2 RA - Storm Water Drainage Works (Revised)

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 19

Task Base Risk Assessment (RA)

Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1


West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 1 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

1 Handling  Site  Improper  Personal 3 2 6  Risk Assessment is communicated to all 1 2 2 Safety Low
of lifting concerned personnel. Officer/
Operatives injury
Surveyor/
total Technique  Back  Daily, JSA pre-start briefing to the entire Workers
station (Sudden injury relevant workforce and signed for, prior
and awkward  Upper commencing the job.
accessorie movement / limb  Conduct manual handling training to
s twisting & disorders ensure safe performance.
jerking  PPE’s – Helmet, Safety Shoes, Coverall,
whilst Goggles, Disposable face mask
lifting). respirator, Ear plug, Hand gloves, High
Visibility vest

Survey  Site  Impact of  Personal 3 4 12  Obtain PTW before commencing the 1 4 4 Safety Moderate
2 Work & Officer/
Operatives steel rod Injury work.
Underground  Inspectors inside ground  Fatality  Risk Assessment is communicated to all Site
Utility  Exposed concerned personnel. Supervisor/
 Damage to
steel rod Surveyor/
Detection underground  Daily, JSA pre-start briefing to the entire
(Without Utilities
utilities relevant workforce and signed for, prior
rebar cap) detecting
to commence the work.
Operator/
 Contact with  Obtain information /drawing from Workers
Underground concerned authorities about underground
utilities utilities.
 Obstruction  Identification of buried services by CAT
causing (Cable Avoidance Tool) detector and
slip/trip/fall Portable transmitter or signal generator

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 2 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

(Genny).
 Positive identification of services such as
electricity cables, metal, gas & water
pipes, telephone cables by using CAT
detector & Genny, signal generator.
 Methods of detecting various Utilities
include: Power detection, Radio
frequency, Transmitter and receiver
(inductive and conductive).
 The Operator of Utility detector must be
trained and competent to operate the
scanner of each type and make and shall
have a training certificate.
 Avoid impact of survey steel rod above
the existing utilities.
 Use rebar cap.
 Where necessary barricade the area
around steel rods.
 Avoid short cuts.
 PPE’s – Helmet, Safety Shoes, Coverall,
Goggles, Disposable face mask
respirator, Ear plug, Hand gloves, High
Visibility vest
3 Movement  Site  Unskilled  Personal 4 4 16  Vehicles/equipments have valid Qatar 2 4 8 Safety High
of heavy Operatives drivers/ Injury Registration documents. Officer/

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 3 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

mobile  Inspectors operators  Fatality  All vehicles/equipments are inspected Site


plants,  Visitors  Overloading  Damage and certified by 3rd party. Engineer/
Loading &  Over to  All drivers/ operators should have Foremen/
 Drivers
Transportatio Drivers/
speeding existing valid Qatar driving license
n of Operators/
 Unsecured utilities appropriate for the type of vehicle Banks men/
Excavating being driven.
load /  Damage to workers
Materials,
improperly assets/  All drivers/operators are tested and
VC Pipes
covered load equipment certified by 3rd party.
(shift/fall of  Acute &  Vehicle Inspection checklist is
Storage &
load) Chronic completed.
Handling
 Falling/ health  Risk assessment is communicated to
of pipes &
ejected effects all concerned personnel.
fittings,
objects  Fire/  Daily, JSA pre-start briefing to the
Steels
 Mechanical Explosio entire relevant workforce and signed
Failure n for, prior commencing the work.
 Congested  Disruption  Daily pre-start inspection of vehicles/
work area of work equipment by drivers/operators and
 Poor progress monthly by mechanic.
Visibility  Damage to  Trained Flagman should be used all
 Poor company the time to assist the drivers/operators
organization reputation when there is movement of
of work  RTA for plants/machineries, especially while
activities the users reversing.
 Improperly of the  Drivers/operators should report any

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 4 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

maintained road defect found to direct


equipment  Fire supervisor/mechanic.
 Users of the  Overhead services to be identified
road and avoid loading/ offloading under
 Improper it.
stacking  Avoid overloading.
 Dust  Existing underground utilities should
 Noise be properly marked and protected.
 Vibration  All vehicles are fitted with reverse
 Non- alarms, rotating lights and appropriate
compliance type and size ABC dry powder fire
with traffic extinguishers.
rules  Non-essential personnel shall be kept
 Overhead or well away from the area of operation.
buried  Close supervision should be
services maintained.
 Weather  Site speed limit to be set and strictly
condition enforced.
 Seat Belt Policy strictly enforced.
 All trucks should be equipped with
covering canvas and ropes
 Suitable ladder should be available on
vehicle body for safe access to
fix/remove the cover

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 5 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

 Ensure clear vicinity in trucks


working area
 Load pipes on wooden platform with
anti-roll over stop blocks and
properly secured.
 Working day for drivers must not
exceed 12 hours.
 Prohibition of driving in fog
condition.
 Regular spot checking of driving
performance.
 Driver to ensure that the cargo
compartment shutter is properly
closed after each loading &
offloading operation
 All personnel are trained in manual
handling technique.
 Good housekeeping standards must be
maintained.
 Safe access for people and equipment
should be maintained.
 All pipes should be stored on wooden
platform fitted with anti-roll over stop
blocks.

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 6 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

 Pipes of big diameter should be stored in


single layer.
 Avoid manual handling
 Storage area barricaded and appropriate
safety warning signage’s to be posted.
 Packages are not to be dropped to avoid
damages.
 Boxes should stack in flat area.
 Trained & Certified First Aider and
First aid kit available on site.
 All site personnel are familiar with
accident/Incident reporting
procedures and emergency telephone
numbers are known to everyone.
 PPE’s – Helmet, Safety Shoes, Coverall,
Goggles, Disposable face mask
respirator, Ear plug, Hand gloves, High
Visibility vest
4 Excavatio  Site  Damage to  Personnel 5 4 20  Obtain Excavation permit prior to start 2 4 8 Safety High
n Operatives underground injury the work. Officer/
 Inspectors utilities  Fatality  Obtain drawings/information from Excavation
(electrical Engineer/
 Eye injury concerned authorities.
Utilities
cables, q-Tel  Acute &  Risk Assessment is communicated to all detecting
cables, Chronic concerned site personnel. Operator/

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 7 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

crossing health  Daily, JSA pre-start briefing to the Site


pipes etc.) effects entire relevant workforce and signed Supervisor/
 Employees  Damage to for, prior commencing work. Workers
struck by assets  Identification of buried services by CAT
vehicles  Interruption (Cable Avoidance Tool) detector and
 Inhalation of of job Portable transmitter or signal generator
dust  Damage to (Genny).
 Foreign company  Positive identification of services such as
bodies in reputation electricity cables, metal, gas & water
pipes, telephone cables by using CAT
eyes
detector & Genny, signal generator.
 Noise
 Methods of detecting various Utilities
 vibration include: Power detection, Radio
frequency, Transmitter and receiver
(inductive and conductive).
 The Operator of Utility detector must be
trained and competent to operate the
scanner of each type and make and shall
have a training certificate.
 Qualified Excavation engineer should
approve, supervise and inspect
excavation
 Trial holes must be done by using safe
method of excavation and expose the
existing underground utilities.

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 8 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

 Trained Flagman should be used all the


time to assist the drivers/operators
when there is movement of
plants/machineries, especially while
reversing.
 Avoid direct excavation above the lines.
 Identified/exposed utilities should be
properly protected and labeled.
 Close supervision by site supervisor.
 Trained & Certified First aider and First
aid kit available on site.
 All personnel are trained and familiar
with accident/incident reporting
procedures and emergency telephone
numbers are known to everyone.
 PPE’s – Helmet, Safety Shoes, Coverall,
Goggles, Disposable face mask
respirator, Ear plug, Hand gloves, High
Visibility vest
 Collapse of  Personal 4 4 16  Identification of Soil stability prior to 1 4 4 Excavation Moderate
excavation Injury start the work. Engineer/
sides  Fatality  Select safe sloping, shoring and benching Foremen/
methods before starting excavation. Workers
 Damage to
assets  Types of excavation support systems
 Interruption include: shields, trench boxes and plate
EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)
Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 9 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

of job. lining, to be used as necessary.


 Vehicles and equipment must be kept
away from the excavation side.
 Daily inspection of all parts of an
excavation including hard barricades,
shoring and access/ egress.
 Spoils from Excavation should be placed
at least 2 meters from the edge of cut.
 Falls  Personal 4 4 16  Barricade the area by using hard barriers. 1 4 4 Site Moderate
(Personnel, Injury  Maintain safe space (> 2.0 meters Supervisor/
objects,  Fatality between edge of cut and barriers). Workers
Vehicles,  Damage to  Warning signs (Keep Away Deep
Animals). assets Excavation) shall be placed behind the
 Interruption barriers at regular intervals.
of job.  Warning flash light should be fixed on
the top of Plastic or concrete barriers.

 Slip/Trip &  Personal 4 2 8  Safe access/egress should be maintained. 2 2 4 Safety Moderate


Fall injury  Ladder should be properly secured. Officer/
Excavation
 Ladder should be extended at least 1.05
engineer/
meters above the landing point.
Foremen/
 Ladders shall be placed every 25feet for Workers
each entry and exit from the excavation.
 All concerned personnel should be
trained on ladder safety.
EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)
Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 10 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

 Exposed rebar fitted with caps


 Daily inspection by site safety officer
and Excavation engineer.
 Trained and Certified First Aider and
First Aid Kit available on site.

 Biological  Personnel 3 4 12  Inform employees about the possibility 1 4 4 Foremen/ Moderate


Hazard injury of snake/scorpion/insects bites during Workers
 Fatality excavation and backfilling.
 Trained & Certified First Aider, First Aid
kit & Bite Kit available on site.
 Long boots, if necessary, in addition to
the above mentioned personal protective
equipments.
5 Mobile  Crane  Unskilled  Personal 4 4 16  Obtain PTW before starting the work. 2 4 8 Lifting High
Crane Operator Operator/ Injury  Risk assessment should be Supervisor/
Operation,  Rigger/ driver  Fatality communicated to all concerned Safety
Steel Slinger  Failure of personnel. Officer
 Damage to
lifting, support Crane
 Site property/  Daily, JSA pre-start briefing to the entire
Concrete Operator/
Operatives  Load Fall equipment relevant workforce and signed for, prior
Mixers & Driver/
 Banks men  Mechanical / load commencing the work.
Concrete Rigger/
Pumps Failure  Crane on  Suitability of the crane lifting capacity. Flag man/
 Congested Fire  Suitability of the belts lifting capacity Workers
work area  Disruption  Crane is inspected and certified by
 Poor of work approved 3rd party.
EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)
Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 11 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

visibility progress  Operator competency and training


 Improperly  Damage to certificate available and issued by
maintained reputation approved 3rd party.
equipment  Rigger competency and training
 Overhead certificate available and issued by
services approved 3rd party.
 Failure of  Trained Flagman should be used all the
concrete time to assist the drivers/operators when
pump, there is movement of mobile
support, plants/machineries, especially while
hydraulic reversing.
system  Crane inspection check list is completed.
 Crane is inspected for any defect, oil leak
before starting the job.
 Daily/weekly inspection of
equipment/vehicles by operators/drivers
and monthly by mechanic.
 Lifting tackles are tested & certified by
3rd party and Colour coded.
 Lifting tackles are inspected before
starting the job.
 Close supervision by lifting supervisor
should be maintained all the time.
 Adequate length taglines should be used
to control the suspended load.

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 12 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

 Stability of the ground and crane


positioned horizontally (adequate size
wooden support to be used).
 Crane trajectory barricaded & free of
people or obstruction.
 Hook safety latch.
 Appropriate safety warning sign boards.
 All vehicles should be fitted with reverse
alarm and rotating light.
 Pump is inspected for any defect, oil leak
before starting the job.
 Stability of the ground and pump
positioned horizontally (wooden support
to be used).
 Avoid using of concrete pump under
overhead services.
 Site speed limit to be set and strictly
enforced.
 Non-essential personnel shall be kept
well away from the area of operation.
 Proper organization of the work area
(safe access/exit).
 Appropriate & adequate Fire
Extinguisher available on site.

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 13 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

 All personnel are familiar with


emergency procedures and emergency
telephone numbers are known to
everyone.
 Trained and Certified First aider and First
aid kit available on site
 PPE’s – Helmet, Safety Shoes, Coverall,
Goggles, Hand gloves, High Visibility
vest.
6 Bedding  Site  Inhalation of  Personal 4 4 16  Risk assessment is communicated to 1 4 4 Safety Moderate
and Operatives dust. Injury all concerned personnel prior to Officer/
Surround  Inspectors  Foreign  Fatality commencement of work. Concrete
(Granular bodies in Supervisor/
 Person  Acute &  Daily, JSA pre-start briefing to the entire
& eyes Foremen/
using Plate chronic relevant workforce and signed for, prior
Concrete), Workers
compactor  Reversing & health commencing the work
Compaction
moving effects  Trained Flagman should be used all
vehicles  Eye injury the time to assist the drivers/operators
 Improperly  Falling of when there is movement of mobile
maintained vehicle plants/machineries, especially while
equipment  Chemical reversing.
 Noise burns  Stop blocks must be fixed at safe
 Vibration distance from the edge of cut where
 Biological trucks should reverse close to the
hazard excavation.
(snake,  Ensure good physical condition of
EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)
Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 14 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

scorpions & workers involved.


insect bites)  Pump, hose & fittings to be checked
 Poor prior to start work.
visibility  Daily checking of equipment before
 Employees starting the work by the operator and
struck by monthly by mechanic.
vehicles  Workers are trained in the proper use and
 Split of checking of their respective equipments.
Concrete  Vibration tag to be checked for vibration
 Upper limb magnitude (m/s2) & rotation frequency to
disorders be implemented.
 Provision of low vibration equipment
where possible.
 Regular rotation of employees not to
exceed the recommended EAV.
 Close supervision
 Regular water spray
 Trained & Certified First Aider and First
Aid kit are available on site
 All personnel are familiar with
accident/incident reporting procedures
and emergency telephone numbers are
known to everyone.
 PPE’s – Helmet, Safety Shoes, rubber
shoes(for concrete works), Hand gloves,

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 15 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

Coverall, Face shield, Safety glasses,


Disposable face mask respirator,
Ear plug, High Visibility vest.

7 VC pipes  Site  Unskilled  Personal 3 4 12  Risk assessment is communicated to all 1 4 4 Safety Moderate
cutting & Operatives worker injury employees involved in task. Officer/
Jointing  Collapse of  Damage to  Daily, JSA pre-start briefing to the entire Foremen/
excavation pipes relevant workforce and signed for, prior Workers
 Damaged  Trapping commencing the work
sling/chain  Daily inspection of the excavation.
 Hand/fingers  Trench box to be used when necessary
on Pinch  Daily inspection of chain block/slings,
point tools prior to use for work.
 Improper PPE  Chain block/sling inspected and certified
by approved 3rd party
 Any defective tools/equipment should be
removed from site and returned to store.
 Close supervision.
 PPE’s - Helmet, Safety Shoes, Hand
gloves, Goggles, Coverall, High
visibility vest.
8 Concrete  Site  Split of  Personal 3 4 12  Obtain PTW in advance of work. 1 4 4 Safety Moderate
Pouring & Operatives Concrete Injury  MSDS available and communicated to Officer/
Vibration  Inspectors  Slip/Trip/  Fatality all concerned personnel. Concrete
at heights Supervisor/
Fall  Chemical  Risk assessment is communicated to all
EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)
Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 16 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

 Noise burns concerned personnel. Workers


 Vibration  Damage to  Daily, JSA pre-start briefing to the
assets/ entire relevant workforce and signed
equipment for, prior to start of work.
 Eye  Concrete Pouring shall be under the
injury direct supervision of a competent
 Acute & person having at least 5 years of
Chronic experience.
health  Safe work platform must be
effects maintained across the
excavation/along the beams.
 Pump, hose & fittings to be checked
prior to start the activity by the
operator and monthly by mechanic.
 Timber boarding on the top of steel
structure (slab area) for safe access
and safe place of work.
 Vibration tag to be checked for vibration
magnitude (m/s2) & rotation frequency to
be implemented
 Daily checking of the equipment before
starting the work by the operator.
 Workers are trained in the proper use and
checking of their respective equipment.

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 17 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

 Provision of low vibration equipment


where possible.
 Ensure good physical condition of
workers involve.
 Regular rotation of employees not to
exceed the recommended EAV.
 Close supervision
 Trained and Certified First aider and
First aid kit are available on site.
 All personnel are trained in Emergency
procedures and Emergency telephone
numbers are known to everyone.
 PPE’s - Helmets, Full face shield,
coverall, rubber shoes, Hand gloves, Ear
plug, safety glasses, full body harness.
9 Backfilling  Site  Reversing &  Personal 4 4 16  Risk assessment is communicated to 1 4 4 Safety Moderate
Operatives moving Injury. all personnel prior to commencement Officer/
 Persons vehicles  Fatality of work. Foremen/
visiting the  Employees Banks men/
 Damage to  Daily, JSA pre-start briefing to the
site struck by Workers
property. entire relevant workforce and signed
vehicles  Disruption for, prior commencing the work.
 Poor of work.  Trained Flagman should be used all
organization  Falling the time to assist the drivers/
of work hazard
activities.
operators when there is movement of
 Acute & mobile plants/machineries, especially
EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)
Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 18 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

RISK RATING
ADVERSE RISK RATING
No PERSON AT CAUSE OF CONTROL MEASURES TO AFTER
JOB/TASK EFFECT RESPONSIBLE ASSESSMENT
. RISK ADVERSE EFFECT BE TAKEN / ADOPTED
L1 S1 RFN L2 S2 RNN

 Inhalation of Chronic while reversing.


dust. health  Stop blocks must be fixed at safe
 Improperly effects distance from the edge of cut where
maintained trucks/equipment should reverse close to
equipment the excavation.
 Congested  Close Supervision.
work area  Area under backfilling must be
 Foreign barricaded to avoid unauthorized
bodies in entrance of people & vehicles.
eyes.  Safe access/egress should be maintained.
 Noise  Regular spraying of water
 Regular rotation of employees to reduce
adverse health effects
 Trained & Certified First aider and First
aid kit are available on site.
 PPE’s – Helmet, Safety Shoes, Coverall,
Goggles, Disposable face mask
respirator, Hand gloves, High Visibility
vest.

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)


Task Base Risk Assessment (RA)
Project: Construction and Upgrade of Rayyan Road, Project 7 : Contract 1
West of New Rayyan R/A to East of BaniHajer R/A
Project No:P007 Contract No: 01
Contractor: Sixco – Boom JV
Sheet no. 19 of 19
Doc No:………….. Risk Assessment for Storm water Drainage works

Date of assessment : Consequence


Reassessment date :
Likelihood
Assessment reference : Insignificant Minor Moderate Major Catastrophic
Location :Rayyan Road-West of New Rayyan R/A to East of BaniHajer R/A 1 2 3 4 5
Assessment Activity : 1 (Rare) 1 (Low) 2 (Low) 3 (Moderate) 4 (Moderate) 5 (High)
2 (Unlikely) 2 (Low) 4 (Moderate) 6 (High) 8 (High) 10 (Extreme)
3 (Possible) 3 (Moderate) 6 (High) 9 (High) 12 (Extreme) 15 (Extreme)
Legend: L = low, M = medium, H = High, E = Extreme 4 (Likely) 4 (Moderate) 8 (High) 12 (Extreme) 16 (Extreme) 20 (Extreme)
5 (Repeatedly) 5 (High) 10 (Extreme) 15 (Extreme) 20 (Extreme) 25 (Extreme)

NAME POSITION SIGNATURE DATE


Prepared by: SAJEEV MOHAN LEAD ENGINEER - HSE 05-08-2014
Reviewed by:
Approved by:

EXW-P007-0101-HS-SIX-AS-00001 – Task Base Risk Assessment - Edition 01 – (07/2014)