PW CF5 v2.6 07 01 2022
PW CF5 v2.6 07 01 2022
PW CF5 v2.6 07 01 2022
for
designed by
THE EMPLOYER
Public Works Contract for Minor Building and Civil Engineering Works Designed by the Employer
Document Reference PW-CF5 v.2.6
7 January 2022
CONDITIONS
Contents
1. THE CONTRACT 1
1.1 Definitions 1
1.2 Interpretation 5
1.3 Inconsistencies 6
1.4 Pricing Document and Works Proposals 6
1.5 Performance Bond 6
1.6 (not used) 6
1.7 Joint Ventures 6
1.8 Assignment 6
1.9 Miscellaneous 6
1.10 Background Information 7
2. THE LAW 8
2.1 Law Governing the Contract 8
2.2 Compliance with Legal Requirements 8
2.3 Consents 8
2.4 Project Supervisor 8
2.5 Safety, Health and Welfare at Work Act 2005 and Safety, Health and Welfare at Work 9
(Construction) Regulations 2013
2.6 Ethics in Public Office 9
2.7 Data Protection 9
3. LOSS, DAMAGE AND INJURY 11
3.1 Employer's Risks of Loss and Damage to the Works 11
3.2 Care of the Works 11
3.3 Insurance of the Works and Other Risk Items 12
3.4 Contractor's Indemnity 12
3.5 Employer's Indemnity 12
3.6 Public Liability and Employer's Liability Insurances 13
3.7 Professional Indemnity Insurance 13
3.8 Existing Facilities and Use or Occupation by Employer 13
3.9 General Requirements Concerning Insurance 13
4. MANAGEMENT 15
4.1 Co-operation 15
4.2 Contractor's Representative and Supervisor 15
4.3 Employer's Representative 15
4.4 Employer's Representative's Communications 16
4.5 Instructions 16
4.6 Works Proposals 17
4.7 Required Contractor Submissions 17
4.8 (not used) 17
4.9 Programme 18
4.10 Progress Reports 18
4.11 Notice and Time for Employer's Obligations 18
4.12 Documents 19
4.13 Contractor's Management 19
4.14 Communications 19
4.15 Meetings 20
4.16 Confidentiality and Secrecy 20
4.17 Contractor's Things Not to Be Removed 20
4.18 Contractor's Documents 20
5. CONTRACTOR'S PERSONNEL 21
5.1 Contractor’s Personnel to Carry Out Contractor’s Obligations 21
5.2 Qualifications and Competence 21
5.3 Pay and Conditions of Employment 21
5.4 Subcontractors and Specialists 22
5.5 Collateral Warranties 23
5.6 Removal of Workers 23
5.7 Weekly Labour Records 23
5.8 Ancillary Certificates 23
6. PROPERTY 24
6.1 Ownership of Works Items 24
6.2 Infringement of Property Rights 24
6.3 Works Requirements 24
6.4 Rights in Contractor's Documents 24
7. THE SITE 25
7.1 Lands Made Available for the Works 25
7.2 Trespassers 25
7.3 Contractor Responsible for All Site Operations 25
7.4 Services for Employer's Facilities 25
7.5 Security and Safety of the Site and Nuisance 25
7.6 Other Contractors 26
7.7 Setting Out the Works 26
7.8 Archaeological Objects and Human Remains 26
7.9 Access and Facilities 26
7.10 (not used) 26
7.11 (not used) 26
7.12 Charges 27
8. QUALITY, TESTING AND DEFECTS 28
8.1 Standards of Workmanship and Works Items 28
8.2 Quality Assurance 28
8.3 Inspection 28
8.4 Tests 28
8.5 Defects 29
8.6 Defects Period 29
ii
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
iii
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
13. DISPUTES 46
13.1 Conciliation 46
13.2 Adjudication 47
13.3 Arbitration 47
13.4 Jurisdiction 47
13.5 Agent for Service 48
13.6 Continuing Obligations 48
14. COVID-19 MANDATORY CLOSURE 49
14.1 Covid-19 Definitions 49
14.2 Covid-19 General Provisions 49
14.3 Covid-19 Costs 50
PV1. PRICE VARIATION 51
PV1.1 Contract Sum Adjustment 51
PV1.2 Communications 52
PV1.3 Compensation Events 52
PV1.4 Efficiency 53
PV1.5 Certificates & Payment 53
iv
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
Conditions
1 THE CONTRACT
1.1 Definitions
The following terms have the following meanings in the Contract:
Term Meaning
Adjudication means adjudication under the Construction Contracts Act 2013
Ancillary Certificate a certificate as prescribed by the Building Control Regulations, other than a
statutory certificate of compliance, given by a competent person to confirm
compliance of elements of the building, design or Works with Building
Regulations; and “Ancillary Certifier” means the person proposed to issue
such a certificate.
Applicable Factor the number in the Schedule, part 3D identified as the Applicable Factor
(Contractor) (Contractor).
Applicable Factor the number in the Schedule, part 3B identified as the Applicable Factor
(Specialist) (Specialist) for each Specialist.
Assigned Certifier the person so assigned by the Employer to certify compliance with the relevant
requirements under the Building Control Regulations.
Building Control the Building Control Regulations 1997-2014 and any amendments thereto to
Regulations the extent that they apply to the Works.
Change Order an instruction of the Employer’s Representative to change [including add to
or omit from] the Works or to change [including impose or remove]
constraints in the Contract on how the Works are to be executed.
Code of Practice for The code of practice published by the Department of Environment,
Inspecting and Community and Local Government with reference to Article 20G of the
Certifying Buildings Building Control Regulations.
and Works
Consent planning permission, order, approval, certificate, Ancillary Certificate, fire
certificate, licence, permit, environmental impact statement, or other consent
required by Legal Requirement for the execution or completion of the Works,
or identified as a Consent in the Works Requirements.
Contract Date the date the Employer issued the Letter of Acceptance.
Contract Sum the amount identified in the Agreement as the initial Contract Sum, as
adjusted in accordance with the Contract.
Contractor’s drawings, specifications, manuals, reports, Consents and other [eye
Documents readable and machine readable] written material relating to the Works that
the Contractor uses, prepares or gives to the Employer or any other person,
or is to use, prepare or give to the Employer or any other person
under the Works Requirements or
under any Legal Requirement or
to obtain any Consent.
Contractor’s Things equipment, facilities and other things the Contractor [or Contractor’s
Personnel] uses on or adjacent to the Site to execute the Works, except
Works Items.
Contractor’s the Contractor’s representative, supervisor and Subcontractors, employees
Personnel and other persons working on or adjacent to the Site for the Contractor or
Subcontractors, and other persons assisting the Contractor to perform the
Contract.
1
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
Term Meaning
Date for Substantial the date identified as the Date for Substantial Completion of the Works or
Completion of the Section in the Schedule, part 1G or 2C, and, if the Schedule states a period,
Works or a Section the last day of that period, starting on the Contract Date, in either case as
adjusted in accordance with the Contract.
Data Protection Law is all applicable data protection Law, including the General Data Protection
Regulation (Regulation (EU) 2016/679).
Defect non-compliance of the Works or a Works Item with the Contract [including a
failed test and, after Substantial Completion, work that has not been
completed].
Defects Certificate a certificate of the Employer’s Representative that the Defects Period has
ended.
Defects Period the period starting on Substantial Completion of the Works and continuing
for the period stated in the Schedule, as may be extended under sub-clause
8.6.2.
Designated Date the date 10 days before the last day for receipt of the Contractor’s tender for
the Works, or, if there was none, 10 days before the Employer received the
Contractor’s tender for the Works.
Employer’s any of the following:
Personnel the Employer’s Representative
the Employer’s employees, agents and consultants in connection with
the Contract when acting on behalf of the Employer but not when
exercising authority under Law
other contractors of the Employer working on the Site when acting within
the scope of their contracts with the Employer
anyone else the Employer’s Representative notifies the Contractor is
Employer’s Personnel
Assigned Certifier.
Employer’s the architect, engineer, quantity surveyor or other person appointed by the
Representative Employer as its representative in accordance with the Contract.
Inspection Plan the document prepared by the Assigned Certifier in accordance with the Code
of Practice for Inspecting and Certifying Buildings and Works having regard to
the Works Requirements. The Inspection Plan also includes the Inspection
Notification Framework, both of which may be amended by the Assigned
Certifier from time to time.
Inspection the document prepared by the Assigned Certifier and agreed with the
Notification Contractor and the Employer in accordance with the Code of Practice for
Framework Inspecting and Certifying Buildings and Works identifying key stages or items
of work that individual certifiers and the Assigned Certifier are to be notified
by the Contractor as the Works are ready for inspection.
Law enactments and statutory instruments, each as defined by the Interpretation
Act 2005, and regulations, directives and decisions of the European Union
having direct effect in Ireland.
2
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
Term Meaning
Legal Requirement a requirement that applies to the Works as a result of any of the following:
Law
a Consent
a decision of an Irish court, the European Court of Justice or the
European Court of First Instance
the requirements of any person having authority in connection with the
Works under any Law
the requirements of any person with whose systems the Works will
connect
the legal rights of any person.
Letter of Acceptance the Employer’s letter to the Contractor accepting the Contractor’s tender.
Personal Data shall have the meaning set out in the General Data Protection Regulation in
respect of any such personal data processed on behalf of the Employer.
Section a part of the Works identified as a Section in the Schedule, part 1G.
Site any place
where the Works are to be executed according to the Contract or
provided by the Employer for the Works or
where the Contractor is to operate or maintain Employer’s facilities or
that the Works Requirements identify as part of the Site.
Site Working Day a day on which, according to the Contract and the Contractor’s programme
most recently submitted to the Employer’s Representative, the Contractor is
to execute the Works on the Site.
Specialist any of the following:
a Subcontractor or supplier of a Works Item named in the Contract
Contractor’s Personnel who do or are to do design
Contractor’s Personnel stated in the Works Requirements to be
Specialists.
Starting Date the day the Contractor proposes to start executing the Works, as notified by
the Contractor to the Employer’s Representative under sub-clause 9.1.
Subcontractor a person to whom the execution of part of the Works is subcontracted [by the
Contractor or another Subcontractor].
3
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
Term Meaning
4
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
1.2. Interpretation
1.2.1 The Parties intend the Contract to be given purposeful meaning for efficiency and public benefit
generally and as particularly identified in the Contract.
1.2.2 Unless the context indicates otherwise, in the Contract
(1) References to the Works are to the works described in the Works Requirements.
(2) Words in the singular include the plural and vice versa.
(3) References to an individual are to a human person.
(4) References to a person include human persons and corporate and unincorporated
bodies.
(5) Words in any gender include all genders.
(6) References to any Law include amendments and replacements.
(7) References to the Contract or any other writing include amendments.
(8) References to a day mean a calendar day.
(9) References to a week mean a period of 7 days.
(10) References to a month mean a calendar month.
(11) References to a working day mean a day that is not Saturday, Sunday, a public holiday
established under the Organisation of Working Time Act 1997 or Good Friday.
(12) References to a requirement to submit a document or proposed course of action to
Employer’s Representative mean to submit it according to sub-clause 4.7, or another
procedure that applies according to the Works Requirements, and sub-clause 4.7 or the
Works Requirements shall apply in every such case. [Accordingly the Contractor may not
implement the submission until permitted by sub-clause 4.7 or the Works Requirements.]
(13) References to the Contractor’s current programme are to the programme in the Works
Proposals, if there is one, if not, to the programme first submitted by the Contractor under
sub-clause 4.9, or, in either case, to any later programme submitted by the Contractor if
the period for the Employer’s Representative to review it has passed and there is no
outstanding objection.
(14) References to liability include claims, demands and proceedings.
(15) Terms such as including, in particular, such as, and for example, are not to be read as
exhaustive, or to limit, but may extend, the generality of the provisions to which they relate.
(16) References to the Agreement and Schedule are to the attached agreement and
completed schedule.
(17) References to the Works Requirements, Works Proposals and the Pricing Document
are to the Works Requirements, Works Proposals and Pricing Document identified in the
Schedule, part 1B; in the case of Works Requirements, as changed by Change Orders; in
the case of Works Proposals, as changed under sub-clause 4.6.2; and in the case of the
Pricing Document, the rates shall be adjusted by multiplying the rates by the Applicable
Factor (Contractor) or Applicable Factor (Specialist) in accordance with sub-clause 11.1.3.
(18) References to Delay Events and Compensation Events are to events identified as Delay
Events and Compensation Events in the Schedule, part 1K.
(19) References to the initial Contract Sum are to the Contract Sum stated in the Agreement;
references to an initial Date for Substantial Completion are to a Date for Substantial
Completion identified in the Schedule; and references to the initial Works Requirements
are to the Works Requirements identified in the Schedule.
(20) The Parties are the Employer and the Contractor
1.2.3 Clarifications, examples and reminders are included occasionally in square brackets to show
that no significance is to be given to their absence elsewhere.
1.2.4 No rule of legal interpretation applies to the disadvantage of a Party on the basis that the Party
provided the Contract or any of it or that a term of the Contract is for the Party’s benefit.
5
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
1.3 Inconsistencies
1.3.1 Except when the Contract states otherwise, the documents in the Contract are to be taken as
mutually explanatory of each other if possible. If there is an inconsistency between the
documents, they take precedence as follows:
First, the Agreement, even if it has not been executed
Second, the attached Schedule and the Letter of Acceptance and any post-tender
clarifications listed in it
Third, the Contractor’s completed form of tender (excluding other documents in the tender)
Fourth, these Conditions
Fifth, the Works Requirements
Sixth, the Pricing Document
Seventh, the Works Proposals, if there are any
Eighth, any other documents in the Contract
1.3.2 If either Party becomes aware of any inconsistency between terms of the Contract, it shall
promptly inform the other Party.
1.3.3 If there is an inconsistency between figured and scaled dimensions, the figured dimensions
prevail.
1.3.4 Inconsistencies between the Works Requirements and the Pricing Document shall be resolved
by an instruction from the Employer’s Representative under sub-clause 4.4.1(1) of the Contract.
Where inconsistencies are found to exist between the Works Requirements and the Pricing
Document the Works Requirements take precedence with respect to the Works to be completed
and a compensation event shall arise in accordance with the Schedule, Part 1K (17).
1.8 Assignment
The Contractor may not assign the benefit of the Contract, or any part of it, without the Employer’s
consent.
1.9 Miscellaneous
1.9.1 The Contract and the documents referred to in it supersede all previous representations,
arrangements, understandings and agreements between the Parties about the subject-matter of
the Contract, and set out the entire agreement between the Parties about the subject-matter of
6
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
the Contract. Neither Party has relied on any other written or oral representation, arrangement,
understanding or agreement.
1.9.2 All the terms of the Contract are severable, and if any part is unenforceable, illegal or void, it is
to that extent considered not to form part of the Contract, and the enforceability, legality and
validity of the rest of the Contract will not be affected.
1.9.3 The Contract may only be changed by a document in writing signed by an authorised
representative of each Party.
1.9.4 The rights of a Party will not be prejudiced or restricted by any indulgence or forbearance
extended to the other Party, and no waiver by a Party of any breach will waive any other
breach.
(1) The Employer has no liability whatsoever to the Contractor in contract, tort, under statute,
or on any other basis whatsoever (including negligence and breach of statutory or other
duty) in connection with Background Information.
(2) The Employer has not made and does not make any warranty, representation, or
undertaking in connection with Background Information.
(3) The Employer has not authorised anyone to make any warranty, representation, or
undertaking on the Employer’s behalf in connection with Background Information.
(4) Without limiting anything in this sub-clause 1.10, the Contractor irrevocably and forever
waives any liability that the Employer may have to the Contractor in connection with
Background Information regardless of any of the following circumstances, and the
Contractor acknowledges that the Employer makes no warranty, representation, or
undertaking in regard to those circumstances:
a) whether or not Background Information is correct
b) whether or not Background Information is complete
c) whether or not any testing, investigation, surveys, or other work to prepare
Background Information was done negligently or in breach of statutory or other
duties
d) whether or not those who carried out any testing, investigation, surveys, or other
work to prepare Background Information were properly selected or supervised
e) whether or not Background Information was suitable for the purposes for which
the Contractor or anyone on the Contractor’s behalf might use it
f) whether or not any errors or omissions in Background Information are major or
numerous or both
g) whether or not Background Information represents all the information available to
the Employer
h) whether or not any works described in Background Information are done as
described in Background Information or at all
i) whether or not the Employer had or has other information that might render
Background Information misleading
j) the manner in which Background Information was made available
k) whether or not the Contractor had adequate opportunity to carry out any testing,
investigations, surveys, or other work or otherwise to verify Background
Information.
(5) The Contractor has included in the Contract Sum for the risks that the Contractor has
agreed to bear under this sub-clause 1.10.
7
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
2 THE LAW
2.3 Consents
2.3.1 The Employer has obtained, or shall obtain, the Consents that the Works Requirements say
that the Employer is to obtain. The Contractor shall obtain all other Consents.
2.3.2 The Contractor shall give and comply with all notices and pay all taxes, fees and charges
required under Legal Requirements to be paid in connection with performing the Contract,
unless the Works Requirements say otherwise.
8
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
2.5 Safety, Health and Welfare at Work Act 2005 and Safety, Health and Welfare at Work
(Construction) Regulations 2013
2.5.1 The Contractor shall [without limiting other obligations] ensure, so far as is reasonably
practicable, that the Works are constructed to be safe and without risk to health, and that the
Works comply in all respects, as appropriate, with the relevant statutory provisions.
2.5.2 The Contractor represents and warrants to the Employer that the Contractor is, and will, while
performing the Contract, be a competent person for the purpose of ensuring, so far as is
reasonably practicable, that the Works are constructed to be safe and without risk to health
and that they comply in all respects, as appropriate, with the relevant statutory provisions.
2.5.3 The Contractor represents and warrants to the Employer that the Contractor is and will, while
performing the Contract, be a competent person to carry out the Works and has allocated and
will allocate sufficient resources to enable itself to comply with the requirements and
prohibitions imposed on the Contractor by or under the relevant statutory provisions.
2.5.4 In this sub-clause 2.5 and sub-clause 2.4, competent person, reasonably practicable and
relevant statutory provisions are construed according to section 2 of the Safety, Health and
Welfare at Work Act 2005.
(b)(b) the Contractor shall ensure persons authorised by the Contractor to process Personal Data
are subject to confidentiality obligations as provided under Data Protection Law;
(c) (c) the Contractor must take appropriate technical and organisational security measures as
are required to comply with Data Protection Law;
(d)(d) the Contractor may engage sub-processors to perform processing on its behalf, provided
it gives prior written notice and informs the Employer of any changes concerning the status
of such sub-processors and allows the Employer reasonable opportunity to object to such
changes;
9
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
(e) (e) where any sub-processor of the Contractor will be processing Personal Data on behalf of
the Employer, the Contractor shall ensure that a written contract exists between the
Contractor and the sub-processor containing clauses equivalent to those imposed on the
Contractor by the Contract;
(f) (f) the Contractor shall delete or return all Personal Data as directed by the Employer’s
Representative and not later than when the Contractor completes its contractual duties
relating to such data processing;
(g)(g) the Contractor shall: (i) make available to the Employer all information necessary to
demonstrate compliance with this Clause; and (ii) allow for and assist with audits, including
inspections, conducted by or on behalf of the Employer, in order to ensure such
compliance, provided however that the Employer shall be entitled, at its discretion, to
accept adherence by the Contractor to an approved code of conduct or an approved
certification mechanism to aid demonstration by the Contractor that it is compliant;
(h)(h) the Contractor shall inform the Employer’s Representative immediately if, in its opinion, it
receives an direction which infringes Data Protection Law;
(i) (i) the Contractor shall notify the Employer’s Representative within 24 hours of becoming
aware of any act or omission [including breach of security] leading to the accidental or
unlawful destruction, loss, alteration, unauthorised disclosure of or access to Personal
Data transmitted, stored or otherwise processed and shall provide co-operation and
assistance to the Employer as is required to mitigate the effects of, and comply with
applicable reporting obligations in respect of, such act or omission; and
(j) (j) no Personal Data shall be transferred outside the European Economic Area by the
Contractor or any of its agents or sub-processors without the prior written consent of the
Employer, and the Contractor shall comply with Data Protection Law in respect of Personal
Data transfers outside the European Economic Area which the Employer has consented
to.
10
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
11
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
12
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
13
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
3.9.3 Liability Insurance on which the Employer is required to be insured shall include a cross-
liability clause. All Insurance on which the Employer is required to be insured shall provide that
the insurer accepts the term “insured” as applying to each insured person as if a separate
policy of insurance had been issued to each of them, but without the overall limit of indemnity
being increased as a result, and that non-compliance by the Contractor or any other insured
will not affect the Employer’s rights
3.9.4 The Contractor shall comply with the terms of the Insurance policies.
3.9.5 Within 10 working days of being requested to do so, the Contractor shall give the Employer
evidence to the Employer’s satisfaction that the Insurances are in effect, including copies of
policies and receipts for premiums. For professional indemnity insurance, a certificate in the
form included in the Works Requirements, or, if there is none, a form approved by the
Employer, signed by the broker or underwriter, may be given instead of a copy of the
professional indemnity policy.
3.9.6 The Contractor shall not make any material reduction to the Insurance cover unless approved
in advance by the Employer. The Contractor shall promptly notify the Employer of any
cancellation, renewal, non-renewal or material reduction by the insurer of any Insurance policy.
3.9.7 If the Contractor fails to maintain any of the Insurances in the terms required by the Contract,
the Employer shall be entitled [without affecting its other rights] to take out the insurance and
pay the premiums, and the Contractor shall pay the amount of the premiums to the Employer
on demand.
14
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
4 MANAGEMENT
4.1 Co-operation
4.1.1 The Employer [subject to restraints as a public authority] and the Contractor shall support
reciprocal co-operation for the Contract purposes, including co-operation with and between
Contractor’s Personnel and Employer’s Personnel.
4.1.2 Such support may be relevant particularly to any of the following:
(1) negotiation of agreements provided for in the Contract
(2) use of most effective and compatible electronic and other methods of communicating
and recording
(3) efficient order and timing of information provided for in the Contract
(4) minimising the effects of suspension
(5) efforts by the Contractor to minimise delay and Compensation Events and their effects
(6) Contractor’s flexible management
4.1.3 Either Party, or the Employer’s Representative, may request clarifications, consultations,
workshops, exchange of information and expertise, or investigations, although not provided
for elsewhere in the Contract. The request shall specify purposes and, as relevant, proposed
participants, arrangements, methods and any proposals for recording or agreeing results.
4.1.4 The Parties may agree to consult or communicate, without prejudice. In any case, offering or
giving co-operation does not imply any admission of any responsibility or alter either Party’s
rights or duties unless otherwise agreed in writing.
15
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
4.3.3 The Employer’s Representative may delegate in writing to named representatives any
functions or powers under the Contract and revoke any delegation. The appointment of such
a representative shall not prevent the Employer’s Representative from exercising directly any
functions or powers. The Employer’s Representative shall notify the Contractor and the
Employer of any delegation, and the names of representatives, and of any subsequent
changes, within 5 working days after the event in each case.
4.3.4 Any opinion, certificate, determination, assessment or objection of the Employer’s
Representative under the Contract may be revised in accordance with clause 13, except for
decisions stated in the Contract to be conclusive [such as rejection of a Defect under sub-
clause 8.5.4].
4.3.5 The Employer may replace the Employer’s Representative at any time, notifying the
Contractor of the replacement, and shall do so promptly if the position of Employer’s
Representative becomes vacant before the Defects Certificate (or alternatively the certificates
required following termination) have been issued. Pending appointment of a replacement, the
Employer shall carry out the functions and powers of the Employer’s Representative.
4.5 Instructions
4.5.1 The Employer’s Representative may issue instructions to the Contractor on any matter
connected with the Works [whether or not mentioned elsewhere in the Contract] at any time
up to the date the Defects Certificate is issued. The Contractor shall comply with an
instruction of the Employer’s Representative.
4.5.2 If the Employer’s Representative gives an instruction and calls it a direction, but the
Contractor considers that it is a Change Order, the Contractor shall be entitled to give notice
under sub-clause 10.3, and have the issue determined under clause 10. In addition to the
requirements of sub-clause 10.3, the Contractor must give this notice before starting to
implement the instruction, otherwise it will be taken to be a direction.
4.5.3 The Employer’s Representative shall not give a Change Order concerning the Works or a
Section after its Substantial Completion has been certified, except concerning Defects or
work to be done after Substantial Completion.
4.5.4 The Employer’s Representative shall give an instruction that is, in the Employer’s
Representative’s opinion, necessary for the completion of the Works. If, in the Employer’s
Representative’s opinion, it is physically impossible or contrary to Legal Requirements to
complete the Works in accordance with the Works Requirements, the Employer’s
Representative shall give a Change Order. The Employer’s Representative shall give an
instruction required under this sub-clause 4.5.4 within the time required by sub-clause 4.11.
4.5.5 Instructions of the Employer’s Representative shall be given in writing except when there is
imminent danger to safety or health or of damage to property, in which case the Employer’s
Representative may give oral instructions, and shall confirm them in writing as soon as
practicable.
16
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
17
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
4.9 Programme
4.9.1 Before the Starting Date, the Contractor shall submit to the Employer’s Representative a
detailed programme having regard to the requirements of the Inspection Plan and the
Inspection Notification Framework. If there is a programme in the Works Proposals that
complies with the Contract, the Contractor shall submit that programme, with any required
additional information [such as the actual programmed dates and any Inspection Plan
requirements]. The programme shall be of a quality that will permit effective monitoring of the
Works and shall include details of when the Contractor will require any instructions, Works
Items or other things to be given by the Employer, or anything else the Contract requires the
Employer, the Employer’s Representative or others to give the Contractor.
4.9.2 The Contractor’s programme shall allow reasonable periods of time for the Employer and the
Employer’s Personnel to comply with their obligations under the Contract.
4.9.3 If the Contractor’s programme most recently submitted to the Employer’s Representative
does not correspond with actual or reasonably projected progress or the Contractor’s
obligations, the Contractor shall, if so directed by the Employer’s Representative, submit to
the Employer’s Representative a revised programme that complies with this sub-clause and
the other provisions of the Contract, showing actual progress and progress projected by the
Contractor. If the Contractor asserts that it is not possible to reach Substantial Completion of
the Works or a Section by its Date for Substantial Completion, the revised programme shall
show Substantial Completion by the earliest possible date. [Neither the programme nor its
review will limit the Contractor’s responsibility or liability for the delay.] If the Contractor fails to
submit the revised programme within 15 working days of a request from the Employer’s
Representative, the Employer shall be entitled to withhold from the Contractor 15% of any
payment to be made to the Contractor until the revised programme is submitted.
18
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
4.12 Documents
4.12.1 The Contractor shall keep on the Site all of the following:
(1) a full up-to-date set of the Contract documents (but the Pricing Document may be
unpriced), instructions of the Employer’s Representative, and Contractor’s Documents
(2) a log of all instructions and Contractor’s Documents showing dates of issue for each
and any subsequent revisions
(3) if requested by the Employer’s Representative, all publications named in the Contract
and the Contractor’s Documents.
(4) wage records [including time sheets and copies of all pay slips] applicable to all
workers [as defined in sub-clause 5.3.1].
The Employer’s Representative, and any person authorised by the Employer’s
Representative, shall have a right of access to these at all reasonable times.
4.12.2 The Contractor shall retain the Contractor’s Documents in relation to the Works for a period of
six [6] years from the date of completion of the Works or if applicable from the date of
termination of the Contract for any reason.
4.14 Communications
4.14.1 The Parties intend all communications between them to be interpreted purposefully, having
regard to the Contract’s purposes.
4.14.2 Whenever any communication [including a notice, decision, objection, approval, certificate,
determination, instruction or request] is to be given under the Contract it shall, unless the
Contract provides otherwise, be in English, in writing and delivered as follows:
(1) for notices under clause 12 or clause 13, delivered by hand or sent by pre-paid
registered post to the address for those notices in the Schedule, part 1A, as updated
by the relevant Party
(2) for other communications, delivered by hand or sent by pre-paid post, fax or email
according to the particulars for other communications in the Schedule, part 1A, as
updated by the relevant Party.
4.14.3 Communications by pre-paid registered post are presumed to have been received at
10:00 a.m. two working days after posting. Fax and email communications are presumed to
have been received when receipt is electronically recorded.
19
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
4.15 Meetings
4.15.1 The Contractor’s representative and the Employer’s Representative shall attend regular
meetings scheduled by the Employer’s Representative and any special meeting called by
either of them to discuss a particular issue identified when calling the meeting. The
Employer’s Representative may invite other Employer’s Personnel and the Contractor may
invite Contractor’s Personnel to attend meetings. The Contractor shall arrange for the
attendance at a meeting of any Contractor’s Personnel requested by the Employer’s
Representative. The time and place of meetings shall be set by the Employer’s
Representative, after consulting the Contractor, acting reasonably.
4.15.2 Within 5 working days after each meeting the Employer’s Representative shall issue minutes
of the meeting to the Employer and the Contractor. The Contractor shall notify the Employer’s
Representative of any objection to the minutes within 5 working days of receiving them,
otherwise, unless clearly wrong, they shall be considered correct.
20
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
5 CONTRACTOR’S PERSONNEL
21
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
Equality Act 1998 to 2005, the Industrial Relations Acts 1946 to 2015, the National
Minimum Wage Act 2000 and 2015, and regulations, codes of practice, legally binding
determinations of the Labour Court and sectoral employment orders, employment
regulation orders or registered employment agreements implemented under those
Laws.
5.3.3A (1) Sub-clause 5.3.3A(2) shall only be included in the Contract if the Schedule, part 1J
says so, and if not, neither sub-clause 5.3.3A(2) nor its omission shall be taken into
account.
(2) The Employer shall be entitled to make random checks requiring production of records
under sub-clauses 5.3.3(5) and (6).
5.3.4 If the Employer so requests, the Contractor shall, within 5 working days after the receipt of
the request, give to the Employer a statement showing the amount of wages and other
payments due at the date of the request to and in respect of each worker, or, in respect of
workers not employed by or otherwise working for the Contractor, ensure that their employer
or the person for whom they are working does the same.
5.3.5 The Employer may seek information under sub-clause 5.3.3 only for the purpose of ensuring
the obligations referred to in this sub-clause 5.3 to workers have been properly discharged.
All documents and records received under sub-clause 5.3.3 shall be returned to the person
providing them or destroyed if the Employer is satisfied that the relevant employer has
complied with legal obligations to workers.
5.3.6 If the Contractor has not complied with this sub-clause 5.3, the Employer shall [without
limiting its other rights or remedies] be entitled to estimate the amount that should have been
paid to workers and contributions that should have been made on their behalf, and the
Employer may deduct the estimated amount from any payment due to the Contractor, until
the Employer is satisfied that all proper amounts have been paid.
5.3.7 The Contractor shall give the Employer’s Representative with each interim statement under
sub-clause 11.1 a certificate in the form in the Works Requirements, that, in respect of the
work to which the interim certificate relates, the Contractor has complied in full with this sub-
clause 5.3.
5.3.8 If the Contractor does not comply with this sub-clause 5.3, it shall pay to the Employer any
costs the Employer incurs in investigating and dealing with the non-compliance.
5.3.9 The Contractor shall ensure that in the event of an official of a trade union representing
workers who are affected by a sectoral employment order, employment regulation order or
which is a party to a which is party to a registered employment agreement affecting workers
having concerns in relation to the Contractors or Contractor’s Personnel’s compliance with
the order or agreement, that official will have access to a designated member of the
Contractor’s management who shall engage constructively to resolve matters at this point.
(ii) where the Contractor is to enter a sub-contract with a named Specialist, (Reserved
Specialist), the Reserved Specialist sub-contract shall be an unamended form of
sub-contract as identified in Schedule Part 1F(iii) and the Contractor shall enter into
the sub-contract with the Reserved Specialist before the Starting Date.
5.4.4 The Employer’s Representative may not instruct the Contractor to enter a contract with a
particular Specialist selected by the Employer’s Representative unless the Specialist is
named in the Contract (named Specialists).
5.4.5 The Contractor shall fully comply with its obligations under any contract with a Specialist and
shall not terminate, allow to be terminated or accept a repudiation of such a contract without
first submitting details to the Employer’s Representative, except when an insolvency event,
as set out in sub-clause 12.1, occurs in respect of the Specialist, or the Specialist has
committed a serious breach of Law concerning safety, or the Specialist has failed to put or
keep in effect insurance as required by the Specialist’s contract. On any termination, the
Contractor shall replace the Specialist, having submitted details of the replacement to the
Employer’s Representative. In the case of a named Specialist, referred to in sub-clause 5.4.3,
the replacement Specialist proposed by the Contractor must meet minimum standards set out
in the Works Requirements.
5.4.6 In addition to the reasons in sub-clause 4.7, the Employer’s Representative may object to the
proposed replacement of Contractor’s Personnel because the proposed replacement does
not have at least the level of experience, qualifications, competence, technical capacity, and
financial standing of the person being replaced.
23
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
6 PROPERTY
24
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
7 THE SITE
7.2 Trespassers
After the Employer has allowed the Contractor to occupy and use any part of the Area Provided by the
Employer, the Contractor shall be responsible for activities of trespassers, protesters and others, that
are not Employer’s Personnel, on the Site, and the Employer shall have no responsibility to the
Contractor for their activities or presence.
25
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
(iii) persons exercising public access to any roads, footpaths and areas on the Site
(iv) persons having a right to enter the Site under Legal Requirements
(2) keep the Site in good order and free from unnecessary obstructions
(3) take all necessary steps to secure the safety of all persons entitled to be on the Site
and to protect users, owners and occupiers of land adjacent to the Site from hazards
and interference arising from the Works [including providing any required fences,
lighting, guarding, watching, roads and footpaths]
(4) take all necessary steps to ensure that the Contractor, the Contractor’s Personnel and
the execution of the Works do not do any of the following:
(i) unnecessarily cause a nuisance or inconvenience to the public or any user,
owner or occupier of any land, road or footpath on or adjacent to the Site
(ii) unnecessarily interfere with the use of any such land, road or footpath.
7.5.2 The Employer shall ensure that Employer’s Personnel on the Site comply with the
Contractor’s reasonable safety rules that have been notified to them by the Contractor.
7.5.3 This sub-clause 7.5 is subject to any exceptions in the Works Requirements
26
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
7.12 Charges
The Contractor shall pay any charges provided for in the Works Requirements for occupation of the Site
or any part of it or other place, or in respect of operation or maintenance of Employer’s facilities, or in
respect of services, or otherwise. [The Employer may deduct the amount of charges from payments to
the Contractor. Payment of charges does not excuse the Contractor from any of its obligations].
27
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
8.3 Inspection
8.3.1 The Contractor shall ensure that the Employer’s Representative, Assigned Certifier, and
anyone authorised by the Employer’s Representative, is able at all reasonable times to have
access to all places where the Works are being executed [whether or not at the Site] and any
place where any Works Items are produced, stored, extracted or prepared, or any other
obligation of the Contractor under the Contract is being performed, and are able there to
inspect, test, observe and examine all such items and activities.
8.3.2 The Contractor shall promptly give the Employer’s Representative and the Assigned Certifier
all particulars the Employer’s Representative and the Assigned Certifier requests about the
mode, place and time of manufacture, the source of supply and the performance capabilities
of Works Items and any related information, including any test certificates that the Contract
provides for.
8.3.3 The Contractor shall notify the Employer’s Representative and the Assigned Certifier before
any Works Item is covered or any Works Item that is to be inspected is packed or made
impossible or difficult to inspect, in either case giving the Employer’s Representative, and any
person authorised by the Employer’s Representative, a reasonable opportunity to inspect the
Works Item.
8.4 Tests
8.4.1 The Contractor shall supply all Contractor’s Things, documents, information, suitably qualified
and experienced personnel, power, consumables and instruments required to carry out tests
that the Contract [including the Inspection Plan] requires the Contractor to do [both before
and after Substantial Completion]. The Contractor shall agree with the Employer’s
Representative and the Assigned Certifier the time and place for these tests. The Employer’s
Representative, and others authorised by the Employer, may attend and observe the tests,
and the Contractor shall facilitate their attendance and observation. Regardless of whether
any Employer’s Personnel attends, the Contractor shall promptly give the Employer’s
Representative a certified report of the result of every test.
28
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
8.4.2 If a test is failed, the Contractor may elect to repeat the test, or the Employer’s
Representative may require that the test be repeated. The Contractor shall, on request, pay
the Employer any costs the Employer incurs as a result of any re-testing.
8.4.3 If the Contractor rectifies a Defect, it shall repeat any relevant test the Contract specifies for
the relevant Works Item, if the Employer’s Representative so directs.
8.5 Defects
8.5.1 The Employer’s Representative may direct the Contractor to search for a Defect or suspected
Defect or its cause. This may include uncovering, dismantling, re-covering and re-erecting
work, providing facilities for tests, testing and inspecting. If, through searching or otherwise,
the Contractor discovers a Defect, the Contractor shall notify the Employer’s Representative
as soon as practicable.
8.5.2 If, through notification or otherwise, the Employer’s Representative becomes aware of a
Defect, the Employer’s Representative may direct the Contractor to do any of the following [or
any combination of them]:
(1) to remove the Works Item with the Defect from the Site
(2) to demolish the Works Item with the Defect, if incorporated in the Works
(3) to reconstruct, replace or correct the Works Item with the Defect
(4) not to deliver the Works Item with the Defect to the Site.
8.5.3 The Contractor shall comply with any direction under this sub-clause 8.5 within the
reasonable times, if any, the Employer’s Representative directs. If the Contractor fails to
begin the work required to comply with the direction within the reasonable time directed, if
any, or to complete it as soon as practicable, the Employer may have the work done by
others and the Contractor shall, on request, pay the Employer its cost of doing so.
8.5.4 Alternatively, the Contractor and the Employer’s Representative may, with the Employer’s
consent, agree that the Employer will accept the Defect, either in whole or subject to any
change to the Works Requirements that the Employer’s Representative directs. In this case,
the Contract Sum shall be reduced by the amount that, in the opinion of the Employer’s
Representative, is the resulting decrease in the value of the Works to the Employer. If the
Employer’s Representative notifies the Contractor that the Employer will not accept a Defect,
this shall be conclusive.
8.5.5 The Employer’s Representative may give a direction or rejection under this sub-clause 8.5 at
any time before the Defects Certificate is issued. [The Contractor shall not be entitled to any
adjustment to the Contract Sum or extension of time because of a direction given to deal with,
or as a result of, a Defect or any other breach of the Contract by the Contractor.]
29
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
9.2 Suspension
9.2.1 The Employer’s Representative may at any time direct the Contractor to suspend all or part of
the work under the Contract. The Contractor shall comply with the direction and, during
suspension, shall protect, store and secure the affected Works Items against deterioration,
loss and damage and maintain the Insurances.
9.2.2 After a suspension under clause 9.2.1, the Contractor shall resume work when so directed by
the Employer’s Representative. When a direction to resume is given, the Contractor and the
Employer’s Representative shall jointly examine the Works and Works Items affected by the
suspension. If the Contractor is entitled to an adjustment of the Contract Sum or an extension
of time because of the suspension, the Contractor’s cost of rectifying any deterioration in or
loss of the Works or Work Items that the Contractor could not have avoided shall be included
in the determination of the adjustment, and any resulting delay shall be taken into account in
determining the extension.
9.2.3 If a suspension, that did not result from a breach of the Contractor’s obligations, has
continued for more than 3 months, the Contractor may request the Employer’s
Representative’s permission to proceed. If the Employer’s Representative does not give
permission within 28 days after being requested to do so, the Contractor may, by giving
notice to the Employer’s Representative
(1) if the suspension affects part of the Works, treat the suspension as a Change Order to
omit that part of the Works or
(2) if the suspension affects the whole of the Works, give notice to terminate the
Contractor’s obligation to complete the Works under the Contract.
30
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
31
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
32
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
33
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
10.3.3 If the cause of the claim has a continuing effect, the Contractor shall update the information at
monthly intervals
(1) stating the extension of time and adjustment to the Contract Sum claimed for delay and
cost already incurred and
(2) so far as practicable, proposing a final adjustment to the Contract Sum and Date for
Substantial Completion of the Works and any affected Section and
(3) providing any other information the Employer’s Representative reasonably requires.
10.3.4 The Contractor shall keep detailed contemporary records to substantiate any aspect of an
event or circumstance about which it has given, or is entitled to give, notice under this sub-
clause 10.3, and its resulting costs. These shall include any records the Employer’s
Representative directs the Contractor to keep. The Contractor shall give the records to the
Employer’s Representative if so directed.
34
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
10.5.3 If the Employer’s Representative fails to take any of the actions in sub-clause 10.5.1 within the
time stated, the Employer’s Representative will be taken to have made a determination under
sub-clause 10.5.1(3) that there be no adjustment to the Contract Sum, no use of programme
contingency referred to in sub-clause 9.4, and no extension to any Date for Substantial
Completion. The determination will be taken to have been made on the last day of the time
provided for in sub-clause 10.5.1.
10.5.4 A determination of the Employer’s Representative notified to the Contractor and the Employer
under sub-clause 10.5.1(3) or 10.5.2 shall be final and binding on the Parties unless, within 28
days after receiving notice of the determination (or, if sub-clause 10.5.3 applies, within 28 days
after the determination is taken to have been made), the Contractor or the Employer gives
notice to the other under sub-clause 13.1.1 disputing the determination and referring the
dispute to conciliation.
10.5.5 Notice of an agreement under sub-clause 10.5.1(2) shall be final and binding on the Parties
unless, within 28 days after receiving the notice, either:
(1) the Contractor both (a) notifies the Employer’s Representative and the Employer that the
Contractor disagrees that the notice correctly records agreed terms and (b) gives notice
to the Employer under sub-clause 13.1.1 referring the dispute to conciliation or
(2) the Employer both (a) notifies the Employer’s Representative and the Contractor that the
Employer does not agree with the terms notified by the Employer’s Representative and
(b) gives notice to the Contractor under sub-clause 13.1.1 referring the dispute to
conciliation.
35
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
made in accordance with the Industrial Relations Acts 1946 – 2015 the Employer’s
Representative will determine the most appropriate basic hourly rate based on the
category of work person’s skills and experience) and
(2) the cost of materials used in that work, taking into account discounts and excluding
VAT, plus the percentage adjustment tendered by the Contractor and stated in the
Schedule, part 2D. Where the additional or substituted work includes named Specialist
Works, the percentage addition to costs of material tendered by the respective named
Specialist in Appendix part 2C of their sub-contract is applied. (But if the percentage
adjustment tendered is negative or blank it will be read as 0%) and
(3) the cost of plant reasonably used for that work, whether hired or owned by the
Contractor, at the rates in the document listed in the Schedule, part 1K (as that
document may be modified according to the Schedule, part 1K) plus or minus the
percentage adjustment tendered by the Contractor and included in the Schedule, part
2D. Where the additional or substituted work includes named Specialist Works, the
percentage addition to costs of plant tendered by the respective named Specialist in
Appendix part 2C of their sub-contract is applied. (But if the percentage adjustment
tendered is a deduction of more than 50% it will be read as a deduction of 50% or if the
entry is blank it will be read as 0%). If the document listed in the Schedule does not
give a rate for a plant item, a market rental rate shall be used, plus or minus the
percentage adjustment.
36
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
37
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
11 PAYMENT
38
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
Representative shall issue to the individual named Specialists, details of the gross and net
amount included within the certificate to the respective named Specialists.
11.1.5 If there is a sum due to the Contractor, the Contractor shall send an invoice to the Employer
for that sum after receiving the response to the payment claim notice. The Employer shall
pay the amount due on the invoice within 21 days after receiving the invoice.
11.3 Retention
11.3.1 There shall be deducted from each interim payment to the Contractor the retention
percentage stated in the Schedule, part 1L.
11.3.2 Upon issue of the certificate of Substantial Completion of the Works, the Contractor shall be
entitled to invoice the Employer for half of the amount so retained and the Contractor shall
furnish the Employer’s Representative with a copy of the invoice. Upon the issue of the
Defects Certificate, the Contractor shall be entitled to invoice the Employer for the balance
of the money so retained and the Contractor shall furnish the Employer’s Representative
with a copy of the invoice.
11.3.3 If, within 14 days of the issue of the certificate of Substantial Completion of the Works, or
another date agreed by the Employer’s Representative, the Contractor provides to the
Employer a retention bond in the form in the Work Requirements, or, if there is none, a form
approved by the Employer, for the amount retained by the Employer, and executed by a
surety approved by the Employer, the Contractor shall be entitled to invoice the Employer for
the balance of the money retained.
11.3.4 Upon issue of the certificate of Substantial Completion of a Section of the Works, the
retention amount to be withheld until issue of the certificate of Substantial Completion of the
Works shall be reduced by the amount stated in the Schedule, part 1G, and the Contractor
39
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
40
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
[for example, for Defects that the Contractor has not rectified] and
(4) deductions from the Contract Sum under sub-clause 11.4 and
(5) other amounts that, according to the Contract, are to be paid after Substantial
Completion of the Works [such as payments for testing after Substantial Completion].
11.5.4 If the penultimate or final payment certificate states that there is a sum owing to the
Contractor, the Contractor shall issue an invoice to the Employer for that sum and the
Employer shall pay the amount due on the invoice within 21 days after receiving the invoice.
If the penultimate or final payment certificate states that there is a sum owing to the
Employer, the Contractor shall pay the amount due within 14 days of receipt of the
Employer’s demand for payment. [Payments and certificates, including the penultimate and
final payment certificates and the Defects Certificate, will not relieve the Contractor of any
obligations, or be evidence of the value of work or that work has been completed
satisfactorily].
41
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
12 TERMINATION
42
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
12.1.2 If the Contractor is more than one person, if any of the insolvency events occur in respect of
any of them, the Employer may either
(1) terminate the Contractor’s obligation to complete the Works or
(2) terminate the obligation to complete the Works of the person concerned and the
others shall remain liable to perform the Contractor’s obligations.
12.1.3 If any insolvency events occur in respect of any person who has guaranteed the
Contractor’s performance of the Contract to the Employer, or a guarantee ceases to be
enforceable against the guarantor, the Employer may terminate the Contractor’s obligation
to complete the Works unless, within 10 working days of the event, the Contractor has
arranged a replacement guarantee and guarantor to the Employer’s satisfaction.
43
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
44
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
12.7 Survival
Termination of the Contractor’s obligation to complete the Works shall not affect the Contractor’s
obligations under the Contract, other than the obligation to complete the Works. [In particular the
following provisions of the Contract continue to have effect after termination: sub-clauses 1.1, 1.2, 1.3,
1.4, 1.7, 1.8, 1.9, 2.1, 2.6, 2.7, 3.4, 3.5, 4.16, 4.17, clause 6, this clause 12 and clause 13.]
12.8 Payment
On termination of the Contractor’s obligation to complete the Works, the Employer’s liability to the
Contractor under or in connection with the Contract shall be limited to payment of the amount provided
for in this clause 12, and any other amount that fell due under the Contract before the termination.
45
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
13 DISPUTES
13.1 Conciliation
13.1.1 If a dispute arises under the Contract, either Party may, by notice to the other, refer the
dispute for conciliation under this sub-clause 13.1. The notice shall state that it is given
under sub-clause 13.1 of the Contract.
13.1.2 Within 10 working days of the referral of a dispute to conciliation, the Parties shall jointly
appoint a conciliator who is competent to adjudicate upon the dispute and independent of
the Parties. If the Parties fail to appoint a conciliator within 10 working days of the referral, or
if a person appointed refuses to act or becomes unable to act, the conciliator shall be
appointed by the appointing body or person named in the Schedule, part 1N, on the
application of either Party. If there is a fee for making the appointment, the Parties shall
share it equally. If one Party pays the entire fee, it shall be entitled to reimbursement of the
other Party’s share from the other Party on demand.
13.1.3 Each Party shall, within the period set by the conciliator, send to the conciliator and the other
Party brief details of the dispute stating its contentions as to the facts and the Parties’ rights
and obligations concerning the dispute. The conciliator may, for this purpose, suggest
further actions or investigations that may be of assistance.
13.1.4 The Parties shall promptly make available to the conciliator all information, documents,
access to the Site and appropriate facilities that the conciliator requires to resolve the
dispute.
13.1.5 The conciliator shall consult with the Parties in an attempt to resolve the dispute by
agreement. The conciliator may do any of the following, or any combination of them:
(1) meet the Parties separately from each other or together and consider documents
from one Party not sent or shown to the other
(2) conduct investigations in the absence of the Parties
(3) make use of specialist knowledge
(4) obtain technical or legal advice
(5) establish the procedures to be followed in the conciliation
13.1.6 The conciliator shall not be an arbitrator and the Arbitration Act 2010 and the law relating to
arbitration shall not apply to the conciliation.
13.1.7 The conciliator’s terms of appointment shall be those in the Works Requirements or, if there
are none, those agreed by the Employer and the Contractor with the conciliator.
13.1.8 If the dispute is not resolved by agreement within 42 days after the conciliator was
appointed, or a longer period proposed by the conciliator and agreed by the Parties, the
conciliator shall give both Parties a written recommendation. The conciliator shall base the
recommendation on the Parties’ rights and obligations under the Contract.
13.1.9 If either Party is dissatisfied with the conciliator’s recommendation, it may, within 42 days
after receiving the conciliator’s recommendation, so notify the other Party. The notice shall
state that it is given under sub-clause 13.1 of the Contract, and shall state the matters in
dispute and the reasons for dissatisfaction. If the conciliator has failed to give a
recommendation within 42 days after appointment, either Party may give a notice of
dissatisfaction. If notice of dissatisfaction has been given in accordance with this clause,
either Party may refer the dispute to arbitration under sub-clause 13.3.
13.1.10 If neither Party gives notice of dissatisfaction within 42 days after receiving the conciliator’s
recommendation, the recommendation shall be conclusive and binding on the Parties, and
the Parties agree to comply with it. If, in such circumstances, a Party fails to comply with the
conciliator’s recommendation, the other Party may [without limiting its other rights] refer the
failure itself to Adjudication, [where the dispute is a dispute relating to payment], or to
arbitration under sub-clause 13.3, and need not invoke this sub-clause 13.1 for this reference.
46
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
13.1.11 If the conciliator has recommended the payment of money and a notice of dissatisfaction is
given, the following shall apply:
(1) The Party concerned shall make the payment recommended by the conciliator,
provided that the other Party first
(a) gave a notice, complying with the arbitration rules referred to in sub-clause
13.3, referring the same dispute to arbitration and
(b) gave the paying Party a bond executed by a surety approved by the paying
Party, acting reasonably, in the form included in the Works Requirements, or if
there is none, a form approved by the paying Party, acting reasonably, for the
amount of the payment.
(2) If, when the dispute is finally resolved, it is found that the Party receiving payment on
the conciliator’s recommendation was not entitled to some or all of the amount paid,
then that Party shall repay the amount it was paid and found not to be entitled to,
together with interest.
(3) When the dispute is finally resolved, interest will be deducted from final payment
under the award or judgment.
(4) Interest under this sub-clause is calculated at the reference rate referred to in the
European Communities (Late Payment in Commercial Transactions) Regulations
2012 plus 2% per year and runs from the date of the original payment to the date of
the repayment or final payment.
(5) [This provision for interest is confidential under sub-clause 13.1.12, and in particular
shall not be taken into account or referred to in arbitration until all other matters are
resolved.]
13.1.12 The conciliation shall be confidential, and the Parties shall respect its confidentiality, except
when any of the exceptions in sub-clause 4.16 apply, or to the extent necessary to enforce a
recommendation that has become conclusive and binding. All documents provided by a
Party in connection with a conciliation shall be returned when the conciliation is concluded.
13.2 Adjudication
13.2.1 The parties have recourse to Adjudication in accordance with the Construction Contracts
Act 2013
13.2.2 Where an adjudicator reaches a decision on a dispute referred under the Construction
Contracts Act 2013, that same dispute shall not be referred to conciliation under the
Contract.
13.2.3 If a dispute between the Parties is referred to Adjudication, any conciliation relating to that
dispute immediately adjourns. In the event that no decision is reached by the adjudicator,
the parties may continue to resolve the dispute under the conciliation from the date the
dispute was referred to Adjudication. In the event that a decision is reached by the
adjudicator, the conciliation for that dispute shall be terminated.
13.3 Arbitration
Any dispute that, under sub-clause 13.1, may be referred to conciliation shall, subject to sub-clause
13.1 be finally settled by arbitration in accordance with the arbitration rules identified in the Schedule,
part 1N. For purposes of those rules, the person or body to appoint the arbitrator, if not agreed by the
Parties, is named in the Schedule, part 1N.
13.4 Jurisdiction
Subject to the above provisions of this clause, the Parties submit to the jurisdiction of the Irish courts to
settle any dispute that may arise out of or in connection with the Contract or the Works.
47
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
48
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
14.1.2 Covid-19 Mandatory Closure means the closure of the Site due to Covid-19 mandated by
Law and/or mandated by order of a public authority exercising authority under Law, that did
not arise as a result of or in connection with an act, omission or breach of Legal Requirements
of the Contractor or the Contractor’s Personnel or a breach of the Contract by the Contractor.
14.1.3 Site Closure Costs has the meaning set out in the Site Closure Costs Supplement.
14.1.4 Site Closure Costs Supplement means the document of the same name in the Works
Requirements or, if there is none, the version of the document of the same name published
on the Office of Government Procurement website most recently before the Designated Date.
14.2.1 The Contractor’s sole remedies for a Covid-19 Mandatory Closure shall be those stated in
sub-clause 9.3 for a Delay Event under the Schedule Part 1K Event 15 and Site Closure Costs
under this clause 14. The provisions of clause 10 shall apply in respect of any extension of
time to the Date of Substantial Completion under sub-clause 9.3 for a Delay Event under the
Schedule Part 1 K Event 15 and an adjustment to the Contract Sum for the Site Closure Costs
under this clause 14 in respect of a Covid-19 Mandatory Closure.
14.2.2 The period of any Covid-19 Mandatory Closure shall not be taken into consideration in
calculating the period under sub-clause 12.4(4).
14.3.1 In the event of a Covid-19 Mandatory Closure there shall be added to the Contract Sum the
Site Closure Costs for the period of the Covid-19 Mandatory Closure[s], excluding the first [7]
days in total of the Covid-19 Mandatory Closure or where there is more than one Covid-19
Mandatory Closure, the Covid-19 Mandatory Closures.
14.3.2 The Contractor shall only be entitled to Site Closure Costs to the extent that all of the following
apply:
(1) the Site Closure Costs are not a result of the Contractor’s or Contractor’s Personnel’s
act or omission or the Contractor’s breach of the Contract
(2) if the Works are concurrently delayed by more than one cause, and one or more of the
causes is not a Covid-19 Mandatory Closure, there shall be no increase to the Contract
Sum for Site Closure Costs for the period of concurrent delay
(3) the Contractor makes all reasonable efforts to avoid and minimise the adverse effects
of the Covid-19 Mandatory Closure
(4) the Contractor has complied with sub-clause 10.3, clause 14 and the Site Closure
Costs Supplement in full [including giving notices and details within the time required]
and continues to comply with its obligations under the Contract
(5) the Contractor has not claimed or received as part of the Site Closure Costs, any costs
in respect of which it is entitled to claim assistance or receive payment under any
scheme, relief, benefit or otherwise [including under the Financial Provisions (Covid-
19) (2) Act 2020 (Act No. 8 of 2020) or similar Law]
49
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
14.3.3 The Contractor warrants that the details that it provides as required by the Site Closure Costs
Supplement are a complete and full break-down of the relevant costs, on a transparent and
‘open book’ basis.
14.3.4 Any adjustment to the Contract Sum in accordance with sub-clause 14.3.1 shall be paid as
part of the Contract value of the Works properly executed by the Contractor under sub-clause
11.1.2(1). The retention percentage at 11.3.1 shall not apply to payments under clause 14.
End of Conditions.
50
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
Remuneration has the meaning set out in Section 13 of the Industrial Relations
(Amendment) Act 2015.
Workers means
(a) any individuals employed by, or otherwise working for the Contractor or the
Contractor’s Personnel on or adjacent to the Site and fall within any categories of
workers to whom a relevant sectoral employment order applies in accordance with
its terms and
(b) any foreperson, charge hand or other person who supervises or administers while
performing duties within (a) but in respect only of the remuneration according to
sub-clause PV1.1.2(i) applicable to those duties and 50% of their total hours
worked.
[Site agents, managers, other full time supervisors and administrators, and surveyors, for
example, are excluded.]
51
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS
PV1.1.3 Materials
The Contract Sum shall be adjusted by the amount of an increase (in the case of an
increase) or the amount of a decrease (in the case of a decrease) in the Price of material
that results from either or both of these calculations where applicable:
So far as the Price of any material at the Purchase Date has increased or decreased
by more than 15 percent of the Price at the Tender Inflation Indexation Date, then that
excess percentage over 15 percent is applied to its Price at the Tender Inflation
Indexation Date (the “First Adjustment”).
So far as the Price of any material at the Base Date has increased or decreased at the
Purchase Date by more than 10 percent, then that excess percentage over 10 percent
is applied to the Price at the Base Date (the “Second Adjustment”)
PROVIDED THAT
in the case of an increase arising from both the First Adjustment and the Second
Adjustment, the Contract Sum shall only be adjusted by the amount of the higher of
the two increases, but not the amount of both; and
in the case of a decrease arising from both the First Adjustment and the Second
Adjustment, the Contract Sum shall only be adjusted by the amount of the lower of the
two decreases, but not the amount of both.
PV1.2 Communications
The Contractor shall maintain arrangements to become aware of any significant possibility of an
increase or decrease in the Contract Sum that may arise in accordance with this clause PV1 and
shall immediately notify the Employer’s Representative of any such possibility and keep him informed
of any opportunities to minimise an increase.
53
PW-CF5 v2.6 07/01/2022