India Gandhi Sports Complex
India Gandhi Sports Complex
India Gandhi Sports Complex
NEW DELHI
INDIRA GANDHI INDOOR STADIUM SPORTS COMPLEX DELHI
Introduction :
● The Indoor stadium , the core of Indraprastha indoor stadium sports complex , sits almost in
the centre of the 102 acres of land.
● The stadium is the first of its kind in Asia and Europe and in size , ranks the third largest in the
world .
● In the Ninth Asian Games , this stadium was the venue for Gymnastics , Badminton and
Volleyball. This stadium has been certified by all , as not only being an architectural feature.
Capacity: 25,000 ( which has been proposed to be reduced to 18,000 for the
2010 Commonwealth Games)
Area: 102 acres
Cost: Rs.25 crores plus Rs.1.5 crore for partition curtain
Velodrome:
● A velodrome is an arena for track cycling. Modern
velodromes feature steeply banked oval tracks,
consisting of two 180-degree circular bends
connected by two straights. The straits transition to
the circular turn through a moderate easement
curve.
● Velodromes may be indoors or outdoors.
● 40 MM in diameter connected to the pylons through 8 girders
forming the valley of roof
● The roofing purlins were installed after the The octagonal lotus like roof structure, covering
decentering operation. an area larger than the cricket grounds
● Special anti-corrosive paint treatment
was provided for the junction area of
dissimilar metals as the roofing sheet is
made of Aluminium.
● Stretched piano wires were used to keep
the top of the purlin in required place.
● Since the span of the roof exceeds 140m.
● 12 temporary supports right under the PLAN
outer shell location and 4 under
apex of the roof at 41.5 m from ground lvl
compression ring were used at the time
of the erection.
lowest points about 23 mts
SECTION
Structural members' connections :
Fenestrations :
Beyond the last tier of seats , the circular openings are provided with Venetian blinds .This is the only
provision of lighting through openings . Each of these openings have a diameter of approximately
2’-0” .
A) Pylon-girder B) pylon-cables
The elastomeric bearing stopper plate on one side were carefully cut and removed before loosening the
nuts. To enable safe working suspended working platform was fabricated and erected towards the roof
side of the saddle.
Pre-measurements of the gap available between the bottom bearing plate and the saddle bearing plate
were recorded and noted.