International Journal of Global Community

Volume IV No. 2 (July), 2021


Dispute Resolution Model of Construction Work


Contract: A Case Study In Indonesia

Joni Emirzon1 and Henry Dianto Pardamean Sinaga2

1
University of Sriwijaya-Palembang, 2University of Diponegoro-Semarang
E-mail: joniemirzon@yahoo.co.id; sinagahenrydp@gmail.com

Abstract
The complexity of the construction industry causes the potential for construction
disputes to be very large and cannot be avoided. There have been many methods
of resolving construction contract disputes, such as litigation and non-litigation
method, but the resolutions still cause losses to the conflicting parties, both
financially and non-financially. Thus, it is necessary to explain the construction
work contract dispute resolution model in Indonesia, and propose its ideal model.
Considering that a construction work contract dispute arises as a result of an
escalation of disagreements, a dispute resolution should be done quickly, and
without harming each other, this study is adequate to use normative legal method.
The method works to find correct answers for proof and to give legal prescriptions
by using secondary data sources, which consisting of primary, secondary, and
tertiary legal materials. This study yields two conclusions. First, the dispute
resolution model of construction work contracts still reflects the win-win solution
principle, which consists of mediation, conciliation, and dispute council, that only
produces suggestions and does not have binding force and is not final. Whereas,
the construction sector which basically has a high business risk, needs a quick
resolution and can be complied with by all parties in the construction work
contract. Second, the ideal dispute resolution model of construction work contract
in Indonesia is sufficient to use arbitration in a broad sense, which accommodates
final and binding mediation and conciliation. It is recommended to remove the
word "court" in the explanation of Article 47 paragraph (1) letter (h) of the
Construction Services Law, as well as adopt a compromise on the revocability
doctrine and its exceptions and ratifies the New York Convention in 2015 in the
reformation of the 1999 Arbitration Act.

Keywords: construction work contract, win-win solution principle, arbitration

163

International Journal of Global Community
Volume IV No. 2 (July), 2021

Introduction
The very significant increase in the development of facilities and
infrastructure carried out in Indonesia shows that the construction sector is one of
the most important sectors in increasing economic growth. The priority of the
construction services sector is seen in the 2021 State Budget (APBN), which
shows the existence of things, such as maintenance/rehabilitation of 2,375 km of
roads, widening of 229 km of roads, construction of 699 km of bridges,
construction of 41,488 ha of irrigation networks, construction and improvement of
1,769 km strategic village roads, construction of 971 public health center
(Puskesmas) buildings, provision of housing in 50,000 units of slum resolutions,
and construction of 1,000 km of farming/production roads (Ministry of Finance,
2021).
However, it must be realized that the construction sector is a complex
business activity, wherefrom a legal point of view, this sector is in direct contact
with many regulations, such as highway road construction which must intersect
with construction service regulations, environmental regulations, land regulations,
investment regulations, labour regulations, tax regulations, banking regulations,
and other regulations (Lature, 2018: 212). The complexity of this construction
industry activity causes the potential for construction disputes to be very large and
cannot be avoided.
Indeed, there have been several dispute resolution methods that have
arisen in construction services in Indonesia based on Law Number 2 of 2017
concerning Construction Services (Construction Services Law) and Law Number
30 of 1999 concerning Arbitration and Alternative Dispute Resolution
(Arbitration Law), that are litigation and non-litigation (such as deliberation to
reach consensus, mediation, negotiation, conciliation, formation of dispute boards,
and arbitration). However, the resolution still causes losses to the conflicting
parties, both financial and non-financial. Hidayat and Gunawan's research on 330
State-Owned Enterprises (BUMN) contractor litigations at the Supreme Court
(MA) level in Indonesia concluded that the parties had to incur huge costs to be
able to resolve the dispute in a fairly long period of time, which ranged from three
up to six years (Hidayat, 2013). Even resolutions with non-litigation mechanisms
take a short time as the
data in Figure 1 processed
from the Indonesian
National Arbitration
Agency (BANI) as of
2017 on about 955 cases
that have been processed,
there were 59% dispute
resolution cases in 2014-
2016 which the resolution
Source: Data processed from BANI Center for the period 2014-2016
is more than 90 days.

164

International Journal of Global Community
Volume IV No. 2 (July), 2021

In addition, other losses await the conflicting parties, such as the


occurrence of bad business relationships in the future, unfocused corporations in
running their business, reduced levels of third party trust in the conflicting parties,
and additional costs that are not necessary. Few can reduce the company's
liquidity (in the form of lawyers and expert witnesses/consultant fees) (Gebken,
2006).
The vital role of the construction industry in development in Indonesia
and the potential for construction disputes to arise which are very detrimental to
the conflicting parties lead to two problem formulations in this study. First, does
the current construction work contract dispute resolution model in Indonesia
reflect the win-win solution principle? Second, what is the ideal dispute resolution
model of construction work contracts in Indonesia?

Material And Method


This study is a normative legal study or a doctrinal law study that works
to find correct answers for proof of or from written legal prescriptions
(Wignjosoebroto, 2009: 121). This study uses secondary data sources, which are
seen from the point of view of their binding strength consisting of legal materials,
which have binding power, secondary legal materials, which can help to analyze
and understand primary legal materials, and tertiary legal materials, which can
provide information on primary and secondary legal materials (Soemitro, 1990:
10-12).
The primary legal materials used in this study include the Civil Code
(KUH Perdata), the Construction Services Law, the Arbitration Law, Government
Regulation No. 22 of 2020 concerning Implementing Regulations of Law no. 2 of
2017 concerning Construction Services, and Supreme Court Regulation (PERMA)
Number 1 of 2016 concerning Mediation Procedures in Courts. The secondary
legal materials used in this study consist of books, journal articles, national and
international proceedings. The tertiary legal materials used in this study consist of
legal dictionaries, Indonesian language dictionaries, encyclopedias, internet
sources, and other tertiary legal materials. The secondary data obtained were
analyzed in a qualitative juridical manner, compiled systematically, and
conclusions and suggestions were drawn (Sinaga et al., 2020: 177).

Results
The problem of claims and disputes in the construction industry is a
worldwide phenomenon. According to Eilenberg (2003: 9-10), a dispute in
construction work contracts cannot be separated from the escalation of
disagreements that escalates into arguments escalates again into disputes.
Disagreement as the forerunner of dispute should be resolved by the parties
involved based on a common goal to resolve the issue quickly and without
harming each other. However, when a disagreement is not resolved immediately,

165

International Journal of Global Community
Volume IV No. 2 (July), 2021

it can escalate into an argument or fight, the level of difference in such a way
cannot be easily resolved. If an argument cannot be resolved, it will lead to a
dispute whose differences are such that it cannot be resolved without the help of a
formal system and outside assistance. A brief description of the escalation of
disagreements according to Eilenberg (2003: 10-11) is briefly described in Figure
2 below.

As a legal relationship, disputes arising from construction work contracts


must be legally resolved. The trend in the last ten years shows that non-litigation
resolutions dominate over litigation resolutions. The urgency of this non-litigation
resolution is emphasized by Chistoper W. Moore in Emirzon (2000: 20), whose
scope is in the form of volunteerism in the process; the procedure is fast, efficient
in time and cost, the decisions are non-judicial, the manager carries out the
control, who are most aware of the needs of the organization, whose procedures
are confidential, great flexibility in designing the terms of problem-solving,
protection and maintenance of excellent working relationships, have a very high
level of possibility to carry out agreements, a higher level of control and easier to
predict results, have agreements that are better than just a compromise or the
results obtained from a win/lose resolution, and decisions that last over time
(Emirzon, 2000: 20).
In terms of resolution of construction disputes in Indonesia, the
Construction Services Law has emphasized resolutions outside the court (non-
litigation) to achieve a "win-win solution" by providing space for the disputing
parties to use Alternative Dispute Resolution. (Lature, 2018: 218). However, there
is an explanation in Article 47 paragraph (1) letter (h) of the Construction
Services Law which seems to be able to justify the resolution of construction
disputes through litigation as it states: “...Dispute resolution is pursued through,
among others, deliberation, mediation, arbitration, or courts. In fact, it must be
realized that disputes in the construction service sector must be handled
immediately considering that the abandonment of construction projects will pose
a big risk, such as costly costs, fluctuating material prices, project abandonment
can endanger human lives, and the potential for material theft in the project

166

International Journal of Global Community
Volume IV No. 2 (July), 2021

environment so that it is hoped that legal settlement in a progressive legal context,
that is the parties involved in the contract must carry out the mandate of the
contract actively, transparently, and accountable in fulfilling justice, benefit, and
certainty (Hermawan et al., 2020: 157) in the contract. The urgency of a
construction dispute resolution period as quickly as possible can be compared
with the average period of arbitration resolution at BANI during 2014-2016,
which was still above three months on average, while the business sectors that
dominated case resolution at BANI during 2014-2016 were the construction
sector, as Figure 3 presents data on the completion of cases which have reached
26.9%.

Source: Data processed from BANI Center for the period 2014-2016

Discussion
1. Overview of construction contracts in Indonesia
Article 46 and Article 49 of the Construction Services Law have
emphasized that the working relationship between Service Users and Service
Providers as well as between Service Providers and Service Sub-Providers must
be stated in a Construction Work Contract, where the form of a Construction
Work Contract can follow the development of needs and be implemented
following the provisions of the regulation. What is meant by a Construction Work
Contract following Article 1 point 8 of the Construction Services Law is "the
entire contract document that regulates the legal relationship between Service
User and Service Provider in the implementation of Construction Services".
Furthermore, Article 47 of the Construction Services Law stipulates that a
Construction Work Contract must at least include clear identities of the parties, a
job formulation (which explains and details the scope of work, work value, unit
price, lump sum, and implementation time limit), and implementation period. And

167

International Journal of Global Community
Volume IV No. 2 (July), 2021

maintenance that is the responsibility of the Service Provider, equality of rights


and obligations between the Service User and the Service Provider, the obligation
to employ certified construction workers, payment methods, default, resolution of
disputes, termination of the Construction Work Contract, coercive circumstances,
Building Failure, worker protection, protection to third parties other than the
parties and workers, environmental aspects, guarantees for risks that arise and
legal liability to other parties in the implementation of Construction Works or as a
result of Building Failures, and options for resolving construction disputes. In
addition to containing the provisions as referred to in Article 47, Article 48 of the
Construction Services Law stipulates that the Construction Work Contract: 1) for
planning services must contain provisions on intellectual property rights, 2) for
the implementation of Construction Services, may contain provisions concerning
Service Sub-providers and suppliers of materials, building components, and/or
equipment that must comply with applicable standards, and 3) which is carried out
with foreign parties, contains the obligation to transfer technology.
Construction Work Contracts in Indonesia show that the engagement that
arises cannot be separated from the agreement, as Article 1233 of the Civil Code
formulates that "every engagement is born good because of approval, whether
because of the law". Furthermore, Article 1234 of the Civil Code confirms that
achievement as an object of a contract can be in the form of giving something,
doing something and not doing something, as long as it fulfils the four legal
requirements of a contract (according to the four conditions of Article 1320 of the
Civil Code, in the form of agreeing that those who bind themselves, are capable of
making a contract). An engagement, a certain matter, and a lawful cause), and
fulfils the requirements of the achievement itself, that is the form must be certain
or can be determined (Article 1320 paragraph 3 of the Civil Code), the object is
permitted by law (Article 1335 and Article 1337 of the Civil Code). Its
achievements are possible to be implemented.
The existence of a Construction Work Contract as a contractual
relationship will be evidence for each party if there is a violation committed by
one of the parties in the contract. Violation of the contractual relationship will
give birth to a dispute, which in the context of legal science, the lawsuit should be
in the realm of civil law referring to the possibility of a breach of contract (Lature,
2018: 218), as Article 47 paragraph (1) letter g of the Construction Services Law
requires a Contract Construction work must contain provisions regarding
responsibility if one of the parties does not carry out the obligations as agreed.

2. Resolution of construction contract disputes that apply in Indonesia


Article 88 of the Construction Services Law stipulates that the resolution
of a Construction Work Contract dispute must begin with the basic principle of
deliberation to reach a consensus. Still, if this principle is not achieved, then the
parties will take the stages of dispute resolution as stated in the Construction
Work Contract, which can be in the form of mediation, conciliation, and
arbitration, where the resolution of each of these processes can be terminated if

168

International Journal of Global Community
Volume IV No. 2 (July), 2021

the previous stages of the dispute have been resolved. Then, Article 93 paragraph
(3) - paragraph (5) of Government Regulation Number 22 of 2020 stipulates that
in addition to efforts to resolve disputes through Mediation and Conciliation, the
parties can appoint a Dispute Council, which functions as an effort to prevent and
resolve construction disputes. Regarding mediation and conciliation as Alternative
Dispute Resolution, as Article 1 point (10) confirms that Alternative Dispute
Resolution is an institution for resolving disputes or differences of opinion
through procedures agreed upon by the parties, that is resolution out of court by
means of consultation, negotiation, mediation, conciliation, or expert judgment.
The use of the Dispute Board in disputes of construction contracts in
Indonesia is based on Article 94 – Article 96 of Government Regulation No. 22 of
2020. The authority of the Dispute Board arises after the parties agree to use the
Dispute Board in the clauses of the Construction Services engagement and make a
tripartite Dispute Board agreement. The process and decision of the Dispute
Board must be based on the principle of justice. Still, if the parties/one of the
parties object to the decision of the Dispute Board, the stages of dispute resolution
in the form of mediation, conciliation, and arbitration can be taken.
Arrangements regarding construction mediation in Indonesia can refer to
the Arbitration Law, Government Regulation Number 22 of 2020, and PERMA
Number 1 of 2016 concerning Mediation Procedures in Courts. There are two
understandings of mediation that can lead to various interpretations, where Article
1 number (28) of Government Regulation Number 22 of 2020 defines mediation
as an effort to resolve disputes by involving third parties who act as advisors,
while Article 1 number (28) of PERMA Number 1 of 2016 defines mediation as a
way of resolving disputes through a negotiation process to obtain an agreement
between the Parties with the assistance of the Mediator. Article 1 number (2) of
PERMA Number 1 of 2016 stipulates that a mediator is a judge or other party
who has a Mediator certificate as a neutral party who assists the parties in the
negotiation process in order to seek various possible dispute resolutions without
resorting to a way of deciding or forcing a settlement. Then, Article 6 paragraph
(3) of the Arbitration Law stipulates that if a dispute or difference of opinion
through a direct meeting by the parties cannot be resolved, then upon the written
agreement of the parties, the dispute or difference of opinion is resolved through
the assistance of one or more expert advisors or a mediator. However, if the
parties within a period of 14 days with the assistance of one or more expert
advisors or through a mediator fail to reach an agreement, or the mediator fails to
bring the two parties together, then, following Article 6 paragraph (4) of the
Arbitration Law, the parties may contact an arbitration institution or alternative
dispute resolution body to appoint a mediator. After the appointment of a
mediator by the arbitration institution or alternative dispute resolution institution,
within a maximum of 7 days, the mediation business must start. Efforts to resolve
disputes or differences of opinion through a mediator by upholding confidentiality
within a maximum period of 30 days must be reached in writing signed by all
parties concerned. The agreement to settle disputes or differences of opinion in

169

International Journal of Global Community
Volume IV No. 2 (July), 2021

writing is final and binding on the parties to be implemented in good faith. It must
be registered at the District Court within 30 days of signing.
The understanding of conciliation is only obtained from its definition
contained in Article 1 number (29) of Government Regulation Number 22 of
2020, which reads: "Conciliation is an effort to resolve disputes by involving a
third party (conciliator) who actively intervenes". There are no further regulations
regarding the mechanism and procedures for conciliation in the Arbitration Law,
the Construction Services Law, and Government Regulation Number 22 of 2020.
As for Arbitration, following Article 1 number (1) of the Arbitration Law
is a way of settling a civil dispute outside the general court based on an arbitration
agreement made in writing by the disputing parties. Article 3, Article 6, and
Article 11 of the Arbitration Law have confirmed that the disputes of the parties
who have been bound in the arbitration agreement nullify the rights of the parties
to submit dispute resolutions or differences of opinion to the District Court. The
arbitration award is final and has permanent legal force, and is binding on the
parties; however, by Article 70 of the Arbitration Law, the parties may apply for
annulment of the arbitral award if the award is suspected to contain the following
three elements: 1) a letter or document submitted in the examination, after the
decision is handed down, it is recognized as false or declared false, 2) after the
decision is taken, a decisive document is found, which is hidden by the opposing
party, or 3) the decision is taken from the results of a ruse carried out by one of
the parties in the examination of the dispute.

3. The ideal dispute resolution model of construction contract in Indonesia


Many factors cause construction contract disputes in an economic
relationship. The first factor is the misinterpretation of legal certainty as merely
legal certainty in a practice of economic activity. The second factor is the
development of business contracts from time to time, the variety of types of
businesses, and the increasingly complex problems that arise, which have
prompted the emergence of new forms of business contracts that cannot be
separated from the following three factors: internal factors (dominated by various
government policies), external factors (a factor for business development that
comes from abroad), and factors for increasing the frequency and various forms of
business activities. The increase in contract activities requires adjustments to
certain legal areas, which inevitably can cause business disputes or conflicts. At
the same time, the third factor is the assumption that the occurrence of disputes is
a means of seeking justice and or legal certainty in terms of the emergence of
legal liability.
These factors often make disputes in the construction industry long,
complex and expensive to resolve and can cause long-term damage to the
commercial relationship between the parties. Construction contract disputes
should be avoided (or at least overcome) by ensuring there is a spirit of obligation
due to propriety to act or act and obligations due to propriety not to act or not to
act for the parties to the contract made, which of course the draft will be clear and

170

International Journal of Global Community
Volume IV No. 2 (July), 2021

fair. And contains early dispute resolution and effective contract management
(Chambers, 2011: 7). The contractual method that has the spirit of legal liability
so that it can be a basic preventive measure that contributes to the minimization of
disputes is carried out with the following four main things: 1) ensuring that the
parties have signed the final contract before the work begins, 2) ensuring that the
scope and quality of work have been determined. Clearly defined at the pre-
contract stage, 3) ensure that the terms of the contract are fair and clear, and use
standard contract forms wherever possible, 4) ensure that the contracts used
contain provisions on early notification of potential disputes and well-structured
dispute resolution clauses which is not limited to litigation but also to arbitration
and alternative dispute resolution (Chambers, 2011: 7).
Considering that in general, construction disputes arise from violations of
Article 47 paragraph (1) letter g-letter k of the Construction Services Law, that is
violations related to default, dispute resolution, termination of Construction Work
Contracts, coercive circumstances, and Building Failures, the resolution of
construction contract disputes can be based on on the idea of legal liability which
must provide justice to parties who do not carry out their contractual obligations
through non-litigation resolutions (Priyambudi et al., 2020: 11993). This legal
liability must refer to obligations due to propriety to act or do and obligations not
acting or not acting. There are 4 (four) criteria attached to the obligation due to
propriety to act/act, that are: 1) it is carried out in good faith to fulfil its legal
obligations unless it can be proven that a state of force majeure or coercion or
other things make it act otherwise, 2) carried because of the danger or damage or
loss that may occur immediately and or cannot be avoided, 3) there is no better
alternative, or if the action is not taken it will cause even greater harm or damage
or loss, and 4) the act or deed is purely by accident. While the obligation due to
propriety not to do/not act is attached to 4 (four) criteria, that are: 1) it is a mala
prohibita act, 2) it is not within the scope of its capacity so that it cannot act/act
according to its professional judgment, 3) there are still some alternative
actions/other actions that are even better that do not violate the applicable laws
and regulations, and 4) are actions/actions that enrich oneself/a group and/or other
parties that cause financial losses to the victim (Sinaga and Sinaga, 2018: 103-
104).
The existence of an obligation due to propriety to act or act and an
obligation due to propriety not to act or not act in a construction contract (dispute)
is adequate to be carried out through non-litigation channels as a win-win solution,
considering that a contract cannot be separated from the legal relationship
between two or more persons. More, where one party is entitled to achievement,
and the other party is obliged to fulfil that achievement. This is reinforced by the
doctrine of pacta sunt servanda, which teaches that a contract made legally, in
good faith, and based on the applicable laws and regulations, binds the parties
who made it so that every contract implementation must not harm the parties in
the contract. Contracts and other third parties related to the contract (Fuady, 2013:
211).

171

International Journal of Global Community
Volume IV No. 2 (July), 2021

The non-litigation construction work contract disputes in the


Construction Services Law in the form of mediation, conciliation, and the Dispute
Board are not yet binding considering that the stages of the dispute can still be
arbitrated, even though efforts to resolve mediation, conciliation, and the Dispute
Board have taken months. The moon and its position are only suggestions by not
deciding who is right or wrong (Chern, 2015: 6). Not to mention the matter of
mediation, conciliation, and the Dispute Council, which still lacks laws and
regulations at the level of Government Regulations and their implementing rules.
Of course, if the stages of mediation, conciliation, and the Dispute Board have
been terminated, arbitration can still be submitted as the arbitration decision is
final and has permanent legal force and is binding on the parties (as long as it
does not meet the elements of Article 70 of the Arbitration Law). In addition, the
arbitrator or arbitral tribunal is obliged to make peace between the disputing
parties in the arbitration process itself. The arbitrator or arbitral tribunal draws up
a deed of reconciliation that is final and binding on the parties if peace is reached.
Arbitration should meet the qualifications for applying the legal liability
doctrine and the pacta sunt servanda doctrine to resolve construction work
contract disputes. This has also been emphasized by Hasan (2010: 25-26), who
argues that the three expectations for the outcome of the arbitration are: 1)
impartiality and expertise of the arbitrator who decides the case because the
parties can choose a qualified arbitrator with the required expertise (Hoellering,
1984: 35), which has no interest and is impartial, and can fully give the necessary
time to understand the facts and applicable rules, 2) examination through closed
arbitration and private and confidential, and 3) efficiency an arbitration process
that is more efficient than going through the courts, one of which is a binding and
final arbitration award.
The three pillars of the expectation that every construction work contract
dispute is resolved through arbitration will be better if some shortcomings or
weaknesses can be addressed. Hasan (2010: 26) and Besaiso et al. (2018) stated
several challenges and weaknesses of arbitration in Indonesia, such as 1) there is
no guarantee that the arbitration process will run fairly, while the arbitration
award is binding and final, so there will always be a risk of prejudice against the
arbitrator, 2) the concept of arbitration in each country often different because
each is influenced by the law and their respective legal structures, resulting in the
reluctance of many international organizations/companies to participate in
arbitrations in Indonesia, and 3) arbitration decisions always depend on the
technical ability of the arbitrators to be able to provide satisfactory decisions for
the parties and following the sense of justice of the parties.
Of course, some of the shortcomings or weaknesses of arbitration can be
corrected if re-understanding the nature of arbitration that is as a dispute
resolution process that is faster and cheaper than litigation, which binds the parties
who have agreed to submit their dispute to a neutral third party who hears from
the parties. All parties impose binding decisions on the disputing parties because
they use simplified procedures to achieve results based on the principles of law,

172

International Journal of Global Community
Volume IV No. 2 (July), 2021

equality, custom, and practice unique to a particular industry (Jill, 2019: 193).
Thus, the equality of the parties in the contract shows that the central concept
behind arbitration is to provide enforceability of the results of the arbitration
between the disputing parties as equal bargaining power while still not allowing
the defaulting party to escape from its obligations (Norris, 2018: 259). ).
One of the disputing parties can do several things if it is suspected that
the arbitration process is running unfairly, such as the right to deny and revive the
revocability doctrine. Article 22 of the Arbitration Law stipulates that if a reason
is found and sufficient authentic evidence is found, a claim for denial may be filed
against the arbitrator. The revocability doctrine allows either party to withdraw
their agreement to arbitrate until the arbitrator decides (Horton, 2013: 1225). The
compromise on the revocability doctrine and its exceptions has been adopted in
Part II of the 1980 Vienna Convention on Contracts for the International Sale of
Goods (CISG) Article 16, as the formula reads: “1) Until a contract is concluded
an offer may be revoked if the revocation reaches the offeree before he has
dispatched an acceptance. 2) However, an offer cannot be revoked: a) if it
indicates, whether by stating a fixed time for acceptance or otherwise, that it is
irrevocable; or b) if it was reasonable for the offeree to rely on the offer as being
irrevocable and the offeree has acted in reliance on the offer” (Lookofsky, 2018:
580-581). The existence of the revocability doctrine will increasingly provide
equality to the disputing parties and provide mutual control and give the disputing
parties the right to make peace when the arbitration process is in progress.
Meanwhile, the efforts made by Indonesia in dealing with the reluctance of
international companies/organizations to participate in the arbitration in Indonesia
by ratifying the New York Convention in 2015 concerning its prospective
guarantee that the parties to the contract will follow international practice
(Besaiso et al., 2018).

Conclusion
This study yields two conclusions. First, Indonesia's current construction
work contract dispute resolution model still reflects the win-win solution principle
in a narrow sense. This means that the win-win solution principle is limited to the
Arbitration Law and the Construction Services Law, which stipulates that the
resolution of construction contract disputes must be carried out in a non-litigation
manner. In fact, the non-litigation resolution of construction work contracts
consisting of mediation, conciliation, and dispute councils only produces
suggestions. It does not have binding and non-final power, which will harm the
parties in the construction sector, which basically have high business risks.
Second, the ideal construction work contract dispute resolution model in
Indonesia is adequate by using arbitration in a broad sense, that is, arbitration in
which mediation and conciliation are accommodated. However, the results are
still final and binding.

173

International Journal of Global Community
Volume IV No. 2 (July), 2021

Recommendation
Based on the two conclusions that have been drawn. There are several
suggestions in producing an ideal arbitration model in resolving construction
work contract disputes in Indonesia, including:
a. Removing the word "court" in the explanation of Article 47 paragraph (1)
letter (h) of the Construction Services Law because it can justify the
resolution of construction disputes through litigation.
b. The need to consider reforming the 1999 Arbitration Act by adopting a
compromise on the revocability doctrine and its exceptions and ratifying
the New York Convention in 2015.***

References
Besaiso, H., Fenn, P., and Emsley, M. (2018), Evolution of Construction
Arbitration, Journal of Legal Affairs and Dispute Resolution in
Engineering and Construction, Vol. 10, No. 2, retrieved from
http://insight.cumbria.ac.uk/id/eprint/5181/1/Besaiso_EvolutionOf.pdf.
Chern, Cyril, (2015), Chern on Dispute Boards: Practice and Procedure, Informa
Law from Rotledge, Oxon.
Eilenberg, Ian M., (2003), Dispute Resolution in Construction Management,
University of New South Wales Press Ltd, Sidney.
Emirzon, J., (2000), Alternatif Penyelesaian Sengketa di Luar Pengadilan
(Negosiasi, Mediasi, Konsolidasi, dan Arbitrase) (Alternative Dispute
Resolution Out of the Court (Negotiation, Mediation, Consolidation, and
Arbitration), Gramedia Pustaka Utama, Jakarta.
Fuady, M., (2013), Teori-Teori Besar (Grand Theory) Dalam Hukum (Grand
Theories in Law), Kencana, Jakarta.
Gebken, R. J., (2006), Quantification of Transactional Dispute Resolution Costs
for the U.S. Construction Industry, A PhD Dissertation of The University
of Texas at Austin, Austin.
Gross, Jill I., (2019), Bargaining in the (Murky) Shadow of Arbitration, Harvard
Negotiation Law Review, Vol. 24, Spring, pp. 185-212.
Hasan, Madjedi, (2010), Hal-hal Yang Perlu Dipertimbangkan Sebelum
Menandatangani Kesepakatan Berarbitrase (Matters to Consider before
Signing an Arbitration Agreement), Indonesia Arbitration Quarterly
Newsletter, Vol. 11, pp. 21-26.
Hermawan, A. W., Sinaga, H. D. P., and Barus, L. B., (2020), Legal
Reconstruction of Tax-Sharing Funds in Indonesia: Towards the
Progressive and Democratic Tax Function, Advances in Social Science,
Education and Humanities Research Vol. 499, pp. 153-159.
Hidayat, C. G. F., (2013), Analisa Karakteristik Penyelesaian Sengketa pada
Proyek Konstruksi di Tingkat Mahkamah Agung (Analysis of the
Characteristics of Dispute Resolution on Construction Projects at the

174

International Journal of Global Community
Volume IV No. 2 (July), 2021

Supreme Court), Konferensi Nasional Teknik Sipil 7 (KoNTekS 7) in
Surakarta.
Hoellering, Michael F., (1984), Construction Arbitration and Mediation, Journal
(American Water Works Association), Vol. 76, No. 2, Minimizing
Construction Problems, pp. 34-38.
Horton, David, (2013), Federal Arbitration Act Preemption, Purposivism, and
State Public Policy, The Georgetown Law Journal, Vol. 101, pp. 1217-
1273.
Kementerian Keuangan, “Informasi APBN 2021: Percepatan Pemulihan Ekonomi
dan Penguatan Reformasi (The 2021 State Budget Information:
Accelerating Economic Recovery and Strengthening Reforms)”, available
at https://www.kemenkeu.go.id/media/ 16835/informasi-apbn-2021.pdf
retrieved on April 30, 2021.
Lature, K. E., (2018), Analisis Penyelesaian Sengketa Konstruksi di Indonesia
(Analysis of Construction Dispute Resolution in Indonesia), vol. 15, no. 3,
pp. 211-222.
Lookofsky, Joseph, (2018), Revocability, Unconscionability and Impracticability
in American, Danish and International Law, retrieved from
https://papers.ssrn.com/sol3/papers.cfm?abstract_id=3487520 on July
9, 2021.
Norris, Luke P., (2018), The Parity Principle, New York University Law Review,
Vol. 93, pp. 249-317.
Priyambudi, Sinaga, H.D.P., and Bolifaar, A.H, (2020), Managing Plea
Bargaining Risk in Indonesia: An Effort to Overcome the Corporate
Corruption. Tes Engineering & Management 83, March–April, pp. 11993–
12005. Retrieved from
http://www.testmagzine.biz/index.php/testmagzine/article/view/5815/
Republik Indonesia, Law Number 2 of 2017 concerning Construction Service.
________________, Law Number 30 of 1999 concerning Arbitration and
Alternative Dispute Resolution.
________________, Code of Civi Law.
________________, Government Regulation Number 22 of 2020 concerning the
Implementation Regulation Law Number 2 of 2017 concerning
Construction Service.
________________, The Supreme Court Regulation Number 1 of 2016
concerning Mediation Procedures in the Court.
Sinaga, B. R. P., Sinaga, E. N., Barus, L. B., Sinaga, R. Y., and Sinaga, H. D. P.,
(2020), Justice Reconception In Establishing Responsive Tax Law In
Indonesia: A Rawlsian Perspective. Ayer Journal, Vol. 27, No. 3, pp. 171-
189.
Sinaga, H. D. P., and Sinaga, B. R. P., (2018), Rekonstruksi Model-Model
Pertanggungjawaban di Bidang Perpajakan dan Kepabeanan
(Reconstruction of Liability Models in Taxation and Customs), Kanisius,
Yogyakarta.

175

International Journal of Global Community
Volume IV No. 2 (July), 2021

Soemitro, R. H., (1990), Metodologi Penelitian Hukum dan Jurimetri


(Methodology of Legal Research and Jurimetry), Ghalia Indonesia,
Jakarta.
Wignjosoebroto, S., (2009), Ragam-Ragam Penelitian Hukum (Varieties of Legal
Research), in Irianto, S., & Sidharta (Eds.), Metode Penelitian Hukum:
Konstelasi dan Refleksi (Legal Research Method: Constelation and
Reflection), Yayasan Obor Indonesia, Jakarta, pp. 121-141.