Egim 2016
Egim 2016
Egim 2016
ASSESSMENT GUIDELINES IN
MALAYSIA
ACKNOWLEDGEMENT
The Department of Environment (DOE) would like to express our gratitude to all the
government agencies, both at the Federal and States level, the local authorities,
planners, developers, consultants, statutory consulters and non-governmental
organisation (NGO) in providing input and information for development of this
handbook.
The Department is also grateful to all the DOE staffs for their great efforts and
passion in steering the development of this project into reality.
Finally, we wish to acknowledge all stakeholders for their great contribution in the
development of this book of guidelines.
PREFACE
The purpose of this guideline is to guide the project proponent and qualified
person (registered consultants by Department of Environment, DOE) in the
preparation of the EIA reports. The project proponent is required to appoint
registered consultants and consult with the DOE about the proposal as early
as at the project identification stage.
The Guideline contains EIA order which comprises of two schedules. For the
First Schedule, EIA report should be submitted to the relevant State Offices
of the DOE for review and approval. However, for the Second Schedule
report should be submitted to the DOE headquarters. In addition, for the
proposed project that traverse two or more states (such as linear project –
Highway), even though it is under first schedule, the EIA Report submission
must be made through the DOE Headquarters for review and approval.
Chapter 2: This chapter explains the policy and legislations relating to EIA
Procedures in Malaysia.
This guideline was first drafted in December 1979 and was reviewed in 1987,
1995, 2000, 2007 and 2009. The guideline in its present form includes
updates and additional provisions required under Section 34A of the
Environmental Quality Act, 1974 (Amendment) 2012 and the Environmental
Quality (Prescribed Activities) (Environmental Impact Assessment) Order
2015. It will be further updated as and when deemed necessary by the
Director General of Environmental Quality.
Page
Table of Contents i
List of Tables iii
List of Figures iii
List of Appendices iv
CHAPTER 1: INTRODUCTION
i
Environmental Impact Assessment Guideline in Malaysia
2.1 Introduction 12
2.2 Relevant National Policies and Plans 12
2.2.1 National Policy on the Environment 12
2.2.2 National Physical Plan 13
ii
Environmental Impact Assessment Guideline in Malaysia
4.1 Screening 32
4.2 Scoping and Terms of Reference 32
4.2.1 Terms of Reference for Activities Falling Under the First Schedule
4.2.1.1 Terms of References (TOR) Review Procedure
4.2.2 Terms of Reference for Activities Falling Under the Second Schedule
4.2.2.1 Terms of References (TOR) Review Procedure
iii
Environmental Impact Assessment Guideline in Malaysia
5.3.1 Procedural steps for five (5) weeks assessment of EIA Report 45
5.4 Review Process of EIA Reports for Second Schedule Activities 48
5.4.1 EIA Report Reviewing Procedures 50
5.4.2 Display of EIA Reports 51
Chapter 1: Introduction
Chapter 2: Policy
i. Environmental monitoring
ii. Effluent treatment
iii. Temporary sullage and sewage treatment
iv. Permanent sullage and sewage treatment
LIST OF TABLES
LIST OF FIGURES
Figure 4.2 Procedural steps for assessment of EIA Report for Second Schedule
Activities – TOR Adequacy Check Stage
Figure 5.1 Procedural steps for five (5) weeks assessment of EIA Report 54
Figure 5.2 Procedural steps for assessment of EIA Report for Second
Schedule Activities – EIA Report Review Stage 55
Figure 6.1 Typical steps in EMP Preparation 58
vi
Environmental Impact Assessment Guideline in Malaysia
LIST OF APPENDICES
vii
ABBREVIATION
3
Environmental Impact Assessment Guideline in Malaysia
CHAPTER 1
INTRODUCTION
1
Environmental Impact Assessment Guideline in Malaysia
accountability for ensuring environmental friendly options are chosen in the course
of implementing his project.
This EIA Guideline does not only serve as the primary guidance and resource
document for Project Proponents and Qualified Persons (EIA Consultants), but it
also serves as a useful reference for project approval authorities and the relevant
stakeholders.
This EIA Guideline shall only be used within the framework of the Environmental
Quality Act 1974 and its subsidiary regulations. It is not be applicable for EIA
legislations enacted under the environmental laws of Sabah and Sarawak.
However, for prescribed activities in Sabah and Sarawak that are subject to the
EQA 1974, this Guideline shall prevail.
The EIA procedure in Malaysia has been developed primarily as an aid to the
environmental planning of new development projects or to the expansion of
existing development projects. It can be compared with similar techniques which
have been devised for the technical and economic planning of projects such as
financial feasibility studies. The procedure has been tailored specifically to the
assessment of development project proposals.
2
Environmental Impact Assessment Guideline in Malaysia
In the EIA Report, the Project Proponent makes a legal pledge of his commitment
to implement pollution prevention and mitigation measures (P2M2) to reduce the
adverse impacts to the environment. EIA Report serves as a decision making tool
for the project approval authority to decide whether a proposed project can be
approved for implementation.
3
Environmental Impact Assessment Guideline in Malaysia
Proposed Project
Process
PRE-SUBMISSION Scoping Ends
OF EIA REPORT (Formulation of Terms of Reference)
STAGE
Revised TOR
Submission of TOR not submitted
TOR Revised,
TORAC MEETING No Re-submited
in time
Yes
If Conformed
First Schedule Second Schedule
EIA
TRC Report
Rejected Rejected
TRC
DURING
SUBMISSION Yes
OF EIA REPORT
STAGE Public Display
EIATRC EIATRC
.MEETING .MEETING
No . AND DECISION Approved
AND DECISION
MAKING (STATE
MAKING(DG) No
DIRECTOR OR DG)
Yes
4
Environmental Impact Assessment Guideline in Malaysia
(b) Pro-active
The EIA process should start as early as possible within the
project planning cycle and decision making for project approval so
that environmental impacts of a project are considered right from
the beginning to address all potential environmental impacts that
might result from the proposed development.
(c) Transparency
The EIA study should be conducted in a transparent manner
involving inputs from all relevant stakeholders. The EIA Report
produced should be clear, concise, informative, transparent,
balanced, easily accessible, and understood by the stakeholders.
(d) Credibility
The EIA study should be carried out by professionals and
performed with integrity, rigor, fairness, and objectivity. The study
which invariably involves measurement and collection of data and
its subsequent analysis and interpretation should apply established
5
Environmental Impact Assessment Guideline in Malaysia
(e) Cost-effectiveness
The proposed environmental management plan including pollution
prevention and mitigating measures, follow up surveillance and
monitoring, and compliance audit should be cost-effective and be
based on best available technologies or best industry practices.
The environmental cost should be accounted for in the total project
cost which should be reflected in the contract documents signed by
the Project Proponent and his contractors and suppliers.
(f) Practical
The information and outputs provided by the environmental
assessment process, documented in the EIA Report should be in
the form which is readily usable for decision making and planning.
The proposed mitigation measures should be practically
implemented.
6
Environmental Impact Assessment Guideline in Malaysia
(i) Self-Regulatory
Self-regulation ensures environmental commitment and regulatory
compliance is achieved on a sustained basis. The practice of self-
regulation by Project Proponent is a driver for cultivating a positive
work culture in the day-to-day management of the project paving
the way for excellence in environmental regulatory compliance.
The environmental commitment should be displayed and
translated into action at all levels of the project organization and all
phases of project development.
(j) Ethical
All personnel involved in the EIA study should uphold their
professional ethics to fulfil their professional obligations with
extreme sense of responsibility, professionalism and integrity. The
ethical principles should be applied not only in the EIA study phase
but also in the project implementation and operational phases.
(k) Participative
EIA is a multi-disciplinary study on environmental components
7
Environmental Impact Assessment Guideline in Malaysia
(l) Sustainability
The proposed project should be thoroughly studied to ensure it is
environmentally sound, sustainable, and beneficial to the society.
The benefits of EIA may only be achieved if the environmental dimensions are
integrated in a timely manner within the project planning and development cycle.
As EIA is conducted in response to a project proposal, the assessment
procedure is project centred, and moulded around the normal project planning
process.
8
Environmental Impact Assessment Guideline in Malaysia
EIA is carried out not for the sole purpose of securing authority approval
for the project but to be applied to improve project design and to meet
sustainability objectives of quality planning, social acceptability and
investment security. The EIA Report provides the information needed for
decision-making by the authority.
9
Environmental Impact Assessment Guideline in Malaysia
The benefits of integrated project planning of which EIA is one of the tools
available for that purpose to the Project Proponent include:
10
Environmental Impact Assessment Guideline in Malaysia
11
Environmental Impact Assessment Guideline in Malaysia
CHAPTER 2
2.1 Introduction
12
Environmental Impact Assessment Guideline in Malaysia
13
Environmental Impact Assessment Guideline in Malaysia
2. 3 ENVIRONMENTAL LEGISLATION
14
Environmental Impact Assessment Guideline in Malaysia
15
Environmental Impact Assessment Guideline in Malaysia
16
Environmental Impact Assessment Guideline in Malaysia
17
Environmental Impact Assessment Guideline in Malaysia
18
Environmental Impact Assessment Guideline in Malaysia
CHAPTER 3
An EIA study shall only be carried out by a team of Qualified Persons who
hold a valid registration with the DOE as stipulated under Section 34A
(2B) of the EQA 1974 (Amendment) 2012. The Qualified Persons are
commonly referred to as the EIA Consultants. The EIA team shall
comprise professionals (qualified persons) who are competent and
experienced in the technical fields relevant to the EIA study. The team
shall be led and supervised by a team leader who shall be responsible for
coordinating the EIA study and for ensuring the EIA Report to be written
is complete, clear, coherent, balanced, and impartial and is useful for
decision making process.
EIA study shall follow the following typical steps or phases commonly
followed by EIA practitioners and widely adopted by environmental
agencies worldwide:
o Screening
o Scoping towards formulation of terms of reference
o Baseline study
o Identification of mitigation measures
o Impact assessment and evaluation of significance
19
Environmental Impact Assessment Guideline in Malaysia
3.2.1 Screening
3.2.2 Scoping
20
Environmental Impact Assessment Guideline in Malaysia
21
Environmental Impact Assessment Guideline in Malaysia
22
Environmental Impact Assessment Guideline in Malaysia
Physical:
- Land use
- Topography
- Geology, hydrogeology
- Soils and terrain
- Watershed
Environmental:
- Air quality
- Water quality
- Noise, vibration and nuisance
- Groundwater
- Visual/aesthetics
Biological:
- Terrestrial and aquatic ecosystems
- Flora and fauna
- Environmentally sensitive areas
Socio‐economic:
- Demography
- Development needs and potential
- Infrastructure facilities
- Economic activities
23
Environmental Impact Assessment Guideline in Malaysia
Cultural/Heritage:
- Archaeological resources
- Historical resources
The list is not exhaustive, and not all items listed above are applicable to
all EIA studies. The subject areas to be covered in the baseline study
should focus only on those aspects that are likely to be affected. The
areas generally depend on the nature, scale, location of the proposed
project, and the extent of the impact.
During the impact assessment phase of the EIA study, the impacts of the
proposed project are determined. The impacted sectors could be
environmental, socio-economic, health, etc. To identify and assess the
magnitude of potential impacts associated with or resulting from project
activities, a number of methodologies have been developed and used
worldwide. These include the following:
Experts judgement
Checklist and matrices
Multi-criteria analysis
Mathematical models and simulation
Case comparison
Geospatial analysis
Risk analysis
24
Environmental Impact Assessment Guideline in Malaysia
25
Environmental Impact Assessment Guideline in Malaysia
This step of the EIA study will identify mitigation measures that can be
implemented to avoid, prevent, minimize, or offset the predicted adverse
impacts. The environmental agencies normally require that state of the art
technologies or best available technologies (BAT) and industry best
practices appropriate to the project components are evaluated for
implementation to mitigate the adverse environmental impacts on the
various receptors.
Based on the results of all studies, the EIA team leader will coordinate the
writing of the EIA Report and thoroughly review it to ensure it
encompasses all the elements in the TOR, and is comprehensive,
coherent, balanced, impartial and technically acceptable for submission
to the authorities.
The EIA consultant acting as the team leader shall extract and
summarize the major findings of the reports prepared by subject matter
consultants (SMCs) and place them in the appropriate chapters in the EIA
Report. The report summary made by the EIA consultant shall be cross
referenced to the relevant pages in the SMCs' reports. The original
reports by the SMCs shall be placed in the Appendix to the EIA Report.
26
Environmental Impact Assessment Guideline in Malaysia
EIA Report review is conducted either at the DOE state office or at the
DOE Headquarters depending on the nature and location of the proposed
project. If the project falls under the First Schedule of the EIA Order, the
EIA Report will be reviewed at the state office, while for a project which
falls under the Second Schedule, the EIA Report will be reviewed at the
DOE Headquarters. If a First Schedule activity traverses two or more
states, the EIA Report will also be reviewed at the DOE Headquarters.
The differences between the EIA reports review process at the state DOE
and at the DOE Headquarters are briefly discussed below.
27
Environmental Impact Assessment Guideline in Malaysia
28
Environmental Impact Assessment Guideline in Malaysia
As general guidance, the Project Proponent and the EIA Consultant may
utilize the EIA Report Quality Self-Assessment Tool (RQSAT) shown in
Table 3.2 to assist them in conducting self-check on the quality of the EIA
Report prepared and the possibility of it be approved. EIA Reports scoring
an A or B will likely to be approved while those scoring an F will be
rejected. The Project Proponent and the EIA Consultant are advised not
to submit to the DOE any EIA Reports which has been self-assessed,
29
Environmental Impact Assessment Guideline in Malaysia
30
Environmental Impact Assessment Guideline in Malaysia
31
Environmental Impact Assessment Guideline in Malaysia
CHAPTER 4
4.1 Screening
Prior to conducting an EIA study, the Project Proponent and the Qualified
Person (i.e. the EIA Consultant) shall carry out the screening process to
determine whether a proposed project is a prescribed activity under the
Environmental Quality (Prescribed Activities) (Environmental Impact
Assessment) Order, 2015. The Environmental Quality (Prescribed Activities)
(Environmental Impact Assessment) Order, 2015 is reproduced in Appendix 6.
The EIA Consultant needs to determine which Schedule the proposed project
falls under: the First Schedule or the Second Schedule. The EIA for First
Schedule projects follows a different EIA procedure from the EIA for Second
Schedule projects, as described in Chapter 3.
The Case Where the Proposed Project Has More Than One Prescribed Activity
If the proposed project consists of more than one prescribed activity and one of
them falls under the Second Schedule, then the project as a whole shall be
considered to fall under the Second Schedule of the Environmental Quality
(Prescribed Activities) (Environmental Impact Assessment) Order, 2015.
32
Environmental Impact Assessment Guideline in Malaysia
given in Appendix 7. From the scoping process the EIA Consultant then
prepares an Environmental Scoping Information (ESI) that determines the
proposed Terms of Reference (TOR) for the EIA study. The general
requirements for scoping process and TOR preparation shall follow those
described in Chapter 3.
4.2.1 Terms of Reference for Activities Falling Under the First Schedule
For prescribed activities that fall under the First Schedule, the EIA Consultant
shall prepare an Environmental Scoping Information (ESI) that determines the
proposed - Terms of Reference (TOR) for the EIA study and submit it to the
DOE State Office for endorsement. The ESI and TOR will be assessed and
endorsed by the Director of DOE State Office either through a TORAC meeting
or mail correspondence, whichever deemed appropriate. Subsequently, when
the EIA Report has been prepared, it shall be submitted to the relevant DOE
state office for review, as described in Chapter 3.
The output of scoping exercise is the terms of reference (TOR). The Project
Proponent shall first submit to the DOE the TOR together with the
Environmental Scoping Information (ESI), in accordance with the format outlined
in the Guidance Document For Preparing Terms Of Reference (TOR) and/or
specific EIA guidelines (if available) for endorsement. Appendix 8 gives a
general guidance on scoping and also the general contents of TOR which shall
be followed in the TOR formulation.
The review of the TOR is carried out by the EIA Technical Review Committee
(EIATRC) comprised of TRC members (a team of DOE officers at the State
33
Environmental Impact Assessment Guideline in Malaysia
Office), and may include individuals who are specifically appointed (AIs) on an
ad hoc basis from within or outside of the DOE as well as representatives
from government agencies (GAs).
The TOR review involving parties outside of the DOE shall be done either
through a Terms of Reference Adequacy Check (TORAC) meeting or by
submission of comments through mail correspondence.
The adequacy of the scoping coverage and the TOR formulated will be decided
in a Terms of Reference Adequacy Check (TORAC) meeting which will be
chaired by the State Director of the DOE. The TORAC meeting members
comprise the TRC members, and may include AIs and GAs, as well as NGOs as
deemed appropriate. At this meeting, the TOR may be accepted or agreed upon
or it may require a revision.
34
Environmental Impact Assessment Guideline in Malaysia
Proposed project
Submission of
TOR
Appointment of AIs
Process Ends
Distribution of TOR
Site Visit
(if necessary)
Submission of
TERMS OF REFERENCE ADEQUACYYCY Revise Revised TOR
CHECK MEETING (TORAC)
Conformed
TOR
Endorsement
NOTE:
Process ends when
EIA Revised TOR is not
Submission submitted within timeframe
Process by the Project Proponent
Figure 4.1: Procedural steps for assessment of EIA Report for First Schedule
Activities – TOR Adequacy Check Stage
35
Environmental Impact Assessment Guideline in Malaysia
36
Environmental Impact Assessment Guideline in Malaysia
4.2.2 Terms of Reference for Activities Falling Under the Second Schedule
For prescribed activities that fall under the Second Schedule, the EIA Consultant
shall prepare an Environmental Scoping Information (ESI) that determines the
proposed - Terms of Reference (TOR) for the EIA study and submit it to the
DOE Headquarters for endorsement. The same procedure applies to a
prescribed activity that traverses two or more states.
A site visit by the TRC members and appointed individuals may be required,
37
Environmental Impact Assessment Guideline in Malaysia
The review of the TOR is carried out by the EIA Technical Review
Committee (EIATRC) comprised of TRC members (a team of DOE
officers at the Headquarters), individuals specifically appointed (AIs) on
an ad hoc basis from within or outside of the DOE and representatives
from government agencies (GAs). Non-Governmental Organizations
(NGOs) may also be invited to the EIATRC meetings as general
representatives or as Appointed Individuals (AIs). The AIs are individuals
who have vast technical experiences in the relevant areas related to the
proposed project, which may include potential project environmental
impacts, impact study methodologies, and applicable pollution prevention
and mitigation measures. The same personnel (i.e. TRC members and
AIs) will also serve as the committee for reviewing the EIA Reports. The
adequacy of the scoping coverage and the TOR formulated will be
decided in a Terms of Reference Adequacy Check (TORAC) meeting
which will be chaired by the Director General of the DOE. The TORAC
meeting members comprise the TRC members, AIs and GAs, and may
include NGOs. At this meeting, the TOR may be accepted or agreed upon
or it may require a revision.
Figure 4.2 shows the procedural steps for submission of TOR.
38
Environmental Impact Assessment Guideline in Malaysia
Proposed project
Submission of
TOR
Appointment of AIs
Process Ends
Distribution of TOR
Site Visit
(if necessary)
Submission of
TERMS OF REFERENCE Revised TOR
ADEQUACY CHECK MEETING (TORAC) Revise
Conformed
TOR
Endorsement
agreed
EIA NOTE:
Process ends when
Submission Revised TOR is not
Process submitted within timeframe
by the Project Proponent
Figure 4.2: Procedural steps for assessment of EIA Report for Second Schedule
Activities – TOR Adequacy Check Stage
39
Environmental Impact Assessment Guideline in Malaysia
(iii) The TORAC meeting will be conducted after the site visit,
normally within the third week from date of submission of
the TOR to DOE. At this meeting, the proposed TOR will be
presented by the Project Proponent and his Consultant to
the TORAC meeting when deemed necessary.
(iv) The outcome of the TOR review meeting may lead to:
40
Environmental Impact Assessment Guideline in Malaysia
41
Environmental Impact Assessment Guideline in Malaysia
For example, for air pollution impact studies, several mathematical models
which have been developed by US Environmental Protection Agency (USEPA)
are available, while some companies have developed their own models. Specific
dispersion models such as the industrial source complex (ISC3) dispersion
models developed by US Environmental Protection Agency may be used for
calculation of the ground-level concentrations for point, area, flare and volume
sources. The results of modeling exercise shall be presented in an appropriate
form such as pollutant concentration with contour visualization on a map using
ArcGIS as GIS platform. The meteorological data (wind speed, wind direction,
42
Environmental Impact Assessment Guideline in Malaysia
stability class, ambient temperature, cloud base height, cloud cover, mixing
height) used for model input shall be adequate and acceptable to be used for
determining the highest short term and long term air quality impacts at air
sensitive receptors. The modeling exercise shall capture the worst case
scenarios to determine the worst case short term impacts.
It is the responsibility of the Project Proponent and the EIA consulting team
(especially the EIA team leader) to ensure quality control of the EIA Report is
performed before the EIA Report is submitted to the DOE. Internal quality check
will ensure that all relevant and pertinent tasks have been performed
satisfactorily and no important tasks left incomplete; the latter situation may lead
to rejection of the Report or delay in decision making on the Report. The EIA
Report which is ready for submission shall have taken into account the following
general quality control elements:
43
Environmental Impact Assessment Guideline in Malaysia
An example of arrangement of the front cover and various chapters of the EIA
report shall follow the example given in Appendix 9.
44
Environmental Impact Assessment Guideline in Malaysia
CHAPTER 5
EIA Reports for activities falling under the First Schedule are to be
submitted to the respective DOE state offices, while those falling under
the Second Schedule are to be submitted to the DOE Headquarters. If a
project is located on a site involving two or more states, the Report shall
be submitted to the DOE Headquarters.
EIA Reports shall be prepared in the form of hard and soft copies,
accompanied with a cover letter bearing the Project Proponent’s letter
head which shall be submitted to the respective DOE office. A summary
of EIA Report submission requirements is shown in Table 5.1.
DOE State*
Submission of (*For prescribed activity that
DOE Headquarters
EIA Report traverses across states, the EIA
report shall be submitted to the
DOE Headquarters)
Minimum thirty fives
No. of EIA Five (5) weeks procedure: (35) Hard copies and
Report Minimum twelve (12) hard one (1) soft copy
copies and 1 soft copy to
45
Environmental Impact Assessment Guideline in Malaysia
Second Schedule
Item First Schedule Activities
Activities
State DOE
Minimum one (1) hard copy
and 1 soft copy to DOE HQ
46
Environmental Impact Assessment Guideline in Malaysia
47
Environmental Impact Assessment Guideline in Malaysia
48
Environmental Impact Assessment Guideline in Malaysia
49
Environmental Impact Assessment Guideline in Malaysia
The timeline for the EIA review process and decision is as follows:
(a) For EIA Reports of projects falling under the First Schedule
- 25 working days (5 weeks)
(b) For EIA Reports of projects falling under the Second Schedule
- 60 working days (12 weeks)
The general requirements on EIA Report review are summarized in Table 5.2
while the committees involved in the review process are summarized in Table
5.3.
50
Environmental Impact Assessment Guideline in Malaysia
Personnel involved
Details of Review First Schedule Second Schedule
Committee Activities Activities
Name of Review DOE State Office DOE Headquarters
Committee EIA Technical Review EIA Technical Review
Committee Committee
(EIATRC) (EIATRC)
Chairperson of Review Director of DOE State Director General of
Committee Office Environment
Members of Review DOE state officers, DOE Head Office
Committee appointed individuals officers, appointed
(AIs) – in certain individuals (AIs),
circumstances, representatives from
representatives from Government Agencies
Government Agencies (GAs)
(GAs) and NGOs and NGOs, if required
51
Environmental Impact Assessment Guideline in Malaysia
5.3.1 Procedural steps for five (5) weeks assessment of EIA Report
52
Environmental Impact Assessment Guideline in Malaysia
f. The EIA review meeting will be conducted in the third week from
date of submission of the EIA Report to the DOE.
53
Environmental Impact Assessment Guideline in Malaysia
Proposed Project
Rejected
TRC
(STATE)
Process
Ends
Corrected EIA
Report NOT
submitted
Site Visit EIATRC Rejected
(If necessary) MEETING
& DECISION
MAKING (STATE
DIRECTOR or DG)
Within
Time Limit Submission of Corrected EIA
Approve With or Without Report to state DOE within
Conditions timeframe Exceed
Time
Limit
- Submission of EMP
- Presentation of COA NOTE:
Execution Plan Process ends when
Figure 5.1: Procedural Corrected EIA Report is
steps for five (5) weeks not submitted within
assessment of EIA Report timeframe by the Project
-Compliance Monitoring (CM) Proponent
-Impact Monitoring (IM)
-Performance Monitoring (PM)
-3rd Party Audit
-EMR, EAR, etc.
54
Environmental Impact Assessment Guideline in Malaysia
The review of EIA Report for Second Schedule activities is carried out by
the DOE Headquarters as described as follows: Firstly, the DOE HQ
Technical Review Committee (TRC) comprised of a team of DOE officers
will check for “Report Adequacy” (RAC). This quality check process will
check the EIA Report for compliance with the Terms of Reference (TOR)
and EIA Report format, absence of obvious technical errors, coherence of
the report, environmental pledge by the Project Proponent, etc. An EIA
Report which does not pass the RAC will be rejected. The EIA Report
which passes the RAC will be reviewed by the EIATRC, which is
composed of individuals specifically appointed (AIs) on an ad hoc basis
from within the DOE or outside of DOE, and representatives from relevant
government agencies (GAs). EIATRC may include NGOs, either invited
to sit on the committee as general representatives or appointed as AIs.
The individuals appointed (AIs) based on their broad experience or
particular expertise on a subject matter relevant to the EIA study are
required to critically review the Report and submit a written comment on
the Report to the DOE. The reviews by the AIs shall focus on specific
subject areas and examine whether they have been addressed in a
technically defensible manner. Additionally, the review shall evaluate
whether the proposed pollution prevention and mitigation measures are
adequate and can be considered to be the best available technologies
(BATs) or the best industry practices. The Director General will make the
final decision whether to approve or not to approve the EIA Report after
taking into account the opinions of the EIATRC members.
55
Environmental Impact Assessment Guideline in Malaysia
The entire review process will be completed by the DOE within a period of
60 working days. Figure 5.2 shows the EIA Report Review Process for
Second Schedule Activities. The review process is characterized by the
following:
(ii) A minimum of 35 hard copies and 1 softcopy (in PDF format) of the
report shall be submitted to the DOE HQ. Additional copies are to
be submitted whenever necessary. The DOE will distribute the
Report through the Project Proponent to the relevant government
agencies and members of the EIATRC. The Project Proponent
shall display the Report at specified locations. Additionally, the
Project Proponent/Consultant may also recommend suitable
display locations besides those specified by the DOE. This is to
allow as many affected or interested parties to review the Report
and submit comments to the DOE. This has to be done within one
week from the date of submission of the EIA Report.
(iii) Upon submission of the EIA Report, the Project Proponent shall
advertise in major newspapers to announce the availability of the
EIA Report for public review. This entails placing advertisements in
56
Environmental Impact Assessment Guideline in Malaysia
at least two (2) major newspapers for three (3) consecutive days (a
total of 6 advertisements). A draft copy of the advertisement shall
be submitted to the EIA Secretariat for approval prior to the
placement. The advertisement shall include information on the
project and the locations where copies of the Reports may be
reviewed or purchased. For projects in Sabah and Sarawak, the
advertisement must be placed in at least one regional newspaper.
The Project Proponent may also choose to advertise in on-line
news portals, subject to agreement by the DOE.
(iv) The Project Proponent and/or the Consultant shall make available
the EIA Report, both in the form of hard copies and soft copies (in
PDF format) for purchase by the public. The price of the Report in
hard copy shall be affordable to the public and shall normally be
equivalent to its printing cost.
(v) The EIA Report shall be displayed for 30 days from the date of
announcement. The time frame for public to submit their comments
to the DOE is 45 days.
(vi) A visit to the project site by the DOE officers (TRC) (if necessary).
(vii) The Project Proponent and the Consultant shall respond to all the
written comments received from the public. The responses are to
be submitted to the DOE Headquarters for review.
57
Environmental Impact Assessment Guideline in Malaysia
58
Environmental Impact Assessment Guideline in Malaysia
TRC (HQ)
Rejected
NOTE:
Process ends when
Revised Corrected EIA
i. Public Displays & Comments Report is not submitted
ii. Distribution of EIA Report within timeframe by the
Project Proponent
Site Visit
(if necessary)
EIATRC
MEETING
AND DECISION Process
MAKING (DG) Rejected
Ends
Corrected EIA
Report NOT
submitted
Meets The Minor documentation errors:
Requirement of Sec. (eg. Typo errors, unclear maps etc.)
34A(3), EQA 1974
Within Time
Approval with or without Submission of Corrected EIA
Limit
conditions Report to DOE HQ within
timeframe Exceed Time Limit
59
Environmental Impact Assessment Guideline in Malaysia
CHAPTER 6
60
Environmental Impact Assessment Guideline in Malaysia
Firstly the Project Proponent and the Consultant who has been tasked to
prepare the EMP shall study and understand the pollution prevention and
mitigation measures (P2M2s) recommended in the EIA Report and the
EIA approval conditions (COAs).
Fourthly, the Consultant shall brief the Project Proponent (PP) on the
executable actions to be undertaken and the cost implication. Later, the
PP shall make a declaration or pledge that all the actions stipulated in the
EMP will be implemented.
61
Environmental Impact Assessment Guideline in Malaysia
Note: The EMP preparer shall be a consultant registered with the DOE.
62
Environmental Impact Assessment Guideline in Malaysia
63
Environmental Impact Assessment Guideline in Malaysia
64
Environmental Impact Assessment Guideline in Malaysia
The EMP for prescribed activities falling under both Schedules (First
Schedule and Second Schedule) of the EIA Order shall follow the general
specifications and format, and shall contain chapters 1 to 5 as explained
below.
65
Environmental Impact Assessment Guideline in Malaysia
Chapter 1: Introduction
Chapter 2: Policy
66
Environmental Impact Assessment Guideline in Malaysia
67
Environmental Impact Assessment Guideline in Malaysia
68
Environmental Impact Assessment Guideline in Malaysia
69
Environmental Impact Assessment Guideline in Malaysia
70
Environmental Impact Assessment Guideline in Malaysia
iii. Biomass.
The following information shall be provided: proposal for the
management of biomass during land clearing and construction
phase.
v. Open burning.
The following information shall be provided: Measures to
prevent occurrence of open burning.
vi. Housekeeping.
The following information shall be provided: proposal for
implementing best practices in general housekeeping, including
71
Environmental Impact Assessment Guideline in Malaysia
72
Environmental Impact Assessment Guideline in Malaysia
(a) Declaration
The Project Proponent is required to make a declaration that all
the actions/measures/plans outlined in the EMP will be
implemented as in the Table 6.2. The form is required to be filled
out and submitted to the DOE together with the EMP document.
……………………………………………………..
Name of Project Proponent/authorized person
(b) CHECKLIST
Signature: (…………………………)
Date: ………………………
73
Environmental Impact Assessment Guideline in Malaysia
……………………………………………………..
Signature : (…………………………)
Date : ……………………………
74
Environmental Impact Assessment Guideline in Malaysia
CHAPTER 7
The EIA procedure, a preventive strategy of the DOE also needs to embrace the
environmental mainstreaming and self-regulation goal in order to enhance its
effectiveness in mitigating the adverse impacts from development projects on
the environment at every stage of the EIA procedure. Self-regulation culture in
EIAs means that the Project Proponent will be charged with full responsibility
and accountability for taking environmental friendly options and instituting
effective pollution prevention and mitigation measures (P2M2) and self-
75
Environmental Impact Assessment Guideline in Malaysia
This chapter is dedicated to the discussion of the roles, functions and core
duties of the various players involved in a development project: the Project
Proponent, the EIA Consultant, and the Environmental Officer (EO). The
implementation of the guidance provided in this chapter would result in
mainstreaming the environmental agenda into the EIA project management
decision making process as well as into the day to day management of project
implementation, paving the way for excellence in environmental regulatory
compliance. The guidance is also intended to cultivate self-regulation by
promoting the practice of quality control and performance monitoring of EIA
projects as a routine activity at every stage of the EIA procedure including pre-
submission, during submission and post submission of EIA Report.
76
Environmental Impact Assessment Guideline in Malaysia
Project Proponent is the key driver for ensuring the success self-regulation
approach in environmental management through the mainstreaming of
environmental agenda throughout his project implementation phases. The
project proponent shall ensure top-down organizational commitment to
environmental regulatory compliance to all personnel, at all levels of the
organization, including the registered EIA consultant, the EO, the contractors,
and other parties involved in the project implementation.
77
Environmental Impact Assessment Guideline in Malaysia
In the course of EIA Report preparation, the Project Proponent shall take
into consideration of the alternatives, demonstrate commitment to
ensuring the successful conduct of the EIA study and implementation of
measures to mitigate the significant impacts as recommended by the EIA
Consultant. This is accomplished by allocating sufficient funds for the
above purposes. The funds shall cover the cost required for all activities
associated with the EIA study, and preparation and implementation of
environmental management plan (EMP) and pollution prevention and
mitigation measures (P2M2).
78
Environmental Impact Assessment Guideline in Malaysia
Specific considerations which shall also be taken into account during each stage
of project implementation are enumerated below.
79
Environmental Impact Assessment Guideline in Malaysia
(c) Allocating sufficient funds for all steps in the EIA process and
every stage of project planning and implementation with itemized
budget required for water quality monitoring, air quality and noise
monitoring, for comprehensive site survey and investigation of the
specific existing site conditions, for implementation of
Environmental Management Plan (EMP) including temporary
pollution prevention and mitigation measures (P2M2). P2M2 shall
be those which can be described as state of the art technologies,
best available technologies (BATs), or industry best practices.
80
Environmental Impact Assessment Guideline in Malaysia
81
Environmental Impact Assessment Guideline in Malaysia
The registered EIA Consultant is the key person who is entrusted with the
responsibilities for ensuring environmental impacts from a project are correctly
identified, assessed, and mitigated. The roles and core duties of the EIA
Consultant include the following:
82
Environmental Impact Assessment Guideline in Malaysia
83
Environmental Impact Assessment Guideline in Malaysia
84
Appendix 1
10. Town and Country Planning Act 1976 (Act 172) (Incorporating amendments up to
1st January 2006)
11. Land Conservation Act (Act 385) (incorporating amendments up to 1st January
2006)
13. Local Government Act 1976 (Act 171) (Incorporating amendments up to 1 st Act
A1311 of the year 2007)
Appendix 2
23. Environmental Quality (Control of Petrol and Diesel Properties) Regulations, 2007.
37. Environmental Quality (Control of Pollution from Solid Waste Transfer Station and
Landfill) Regulations, 2009.
Appendix 3
1. All Environmental Impact Assessment (EIA) reports are required to address the
aspects of soil erosion and sediment control.
3. Soil erosion and sediment control shall be discussed in the following chapters in
the EIA report.
3.1 Project Description The project concept shall take into consideration the following
aspects amongst others: terrain, geology, natural topography, hydrology and natural
features.
Specifically, the following principles shall be adopted:-
a. Plan the development to fit the particular topography, soils, drainage patterns,
natural features and vegetation of the sites, which is to be reflected in the layout
plan.
b. Method statement that describes how the major activities of the project that may
cause erosion and sedimentation are going to be undertaken. Taking into
consideration site conditions involved, the method statement shall also incorporate
appropriate phasing (taking into account rainy seasons or monsoon period),
preservation of green areas and buffer zones.
3.2 Project Options describe options for method statement and layout plans and the
reasons why a specific method statement and layout plan has been chosen.
3.3 Description of the Existing Environment apart from the information required as
described in the EIA Guideline in Malaysia, the following information shall be
included:-
rainfall-runoff erosivity factor (R), soil erodibility (K), topographic factor (LS), cover
management factor (C), erosion control practice factor (P), volume of runoff (V) and
peak flow (Q) for the storm event in order to determine soil loss and sediment yield
using Universal Soil Loss Equation (USLE) and Modified Universal Soil Loss
Equation (MUSLE).
All factors used in the USLE and MUSLE shall be taken from local conditions and
results from studies conducted locally. R= rainfall erosivity data, must be obtained
from rainfall station nearest to the project site based on average ten years records.
C = cover management factor must be taken from the published results of studies by
the DID Malaysia or other researchers, if unavailable. K= soil erodibility data, must
be obtained from results from tests done for the specific site. Tests must be
conducted to obtain values for K (erodibility).
Apart from the information required as described in the EIA Guideline, the
information on R, K, LS, C, P, V, and Q for the storm event shall be provided and
used to determine soil loss and sediment yield using Universal Soil Loss Equation
(USLE) and Modified Universal Soil Loss Equation (MUSLE) for the following
scenarios:
a. During development/construction:
The calculation to determine the soil loss (USLE) and sediment yield (MUSLE) must
be performed according to the stages of construction and phases of development.
Mitigation measures shall be instituted to ensure that the pre development’s flow
conditions at the site are maintained in the post development stage.
The details of USLE and MUSLE calculations in paragraphs 3.3c, 3.4a and 3.4b
shall be included as an appendix to the EIA report.
4. Pollution Prevention and Mitigation Measures (P2M2)
To prevent erosion and control sediment, the following primary principles shall be
adopted:-
d. Control runoff flows onto, through, and from the site in stable drainage structures.
e. Install perimeter controls.
In addition to the measures taken in conformity with the above principles, erosion
and sediment loss from the site shall be effectively controlled by applying appropriate
P2M2.
A site plan (which contains existing topographical and hydrological features, and
land use) to be superimposed with site development plan (which illustrates the
earthwork activities) which depicts pollution prevention and mitigating measures
(P2M2) to be implemented on the site. The P2M2 shall include both temporary and
permanent measures as described in paragraph 4.1. The drawings shall be drawn to
scale and the scale clearly indicated. Drawings shall be legible with standard coding
and submitted in A1 or A3 paper depending on the size of the project.
5. The write-up on soil erosion and sediment control as required by this Guidance
Document shall be undertaken by an environmental consultant who is
knowledgeable and experienced in the subject matter and holds a certification as a
professional in erosion and sediment control issued by the Department of
Environment.
6. Sufficient fund shall be made available for the implementation of P2M2 and their
maintenance, including EMP preparation, auditing, monitoring and emergencies. The
commitment of the project proponent on making the fund available for the above
purposes shall be clearly stated in the EIA report.
Response from
Provision *Accepted
Contractor dated Observations/Findings/Suggestions
Control Status Observations/Findings/Suggestions Observations/Findings/Suggestions
No. Location 09/10/2014 (Recent Inspection – 30/09 &
Measures (Installation) (Last Inspection – 18/09/2014) (Latest Inspection – 14/10/2014)
ESCP Actual (Maintenance: Reply to 01/10/2014) (√ / X)
PM-01/10/2014)
A. Silt Traps and Vicinity Area
Installed on: 1 Aug Proposed Action / Action Observation: Observation: Observation:
2011 Taken: Clear discharge is observed from Clear discharge is observed from Slightly clear discharge is observed
silt trap. silt trap. from silt trap.
Status: Operational Next Maintenance: Some section of exposed slope at Some section of exposed slope at Some section of exposed slope at
09 October 2014 RHS & LHS Saddle Dam A has RHS & LHS Saddle Dam A has RHS & LHS Saddle Dam A has yet
Last Maintenance: yet to be vegetated. yet to be vegetated. to be vegetated.
- 09 Aug 2014: De-
silt Suggestions/Recommendations: Suggestions/Recommendations: Suggestions/Recommendations:
Saddle Dam
1. ST-2-01 - 09 June 2014: - To vegetate the exposed slope - To vegetate the exposed slope - To vegetate the exposed slope X
A
De-silt immediately. immediately. immediately.
- 24 Feb 2014: De- - Daily monitoring and regular - Daily monitoring and regular - Daily monitoring and regular
silt inspection to be carried out after inspection to be carried out after inspection to be carried out after
- 14 Jan 2014: De- event of heavy downpour. event of heavy downpour. event of heavy downpour.
silt
- 28 Dec 2013:
Gabion wall X X X
Response from
Provision *Accepted
Contractor dated Observations/Findings/Suggestions
Control Status Observations/Findings/Suggestions Observations/Findings/Suggestions
No. Location 09/10/2014 (Recent Inspection – 30/09 &
Measures (Installation) (Last Inspection – 18/09/2014) (Latest Inspection – 14/10/2014)
ESCP Actual (Maintenance: Reply to 01/10/2014) (√ / X)
PM-01/10/2014)
- 17 November Contractor) Suggestions/Recommendations: Suggestions/Recommendations: - To clear the bushes and make an
2013: Close - To clear the bushes and make an - To clear the bushes and make an access.
turfing access. access. - Daily monitoring and regular
- 9 Oct 2013: - Daily monitoring and regular - Daily monitoring and regular inspection to be carried out after
Closed-turfing inspection to be carried out after inspection to be carried out after event of heavy downpour.
event of heavy downpour. event of heavy downpour.
X X X
Response from
Provision *Accepted
Contractor dated Observations/Findings/Suggestions
Control Status Observations/Findings/Suggestions Observations/Findings/Suggestions
No. Location 09/10/2014 (Recent Inspection – 30/09 &
Measures (Installation) (Last Inspection – 18/09/2014) (Latest Inspection – 14/10/2014)
ESCP Actual (Maintenance: Reply to 01/10/2014) (√ / X)
PM-01/10/2014)
silting carried out after event of heavy carried out after event of heavy - To plan and provide schedule for
- 30 Dec 2013: downpour. downpour. maintenance works.
Closed turfing - To plan and provide schedule for - To plan and provide schedule for
- 10 Dec 2013: De- maintenance works. maintenance works.
silting X
X X
Installed on: 21 Next Maintenance: Observation: Observation: Observation:
February 2014 03 October 2014 - No discharge is observed from the - Slightly turbid discharge is - Turbid discharge is observed from
silt trap. observed from the silt trap due to the silt trap due to heavy downpour.
Status: Operational heavy downpour at night.
Suggestions/Recommendations: Suggestions/Recommendations:
Relocation ST-2-15 - To rectify the outlet immediately. Suggestions/Recommendations: - Daily monitoring and regular
13. - X
Road (B) CH 2550 - Daily monitoring and regular - Daily monitoring and regular inspection/maintenance to be carried
inspection/maintenance to be inspection/maintenance to be out after event of heavy downpour.
carried out after event of heavy carried out after event of heavy
downpour. downpour.
√ X X
Response from
Provision *Accepted
Contractor dated Observations/Findings/Suggestions
Control Status Observations/Findings/Suggestions Observations/Findings/Suggestions
No. Location 09/10/2014 (Recent Inspection – 30/09 &
Measures (Installation) (Last Inspection – 18/09/2014) (Latest Inspection – 14/10/2014)
ESCP Actual (Maintenance: Reply to 01/10/2014) (√ / X)
PM-01/10/2014)
downpour.
X X X
26. Reservoir RP 23 -
√ √ √
Response from
Provision *Accepted
Contractor dated Observations/Findings/Suggestions
Control Status Observations/Findings/Suggestions Observations/Findings/Suggestions
No. Location 09/10/2014 (Recent Inspection – 30/09 &
Measures (Installation) (Last Inspection – 18/09/2014) (Latest Inspection – 14/10/2014)
ESCP Actual (Maintenance: Reply to 01/10/2014) (√ / X)
PM-01/10/2014)
Installed on: Proposed Action / Action Observation: Observation: Observation:
06 November 2012 Taken: - Maintenance of WT has been - Maintenance of WT has been - Maintenance of WT has been carried
carried out. carried out. out.
Status: Operational Date to be completed /
Date of completion: Suggestions/Recommendations: Suggestions/Recommendations: Suggestions/Recommendations:
Wash Last Maintenance: - Daily monitoring and regular - Daily monitoring and regular - Daily monitoring and regular
2. WT - 23 Jan 2014: Next Maintenance: inspection/maintenance to be inspection/maintenance to be inspection/maintenance to be
Trough
Carry out Everyday monitoring carried out. carried out. carried out.
maintenance
works
- 16 Jan 2014: De-
silting earth drain √ √ √
Response from
Provision *Accepted
Contractor dated Observations/Findings/Suggestions
Control Status Observations/Findings/Suggestions Observations/Findings/Suggestions
No. Location 09/10/2014 (Recent Inspection – 30/09 &
Measures (Installation) (Last Inspection – 18/09/2014) (Latest Inspection – 14/10/2014)
ESCP Actual (Maintenance: Reply to 01/10/2014) (√ / X)
PM-01/10/2014)
Response from
Provision *Accepted
Contractor dated Observations/Findings/Suggestions
Control Status Observations/Findings/Suggestions Observations/Findings/Suggestions
No. Location 09/10/2014 (Recent Inspection – 30/09 &
Measures (Installation) (Last Inspection – 18/09/2014) (Latest Inspection – 14/10/2014)
ESCP Actual (Maintenance: Reply to 01/10/2014) (√ / X)
PM-01/10/2014)
slope Date to be completed / Suggestions/Recommendations: Suggestions/Recommendations:
15 May 2014: Date of completion: Suggestions/Recommendations: - To install sprinkler to watering the - To install sprinkler to watering the
Closed turfing has - To use others method to plant the hydroseeded grass. hydroseeded grass.
been carried out. Next Maintenance: seeds (netting, coil log). - To plan and provide schedule for - To plan and provide schedule for
Everyday monitoring - To install sprinkler to watering the maintenance works. maintenance works.
hydroseeded grass.
- To plan and provide schedule for
maintenance works.
X X X
Last Maintenance: Proposed Action / Action Observation: Observation: Observation:
Taken: - Exposed slope is observed along - Turfing works has been started at - Turfing works has been started at
Constructed check dam at relocation. some area. However still many some area. However still many
culvert C4. - Riprap works is in progress at exposed slope is observed along exposed slope is observed along
slope area. relocation. relocation.
Date to be completed / - Riprap works is also in progress - Riprap works is also in progress at
Date of completion: Suggestions/Recommendations: at slope area. slope area.
Relocation Exposed
12. - To vegetate/ protect exposed X
Road slope
Next Maintenance: slope immediately. Suggestions/Recommendations: Suggestions/Recommendations:
Everyday - To plan and provide schedule for - To vegetate/ protect exposed - To vegetate/ protect exposed slope
maintenance works. slope immediately. immediately.
- To plan and provide schedule for - To plan and provide schedule for
maintenance works. maintenance works.
X X X
Last Maintenance: Proposed Action / Action Observation: Observation: Observation:
- 3 June 2013: Taken: - Oil spill and contaminated soil - Oil spill and contaminated soil - Oil spill and contaminated soil has
Repair broken Oil spillage has been has yet to be rectified. has yet to be rectified. yet to be rectified.
bund collected as SW and the - Poor housekeeping is observed. - Housekeeping has yet to be to be
area has been rectified. Suggestions/Recommendations: - Silted earth drain is observed. carried out.
- SW to be properly contained, - Silted earth drain has yet to be de-
Next Maintenance: labelled, stored and Suggestions/Recommendations: silted.
Every day morning handled/disposed in accordance - To carry out housekeeping and
Oil & Grease;
Batching to the regulations. de-silting works immediately. Suggestions/Recommendations:
13. Scheduled - - X
Plant - Inventory record to be - SW to be properly contained, - To carry out housekeeping and de-
Waste (SW)
maintained. labelled, stored and silting works immediately.
handled/disposed in accordance - SW to be properly contained,
to the regulations. labelled, stored and
- Inventory record to be handled/disposed in accordance to
maintained. the regulations.
- Inventory record to be maintained.
X X X
PHOTOS
Areas of Concern on 14 October 2014 and pending issues on 30 September & 01 October 2014
Plate 1a: Exposed slope along the constructed Plate 1b: Exposed slope is observed (RHS Plate 1c: Exposed slope is observed (LHS u/stream Plate 1d: Exposed slope is observed (Main Dam).
drain (access road). u/stream of ST-2-01; Saddle Dam A). of ST-2-01; Saddle Dam A).
Plate 1e: Formation of gullies is observed (RHS Plate 1f: Exposed slope is observed (d/stream Plate 1g: Exposed slope is observed (LHS Plate 1h: Exposed slope is observed (LHS & RHS
Main Dam). spillway). relocation road CH 2150). relocation road CH 2150).
Plate 1i: Exposed slope is observed (LHS CH 2650 Plate 2a: Silted drain is observed (behind batching Plate 2b: Silted earth drain has yet to be de-silted Plate 3a: Turfing has been dead is observed (Main
relocation road). plant-access road). (batching plant). Dam).
Plate 3b: Turfing has been dead is observed Plate 3c: Turfing has been dead is observed (near Plate 4a: Eroded embankment of silt trap is Plate 4b: Outlet to be eroded is observed (ST-2-18).
(behind batching plant). to the pipe storage). observed (ST-2-06e).
Plate 5a: Solid waste is observed scatter around Plate 5b: Housekeeping for construction waste has Plate 5c: Poor housekeeping is observed (batching Plate 5d: Poor housekeeping is observed (batching
(workers’ camp). yet to be carried out (draw-off tower). plant). plant).
Plate 6a: Poor housekeeping is observed (batching Plate 6b: Oil spill is observed (batching plant). Plate 6c: Contaminated geotextile and oil ponding is
plant). observed (workers’ camp).
PHOTOS
Areas of Concern on 14 October 2014
Plate 1a: Remnant of open burning activity is Plate 1b: Poor housekeeping is observed (drain at Plate 2a: Silted drain has yet to be de-silted (near Plate 2b: Silted silt trap has yet to be de-silted (ST-
observed (workers’ camp near pipe storage). workers’ camp). main entrance gate). 2-06d).
Plate 3a: Gap is observed at gabion wall (ST-2-16). Plate 3b: Gap is observed at gabion wall (ST-2-17). Plate 4a: Exposed slope has yet to be protected Plate 4b: Exposed slope has yet to be vegetated
(relocation road under bridge). (relocation road).
Plate 4c: Exposed slope has yet to be vegetated Plate 5a: Schedule waste without labelling is Plate 5b: Oil drums without tray are observed
(relocation road). observed (workers’ camp). (saddle dam b).
Rectification works
Plate 1a (Before): Oil spill is observed (near genset Plate 1a (After): No more oil spill (near genset at Plate 1b (Before): Contaminated sand is observed Plate 1b (After): Contaminated sand has been
at site office). site office). in the tray and no labelling (workers’ camp). collected (workers’ camp).
Plate 2 (Before): Remnant of open burning activity Plate 2 (After): Remnant of open burning activity Plate 3a (Before): Exposed slope has yet to be Plate 3a (After): Riprap works is in progress
is observed (workers’ camp). has been clean up (workers’ camp). protected (relocation road near bridge). (relocation road near bridge).
Plate 3b (Before): Exposed slope has yet to be Plate 3b (After): Exposed slope has been turfed Plate 3c (Before): Exposed slope has yet to be Plate 3c (After): Exposed slope has been turfed
vegetated (relocation road). (relocation road). vegetated (relocation road). (relocation road).
PREFACE
This paper provides guidance for the preparation of LD-P2M2 document which is to be
included as a part of the Environmental Management Plan (EMP) to be submitted to the
Department of Environment (DOE) for approval.
LD-P2M2 refers to the use of construction methods, processes, materials, and practices
that is intended to prevent, reduce, or eliminate the generation of pollutants at the
source (development site) during any land-disturbing activity through the protection of
natural resources by preservation and conservation, reduction of waste generation and
releases or discharges of pollutants to land, air, and water, and incorporation of best
management practices (BMPs) and techniques to attain compliance with the conditions
stipulated in the EIA approval conditions (Conditions of approval-COA).
The focus of the LD-P2M2 document (or simply LD-P2M2) is on the prevention,
mitigation and control of the discharge from the development area containing the major
pollutant (suspended solids) resulting from land disturbing activities.
1
This Guidance Document is organized into 8 sections as follows:
2
ACKNOWLEDGEMENT
Special thanks and credit are due to Mr Don Lee from the Roadside Environmental Unit
of the North Carolina Department of Transportation of the United States of America for
granting permission to DOE, Malaysia for the use of the 'BMPs For Construction And
Maintenance Activities Manual' issued by the North Carolina Department of
Transportation. Similarly, thanks and credit are also due to Mr Mell Nevils from the
North Carolina Sedimentation Control Council for granting permission to the DOE for
the use of the 'Erosion and Sediment Control Planning and Design Manual' issued by
the North Carolina Department of Environment and Natural Resources.
3
1.0 INTRODUCTION
1.2 Definitions
4
soil or inland or Malaysian waters and the existing and designated uses of
waters before, during, and after land disturbing activities.
The overall objective of the Guidance Document is to ensure good quality LD-
P2M2s are prepared by competent professionals and the LD-P2M2s are
effectively implemented to mitigate and minimize environmental and pollution
impact of land disturbing activities.
ii. To standardize the format of LD-P2M2 which includes maps, plans and
drawings, information required and procedures for LD-P2M2 submission.
iii. To assist the Project Proponent (PP) personnel, especially the Environment
Officer in supervising the overall implementation of the significant and site
specific ingredients of the LD-P2M2 that include the installation, inspection
and maintenance (2I’s1M)* of pollution prevention and mitigation measures
(P2M2s) as well as in preparing the required documentation and reports
(photographs, data collections and corrective actions) on 2I’s1M.
5
1.4 Scope of the guidance document
ii. LD-P2M2s will be used for future site inspections either by the
regulatory agencies or designated project site inspectors and
managers for desktop tasks and ground inspections.
6
early planning on how, what, where, why, and when to effectively implement
the pollution prevention and mitigation measures at the development site.
(Note: Environment Officer here and throughout this Guidance Document refers
to the person who has been certified by the Department of Environment and
officially appointed or engaged by the project proponent to be responsible for
environmental performance of the project. The responsibilities of the
Environmental Officer are described in other documents issued by the DOE).
The LD-P2M2s prepared shall identify, cover and address the following:
i. The locations of potential discharge point(s) of pollutants
ii. The locations of designated discharge point(s) of pollutants
iii. The locations of the P2M2s to be installed
The LD-P2M2 shall incorporate the P2M2s identified to be installed at the land
disturbing development areas into the design, construction and operation stage
of the development project as stipulated in Section 34A (7) of the EQA. The
P2M2s shall be effective in preventing, reducing and controlling pollution as well
as preventing non-compliant pollution discharges from reaching any water
bodies.
All activities subject to EIA Order, 2015 which involve land disturbing or site preparation
activities are required to prepare a LD-P2M2 as part of the EMP submission
requirement. Non-compliance with the specifications stipulated in this Guidance
Document may be a cause for the rejection of the EMP or will cause a delay in the EMP
processing.
7
3.0 REFERENCES FOR PREPARATION OF LAND-DISTURBING
POLLUTION PREVENTION AND MITIGATION MEASURES (LD-P2M2s)
The LD-P2M2 prepared for EIA projects shall be prepared based on the project
concept, components and minimum mitigating measures approved in the EIA
Conditions of Approval (COA).
For the preparation of LD-P2M2, the preparer can make reference to the following
documents:
(a) Department of Irrigation and Drainage – DID. 2010. Guideline for Erosion and
Sediment Control in Malaysia
(b) Department of Irrigation and Drainage – DID. 2000. Urban Storm Water
Management Manual for Malaysia
(c) Erosion and Sediment Control Planning and Design Manual issued by North
Carolina Department of Environment and Natural Resources
(d) Best Management Practices for Construction and Maintenance Activities issued by
North Carolina Department of Transportation
(e) Other useful references on the design of BMPs for soil erosion and sediment control:
(i) CESSWI, LLC. 2008. Certified Erosion, Sediment and Storm Water Inspector
Exam Review Study Guide. Marion, NC
8
(iii) Douglas County Department of Public Works. 2004. Grading, Erosion and
Sediment Control (GESC) Manual. Douglas County, CO
(iv) Fifield, J. S. 2004. Designing for Effective Sediment and Erosion Control on
Construction Sites. Forester Press. Santa Barbara, CA
(v) Fifield, J. S. 2004. Field Manual on ESC. Best Management Practices for
Contractors and Inspectors. Forester Press. Santa Barbara, CA
(vi) Sacramento Storm Water Quality Partnership and the City of Roseville 2007.
Storm Water Quality Design Manual for the Sacramento and South Placer
Regions. Sacramento County, CA
The LD-P2M2 shall be prepared and signed by a DOE registered consultant who holds
a certification as a professional in erosion and sediment control issued by the
Department of Environment.
9
In principle, the Project Proponent (PP) shall be responsible for the implementation of
the LD-P2M2.
The focus of the LD-P2M2 is on the prevention, mitigation and control of the discharge
from the development area containing the major pollutant (suspended solids) resulting
from land disturbing activities. Controlling the sediment-laden runoffs means in some
way to control the discharge of other pollutants too that may contain in the sediment
strains such as nutrients, bacteria, oxygen demanding materials, heavy metals,
petroleum hydrocarbons and synthetic organics. Everyone involved with land disturbing
activity shall make the most of the following basic principles in every stage of
development when implementing the pollution prevention and mitigation measures:
10
l) Employ experienced and competent personnel and consistently
conduct relevant training.
7.0 MINIMUM STANDARDS REQUIREMENTS OF POLLUTION
PREVENTION AND MITIGATION MEASURES
The minimum standards requirements outlined in the following section 7.0 shall
be implemented and complied with wherever relevant by the Project Proponent.
These minimum standards requirements shall be attached or inserted in the LD-
P2M2 document and shall be the minimum P2M2s that will be adopted, applied,
and implemented in the process of carrying out land disturbing activities at the
development site.
(Note: The term “standards requirements” here refers to the physical or non-
physical measures to be taken to prevent, reduce and control the discharge of
suspended solids and other pollutants from the development site. The standards
requirements are meant to achieve a certain quality or attainment)
11
The following paragraphs detail out the P2M2s (which include BMPs) to be
installed:
ii. Critical Path Method (CPM) may be adopted in establishing work program
that shall fit in the elements of pollution prevention and mitigation measures
for each phase, stage and sequence of project development.
12
Land disturbing from any drainage way or waterway or watercourse
within project site;
Areas not to be worked or disturbed, and
Buffer area or/and existing vegetation meant for temporary or
permanent preservation and for protection.
ii. The construction markers are fences, signs, tapes, flags or other similar
marking device.
i. All entrance/exit roads to the site shall be stabilized and paved for a suitable
distance from where these access roads join the existing paved roads or
public road where Stabilized Construction Entrance P2M2 and/or Tires
Washing Facility shall be constructed from this point inward to the subjected
construction site.
i. Retain a 20 metres natural buffer between on-site land disturbance and any
watercourse (intermittent or permanent) unless otherwise specified by the
relevant authority; or
13
ii. Provide a vegetated buffer that is less than 20 metres between on-site land
disturbance and any watercourse (intermittent or permanent) in combination
with additional erosion and sediment controls; or
iii. If not feasible to provide a natural or vegetated buffer of any size between
on-site land disturbance and any watercourse (intermittent or permanent),
install suitable erosion and sediment controls in combination with all
possible perimeter controls.
14
basin/trap shall install vertical silt marker for the purpose of measuring the
depth of accumulated sediment to facilitate maintenance program.
(h) Runoff Management
ii. Slope drains, flexible pipe slope drains or downpipe, rock lined drainage
chutes or flume, cascade drain shall be applied to convey upslope runoff
down slope without affecting the slope surface.
iv. Any incomplete permanent drainage lines constructed along sloping area,
shall not be left unattended without first applying rocks dissipater at the end
points or at the toe end of the incomplete adjoining conveyance structure.
The anticipated runoff discharge from this point should be diverted using
temporary earth drain combined with check dam towards stabilized area or
into sediment treatment P2M2s. It is highly recommended that pipe slope
drains are used to convey runoff directly into sediment containment system.
15
i. Temporary or permanent diversion channel of any watercourse or off-site
run-on water shall be protected either by using rock lined channel bed with
protected side slope using Turf Reinforcement Mat (TRM) or plastic
sheeting or by installing plastic sheeting canvas along the channel with
extend across the side slope in combination with constructed check dams or
sump slot checks. This has to be done to minimize erosive forces flow
velocity along the channel bed and channel side slope surface to prevent it
from eroding.
ii. The approach distance of 10 metres or any suitable distance from both
sides of the watercourse crossing shall be installed with sediment fence or
equivalent along the sides, together with gravels or stone pad and water bar
to prevent sediment traction onto the crossing that may potentially enter the
stream.
i. Runoff conveyance system such as road ditch, temporary earth drain, catch
drains, berm drains, toe drains, slope drains and in-slope or out-slope
diversion shall be constructed and conveyed runoff to stabilized area or into
sediment treatment P2M2s prior to discharge.
16
(l) Temporary Stabilization
ii. Temporary soil stabilization shall be applied within seven (7) days to
exposed areas that may not be at final grade but will remain unattended for
longer than fourteen (14) days.
ii. The stockpiled soil shall be protected from contact with runoff water
(including run-on) using a temporary perimeter control such as berms,
dikes, fiber rolls, silt fences, sandbag and gravel bags.
17
(n) Spoil Management Area (Disposal Area)
ii. All disposal area shall be protected from contact with runoff water (including
run-on) using a temporary perimeter sediment barrier such as berms, dikes,
fiber rolls, silt fences, sandbags and gravel bags.
iii. All anticipated runoff flowing from any disposal area shall be drained into a
sediment trap/basin prior to discharge.
18
ii. The Director General of DOE reserves the right to instruct any PP to install
ATS system whenever:-
(a) The project site has been found to have violated the total
suspended solids discharge standard stipulated in the EIA
approval conditions (COAs); or
(q) Discharge
i. All discharge runoff water from any land-disturbing activities shall be made
through a sediment control P2M2 such as sediment basin or trap or any
other erosion and sediment controls which is regarded as the designated
final discharge(s).
ii. All disturbed areas shall drain to sediment control measures at all times
during land-disturbing activities and during site development until stabilized,
after which, the sediment controls shall be removed. Any trapped sediment
and the disturbed soil areas resulting from the removal of temporary
19
measures shall be permanently stabilized to prevent further erosion and
sedimentation.
iii. The discharge point of the treated runoff shall be released by using a
dissipater or other means of outlet protection.
iv. All discharge run off water to offsite area shall only be allowed through a
sediment basin or trap or other specified control measures.
(r) Corrective Actions
ii. The PP shall within 7 calendar days of discovering the occurrence of one of
the triggering conditions above complete a report as described in the
Performance Monitoring Document (PMD) and which shall be reported in
the Performance Monitoring Report (PMR). The report details which shall
also be recorded in the logbook include the following:
20
3. The PP shall send a report with photographic evidence as
soon as practicable whenever corrective actions or
measures have been taken or scheduled to be taken, using
an online communication medium to the DOE.
iii. In all circumstances, the PP shall immediately take all reasonable steps to
minimize or prevent the discharge of pollutants until a permanent solution is
taken and an appropriate P2M2 is installed or applied and made
operational, including cleaning up any contaminated surfaces so that the
material will not be discharged in subsequent storm events.
i. Site inspections shall be conducted to check and to ascertain that all P2M2s
specified in the EIA Report and this document have been properly installed
and maintained as well as to determine whether any controls that is clearly
not operating as intended or any P2M2s requires replacement, or additional
P2M2s are required. The site inspections shall also assess if pollution is
effectively being controlled and off-site discharge is being prevented in
compliance with the EIA conditions of approval (COAs).
21
c) Roadways;
d) All P2M2s installed or applied at the site;
e) Material storage areas, spoil area, borrow area, or
equipment storage and maintenance areas;
f) All areas where runoff water typically flows within the site,
including drainage ways designed to divert, convey, and/or
treat runoff water;
g) All points of discharge from the site;
h) All locations where stabilization measures have been
implemented at least once every seven (7) days and within
24 hours after the end of a storm event of 12.5 mm or
greater.
(t) Maintenance
The PP shall maintain the P2M2s in accordance with the following requirements:
22
ii. Unless advised otherwise, maintenance shall occur within seven (7)
calendar days of the inspection noted/reported. All maintenance activities
shall be recorded in the PM logbook
ii. Application of all P2M2s onsite shall be in accordance with standards and
specifications indicated, specified, stated, depicted and set forth in:
23
a. Department of Irrigation and Drainage – DID. 2010.
Guideline for Erosion and Sediment Control in Malaysia
[Note: For the use of the manuals mentioned in (c) and (d),
credit is hereby given to the Sedimentation Control
Commission for granting permission for its use in Malaysia-
See the acknowledgement page of this Guidance Document]
7.2 Self-Regulation
24
Documentation
(ii) The EPMC shall be represented by all relevant parties involved in project
implementation and chaired by a senior member representing the PP.
The chairman shall be responsible for ensuring the decisions of the
meeting are responsibly executed. The EPMC shall meet at a minimum,
once in a quarter and the minutes of the meeting be maintained.
25
shall be adequately equipped with relevant resources including portable
analytical testing equipment such as in-situ total suspended solids
meter, turbidity meter, etc.
(vi) The PP through the EO shall establish and maintain proper records
using a log book (called the Performance Monitoring logbook) that
contains among others, Checklist of P2M2s List Sheet, Installation
Sheet, Maintenance Sheet, Site and P2M2 Inspection Sheet,
Photograph Folder Sheet, Corrective Action Sheet, Performance
Monitoring Sheet, etc. The PMD and PMR shall be maintained for five
years upon completion of project development. For a reference, see
Appendix I and Appendix II for the samples of the PMD conducted at
two different development project sites.
(vii) The PP is required to keep a current copy of the PMD and PM log book
at the site or at an easily accessible location, so that it can be made
available at the time of an onsite inspection or upon request by the
Department of Environment inspector. This log book shall be maintained
or updated by weekly/event-based inspections.
26
8.0 LD-P2M2 SUBMISSION CHECKLIST
INSTRUCTIONS
(i) All relevant items cited in Section 8.1, 8.2, 8.3 and 8.4 checklist are required to
be identified, addressed, discussed, assessed, evaluated and presented in the
LD-P2M2 document according to appropriate chapters.
(ii) All relevant items cited in Section 8.3 and 8.4 checklist are required to be
illustrated or depicted in a minimum of three (3) sheets of plan or map or drawing
to be referred to as LD-P2M2 Plan which contains the following:
(a) Map of site plan with the existing site conditions (pre-development),
(b) Map of site development plan (during development) and
(c) Overlaid map of (a) and (b).
(iii) Maps shall be clear and legible where they may be provided with more than one
sheet to commensurate with the size and complexity of the drainage areas as
well as the terrain of the project site.
(iv) The LD-P2M2 document shall include a legal pledge by the Project Proponent
(PP) to comply with the Minimum Standards requirement of P2M2s as outlined in
Section 7 of this Guidance Document (PP).
27
ITEM PAGE MARK REMARKS
√ - Yes
X - No
NA - Non
Applicable
28
(f) Estimated start date, completion
date and stabilization schedule for
each major land-disturbing activities
or construction activities phases,
stages and sequences.
√ - Yes
X - No
NA - Not
Applicable
i. Soil types
29
areas, and roads that might be
affected by the land disturbance.
30
estimation for pre, during and post
development accounted for both with
and without the implementation of
LDP2M2s. All of the data and
parameters used in the calculations
shall be measured or rationally
determined, and identified. If
secondary sources are used, they
shall be clearly identified.
√ - Yes
X - No
NA - Non
Applicable
i. Contours
ii. Elevation
iii. Slopes
31
(b) Geological Terrain Mapping (if
relevant).
i. Delineation of watercourses.
i. Trees.
iv. Buildings.
v. Utilities.
32
i. 1:500 for area less than 20
hectares;
√ - Yes
X - No
NA - Non
Applicable
33
(i) Identify and mark on-site
temporary access or construction or
haul road
34
(w) Identify and mark concrete
wash P2M2 location.
Size: A3 or A1.
35
Appendix 5
1. Technical Guidance Document On The Design and Operation Sixth Edition 2015
Of Industrial Effluent Treatment Systems (DOE-IETS-9), Sixth
Edition 2015
1
NO GUIDELINES/ GUIDANCE DOCUMENTS DATE OF
PUBLICATION
12. Manual Panduan Pemeriksaan BMPs Untuk Kawalan Hakisan First Edition 2015
dan Sedimen
13. Industrial Processes & the Environment (Handbook No.1) ; First Edition 2000
Metal Finishing – Electroplating
14. Industrial Processes & the Environment (Handbook No.2) ; First Edition 2000
Raw Natural Rubber Industry
15. Industrial Processes & the Environment (Handbook No.3) ; First Edition 2000
Crude Palm Oil Industry
16. Industrial Processes & the Environment (Handbook No.4) ; First Edition 2000
Textile & Apparel Industry
17. Industrial Processes & the Environment (Handbook No.5) ; First Edition 2000
Food Industry – Rice Noodle Processing
2
Appendix 6
FEDERAL GOVERNMENT
28 Ogos 2015
GAZETTE
28 August 2015
P.U. (A) 195
ENVIRONMENTAL QUALITY
(PRESCRIBED ACTIVITIES)
(ENVIRONMENTAL IMPACT ASSESSMENT)
ORDER 2015
DISIARKAN OLEH/
PUBLISHED BY
JABATAN PEGUAM NEGARA/
ATTORNEY GENERAL’S CHAMBERS
P.U. (A) 195
PADA menjalankan kuasa yang diberikan oleh subseksyen 34A(1) Akta Kualiti Alam
Sekeliling 1974 [Akta 127], Menteri, selepas berunding dengan Majlis, membuat
perintah yang berikut:
Nama
1. Perintah ini bolehlah dinamakan Perintah Kualiti Alam Sekeliling (Aktiviti yang
Ditetapkan) (Penilaian Kesan kepada Alam Sekeliling) 2015.
Tafsiran
2. Dalam Perintah ini—
2
P.U. (A) 195
(4) Walau apa pun subperenggan (1), aktiviti yang berikut juga ialah aktiviti
yang ditetapkan:
(5) Pameran awam dan ulasan awam yang disebut dalam subperenggan (2)
dan (3) ialah suatu pameran laporan, di tempat dan dalam tempoh yang ditentukan oleh
Ketua Pengarah, bagi mendapatkan ulasan awam berhubung dengan laporan itu.
(a) butiran 2, 6, 9 dan 10 dan subbutiran 11(a) dan (b) dan 14(a)
Jadual Pertama; dan
3
P.U. (A) 195
(2) Perintah ini terpakai bagi Negeri Sabah berkenaan dengan aktiviti yang
ditetapkan yang dinyatakan dalam butiran yang berikut:
(2) Perintah ini tidak menjejaskan mana-mana aktiviti yang ditetapkan di bawah
Perintah yang dibatalkan jika laporan telah diluluskan oleh Ketua Pengarah sebelum
berkuat kuasanya Perintah ini.
JADUAL PERTAMA
[Subperenggan 3(1) dan (4)]
1. PERTANIAN:
(a) Skim kemajuan tanah yang meliputi kawasan seluas 20 hektar atau lebih tetapi kurang
daripada 500 hektar untuk menjadikan hutan kepada pengeluaran pertanian.
4
P.U. (A) 195
(b) Pembangunan estet pertanian yang meliputi kawasan seluas 500 hektar atau lebih yang
melibatkan perubahan dalam jenis kegunaan pertanian.
2. AERODROM:
Peluasan aerodrom yang melibatkan landasan terbang sepanjang 1,000 meter atau lebih.
(a) Pembinaan tasik buatan manusia dan pembesaran tasik bukan semula jadi dengan
kawasan permukaan seluas 100 hektar atau lebih.
(b) Skim pengairan yang meliputi kawasan seluas 500 hektar atau lebih.
4. PERIKANAN:
Projek akuakultur berasaskan penggunaan tanah beserta dengan pembersihan hutan paya bakau,
hutan paya gambut atau hutan paya air tawar yang meliputi kawasan seluas 20 hektar atau lebih
tetapi kurang daripada 50 hektar.
5. PERHUTANAN:
(a) Pengubahan hutan pada ketinggian 300 meter atau lebih di atas purata aras laut kepada
kegunaan lain tanah yang meliputi kawasan seluas 20 hektar atau lebih tetapi kurang
daripada 100 hektar.
(b) Pembalakan, atau penebangan atau pengambilan kayu bagi maksud pengubahan hutan
kepada kegunaan tanah yang lain yang meliputi kawasan seluas 100 hektar atau lebih
tetapi kurang daripada 500 hektar.
(c) Pembalakan, atau penebangan atau pengambilan kayu daripada hutan pada ketinggian
kurang daripada 300 meter di atas purata aras laut yang meliputi kawasan seluas 100
hektar atau lebih, di luar hutan simpan kekal.
5
P.U. (A) 195
bagi kegunaan perindustrian, perumahan atau pertanian yang meliputi kawasan seluas
20 hektar atau lebih tetapi kurang daripada 50 hektar.
(e) Pembangunan ladang hutan yang meliputi kawasan seluas 100 hektar atau lebih tetapi
kurang daripada 500 hektar.
6. INDUSTRI:
(a) Kimia:
Keupayaan pengeluaran setiap keluaran atau gabungan keluaran sebanyak 100 tan atau
lebih sehari.
(b) Simen:
Loji pengisaran simen dengan keupayaan pengeluaran simen sebanyak 200 tan atau
lebih sehari.
(c) Kapur:
Pengeluaran kapur 100 tan atau lebih sehari menggunakan relau putar atau 50 tan atau
lebih sehari dengan menggunakan relau tegak.
(d) Petrokimia:
Keupayaan pengeluaran setiap keluaran atau gabungan keluaran kurang daripada 50 tan
sehari.
7. PENEBUSGUNAAN TANAH:
Penebusgunaan kawasan pantai atau penebusgunaan tanah sepanjang tebing sungai yang
melibatkan kawasan kurang daripada 50 hektar.
6
P.U. (A) 195
8. PERLOMBONGAN:
(a) Pemprosesan bijih di luar kawasan tenemen mineral, termasuk pemekatan aluminium,
kuprum, emas, besi, tantalum atau elemen nadir bumi.
(b) Perlombongan pasir di darat atau sungai atau di kawasan pantai atau di laut wilayah
yang tidak melebihi 3 batu nautika yang diukur dari garis air surut, meliputi kawasan
seluas 20 hektar atau lebih.
9. PETROLEUM:
(a) Pembangunan—
(c) Pembinaan—
(d) Pembinaan depoh keluaran bagi penstoran petrol, gas atau diesel yang mempunyai
keupayaan penstoran tergabung sebanyak 60,000 tong atau lebih
7
P.U. (A) 195
(tidak termasuk stesen servis) dalam jarak 3 kilometer dari kawasan perdagangan,
perindustrian atau kediaman.
10. PELABUHAN:
(a) Peluasan pelabuhan yang melibatkan penambahan sebanyak 50 peratus atau lebih
dalam keupayaan pengendalian setahun.
(b) Peluasan pelabuhan perikanan yang melibatkan penambahan sebanyak 50 peratus atau
lebih dalam keupayaan pendaratan ikan setahun.
(a) Pembinaan stesen janakuasa stim yang menggunakan bahan api fosil (selain arang batu)
dan mempunyai keupayaan 10 megawatt atau lebih, dengan atau tanpa talian pemancar.
(b) Pembinaan stesen janakuasa kitar padu, dengan atau tanpa talian pemancar.
(a) Pembinaan bangunan atau kemudahan yang mempunyai 80 bilik atau lebih di kawasan
pantai.
(b) Pembinaan resort atau hotel peranginan bukit pada ketinggian 300 meter atau lebih di
atas purata aras laut yang meliputi kawasan seluas 20 hektar atau lebih.
Pembangunan atau pembersihan tanah yang meliputi kawasan yang kurang daripada 50 peratus
kawasan cerun yang berkecerunan melebihi atau sama dengan 250 tetapi kurang daripada 350.
8
P.U. (A) 195
(c) Kumbahan:
(i) Pembinaan loji pengolahan kumbahan dengan 20,000 kesetaraan populasi atau
lebih.
15. PENGOREKAN:
16. PERUMAHAN:
Pembangunan estet perindustrian yang meliputi kawasan seluas 20 hektar atau lebih.
Pembinaan bandar baharu yang terdiri daripada 2,000 unit kediaman atau lebih yang meliputi
kawasan seluas 100 hektar atau lebih.
19. KUARI:
9
P.U. (A) 195
20. JALAN:
(c) Pembinaan jalan, terowong atau jambatan yang melintasi atau bersebelahan atau
berdekatan dengan kawasan sensitif alam sekitar.
Pemajuan air bawah tanah bagi bekalan air perindustrian, pertanian atau kawasan bandar
sebanyak 4,500 meter padu atau lebih sehari.
JADUAL KEDUA
[Subperenggan 3(1) dan (4)]
1. PERTANIAN:
(a) Skim kemajuan tanah yang meliputi kawasan seluas 500 hektar atau lebih untuk
menjadikan hutan kepada pengeluaran pertanian.
(b) Kawasan baru penternakan babi yang mempunyai sebanyak 2,000 populasi babi dirian
atau lebih.
2. AERODROM:
(a) Pembinaan aerodrom baharu yang melibatkan landasan terbang sepanjang 1,000 meter
atau lebih.
(b) Pembinaan aerodrom di dalam atau bersebelahan atau berdekatan dengan mana-mana
taman negeri, taman negara, taman laut negara, pulau sekeliling taman laut atau
kawasan sensitif alam sekitar.
(a) Pembinaan tasik buatan manusia dan pembesaran tasik bukan semula jadi dengan
kawasan permukaan seluas 50 hektar atau lebih di dalam atau bersebelahan atau
berdekatan dengan kawasan sensitif alam sekitar.
10
P.U. (A) 195
(b) Mana-mana saliran kawasan tanah bencah, habitat hidupan liar atau hutan darat yang
meliputi kawasan seluas 20 hektar atau lebih.
4. PERIKANAN:
Projek akuakultur berasaskan penggunaan tanah beserta dengan pembersihan hutan paya bakau,
hutan paya gambut atau hutan paya air tawar yang meliputi kawasan seluas 50 hektar atau lebih.
5. PERHUTANAN:
(a) Pengubahan hutan pada ketinggian 300 meter atau lebih di atas purata aras laut kepada
kegunaan lain tanah yang meliputi kawasan seluas 100 hektar atau lebih.
(b) Pembalakan atau pengubahan hutan kepada kegunaan tanah yang lain di dalam—
(i) kawasan tadahan di kolam takungan air yang digunakan bagi bekalan air
perbandaran, pengairan atau penjanaan kuasa hidro;
(ii) kawasan yang bersebelahan atau berdekatan dengan mana-mana taman negeri,
taman negara atau taman laut negara;
(iii) mana-mana taman negeri, taman negara atau taman laut negara; atau
(iv) kawasan yang diwartakan sebagai hutan tadahan air di bawah Akta Perhutanan
Negara 1984 [Akta 313].
(c) Pembalakan, atau penebangan atau pengambilan kayu dari hutan pada ketinggian 300
meter atau lebih di atas purata aras laut yang meliputi kawasan seluas 100 hektar atau
lebih, di luar kawasan hutan simpan kekal.
(d) Pembalakan, atau penebangan atau pengambilan kayu yang meliputi kawasan
500 hektar atau lebih.
(e) Pembangunan ladang hutan yang meliputi kawasan seluas 500 hektar atau lebih.
bagi kegunaan perindustrian, perumahan atau pertanian yang meliputi kawasan seluas
50 hektar atau lebih.
(g) Pembersihan kawasan hutan paya bakau, hutan paya gambut atau hutan paya air tawar
di pulau yang bersebelahan dengan mana-mana taman laut negara.
6. INDUSTRI:
(iii) Peleburan utama bukan besi yang lain (mengeluarkan 50 tan keluaran atau
lebih sehari).
(b) Simen:
(i) Menggunakan bijih besi sebagai bahan mentah bagi pengeluaran 100 tan atau
lebih sehari.
(ii) Menggunakan besi sekerap sebagai bahan mentah bagi pengeluaran 200 tan
atau lebih sehari.
(d) Petrokimia:
Keupayaan pengeluaran setiap keluaran atau gabungan keluaran sebanyak 50 tan atau
lebih sehari.
12
P.U. (A) 195
7. PENEBUSGUNAAN TANAH:
(a) Penebusgunaan kawasan pantai atau penebusgunaan tanah sepanjang tebing sungai
yang melibatkan kawasan seluas 50 hektar atau lebih.
(b) Penebusgunaan kawasan pantai atau penebusgunaan tanah sepanjang tebing sungai di
dalam atau bersebelahan atau berdekatan dengan kawasan sensitif alam sekitar.
8. PERLOMBONGAN:
(a) Perlombongan bahan galian dalam kawasan baharu yang melibatkan operasi berskala
besar.
(b) Perlombongan bahan galian di dalam atau bersebelahan atau berdekatan dengan
kawasan sensitif alam sekitar.
9. PETROLEUM:
10. PELABUHAN:
(a) Pembinaan stesen janakuasa yang menggunakan bahan api arang batu yang mempunyai
keupayaan 10 megawatt atau lebih dengan atau tanpa talian pemancar.
13
P.U. (A) 195
(b) Pembinaan stesen janakuasa yang menggunakan bahan api nuklear dengan atau tanpa
talian pemancar.
(b) di mana-mana pulau dalam perairan sekeliling yang telah diwartakan sebagai taman laut
atau rizab laut di bawah Akta Perikanan 1985 [Akta 317].
(a) Pembangunan atau pembersihan tanah yang meliputi 50 peratus atau lebih kawasan
cerun yang berkecerunan lebih daripada atau sama dengan 25 0 tetapi kurang daripada
350 .
(b) Pembinaan jalan, terowong atau jambatan yang melintasi kawasan cerun yang
berkecerunan melebihi atau sama dengan 350 .
(ii) Pembinaan loji pulih guna luar tapak bagi buangan bateri asid plumbum.
(iii) Pembinaan loji pulih guna luar tapak atau kemudahan rawatan yang
mengeluarkan jumlah air buangan yang ketara yang terletak di hulu
pengambilan bekalan air awam.
14
P.U. (A) 195
(a) Pembinaan empangan atau kolam takungan air bagi maksud pengairan, tebatan banjir,
kawalan pengelodakan, rekreasi, bekalan air atau apa-apa sebab lain dengan kawasan
permukaan seluas 100 hektar atau lebih.
(b) Empangan dan skim kuasa hidroelektrik dengan salah satu atau kedua-dua yang berikut:
(i) empangan yang ketinggiannya 15 meter atau lebih dan struktur sampingan
yang meliputi kawasan seluas 40 hektar atau lebih;
(ii) kolam takungan air dengan kawasan permukaan seluas 100 hektar atau lebih.
16. PENGANGKUTAN:
(a) Pembinaan laluan atau landasan cabang baharu bagi projek pengangkutan laju massa.
(b) Pembinaan landasan laluan atau landasan cabang baharu kereta api.
Mana-mana aktiviti yang dinyatakan dalam Jadual ini dan Jadual Pertama yang menggunakan
bahan radioaktif dan menghasilkan buangan radioaktif.
15
P.U. (A) 195
Citation
1. This order may be cited as the Environmental Quality (Prescribed Activities)
(Environmental Impact Assessment) Order 2015.
Interpretation
2. In this Order—
(a) any area specified as such in the development plan or national physical
plan under the Town and Country Planning Act 1976 [Act 172]; or
Prescribed activities
3. (1) The activities specified in the First Schedule and the Second Schedule are
prescribed activities.
(2) The activities specified in the First Schedule do not require public display and
public comment unless otherwise instructed, in writing, by the Director General.
16
P.U. (A) 195
(3) The activities specified in the Second Schedule require public display and
public comment.
(a) any prescribed activity which has been divided into a size or
quantum smaller than the size or quantum specified in the First
Schedule and the Second Schedule; or
(5) Public display and public comment referred to in subparagraphs (2) and
(3) are a display of a report, at a place and within the time determined by the Director
General, to obtain public comment in relation to that report.
(a) items 2, 6, 9 and 10 and subitems 11(a) and (b) and 14(a) of the
First Schedule; and
(b) items 2, 6, 9, 10, 11, 16 and 17 and subitem 14(a) of the Second
Schedule.
(2) This Order shall apply to the State of Sabah in respect of the prescribed
activities specified in the following items:
(a) items 2, 6, 9 and 14 and subitems 11(a) and (b) of the First
Schedule; and
17
P.U. (A) 195
(2) This Order shall not affect any prescribed activity under the revoked
Order where a report has been approved by the Director General before the coming into
operation of this Order.
(3) A report in respect of any prescribed activity under the revoked Order
which has been received by the Director General before the coming into operation of this
Order shall be dealt with as if this Order has not been made.
(4) If the Director General does not approve the report under subparagraph
(3) and the person who submitted the report re-submits it for approval after the coming
into operation of this Order, the report shall be dealt with in accordance with this Order.
FIRST SCHEDULE
[Subparagraphs 3(1) and (4)]
1. AGRICULTURE:
(b) Development of agricultural estates covering an area of 500 hectares or more involving
changes in types of agricultural use.
2. AERODROME:
18
P.U. (A) 195
(a) Construction of man-made lakes and enlargement of artificial lakes with surface areas of
100 hectares or more.
4. FISHERIES:
Land based aquaculture projects accompanied by clearing of mangrove forest, peat swamp forest
or fresh water swamp forest covering an area of 20 hectares or more but less than 50 hectares.
5. FORESTRY:
(a) Conversion of forest at 300 meters or more above mean sea level to other land use
covering an area of 20 hectares or more but less than 100 hectares.
(b) Logging, or cutting or taking of timber for the purpose of conversion from forest to other
land use covering an area of 100 hectares or more but less than 500 hectares.
(c) Logging, or cutting or taking of timber from forest at less than 300 meters above mean
sea level covering an area of 100 hectares or more, outside permanent reserved forest.
for industrial, housing or agricultural use covering an area of 20 hectares or more but
less than 50 hectares.
(e) Development of planted forest covering an area of 100 hectares or more but less than
500 hectares.
19
P.U. (A) 195
6. INDUSTRY:
(a) Chemical:
Production capacity of each product or combined products of 100 tonnes or more per
day.
(b) Cement:
Cement grinding plant with cement production capacity of 200 tonnes or more per day.
(c) Lime:
Production of 100 tonnes or more per day of burnt lime using rotary kiln or 50 tonnes or
more per day of burnt lime using vertical kiln.
(d) Petrochemicals:
Production capacity of each product or combined product of less than 50 tonnes per day.
(e) Shipyards:
7. LAND RECLAMATION:
Coastal reclamation or land reclamation along river banks involving an area of less than 50
hectares.
8. MINING:
(a) Ore processing outside mineral tenement area, including concentrating of aluminium,
copper, gold, iron, tantalum or rare earth element.
20
P.U. (A) 195
9. PETROLEUM:
(iii) oil and gas separation, processing, handling and storage facilities.
(d) Construction of product depot for the storage of petrol, gas or diesel which has
the combined storage capacity of 60,000 barrels or more (excluding service station)
within 3 kilometres from any commercial, industrial or residential area.
10. PORTS:
(a) Expansion of port involving an increase of 50 percent or more in handling capacity per
annum.
(b) Expansion of fishing port involving an increase of 50 percent or more in fish landing
capacity per annum.
21
P.U. (A) 195
(a) Construction of steam generated power station using fossil fuels (other than coal) and
having the capacity of 10 megawatts or more, with or without transmission line.
(b) Construction of combined cycle power station, with or without transmission line.
(b) Construction of hill-station resort or hotel at 300 meters or more above mean sea level
covering an area of 20 hectares or more.
Development or land clearing less than 50 per cent of an area with slope greater than or equal to
250 but less than 350.
22
P.U. (A) 195
(c) Sewage:
15. DREDGING:
16. HOUSING:
19. QUARRY:
20. ROAD:
23
P.U. (A) 195
Groundwater development for industrial, agricultural or urban water supply of 4,500 cubic
metres or more per day.
SECOND SCHEDULE
[Subparagraphs 3(1) and (4)]
1. AGRICULTURE:
(a) Land development schemes covering an area of 500 hectares or more to bring forest into
agricultural production.
(b) New pig farming area of 2,000 or more standing pig population.
2. AERODROME:
(b) Construction of aerodrome in or adjacent or near to any state park, national park,
national marine park, island surrounding marine park or environmentally sensitive area.
(a) Construction of man-made lakes and artificial enlargement of lakes with surface areas of
50 hectares or more in or adjacent or near to environmentally sensitive area.
(b) Any drainage of wetland, wild-life habitat or of dry inland forest covering an area of 20
hectares or more.
4. FISHERIES:
Land based aquaculture projects accompanied by clearing of mangrove forest, peat swamp forest
or fresh water swamp forest covering an area of 50 hectares or more.
5. FORESTRY:
(a) Conversion of forest at 300 meters or more above mean sea level to other land use
covering an area of 100 hectares or more.
24
P.U. (A) 195
(i) a catchment area of reservoirs used for municipal water supply, irrigation or
hydro-power;
(ii) an area adjacent or near to any state park, national park or national marine
park;
(iv) an area gazetted as water catchment forest under the National Forestry Act
1984 [Act 313].
(c) Logging, or cutting or taking of timber from forest at 300 meters or more above mean
sea level covering an area of 100 hectares or more, outside permanent reserved forest.
(d) Logging, or cutting or taking of timber covering an area of 500 hectares or more.
(g) Clearing of mangrove forest, peat swamp forest or fresh water swamp forest on islands
adjacent to any national marine park.
6. INDUSTRY:
(a) Non-ferrous:
(iii) Primary smelting other non-ferrous (producing 50 tonnes product or more per
day).
(b) Cement:
(i) Using iron ore as raw materials for production of 100 tonnes or more per day.
(ii) Using scrap iron as raw materials for production of 200 tonnes or more per day.
(d) Petrochemicals:
Production capacity of each product or combined product of 50 tonnes or more per day.
7. LAND RECLAMATION:
(a) Coastal reclamation or land reclamation along river banks involving an area of 50
hectares or more.
(b) Coastal reclamation or land reclamation along river banks within or adjacent or near to
environmentally sensitive areas.
8. MINING:
26
P.U. (A) 195
9. PETROLEUM:
10. PORTS:
(a) Construction of coal fired power station and having the capacity of 10 megawatts or
more with or without transmission line.
(b) on any island in surrounding waters which has been gazetted as a national marine park
or marine reserve under the Fisheries Act 1985 [Act 317].
(a) Development or land clearing of 50 per cent or more of an area with slope greater than
or equal to 250 but lesser than 350.
(b) Construction of road, tunnel or bridge traversing an area with slope greater than or
equal to 350.
27
P.U. (A) 195
(ii) Construction of off-site recovery plant for lead acid battery wastes.
(a) Construction of dam or impounding reservoir for the purpose of irrigation, flood
mitigation, control of siltation, recreational, water supply or any other reason with a
surface area of 100 hectares or more.
(b) Dam and hydro-electric power scheme with either or both of the following:
(i) dam of 15 metres or more in height and ancillary structures covering a total
area of 40 hectares or more;
16. TRANSPORTATION:
(a) Construction of new routes or branch line for a mass rapid transport project.
Any activity specified in this Schedule and the First Schedule using radioactive materials and
generating radioactive wastes.
29
Appendix 7
Key:
PROJECT ACTIVITIES
OPERATION AND
SITE INVESTIGATION CONSTRUCTION
MAINTENANCE
Insignificant and excluded from Matrix
√ Environmental impact that is potentially but on a
temporary basis and will assue equilibrium after certain
period of time
PRODUCT STORAGE
Environmental impact that is potentially significant but
EROSION CONTROL
LAND ACQUISITION
ABONDMENT PLAN
ACCESS ROADS
INVESTIGATION
SITE CLEARING
about which there is insutificient data to make a
ABANDOMENT
EXCAVATION
reliable prediction. Close monitoring and control is
DRAINAGE
UTILITIES
SURVEY
recommended
√
Potentially significant adverse environmental impact for
which a design solution has been identified
√
Residual and significant adverse environmental impact
Flood Plains/Swamps
Land Use
PHYSICOCHEMICAL
Flow Variation
Water Quality
Drainage Pattern
Water Balance
Flooding
Existing Use
GROUND
Water Table
WATER
Flow Regime
Water Quality
Recharge
Aquifer Characteristics
Existing Use
ATMOSPHERE Air Quality
Air Flow
Climatic Changes
Visibility
Intensity
NOISE
Duration
Frequency
Terrestrial Vegetation
POPULATIONS
SPECIES AND
Terrestrial Wildlife
Other Terrestrial Fauna
Aquatic/Marine Flora
BIOLOGICAL
Fish
Other Aquatic/Marine Fauna
Terrestrial Habitats
HABITATS AND
COMMUNITIES
Terrestrial Communities
Aquatic Habitats
Aquatic Communities
Estuarine Habitats
Estuarine Communities
Marine Habitats
Marine Communities
Physical Safety
HEALTH AND
SAFETY Psychological Well-Being
Parasitic Disease
Communicable Disease
Physiological Disease
Employment
SOCIAL AND
Housing
ECONOMIC
Education
Utilities
HUMAN
Amenities
Property & Settlement
Landforms
AESTHETIC AND CULTURAL
Biota
Wilderness
Water Quality
Atmospheric Quality
Climate
Tranquility
Sense of Community
Community Structure
Man-Made Objects
Historic Places or Structure
Religious Places or Structure
Landscape
Appendix 8
A. INTRODUCTION
The process for preparing an Environment Impact Assessment (EIA) report can be a
rather complicated and long process, especially if the project itself is a mega project
involving multiple disciplines and located within a sensitive environment. In this
regard, DOE needs to streamline the initial information that is provided by the Project
Proponent at the conception stage of the project in accordance with the Section 34A
(2C) of Environmental Quality Act 1974, so as to steer the Project Proponent in
preparing a „focused‟ EIA report which would be used to address all significant
environmental issues that are predicted in the EIA during the construction and
operational stage.
The TOR document can provide DOE with a snapshot picture of the Project
Proponent‟s overall project scheme and his plan for addressing potential
environmental issues that are predicted to arise at the early stage of the project. The
TOR is also a good indication that the Project Proponent (and his consultants) have
given adequate consideration in the potential environmental issues that may arise
during the construction and operation of the project, and that relevant mitigating
measures are well thought early enough to be incorporated into the design and
planning of the construction & operational methodologies for the project. More
importantly, however, the TOR serves as the “blueprint” for the Environmental
Impact Assessment which will be prepared by the Project Proponent, and to facilitate
the DOE during the review and vetting of the completed EIA report.
1
the “executive summary” of the ESI, which can also be used to outline the skeletal
framework for the EIA report to be prepared in detail at the later stage.
The contents of a typical TOR are shown below, as an example. This should not be
taken as a “fix format” for a TOR because all projects are different and the Project
Proponent should prepare a specific TOR that suits his project needs. The sample
TOR shown below is for guidance only.
No Contents Description
1 Introduction This Terms of Reference is for the preparation of an
Environmental Impact Assessment (EIA) Study for “Project
Title”
2 List of Details of each individuals (must be registered with DOE)
Consultants/ who will carry out the EIA study, which include:-
Study Team
DOE Registration number.
Academic background.
Experience.
Area of study.
Declaration (signatures).
3 Scope of List out those components of the Project which fall under the
Project Prescribed Activities under the EIA Order, and describe with
enough details to understand the scope of the significant
project work components, without the technical details,
including a well described engineering implementation
programme of the Project.
4 Alternatives Outline alternative solutions (project site, technologies, etc)
Consideration that will be studied or described to justify that the Project will
result in the least environmental impacts.
5 Significant List and describe those significant environmental impacts
Environmental which will potentially be affected by the project works or
Impacts to be components which will need to be covered in detail in the
studied EIA
6 Study Delineate study boundaries for each of the above significant
Boundaries environmental elements to be investigated, and identifying
the critical groups of sensitive receptors and how the impacts
2
No Contents Description
on the sensitive receptors will be studied
7 Assessment List out standards, criteria, acceptable limits, etc that will be
Standards used to assess the environmental impacts to be investigated.
8 Timeline of Details of all studies/investigations to be carried out: who,
studies where, when, how, etc. with indicative dates
9 Consideration List out potential concurrent or planned project that may
of Concurrent result in cumulative impacts
Projects
10 Description of List out modelling tools, methodologies, etc for undertaking
modelling impact assessment and evaluation of significance. The
tools, extent of accuracy of these tools will also need to be
assessment provided, including, name of models, applicability of models
methodologies and tools, verifiability of results, how results are verified, grid
size (for water modelling)
11 Possible Outline possible mitigation measures or best management
Mitigation practices from similar projects that may be used to address
Measures the environmental impacts on this project.
1. Purpose of ESI
As mentioned above, the ESI provide further elaboration to the Terms of Reference,
by demonstrating to DOE that the Project Proponent has given due consideration to
his project and the potential environmental issues that may result from the
construction and operation of the project. Scoping is a critical activity which should
take place at the early stage in the EIA process. It is designed to identify and assess
the key environmental impacts and issues of concern that are required to be
considered in detail during the EIA for a particular project. Scoping shall ensure that
matters which are of most importance are addressed in most detail and valuable
resources are not spent on nonsignificant matters.
From the DOE‟s perspective, the purpose of scoping is for the Project Proponent to
identify the matters which shall be covered in the environmental information to be
submitted to the DOE. The scoping activity will result in the preparation of an
Environmental Scoping Information (ESI).
3
In general, an ESI is prepared to identify the key concerns associated with a
proposed Project and specifically will serve the following purposes:
4
i. Introduction to ESI
5
Name and Telephone Number of Contact Person: Provide contacts of key
personnel of Project proponent, normally no more than 2 persons.
iii. Alternative Consideration
Outline alternative solutions (project option, project site, technologies, etc)
that will be studied or described to justify that the Project will result in the
least environmental impacts.
iv. Major Elements of the Environment in the Vicinity of Project Site and
Study Boundaries
Air Quality: Briefly describe the prevailing air streams and wind directions
at the Project site, and identify the list of air sensitive receivers within a
study boundary of 500 m
Noise and Vibration: Briefly describe the existing noise contributors around
the project site, and identify the list of sensitive noise receptors within a
study boundary of 500 m
Water Quality: Briefly describe the existing waterbodies and rivers around
the project site, and identify the list of water sensitive receivers within a
study boundary of 500 m
Hydrology and Hydrogeology: Briefly describe the hydrology and
hydrogeology around the project site within a study boundary of 1000 m
Flood risk: Briefly describe the existing risk of flooding and flood defense
infrastructure around the project site within a study boundary of 500 m
Erosion risk: Briefly describe the existing risk of erosion and erosion
mitigation infrastructure around the project site within a study boundary of
500 m
Waste Management: Briefly describe the existing sources of solid and
hazardous waste arising around the Project site within a study boundary of
3 km.
6
Ecology: Briefly describe the existing habitats (land and marine, including
bathymetric characteristics for marine projects) around the Project site
within a study boundary of 500 m.
Cultural Heritage: Briefly describe any historical evidence of cultural
importance around the Project site within a study boundary of 500 m.
Land Contamination: Briefly describe the existing and previous land uses
around the Project site that may have caused any land contamination
within a study boundary of 500 m.
Groundwater: Briefly describe the existing uses of groundwater around the
Project site and the existing and previous land uses that may have caused
any groundwater contamination within a study boundary of 1000 m.
Landuse, Landscape and Visual: Briefly describe the existing landuse and
landscape around the Project site within a study boundary of 500 m and
identify a list of visually sensitive receptors.
Traffic: Briefly describe the existing traffic conditions around the Project
site within a study boundary of 3000 m.
Hazards and Risk Assessment: Briefly describe any existing hazardous
installations around the Project site or risks associated with the project
itself within a study boundary of 500 m (including possibilities such as
seismic & geological events)
Socio-economy: Briefly describe the socio-economic conditions around the
Project site within a study boundary of 500 m.
Geology: Briefly describe the topographical and geological features around
the Project site within a study boundary of 500 m, and may include
information on mineral deposits and soil characteristic.
7
Project Time Table: Provide indicative dates when the project will
commence and end.
Interactions with other Projects: List out all concurrent or planned projects
in the vicinity of this Project. The purpose of this list is to enable DOE to
assess the significance of cumulative impacts from all the projects.
Project Assessment Timeline: Provide a proposed target timeline for the
whole assessment process. The time table for proposed studies and
investigations shall be included, and as a minimum, shall include:- TOR
submission; TOR public review (if relevant); environmental studies;
consultation program; EIA report submission; EIA report public
display;
Project proponent’s response to public comments.
Proposed studies: Describe scope of works of
studies/investigations/surveys that will be undertaken to obtain the
baseline information on the major elements of the environment.
Outline the methodologies used in the impact analysis/ assessment and provide a
brief qualitative description of the potential impacts during construction and
operational phases of project implementation on the following:
Air Quality
Noise and Vibration
Water Quality
Hydrology and Hydrogeology
Flood risk
Erosion risk
Waste Management
Ecology
Cultural Heritage
8
Land Contamination
Groundwater
Landuse, Landscape and Visual
Traffic
Hazards / Risk Assessment
Socio-economy
Geology
Outline and describe any relevant information that is referenced from the
previous EIAs or studies that were identified in Section 3(ii) above and briefly
discuss how this information is suitable to be used for this Project.
9
An updated satellite image to indicate the recent existing environment may
be used. The coverage of the landuse map must be at least within 5 km
radius (interval of 250m). For large scale projects such as the construction
of dams or impounding reservoirs, the coverage of the landuse map may
be beyond 5 km radius depending on the catchment area.
Other types of map that may be relevant to the key and critical issues of
the proposed Project. They may include cadastral map, topography and
geological map, bathymetry map, hydrological map, coral population map,
etc.
For industrial-based projects, clear and readable flow chart of the
production processes and explanation on the processes and the Project’s
maximum capacity
x. References
Provide a list of documents and studies used to prepare the Environmental Scoping
Information (ESI).
Note: The items listed in Section 3 are not exhaustive. Other items shall be
included whenever relevant.
Issued by:
Director General
Department of Environment
July…., 2016
Note: Please submit three (3) hardcopy and a softcopy (in PDF format) of the Term
of Reference with Environmental Scoping Information to:
Director General
Department of Environment
Ministry of Natural Resources & Environment
Level 1-4, Podium 2 & 3, Wisma Sumber Asli
No. 25, Persiaran Perdana, Precinct 4
62574 PUTRAJAYA
(Attn. to: Director of Assessment Division)
10
Appendix 9
PROJECT TITLE
VOLUME X/Y
MONTH/YEAR
1
Table of Content
Project Proponent’s Declaration
Consultant’s Declaration
Executive Summary in Bahasa Malaysia and English
Chapter 1: Introduction
Chapter 2: Terms of Reference of EIA Study
Chapter 3: Statement of Need
Chapter 4: Project Options
Chapter 5: Project Description
Chapter 6: Existing Environment
Chapter 7: Evaluation of Impacts
Chapter 8: Mitigation Measures
Chapter 9: Environmental Management Plan (EMP)
Chapter 10: Study Findings
References
Appendices
The format of the Report and its content are explained as follows:-
2
company of the Project Proponent as follows:-
“I hereby declare that the entire EIA Report is the product of the
Qualified Person (i.e. the EIA Consultant) engaged by my
company and all the facts stated in the Report and the
accompanying information are to the best of my knowledge and
belief true and correct, and that I have not withheld or distorted
any material facts. I agree and I undertake the responsibility to
implement all the pollution prevention and mitigation measures
(P2M2s) described in the EIA Report, in the Environmental
Management Plan (EMP), and in the LD-P2M2* as proposed by
the EIA Consultant. I have allocated sufficient funds for the
above purpose.
4
(i) Name / Title of project
(ii) A description of the project and the environment
(iii) Name and contact details of the Project Proponent
(Contact person, address, telephone number, e-mail
address)
(iv) Name of the registered EIA consulting firm and contact
details (EIA team leader, address, telephone number, e-
mail address)
(v) Location of the project (including where applicable,
coordinates, lot numbers, sub-district and district name)
(vi) Relevant maps showing project location and sensitive
receptors
(vii) Flow diagrams of main processes (for industrial and other
relevant activities)
(viii) A tabulation of potential impacts, their magnitude and
proposed pollution prevention and mitigation measures
(P2M2s) as shown below:
(Notes-
*P2M2s: Pollution prevention and mitigation measures.
P2M2s shall be those which can be described as state of
5
the art technologies or best available technologies, or
industry best practices.
** Reference page: page in the EIA Report)
(ix) A description of performance monitoring (PM) program
and compliance monitoring (CM) for pollution prevention
and mitigation measures (P2M2) and tabulation of
relevant PM parameters, recommended limits, monitoring
locations and frequencies.
(x) Whenever applicable, a description of impact monitoring
program (IM), monitoring locations and frequencies.
6
Chapter 1: Introduction
1.1 Title of Project
The project title shall identify the type of proposed project and its
specific location. The title shall also indicate if the project is part of a
larger project proposal.
7
1.3 Legal Aspects
This chapter shall provide the TOR of the EIA study which has been
endorsed by the DOE. The reference of the endorsement shall be cited
(example TOR meeting or DOE’s letter).
8
Chapter 3: Statement of Need
The statement of need shall outline the background of the project and
the reasons for it being proposed. It shall establish social, economic or
other needs for the project and shall conclude with a definitive
statement of the aim of the project. The statement of need for the
proposed project shall be substantiated.
This chapter shall discuss project options including the advantages and
disadvantages from the perspective of technical, economic, social, and
environmental aspects of the following alternatives (wherever
applicable):
(i) Site Options
(ii) Project Options (including “no project option”, and
“scaled-down project option”)
(iii) Technology Options
(iv) Raw Materials Options
(v) Construction Method Options
(vi) Layout Options
(vii) Alignment Options
(viii) Operation Options
10
(iii) Special attention is given to environmental sensitive areas, and
areas of special or unique scientific, socio- economic or cultural
values
11
7.2 Detailed Examination of Impacts
13
This subchapter contains a discussion of all the mitigation
measures which have been adopted and incorporated into the
design and implementation of the project to effectively eliminate,
prevent, minimize predicted adverse impacts. For each
potential adverse impact, at each stage of project
implementation, the mitigation measure shall be
identified, documented and costed. Mitigation measures
include all actions and activities taken, put in place, or
executed which could be structural, non -structural,
procedural, or administrative in nature, to mitigate the
adverse impacts. The Project Proponent shall provide
evidence to show his commitment to implement all the
proposed pollution prevention and mitigation measures
(P2M2s).
14
impact monitoring (IM). Each type shall be detailed out in this
chapter.
References
Provide full citation of all the references used.
Appendices
The appendices may include the following:
(a) Input data and results of any modelling studies (soft and hard
copy)
(b) Supporting documents such as Site Suitability Assessment,
Environmental Scoping Information, etc.
(c) Other relevant documents such as list of attendance, meeting
minutes, and photographs of public engagements, etc.
16
17
BMPs Description
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
DEFINITION
PURPOSE
APPLICATION
2
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
DEFINITION
PURPOSE
APPLICATION
3
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
4
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
V NURSERY
DEFINITION
Explore the existing site sources that can benefit the potential material for
erosion control such as topsoil, rocks, biomass, existing vegetation and make
use of existing native vegetation to establish seedbed preparation or grass
growing and plant nursery.
PURPOSE
To make use of the existing site sources materials for erosion and sediment
control which may minimize cost and time in the materials procurement.
APPLICATION
5
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
RUN-ON RUNOFF
DEFINITION
PURPOSE
APPLICATION
Earth dikes are often constructed across disturbed areas and around
construction sites. The dikes shall remain in place until the disturbed areas
are permanently stabilized.
6
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
KALP -2 DIVERSION
DEFINITION
PURPOSE
APPLICATION
7
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
DEFINITION
PURPOSE
APPLICATION
2. Steep grades, prolonged base flow, seepage, or piping that would cause
erosion.
8
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
DEFINITION
A drain running along the side of a road or track to collect runoff from the
road/track surface.
PURPOSE
To prevent silt from overflowing to road surfaces, the bare earth strip
between the drain and the road must be turfed to serve as a buffer strip.
APPLICATION
9
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
DEFINITION
These are concrete stepped catch drains laid on the steep terraced slopes.
PURPOSE
To guide flows from the berm drains down to catch drains at the base.
APPLICATION
• Any cut and fill slopes at construction sites where there is a need to
channel concentrated flow down slopes.
10
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
KALP -6 RIPRAP
DEFINITION
Riprap is a layer of large stones laid onto slopes and channel beds.
PURPOSE
APPLICATION
Use riprap to stabilize cut-and-fill slopes with 1:2 slope; channel side
slopes and bottoms; inlets and outlets for culverts, bridges, slope drains,
grade stabilization structures, and storm drains; and streambanks and
grades.
11
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
DEFINITION
PURPOSE
APPLICATION
12
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
DEFINITION
PURPOSE
APPLICATION
13
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
KALP 9 SWALES
DEFINITION
Swales are temporary or permanent channel, which may be lined with natural
vegetation, synthetic materials, or rock.
PURPOSE
APPLICATION
14
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
DEFINITION
PURPOSE
To convey storm water runoff down the face of a cut or fill slope without
causing erosion on or below the slope.
APPLICATION
Temporary slope drains are used where sheet or concentrated storm water
flow could cause erosion as it moves down the face of a slope.
15
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
DEFINITION
Paved and/or riprapped channel treatment, placed below storm drain outlets
or any discharge outlets.
PURPOSE
To reduce storm water velocity and dissipate the energy of flow leaving a
storm drain or discharge outlets before it empties into receiving channels,
To prevent scour at storm water outlets and to minimize the potential for
downstream erosion through velocity dissipation.
APPLICATION
Applicable to all storm drain outlets, road culverts, paved channel outlets and
discharge outlets.
16
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICE
(RUNOFF CONTROL)
DEFINITION
PURPOSE
APPLICATION
17
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
(RUNOFF CONTROL)
DEFINITION
Measures such as silt fence, sandbag, and fiber roll, installed around any
storm drain inlet;
PURPOSE
APPLICATION
18
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KH KAWALAN HAKISAN
(EROSION CONTROL)
KH 1 MULCHING
DEFINITION
PURPOSE
APPLICATION
19
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KH KAWALAN HAKISAN
(EROSION CONTROL)
KH-2 REVEGETATION
DEFINITION
PURPOSE
APPLICATION
Any completed graded area such as bare area, slope surfaces and areas
meant to be vegetated permanently.
20
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KH KAWALAN HAKISAN
(EROSION CONTROL)
KH-3 HYDROSEEDING
DEFINITION
Hydroseeding or may also be called hydromulching ( if no seed is applied) is
a mechanical method with forced water of applying seed, fertilizer, and mulch
to land in one step in order to re-vegetate.
PURPOSE
APPLICATION
21
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KH KAWALAN HAKISAN
(EROSION CONTROL)
DEFINITION
PURPOSE
To protect the soil surface from erosive forces and/or improve the stability of
soil slopes.
APPLICATION
Where cut and fill slopes are subject to seepage, erosion, or weathering,
particularly where conditions prohibit the establishment of vegetation.
22
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KH KAWALAN HAKISAN
(EROSION CONTROL)
KH - 5 PLASTIC COVER
DEFINITION
PURPOSE
APPLICATION
23
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KH KAWALAN HAKISAN
(EROSION CONTROL)
DEFINITION
PURPOSE
To protect soil and hold seed and mulch in place on slopes and in channels
so that vegetation can become well established.
APPLICATION
24
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
• Concentrated flow areas.
• All slopes steeper than 1:2, with a height of three metres or greater,
and cuts and fills within stream buffers, should be stabilized with the
appropriate erosion control matting or blanket.
Notes
• Nets are made of high tensile material woven into an open net which
overlays mulch materials.
25
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KH KAWALAN HAKISAN
(EROSION CONTROL)
DEFINITION
PURPOSE
To loosen compacted soil on a slope that has been cleared and graded, cut,
or filled as well as creates small grooves or terraces which reduce runoff
velocity, trap seed, fertilizer and sediment, and provide more favourable
conditions for vegetation establishment.
APPLICATION
26
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KS KAWALAN SEDIMEN
(SEDIMENT CONTROL)
DEFINITION
PURPOSE
APPLICATION
27
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Notes
The trap has a discharge point over or cut into natural ground.
The outlet for the trap is though a perforated riser and a pipe through the
embankment. The outlet pipe and riser shall be made of corrugated metal.
The outlet for the sediment trap shall consist of a crushed stone section of
the embankment located at the low point in the basin. The outlet shall be
constructed of crushed stone.
The trap has a discharge point through an opening in a storm drain inlet
structure. This opening can either be the inlet opening or a temporary
opening made by omitting bricks or blocks in the inlet.
28
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KS KAWALAN SEDIMEN
(SEDIMENT CONTROL)
DEFINITION
PURPOSE
APPLICATION
29
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KS KAWALAN SEDIMEN
(SEDIMENT CONTROL)
DEFINITION
PURPOSE
APPLICATION
• Applicable whenever travel ways are needed around poor soils area
in a construction site of which the exposed soil is continually
disturbed which eliminating the possibility of stabilization with
vegetation.
30
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KS KAWALAN SEDIMEN
(SEDIMENT CONTROL)
DEFINITION
A fiber roll consists of straw, flax, coconut husk or other similar materials that
are rolled and bound into a tight tubular roll and placed around the worksite
perimeter and is referred to as wattles when placed on the face of slopes at
regular intervals.
PURPOSE
• To intercept runoff.
• To reduce runoff flow velocity.
• To release the runoff as sheet flow.
• To provide some removal of sediment from the runoff.
APPLICATION
• May be used along the top, face, and at grade breaks of exposed and
erodible slopes to shorten slope length and spread runoff as sheet flow.
• Install on disturbed areas that require immediate erosion protection.
• Can be used along the perimeter of a project.
• Unlined ditches as a check dam
• Around temporary stockpiles
31
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KS KAWALAN SEDIMEN
(SEDIMENT CONTROL)
DEFINITION
PURPOSE
To prevent sediment carried by sheet flow from leaving the site and entering
natural drainage ways or storm drainage systems by slowing storm water
runoff and causing the deposition of sediment at the structure. Silt fencing
encourages sheet flow and reduces the potential for development of rills and
gullies.
APPLICATION
32
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KS KAWALAN SEDIMEN
(SEDIMENT CONTROL)
DEFINITION
PURPOSE
33
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
APPLICATION
34
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KS KAWALAN SEDIMEN
(SEDIMENT CONTROL)
DEFINITION
PURPOSE
By properly packed and stacked, the branches layer placed on the berm or
terrace step and covering the slope as mat may function to intercept and
retain sediment from disturbed areas of limited extent, preventing sediment
from leaving the site.
APPLICATION
35
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KS KAWALAN SEDIMEN
(SEDIMENT CONTROL)
DEFINITION
Active treatment system refers to the water treatment process of which, the
sediment-laden runoff collected in pond are pump into a container (geo-tube
bag). In the process of pumping the turbid waters, online injection of site-
specific polymers/PAM are introduce to the turbid waters in such a manner to
facilitate mixing and reaction between the polymer and the suspended
particles. Upon reaching into the geo-tube bag, the turbid waters will start to
coagulate and subsequently flocculate or agglomerate stage proceeds in the
pipe line and bag. A pulsing pump used to pressure the geo-tube bag leading
to permeation of clear water through the geo-tube bag container wall or also
known as dewatering bag leaving the sediment behind.
36
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
PURPOSE
• To bind and stabilize soil particles.
• To treat turbid water prior to discharge into receiving watercourse.
APPLICATION
• Any bare areas that need to be immediately stabilized.
• Along the runoff conveyances that lead to sediment trapping device.
• Recommended for use when treatment of sediment-laden runoff
especially dealing with fine clay soil type using sediment basin BMPs
are not effective enough to reduce the turbidity and suspended solids
in the water prior to be discharge into the watercourse.
37
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
KS KAWALAN SEDIMEN
(SEDIMENT CONTROL)
DEFINITION
A temporary stream crossing is a structure placed across a waterway, which
allows vehicles to cross the waterway during construction without entering
the water, eliminating erosion and downstream sedimentation caused by the
vehicles.
PURPOSE
• To provide safe, environmentally sound access across a waterway for
construction equipment.
Where heavy construction must be moved from one side of a stream channel
to the other and equipment and construction vehicles will cross the stream
repeatedly during construction.
38
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
DEFINITION
PURPOSE
APPLICATION
39
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
KLL -2 LIMITS OF CONSTRUCTION
DEFINITION
PURPOSE
• This will physically delineates areas and clearly limits the construction
activities that can take place while limiting the disturbed area to the
minimum deem necessary.
APPLICATION
40
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
DEFINITION
PURPOSE
APPLICATION
41
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
KLL-4 VEHICLE AND EQUIPMENT FUELING AND MAINTENANCE
DEFINITION
PURPOSE
APPLICATION
These procedures are applied on all construction sites where vehicle and
equipment fueling and maintenance take place.
42
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
KLL-5 SOLID WASTE MANAGEMENT AREA
DEFINITION
These are procedures and practices to collect and dispose all construction
sites waste at a designated location and containers/trash bin.
PURPOSE
APPLICATION
43
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
DEFINITION
PURPOSE
To establish a document and describe the systems and procedures
developed to mitigate environmental impacts during handling, transportation,
stockpiling and disposal of spoil materials such as develops or prepares a
separate ESCP.
APPLICATION
Implemented in all projects that generates surplus of earthen materials,
unsuitable materials and biomass. Spoil management area should be located
on relatively flat land, in areas away from watercourse, away from
threatened plant species and fauna habitat areas, away from steep slopes
and gullies, upstream of sediment basins; and so that material is easily
accessible and may be retrieved at any time.
44
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
DEFINITION
PURPOSE
To stabilize staging area and reduces the likelihood that the vehicles most
frequently entering a site are going to come in contact with mud.
APPLICATION
45
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
DEFINITION
PURPOSE
APPLICATION
46
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
KLL-9
DEFINITION
PURPOSE
APPLICATION
47
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
KLL-10 SANITARY WASTE MANAGEMENT
DEFINITION
PURPOSE
APPLICATION
48
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
Item
BMPs
Coding PRACTICES
DEFINITION
PURPOSE
To failsafe the primary containment (vessel or tank wall) that leaks or spills
from flowing out further into drainageway or watercourses before recovering
action to be taken.
APPLICATION
49
JADUAL 2 : PENERANGAN BMPs
(BMPs DESCRIPTION)
KKL-12 DUST CONTROL & STREET CLEANING
DEFINITION
Practices to collect and remove tracked sediments that have escaped the
perimeter of the construction site.
PURPOSE
APPLICATION
Anywhere sediment is tracked from the project site onto public or private
paved roads, typically at points of ingress and egress.
50