Civil Work at WellPad B

Activity ID Activity Name Original Start Finish 2023


Duration Nov
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
WPB-09-7-MTO Civil Work at WellPad B 182 12-Sep-22 11-Apr-23 11-Apr-23, WPB-09-7-MTO Civil Work at WellPad B

WPB-09-7-MTO.1 Milestone 182 12-Sep-22 11-Apr-23 11-Apr-23, WPB-09-7-MTO.1 Milestone


A2780 PO Released 0 12-Sep-22* PO Released, 12-Sep-22*

A3025 Conductor Pipe Arrived 0 13-Mar-23* Conductor Pipe Arrived,


A3030 Project Finished 0 11-Apr-23 Project Finished,

WPB-09-7-MTO.2 Engineering 14 12-Sep-22 27-Sep-22 27-Sep-22, WPB-09-7-MTO.2 Engineering


A2790 Engineering 14 12-Sep-22 27-Sep-22 Engineering
WPB-09-7-MTO.3 Procurement 0

WPB-09-7-MTO.4 Construction 154 28-Sep-22 25-Mar-23 25-Mar-23, WPB-09-7-MTO.4 Construction

WPB-09-7-MTO.4.1 Mud Pit 129 28-Sep-22 24-Feb-23 24-Feb-23, WPB-09-7-MTO.4.1 Mud Pit
A2300 Mud Pit Start 0 28-Sep-22 Mud Pit Start, 28-Sep-22
A2310 Mud Pit Finish 0 24-Feb-23 Mud Pit Finish,
WPB-09-7-MTO.4.1.1 Earth Works 42 28-Sep-22 15-Nov-22 15-Nov-22, WPB-09-7-MTO.4.1.1 Earth Works
A1000 Excavation 39 28-Sep-22 11-Nov-22 Excavation
A1010 Soil Disposal 36 05-Oct-22 15-Nov-22 Soil Disposal
WPB-09-7-MTO.4.1.2 1400 m³ Pit 26 15-Nov-22 14-Dec-22 14-Dec-22, WPB-09-7-MTO.4.1.2 1400 m³ Pit
WPB-09-7-MTO.4.1.2.1 Pit 23 15-Nov-22 10-Dec-22 10-Dec-22, WPB-09-7-MTO.4.1.2.1 Pit
A1700 Selected Excavated Soil Filling 2 15-Nov-22 16-Nov-22 Selected Excavated Soil Filling
A1710 Compaction 3 16-Nov-22 18-Nov-22 Compaction
A1720 Liner Installation 12 28-Nov-22 10-Dec-22 Liner Installation
WPB-09-7-MTO.4.1.2.2 Bund Wall 9 19-Nov-22 29-Nov-22 29-Nov-22, WPB-09-7-MTO.4.1.2.2 Bund Wall
A1730 Geotextile Installation 6 19-Nov-22 25-Nov-22 Geotextile Installation
A1750 Soil and PC Mixing 6 21-Nov-22 26-Nov-22 Soil and PC Mixing
A1760 Soil Spreading 6 22-Nov-22 28-Nov-22 Soil Spreading
A1770 Compaction 4 25-Nov-22 29-Nov-22 Compaction
WPB-09-7-MTO.4.1.2.3 Anchor Trench 16 26-Nov-22 14-Dec-22 14-Dec-22, WPB-09-7-MTO.4.1.2.3 Anchor Trench
A1780 Excavation (Hand Excavation) 5 26-Nov-22 01-Dec-22 Excavation (Hand Excavation)
A1790 Soil and PC Mixing (Hand Mixing) 3 09-Dec-22 12-Dec-22 Soil and PC Mixing (Hand Mixing)
A1800 Soil Spreading (Hand Spreading) 3 10-Dec-22 13-Dec-22 Soil Spreading (Hand Spreading)
A1810 Compaction (Stamper) 3 12-Dec-22 14-Dec-22 Compaction (Stamper)
WPB-09-7-MTO.4.1.3 1000 m³ Pit 33 17-Nov-22 24-Dec-22 24-Dec-22, WPB-09-7-MTO.4.1.3 1000 m³ Pit
WPB-09-7-MTO.4.1.3.1 Pit 29 17-Nov-22 20-Dec-22 20-Dec-22, WPB-09-7-MTO.4.1.3.1 Pit
A1820 Selected Excavated Soil Filling 2 17-Nov-22 18-Nov-22 Selected Excavated Soil Filling
A1830 Compaction 3 19-Nov-22 22-Nov-22 Compaction
A1840 Liner Installation 8 12-Dec-22 20-Dec-22 Liner Installation
WPB-09-7-MTO.4.1.3.2 Bund Wall 8 26-Nov-22 05-Dec-22 05-Dec-22, WPB-09-7-MTO.4.1.3.2 Bund Wall
A1850 Geotextile Installation 5 26-Nov-22 01-Dec-22 Geotextile Installation
A1870 Soil and PC Mixing 4 29-Nov-22 02-Dec-22 Soil and PC Mixing
A1880 Soil Spreading 4 30-Nov-22 03-Dec-22 Soil Spreading
A1890 Compaction 3 02-Dec-22 05-Dec-22 Compaction
WPB-09-7-MTO.4.1.3.3 Anchor Trench 19 03-Dec-22 24-Dec-22 24-Dec-22, WPB-09-7-MTO.4.1.3.3 Anchor Trench
A1900 Excavation (Hand Excavation) 4 03-Dec-22 07-Dec-22 Excavation (Hand Excavation)
A1910 Soil and PC Mixing (Hand Mixing) 2 20-Dec-22 21-Dec-22 Soil and PC Mixing (Hand Mixing)
A1920 Soil Spreading (Hand Spreading) 2 21-Dec-22 22-Dec-22 Soil Spreading (Hand Spreading)
A1930 Compaction (Stamper) 3 22-Dec-22 24-Dec-22 Compaction (Stamper)

Actual Level of Effort Critical Remaining Work Page 1 of 6


Actual Work Milestone
Remaining Work summary
Civil Work at WellPad B
Activity ID Activity Name Original Start Finish 2023
Duration Nov
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
WPB-09-7-MTO.4.1.4 900 m³ Pit 37 19-Nov-22 31-Dec-22 31-Dec-22, WPB-09-7-MTO.4.1.4 900 m³ Pit
WPB-09-7-MTO.4.1.4.1 Pit 35 19-Nov-22 29-Dec-22 29-Dec-22, WPB-09-7-MTO.4.1.4.1 Pit
A1940 Selected Excavated Soil Filling 2 19-Nov-22 21-Nov-22 Selected Excavated Soil Filling
A1950 Compaction 2 23-Nov-22 24-Nov-22 Compaction
A1960 Liner Installation 8 21-Dec-22 29-Dec-22 Liner Installation
WPB-09-7-MTO.4.1.4.2 Bund Wall 6 02-Dec-22 08-Dec-22 08-Dec-22, WPB-09-7-MTO.4.1.4.2 Bund Wall
A1970 Geotextile Installation 4 02-Dec-22 06-Dec-22 Geotextile Installation
A1990 Soil and PC Mixing 4 03-Dec-22 07-Dec-22 Soil and PC Mixing
A2000 Soil Spreading 4 05-Dec-22 08-Dec-22 Soil Spreading
A2010 Compaction 3 06-Dec-22 08-Dec-22 Compaction
WPB-09-7-MTO.4.1.4.3 Anchor Trench 20 09-Dec-22 31-Dec-22 31-Dec-22, WPB-09-7-MTO.4.1.4.3 Anchor Trench
A2020 Excavation (Hand Excavation) 4 09-Dec-22 13-Dec-22 Excavation (Hand Excavation)
A2030 Soil and PC Mixing (Hand Mixing) 2 28-Dec-22 29-Dec-22 Soil and PC Mixing (Hand Mixing)
A2040 Soil Spreading (Hand Spreading) 2 29-Dec-22 30-Dec-22 Soil Spreading (Hand Spreading)
A2050 Compaction (Stamper) 2 30-Dec-22 31-Dec-22 Compaction (Stamper)
WPB-09-7-MTO.4.1.5 400 m³ Pit 40 22-Nov-22 06-Jan-23 06-Jan-23, WPB-09-7-MTO.4.1.5 400 m³ Pit
WPB-09-7-MTO.4.1.5.1 Pit 37 22-Nov-22 03-Jan-23 03-Jan-23, WPB-09-7-MTO.4.1.5.1 Pit
A2060 Selected Excavated Soil Filling 1 22-Nov-22 22-Nov-22 Selected Excavated Soil Filling
A2070 Compaction 1 25-Nov-22 25-Nov-22 Compaction
A2080 Liner Installation 4 30-Dec-22 03-Jan-23 Liner Installation
WPB-09-7-MTO.4.1.5.2 Bund Wall 5 07-Dec-22 12-Dec-22 12-Dec-22, WPB-09-7-MTO.4.1.5.2 Bund Wall
A2090 Geotextile Installation 2 07-Dec-22 08-Dec-22 Geotextile Installation
A2110 Soil and PC Mixing 2 08-Dec-22 09-Dec-22 Soil and PC Mixing
A2120 Soil Spreading 2 09-Dec-22 10-Dec-22 Soil Spreading
A2130 Compaction 1 12-Dec-22 12-Dec-22 Compaction
WPB-09-7-MTO.4.1.5.3 Anchor Trench 21 14-Dec-22 06-Jan-23 06-Jan-23, WPB-09-7-MTO.4.1.5.3 Anchor Trench
A2140 Excavation (Hand Excavation) 2 14-Dec-22 15-Dec-22 Excavation (Hand Excavation)
A2150 Soil and PC Mixing (Hand Mixing) 1 04-Jan-23 04-Jan-23 Soil and PC Mixing (Hand Mixing)
A2160 Soil Spreading (Hand Spreading) 1 05-Jan-23 05-Jan-23 Soil Spreading (Hand Spreading)
A2170 Compaction (Stamper) 1 06-Jan-23 06-Jan-23 Compaction (Stamper)
WPB-09-7-MTO.4.1.6 300 m³ Pit 42 23-Nov-22 10-Jan-23 10-Jan-23, WPB-09-7-MTO.4.1.6 300 m³ Pit
WPB-09-7-MTO.4.1.6.1 Pit 39 23-Nov-22 06-Jan-23 06-Jan-23, WPB-09-7-MTO.4.1.6.1 Pit
A2180 Selected Excavated Soil Filling 1 23-Nov-22 23-Nov-22 Selected Excavated Soil Filling
A2190 Compaction 1 26-Nov-22 26-Nov-22 Compaction
A2200 Liner Installation 3 04-Jan-23 06-Jan-23 Liner Installation
WPB-09-7-MTO.4.1.6.2 Bund Wall 5 09-Dec-22 14-Dec-22 14-Dec-22, WPB-09-7-MTO.4.1.6.2 Bund Wall
A2210 Geotextile Installation 2 09-Dec-22 10-Dec-22 Geotextile Installation
A2230 Soil and PC Mixing 1 12-Dec-22 12-Dec-22 Soil and PC Mixing
A2240 Soil Spreading 1 13-Dec-22 13-Dec-22 Soil Spreading
A2250 Compaction 1 14-Dec-22 14-Dec-22 Compaction
WPB-09-7-MTO.4.1.6.3 Anchor Trench 22 16-Dec-22 10-Jan-23 10-Jan-23, WPB-09-7-MTO.4.1.6.3 Anchor Trench
A2260 Excavation (Hand Excavation) 2 16-Dec-22 17-Dec-22 Excavation (Hand Excavation)
A2270 Soil and PC Mixing (Hand Mixing) 1 07-Jan-23 07-Jan-23 Soil and PC Mixing (Hand Mixing)
A2280 Soil Spreading (Hand Spreading) 1 09-Jan-23 09-Jan-23 Soil Spreading (Hand Spreading)
A2290 Compaction (Stamper) 1 10-Jan-23 10-Jan-23 Compaction (Stamper)
WPB-09-7-MTO.4.1.7 Safety Fence 59 19-Dec-22 24-Feb-23 24-Feb-23, WPB-09-7-MTO.4.1.7 Safety Fence
WPB-09-7-MTO.4.1.7.1 Earth Works 13 19-Dec-22 02-Jan-23 02-Jan-23, WPB-09-7-MTO.4.1.7.1 Earth Works

Actual Level of Effort Critical Remaining Work Page 2 of 6


Actual Work Milestone
Remaining Work summary
Civil Work at WellPad B
Activity ID Activity Name Original Start Finish 2023
Duration Nov
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A3040 Excavation (Hand Excavation) 12 19-Dec-22 31-Dec-22 Excavation (Hand Excavation)
A3050 Compaction (Stamper) 10 22-Dec-22 02-Jan-23 Compaction (Stamper)
WPB-09-7-MTO.4.1.7.2 Foundation 11 03-Jan-23 14-Jan-23 14-Jan-23, WPB-09-7-MTO.4.1.7.2 Foundation
A1620 Lean Concrete (Manual Mixing and Pouring) 1 03-Jan-23 03-Jan-23 Lean Concrete (Manual Mixing and Pouring)
A1630 Formwork 8 04-Jan-23 12-Jan-23 Formwork
A1640 Rebar 5 09-Jan-23 13-Jan-23 Rebar
A1650 Pouring Concrete (Manual Mixing and Pouring) 3 12-Jan-23 14-Jan-23 Pouring Concrete (Manual Mixing and Pouring)
WPB-09-7-MTO.4.1.7.3 Fence 47 28-Dec-22 20-Feb-23 20-Feb-23, WPB-09-7-MTO.4.1.7.3 Fence
A1660 Fence Fabrication 22 28-Dec-22 23-Jan-23 Fence Fabrication
A1670 Fence Installation 25 23-Jan-23 20-Feb-23 Fence Installation
WPB-09-7-MTO.4.1.7.4 Gravel 8 16-Feb-23 24-Feb-23 24-Feb-23, WPB-09-7-MTO.4.1.7.4 Gravel
A1680 Gravel Importing 7 16-Feb-23 23-Feb-23 Gravel Importing
A1690 Gravel Spreading 7 17-Feb-23 24-Feb-23 Gravel Spreading
WPB-09-7-MTO.4.2 Concrete Rig Pad 132 28-Sep-22 28-Feb-23 28-Feb-23, WPB-09-7-MTO.4.2 Concrete Rig Pad
A2430 Concrete Rig Pad Start 0 28-Sep-22 Concrete Rig Pad Start, 28-Sep-22
A2440 Concrete Rig Pad Finish 0 28-Feb-23 Concrete Rig Pad Finish,
WPB-09-7-MTO.4.2.1 Demolition Works 32 28-Sep-22 03-Nov-22 03-Nov-22, WPB-09-7-MTO.4.2.1 Demolition Works
A2320 Existing Rig Pad Demolition 31 28-Sep-22 02-Nov-22 Existing Rig Pad Demolition
A2330 Demolished Material Disposal 8 26-Oct-22 03-Nov-22 Demolished Material Disposal
WPB-09-7-MTO.4.2.2 Earth Works 7 02-Nov-22 09-Nov-22 09-Nov-22, WPB-09-7-MTO.4.2.2 Earth Works
A2340 Excavation 3 02-Nov-22 04-Nov-22 Excavation
A2350 Soil Disposal 5 03-Nov-22 08-Nov-22 Soil Disposal
A2610 Compaction 4 05-Nov-22 09-Nov-22 Compaction
WPB-09-7-MTO.4.2.3 Pilling Works 42 10-Nov-22 28-Dec-22 28-Dec-22, WPB-09-7-MTO.4.2.3 Pilling Works
A2360 Piling 40 10-Nov-22 26-Dec-22 Piling
A2370 Cutting Pile 9 17-Dec-22 27-Dec-22 Cutting Pile
A2380 Cutted Pile Disposal 9 19-Dec-22 28-Dec-22 Cutted Pile Disposal
WPB-09-7-MTO.4.2.4 Concrete Works 45 07-Jan-23 28-Feb-23 28-Feb-23, WPB-09-7-MTO.4.2.4 Concrete Works
WPB-09-7-MTO.4.2.4.1 Phase 1 24 07-Jan-23 03-Feb-23 03-Feb-23, WPB-09-7-MTO.4.2.4.1 Phase 1
A2390 Lean Concrete 1 07-Jan-23 07-Jan-23 Lean Concrete
A2400 Formwork 5 09-Jan-23 13-Jan-23 Formwork
A2410 Rebar 21 10-Jan-23 02-Feb-23 Rebar
A2420 Pouring Concrete 7 27-Jan-23 03-Feb-23 Pouring Concrete
WPB-09-7-MTO.4.2.4.2 Phase 2 44 09-Jan-23 28-Feb-23 28-Feb-23, WPB-09-7-MTO.4.2.4.2 Phase 2
A3560 Lean Concrete 1 09-Jan-23 09-Jan-23 Lean Concrete
A3570 Formwork 5 31-Jan-23 04-Feb-23 Formwork
A3580 Rebar 21 03-Feb-23 27-Feb-23 Rebar
A3590 Pouring Concrete 7 21-Feb-23 28-Feb-23 Pouring Concrete
WPB-09-7-MTO.4.2.4.3 Phase 3 24 07-Jan-23 03-Feb-23 03-Feb-23, WPB-09-7-MTO.4.2.4.3 Phase 3
A3600 Lean Concrete 1 07-Jan-23 07-Jan-23 Lean Concrete
A3610 Formwork 5 09-Jan-23 13-Jan-23 Formwork
A3620 Rebar 21 10-Jan-23 02-Feb-23 Rebar
A3630 Pouring Concrete 7 27-Jan-23 03-Feb-23 Pouring Concrete
WPB-09-7-MTO.4.2.4.4 Phase 4 44 09-Jan-23 28-Feb-23 28-Feb-23, WPB-09-7-MTO.4.2.4.4 Phase 4
A3640 Lean Concrete 1 09-Jan-23 09-Jan-23 Lean Concrete
A3650 Formwork 5 31-Jan-23 04-Feb-23 Formwork
A3660 Rebar 21 03-Feb-23 27-Feb-23 Rebar

Actual Level of Effort Critical Remaining Work Page 3 of 6


Actual Work Milestone
Remaining Work summary
Civil Work at WellPad B
Activity ID Activity Name Original Start Finish 2023
Duration Nov
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A3670 Pouring Concrete 7 21-Feb-23 28-Feb-23 Pouring Concrete
WPB-09-7-MTO.4.2.4.5 Phase 5 24 07-Jan-23 03-Feb-23 03-Feb-23, WPB-09-7-MTO.4.2.4.5 Phase 5
A3680 Lean Concrete 1 07-Jan-23 07-Jan-23 Lean Concrete
A3690 Formwork 5 09-Jan-23 13-Jan-23 Formwork
A3700 Rebar 21 10-Jan-23 02-Feb-23 Rebar
A3710 Pouring Concrete 7 27-Jan-23 03-Feb-23 Pouring Concrete
WPB-09-7-MTO.4.3 Culvert and Pipe Trench 119 08-Nov-22 25-Mar-23 25-Mar-23, WPB-09-7-MTO.4.3 Culvert and Pipe Trench
A2760 Culvert and Pipe Trench Start 0 08-Nov-22 Culvert and Pipe Trench Start, 08-Nov-22
A2770 Culvert and Pipe Trench Finish 0 25-Mar-23 Culvert and Pipe Trench Finish,
WPB-09-7-MTO.4.3.1 Culvert and Pipe Trench 1 117 08-Nov-22 23-Mar-23 23-Mar-23, WPB-09-7-MTO.4.3.1 Culvert and Pipe Trench 1
WPB-09-7-MTO.4.3.1.1 Earth Works 6 08-Nov-22 14-Nov-22 14-Nov-22, WPB-09-7-MTO.4.3.1.1 Earth Works
A2620 Excavation 3 08-Nov-22 10-Nov-22 Excavation
A2630 Soil Disposal 4 09-Nov-22 12-Nov-22 Soil Disposal
A2750 Compaction 2 12-Nov-22 14-Nov-22 Compaction
WPB-09-7-MTO.4.3.1.2 Concrete Works 61 09-Jan-23 20-Mar-23 20-Mar-23, WPB-09-7-MTO.4.3.1.2 Concrete Works
WPB-09-7-MTO.4.3.1.2.1 Slab 48 09-Jan-23 04-Mar-23 04-Mar-23, WPB-09-7-MTO.4.3.1.2.1 Slab
A2640 Lean Concrete 1 09-Jan-23 09-Jan-23 Lean Concrete
A2650 Formwork 7 06-Feb-23 13-Feb-23 Formwork
A2660 Rebar 18 10-Feb-23 02-Mar-23 Rebar
A2670 Water Stop 3 01-Mar-23 03-Mar-23 Water Stop
A2680 Pouring Concrete 3 02-Mar-23 04-Mar-23 Pouring Concrete
WPB-09-7-MTO.4.3.1.2.2 Wall 34 09-Feb-23 20-Mar-23 20-Mar-23, WPB-09-7-MTO.4.3.1.2.2 Wall
A2690 Formwork 13 14-Feb-23 28-Feb-23 Formwork
A2700 Rebar 24 14-Feb-23 13-Mar-23 Rebar
A2705 Grating Support Fabrication 27 09-Feb-23 13-Mar-23 Grating Support Fabrication
A2710 Grating Support Installation 2 13-Mar-23 14-Mar-23 Grating Support Installation
A2720 Pouring Concrete 6 14-Mar-23 20-Mar-23 Pouring Concrete
WPB-09-7-MTO.4.3.1.3 Grating 31 16-Feb-23 23-Mar-23 23-Mar-23, WPB-09-7-MTO.4.3.1.3 Grating
A2730 Grating Fabrication 28 16-Feb-23 21-Mar-23 Grating Fabrication
A2740 Grating Installation 3 21-Mar-23 23-Mar-23 Grating Installation
WPB-09-7-MTO.4.3.2 Culvert and Pipe Trench 2 116 11-Nov-22 25-Mar-23 25-Mar-23, WPB-09-7-MTO.4.3.2 Culvert and Pipe Trench 2
WPB-09-7-MTO.4.3.2.1 Earth Works 7 11-Nov-22 18-Nov-22 18-Nov-22, WPB-09-7-MTO.4.3.2.1 Earth Works
A3720 Excavation 3 11-Nov-22 14-Nov-22 Excavation
A3730 Soil Disposal 4 14-Nov-22 17-Nov-22 Soil Disposal
A3850 Compaction 2 17-Nov-22 18-Nov-22 Compaction
WPB-09-7-MTO.4.3.2.2 Concrete Works 62 10-Jan-23 22-Mar-23 22-Mar-23, WPB-09-7-MTO.4.3.2.2 Concrete Works
WPB-09-7-MTO.4.3.2.2.1 Slab 49 10-Jan-23 07-Mar-23 07-Mar-23, WPB-09-7-MTO.4.3.2.2.1 Slab
A3740 Lean Concrete 1 10-Jan-23 10-Jan-23 Lean Concrete
A3750 Formwork 7 14-Feb-23 21-Feb-23 Formwork
A3760 Rebar 18 13-Feb-23 04-Mar-23 Rebar
A3770 Water Stop 3 03-Mar-23 06-Mar-23 Water Stop
A3780 Pouring Concrete 3 04-Mar-23 07-Mar-23 Pouring Concrete
WPB-09-7-MTO.4.3.2.2.2 Wall 34 11-Feb-23 22-Mar-23 22-Mar-23, WPB-09-7-MTO.4.3.2.2.2 Wall
A3790 Formwork 13 22-Feb-23 08-Mar-23 Formwork
A3800 Rebar 24 16-Feb-23 15-Mar-23 Rebar
A3805 Grating Support Fabrication 27 11-Feb-23 15-Mar-23 Grating Support Fabrication
A3810 Grating Support Installation 2 15-Mar-23 16-Mar-23 Grating Support Installation

Actual Level of Effort Critical Remaining Work Page 4 of 6


Actual Work Milestone
Remaining Work summary
Civil Work at WellPad B
Activity ID Activity Name Original Start Finish 2023
Duration Nov
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A3820 Pouring Concrete 6 16-Mar-23 22-Mar-23 Pouring Concrete
WPB-09-7-MTO.4.3.2.3 Grating 31 18-Feb-23 25-Mar-23 25-Mar-23, WPB-09-7-MTO.4.3.2.3 Grating
A3830 Grating Fabrication 28 18-Feb-23 23-Mar-23 Grating Fabrication
A3840 Grating Installation 3 23-Mar-23 25-Mar-23 Grating Installation
WPB-09-7-MTO.4.4 Well Cellar 112 05-Nov-22 15-Mar-23 15-Mar-23, WPB-09-7-MTO.4.4 Well Cellar
A2940 Well Cellar Start 0 05-Nov-22 Well Cellar Start, 05-Nov-22
A2950 Well Cellar Finish 0 15-Mar-23 Well Cellar Finish,
WPB-09-7-MTO.4.4.1 Well Cellar 1 111 05-Nov-22 14-Mar-23 14-Mar-23, WPB-09-7-MTO.4.4.1 Well Cellar 1
WPB-09-7-MTO.4.4.1.1 Conductor Pipe 1 14-Mar-23 14-Mar-23 14-Mar-23, WPB-09-7-MTO.4.4.1.1 Conductor Pipe
A2930 Conductor Pipe Driving 1 14-Mar-23 14-Mar-23 Conductor Pipe Driving
WPB-09-7-MTO.4.4.1.2 Sheet Pile Works 0
WPB-09-7-MTO.4.4.1.3 Shoring Protection 6 23-Dec-22 29-Dec-22 29-Dec-22, WPB-09-7-MTO.4.4.1.3 Shoring Protection
A3380 Brickwall Installation 6 23-Dec-22 29-Dec-22 Brickwall Installation
WPB-09-7-MTO.4.4.1.4 Earth Works 6 05-Nov-22 11-Nov-22 11-Nov-22, WPB-09-7-MTO.4.4.1.4 Earth Works
A3200 Excavation 1 05-Nov-22 05-Nov-22 Excavation
A3210 Soil Disposal 1 09-Nov-22 09-Nov-22 Soil Disposal
A3220 Compaction 2 10-Nov-22 11-Nov-22 Compaction
WPB-09-7-MTO.4.4.1.5 Concrete Works 27 20-Dec-22 19-Jan-23 19-Jan-23, WPB-09-7-MTO.4.4.1.5 Concrete Works
WPB-09-7-MTO.4.4.1.5.1 Slab 8 30-Dec-22 07-Jan-23 07-Jan-23, WPB-09-7-MTO.4.4.1.5.1 Slab
A2820 Lean Concrete 1 30-Dec-22 30-Dec-22 Lean Concrete
A2830 Formwork 3 02-Jan-23 04-Jan-23 Formwork
A2840 Rebar 2 04-Jan-23 05-Jan-23 Rebar
A2850 Water Stop 1 06-Jan-23 06-Jan-23 Water Stop
A2860 Pouring Concrete 1 07-Jan-23 07-Jan-23 Pouring Concrete
WPB-09-7-MTO.4.4.1.5.2 Wall 27 20-Dec-22 19-Jan-23 19-Jan-23, WPB-09-7-MTO.4.4.1.5.2 Wall
A2865 Scaffolding 6 09-Jan-23 14-Jan-23 Scaffolding
A2870 Formwork 3 13-Jan-23 16-Jan-23 Formwork
A2880 Rebar 3 14-Jan-23 17-Jan-23 Rebar
A2885 Grating Support Fabrication 24 20-Dec-22 17-Jan-23 Grating Support Fabrication
A2890 Grating Support Installation 2 17-Jan-23 18-Jan-23 Grating Support Installation
A2900 Pouring Concrete 2 18-Jan-23 19-Jan-23 Pouring Concrete
WPB-09-7-MTO.4.4.1.6 Grating 30 19-Dec-22 21-Jan-23 21-Jan-23, WPB-09-7-MTO.4.4.1.6 Grating
A2910 Grating Fabrication 28 19-Dec-22 20-Jan-23 Grating Fabrication
A2920 Grating Installation 2 20-Jan-23 21-Jan-23 Grating Installation
WPB-09-7-MTO.4.4.2 Well Cellar 2 111 07-Nov-22 15-Mar-23 15-Mar-23, WPB-09-7-MTO.4.4.2 Well Cellar 2
WPB-09-7-MTO.4.4.2.1 Conductor Pipe 1 15-Mar-23 15-Mar-23 15-Mar-23, WPB-09-7-MTO.4.4.2.1 Conductor Pipe
A3500 Conductor Pipe Driving 1 15-Mar-23 15-Mar-23 Conductor Pipe Driving
WPB-09-7-MTO.4.4.2.2 Sheet Pile Works 0
WPB-09-7-MTO.4.4.2.3 Shoring Protection 6 30-Dec-22 05-Jan-23 05-Jan-23, WPB-09-7-MTO.4.4.2.3 Shoring Protection
A3540 Brickwall Installation 6 30-Dec-22 05-Jan-23 Brickwall Installation
WPB-09-7-MTO.4.4.2.4 Earth Works 7 07-Nov-22 14-Nov-22 14-Nov-22, WPB-09-7-MTO.4.4.2.4 Earth Works
A3510 Excavation 1 07-Nov-22 07-Nov-22 Excavation
A3520 Soil Disposal 1 10-Nov-22 10-Nov-22 Soil Disposal
A3530 Compaction 2 12-Nov-22 14-Nov-22 Compaction
WPB-09-7-MTO.4.4.2.5 Concrete Works 27 27-Dec-22 26-Jan-23 26-Jan-23, WPB-09-7-MTO.4.4.2.5 Concrete Works
WPB-09-7-MTO.4.4.2.5.1 Slab 8 06-Jan-23 14-Jan-23 14-Jan-23, WPB-09-7-MTO.4.4.2.5.1 Slab
A3390 Lean Concrete 1 06-Jan-23 06-Jan-23 Lean Concrete

Actual Level of Effort Critical Remaining Work Page 5 of 6


Actual Work Milestone
Remaining Work summary
Civil Work at WellPad B
Activity ID Activity Name Original Start Finish 2023
Duration Nov
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A3400 Formwork 3 09-Jan-23 11-Jan-23 Formwork
A3410 Rebar 2 11-Jan-23 12-Jan-23 Rebar
A3420 Water Stop 1 13-Jan-23 13-Jan-23 Water Stop
A3430 Pouring Concrete 1 14-Jan-23 14-Jan-23 Pouring Concrete
WPB-09-7-MTO.4.4.2.5.2 Wall 27 27-Dec-22 26-Jan-23 26-Jan-23, WPB-09-7-MTO.4.4.2.5.2 Wall
A3435 Scaffolding 6 16-Jan-23 21-Jan-23 Scaffolding
A3440 Formwork 3 20-Jan-23 23-Jan-23 Formwork
A3450 Rebar 3 21-Jan-23 24-Jan-23 Rebar
A3455 Grating Support Fabrication 24 27-Dec-22 24-Jan-23 Grating Support Fabrication
A3460 Grating Support Installation 2 24-Jan-23 25-Jan-23 Grating Support Installation
A3470 Pouring Concrete 2 25-Jan-23 26-Jan-23 Pouring Concrete
WPB-09-7-MTO.4.4.2.6 Grating 30 26-Dec-22 28-Jan-23 28-Jan-23, WPB-09-7-MTO.4.4.2.6 Grating
A3480 Grating Fabrication 28 26-Dec-22 27-Jan-23 Grating Fabrication
A3490 Grating Installation 2 27-Jan-23 28-Jan-23 Grating Installation
WPB-09-7-MTO.5 PSSR, Closing Punch List, & Reinstatement/Housekeeping 39 25-Feb-23 11-Apr-23 11-Apr-23, WPB-09-7-MTO.5 PSSR, Closing Punch List, & Reinstatement/Housek
A2980 Mud Pit 14 25-Feb-23 13-Mar-23 Mud Pit
A2990 Concrete Rig Pad 14 01-Mar-23 16-Mar-23 Concrete Rig Pad
A3000 Culvert and Pipe Trench 14 27-Mar-23 11-Apr-23 Culvert and Pipe Trench
A3010 Well Cellar 14 16-Mar-23 31-Mar-23 Well Cellar
A3020 Conductor Pipe 14 16-Mar-23 31-Mar-23 Conductor Pipe

Actual Level of Effort Critical Remaining Work Page 6 of 6