EIA
EIA
EIA
Essential Elements
•Identification of possible positive or negative impacts of the project.
•Quantifying impacts with respect to common base.
•Preparation of mitigation plan to offset the negative impacts.
Who prepares an EIA?
• Screening
• Scoping
• Impact mitigation
• EIS preparation
Step 1:-Identifying and Defining the Project or
Activity:
7
Step 2:-Screening
To determine whether or not a proposal should be subject to EIA
Screening is done to see whether a project requires environmental
clearance as per the statutory notification. Screening Criteria are
based upon:
Scales of investment;
Type of development; and,
Location of development.
8
List of Environmentally Sensitive Places
Scenic areas
Health resorts
9
List of Environmentally Sensitive Places
Gulf areas
Biosphere reserves
10
List of Environmentally Sensitive Places
Airport
11
List of Environmentally Sensitive Places
Railway lines
Highways
Urban agglomeration
12
Screening
13
14
15
16
List of projects requiring environmental clearance from the Central Government
6. Pesticides (Technical).
17
List of projects requiring environmental clearance from the
Central Government
18
List of projects requiring environmental clearance from the
Central Government
19
List of projects requiring environmental clearance from the
Central Government
18. All tourism projects between 200m-500 metres of High Water Line
and at locations with an elevation of more than 1000 metres with
investment of more than Rs. 5 crores.
20
List of projects requiring environmental clearance from the
Central Government
23. Distilleries.
26. Dyes.
27. Cement.
29. Electroplating.
21
30. Meta amino phenol.
Step 3:-Scoping
• Scoping is a very key stage of the EIA process in which those impacts
which might have significant effect on the environment, to be
addressed in the EIA, are determined.
24
• Make the information available to those whose views are to be
obtained.
❖ The ToR should give an indication of the team considered necessary for
the study and a team leader identified. Depending on the scope of the
study this may be multi- disciplinary. However, as the team should not be
rigidly imposed on the consultant.
❖ The expected date of commencement and time limit should be given and
consultants program of work must be within the given time limit.
28
❖ The budget limit should be given in the ToR. Any assistance to be
provided by the Client to reduce costs should be clearly stated in the ToR.
❖ ToR should make provision for the consultants to improve the terms of
reference in order to improve the quality of EIA.
29
Step 4:-Baseline Data collection
Baseline data described the existing environmental status of the identified
study area. The site-specific primary data should be monitored for the
identified parameters and supplemented by secondary data if available.
Expected Outcome:
Assessment of existing environmental conditions and social settings in
the project area
30
Coverage of baseline data
31
Step 5:-Impact Prediction
Air
Noise
Water
Land
Socio-Economic
32
LAND
Slope stability
Floodplains / swamps
Land use
Soil erosion
Shoreline
Bottom interface
Water balance
Flooding
Siltation
35
GROUND WATER POTENTIAL
Water table
Flow regime
Water quality
Recharge rate
Aquifer characteristic
Visibility Duration
Meteorology Frequency
37
SPECIES AND POPULATION HABITATS AND COMMUNITIES
38
HEALTH AND SAFETY
SOCIO-ECONOMIC
Occupational Housing
Community health
Disease Vectors
39
AESTHETIC \ CULTURAL
Landscape
Wilderness
Climate
Community structure
40
Step 6:-Impact Mitigation
Mitigation
The implementation of measures designed to reduce the undesirable
effects of a proposed action on the environment.Negative impacts on the
environment identified during the EIA can be alleviated through mitigation
measures
The objectives of mitigation are to:
•find better alternatives and ways of doing things;
•enhance the environmental and social benefits of a project
•avoid, minimise or remedy adverse impacts; and
•ensure that residual adverse impacts are kept within acceptable levels
41
Types of Mitigation In EIA :
1. The source of the effect (for instance, noise emitting equipment, a
toxicant, a tall structure);
2. The receptor (that is, the environmental entity likely to be adversely
affected); and
3. The pathway (the route by which a receptor could be exposed to
the effect)
Adverse effect can only occur when all three components are
simultaneously present in the Surrounding environment.
42
Mitigation hierarchy
43
Step 7:-Public Hearing
•Local associations
44
Step 8:-EIS preparation
45
A typical EIS contains the following three parts:
Part 1 – Methods and key issues: This part deals with the statement of
methods used and a summary of key issues.
Part 2 – Background to the proposed development: This part deals with
preliminary studies (i.e., need, planning, alternatives, site selection, etc.), site
description/baseline conditions, description of proposed development and
construction activities and programmes.
Part 3 – Environmental impact assessments on topic areas: This part deals
with land use, landscape and visual quality, geology, topography and soils,
hydrology and water quality, air quality and climate, terrestrial and aquatic
ecology, noise, transport, socio-economic and interrelationships between
effects.
46
OUTLINE FOR CATEGORY A REPORT
47
Step 9:-Review
48
Step 10:-Decision making
groups if necessary)
49
Step 11:-Monitoring the Clearance Condition
• This is not only to ensure that the commitments made on reports were
correct or not. Where the impact exceed the predicated levels,
corrective action should be taken.
50
Participants in the EIA Process
The Public
51
Dimension of environment in EIA
52
Summary of EIA process and
Rough Timelines Who does it?
State Pollution
45 days Stage 3: Public consultation (2 components) Control Board
Update EIA report (Investor)
Expert
60 days Stage 4: Appraisal
Committee
15 days
Regulatory
30 days Final Decision Authority 53