Civil Work at WellPad B - Construction Schedule
Civil Work at WellPad B - Construction Schedule
Civil Work at WellPad B - Construction Schedule
WPB-09-7-MTO.4.1 Mud Pit 129 28-Sep-22 24-Feb-23 24-Feb-23, WPB-09-7-MTO.4.1 Mud Pit
A2300 Mud Pit Start 0 28-Sep-22 Mud Pit Start, 28-Sep-22
A2310 Mud Pit Finish 0 24-Feb-23 Mud Pit Finish,
WPB-09-7-MTO.4.1.1 Earth Works 42 28-Sep-22 15-Nov-22 15-Nov-22, WPB-09-7-MTO.4.1.1 Earth Works
A1000 Excavation 39 28-Sep-22 11-Nov-22 Excavation
A1010 Soil Disposal 36 05-Oct-22 15-Nov-22 Soil Disposal
WPB-09-7-MTO.4.1.2 1400 m³ Pit 26 15-Nov-22 14-Dec-22 14-Dec-22, WPB-09-7-MTO.4.1.2 1400 m³ Pit
WPB-09-7-MTO.4.1.2.1 Pit 23 15-Nov-22 10-Dec-22 10-Dec-22, WPB-09-7-MTO.4.1.2.1 Pit
A1700 Selected Excavated Soil Filling 2 15-Nov-22 16-Nov-22 Selected Excavated Soil Filling
A1710 Compaction 3 16-Nov-22 18-Nov-22 Compaction
A1720 Liner Installation 12 28-Nov-22 10-Dec-22 Liner Installation
WPB-09-7-MTO.4.1.2.2 Bund Wall 9 19-Nov-22 29-Nov-22 29-Nov-22, WPB-09-7-MTO.4.1.2.2 Bund Wall
A1730 Geotextile Installation 6 19-Nov-22 25-Nov-22 Geotextile Installation
A1750 Soil and PC Mixing 6 21-Nov-22 26-Nov-22 Soil and PC Mixing
A1760 Soil Spreading 6 22-Nov-22 28-Nov-22 Soil Spreading
A1770 Compaction 4 25-Nov-22 29-Nov-22 Compaction
WPB-09-7-MTO.4.1.2.3 Anchor Trench 16 26-Nov-22 14-Dec-22 14-Dec-22, WPB-09-7-MTO.4.1.2.3 Anchor Trench
A1780 Excavation (Hand Excavation) 5 26-Nov-22 01-Dec-22 Excavation (Hand Excavation)
A1790 Soil and PC Mixing (Hand Mixing) 3 09-Dec-22 12-Dec-22 Soil and PC Mixing (Hand Mixing)
A1800 Soil Spreading (Hand Spreading) 3 10-Dec-22 13-Dec-22 Soil Spreading (Hand Spreading)
A1810 Compaction (Stamper) 3 12-Dec-22 14-Dec-22 Compaction (Stamper)
WPB-09-7-MTO.4.1.3 1000 m³ Pit 33 17-Nov-22 24-Dec-22 24-Dec-22, WPB-09-7-MTO.4.1.3 1000 m³ Pit
WPB-09-7-MTO.4.1.3.1 Pit 29 17-Nov-22 20-Dec-22 20-Dec-22, WPB-09-7-MTO.4.1.3.1 Pit
A1820 Selected Excavated Soil Filling 2 17-Nov-22 18-Nov-22 Selected Excavated Soil Filling
A1830 Compaction 3 19-Nov-22 22-Nov-22 Compaction
A1840 Liner Installation 8 12-Dec-22 20-Dec-22 Liner Installation
WPB-09-7-MTO.4.1.3.2 Bund Wall 8 26-Nov-22 05-Dec-22 05-Dec-22, WPB-09-7-MTO.4.1.3.2 Bund Wall
A1850 Geotextile Installation 5 26-Nov-22 01-Dec-22 Geotextile Installation
A1870 Soil and PC Mixing 4 29-Nov-22 02-Dec-22 Soil and PC Mixing
A1880 Soil Spreading 4 30-Nov-22 03-Dec-22 Soil Spreading
A1890 Compaction 3 02-Dec-22 05-Dec-22 Compaction
WPB-09-7-MTO.4.1.3.3 Anchor Trench 19 03-Dec-22 24-Dec-22 24-Dec-22, WPB-09-7-MTO.4.1.3.3 Anchor Trench
A1900 Excavation (Hand Excavation) 4 03-Dec-22 07-Dec-22 Excavation (Hand Excavation)
A1910 Soil and PC Mixing (Hand Mixing) 2 20-Dec-22 21-Dec-22 Soil and PC Mixing (Hand Mixing)
A1920 Soil Spreading (Hand Spreading) 2 21-Dec-22 22-Dec-22 Soil Spreading (Hand Spreading)
A1930 Compaction (Stamper) 3 22-Dec-22 24-Dec-22 Compaction (Stamper)