Chapter 4
Chapter 4
Chapter 4
1. Introduction
This chapter analyses, presents and discusses the responses gathered from the study via the
questionnaires and interviews. Project managers, procurement managers, site supervisors, project
engineers, consultants and clients from various institutions were interviewed and questionnaires
were sent to them to get their responses in relation to the research being conducted.
the total population. These were made up of twenty (20) construction firms and (10) construction
consulting companies and fifteen (15) clients or companies who have awarded construction
contract were selected via purposive sampling method. There were fifty (50) workers from the
construction companies availing themselves to answer the questionnaires and interview whiles
the consulting companies had fifteen (15) respondents from the consulting firms.
Construction companies. 20 15 75
Consulting firms. 10 8 80
Clients. 15 10 66.66
1.1.2. Table for respondents for the workers
Respondent Study population Sample size Percentage
Construction companies. 70 50 75
Consulting firms. 20 15 80
Clients. 15 10 66.66
the person has been working with the company. His level of specialization and the role is playing
on the project. Also, the position he plays on the organizational ladder in relation to the company
he is working for.
determine their level of training towards the work they are doing especially formal academic
training. Also, it will help the researcher to know how best they will understand the purpose of
the research and what they seek to find. Out of the fifty (50) respondents from the construction
companies 35 of them had Tertiary education whiles the 15 had secondary education. Six of the
clients were corporate bodies whiles four (4) were private individual who had tertiary education.
the answers provided, there was the need for the researcher to know the area of specialization for
the respondent. Since the research is about the construction industry and the various players in
there, most of the respondents were Civil Engineers, Procurement Professionals, Project
Managers, Site Managers, Architect, Quantity Surveyors and Health Safety and Environmental
officers. These were mostly from the construction companies and consulting firms, however,
most of the client had little or no background in construction since some of them were corporate
bodies The table below represent the various professions and the numbers that contributed to the
research.
Most of the respondents were Civil Engineers, Quantity Surveyors and Architect, with foremen,
procurement officers forming the minority of the respondents. Most of the clients where
Years of experience
The years of experience for the various respondents were established to know the requisite
practical and on the field skill they bring to the work. This will inform us as to how best they will
deal with the pandemic and solutions they will provide in resolving the issues that confronted the
industry and the project they were on during the pandemic area.
From the table above, it is evident that majority of the respondents had one to five years of
experience in their respective fields. This is followed by eleven (11) to fifteen (15) years of
experience which makes up the largest number of people with experience. This makes us to
understand that most of the people who respondent to the questionnaires and availed themselves
The number of years an employee has worked with the company will help to determine the
influence he has in the company and the psychology behind the decisions they make. Since most
of the decision made during the covid-19 pandemic area was made by mostly top management
Total 65
From the table above most of the workers have been with their company for the three years,
which indicate that most them were either recruited for the project or joined the company not too
long ago. Also, there are many people who have been with the company for an appreciable
To be able to understand the perspective of each of the respondents on the various project, their
ole on the project needs to be determine. The role a person plays on the project determines the
authority and influence he yields in relation to decision making and the implementation as well.
1 Project Managers 10 20
2 Site Managers 10 20
3 Quantity Surveyors 8 16
4 Procurement officers 7 14
5 Project engineers 10 20
6 HSE officers 5 10
With reference to the table above, most of the respondents served as Project Managers, Site
Managers and Project Engineers. From further enquiries, most of the architect are made project
managers who have the ultimate power and control over the project. The project engineers and
quantity surveyors were the next to follow especially that of the consultants. Most of the
consulting companies have engineers and quantity surveyors as their representative on the
project.
Category of staff
In order to know the power and influence the respondents have on the project and in the
company at large, the researcher wanted to know the position the respondents have in either the
construction, the consulting and client’s company. This will help the determine the weight of the
responses they give especially in relation to decision making and implementation of the decision.
Category of staff
Management
15%
31% Senior Staff
Junior Staff
54%
The pie chart above indicates the categories of staff members that served as respondents for the
research. Majority of the respondents were senior staff whiles junior and management level staff
were followed as second and third highest staff. The data provides a faire balance in the
This section wanted to know the type of construction projects the respondents were doing during
the covid-19 pandemic area. This will bring to light a better understanding of the adverse effect
of the pandemic and the solutions proffered to resolve the problem. Even though the
concentration of the researched was centered on building construction project, respondent that
were not doing building construction project were given the opportunity to indicate the project
they were doing so as to help draw a relation between the various project they are doing.
12
12
10
6
6
4
4
3
2
0
Building construction Road construction Bridge construction Mining engineering
construction
From the above graph, it is clear that most of the respondents were doing building construction
projects whiles the road construction and the other construction areas followed. Since majority of
the respondents were into building construction project, it will provide a correct representative
Baseline Duration
The baseline duration is the planned schedule of the project after its approval by the relevant
stakeholders (Sabestian, 2022). This is set at the beginning of the project which is then followed
to ensure the project complete on time. The researcher wanted to know the baseline duration of
12
48%
10
8
32%
6
4 20%
0
One Two Three Four
0
The graphical representation indicate that majority of the companies were involved with project
with a baseline schedule of two years. Most of them were in their second year of the project
when the pandemic started with about forty percent (40%) of the work left to be done. This
electrical installation telecommunication lines and plumbing works. This is a good indication
that majority were in the process of hiring specialist in the installation of the above services and
infrastructure and also the purchases of these materials has also commenced whiles some were
The success of every project is the sole aim of every stakeholder involved in the project. The
criteria for determining project success lies in the project requirement and set by the stakeholders
of the project. In order to determine the what the project stakeholders consider as key to the
success of the project the researcher decided to make enquiries on that. Also, this will help to
know the extent the pandemic will affect the project depending on which aspect of the project the
pandemic really affected. Below represent the what the respondent considers as vital in relation
0 5 10 15 20 25 30
In soliciting information from respondents in relation to the success criteria they see to be key in
determining projects success, additional interview was done in addition to the questionnaire.
The criteria most clients and company consider as vital to the success of their construction
project is that, the project satisfy their clients or meet their expectations. Staying within budget is
the next most important criteria due to the capital-intensive nature of construction projects. Most
of the respondents stated that, though quality and completion on schedule is important to them, it
has become difficult trying to get project to be completed within schedule in the country.
projects, contractors, clients and consultants were asked whether the pandemic affected the
project they were undertaking. The pie chart is an illustration of the answers respondents
14%
yes
no
86%
The graph above is an illustration the number of respondents who admitted that the covid-19
affected the projects they were on. This is an indication that the covid-19 pandemic had a wide
spread effect on the construction projects being undertaken in the country. The remaining
questions were to solicit further information in relation to how the pandemic affected the
projects.
Effect on Cost
The effect of covid-19 on cost was to be accessed to ascertain the extent it affected the cost of
the project. Respondents were asked if the pandemic affected the cost of the project which they
were to answer in a straight forward answer. It was then followed up the difference it had on the
14%
yes
no
86%
It was categorical that the pandemic had a direct effect on the cost of the projects. There were
several complains as to how the covid-19 pandemic had an escalating effect on the total cost of
the project hence an increase in the final cost of the project. Managers stated that several
negotiations went on during the pandemic to ensure the escalations are contained within limit
Since there was direct effect of the pandemic on cost, the researcher wanted to know the
difference between the planned cost and the actual cost of the project. This was to be determine
in percentage wise thus the percentage difference between these cist groups.
effect covid had on the project. With majority of the respondents stating a difference of 40%
escalation of actual cost over planned cost meant contractors will have to devise ways of dealing
with the increase in cost during the pandemic. With an average of twenty-five (25%) of
increment in the total cost, contractors had to negotiate with clients to settle an amicable way of
Due to the wide effect of the pandemic, construction resources around the world were affected
which resulted in the adverse effect on ongoing projects being undertaking. Respondents were
taken through a series of questions that was to illicit answers on how the resource management
with respect to the pandemic as handled. The first question that was asked is find out if the
pandemic had a direct effect on resources as was experienced by other countries. The graph
14%
yes
no
86%
The number of respondents that affirm to the effect of covid-19 on project resources were the
same as those for the cost. There was a direct price escalation effect of resources that affected the
cost of the project especially those that were imported from outside the country.
In order to understand the extent of price differential of material resources between budget and
actual cost, the researcher enquire from the respondents the rate of the differences between the
Percentage of total
Percentage difference Number of companies respondents
1%-10% 7 27%
11%-20% 4 15%
20%-30% 10 38%
30%-40% 5 19%
Average 25%
From the table above ten of the respondents which represented the majority confirmed to
experience twenty to thirty percent of price escalation in relation to materials cost. This
eventually affected the rate of supply of materials to site with a rippling effect on schedule.
Human Resources
The human capital at every construction site is pivotal to the success of the project. The various
restrictions that were impose on human movement as a measure to control the spread of the
pandemic, the researcher wanted to know if the respondents had the needed or requisite human
resources for the projects. The table below represent the responses from the sample size.
Availability of Human Resouces
14%
yes
no
86%
With respect to human resource availability, majority of the respondents affirmed that they had
the needed human resources especially residential construction works around mining areas which
considered as part of the mining projects. Majority of the construction works going on in the
cities experience temporary shortage of labour as managers had to comply with government
policy to ensure availability of resources. It is clear from the table above that, there was quite a
close gab between the shortage and availability of human resources for construction works.
The supply chain management of resources to site is key to a successful resources management
and prevent major delays to the project. As stated by (Keely L Croxton, 2001) the management
of an organization's core business network is included in the supply chain. It behooves on the
construction organization to ensure the right mechanisms are put in place to prevent supply chain
disruption. The bar chart below explains the results from the respondents.
Projects with Supply Chain
Disruptions
86%
14%
yes no
The bar chart above shows that 86% of the respondents attested to the fact that they experienced
supply chain disruption. The large confirmation of supply chain disruption is an affirmation of
the global effect the pandemic had on construction industry. The supply of material from Asia
and Europe had the greatest impact as container and ship prices increased immensely during the
pandemic. This also had a resulting effect on the prices of the material being bought therefore
Which aspect of the project had the highest impact by the pandemic
The major areas where the pandemic had a devastating effect was to be examine by the
researcher. In view of this, the respondents were asked to identify the major areas they had major
impact from the pandemic. This was done in relation to the major areas being considered in the
research that is resources, schedule and cost. The graph below shows the major areas of project
11% 14%
Resources (Human and material)
Schedule
74%
From the table above, cost was the largest impacted area of the project being undertaking. Most
respondent attested to the fact that the cost of the project increased significantly and that affected
their profit margins. Also, the delay in the arrival and the increase in prices of the resources also
led to the increase of the cost of the project. Subsequently affecting the schedule for the projects.
Certain interventions were introduced to reduce the spread of covid across many countries that
were suffering from the effect of covid-19. These interventions included ensuring social distance
among construction workers, people not crowding at places, wearing of nose masks and
constantly washing your hands to prevent touching your mouth and or eyes with the infection. To
be able to understand the effect of these interventions on construction workers and how workers
had to cope with observing the covid-19 protocols whiles working, respondents were asked
questions on how they went about these protocols whiles working. This was done with an open-
ended question which they were to provide their own answers. Also, further conversations were
asked some of the respondents especially the health and safety officers who were assign to the
As stated by the respondents, observation of the protocols was initially seriously observed as
contractors bought veronica buckets, personal protective equipment, nose masks etc for workers
to protect themselves against the spread of the virus. However, as time went on the observation
of these protocols went down as workers were complaining of not filling comfortable working in
nose masks. Construction workers working on huge projects were made to work on a twelve (12)
hour shift. This was instituted because less people were being made to work in the morning,
which made the progress of work move slowly. Therefore, workers were made to work at night
to catchup with the loss time. Contractors also complained of the increase in their indirect cost as
they had to buy nose masks, veronica buckets and other gadgets that were bought to prevent the
Many interventions were implemented by contractors and clients to help manage cost during the
pandemic. Theses ranges from changes in the prices of work packages in the scope of works,
changing of contract types to influence cost of the projects, changing of the terms of the contract
To explain this further, several negotiations were done to ensure that cost were managed by
putting in place measures the will help in the regard. For example, for building construction
projects, clients agreed with contractors that they will buy materials themselves whiles the
contractors cost for labour will be reimbursed when invoices are raised. Also, certain escalation
clauses were inserted contracts in a form of an addendum which allowed contractors to submit a
higher amount than what was agreed in the contract when prices exceed certain level due to
covid-19. With less complicated or smaller projects, contractors were paid monies to complete
certain portions of the projects then it is reported on before funds are released to continue with
the projects. Certain solutions which contractors wanted to implement also did not work. Some
of these solutions includes, contractors wanting to agree fixed prices to some of their key
One of the challenges faced by contractors was the unwillingness of financial institutions to
provide loans for the commencement of new construction works. This was due to the effect the
covid was having on the economy. Due to this they held on the disbursement of new loans so can
obviate the effect of the covid as a risk to business. These were some of the measures that were
There were general delays in almost all of the construction projects that were being undertaking
during the period of the pandemic. Many of the respondents attested to the fact that, they struggle
to comply to timelines as stated in the contract due to the delay in almost everything that were
used as input for construction. The schedule for most of the projects were changed to
accommodate the delay that was occasion by the pandemic. Delay claims were negotiated on to
eighter stop or prevent it from delaying the projects further. Though delay in the schedule of
projects normally leads to increase in the cost of projects, in this case the delays were as a result
of external factors. These cost in relation delays caused by external factors were negotiated on
for some critical tasks. When some measures were taken to crash the construction programme,
there was a clear indication that it will astronomically increase the cost of the projects.
The pandemic had a drastic effect on both human and material resources in the construction
industry. Much of the adverse effect was impacted on the material resources, especially on
supply chain disruptions. In order to prevent this happening, both clients and contractors had to
implement certain measures to prevent and control the effect on the project. The foremost
solution implemented was to agree on different timelines for the arrival of some of the critical
materials needed for the project due to in crease in the cost of shipping and slow of work due to
restrictions impose by government to control the spread of the virus. This however was good as
clients and contractors were on the same page when it comes to resource availability. Many
shops in the country were also complaining of their unavailability of materials due to lack of
Cash flow for the purchase of materials also affected the availability of resources for the works
being done. This was in relation to major projects; this was attributed to the slowdown in the
operations of these business and their decisions to slow down disbursement to the construction of
new project. Most of the problems encountered by the contractors led to a revision of the
contract for large project and negotiations were done for smaller companies.
Discussions of major findings
The determination of project success as identified by (Standish Group International, 2015) is one
that meet the satisfaction of the customer. This definition includes the success rate of the project
itself as well as the project management of the project. This was further corroborated by the
responses elicited from the respondents for the research. by. The impact of covid-19 on the main
determinant of project success was at the root of the research. In managing projects, there are
certain aspect of the project that needs to be kept under control to enable the stakeholders to be
satisfied with the end results. These are schedule, cost and resources allocated or needed to
achieve a successful project. From the findings above, all the factors being considered here were
badly affected by the effect of covid-19. Below are the major findings on these main areas and
Effect of covid-19 on the schedule baseline of the various project was wide spread among all the
projects that were being done by the various respondents. This gives a wide indication of the
delay that was caused by the pandemic. Rescheduling of certain key element of the construction
process had to be done to enable the construction to be completed within a timeframe that did
will not of the on schedule. As stated by Muhammad Sami Ur Rehman (2021) an extension of
the project timelines were paramount as project at different levels were given an option for
The cost of almost all the project had wide difference between the planned cost and actual cost.
This really escalated the cost of most project. This cut across both big and small construction
projects. The baseline cost of most of the project was changed and led to changes in the contract
and it terms. Cost escalation was the factor that actually led the many changes in the construction
contract. The pandemic came with many adverse factors that affected all the factors that affect
the price of construction materials. This actually reduced the profit margins of most contractors
and as clients were not ready to absorb the initial cost increment due to the pandemic. As
discovered by (Yervi Hensa, 2021) when he conducted a study on the factors of pricing that the
pandemic affected which is made up of six components, including labor, material, implementation
time, project financial aspects, predicted cost, and occupational health and safety, had a frequency of
occurrence for each cause of cost overrun. This was done with special emphasis on hotel construction.
The impact of covid-19 on project resources were the worse among the three factors being
considered in the research. This spans from human to material resources and it affected every
material needed for the work that has to be done. Due to the work from home policy, it was
expected that there will be shortage of human capital on site but the situation was different from
that as most of the respondents stated that, they had all the needed human resource for the work
they were doing. Supply disruptions was very critical to the resource management performance
of the contractors. The disruption was worldwide and it affected most market across the world,
Ghana was no exception. The various shops that deal in the sales of building materials had to
eighter close their shops due to lack of materials to import or the increase in prices that is
keeping them out of business. There were job losses as a results of escalating construction cost
General Conclusions
The unexpected effect of covid-19 on the global economy was devastating enough to reach all
countries especially the underdeveloped and developing countries. The construction industry had
its fair share of adverse effect which had a dent on the performance of construction works in the
country. In view of this the critical areas of project management was considered to know the
extent to which these factors were affected due to the pandemic. In contrary to situations in other
countries, the contribution of the construction industry to the national economy increased in the
Building construction resources were the worse affected as the global supply chain was
interrupted which led to the shortages of shipping containers and cost of shipping also increased.
Many factories closed down which affected the supply of manufactured materials for
construction. and those that were working had to run of a shift system due to reduction of
number of people that were suppose to work in a factory at time. These and other governmental
legislations that were meant to regulate the spread of covid affected the supply chain for the
production and distribution of building materials. In Ghana prices of building materials increased
hence affecting the cost of construction however, scarcity of human resources during the
pandemic was not experienced as most of the responses from the respondents where not in
support of that.
Cost of construction was affected as a result of increase in the prices of building materials. There
was a gap between the budgeted cost and actual cost of most of the project. This led to several
negotiations between contractors and clients. The cost of human resources also increased due to
the
Schedule delays were experience during the covid because of the various disruption in the supply
chain and the limited number of people that were expected to be working at construction site.
Some projects were halted whiles others were abrogated at an early. The uncertainties with
pricing led contributed largely to that. In order for contractors to limit their losses various terms
in the contract had to amended to ensure that the adverse effect on cost is limited.
Recommendations
The following are the recommendations being proposed to help the country mitigate the effect of
Onsite worker accommodation facilities needs to be provided for workers working at site which
will help reduce the cost of accommodation on site. This is very important as ensuring social
practiced by the UAE government when the rules were changed to let contractors to put up on-
The need to start the production of locally manufactured materials is very critical to the success
of the construction. this is due to the fact that most of the materials that has the highest price
escalation was the ones that were imported. The government should cease the opportunity to
construction materials.
Companies should also change their policy and concentrate on the purchase of raw materials for
the construction of buildings in the country. This will help reduce the over reliance of
that will make the sourcing of labour and material resources to be based locally that will help
prevent the situation where material cost will increase in the country when there is shortage else
Payment terms in contracts should be made flexible to enable stakeholder in the construction
industry to adopt alternative means of making payment. As adopted by some contractors in the
UAE, some contractors, asked some vendors and suppliers if they will accept early payment
without achieving pre-set milestones then they will have to accept discounts. In that way, the
associated stakeholders received the required payments to effectively conduct their operations
and survive the pandemic, and the main contractor saved funds to cover the additional costs
Contractors and consultants should be timely and accurate cost estimating, use of cost data for
more informed, collaborative decision-making and leverage the advancement of technology. The
use of technology is key to the development of an accurate database for the development and
dissemination of reliable data for pricing. The use of video conferencing technology and building
Flexibility in the execution of projects management practices is key to the successful completion
of the projects. Provisions such as the submission of a revised schedule baseline by transferring
the impact of COVID-19 to the end of the project’s lifecycle. Secondly, partially completed and
nearly completed projects should have applied for an extension of time (EoT) to accommodate
the delays caused by the pandemic without modifying the existing schedule’s baseline.
The flexibility or extension needed to complete the appropriate testing, commissioning, and
handover to the end-user should have been granted for finished projects.