
two coats of hot bitumen & 2 sheets of
Polythene.
Quantity of BOQ item No.5=55.50x0.125 = 6.93 cft
Note: (i) Dry material for 100 cft of cement concrete = 154 cft
(ii) Bitumen for 100 sft of DPC (first coat) = 15 Kg
(iii) Bitumen for 100 sft of DPC (second coat) = 10 Kg
Material
(i) Cement=154x1x6.93/(100x7) = 1.52 cft
(ii) Sand=154x2x6.93/(100x7) = 3.04 cft
(iii) Coarse aggregate=154x4x6.93/(100x7) = 6.09 cft
(iv) Bitumen =25x55.50/100 = 13.87 Kg
(v) Polythene Sheet (2 x 55.5) = 111.0 sft
5. Ist Class Burnt brick work in Super
structure in cement sand mortar (1:4)
Note: (i) Bricks for 100 cft of brick work = 1350 Nos.
Material
Materials
(i) Cement=154x1x226.39/(100x7) = 49.80 cft
(ii) Sand=154x2x226.39/(100x7) = 99.61 cft
(iii) Coarse aggregate
=154x4x226.39/(100x7) = 199.22 cft
(iv) Mild steel round bars = 1529 lbs
= 693.55 Kg
(Note: 1 Kg = 0.454 lbs)
7. Roof insulation
Quantity of BOQ item No.9 = 430.72 sft
Note: (i) Brick tiles for 100 sft roof insulation = 360 Nos.
(ii) Dry mortar for 100 sft = 9.00 cft
(iii) Bitumen for 100 sft of DPC (first coat) = 15 Kg
(iv) Bitumen for 100 sft of DPC
(second coat) = 10 Kg
Material
(i) 1 ½” thick brick tiles = 1551 Nos.
(ii) Cement=9x1x430.72/(4x100) = 9.69 cft
(iii) Sand=9x4x430.72/(4x100) = 29.07 cft
(iv) Bitumen =430.72/100 = 107.68 Kg
(v) Mud /Earth filling=430.72x0.42 = 180.90 cft
(Vi) Polythene sheet (2 x 430.72) = 862 sft
8. Sand under floors
Quantity of BOQ item No.10 = 213.11 cft
Material
Sand = 213.11 cft
9. 1 ½” thick cement concrete (1:2:4) in
floors
Quantity of BOQ item No.12=457.80x0.125 = 57.23 cft
Note: Dry mortar for 100 sft of ½” thick cement plaster = 6 cft
Material
(i) Cement=6x1x 3197.07/(4x100) = 47.96 cft
(ii) Sand=6x3x 3197.07/(4x100) = 143.87 cft
Material
(i) Timber for doors =13x56/100 = 7.28 cft
(ii) Timber for windows and Ventilators = 5.04 cft
=8x63/100
Total = 13.32 cft
12. White wash / Distemper
Quantity of BOQ item No.16 = 1872.9 sft
Note: Lime for 100 sft of white wash (one coat) = 1.00 Kg
Material
Lime for three coats=1x3x1872.9/100 = 56.24 Kg
Material
Earth for filling = 230.87 cft
2- SUMMARY
S.No. Description of material Quantity