Cable Sheath Bonding Application Guide
Cable Sheath Bonding Application Guide
Cable Sheath Bonding Application Guide
CABLE
SHEATH
BONDING
NZCCPTS
Issue 1
September 1999
Reprinted January 2021
The New Zealand Committee for the Co-ordination of Power
and Telecommunication Systems Inc. (NZCCPTS)
The New Zealand Committee for the Co-ordination of Power and Telecommunication
Systems was established in 1985 following the increasing need to implement efficient
cost-effective measures for the limitation of hazard and interference to power and
Telecommunications Systems and Personnel.
Such measures not only require the determination of optimum engineering solutions
consistent with minimum national cost, but also necessitate clear guide-lines covering
the equitable allocation of responsibilities during all work phases from planning
through to in-service operation.
The objective of the New Zealand Committee for the Co-ordination of power and
Telecommunication Systems is to meet these needs and, by means of publications
and seminars, promote a greater awareness and understanding of the action that
must be taken to ensure that Power and Telecommunication Systems coexist
satisfactorily.
For further information concerning this Committee and its published guides, contact
the Secretary of NZCCPTS via email to secretary@nzccpts.co.nz, or via his contact
details on the ‘Contact Us’ page of the NZCCPTS website (www.nzccpts.co.nz).
APPLICATION GUIDE
FOR
for the control of earth potential rise and for the limitation
of hazardous induction into telecommunication circuits
Issue 1
September 1999
ISBN 0-473-05988-6
Foreword
This guide sets out the technical issues and implications for nearby
telecommunication network plant of various cable sheath bonding
arrangements for high voltage power cables between substations.
Acknowledgements
Comments for revision of this guide are welcomed. Any comments or information
that may be useful for inclusion in this guide should be forwarded to the Secretary of
NZCCPTS via email to secretary@nzccpts.co.nz, or via his contact details on the
‘Contact Us’ page of the NZCCPTS website (www.nzccpts.co.nz).
A brief description of the objectives and organization of the New Zealand Committee
for the Co-ordination of Power and Telecommunication Systems Inc. is printed inside
the back cover of this publication.
Contents
Page
1.0 Introduction 1
1.1 Scope 1
1.2 Definition of Terms 2
1.3 Background 2
2.0 Outline of Cable Sheath Bonding Systems 4
2.1 Solidly Bonded System 4
2.2 End-Point Bonded System 5
2.3 Mid-Point Bonded System 6
2.4 Cross-Bonded System 6
2.5 Cable Sheath Insulation 6
3.0 Electrical Interference on Nearby Telecommunication 8
Network Plant
3.1 Interference Mechanisms 8
3.2 Legislative Requirements 8
3.3 Typical Effects of Cable Sheath Bonding on Electrical 9
Interference on Nearby Telecommunication Network Plant
3.4 Maximum Short Circuit Power, Current, and Fault 9
Clearance Times
4.0 Summary of Impact of Cable Sheath Bonding 11
4.1 Impact on Telecommunication Network Operator’s Network 14
4.2 Impact on Power Network 15
5.0 Advantages and Disadvantages of Cable Sheath 16
Bonding
5.1 Advantages of Cable Sheath Bonding 16
5.2 Disadvantages of Cable Sheath Bonding 16
5.3 Typical Consequences of Cable Sheath Bonding 17
• POD and zone substation earth mats
• zone and distribution substation earth mats
• POD and zone and distribution substation earth mats
5.4 An Example of Cable Sheath Bonding Showing Clear 19
Advantages
6.0 Calculation of EPR and TEPR for Earth Mats 20
Connected Together Via Bonded Cable Sheaths
6.1 Calculation Process for Cable Sheath Bonding 20
6.2 Computer Modelling 35
6.3 Companion Document for Application Guide 36
7.0 Typical Network Configurations Involving Insulated 37
Cables
8.0 Summary 38
9.0 References 39
1.0 Introduction
Techniques now exist for modelling earthing systems with cable sheaths
bonded at either end or both ends, or at cable mid-points. However, for some
situations, the implications of various bonding arrangements may be
determined without the need for detailed modelling studies.
This guide forms part of a series of guides, each one dealing with a particular
aspect of inter-action between power and telecommunication systems.
References to other guides are included in Section 9.0.
1.1 Scope
This guide describes the conditions to be met in power systems that use
insulated cables to interconnect various parts of those systems
and
outlines the factors that should be considered when determining the cable
sheath bonding arrangements at each end of the cable.
2
Distribution Substation
A substation within the distribution network that provides 400/230V output.
Earth Potential
The actual voltage of the earth with respect to remote earth.
Remote Earth
A body of earth sufficiently free of any influence from the HV Stations of
interest or the distribution network under consideration because it is
sufficiently far away from any material resistively connected to those HV
Stations (generally 1 km+), and outside of their electro-magnetic influence (3
km+).
Zone Substation
A substation embedded within a distribution network and that transforms
voltage levels to not less than 6.6kV.
1.3 Background
Early practice appears to have been to simply bond cable sheaths to earth at
both ends to distribute fault current as widely as possible in the earthing
systems.
3
About 1970, concerns were raised in New Zealand over the possible
implications of exporting earth potential rises under fault conditions via cable
sheaths from high voltage transmission substations to lower voltage
distribution substations. At that time, the main concern was with possible
hazards to personnel and equipment at the distribution site. For some time
after 1970, many installations were completed with cable sheaths bonded to
earth at one end only and insulated at the other end.
This system of bonding involves solidly bonding the cable sheath at both ends
to the relevant earth mats. It is very suitable for distribution networks at 11kV
and 33kV, particularly where 3 core lead sheath cables are installed. Sheaths
solidly bonded at both ends of circuits made up of single core or multicore
power cables, will result in circulating currents that are produced in the
sheaths by the magnetic flux linking the conductors and the sheaths. If single
phase cables are laid in close trefoil formation, the sheath circulating currents
can be as high as 40% of the load current. The figure below shows the sheath
circulating current as a percentage of the load current, versus the separation
between the cores of the three single phase cables in a three phase circuit.
The sheath currents are also a function of the sheath resistance. As the
sheath resistance increases, the circulating current decreases. Due to internal
transposition of cores in three core cables, they usually have no significant
sheath circulating currents.
5
Close trefoil formation of single-phase cables affects the load rating of the
cables, because of the heating effect of the cables on each other. However,
de-rating as a consequence of installation in trefoil formation is seldom a
significant issue in distribution systems because it is usually more economic to
use cables of standard manufacturing sizes; these often have a rating
substantially in excess of the maximum required.
This system of bonding involves earthing the cable sheaths at one termination
and insulating the cable sheaths from ground at the other end. In single phase
cable systems, the magnetic flux linking the conductors and the sheaths will
result in a standing 50Hz voltage between the sheaths and the ground at the
insulated end. For cable lengths of over 0.5 km, it may be necessary to use
cables with a higher sheath insulation level than normally provided, or else
provide sheath voltage limiting protectors. Where short lengths of cables are
used between overhead line terminations and substations, it may be more
economic to directly connect the line terminal earth mat (to which the cable
sheath would normally be bonded), to the substation earth mat via a separate
suitably rated conductor to avoid expensive cable requirements. Section 7.0
provides further detail on short cables for overhead line terminations.
End point bonding at the remote end away from the substation can avoid the
export of EPR. However, the implications of this arrangement need careful
consideration.
6
In this system, the cable is earthed midway along the cable route, and both
ends of the cable are insulated from ground. The mid point bonded system
effectively doubles the length of cable that can be installed without requiring
either a higher level of sheath insulation or sheath voltage limiting protectors.
The route length is divided into a number of minor sections, with this number
being a multiple of 3. The sheaths are insulated from ground at the cross
bond joints between each minor section. At each set of minor section joints,
the sheaths are cross connected between cables of different phases so that
the standing voltages on the sheaths of 3 minor sections in series comprise 3
vectors 120° apart, which sum to zero voltage.
The cable sheaths are bonded to earth at both cable ends, and also at every
third set of joints (at the end of major sections). Sheath voltage limiters are
installed at all other minor section cross bond joint positions, or alternatively a
higher rated (and more expensive) sheath/screen insulation can be provided.
For cables longer than 1 km, or with sheaths that are not rated for high fault
currents, the impedance of the cable sheaths is often substantially greater
than the earth mat resistances, and this limits the fault current (and hence
TEPR) transferred through the sheaths between the delivery and receiving
stations' earth mats. Long, high MVA capacity 110 kV and 220 kV cables,
necessitating the use of single core cables, are good examples of this.
Metallic sheaths are essential for paper insulated cables to exclude moisture
from the insulation. Extruded insulation cables (XLPE etc) are usually
manufactured with copper wire screens over the outer semi-conducting
insulation layer for use at 11kV and 33kV, while metallic sheaths are mainly
specified for cables at 66kV and above. A metallic sheath/screen also
reduces the electric field (but not the magnetic field) around the cable to zero
at the outer surface of the cable insulation when the sheath is bonded to earth.
The layers surrounding the sheath are primarily to protect the metallic
sheath/screen against damage or corrosion. Any puncture of the sheath will
eventually allow moisture to penetrate the insulation and consequently lead to
insulation failure. While moisture can lead to corrosion of screens (aluminum
being more susceptible), damage to XLPE insulation may take many years to
arise.
Because the materials that are normally used for sheath protection do not
provide high quality electrical insulation, they in turn need to be protected
against transient and steady state voltages of magnitudes that may puncture
the sheath protection and thereby allow corrosion of the sheath to proceed. In
the UK, the standard practice is to limit the standing sheath voltage on cable
sheaths, relative to ground, to 65V and to protect against sheath damage by
installing sheath voltage limiters between sheath and earth wherever cable
sheaths are not able to be bonded to earth to prevent such sheath voltages
occurring. In long submarine power cables, the cable sheath is bonded to the
external armouring at intervals along the length of the cable; the intervals are
chosen to ensure that the cable sheath protection cannot be overstressed by
any voltages developed between the sheath and the armouring, which is
considered to be effectively at earth potential.
The following sections 3.1 to 3.5 provide a brief summary of aspects relevant
to the causes and magnitude of hazardous electrical interference to nearby
telecommunication plant, together with a summary of the legislative
requirements on interference hazard limits and notification of the construction
of new electrical works in the vicinity of telecommunication plant.
Sections 24 and 25 of the Electricity Act 1992 require that, before an Electricity
Operator can start constructing or altering a works, it must first provide details
of the work involved to any Telecommunication Network Operator (TNO)
whose plant might be affected. The TNO then has 15 working days to notify
the Electricity Operator of any “reasonable” conditions it imposes on that work.
Cable sheath bonding in these cases usually has a substantial net benefit in
terms of its effect on nearby telecommunication network plant.
3.4 Maximum Short Circuit Power, Current and Fault Clearance Times
* Final back-up fault clearance times are longer and are not shown.
Zone substations, which are normally supplied from the national grid and have
an earthed neutral 11kV (or other distribution voltage) secondary, provide a
neutral earthed source for faults which arise within the 11kV distribution
system. An indication of the magnitude of (3 phase) fault currents for various
fault ratings within 11kV and 33kV distribution systems are shown in the
following table:
The currents listed are balanced 3 phase values. Single phase fault values
may be slightly higher.
11
The impact of bonding the sheath of the HV cable between a POD Substation
and a Zone Substation, to the respective substation earth mat at each end of
the cable, can be considered as set out below. The situation considered is
illustrated in the diagram below.
Generating
Station or POD Subst. Zone Distribution
Grid Subst. Subst. Transformer
If (1-2)
Ie (1-2)
EPR1 = R1 x If(1-2)
EPR2 = R2 x Ie(1-2)
TEPR3 = R3 x Ish(2-3) = TEPR2
where Ie(1-2) = net earth return fault current, that passes through
earth mats 1 and 2, for a phase-to-earth mat fault
on the incoming feeder to POD substation (2)
12
Because any current flow through the cable sheath will result in a
voltage drop along the sheath, the “received” transferred EPR (e.g.
TEPR3) will always be less than the original “source” EPR (e.g. EPR2).
If (2-3)
Ish (2-3)
Ie (2-3)
EPR2 = R2 x Ie(2-3)
EPR3 = R3 x Ie(2-3)
13
If (3-4)
Ie (3-4)
Ish (2-3)
TEPR3 = R2 x Ish(2-3)
EPR3 = R3 x Ie(3-4)
EPR4 = R4 x If(3-4)
Note
The maximum earth return fault current between earth mats 2 and 3
may NOT be the “reduced” Ie(2-3), but rather one of the “transferred
EPR” fault currents (Ish(2-3) for a phase-to-earth fault to earth mat 2, or
Ish(2-3) for a phase-to-earth fault to earth mat 4). If this is the case, the
14
maximum earth return fault current between earth mats 2 and 3 may
increase as a result of cable sheath bonding.
EPR2 = maximum of
R2 x Ie(1-2) decreases
R2 x Ie(2-3) decreases (often substantially)
TEPR2 new
EPR3 = maximum of
TEPR3 new
R3 x Ie(2-3) decreases (often substantially)
R3 x Ie(3-4) decreases (usually only slightly)
While bonding the two substation earth mats 2 and 3 together via the cable
sheath will lower the effective resistance of both substations, thereby reducing
any existing EPRs at each substation, the transferred EPRs may still result in
the “worst case” EPR at one of these substations INCREASING.
Also, because the lower effective earth resistance of both substations (2 and
3) will result in higher earth return fault currents from the next upstream
substation (1), and to the next downstream substation (4), the maximum EPRs
at both the next upstream and next downstream substations will increase
(usually only slightly).
These details should be sent to the TNO’s Power Co-ordinator (see Appendix
C for contact details) so he/she can evaluate:
The impact of any new or increased fault currents, earth return currents and
cable sheath return currents, needs to be evaluated with respect to the current
ratings of power network plant.
The impact of any increases in the maximum EPR on any substation earth
mat (i.e. EPR1, EPR4 and possibly EPR2 and/or EPR3) needs to be evaluated
with respect to the consequential touch and step voltages on the earth mats.
16
The following sections 5.1 to 5.4 describe the typical consequences of cable
sheath bonding for a range of situations. The simplified calculation procedure
in section 6.1 illustrates with calculated examples many of the points raised in
this section.
(1) Cable sheath bonding provides a metallic return path for a significant
portion of a phase-to-earth fault current at the downstream substation
and, consequently the portion of the fault current that returns through
the earth (the earth return current) over the HV cable section, will
usually be substantially reduced. This will result in a corresponding
substantial reduction in the voltages induced on any parallel
telecommunication cables.
• in urban areas, with low “effective” zone substation earth mat
impedances, the resultant earth return fault current without cable
sheath bonding is usually very high (with corresponding very high
levels of hazardous induced voltage on any parallel
telecommunication cables).
• in urban areas, the telecommunication cables are often high pair
count cables, so any mitigation adopted in the telecommunication
network is likely to be very expensive.
(2) The maximum EPRs at the upstream (POD) Substation and the
downstream (Zone) Substation are often reduced.
• this can result in a significant reduction in the costs of mitigating the
associated EPR hazard to nearby telecommunication plant,
especially if the upstream POD Substation is located in an urban
area - large numbers of customers premises might otherwise be
within the “unbonded cable sheath” EPR hazard voltage contour (i.e.
require mitigation).
• lower maximum EPRs will result in lower step and touch potentials
on the upstream (POD) and downstream (Zone) Substation earth
mats.
• where cable sheath bonding is being considered for a new
substation at the design stage, lower earth return fault current may
enable a lower cost earth mat to be installed (e.g. Appendix A).
(1) The maximum earth return fault current over the bonded cable sheath
section could actually increase if any of the new “transferred EPR” fault
currents in the cable sheath (for faults to upstream or downstream earth
mats) is greater than the original “unbonded” earth return fault current
over that section. Corresponding voltages induced on any parallel
telecommunication cables could similarly increase.
17
(3) The maximum EPRs at the next upstream and/or the next downstream
substations may increase. This would result in:
• increased step and touch voltages
• increased EPR hazard to nearby telecommunication plant
Normally, any increase in EPR would only be minor, and would
probably require no further mitigation.
(4) The sheath of the HV cable, or an associated earth connection, may not
be rated for the maximum fault current that could pass through it.
The consequences of cable sheath bonding depend primarily on the fault path
impedances, of which earth mat resistances form part, and on the single
phase to earth fault currents flowing through the earth mats of concern.
Because the major source of fault duty is the national grid, it is possible to
summarize typical cable-sheath bonding consequences in terms of
interconnecting POD and zone substation earth mats, zone and distribution
substation earth mats, or POD and zone and distribution substation earth
mats, as follows:
If2
ZSheath ZSheath2
RPOD + Rzone
Isheath = If
RPOD + Rzone + Z sheath
If Zsheath is small in relation to RPOD + Rzone, then Isheath will be a large proportion
of If2.
The transferred EPR will be determined by the voltage divider effect of the
cable sheath impedance in series with the connected earth mat impedance,
that forms a parallel path across the source EPR earth mat.
RPOD
i.e. TEPRPOD = EPRzone
RPOD + Z sheath
Rzone2
and TEPRzone2 = EPRzone
Rzone2 + Z sheath2
Rzone
Also TEPRzone = EPRPOD for a fault at the POD substation
Rzone + Z sheath
EPRzone is reduced below that of the unbonded case because the parallel
resistance of the interconnected earth mats (and MEN system if also
connected via bonded cable sheaths) more than offsets the increased fault
current.
Note: The smaller the cable sheath impedance is in relation to the zone
substation earth mat resistance, the closer the TEPRzone will be to the POD
earth mat EPR. Therefore a zone substation in a rural location fed by cables
with sheaths bonded to earth at both ends with an earth mat resistance in the
order of 5 to 6 ohms, and with a cable sheath impedance in the order of 1
ohm, can be expected to experience TEPR values very close to the POD
substation EPR. In detailed calculations, cable sheath zero sequence self
impedance and mutual impedance will be taken into account. For first
approximations, mutual impedances can be ignored as consequently
calculated currents will be conservative values (i.e. on the high side).
Without any interconnection between the two earth mats, the separate EPR
values were –
With the two earth mats interconnected, both station EPR values and TEPR
values reduced to approximately 1.4kV.
The close proximity between the two sites resulted in negligible impedance in
the interconnection between the two, and in nearly equal EPR and TEPR
values. While this is a special case, it confirms the benefits/expected results
set out in Section 5.3 above.
20
Section 6.1 sets out a simplified calculation process for determining those
cases where bonding can be adopted without the need for detailed study.
Sections 6.2 and 6.3 provide some guidance on techniques available for
determining EPR and TEPR values for proposed installations where detailed
study is necessary.
(a) confirm that bonding is appropriate in those cases where the benefits
clearly favour such action.
or
1. Assemble all relevant data or, if not readily available, choose values
considered typical of similar installations and locations.
4. Compare estimated EPR and earth return fault current values for each
earth mat without cable sheaths bonded, against the estimated EPR,
TEPR and earth return fault current values with cable sheaths bonded.
iii) more accurate cable sheath impedance values and/or earth mat
resistance values are required for re-calculation and possibly
more detailed modelling
iv) field measurements are required
The following notes are intended to provide further suggestions and help in
working through an assessment:
1) Data Assembly
Assemble the following data for all relevant substations likely to be affected by,
or contribute to, the EPR and TEPR values at the substation of concern:
Where data are not readily available, the following approximations may be
useful:
Point of Delivery earth mat resistances are normally 0.5 ohm or less, and
typically lie between 0.15 and 0.3 ohm for earth mats on very large sites.
Zone substation earth mats at high soil resistivity locations, such as on the
shingle plains of Canterbury, may be as high as 6.0 ohms. (Average for the
thirteen central Canterbury rural zone substation earth mats was 2.17 ohms).
2) Circuit Diagrams
The fault current (or fault duty) for a single phase-to-earth (66kV, 110 or 220kV
bus) fault at the relevant POD substation should be obtained from consultation
between the distribution network owner and the grid operator (i.e.
Transpower). If the fault current value is not available, it can be calculated
from the fault duty.
3) Calculations
= 0.04 p.u.
= ZIP = Z2P
= 0.5 p.u.
= ZIZ = Z2Z
100
= 0.1
5
= 2 p.u.
= ZID = Z2D
100
= 0.1
1
= 10 p.u.
The circuit diagram above can now be re-drawn as equivalent positive and
negative sequence diagrams. These are shown below:
24
ZIG = 0.0.4 p.u. Z1P = 0.5 p.u. Z1Z = 2.0 p.u. Z1D = 10 p.u.
Z2G = 0.04 p.u. Z2P = 0.5 p.u. Z2Z = 2.0 p.u. Z2D = 10 p.u.
i) Zbase @ 110kV =
V2
=
(110 10 )3 2
MVAbase 100 10 6
= 121 ohm
and to determine current p.u. values at 100MVA base for each voltage level as
follows:
100MVA
i) Ibase @ 110kV = = 525A
3 110kV
100MVA
ii) Ibase @ 33kV = = 1750A
3 33kV
25
100MVA
iii) Ibase @ 11kV = = 5250A
3 11kV
3 Z neutral
i) for the grid ZOG = ZIG +
Z base @110kV
3 0 .5
Therefore ZOG = 0.04 +
121
= 0.052 p.u.
3 0 .3
ii) for the POD substation ZOP = 0.5 +
10.89
= 0.583 p.u.
3 0.25
iii) for the Zone substation Zoz = 2.0 +
1.21
= 2.62 p.u.
where 0.25 ohms is the effective earth mat impedance of the zone substation
earth mat in parallel with the cable sheath impedance in series with the
distribution substation earth mat (0.5 in parallel with (0.2 + 0.3)).
3 0.21
iv) for the Distribution substation ZOD = 10 +
0.0016
= 404 p.u.
where 0.21 ohms is the effective earth mat impedance of the distribution
substation earth mat in parallel with the cable sheath impedance in series with
the zone substation earth mat (0.3 in parallel with (0.2 + 0.5)).
ZOG = 0.052 p.u. ZOP = 0.583 p.u. ZOZ = 2.62 p.u. ZOD = 404 p.u.
In order to determine all the relevant EPR and TEPR values with and without
cable sheath bonding between the POD and zone substations, a total of 5
separate fault current cases are considered below:
Case 1: The fault current from the 110kV grid into the POD substation earth
mat, without cable sheath bonding to the zone substation earth mat, is
determined as follows:
3Z f
Zof = ZOG +
Z base @110kV
3 0 .3
= 0.052 +
121
= 0.059 p.u.
3
If = I base @110kV
Z1G + Z 2G + Z of
3
= 525 A
0.04 + 0.04 + 0.059
= 11,330A
= 0.3 x 11,330A
= 3,399V
Case 2: The 33kV fault current at the output of the POD 110/33kV
transformer, which will circulate within the earth mat, and cannot cause EPR
or TEPR, is
3
If = I base @ 33kV
(Z 1G + Z 1P ) + (Z 2G + Z 2 P ) + Z OP
3
= 1750 A
(0.04 + 0.5) + (0.04 + 0.5) + 0.5
= 3,323A
(Note ZOP at the transformer terminals excludes the neutral impedance and
therefore equals 0.5 ohms)
Case 3: The 33kV fault current at the input to the zone substation, without
cable sheath bonding between POD and zone substation earth mats, is as
follows:
3Z f
Zof = ZOP +
Z base @ 33kV
where Zf is the circuit impedance between the POD and zone substations of
0.1 ohm plus the effective resistance of the zone substation earth mat of 0.5
ohm in parallel with the cable sheath bonding impedance of 0.2 ohm in series
with the distribution substation earth mat of 0.3 ohm, and which therefore
gives Zf = 0.1 + 0.25 = 0.35 ohm. ZOP is the value at the terminals of the
transformer, and excludes the zone substation earth mat to avoid including it
twice.
3 0.35
Zof = 0.5 +
10.89
= 0.596 p.u.
3
If = I base @ 33kV
(Z1G + Z1P ) + (Z 2G + Z 2 P ) + Z of
3
= 1750 A
(0.04 + 0.5) + (0.04 + 0.5) + 0.596
= 3,132A
28
= 0.3 x 3132A
= 940V
= 0.25 x 3,132A
= 783V
From the voltage divider network established by the interconnected zone and
distribution substation earth mat it is apparent that the EPR in the distribution
substation will be
0.3
= 783V
0.2 + 0.3
= 470V
Case 4: The 110kV fault current from the grid into the POD substation earth
mat, with cable sheath bonding between the POD and zone substation earth
mats, is considered as follows:
3Z f
Zof = ZOG +
Z base @110kV
Zf has now reduced to 0.17 ohms, which is the cable sheath impedance of
0.15 ohm in series with the zone/distribution substation earth mat of 0.25
ohms, all in parallel with the POD substation earth mat impedance of 0.3
ohms.
3 0.17
Zof = 0.052 +
121
= 0.056 p.u.
3
If = I base @110kV
Z1G + Z 2G + Z of
3
= 525 A
0.04 + 0.04 + 0.056
= 11,582A
29
= 0.17 x 11,582A
= 1,969V
0.25
= 1969V
0.15 + 0.25
= 1,231V
0.3
= 1231V
0.3 + 0.2
= 738V
If 0.2 ohms is used for the effective earth mat resistance of the zone/multiple
distribution substation earth mats combined, then very little change occurs to
Z0f and hence to If, but there is a small reduction in the POD substation EPR
because the effective earth mat resistance is now 0.16 ohms, lowering the
EPR slightly to = 1,848V.
However, the TEPR at the zone substation reduces more as it becomes only
0.2
= 1848V
0.15 + 0.2
= 1,056V
0.3
= 1056V
0.5
= 637V
Case 5: The 33kV fault current at the input to the zone substation, with cable
sheath bonding between POD and zone substation earth mats, is as follows:
3Z f
Zof = ZOP +
Z base @ 33kV
30
3 0.22
= 0.5 +
10.89
= 0.561 p.u.
3
If = I base @ 33kV
(Z1G + Z1P ) + (Z 2G + Z 2 P ) + Z of
3
= 1750 A
(0.04 + 0.5) + (0.04 + 0.5) + 0.561
= 3,199A
The return path impedance of 0.22 ohm comprises the circuit impedance of
0.1 ohm in series with the cable sheath impedance of 0.15 ohm, which is in
parallel with the zone/distribution earth mat impedance of 0.25 ohm in series
with the POD substation earth mat impedance of 0.3 ohm.
This fault current will divide between the parallel cable sheath and the earth
mat paths in the inverse ratio of the path impedances. The cable sheath
current will be
0.25 + 0.3
= 3199 A
0.25 + 0.3 + 0.15
= 2,514A
0.15
= 3199 A
0.25 + 0.3 + 0.15
= 686A
This 686A will be divided equally between the zone and distribution earth
mats, and consequently the individual earth mat currents will be
IPOD = 686A
Izone = 343A
Idist = 343A
= 206V
= 172V
= 103V
11330A 3132A
3323A
0.2 ohm
1566A 1566A
Diagram showing fault currents and earth mat resistances with no cable
sheath bonding between POD and zone substations
3255A
EPR
206V 172V (783V)
(940V)
TEPR
103V
(470V)
33kV Fault: New EPR & TEPR values vs original EPR values
Note:
3255A
(3132A)
11582A
(11330A)
3323A
2482A
4964A 2482A (1566A)
6618A (1566A)
Notes:
1. Values in brackets are the maximum fault currents without any cable
sheath bond added.
2. The value of maximum earth return current between the POD
substation and the Zone substation (4,964A) assumes that ALL of the
Distribution substation-to-POD substation earth return current flows via
the Distribution substation - Zone substation - POD substation route
(i.e. it follows the line/cable route). This may be a somewhat
conservative assumption.
Maximum EPR values AFTER cable sheath bond is added between Zone
and Distribution substations
Note:
1. Values in brackets are the maximum EPRs without any cable sheath
bond.
All the above EPRs and currents are higher (possibly much higher) than they
will be in reality, since they have been calculated assuming low impedance
line and cable circuits between the substations, and the total neglect of the
mutual impedance between cable conductors and the sheath which pushes
more current through the sheath and less through the earth mat.
34
5) Consider action
The impacts of the above changes in EPRs and currents on the power
network and any nearby telecommunication network plant must be considered
as described in 5.1 and 5.2.
The increased earth return currents between the POD substation and
the Zone substation (3,132A increases to 4,964A) and between the
Zone substation and the Distribution substation (1,566A increases to
2,482A), will cause a corresponding increase in voltages induced along
parallel telecommunication cables. The increased EPRs at the Zone
substation (783V increases to 1,231V) and the Distribution substation
(470V increases to 738V) may also put nearby telecommunication plant
at risk.
These levels of earth return currents and EPRs are likely to cause EPR
and induction hazard to nearby telecommunication plant.
Normally cable sheath bonding assists with both these problems. However, in
some cases, the end result is worse than the original problem. In these cases,
alternative solutions such as neutral earthing resistors/reactors (NERs) should
be considered. These can be implemented with or without cable sheath
bonding (refer to Section 9.0).
Power systems analysis programs such as PSS/U (available from the N.Z.
agents Worley Consultants Ltd, New Zealand) can be used for fault current
analysis to determine the division of current between the individual earth mats
forming the earthing system under study.
The results of PSS/U can then be used in earthing system design programs to
calculate the earth mat EPR and TEPR contours.
(a) a continuous length of cable laid between the source substation and a
receiving substation. The cable sheath is usually bonded to earth at both
substation earth mats.
(b) a length of cable laid from the source substation to a pole outside the
substation earth mat, and terminating on the pole where conductors are
connected to an overhead line. The cable sheath is usually bonded to
earth at the source substation and at the pole.
(c) a length of cable commencing on an overhead line pole and terminating
at a receiving substation. The cable sheath is usually bonded to earth at
both the pole and the substation.
(d) a combination of both (b) and (c) on the same circuit.
(e) a length of cable from one pole to another pole within an overhead line
between two substations.
If the cable sheath is not adequate for the fault current likely to pass between
the pothead and the originating substation, then either a buried conductor
should be installed back to the earth mat, or alternatively, the cable should be
end point bonded at the pothead for the line terminating structure. This will
ensure that any exposed metal associated with the cable pothead remains at
earth potential while any live line work is in progress on the overhead line.
However, because such a situation will require all the fault current to return via
the general mass of earth, it will cause higher EPR and the cable insulation
will need to be sufficient for this. Also, the higher EPR contours in the vicinity
of the pothead earthing system could pose a hazard to nearby
telecommunications network plant.
8.0 Summary
Designers should plan for bonding cable sheaths to earth at both ends of each
cable installation unless analysis shows bonding would result in an
unsatisfactory value of calculated (or modelled) TEPR or the export of
substation EPR to situations where it may cause a local hazard.
Economic alternatives, such as using cables with standard rated screens and
the direct interconnection of earth mats via separate conductors, should
always be a secondary or subsequent consideration.
9.0 References
APPENDIX A
Without connection via cable sheaths to Capital Power's zone substation, an initial
earth mat design resistance to ground of 0.6 ohm was calculated which would have
resulted in unacceptable EPR and step and touch potentials unless long earth rods
were added at considerable expense to keep the earth mat potentials within EPR
and step and touch potential limit values. Bonding the 11kV cable sheaths at both
ends reduced the effective earth mat resistance to 0.17 ohms. This enabled less
copper to be used, as well as obviating the need for long earth rods. The 430V EPR
contour was also kept close to the site as a result of cable sheath bonding.
110kV cables were installed for 500m from the Kaiwharawhara Substation along the
nearby road to a suitable location where access to overhead 110kV transmission was
possible. The 110kV XLPE copper sheath cables were end-point bonded to earth at
the station end, and a small earth mat at the 110kV cable to line junction was bonded
to the Kaiwharawhara Substation earth mat via two 240mm² copper conductors laid
in parallel.
In this case, the use of separate copper conductors was chosen for economic
reasons. 110kV cables with adequately fault rated cable sheaths would have
resulted in a higher cost installation. The solution adopted achieved the benefits
determined for cable sheath bonding at both ends, by an alternate approach.
Because the 11kV zone substation was only a very short distance from the POD
substation and two high capacity feeder circuits with very low impedance cable
sheaths interconnected the two earth mats, the resulting EPR and TEPR values
(similar for both earth mats) were within the hazard limit values.
42
APPENDIX B
WORKED EXAMPLE
Consider the case of the following two substations, located in a city and connected
together via 33kV cable(s). A decision needs to be made on whether to bond the two
substation earth mats together via the 33kV cable sheath(s).
(1) a Transpower substation, with incoming 220kV and 110kV lines (from
Generating Stations about 100km away), and outgoing 33kV cables and lines
(2) a Power Distribution Company zone substation, with incoming 33kV cables
and outgoing 11kV cables and lines.
The EPR’s at all voltage levels, for both the bonded and unbonded cases, need to be
calculated. Some values for one case follow (1.3 Transpower Substation earth mat
resistance, two 500m 33kV cables (300mm 2 Al PILCA) in parallel, 0.2 Distribution
Company Zone Substation earth mat resistance).
Bonding decreases the “worst case” EPR’s on both earth mats. However if the
Distribution Company substation is extensively bonded to the urban LV MEN system
(via the 11kV cable sheathes), the resultant “reduced” EPR may still represent a
major hazard to the telecommunications network that is very costly to mitigate. It
may instead prove more economic to:
(i) leave the 33kV cable sheathes unbonded,
(ii) install NER’s at the 33kV point of supply (in the Transpower Substation) to
reduce the EPR on the Distribution Company Substation earth mat below the
650V hazard voltage limit (this will also reduce the EPR on the Transpower
Substation for a 33kV phase-to-earth fault to less than 4.3kV), and
(iii) mitigate for the new “worst case” EPR level at the Transpower Substation of
11.0kV - if the Transpower Substation is an “isolated” substation (e.g. just
outside the city), this may not be a big problem.
43
APPENDIX C
2. TelstraClear Limited
TelstraClear Centre
Private Bag 92143
AUCKLAND.