Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

SPM Unit-1 Material

Download as pdf or txt
Download as pdf or txt
You are on page 1of 17

software project management

UNIT - I
Conventional Software Management: The waterfall model, conventional software Management performance.

Evolution of Software Economics: Software Economics, pragmatic software cost estimation


Improving Software Economics: Reducing Software product size, improving software processes,
improvingteam effectiveness, improving automation, Achieving required quality, peer inspections.

1. Conventional software management


Conventional software management practices are sound in theory, but practice is still tied to archaic
(outdated)technology and techniques.
Conventional software economics provides a benchmark of performance for conventional software
management principles.
The best thing about software is its flexibility: It can be programmed to do almost anything.
The worst thing about software is also its flexibility: The "almost anything" characteristic has made it
difficultto plan, monitors, and control software development.
Three important analyses of the state of the software engineering industry are
1. Software development is still highly unpredictable. Only about 10% of software projects are
delivered successfully within initial budget and schedule estimates.
2. Management discipline is more of a discriminator in success or failure than are technology advances.
3. The level of software scrap and rework is indicative of an immature process.
All three analyses reached the same general conclusion: The success rate for software projects is very
low.The three analyses provide a good introduction to the magnitude of the software problem and the
current norms for conventional software management performance.

1.1.THE WATERFALL MODEL


Most software engineering texts present the waterfall model as the source of the "conventional" software
process.
1. IN THEORY
2. IN PRACTICE

1.IN THEORY
It provides an insightful and concise summary of conventional software managementThree main primary points
are

1. There are two essential steps common to the development of computer programs: analysis and
coding.
Waterfall Model part 1: The two basic steps common to the development of computer programs.
i.e, Analysis and coding

Analysis Analysis and coding both involve creative work that


directly contributes to the usefulness of the end product.
Coding
2. In order to manage and control all of the intellectual freedom associated with software
development, one must introduce several other "overhead" steps, including system requirements
definition, software requirements definition, program design, and testing.
These steps supplement the analysis and coding steps. Below Figure illustrates the resulting
project profile and the basic steps in developing a large-scale program.

1
Fig: Large scale system approach

3.The basic framework described in the waterfall model is risky and invites failure. The testing phase that
occurs at the end of the development cycle is the first event for which timing, storage, input/output transfers,
etc., are experienced as distinguished from analyzed. The resulting design changes are likely to be so disruptive
that the software requirements upon which the design is based are likely violated. Either the requirements must
be modified or a substantial design change is warranted.
Five necessary improvements for waterfall model are:-
1. Program design comes first
2. Document the design
3. Do it twice
4. Plan, control, and monitor testing
5. Involve the customer

1. Program design comes first. Insert a preliminary program design phase between the software
requirements generation phase and the analysis phase. By this technique, the program designer
assures that the software will not fail because of storage, timing, and data flux (continuous
change). As analysis proceeds in the succeeding phase, the program designer must impose on the
analyst the storage, timing, and operational constraints in such a way that he senses the
consequences.If the total resources to be applied are insufficient or if the embryonic(in an early
stage of development) operational design is wrong, it will be recognized at this early stage and
the iteration with requirements and preliminary design can be redone before final design, coding,
and test commences. How is this program design procedure implemented?

The following steps are required:


a. Begin the design process with program designers, not analysts or programmers.
b. Design, define, and allocate the data processing modes even at the risk of being wrong.
c. Allocate processing functions, design the database, allocate execution time, define
interfaces and processing modes with the operating system, describe input and output
processing, and define preliminary operating procedures.
d. Write an overview document that is understandable, informative, and current so that
every worker on the project can gain an elemental understanding of the system.

2. Document the design. The amount of documentation required on most software programs is quite a lot,
certainly much more than most programmers, analysts, or program designers are willing to do if left to their
own devices. Why do we need so much documentation?
(1) Each designer must communicate with interfacing designers, managers, and possibly customers.

(2) During early phases, the documentation is the design.

2
(3) The real monetary value of documentation is to support later modifications by a separate test team, a separate
maintenance team, and operations personnel who are not software literate.

3. Do it twice.
 If a computer program is being developed for the first time, arrange matters so that the version finally
delivered to the customer for operational deployment is actually the second version insofar as critical
design/operations are concerned.
 Note that this is simply the entire process done in miniature, to a time scale that is relatively small with
respect to the overall effort.
 In the first version, the team must have a special broad competence where they can quickly sense trouble
spots in the design, model them, model alternatives, forget the straightforward aspects of the design that
aren't worth studying at this early point, and, finally, arrive at an error-free program.

4. Plan, control, and monitor testing.

 Without question, the biggest user of project resources-manpower, computer time, and/or management
judgment-is the test phase.
 This is the phase of greatest risk in terms of cost and schedule. It occurs at the latest point in the schedule,
when backup alternatives are least available, if at all.
 The previous three recommendations were all aimed at uncovering and solving problems before entering
the test phase.
 However, even after doing these things, there is still a test phase and there are still important things to be
done, including: (1) employ a team of test specialists who were not responsible for the
 original design; (2) employ visual inspections to spot the obvious errors like dropped minus signs, missing
factors of two, jumps to wrong addresses (do not use the computer to detect this kind of thing, it is too
expensive); (3) test every logic path; (4) employ the final checkout on the target computer.

5. Involve the customer.


 It is important to involve the customer in a formal way so that he has committed himself at earlier points
before final delivery.
 There are three points following requirements definition where the insight, judgment, and commitment of
the customer can bolster the development effort.
 These include a "preliminary software review" following the preliminary program design step, a sequence of
"critical software design reviews" during program design, and a "final software acceptance review".
2. IN PRACTICE
Some software projects still practice the conventional software management approach.
It is useful to summarize the characteristics of the conventional process as it has typically been applied,
which is not necessarily as it was intended. Projects destined for trouble frequently exhibit the following
symptoms:

1.Protracted integration and late design breakage.


2. Late risk resolution.
3. Requirements-driven functional decomposition.
4. Adversarial (conflict or opposition) stakeholder relationships.
5. Focus on documents and review meetings.
1.Protracted Integration and Late Design Breakage
For a typical development project that used a waterfall model management process, Figure 1-2 illustrates
development progress versus time. Progress is defined as percent coded, that is, demonstrable in its target
form.

The following sequence was common:

 Early success via paper designs and thorough (often too thorough) briefings.
 Commitment to code late in the life cycle.
 Integration nightmares (unpleasant experience) due to unforeseen implementation issues and
interfaceambiguities.
 Heavy budget and schedule pressure to get the system working.

3
 Late shoe-homing of no optimal fixes, with no time for redesign.
 A very fragile, unmentionable product delivered late.

In the conventional model, the entire system was designed on paper, then implemented all at once, then
integrated. Table 1-1 provides a typical profile of cost expenditures across the spectrum of software activities.

2.Late risk resolution

A serious issue associated with the waterfall lifecycle was the lack of early risk resolution. Figure 1.3
illustrates a typical risk profile for conventional waterfall model projects.

 It includes four distinct periods of risk exposure, where risk is defined as the probability of missing a cost,
schedule, feature, or quality goal.
 Early in the life cycle, as the requirements were being specified, the actual risk exposure was highly
unpredictable.

4
Fig: Risk profile of a conventional software project across its life cycle
3.Requirements-Driven Functional Decomposition:
 This approach depends on specifying requirements completely and unambiguously before other
development activities begin.
 It naively treats all requirements as equally important, and depends on those requirements remaining
constant over the software development life cycle.
 These conditions rarely occur in the real world. Specification of requirements is a difficult and
important part of the software development process.
Another property of the conventional approach is that the requirements were typically specified in a
functional manner.
 Built into the classic waterfall process was the fundamental assumption that the software itself was
decomposed into functions; requirements were then allocated to the resulting components.
 This decomposition was often very different from a decomposition based on object-oriented design and
the use of existing components.
 Figure 1-4 illustrates the result of requirements-driven approaches: a software structure that is
organized around the requirements specification structure.

4.Adversarial Stakeholder Relationships:


The conventional process tended to result in adversarial stakeholder relationships, in large part because of the

5
difficulties of requirements specification and the exchange of information solely through paper documents
that captured engineering information in ad hoc formats.

The following sequence of events was typical for most contractual software efforts:
1. The contractor prepared a draft contract-deliverable document that captured an intermediate
artifactand delivered it to the customer for approval.
2. The customer was expected to provide comments (typically within 15 to 30 days).
3. The contractor incorporated these comments and submitted (typically within 15 to 30 days) a
finalversion for approval.
This one-shot review process encouraged high levels of sensitivity on the part of customers and contractors.

5.Focus on Documents and Review Meetings:


 The conventional process focused on producing various documents that attempted to describe the
software product, with insufficient focus on producing tangible increments of the products
themselves.
 Contractors were driven to produce literally tons of paper to meet milestones and demonstrate
progress to stakeholders, rather than spend their energy on tasks that would reduce risk and produce
quality software.
 Typically, presenters and the audience reviewed the simple things that they understood rather than
the complex and important issues.
 Most design reviews therefore resulted in low engineering value and high cost in terms of the effort
and schedule involved in their preparation and conduct. They presented merely a facade of progress.
 Table 1-2 summarizes the results of a typical design review.

1.2.CONVENTIONAL SOFTWARE MANAGEMENT PERFORMANCE


Barry Boehm's "Industrial Software Metrics Top 10 List” is a good, objective characterization of the
state ofsoftware development.
1. Finding and fixing a software problem after delivery costs 100 times more than finding and
fixing theproblem in early design phases.
2. You can compress software development schedules 25% of nominal, but no more.
3. For every $1 you spend on development, you will spend $2 on maintenance.
4. Software development and maintenance costs are primarily a function of the number of source
linesof code.
5. Variations among people account for the biggest differences in software productivity.
6. The overall ratio of software to hardware costs is still growing. In 1955 it was 15:85; in 1985, 85:15.
7. Only about 15% of software development effort is devoted to programming.

6
8. Software systems and products typically cost 3 times as much per SLOC as individual
softwareprograms. Software-system products (i.e., system of systems) cost 9 times as much.
9. Walkthroughs catch 60% of the errors
10. 80% of the contribution comes from 20% of the contributors.

2. Evolution of Software Economics


2.1.SOFTWARE ECONOMICS
Most software cost models can be abstracted into a function of five basic parameters: size, process,
personnel, environment, and required quality.
1. The size of the end product (in human-generated components), which is typically quantified in
terms of the number of source instructions or the number of function points required to develop
the required functionality
2. The process used to produce the end product, in particular the ability of the process to avoid non-
value-adding activities (rework, bureaucratic delays, communications overhead)
3. The capabilities of software engineering personnel, and particularly their experience with the
computer science issues and the applications domain issues of the project
4. The environment, which is made up of the tools and techniques available to support efficient
software development and to automate the process
5. The required quality of the product, including its features, performance, reliability, and

adaptability The relationships among these parameters and the estimated cost can be written as

follows:

Effort = (Personnel) (Environment) (Quality) ( Sizeprocess)

One important aspect of software economics (as represented within today's software cost models) is
that the relationship between effort and size exhibits a diseconomy of scale. The diseconomy of scale of
software development is a result of the process exponent being greater than 1.0. Contrary to most
manufacturing processes, the more software you build, the more expensive it is per unit item.
Figure 2-1 shows three generations of basic technology advancement in tools, components, and
processes. The required levels of quality and personnel are assumed to be constant. The ordinate of the graph
refers to software unit costs (pick your favorite: per SLOC, per function point, per component) realized by
an organization.
The three generations of software development are defined as follows:

1) Conventional: 1960s and 1970s, craftsmanship. Organizations used custom tools, custom
processes, and virtually all custom components built in primitive languages. Project performance
was highly predictable in that cost, schedule, and quality objectives were almost always
underachieved.
2) Transition: 1980s and 1990s, software engineering. Organiz:1tions used more-repeatable processes and
off- the-shelf tools, and mostly (>70%) custom components built in higher level languages. Some of the
components (<30%) were available as commercial products, including the operating system, database
management system, networking, and graphical user interface.
3) Modern practices: 2000 and later, software production. This book's philosophy is rooted
in theuse of managed and measured processes, integrated automation environments, and
mostly (70%) off-the-shelf components. Perhaps as few as 30% of the components need to
be custom built
Technologies for environment automation, size reduction, and process improvement are not independent
of one another. In each new era, the key is complementary growth in all technologies. For example, the
process advances could not be used successfully without new component technologies and increased tool
automation.

7
Organizations are achieving better economies of scale in successive technology eras-with very large projects
(systems of systems), long-lived products, and lines of business comprising multiple similar projects. Figure
2-2 provides an overview of how a return on investment (ROI) profile can be achieved in subsequent efforts
across life cycles of various domains.

8
2.2.PRAGMATIC SOFTWARE COST ESTIMATION
 One critical problem in software cost estimation is a lack of well-documented case studies of projects
that usedan iterative development approach.
 Software industry has inconsistently defined metrics or atomic units of measure, the data from actual
projects are highly suspect in terms of consistency and comparability.
 It is hard enough to collect a homogeneous set of project data within one organization; it is extremely
difficult to homogenize data across different organizations with different processes, languages,
domains, and so on.
 There have been many debates among developers and vendors of software cost estimation models and
tools. Three topics of these debates are of particular interest here:

1. Which cost estimation model to use?


2. Whether to measure software size in source lines of code or function points.
3. What constitutes a good estimate?

There are several popular cost estimation models (such as COCOMO, CHECKPOINT, ESTIMACS,
Knowledge Plan, Price-S, ProQMS, SEER, SLIM, SOFTCOST, and SPQR/20), CO COMO is also one of
the most open and well-documented cost estimation models. The general accuracy of conventional cost
models (such as COCOMO) has been described as "within 20% of actuals, 70% of the time."
1. Most real-world use of cost models is bottom-up (substantiating a target cost) rather than top-down
(estimating the "should" cost).
2. Figure 2-3 illustrates the predominant practice: The software project manager defines the target cost of
the software, and then manipulates the parameters and sizing until the target cost can be justified.
3. The rationale for the target cost maybe to win a proposal, to solicit customer funding, to attain internal
corporate funding, or to achieve some other goal.
4. The process described in Figure 2-3 is not all bad. In fact, it is absolutely necessary to analyze the cost
risks and understand the sensitivities and trade-offs objectively.
5. It forces the software project manager to examine therisks associated with achieving the target costs
and to discuss this information with other stakeholders.
A good software cost estimate has the following attributes:
1. It is conceived and supported by the project manager, architecture team, development team,
and testteam accountable for performing the work.
2. It is accepted by all stakeholders as ambitious but realizable.
3. It is based on a well-defined software cost model with a credible basis.
4. It is based on a database of relevant project experience that includes similar processes, similar
technologies, similar environments, similar quality requirements, and similar people.

9
5. It is defined in enough detail so that its key risk areas are understood and the probability of
success isobjectively assessed.
Extrapolating from a good estimate, an ideal estimate would be derived from a mature cost model with an
experience base that reflects multiple similar projects done by the same team with the same mature processes
and tools.

3.Improving Software Economics: Reducing Software product size, improving software processes,
improvingteam effectiveness, improving automation, Achieving required quality, peer inspections.
Five basic parameters of the software cost model are
1. Reducing the size or complexity of what needs to be developed.
2. Improving the development process.
3. Using more-skilled personnel and better teams (not necessarily the same thing).
4. Using better environments (tools to automate the process).
5. Trading off or backing off on quality thresholds.
These parameters are given in priority order for most software domains.
Table 3-1 lists some of the technology developments, process improvement efforts, and management
approaches targeted at improving the economics of software development and integration.

10
3.1.REDUCING SOFTWARE PRODUCT SIZE
The most significant way to improve affordability and return on investment (ROI) is usually to produce a
product that achieves the design goals with the minimum amount of human-generated source material.
Component-based development is introduced as the general term for reducing the "source" language size to
achieve a software solution.
Reuse, object-oriented technology, automatic code production, and higher order programming languages are
all focused on achieving a given system with fewer lines of human-specified source directives (statements).
size reduction is the primary motivation behind improvements in higher order languages (such as C++, Ada
95, Java, Visual Basic), automatic code generators (CASE tools, visual modeling tools, GUI builders), reuse
of commercial components (operating systems, windowing environments, database management systems,
middleware, networks), and object-oriented technologies (Unified Modeling Language, visual modeling
tools, architecture frameworks).
The reduction is defined in terms of human-generated source material. In general, when size-reducing
technologies are used, they reduce the number of human-generated source lines.
1. LANGUAGES
2.OBJECT-ORIENTED METHODS AND VISUAL MODELING
3.REUSE
4.COMMERCIAL COMPONENTS
1.LANGUAGES
Universal function points (UFPs1) are useful estimators for language-independent, early life-cycle
estimates. The basic units of function points are external user inputs, external outputs, internal logical data
groups, external data interfaces, and external inquiries. SLOC metrics are useful estimators for software
after a candidate solution is formulated and an implementation language is known. Substantial data have
been documented relating SLOC to function points. Some of these results are shown in Table 3-2.
Languages expressiveness of some of today’s popular languages

Table 3-2
2.OBJECT-ORIENTED METHODS AND VISUAL MODELING
 Object-oriented technology is not germane to most of the software management topics discussed
here, and books on object-oriented technology abound.
 Object-oriented programming languages appear to benefit both software productivity and software
quality.
 The fundamental impact of object-oriented technology is in reducing the overall size of what needs
to be developed.
 People like drawing pictures to explain something to others or to themselves. When they do it for
software system design, they call these pictures diagrams or diagrammatic models and the very
notation for them a modeling language.
These are interesting examples of the interrelationships among the dimensions of improving software eco-
nomics.

11
1. An object-oriented model of the problem and its solution encourages a common vocabulary
between the end users of a system and its developers, thus creating a shared understanding of the
problem being solved.
2. The use of continuous integration creates opportunities to recognize risk early and make incremental
corrections without destabilizing the entire development effort.
3. An object-oriented architecture provides a clear separation of concerns among disparate elements
of a system, creating firewalls that prevent a change in one part of the system from rending the
fabric of the entire architecture.

Booch also summarized five characteristics of a successful object-oriented project.

1. A ruthless focus on the development of a system that provides a well understood collection of
essentialminimal characteristics.
2. The existence of a culture that is centered on results, encourages communication, and yet is not
afraidto fail.
3. The effective use of object-oriented modeling.
4. The existence of a strong architectural vision.
5. The application of a well-managed iterative and incremental development life cycle.

3.REUSE
Reusing existing components and building reusable components have been natural software engineering
activities since the earliest improvements in programming languages. With reuse in order to minimize
development costs while achieving all the other required attributes of performance, feature set, and quality.
Try to treat reuse as a mundane part of achieving a return on investment.
Most truly reusable components of value are transitioned to commercial products supported
by organizations with the following characteristics:

 They have an economic motivation for continued support.


 They take ownership of improving product quality, adding new features, and transitioning
to newtechnologies.
 They have a sufficiently broad customer base to be profitable.
The cost of developing a reusable component is not trivial. Figure 3-1 examines the economic trade-offs.
Thesteep initial curve illustrates the economic obstacle to developing reusable components.
Reuse is an important discipline that has an impact on the efficiency of all workflows and the quality of
mostartifacts.

4.COMMERCIAL COMPONENTS
 A common approach being pursued today in many domains is to maximize integration of commercial

12
components and off-the-shelf products.
 While the use of commercial components is certainly desirable as a means of reducing custom
development, it has not proven to be straightforward in practice.
 Table 3-3 identifies some of the advantages and disadvantages of using commercial components.

3.2.IMPROVING SOFTWARE PROCESSES


Process is an overloaded term. Three distinct process perspectives are.

 Metaprocess: an organization's policies, procedures, and practices for pursuing a software-


intensive line of business. The focus of this process is on organizational economics, long-term
strategies, and software ROI.
 Macroprocess: a project's policies, procedures, and practices for producing a complete software
product within certain cost, schedule, and quality constraints. The focus of the macro process is on
creating an adequate instance of the Meta process for a specific set of constraints.
 Microprocess: a project team's policies, procedures, and practices for achieving an artifact of the
software process. The focus of the micro process is on achieving an intermediate product baseline
with adequate quality and adequate functionality as economically and rapidly as practical.
Although these three levels of process overlap somewhat, they have different objectives, audiences,
metrics, concerns, and time scales as shown in Table 3-4

13
In a perfect software engineering world with an immaculate problem description, an obvious solution space,
a development team of experienced geniuses, adequate resources, and stakeholders with common goals,
we could execute a software development process in one iteration with almost no scrap and rework. Because
we work in an imperfect world, however, we need to manage engineering activities so that scrap and rework
profiles do not have an impact on the win conditions of any stakeholder. This should be the underlying
premise for most process improvements.

3.3.IMPROVING TEAM EFFECTIVENESS


Teamwork is much more important than the sum of the individuals. With software teams, a project manager
needs to configure a balance of solid talent with highly skilled people in the leverage positions. Some
maximsof team management include the following:
 A well-managed project can succeed with a nominal engineering team.
 A mismanaged project will almost never succeed, even with an expert team of engineers.
 A well-architected system can be built by a nominal team of software builders.
 A poorly architected system will flounder even with an expert team of builders.

Boehm five staffing principles are


1. The principle of top talent: Use better and fewer people
2. The principle of job matching: Fit the tasks to the skills and motivation of the people available.
3. The principle of career progression: An organization does best in the long run by helping its
peopleto self-actualize.
4. The principle of team balance: Select people who will complement and harmonize with one another
5. The principle of phase-out: Keeping a misfit on the team doesn't benefit anyone

Software project managers need many leadership qualities in order to enhance team effectiveness.
The following are some crucial attributes of successful software project managers that deserve much more
attention:

14
1. Hiring skills. Few decisions are as important as hiring decisions. Placing the right person in the
right job seems obvious but is surprisingly hard to achieve.
2. Customer-interface skill. Avoiding adversarial relationships among stakeholders is a prerequisite
for success.
Decision-making skill. The jillion books written about management have failed to provide a clear
definition of this attribute. We all know a good leader when we run into one, and decision-making
skill seems obvious despite its intangible definition.
Team-building skill. Teamwork requires that a manager establish trust, motivate progress, exploit
eccentric prima donnas, transition average people into top performers, eliminate misfits, and
consolidate diverse opinions into a team direction.
Selling skill. Successful project managers must sell all stakeholders (including themselves) on
decisions and priorities, sell candidates on job positions, sell changes to the status quo in the face of
resistance, and sell achievements against objectives. In practice, selling requires continuous
negotiation, compromise, and empathy

3.4.IMPROVING AUTOMATION THROUGH SOFTWARE ENVIRONMENTS


 The tools and environment used in the software process generally have a linear effect on the
productivityof the process.
 Planning tools, requirements management tools, visual modeling tools, compilers, editors, debuggers,
quality assurance analysis tools, test tools, and user interfaces provide crucial automation support
for evolving the software engineering artifacts.
 Above all, configuration management environments provide the foundation for executing and
instrument the process. At first order, the isolated impact of tools and automation generally allows
improvements of 20% to 40% in effort.
 However, tools and environments must be viewed as the primary delivery vehicle for process
automation and improvement, so their impact can be much higher.
o Automation of the design process provides payback in quality, the ability to estimate costs
and schedules, and overall productivity using a smaller team.
Round-trip engineering describe the key capability of environments that support iterative development. As
we have moved into maintaining different information repositories for the engineering artifacts, we need
automation support to ensure efficient and error-free transition of data from one artifact to another. Forward
engineering is the automation of one engineering artifact from another, more abstract representation. For
example, compilers and linkers have provided automated transition of source code into executable code.
Reverse engineering is the generation or modification of a more abstract representation from an existing
artifact (for example, creating a .visual design model from a source code representation).
Economic improvements associated with tools and environments. It is common for tool vendors to make
relatively accurate individual assessments of life-cycle activities to support claims about the potential
economic impact of their tools. For example, it is easy to find statements such as the following from
companies in a particular tool.

 Requirements analysis and evolution activities consume 40% of life-cycle costs.


 Software design activities have an impact on more than 50% of the resources.
 Coding and unit testing activities consume about 50% of software development effort and schedule.
 Test activities can consume as much as 50% of a project's resources.
 Configuration control and change management are critical activities that can consume as much
as25% of resources on a large-scale project.
 Documentation activities can consume more than 30% of project engineering resources.
 Project management, business administration, and progress assessment can consume as much as
30%of project budgets.

15
3.5.ACHIEVING REQUIRED QUALITY
Software best practices are derived from the development process and technologies. Table 3-5 summarizes
some dimensions of quality improvement.
Key practices that improve overall software quality include the following:

 Focusing on driving requirements and critical use cases early in the life cycle, focusing on
requirements completeness and traceability late in the life cycle, and focusing throughout the life
cycle on a balance between requirements evolution, design evolution, and plan evolution
 Using metrics and indicators to measure the progress and quality of an architecture as it evolves
froma high-level prototype into a fully compliant product
 Providing integrated life-cycle environments that support early and continuous configuration
control, change management, rigorous design methods, document automation, and regression test
automation
 Using visual modeling and higher level languages that support architectural control, abstraction,
reliable programming, reuse, and self-documentation
 Early and continuous insight into performance issues through demonstration-based evaluations

Conventional development processes stressed early sizing and timing estimates of computer program
resource utilization. However, the typical chronology of events in performance assessment was as
follows

 Project inception. The proposed design was asserted to be low risk with adequate performance
margin.
 Initial design review. Optimistic assessments of adequate design margin were based mostly on
paper analysis or rough simulation of the critical threads. In most cases, the actual application
algorithms and database sizes were fairly well understood.
 Mid-life-cycle design review. The assessments started whittling away at the margin, as early

16
benchmarks and initial tests began exposing the optimism inherent in earlier estimates.
 Integration and test. Serious performance problems were uncovered, necessitating fundamental
changes in the architecture. The underlying infrastructure was usually the scapegoat, but the real
culprit was immature use of the infrastructure, immature architectural solutions, or poorly
understood early design trade-offs.
3.6.PEER INSPECTIONS: A PRAGMATIC VIEW
Peer inspections are frequently over hyped as the key aspect of a quality system. In my experience, peer
reviews are valuable as secondary mechanisms, but they are rarely significant contributors to quality
compared with the following primary quality mechanisms and indicators, which should be emphasized in
the management process:

 Transitioning engineering information from one artifact set to another, thereby assessing the
consistency, feasibility, understandability, and technology constraints inherent in the engineering
artifacts
 Major milestone demonstrations that force the artifacts to be assessed against tangible
criteria in thecontext of relevant use cases
 Environment tools (compilers, debuggers, analyzers, automated test suites) that ensure
representationrigor, consistency, completeness, and change control
 Life-cycle testing for detailed insight into critical trade-offs, acceptance criteria, and
requirements compliance
 Change management metrics for objective insight into multiple-perspective change trends
andconvergence or divergence from quality and progress goals
Inspections are also a good vehicle for holding authors accountable for quality products. All authors of
software and documentation should have their products scrutinized as a natural by-product of the
process. Therefore, the coverage of inspections should be across all authors rather than across all
components.

17

You might also like