Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

PW CF5 v2.6 07 01 2022

Download as pdf or txt
Download as pdf or txt
You are on page 1of 59

PUBLIC WORKS CONTRACT FOR MINOR WORKS

Public Works Contract

for

MINOR BUILDING and CIVIL ENGINEERING WORKS

designed by

THE EMPLOYER

Office of Government Procurement


PUBLIC WORKS CONTRACT FOR MINOR WORKS

Public Works Contract for Minor Building and Civil Engineering Works Designed by the Employer
Document Reference PW-CF5 v.2.6
7 January 2022

© 2022 Office of Government Procurement

Published by: Office of Government Procurement


Department of Public Expenditure and Reform
Government Buildings
Upper Merrion Street
Dublin 2
PUBLIC WORKS CONTRACT FOR MINOR WORKS

CONDITIONS
Contents

1. THE CONTRACT 1
1.1 Definitions 1
1.2 Interpretation 5
1.3 Inconsistencies 6
1.4 Pricing Document and Works Proposals 6
1.5 Performance Bond 6
1.6 (not used) 6
1.7 Joint Ventures 6
1.8 Assignment 6
1.9 Miscellaneous 6
1.10 Background Information 7
2. THE LAW 8
2.1 Law Governing the Contract 8
2.2 Compliance with Legal Requirements 8
2.3 Consents 8
2.4 Project Supervisor 8
2.5 Safety, Health and Welfare at Work Act 2005 and Safety, Health and Welfare at Work 9
(Construction) Regulations 2013
2.6 Ethics in Public Office 9
2.7 Data Protection 9
3. LOSS, DAMAGE AND INJURY 11
3.1 Employer's Risks of Loss and Damage to the Works 11
3.2 Care of the Works 11
3.3 Insurance of the Works and Other Risk Items 12
3.4 Contractor's Indemnity 12
3.5 Employer's Indemnity 12
3.6 Public Liability and Employer's Liability Insurances 13
3.7 Professional Indemnity Insurance 13
3.8 Existing Facilities and Use or Occupation by Employer 13
3.9 General Requirements Concerning Insurance 13
4. MANAGEMENT 15
4.1 Co-operation 15
4.2 Contractor's Representative and Supervisor 15
4.3 Employer's Representative 15
4.4 Employer's Representative's Communications 16
4.5 Instructions 16
4.6 Works Proposals 17
4.7 Required Contractor Submissions 17
4.8 (not used) 17

PW-CF5 v2.6 07/01/2022 i


PUBLIC WORKS CONTRACT FOR MINOR WORKS

4.9 Programme 18
4.10 Progress Reports 18
4.11 Notice and Time for Employer's Obligations 18
4.12 Documents 19
4.13 Contractor's Management 19
4.14 Communications 19
4.15 Meetings 20
4.16 Confidentiality and Secrecy 20
4.17 Contractor's Things Not to Be Removed 20
4.18 Contractor's Documents 20
5. CONTRACTOR'S PERSONNEL 21
5.1 Contractor’s Personnel to Carry Out Contractor’s Obligations 21
5.2 Qualifications and Competence 21
5.3 Pay and Conditions of Employment 21
5.4 Subcontractors and Specialists 22
5.5 Collateral Warranties 23
5.6 Removal of Workers 23
5.7 Weekly Labour Records 23
5.8 Ancillary Certificates 23
6. PROPERTY 24
6.1 Ownership of Works Items 24
6.2 Infringement of Property Rights 24
6.3 Works Requirements 24
6.4 Rights in Contractor's Documents 24
7. THE SITE 25
7.1 Lands Made Available for the Works 25
7.2 Trespassers 25
7.3 Contractor Responsible for All Site Operations 25
7.4 Services for Employer's Facilities 25
7.5 Security and Safety of the Site and Nuisance 25
7.6 Other Contractors 26
7.7 Setting Out the Works 26
7.8 Archaeological Objects and Human Remains 26
7.9 Access and Facilities 26
7.10 (not used) 26
7.11 (not used) 26
7.12 Charges 27
8. QUALITY, TESTING AND DEFECTS 28
8.1 Standards of Workmanship and Works Items 28
8.2 Quality Assurance 28
8.3 Inspection 28
8.4 Tests 28
8.5 Defects 29
8.6 Defects Period 29

ii
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

8.7 Defects Certificate 29


9. TIME AND COMPLETION 30
9.1 Starting Date 30
9.2 Suspension 30
9.3 Delay and Extension of Time 31
9.4 Programme Contingency 31
9.5 Omissions and Reduction of Time 32
9.6 Substantial Completion 32
9.7 (not used) 32
9.8 Liquidated Damages 32
10. CLAIMS AND ADJUSTMENTS 33
10.1 Compensation Event 33
10.2 Contractor to Pay Employer’s Cost of Checking Quantities 33
10.3 Contractor Claims 33
10.4 Proposed Instructions 34
10.5 Employer's Representative's Determination 34
10.6 Adjustments to the Contract Sum 35
10.7 Delay Cost 36
10.8 Price Variation 36
10.9 Employer's Claims 37
11. PAYMENT 38
11.1 Interim Payment 38
11.2 Unfixed Works Items 39
11.3 Retention 39
11.4 Full Payment 40
11.5 Final Statement 40
11.6 Time for Payment and Interest 41
11.7 Value Added Tax 41
11.8 Withholding Tax 41
12. TERMINATION 42
12.1 Termination on Contractor Default 42
12.2 Consequences of Default Termination 43
12.3 Suspension by the Contractor 44
12.4 Termination by the Contractor 44
12.5 Termination at Employer's Election 44
12.6 Consequences of Termination by Contractor or at Employer's Election 44
12.7 Survival 45
12.8 Payment 45
12.9 Reference to Conciliation 45

iii
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

13. DISPUTES 46
13.1 Conciliation 46
13.2 Adjudication 47
13.3 Arbitration 47
13.4 Jurisdiction 47
13.5 Agent for Service 48
13.6 Continuing Obligations 48
14. COVID-19 MANDATORY CLOSURE 49
14.1 Covid-19 Definitions 49
14.2 Covid-19 General Provisions 49
14.3 Covid-19 Costs 50
PV1. PRICE VARIATION 51
PV1.1 Contract Sum Adjustment 51
PV1.2 Communications 52
PV1.3 Compensation Events 52
PV1.4 Efficiency 53
PV1.5 Certificates & Payment 53

iv
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

Conditions
1 THE CONTRACT

1.1 Definitions
The following terms have the following meanings in the Contract:

Term Meaning
Adjudication means adjudication under the Construction Contracts Act 2013
Ancillary Certificate a certificate as prescribed by the Building Control Regulations, other than a
statutory certificate of compliance, given by a competent person to confirm
compliance of elements of the building, design or Works with Building
Regulations; and “Ancillary Certifier” means the person proposed to issue
such a certificate.
Applicable Factor the number in the Schedule, part 3D identified as the Applicable Factor
(Contractor) (Contractor).
Applicable Factor the number in the Schedule, part 3B identified as the Applicable Factor
(Specialist) (Specialist) for each Specialist.
Assigned Certifier the person so assigned by the Employer to certify compliance with the relevant
requirements under the Building Control Regulations.
Building Control the Building Control Regulations 1997-2014 and any amendments thereto to
Regulations the extent that they apply to the Works.
Change Order an instruction of the Employer’s Representative to change [including add to
or omit from] the Works or to change [including impose or remove]
constraints in the Contract on how the Works are to be executed.
Code of Practice for The code of practice published by the Department of Environment,
Inspecting and Community and Local Government with reference to Article 20G of the
Certifying Buildings Building Control Regulations.
and Works
Consent planning permission, order, approval, certificate, Ancillary Certificate, fire
certificate, licence, permit, environmental impact statement, or other consent
required by Legal Requirement for the execution or completion of the Works,
or identified as a Consent in the Works Requirements.
Contract Date the date the Employer issued the Letter of Acceptance.
Contract Sum the amount identified in the Agreement as the initial Contract Sum, as
adjusted in accordance with the Contract.
Contractor’s drawings, specifications, manuals, reports, Consents and other [eye
Documents readable and machine readable] written material relating to the Works that
the Contractor uses, prepares or gives to the Employer or any other person,
or is to use, prepare or give to the Employer or any other person
 under the Works Requirements or
 under any Legal Requirement or
 to obtain any Consent.
Contractor’s Things equipment, facilities and other things the Contractor [or Contractor’s
Personnel] uses on or adjacent to the Site to execute the Works, except
Works Items.
Contractor’s the Contractor’s representative, supervisor and Subcontractors, employees
Personnel and other persons working on or adjacent to the Site for the Contractor or
Subcontractors, and other persons assisting the Contractor to perform the
Contract.

1
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

Term Meaning

Date for Substantial the date identified as the Date for Substantial Completion of the Works or
Completion of the Section in the Schedule, part 1G or 2C, and, if the Schedule states a period,
Works or a Section the last day of that period, starting on the Contract Date, in either case as
adjusted in accordance with the Contract.
Data Protection Law is all applicable data protection Law, including the General Data Protection
Regulation (Regulation (EU) 2016/679).
Defect non-compliance of the Works or a Works Item with the Contract [including a
failed test and, after Substantial Completion, work that has not been
completed].
Defects Certificate a certificate of the Employer’s Representative that the Defects Period has
ended.
Defects Period the period starting on Substantial Completion of the Works and continuing
for the period stated in the Schedule, as may be extended under sub-clause
8.6.2.
Designated Date the date 10 days before the last day for receipt of the Contractor’s tender for
the Works, or, if there was none, 10 days before the Employer received the
Contractor’s tender for the Works.
Employer’s any of the following:
Personnel  the Employer’s Representative
 the Employer’s employees, agents and consultants in connection with
the Contract when acting on behalf of the Employer but not when
exercising authority under Law
 other contractors of the Employer working on the Site when acting within
the scope of their contracts with the Employer
 anyone else the Employer’s Representative notifies the Contractor is
Employer’s Personnel
 Assigned Certifier.
Employer’s the architect, engineer, quantity surveyor or other person appointed by the
Representative Employer as its representative in accordance with the Contract.
Inspection Plan the document prepared by the Assigned Certifier in accordance with the Code
of Practice for Inspecting and Certifying Buildings and Works having regard to
the Works Requirements. The Inspection Plan also includes the Inspection
Notification Framework, both of which may be amended by the Assigned
Certifier from time to time.
Inspection the document prepared by the Assigned Certifier and agreed with the
Notification Contractor and the Employer in accordance with the Code of Practice for
Framework Inspecting and Certifying Buildings and Works identifying key stages or items
of work that individual certifiers and the Assigned Certifier are to be notified
by the Contractor as the Works are ready for inspection.
Law enactments and statutory instruments, each as defined by the Interpretation
Act 2005, and regulations, directives and decisions of the European Union
having direct effect in Ireland.

2
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

Term Meaning

Legal Requirement a requirement that applies to the Works as a result of any of the following:
 Law
 a Consent
 a decision of an Irish court, the European Court of Justice or the
European Court of First Instance
 the requirements of any person having authority in connection with the
Works under any Law
 the requirements of any person with whose systems the Works will
connect
the legal rights of any person.
Letter of Acceptance the Employer’s letter to the Contractor accepting the Contractor’s tender.
Personal Data shall have the meaning set out in the General Data Protection Regulation in
respect of any such personal data processed on behalf of the Employer.
Section a part of the Works identified as a Section in the Schedule, part 1G.
Site any place
 where the Works are to be executed according to the Contract or
 provided by the Employer for the Works or
 where the Contractor is to operate or maintain Employer’s facilities or
 that the Works Requirements identify as part of the Site.
Site Working Day a day on which, according to the Contract and the Contractor’s programme
most recently submitted to the Employer’s Representative, the Contractor is
to execute the Works on the Site.
Specialist any of the following:
 a Subcontractor or supplier of a Works Item named in the Contract
 Contractor’s Personnel who do or are to do design
 Contractor’s Personnel stated in the Works Requirements to be
Specialists.
Starting Date the day the Contractor proposes to start executing the Works, as notified by
the Contractor to the Employer’s Representative under sub-clause 9.1.
Subcontractor a person to whom the execution of part of the Works is subcontracted [by the
Contractor or another Subcontractor].

3
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

Term Meaning

Substantial all of the following have happened:


Completion of the (1) the Works or Section are complete so that they can be taken over and
Works or a Section used by the Employer for their intended purpose and there are no
Defects other than
(a) Defects accepted by the Employer under sub-clause 8.5.4 or
(b) minor Defects to which all of the following apply:
(i) they do not prevent the Works or the part from being used for
their intended purpose
(ii) the Employer’s Representative considers the Contractor has
reasonable grounds for not promptly rectifying them
(iii) rectification will not prejudice the safe and convenient use of
the Works or the part
(2) all tests that are required by the Contract to be passed before
Substantial Completion have been passed
(3) the Contractor has given the Employer’s Representative the
Contractor’s Documents that the Contract requires be provided before
Substantial Completion
(4) the Contractor has given the Employer’s Representative the collateral
warranties that the Contract requires for the Works or part.
(5) the details in the Certificate of Compliance on Completion of the Works
or a part thereof have been included on the Register maintained under
Part IV of the Building Control Regulations.
Tender Inflation the date identified in the Schedule, part 3E.
Indexation Date
VAT value-added tax payable in Ireland under Law.
Works Item a part of the Works, anything that the Contractor intends will become part of
the Works, or temporary works for the Works.

4
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

1.2. Interpretation
1.2.1 The Parties intend the Contract to be given purposeful meaning for efficiency and public benefit
generally and as particularly identified in the Contract.
1.2.2 Unless the context indicates otherwise, in the Contract
(1) References to the Works are to the works described in the Works Requirements.
(2) Words in the singular include the plural and vice versa.
(3) References to an individual are to a human person.
(4) References to a person include human persons and corporate and unincorporated
bodies.
(5) Words in any gender include all genders.
(6) References to any Law include amendments and replacements.
(7) References to the Contract or any other writing include amendments.
(8) References to a day mean a calendar day.
(9) References to a week mean a period of 7 days.
(10) References to a month mean a calendar month.
(11) References to a working day mean a day that is not Saturday, Sunday, a public holiday
established under the Organisation of Working Time Act 1997 or Good Friday.
(12) References to a requirement to submit a document or proposed course of action to
Employer’s Representative mean to submit it according to sub-clause 4.7, or another
procedure that applies according to the Works Requirements, and sub-clause 4.7 or the
Works Requirements shall apply in every such case. [Accordingly the Contractor may not
implement the submission until permitted by sub-clause 4.7 or the Works Requirements.]
(13) References to the Contractor’s current programme are to the programme in the Works
Proposals, if there is one, if not, to the programme first submitted by the Contractor under
sub-clause 4.9, or, in either case, to any later programme submitted by the Contractor if
the period for the Employer’s Representative to review it has passed and there is no
outstanding objection.
(14) References to liability include claims, demands and proceedings.
(15) Terms such as including, in particular, such as, and for example, are not to be read as
exhaustive, or to limit, but may extend, the generality of the provisions to which they relate.
(16) References to the Agreement and Schedule are to the attached agreement and
completed schedule.
(17) References to the Works Requirements, Works Proposals and the Pricing Document
are to the Works Requirements, Works Proposals and Pricing Document identified in the
Schedule, part 1B; in the case of Works Requirements, as changed by Change Orders; in
the case of Works Proposals, as changed under sub-clause 4.6.2; and in the case of the
Pricing Document, the rates shall be adjusted by multiplying the rates by the Applicable
Factor (Contractor) or Applicable Factor (Specialist) in accordance with sub-clause 11.1.3.
(18) References to Delay Events and Compensation Events are to events identified as Delay
Events and Compensation Events in the Schedule, part 1K.
(19) References to the initial Contract Sum are to the Contract Sum stated in the Agreement;
references to an initial Date for Substantial Completion are to a Date for Substantial
Completion identified in the Schedule; and references to the initial Works Requirements
are to the Works Requirements identified in the Schedule.
(20) The Parties are the Employer and the Contractor
1.2.3 Clarifications, examples and reminders are included occasionally in square brackets to show
that no significance is to be given to their absence elsewhere.
1.2.4 No rule of legal interpretation applies to the disadvantage of a Party on the basis that the Party
provided the Contract or any of it or that a term of the Contract is for the Party’s benefit.

5
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

1.3 Inconsistencies
1.3.1 Except when the Contract states otherwise, the documents in the Contract are to be taken as
mutually explanatory of each other if possible. If there is an inconsistency between the
documents, they take precedence as follows:
 First, the Agreement, even if it has not been executed
 Second, the attached Schedule and the Letter of Acceptance and any post-tender
clarifications listed in it
 Third, the Contractor’s completed form of tender (excluding other documents in the tender)
 Fourth, these Conditions
 Fifth, the Works Requirements
 Sixth, the Pricing Document
 Seventh, the Works Proposals, if there are any
 Eighth, any other documents in the Contract
1.3.2 If either Party becomes aware of any inconsistency between terms of the Contract, it shall
promptly inform the other Party.
1.3.3 If there is an inconsistency between figured and scaled dimensions, the figured dimensions
prevail.
1.3.4 Inconsistencies between the Works Requirements and the Pricing Document shall be resolved
by an instruction from the Employer’s Representative under sub-clause 4.4.1(1) of the Contract.
Where inconsistencies are found to exist between the Works Requirements and the Pricing
Document the Works Requirements take precedence with respect to the Works to be completed
and a compensation event shall arise in accordance with the Schedule, Part 1K (17).

1.4 Pricing Document and Works Proposals


Nothing in and no omission from the Pricing Document or Works Proposals limits the scope of the
Works or the Contractor’s obligations. Nothing in the Works Proposals imposes obligations on the
Employer.

1.5 Performance Bond


Before the Starting Date, unless the Schedule, part 1E, says that no bond is required, the Contractor
shall give the Employer a performance bond in the form in the Works Requirements, or, if there is none,
a form approved by the Employer. The performance bond shall be in the amount stated in the
Schedule, part 1E, and shall be executed by the Contractor and by a surety approved by the Employer.

1.6 (sub-clause not used)

1.7 Joint Ventures


If the Contractor is a joint venture, consortium or other unincorporated grouping of two or more persons,
those persons shall be jointly and severally liable to the Employer for the performance of the Contract.

1.8 Assignment
The Contractor may not assign the benefit of the Contract, or any part of it, without the Employer’s
consent.

1.9 Miscellaneous
1.9.1 The Contract and the documents referred to in it supersede all previous representations,
arrangements, understandings and agreements between the Parties about the subject-matter of
the Contract, and set out the entire agreement between the Parties about the subject-matter of

6
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

the Contract. Neither Party has relied on any other written or oral representation, arrangement,
understanding or agreement.
1.9.2 All the terms of the Contract are severable, and if any part is unenforceable, illegal or void, it is
to that extent considered not to form part of the Contract, and the enforceability, legality and
validity of the rest of the Contract will not be affected.
1.9.3 The Contract may only be changed by a document in writing signed by an authorised
representative of each Party.
1.9.4 The rights of a Party will not be prejudiced or restricted by any indulgence or forbearance
extended to the other Party, and no waiver by a Party of any breach will waive any other
breach.

1.10 Background Information


1.10.1 In this sub-clause 1.10 Background Information means any information made available on,
before or after the Contract Date to the Contractor or to anyone on the Contractor’s behalf by
the Employer or by anyone acting on the Employer’s behalf in connection with the Contractor’s
tender for the Contract, which information is not included in this Contract. Background
Information also includes any information stated to be ‘Background Information’.
1.10.2 The Contractor acknowledges and agrees as follows:

(1) The Employer has no liability whatsoever to the Contractor in contract, tort, under statute,
or on any other basis whatsoever (including negligence and breach of statutory or other
duty) in connection with Background Information.
(2) The Employer has not made and does not make any warranty, representation, or
undertaking in connection with Background Information.

(3) The Employer has not authorised anyone to make any warranty, representation, or
undertaking on the Employer’s behalf in connection with Background Information.
(4) Without limiting anything in this sub-clause 1.10, the Contractor irrevocably and forever
waives any liability that the Employer may have to the Contractor in connection with
Background Information regardless of any of the following circumstances, and the
Contractor acknowledges that the Employer makes no warranty, representation, or
undertaking in regard to those circumstances:
a) whether or not Background Information is correct
b) whether or not Background Information is complete
c) whether or not any testing, investigation, surveys, or other work to prepare
Background Information was done negligently or in breach of statutory or other
duties
d) whether or not those who carried out any testing, investigation, surveys, or other
work to prepare Background Information were properly selected or supervised
e) whether or not Background Information was suitable for the purposes for which
the Contractor or anyone on the Contractor’s behalf might use it
f) whether or not any errors or omissions in Background Information are major or
numerous or both
g) whether or not Background Information represents all the information available to
the Employer
h) whether or not any works described in Background Information are done as
described in Background Information or at all
i) whether or not the Employer had or has other information that might render
Background Information misleading
j) the manner in which Background Information was made available
k) whether or not the Contractor had adequate opportunity to carry out any testing,
investigations, surveys, or other work or otherwise to verify Background
Information.

(5) The Contractor has included in the Contract Sum for the risks that the Contractor has
agreed to bear under this sub-clause 1.10.

7
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

2 THE LAW

2.1 Law Governing the Contract


Irish law governs the Contract and its interpretation.

2.2 Compliance with Legal Requirements


The Contractor shall in performing the Contract comply with all Legal Requirements and ensure that
the Contractor’s Personnel comply with all Legal Requirements.

2.3 Consents
2.3.1 The Employer has obtained, or shall obtain, the Consents that the Works Requirements say
that the Employer is to obtain. The Contractor shall obtain all other Consents.
2.3.2 The Contractor shall give and comply with all notices and pay all taxes, fees and charges
required under Legal Requirements to be paid in connection with performing the Contract,
unless the Works Requirements say otherwise.

2.4 Project Supervisor


2.4.1 If the Schedule, part 1C, states that the Contractor is to be appointed project supervisor for the
construction stage in accordance with the Safety, Health and Welfare at Work (Construction)
Regulations 2013 (the Construction Regulations) for the Works, or a project including the
Works, the Contractor shall accept the appointment by entering into the appointment in the
form in the Works Requirements. If the Schedule, part 1C, states that an individual or body
corporate named in the Works Proposals is to be appointed project supervisor for the
construction stage in accordance with the Construction Regulations for the Works, or a project
including the Works, the Contractor shall ensure that the individual or body corporate named in
the Works Proposals accepts the appointment by entering into the appointment in the form in
the Works Requirements. The Contractor shall, if appointed as project supervisor, comply with
its obligations under the Construction Regulations in connection with that appointment. If the
Employer terminates the appointment of the Contractor or other person named in the Works
Proposals as project supervisor for the construction stage as a result of that project
supervisor’s failure to comply with its obligations, the Contractor shall pay to the Employer all
the Employer’s cost resulting from the termination [including the cost of appointing and fees
and expenses paid to a replacement project supervisor, or, if the Employer acts as project
supervisor itself, the Employer’s cost of doing so].
2.4.2 If the Contractor or a person named in the Works Proposals is to be appointed as project
supervisor for the construction stage, the Contractor represents and warrants to the Employer
that the Contractor or person named in the Works Proposals is competent and will allocate
adequate resources to enable itself to perform its duties under the Construction Regulations.
2.4.3 If the Contractor or a person named in the Works Proposals is appointed as project supervisor
for the construction stage the Contractor shall ensure that the project supervisor has the
insurances required of the project supervisor under its appointment.
2.4.4 The Contractor shall [without adjustment to the Contract Sum or extension of time] comply with
all the lawful directions of the project supervisors appointed for the construction stage and the
design process in accordance with the Construction Regulations for the Works, or any project
including the Works, and give them any copies of Contractor’s Documents that they may
request.
2.4.5 The Contractor shall, before Substantial Completion of the Works or any Section, give the
Employer the documents required for the safety file (as defined in the Construction
Regulations).

8
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

2.5 Safety, Health and Welfare at Work Act 2005 and Safety, Health and Welfare at Work
(Construction) Regulations 2013
2.5.1 The Contractor shall [without limiting other obligations] ensure, so far as is reasonably
practicable, that the Works are constructed to be safe and without risk to health, and that the
Works comply in all respects, as appropriate, with the relevant statutory provisions.

2.5.2 The Contractor represents and warrants to the Employer that the Contractor is, and will, while
performing the Contract, be a competent person for the purpose of ensuring, so far as is
reasonably practicable, that the Works are constructed to be safe and without risk to health
and that they comply in all respects, as appropriate, with the relevant statutory provisions.

2.5.3 The Contractor represents and warrants to the Employer that the Contractor is and will, while
performing the Contract, be a competent person to carry out the Works and has allocated and
will allocate sufficient resources to enable itself to comply with the requirements and
prohibitions imposed on the Contractor by or under the relevant statutory provisions.
2.5.4 In this sub-clause 2.5 and sub-clause 2.4, competent person, reasonably practicable and
relevant statutory provisions are construed according to section 2 of the Safety, Health and
Welfare at Work Act 2005.

2.6 Ethics in Public Office


The Contractor warrants that
2.6.1 neither the Contractor nor any person on the Contractor’s behalf has offered, given or agreed
to give to the Employer or to any of the Employer’s Personnel any gift or consideration of any
kind in connection with the Contract, nor will they make such an offer, gift or agreement and
2.6.2 neither the Contractor nor any person on the Contractor’s behalf has committed any offence
under the Prevention of Corruption Acts 1889 to 2010 or the Ethics in Public Office Acts 1995
and 2001 in connection with the Contract, nor will they commit any such offence and
2.6.3 no Minister of the Government or Minister of State, or officer or employee of the Employer, will
have or receive any share or part of the Contract or any benefit from the Contract and
2.6.4 unless fully disclosed to and agreed by the Employer in advance
(1) no former officer nor employee of the Employer nor of a consultant to the Employer
whose duties related to the Works will, for 12 months after leaving the employment or
office, be engaged as Contractor’s Personnel and
(2) no consultant or former consultant to the Employer whose duties related to the Works will
be engaged as Contractor’s Personnel, except for a Specialist whose contract is to be
novated from the Employer to the Contractor.

2.7 Data Protection


2.7.1 The Contractor agrees that
(a) (a) the Contractor shall process Personal Data only in accordance with the Contract and Data
Protection Law;

(b)(b) the Contractor shall ensure persons authorised by the Contractor to process Personal Data
are subject to confidentiality obligations as provided under Data Protection Law;

(c) (c) the Contractor must take appropriate technical and organisational security measures as
are required to comply with Data Protection Law;

(d)(d) the Contractor may engage sub-processors to perform processing on its behalf, provided
it gives prior written notice and informs the Employer of any changes concerning the status
of such sub-processors and allows the Employer reasonable opportunity to object to such
changes;

9
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

(e) (e) where any sub-processor of the Contractor will be processing Personal Data on behalf of
the Employer, the Contractor shall ensure that a written contract exists between the
Contractor and the sub-processor containing clauses equivalent to those imposed on the
Contractor by the Contract;

(f) (f) the Contractor shall delete or return all Personal Data as directed by the Employer’s
Representative and not later than when the Contractor completes its contractual duties
relating to such data processing;

(g)(g) the Contractor shall: (i) make available to the Employer all information necessary to
demonstrate compliance with this Clause; and (ii) allow for and assist with audits, including
inspections, conducted by or on behalf of the Employer, in order to ensure such
compliance, provided however that the Employer shall be entitled, at its discretion, to
accept adherence by the Contractor to an approved code of conduct or an approved
certification mechanism to aid demonstration by the Contractor that it is compliant;

(h)(h) the Contractor shall inform the Employer’s Representative immediately if, in its opinion, it
receives an direction which infringes Data Protection Law;

(i) (i) the Contractor shall notify the Employer’s Representative within 24 hours of becoming
aware of any act or omission [including breach of security] leading to the accidental or
unlawful destruction, loss, alteration, unauthorised disclosure of or access to Personal
Data transmitted, stored or otherwise processed and shall provide co-operation and
assistance to the Employer as is required to mitigate the effects of, and comply with
applicable reporting obligations in respect of, such act or omission; and

(j) (j) no Personal Data shall be transferred outside the European Economic Area by the
Contractor or any of its agents or sub-processors without the prior written consent of the
Employer, and the Contractor shall comply with Data Protection Law in respect of Personal
Data transfers outside the European Economic Area which the Employer has consented
to.

10
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

3 LOSS, DAMAGE AND INJURY

3.1 Employer’s Risks of Loss and Damage to the Works


The Employer shall bear the risk of loss of or damage to the Works resulting from any of the following:
(1) war, invasion, act of foreign enemies, hostilities whether war is declared or not, civil war,
rebellion, revolution, insurrection, military or usurped power
(2) pressure waves caused by aircraft or other airborne objects travelling at sonic or supersonic
speeds
(3) contamination by radioactivity or radioactive, toxic, explosive or other hazardous properties of
any explosive nuclear assembly or its components, in each case not caused by the Contractor
or the Contractor’s Personnel
(4) terrorism, but only if terrorism is a permitted exclusion from the Contractor’s insurance of the
Works
(5) use or occupation of the Works by the Employer or the Employer’s Personnel, other than
(i) as provided for in the Contract or
(ii) to the extent that the loss or damage is caused by the negligence of the Contractor or the
Contractor’s Personnel, or the Contractor’s breach of the Contract (subject to sub-clause
3.8 if it applies)
(6) design of the Works by the Employer or Employer’s Personnel, but not if the design is covered
by insurance required under the Contract.

3.2 Care of the Works


3.2.1 The Contractor shall have full responsibility for the care of, and risk of loss of and damage to,
the Works, Works Items, Contractor’s Things, Works Requirements, Works Proposals,
Contractor’s Documents, and anything the Employer gives the Contractor for the Works
(together, Risk Items) from and including the Starting Date until and including the date the
Employer’s Representative issues the certificate of Substantial Completion of the Works or
relevant Section. After that date, the Contractor shall be responsible for loss of and damage to
Risk Items due to any of the following:
(1) Defects
(2) occurrences before the Employer’s Representative issued the certificate of Substantial
Completion
(3) activities of the Contractor or Contractor’s Personnel.
But the Contractor’s responsibility under this sub-clause 3.2 excludes loss of and damage to
the Works that is at the Employer’s risk under sub-clause 3.1.
3.2.2 The Contractor shall promptly rectify any loss and damage to Risk Items for which it is
responsible under this sub-clause 3.2 [at its own expense if there are not sufficient insurance
proceeds].
3.2.3 If loss of or damage to the Works, for which the Contractor is not responsible under this sub-
clause 3.2, occurs before the Defects Certificate is issued, the Contractor shall rectify it in
accordance with any instruction of the Employer.

11
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

3.3 Insurance of the Works and Other Risk Items


3.3.1 From the Starting Date, the Contractor shall insure the Works and other Risk Items against
loss and damage. The insurance shall name the Contractor, the Employer and any other
persons the Employer requires as insured. The insurance shall be kept in place for each
Section until the date that the certificate of Substantial Completion of the Section is issued,
and for the Works, except Sections that have a certificate of Substantial Completion, until the
date that the certificate of Substantial Completion of the Works is issued. If so required in the
Schedule, part 1D, the insurance for any Section or part of the Works that has reached
Substantial Completion shall be extended until the Employer’s Representative certifies
Substantial Completion of the whole of the Works. In any event, after Substantial Completion,
the insurance shall be kept in place until the Defects Certificate is issued, to cover loss and
damage for which the Contractor remains responsible under the Contract. The limit of the
insurance shall be, except for loss of or damage to Contractor’s Things and Employer’s
property, for the full reinstatement cost of the property insured, including the cost of demolition,
removal of debris, delivery, professional fees, inflation occurring during the construction and
reinstatement periods, and profit. The sum insured for professional fees shall include at least
the percentage of the Contract Sum stated in the Schedule, part 1D. The insurance shall
include any Employer’s property listed in the Schedule, part 1D, and the indemnity limit for
those items shall be as stated in the Schedule.
3.3.2 The proceeds of the insurance of the Works, less the portion to cover professional fees that
the Employer is to pay, shall be paid into a bank account in the joint names of the Employer
and the Contractor. They shall be paid out of the account to the Contractor in instalments on
the basis of interim payment certificates of the Employer’s Representative of the Contract
value of the work done and Works Items delivered to the Site to rectify the loss or damage,
following generally sub-clause 11.1, and also paid out of the account to the Employer for its
other costs. Any balance remaining in the account after the work of rectification is complete
shall be paid to the Employer.

3.4 Contractor’s Indemnity


3.4.1 The Contractor shall indemnify the Employer and the Employer’s employees against
(1) liability and
(2) loss of and damage to the Employer’s property [including the Site], unless excluded
under sub-clause 3.8
arising from or in the course of the Contractor’s performance or non-performance of the
Contract.
3.4.2 The Contractor’s indemnity in this sub-clause 3.4 does not apply to the Employer’s liability
under the Contract to the Contractor; nor does it apply to liability to the extent that the liability
is covered by the Employer’s indemnities in sub-clauses 3.5 and 6.2.

3.5 Employer’s Indemnity


The Employer shall indemnify the Contractor against:
(1) liability for death, injury, or illness of any person or loss of or damage to any physical property
that the Contractor incurs in the course of performing the Contract and to the extent caused by
the negligence of the Employer and
(2) liability for property damage that is the unavoidable result of executing the Works in
accordance with the Works Requirements

12
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

3.6 Public Liability and Employer’s Liability Insurances


3.6.1 From the Starting Date until the date the Defects Certificate is issued, the Contractor shall
insure the Employer and the Contractor against their respective liabilities for
(1) death, injury or illness of any person and
(2) loss of or damage to any physical property and
(3) obstruction, loss of amenities, nuisance, trespass, stoppage of traffic and infringement of
light, easement or quasi-easement
resulting from an accident arising from or in the course of the performance or non-performance
of the Contract except to the extent covered by the Employer’s indemnities in sub-clause 3.5
or sub-clause 6.2.2(2).
3.6.2 From the Starting Date until the date the Defects Certificate is issued, the Contractor shall
insure itself against liability for death, injury or illness of Contractor’s Personnel. For
employees of Subcontractors, this obligation may be satisfied by ensuring that the
Subcontractor maintains the insurance. The Contractor shall ensure that this insurance
includes a provision that indemnifies the Employer against any liability for which the Contractor
would be entitled to an indemnity, including costs, charges and expenses.
3.6.3 The minimum indemnity limit of the Contractor’s public liability and employer’s liability
insurances shall be as stated in the Schedule, part 1D.
3.6.4 If the Contractor or the Contractor’s Personnel return to the Site in connection with the Works
after the Defects Certificate is issued, the Contractor shall ensure the insurances required by
this sub-clause 3.6 are in place at all times that the Contractor or Contractor’s Personnel are
on Site.

3.7 Professional Indemnity Insurance


If the Schedule states that professional indemnity insurance is required, from the Starting Date until
the sixth anniversary of the date that the Employer’s Representative certifies Substantial Completion of
the Works, or any other period stated in the Schedule, part 1D, the Contractor shall maintain
professional indemnity insurance for its performance of the Contract. The indemnity limit shall be at
least that stated in the Schedule, part 1D. This insurance shall include retroactive cover to when the
Contractor’s design of the Works and Works Items started.

3.8 Existing Facilities and Use or Occupation by Employer


This sub-clause 3.8 shall apply only if so stated in the Schedule, part 1D.
To the extent that (a) the Works involve alteration or extension of existing facilities owned by the
Employer, or (b) the Employer uses or occupies the Works, the Employer shall bear the risk of loss of
or damage to those facilities and the part of the Works used or occupied by the Employer, and their
contents owned by the Employer, caused by any of the following perils, as defined in the Works
Requirements or, if not defined there, in standard fire and specified perils insurance policies available
in Ireland:
(1) fire, storm, tempest, flood
(2) bursting or overflowing of water tanks, apparatus or pipes
(3) explosion, impact, aircraft
(4) riot, civil commotion or malicious damage.
but the Contractor shall bear the risk of such loss and damage to the extent caused by the negligence
of the Contractor or Contractors Personnel to the extent (and up to the limit) required to be insured
under sub-clause 3.6.1.

3.9 General Requirements Concerning Insurance


3.9.1 The insurance required by the Contract (the Insurance) shall be placed with reputable
insurers approved by the Employer.
3.9.2 The only exclusions from the Insurance shall be those listed in the Schedule, part 1D. The
levels of excess shall be no higher than stated in the Schedule, part 1D.

13
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

3.9.3 Liability Insurance on which the Employer is required to be insured shall include a cross-
liability clause. All Insurance on which the Employer is required to be insured shall provide that
the insurer accepts the term “insured” as applying to each insured person as if a separate
policy of insurance had been issued to each of them, but without the overall limit of indemnity
being increased as a result, and that non-compliance by the Contractor or any other insured
will not affect the Employer’s rights
3.9.4 The Contractor shall comply with the terms of the Insurance policies.
3.9.5 Within 10 working days of being requested to do so, the Contractor shall give the Employer
evidence to the Employer’s satisfaction that the Insurances are in effect, including copies of
policies and receipts for premiums. For professional indemnity insurance, a certificate in the
form included in the Works Requirements, or, if there is none, a form approved by the
Employer, signed by the broker or underwriter, may be given instead of a copy of the
professional indemnity policy.
3.9.6 The Contractor shall not make any material reduction to the Insurance cover unless approved
in advance by the Employer. The Contractor shall promptly notify the Employer of any
cancellation, renewal, non-renewal or material reduction by the insurer of any Insurance policy.
3.9.7 If the Contractor fails to maintain any of the Insurances in the terms required by the Contract,
the Employer shall be entitled [without affecting its other rights] to take out the insurance and
pay the premiums, and the Contractor shall pay the amount of the premiums to the Employer
on demand.

14
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

4 MANAGEMENT

4.1 Co-operation
4.1.1 The Employer [subject to restraints as a public authority] and the Contractor shall support
reciprocal co-operation for the Contract purposes, including co-operation with and between
Contractor’s Personnel and Employer’s Personnel.
4.1.2 Such support may be relevant particularly to any of the following:
(1) negotiation of agreements provided for in the Contract
(2) use of most effective and compatible electronic and other methods of communicating
and recording
(3) efficient order and timing of information provided for in the Contract
(4) minimising the effects of suspension
(5) efforts by the Contractor to minimise delay and Compensation Events and their effects
(6) Contractor’s flexible management
4.1.3 Either Party, or the Employer’s Representative, may request clarifications, consultations,
workshops, exchange of information and expertise, or investigations, although not provided
for elsewhere in the Contract. The request shall specify purposes and, as relevant, proposed
participants, arrangements, methods and any proposals for recording or agreeing results.
4.1.4 The Parties may agree to consult or communicate, without prejudice. In any case, offering or
giving co-operation does not imply any admission of any responsibility or alter either Party’s
rights or duties unless otherwise agreed in writing.

4.2 Contractor’s Representative and Supervisor


4.2.1 The Contractor shall appoint, before the Starting Date
(1) a representative with full authority to act on behalf of the Contractor in all matters
concerning the Contract and
(2) a supervisor of all the Contractor’s activities on the Site, with full authority to receive
instructions and other communications on behalf of the Contractor in all matters
concerning the Contract.
The representative and the supervisor may, but need not, be the same person.
4.2.2 Matters of which the Contractor’s representative or supervisor are aware [including
communications and instructions] are presumed to be within the Contractor’s knowledge.
4.2.3 If the Contractor’s representative or supervisor are named in the Works Proposals, the
Contractor shall appoint the individuals named. If not, or either of them is changed, the
Contractor shall submit details of the proposed representative or supervisor to the Employer’s
Representative. If the Contractor’s representative or supervisor dies, or becomes incapable of
performing their role, or is no longer available to the Contractor, the Contractor shall appoint a
suitable replacement, having submitted details to the Employer’s Representative. If the
Employer’s Representative so requires because of the misconduct, negligence or
incompetence of either of them, the Contractor shall remove its representative or supervisor
and appoint a suitable replacement, having submitted details to the Employer’s
Representative.

4.3 Employer’s Representative


4.3.1 If the Employer’s Representative is not named in the Schedule, part 1A, the Employer shall,
promptly after the Contract Date, appoint, and notify the Contractor of the identity of, the
Employer’s Representative.
4.3.2 If there are limitations on the authority of the Employer’s Representative to perform its
functions or powers under the Contract, they are stated in the Contract. But any act or
instruction of the Employer’s Representative under the Contract shall have effect as if within
the Employer’s Representative’s authority, and the Contractor need not inquire into whether
the Employer has actually authorised it.

15
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

4.3.3 The Employer’s Representative may delegate in writing to named representatives any
functions or powers under the Contract and revoke any delegation. The appointment of such
a representative shall not prevent the Employer’s Representative from exercising directly any
functions or powers. The Employer’s Representative shall notify the Contractor and the
Employer of any delegation, and the names of representatives, and of any subsequent
changes, within 5 working days after the event in each case.
4.3.4 Any opinion, certificate, determination, assessment or objection of the Employer’s
Representative under the Contract may be revised in accordance with clause 13, except for
decisions stated in the Contract to be conclusive [such as rejection of a Defect under sub-
clause 8.5.4].
4.3.5 The Employer may replace the Employer’s Representative at any time, notifying the
Contractor of the replacement, and shall do so promptly if the position of Employer’s
Representative becomes vacant before the Defects Certificate (or alternatively the certificates
required following termination) have been issued. Pending appointment of a replacement, the
Employer shall carry out the functions and powers of the Employer’s Representative.

4.4 Employer’s Representative’s Communications


4.4.1 The Employer’s Representative may give the Contractor
(1) instructions, which are either
(a) directions in accordance with the Contract or
(b) Change Orders and
(2) objections, in accordance with sub-clause 4.7
4.4.2 The Employer’s Representative may give the Contractor or the Employer, or both
(1) opinions, assessments, determinations and certificates, in accordance with the
Contract and
(2) other communications [including clarifications] in accordance with the Contract or the
Employer’s Representative considers appropriate.

4.5 Instructions
4.5.1 The Employer’s Representative may issue instructions to the Contractor on any matter
connected with the Works [whether or not mentioned elsewhere in the Contract] at any time
up to the date the Defects Certificate is issued. The Contractor shall comply with an
instruction of the Employer’s Representative.
4.5.2 If the Employer’s Representative gives an instruction and calls it a direction, but the
Contractor considers that it is a Change Order, the Contractor shall be entitled to give notice
under sub-clause 10.3, and have the issue determined under clause 10. In addition to the
requirements of sub-clause 10.3, the Contractor must give this notice before starting to
implement the instruction, otherwise it will be taken to be a direction.
4.5.3 The Employer’s Representative shall not give a Change Order concerning the Works or a
Section after its Substantial Completion has been certified, except concerning Defects or
work to be done after Substantial Completion.
4.5.4 The Employer’s Representative shall give an instruction that is, in the Employer’s
Representative’s opinion, necessary for the completion of the Works. If, in the Employer’s
Representative’s opinion, it is physically impossible or contrary to Legal Requirements to
complete the Works in accordance with the Works Requirements, the Employer’s
Representative shall give a Change Order. The Employer’s Representative shall give an
instruction required under this sub-clause 4.5.4 within the time required by sub-clause 4.11.
4.5.5 Instructions of the Employer’s Representative shall be given in writing except when there is
imminent danger to safety or health or of damage to property, in which case the Employer’s
Representative may give oral instructions, and shall confirm them in writing as soon as
practicable.

16
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

4.6 Works Proposals


4.6.1 The Contractor shall ensure that all Works Proposals comply with the Works Requirements.
4.6.2 If any Works Proposals do not comply with the Contract or the Works Requirements or Legal
Requirements or are physically impossible to comply with, the Contractor shall propose a
change to the Works Proposals as necessary. [There shall be no extension of time or
adjustment to the Contract Sum for this.] If the Works Proposals need to be changed
because of a change to the Works Requirements, the Contractor shall propose a change.
The Contractor shall submit any change to the Works Proposals to the Employer’s
Representative.

4.7 Required Contractor Submissions


Unless the Works Requirements say that a different procedure is to apply, whenever the Contract
requires that a document or proposed course of action be submitted to the Employer’s Representative,
the following shall apply:
4.7.1 The Contractor shall give the document or a statement of the proposed action and all
necessary supporting information to the Employer’s Representative.
4.7.2 The Employer’s Representative may [but is not bound to] make a written objection to a
Contractor’s submission, giving reasons.
4.7.3 The Employer’s Representative may request additional information.
4.7.4 The Employer’s Representative’s period for objection is 10 working days from when the
Employer’s Representative has received from the Contractor enough information to make a
purposeful review of the matter submitted should it wish to make one.
4.7.5 The Contractor shall apply in writing for any reduction of the period that it considers desirable
in the interests of the Works, which the Employer’s Representative may agree if it thinks fit.
4.7.6 The Employer’s Representative may alter or withdraw an objection.
4.7.7 The Contractor shall not implement any submission before the period has ended, or contrary
to any outstanding objection given within the period.
4.7.8 The Contractor shall make a new submission to meet any objection given within the period.
4.7.9 The Contractor shall also make new submissions as necessary to perform its duties under
the Contract [whether or not it has received any objection], and in particular so that its
submitted programme shows actual and current planned progress.
4.7.10 The Employer’s Representative may object on the grounds that to proceed according to the
submission
(1) would not comply with the Contract or
(2) would have an adverse effect on the Employer or the public interest or
(3) would impose an obligation on the Employer that the Contract does not require the
Employer to bear or
(4) would be contrary to a Legal Requirement or
(5) would have an adverse effect on the Contractor’s ability to comply with the Contract
or any other ground stated in the Contract.
4.7.11 Neither the Employer’s Representative’s rights to object, nor objections or their absence,
reduce any of the Employer’s Representative’s other powers, or reduce any of the
Contractor’s responsibilities.

4.8 (sub-clause not used)

17
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

4.9 Programme
4.9.1 Before the Starting Date, the Contractor shall submit to the Employer’s Representative a
detailed programme having regard to the requirements of the Inspection Plan and the
Inspection Notification Framework. If there is a programme in the Works Proposals that
complies with the Contract, the Contractor shall submit that programme, with any required
additional information [such as the actual programmed dates and any Inspection Plan
requirements]. The programme shall be of a quality that will permit effective monitoring of the
Works and shall include details of when the Contractor will require any instructions, Works
Items or other things to be given by the Employer, or anything else the Contract requires the
Employer, the Employer’s Representative or others to give the Contractor.
4.9.2 The Contractor’s programme shall allow reasonable periods of time for the Employer and the
Employer’s Personnel to comply with their obligations under the Contract.
4.9.3 If the Contractor’s programme most recently submitted to the Employer’s Representative
does not correspond with actual or reasonably projected progress or the Contractor’s
obligations, the Contractor shall, if so directed by the Employer’s Representative, submit to
the Employer’s Representative a revised programme that complies with this sub-clause and
the other provisions of the Contract, showing actual progress and progress projected by the
Contractor. If the Contractor asserts that it is not possible to reach Substantial Completion of
the Works or a Section by its Date for Substantial Completion, the revised programme shall
show Substantial Completion by the earliest possible date. [Neither the programme nor its
review will limit the Contractor’s responsibility or liability for the delay.] If the Contractor fails to
submit the revised programme within 15 working days of a request from the Employer’s
Representative, the Employer shall be entitled to withhold from the Contractor 15% of any
payment to be made to the Contractor until the revised programme is submitted.

4.10 Progress Reports


The Contractor shall give the Employer’s Representative monthly progress reports from the Starting
Date until the Contractor has completed all work outstanding on Substantial Completion of the Works.
The first report shall cover the period from the Starting Date up to the end of the month in which it
occurs, and each subsequent report shall cover one month. The Contractor shall give each progress
report within 7 days after the end of the month it relates to. Each progress report shall be in a form
agreed by the Employer’s Representative and shall include detailed description of progress of each
stage of the Works against the Contractor’s current programme and anything else relevant to a
progress report that the Employer’s Representative directs.

4.11 Notice and Time for Employer’s Obligations


4.11.1 The Contractor shall give the Employer’s Representative at least 10 working days advance
notice of the date by which the Contractor requires any instructions that the Employer’s
Representative is to give, or Works Items or other things that the Employer is to give
including any requirements arising from the Inspection Plan and the Inspection Notification
Framework.
4.11.2 The latest date for the Employer’s Representative to give required instructions, or the
Employer to give the Contractor any required Works Item or other thing, shall be the latest of
the following:
(1) the date stated in the Contract, if any
(2) the date shown in the Contractor’s current programme
(3) the date for which the Contractor first notifies the Employer’s Representative under this
sub-clause that it is required
(4) the date the Contractor requires the instruction, Works Item or other thing in
accordance with its actual progress.

18
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

4.12 Documents
4.12.1 The Contractor shall keep on the Site all of the following:
(1) a full up-to-date set of the Contract documents (but the Pricing Document may be
unpriced), instructions of the Employer’s Representative, and Contractor’s Documents
(2) a log of all instructions and Contractor’s Documents showing dates of issue for each
and any subsequent revisions
(3) if requested by the Employer’s Representative, all publications named in the Contract
and the Contractor’s Documents.
(4) wage records [including time sheets and copies of all pay slips] applicable to all
workers [as defined in sub-clause 5.3.1].
The Employer’s Representative, and any person authorised by the Employer’s
Representative, shall have a right of access to these at all reasonable times.
4.12.2 The Contractor shall retain the Contractor’s Documents in relation to the Works for a period of
six [6] years from the date of completion of the Works or if applicable from the date of
termination of the Contract for any reason.

4.13 Contractor’s Management


4.13.1 The Contractor’s business includes expertise and experience in construction management.
4.13.2 The Works Proposals include details of the Contractor’s initial management arrangements for
performing its Contract responsibilities.
4.13.3 The Contractor shall implement the arrangements, and shall add to and otherwise change
them, as desirable for its efficient performance.
4.13.4 The arrangements shall include systems, methods, planning and other preparations for
providing personnel and resources, programming, recording, consultation, co-ordination, and
co-operation, and for flexibility, as referred to in the Contract.
4.13.5 The Contractor shall keep the Employer’s Representative fully informed about its current
arrangements, in advance, and about their implementation.
4.13.6 The Contractor shall give the Employer’s Representative all information, documents and
records in the possession of, or available to, the Contractor or the Contractor’s Personnel,
that the Employer’s Representative requires to perform its functions and powers under the
Contract.

4.14 Communications
4.14.1 The Parties intend all communications between them to be interpreted purposefully, having
regard to the Contract’s purposes.
4.14.2 Whenever any communication [including a notice, decision, objection, approval, certificate,
determination, instruction or request] is to be given under the Contract it shall, unless the
Contract provides otherwise, be in English, in writing and delivered as follows:
(1) for notices under clause 12 or clause 13, delivered by hand or sent by pre-paid
registered post to the address for those notices in the Schedule, part 1A, as updated
by the relevant Party
(2) for other communications, delivered by hand or sent by pre-paid post, fax or email
according to the particulars for other communications in the Schedule, part 1A, as
updated by the relevant Party.
4.14.3 Communications by pre-paid registered post are presumed to have been received at
10:00 a.m. two working days after posting. Fax and email communications are presumed to
have been received when receipt is electronically recorded.

19
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

4.15 Meetings
4.15.1 The Contractor’s representative and the Employer’s Representative shall attend regular
meetings scheduled by the Employer’s Representative and any special meeting called by
either of them to discuss a particular issue identified when calling the meeting. The
Employer’s Representative may invite other Employer’s Personnel and the Contractor may
invite Contractor’s Personnel to attend meetings. The Contractor shall arrange for the
attendance at a meeting of any Contractor’s Personnel requested by the Employer’s
Representative. The time and place of meetings shall be set by the Employer’s
Representative, after consulting the Contractor, acting reasonably.
4.15.2 Within 5 working days after each meeting the Employer’s Representative shall issue minutes
of the meeting to the Employer and the Contractor. The Contractor shall notify the Employer’s
Representative of any objection to the minutes within 5 working days of receiving them,
otherwise, unless clearly wrong, they shall be considered correct.

4.16 Confidentiality and Secrecy


4.16.1 The Contractor shall [and shall ensure that the Contractor’s Personnel shall] keep
confidential:
(1) official information as defined in the Official Secrets Act 1963 and
(2) other information stated in the Works Requirements to be confidential or secret, or that
the Employer or the Employer’s Representative notifies the Contractor is confidential
or secret.
4.16.2 The Employer shall keep confidential the Contractor’s rates and prices in the Pricing
Document or provided in accordance with the Contract, and any records given by the
Contractor under the Contract that the Contractor notifies the Employer’s Representative are
confidential.
4.16.3 This sub-clause 4.16 shall not prevent disclosure of information, to the extent permitted by
Law
(1) to the Contractor’s Personnel, the Employer’s Personnel or other professional advisors
to the Contractor or Employer, who have first entered an undertaking in the terms of
this sub-clause 4.16, to the extent necessary for the execution of the Works or to
enforce the Contract or
(2) when required by Law or order of a court or, in the case of disclosure by the Employer,
for governmental, parliamentary, statutory, administrative, fiscal or judicial purposes, or
the publication of an award notice or
(3) that has, except as a result of breach of confidentiality, become available or generally
known to the public at the time of the disclosure.
4.16.4 The Contractor’s obligations under this sub-clause 4.16 shall be perpetual. The Employer’s
obligations under this sub-clause shall expire when the commercial sensitivity of the relevant
information has ceased, in any event 5 years after the information was given.

4.17 Contractor’s Things Not to Be Removed


The Contractor shall submit details to the Employer’s Representative before removing any
Contractor’s Things from the Site before the Employer’s Representative issues a certificate of
Substantial Completion of the Works or relevant Section.

4.18 Contractor’s Documents


All Contractor’s Documents shall be in English, except when the Works Requirements or the Law
specify another language

20
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

5 CONTRACTOR’S PERSONNEL

5.1 Contractor’s Personnel to Carry Out Contractor’s Obligations


The Contractor is liable for the acts and omissions of Contractor’s Personnel [including Specialists and
any design they do] as if they were the Contractor’s acts and omissions.

5.2 Qualifications and Competence


The Contractor shall ensure that the Contractor’s Personnel are suitably qualified and experienced and
are competent to carry out their respective tasks.

5.3 Pay and Conditions of Employment


5.3.1 The Contractor shall prominently exhibit copies of this sub-clause 5.3 for the information of
persons at the Site. In this clause 5 worker means an individual employed by, or otherwise
working for, the Contractor or the Contractor’s Personnel on or adjacent to the Site.
5.3.2 The Contractor shall ensure that the rates of pay and the conditions of employment, including
pension contributions, comply with all applicable law and that those rates and conditions are
at least as favourable as those for the relevant category of worker in any sectoral
employment orders, employment regulation orders or registered employment agreements
implemented under the Industrial Relations Acts 1946 to 2015(including any such
agreements registered prior to the Industrial Relations (Amendment) Act 2015, which have
not otherwise been superseded). This applies to workers who are posted workers (within the
meaning of Directive 96/71/EC of the European Parliament and the Council of the 16
December 1996 as amended by Directive 2014/67/EU concerning the posting of workers in
the framework provision of services), except that the Contractor’s obligation to make pension
contributions in accordance with any sectoral employment orders, registered employment
agreements or employment regulation orders implemented under the Industrial Relations
Acts 1946 to 2015 does not apply to posted workers who already contribute, or whose
contributions are paid, to a supplementary pension scheme established in another member
state of the European Union. The obligations in this sub-clause 5.3 apply regardless of what
rates the Contractor has tendered for adjustments to the Contract Sum.
5.3.3 The Contractor shall in respect of
(i) workers employed by, or otherwise working for, the Contractor and
(ii) all other workers, ensure that their employers, or the persons for whom they are
working,
do all of the following:
(1) pay all wages and other money due to each worker
(2) ensure that workers’ wages are paid in accordance with the Payment of Wages Act
1991 and are never more than 1 month in arrears or unpaid
(3) pay all pension contributions and other amounts due to be paid on behalf of each
worker
(4) make all deductions from payments to workers required by Law, and pay them on as
required by Law
(5) keep proper records [including time sheets, wage books and copies of pay slips]
showing the wages and other sums paid to and the time worked by each worker,
deductions from each worker’s pay and their disposition, and pension and other
contributions made in respect of each worker, and produce these records for
inspection and copying by any persons authorised by the Employer, whenever
required by the Employer
(6) produce any other records relating to the rates of pay, pension and other contributions,
deductions from pay and their disposition, conditions of employment of workers, rest
periods, and annual leave for inspection and copying by any persons authorised by the
Employer, whenever required by the Employer
(7) respect the right under law of workers to be members of trade unions
(8) observe, in relation to the employment of workers, on the Site, the Safety, Health and
Welfare at Work Act, 2005 to 2014 and all employment law including the Employment

21
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

Equality Act 1998 to 2005, the Industrial Relations Acts 1946 to 2015, the National
Minimum Wage Act 2000 and 2015, and regulations, codes of practice, legally binding
determinations of the Labour Court and sectoral employment orders, employment
regulation orders or registered employment agreements implemented under those
Laws.
5.3.3A (1) Sub-clause 5.3.3A(2) shall only be included in the Contract if the Schedule, part 1J
says so, and if not, neither sub-clause 5.3.3A(2) nor its omission shall be taken into
account.
(2) The Employer shall be entitled to make random checks requiring production of records
under sub-clauses 5.3.3(5) and (6).
5.3.4 If the Employer so requests, the Contractor shall, within 5 working days after the receipt of
the request, give to the Employer a statement showing the amount of wages and other
payments due at the date of the request to and in respect of each worker, or, in respect of
workers not employed by or otherwise working for the Contractor, ensure that their employer
or the person for whom they are working does the same.
5.3.5 The Employer may seek information under sub-clause 5.3.3 only for the purpose of ensuring
the obligations referred to in this sub-clause 5.3 to workers have been properly discharged.
All documents and records received under sub-clause 5.3.3 shall be returned to the person
providing them or destroyed if the Employer is satisfied that the relevant employer has
complied with legal obligations to workers.
5.3.6 If the Contractor has not complied with this sub-clause 5.3, the Employer shall [without
limiting its other rights or remedies] be entitled to estimate the amount that should have been
paid to workers and contributions that should have been made on their behalf, and the
Employer may deduct the estimated amount from any payment due to the Contractor, until
the Employer is satisfied that all proper amounts have been paid.
5.3.7 The Contractor shall give the Employer’s Representative with each interim statement under
sub-clause 11.1 a certificate in the form in the Works Requirements, that, in respect of the
work to which the interim certificate relates, the Contractor has complied in full with this sub-
clause 5.3.
5.3.8 If the Contractor does not comply with this sub-clause 5.3, it shall pay to the Employer any
costs the Employer incurs in investigating and dealing with the non-compliance.
5.3.9 The Contractor shall ensure that in the event of an official of a trade union representing
workers who are affected by a sectoral employment order, employment regulation order or
which is a party to a which is party to a registered employment agreement affecting workers
having concerns in relation to the Contractors or Contractor’s Personnel’s compliance with
the order or agreement, that official will have access to a designated member of the
Contractor’s management who shall engage constructively to resolve matters at this point.

5.4 Subcontractors and Specialists


5.4.1 The Contractor shall not subcontract all of the Works to one or more Subcontractors. If the
Contractor intends to subcontract part of the Works, other than when the Subcontractor and
its scope are set out in the Contract, or the Contract provides other procedures, the
Contractor shall first submit details to the Employer’s Representative of the proposed
Subcontractor and its proposed scope of work. The Contractor shall also submit details to the
Employer’s Representative of any proposed Specialist, other than one named in the Contract
or when the Contract provides other procedures.
5.4.2 If Specialists or other Contractor’s Personnel are named in the Contract, the Contractor shall
ensure that they are engaged for and perform the work for which they are named.
5.4.3 If the Schedule, Part 3B names a Specialist, the following apply;
(i) where the Specialist’s contract with the Employer is to be novated to the Contractor,
(novated Specialist), and the Works Requirements includes a copy of that contract,
the Contractor shall accept the novation, and the Parties shall, at the same time as
entering the Agreement, enter the novation agreement. In the case of novated
Specialists who were required to obtain a performance bond by the Employer, once
the novation agreement is executed by the parties, the Employer shall write to the
surety who has provided the performance bond to the novated Specialist informing
them that they are assigning the benefit of that bond to the Contractor.
22
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

(ii) where the Contractor is to enter a sub-contract with a named Specialist, (Reserved
Specialist), the Reserved Specialist sub-contract shall be an unamended form of
sub-contract as identified in Schedule Part 1F(iii) and the Contractor shall enter into
the sub-contract with the Reserved Specialist before the Starting Date.

5.4.4 The Employer’s Representative may not instruct the Contractor to enter a contract with a
particular Specialist selected by the Employer’s Representative unless the Specialist is
named in the Contract (named Specialists).
5.4.5 The Contractor shall fully comply with its obligations under any contract with a Specialist and
shall not terminate, allow to be terminated or accept a repudiation of such a contract without
first submitting details to the Employer’s Representative, except when an insolvency event,
as set out in sub-clause 12.1, occurs in respect of the Specialist, or the Specialist has
committed a serious breach of Law concerning safety, or the Specialist has failed to put or
keep in effect insurance as required by the Specialist’s contract. On any termination, the
Contractor shall replace the Specialist, having submitted details of the replacement to the
Employer’s Representative. In the case of a named Specialist, referred to in sub-clause 5.4.3,
the replacement Specialist proposed by the Contractor must meet minimum standards set out
in the Works Requirements.
5.4.6 In addition to the reasons in sub-clause 4.7, the Employer’s Representative may object to the
proposed replacement of Contractor’s Personnel because the proposed replacement does
not have at least the level of experience, qualifications, competence, technical capacity, and
financial standing of the person being replaced.

5.5 Collateral Warranties


If the Schedule, part 1F, states that a collateral warranty is required from any Specialist, before the
date stated in the Schedule, the Contractor shall give the Employer a collateral warranty in the form
included in the Works Requirements, or if there is none, a form approved by the Employer, executed
by the Specialist and the Contractor. The minimum indemnity limit and maximum excess of
professional indemnity insurance required of the Specialist shall be as stated in the Schedule, part 1F.

5.6 Removal of Workers


The Contractor shall remove from the Site any Contractor’s Personnel that the Employer’s
Representative directs, because of the Contractor’s Personnel’s negligence or incompetence, or on
the basis that the Contractor’s Personnel’s presence on the Site is not conducive to safety, health or
good order.

5.7 Weekly Labour Records


Each Monday (or the next working day if Monday is not a working day) the Contractor shall give the
Employer’s Representative a list of the name of each worker who worked the week ending the
previous Sunday and details of the category of and hours worked by each worker on the list.

5.8 Ancillary Certificates


If the Schedule, part 1F(ii) states that an Ancillary Certificate is required from the Contractor or the
Contractor’s Personnel, the Contractor shall obtain and provide to the Employer’s Representative those
Ancillary Certificates. [This does not limit the Contractor’s obligation to provide all necessary Consents
in accordance with sub-clause 2.3.1.]

23
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

6 PROPERTY

6.1 Ownership of Works Items


It is agreed, and the Contractor shall ensure, that each Works Item shall become the property of the
Employer on the earliest of the following:
(1) when it is delivered to the Site, if owned by the Contractor
(2) when it is incorporated in the Works
(3) when any payment for the Works Item is made by the Employer to the Contractor.

6.2 Infringement of Property Rights


6.2.1 The Contractor shall indemnify the Employer against any liability resulting from any of the
following infringing the property [including intellectual property] rights of any person:
(1) the Contractor’s performance or non-performance of this Contract, unless the liability is
covered by the Employer’s indemnity in this sub-clause
(2) use of Works Items, Contractor’s Things, or Contractor’s Documents by
(a) the Contractor or Contractor’s Personnel or
(b) the Employer or any other person to complete the Works following termination of
the Contractor’s obligation to complete the Works
(3) use by the Employer of the Works, Works Items, or the Contractor’s Documents for the
purpose for which they were given.
6.2.2 The Employer shall indemnify the Contractor against any liability resulting from any of the
following infringing the property [including intellectual property] rights of any person:
(1) the unavoidable use by the Contractor, in accordance with the Contract, of the Works
Requirements or Works Items or other things provided by the Employer
(2) the use or occupation by the Works of the Area Provided by the Employer (defined in
sub-clause 7.1.1), when that is the unavoidable result of performing the Contract.

6.3 Works Requirements


The Works Requirements shall remain the property of the Employer and the Contractor shall not use
them [and shall ensure that the Contractor’s Personnel do not use them] for any purpose other than to
perform the Contract or to prosecute or defend a dispute under the Contract.

6.4 Rights in Contractor’s Documents


6.4.1 The Employer may use, copy, modify, adapt and translate for any purpose in connection with
the Works [including to construct, maintain, extend, use, operate, let, sell, promote, advertise,
reinstate and repair the Works] the Contractor’s Documents that are given, or, according to
the Contract, must be given, to the Employer and the Works Proposals.
6.4.2 Where the Schedule, part 1O, so states, all copyright and other rights in the Contractor’s
Documents that are prepared for the Works and are given, or according to the Contract, must
be given, to the Employer and the Works Proposals transfers to the Employer when the
Employer receives them.
6.4.3 The Contractor shall ensure that the Employer obtains the rights and interests described in
this sub-clause 6.4.
6.4.4 The Contractor has no liability for the use of the Contractor’s Documents for any purpose
other than that for which they were given to the Employer.

24
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

7 THE SITE

7.1 Lands Made Available for the Works


7.1.1 The Employer shall allow the Contractor to occupy and use each part of the area identified in
the Works Requirements to be provided by the Employer (the Area Provided by the
Employer) from a date on or before the latest of the following:
(1) the Starting Date
(2) the day after the Contractor has done what sub-clause 9.1 requires the Contractor to
do before the Starting Date
(3) the date stated in the Works Requirements, if any
(4) the day after the Contractor has submitted its programme according to sub-clause 4.9
(5) the date stated for work to start on that part in the Contractor’s current programme
(6) the date the Contractor actually requires the part in accordance with its actual
progress.
7.1.2 The Contractor’s right to occupy and use the Site shall be subject to any limitations in the
Works Requirements.
7.1.3 The Contractor shall not be entitled to exclusive possession of the Area Provided by the
Employer or any part of it and shall facilitate any occupation and use of it by the Employer
and others stated in the Works Requirements. The Contractor’s occupation and use of the
Area Provided by the Employer shall be solely for the purpose of performing the Contract.
7.1.4 The Contractor’s right to occupy and use the Area Provided by the Employer shall end when
the Employer’s Representative certifies the Works or the relevant Section as Substantially
Complete. After then the Employer shall allow the Contractor access to comply with sub-
clause 8.6.1.
7.1.5 The Contractor’s right to occupy and use the Area Provided by the Employer shall end if the
Contractor’s obligation to complete the Works is terminated.

7.2 Trespassers
After the Employer has allowed the Contractor to occupy and use any part of the Area Provided by the
Employer, the Contractor shall be responsible for activities of trespassers, protesters and others, that
are not Employer’s Personnel, on the Site, and the Employer shall have no responsibility to the
Contractor for their activities or presence.

7.3 Contractor Responsible for All Site Operations


The Contractor shall be responsible for all operations on the Site connected with the execution of the
Works.

7.4 Services for Employer’s Facilities


The Contractor shall operate and maintain parts of the Site and facilities of the Employer if the Works
Requirements so require.

7.5 Security and Safety of the Site and Nuisance


7.5.1 From and including the Starting Date until the Employer’s Representative certifies the Works
or the relevant Section as Substantially Complete, the Contractor shall do all of the following
[without limiting other obligations]:
(1) be responsible for securing the Site and for keeping off the Site persons other than any
of the following:
(i) the Contractor’s Personnel and the Employer’s Personnel
(ii) any other person notified to the Contractor by the Employer or the Employer’s
Representative as authorised to enter the Site

25
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

(iii) persons exercising public access to any roads, footpaths and areas on the Site
(iv) persons having a right to enter the Site under Legal Requirements
(2) keep the Site in good order and free from unnecessary obstructions
(3) take all necessary steps to secure the safety of all persons entitled to be on the Site
and to protect users, owners and occupiers of land adjacent to the Site from hazards
and interference arising from the Works [including providing any required fences,
lighting, guarding, watching, roads and footpaths]
(4) take all necessary steps to ensure that the Contractor, the Contractor’s Personnel and
the execution of the Works do not do any of the following:
(i) unnecessarily cause a nuisance or inconvenience to the public or any user,
owner or occupier of any land, road or footpath on or adjacent to the Site
(ii) unnecessarily interfere with the use of any such land, road or footpath.
7.5.2 The Employer shall ensure that Employer’s Personnel on the Site comply with the
Contractor’s reasonable safety rules that have been notified to them by the Contractor.
7.5.3 This sub-clause 7.5 is subject to any exceptions in the Works Requirements

7.6 Other Contractors


Where so stated in the Works Requirements, the Employer may arrange for work to be executed on
the Site by Employer’s Personnel. The Contractor shall co-operate with such Employer’s Personnel
and shall as far as practicable co-ordinate their activities with the execution of the Works.

7.7 Setting Out the Works


The Contractor shall set out the Works by reference to the points, lines and levels of reference in the
Works Requirements. The Contractor shall be responsible for the correct positioning of all parts of the
Works and shall rectify any errors in the positions, levels, dimensions or alignment of the Works.
Before setting out the Works the Contractor shall make all reasonable efforts to verify the accuracy of
the setting out information in the Works Requirements.

7.8 Archaeological Objects and Human Remains


If any fossils, coins, antiquities, monuments or other items of value or of archaeological or geological
interest or human remains are discovered on or adjacent to the Site unless the Works Requirements
say otherwise, the Contractor shall not disturb them, but shall take all necessary steps to preserve
them, and shall promptly notify the Employer’s Representative [and comply with any instructions]. As
between the Parties, these items shall be the Employer’s property.

7.9 Access and Facilities


7.9.1 The Contractor [and not the Employer] shall be responsible for securing access to and
through the Site and possession and use of any parts of the Site that are not the Area
Provided by the Employer.
7.9.2 The Contractor [and not the Employer] shall be responsible for the suitability and availability
of access routes to and within the Site, and any required maintenance or upgrading of them,
and any charges for use of them.
7.9.3 The Contractor shall also be responsible for obtaining any additional facilities, and for
providing all power, water and other services it requires to perform the Contract.

7.10 (sub-clause not used)

7.11 (sub-clause not used)

26
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

7.12 Charges
The Contractor shall pay any charges provided for in the Works Requirements for occupation of the Site
or any part of it or other place, or in respect of operation or maintenance of Employer’s facilities, or in
respect of services, or otherwise. [The Employer may deduct the amount of charges from payments to
the Contractor. Payment of charges does not excuse the Contractor from any of its obligations].

27
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

8 QUALITY, TESTING AND DEFECTS

8.1 Standards of Workmanship and Works Items


The Contractor shall ensure all of the following:
(1) that the Works are executed and completed
(i) in accordance with all the requirements in, and reasonably inferred from, the Contract
[including, where so required by the Contract, in accordance with Contractor’s
Documents that have been submitted to the Employer’s Representative] and
(ii) in a proper and workmanlike manner and using good practice
(2) that all Works Items [whether or not the Contractor is required to select them]
(i) comply with the Contract and the Legal Requirements and
(ii) are of good quality and, unless the Contract provides otherwise, new
(3) that all materials and goods that are Works Items [whether or not the Contractor is required to
select them] are fit for the purpose for which they are normally used
(4) that all Works Items selected or designed by the Contractor [including by any Specialist] are
fit for their intended purpose in the Works.

8.2 Quality Assurance


The Contractor shall establish and implement quality assurance procedures as required by the Works
Requirements, including procedures for establishing quality assurance systems for itself and
Subcontractors. The quality assurance procedures shall be reflected in appropriate quality plans
submitted to the Employer’s Representative. The Contractor shall give the Employer’s Representative
copies of all reports prepared in accordance with the Contractor’s quality assurance procedures. The
Employer’s Representative may monitor, spot check and audit the Contractor’s quality assurance
procedures.

8.3 Inspection
8.3.1 The Contractor shall ensure that the Employer’s Representative, Assigned Certifier, and
anyone authorised by the Employer’s Representative, is able at all reasonable times to have
access to all places where the Works are being executed [whether or not at the Site] and any
place where any Works Items are produced, stored, extracted or prepared, or any other
obligation of the Contractor under the Contract is being performed, and are able there to
inspect, test, observe and examine all such items and activities.
8.3.2 The Contractor shall promptly give the Employer’s Representative and the Assigned Certifier
all particulars the Employer’s Representative and the Assigned Certifier requests about the
mode, place and time of manufacture, the source of supply and the performance capabilities
of Works Items and any related information, including any test certificates that the Contract
provides for.
8.3.3 The Contractor shall notify the Employer’s Representative and the Assigned Certifier before
any Works Item is covered or any Works Item that is to be inspected is packed or made
impossible or difficult to inspect, in either case giving the Employer’s Representative, and any
person authorised by the Employer’s Representative, a reasonable opportunity to inspect the
Works Item.

8.4 Tests
8.4.1 The Contractor shall supply all Contractor’s Things, documents, information, suitably qualified
and experienced personnel, power, consumables and instruments required to carry out tests
that the Contract [including the Inspection Plan] requires the Contractor to do [both before
and after Substantial Completion]. The Contractor shall agree with the Employer’s
Representative and the Assigned Certifier the time and place for these tests. The Employer’s
Representative, and others authorised by the Employer, may attend and observe the tests,
and the Contractor shall facilitate their attendance and observation. Regardless of whether
any Employer’s Personnel attends, the Contractor shall promptly give the Employer’s
Representative a certified report of the result of every test.

28
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

8.4.2 If a test is failed, the Contractor may elect to repeat the test, or the Employer’s
Representative may require that the test be repeated. The Contractor shall, on request, pay
the Employer any costs the Employer incurs as a result of any re-testing.
8.4.3 If the Contractor rectifies a Defect, it shall repeat any relevant test the Contract specifies for
the relevant Works Item, if the Employer’s Representative so directs.

8.5 Defects
8.5.1 The Employer’s Representative may direct the Contractor to search for a Defect or suspected
Defect or its cause. This may include uncovering, dismantling, re-covering and re-erecting
work, providing facilities for tests, testing and inspecting. If, through searching or otherwise,
the Contractor discovers a Defect, the Contractor shall notify the Employer’s Representative
as soon as practicable.
8.5.2 If, through notification or otherwise, the Employer’s Representative becomes aware of a
Defect, the Employer’s Representative may direct the Contractor to do any of the following [or
any combination of them]:
(1) to remove the Works Item with the Defect from the Site
(2) to demolish the Works Item with the Defect, if incorporated in the Works
(3) to reconstruct, replace or correct the Works Item with the Defect
(4) not to deliver the Works Item with the Defect to the Site.
8.5.3 The Contractor shall comply with any direction under this sub-clause 8.5 within the
reasonable times, if any, the Employer’s Representative directs. If the Contractor fails to
begin the work required to comply with the direction within the reasonable time directed, if
any, or to complete it as soon as practicable, the Employer may have the work done by
others and the Contractor shall, on request, pay the Employer its cost of doing so.
8.5.4 Alternatively, the Contractor and the Employer’s Representative may, with the Employer’s
consent, agree that the Employer will accept the Defect, either in whole or subject to any
change to the Works Requirements that the Employer’s Representative directs. In this case,
the Contract Sum shall be reduced by the amount that, in the opinion of the Employer’s
Representative, is the resulting decrease in the value of the Works to the Employer. If the
Employer’s Representative notifies the Contractor that the Employer will not accept a Defect,
this shall be conclusive.
8.5.5 The Employer’s Representative may give a direction or rejection under this sub-clause 8.5 at
any time before the Defects Certificate is issued. [The Contractor shall not be entitled to any
adjustment to the Contract Sum or extension of time because of a direction given to deal with,
or as a result of, a Defect or any other breach of the Contract by the Contractor.]

8.6 Defects Period


8.6.1 As soon as practicable after Substantial Completion of the Works or any Section, the
Contractor shall complete any outstanding work and rectify any Defects that the Employer’s
Representative directs before the end of the Defects Period. In doing so, and in doing any
tests after Substantial Completion, the Contractor shall cause as little disruption as possible
to occupants and users of the Works.
8.6.2 If work remains outstanding or Defects remain uncorrected at the end of the Defects Period,
or if the Contractor has completed outstanding work or rectified Defects after Substantial
Completion of the Works or relevant Section and before the end of the Defects Period, the
Employer’s Representative may [without limiting the Employer’s other rights] make an
appropriate extension to the Defects Period. With the Employer’s agreement the Employer’s
Representative may, at the time that the Defects Period would have ended without this
extension, issue an interim payment certificate conclusively making an appropriate reduction
in retention, and the Contractor shall be entitled to invoice the Employer for that amount.

8.7 Defects Certificate


The Employer’s Representative shall issue the Defects Certificate to the Contractor and the Employer
within 20 working days after the end of the Defects Period. [Nothing in this clause 8, nor any exercise
or non-exercise by the Employer or the Employer’s Representative of their rights under this clause 8,
nor the Defects Certificate, relieves the Contractor of any obligation, except to the extent that a Defect
is accepted by agreement under sub-clause 8.5.4.]

29
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

9 TIME AND COMPLETION

9.1 Starting Date


9.1.1 The Contractor shall set the Starting Date, giving the Employer’s Representative at least 15
working days notice, or any shorter period the Employer’s Representative may agree, or any
different period stated in the Works Requirements. The Starting Date shall, unless otherwise
stated in the Works Requirements, be no more than 20 working days after the Contract Date.
9.1.2 Before the Starting Date [unless already given by the Contractor before the Contract Date, for
example in response to a letter of intent] the Contractor shall give the Employer all of the
following, all executed, as relevant, by the relevant persons:
(1) the Agreement
(2) a performance bond, if required by the Contract
(3) if the Works Requirements state that the Contractor or the Contractor’s nominee is to be
appointed as project supervisor for the construction stage, the required appointment,
and the developed safety and health plan required by the Construction Regulations
(4) evidence that the insurances required by the Contract are in effect
(5) any collateral warranties required by the Contract
(6) Copies of the signed agreements and unamended form of sub-contract as identified in
schedule Part 1F(iii)
However, collateral warranties may be given on a later date that the Employer’s
Representative has agreed to.
9.1.3 On the Starting Date, the Contractor shall start to execute the Works on the Site. The
Contractor shall, unless the Employer’s Representative directs otherwise, proceed regularly
and diligently in order to achieve Substantial Completion of the Works and each Section by its
Date for Substantial Completion.

9.2 Suspension
9.2.1 The Employer’s Representative may at any time direct the Contractor to suspend all or part of
the work under the Contract. The Contractor shall comply with the direction and, during
suspension, shall protect, store and secure the affected Works Items against deterioration,
loss and damage and maintain the Insurances.
9.2.2 After a suspension under clause 9.2.1, the Contractor shall resume work when so directed by
the Employer’s Representative. When a direction to resume is given, the Contractor and the
Employer’s Representative shall jointly examine the Works and Works Items affected by the
suspension. If the Contractor is entitled to an adjustment of the Contract Sum or an extension
of time because of the suspension, the Contractor’s cost of rectifying any deterioration in or
loss of the Works or Work Items that the Contractor could not have avoided shall be included
in the determination of the adjustment, and any resulting delay shall be taken into account in
determining the extension.
9.2.3 If a suspension, that did not result from a breach of the Contractor’s obligations, has
continued for more than 3 months, the Contractor may request the Employer’s
Representative’s permission to proceed. If the Employer’s Representative does not give
permission within 28 days after being requested to do so, the Contractor may, by giving
notice to the Employer’s Representative
(1) if the suspension affects part of the Works, treat the suspension as a Change Order to
omit that part of the Works or
(2) if the suspension affects the whole of the Works, give notice to terminate the
Contractor’s obligation to complete the Works under the Contract.

30
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

9.3 Delay and Extension of Time


9.3.1 If the Contractor becomes aware that work under the Contract is being or is likely to be
delayed for any reason, it shall as soon as practicable notify the Employer’s Representative
of the delay and its cause. As soon as practicable after that, and in any event within 40
working days after the Contractor became aware of the delay, the Contractor shall give the
Employer’s Representative full details of the delay and its effect on the progress of the
Works. But if the Contractor has given notice and details of the delay under sub-clause 10.3.1
it does not have to give notice or details again under this sub-clause 9.3.1 for the same delay.
In any event, the Contractor shall promptly give any further information about the delay the
Employer’s Representative directs.
9.3.2 If Substantial Completion of the Works or any Section has been, is being or will be delayed
beyond the Date for Substantial Completion by a Delay Event and if all of the following apply:
(1) the Delay Event is not a result of the Contractor’s or Contractor’s Personnel’s act or
omission or the Contractor’s breach of the Contract
(2) the Contractor makes all reasonable efforts to avoid and minimise the delay
(3) the Contract does not provide otherwise
then, subject to this sub-clause 9.3, sub-clause 9.4 and clause 10, there shall be an
extension to the Date for Substantial Completion of the Works and any affected Section equal
to the amount of the delay beyond the Date for Substantial Completion caused by the Delay
Event taking into account only Site Working Days. The Contractor and the Employer’s
Representative shall follow the procedure in clause 10.
9.3.3 The Employer’s Representative may, at any time, revise a determination of an extension to
the Date for Substantial Completion of the Works or any Section, but shall not bring those
dates forward except by agreement with the Contractor under sub-clause 9.5 when work has
been omitted.

9.4 Programme Contingency


9.4.1 The Contractor has included in the initial Contract Sum and shall include in its programme a
contingency for delays to the Date for Substantial Completion of the Works caused by
Compensation Events.
9.4.2 If the total number of Site Working Days’ delay to Substantial Completion of the Works
caused by Compensation Events (for which the Contractor would otherwise be entitled to an
extension) is less than the programme contingency threshold in the Schedule, part 1K, there
shall be no extensions to the initial Date for Substantial Completion of the Works for delay
caused by Compensation Events.
9.4.3 If the total number of Site Working Days’ delay to Substantial Completion of the Works
caused by Compensation Events (for which the Contractor would otherwise be entitled to an
extension) exceeds the programme contingency threshold in the Schedule, part 1K, the
number of Site Working Days stated as that threshold shall be deducted from the total
number of Site Working Days’ extension to the initial Date for Substantial Completion of the
Works for delay caused by Compensation Events.
9.4.4 [This sub-clause 9.4 does not apply to extensions to the Date for Substantial Completion of a
Section, nor to extensions of time resulting from Delay Events that are not Compensation
Events.]
9.4.5 Use of the programme contingency provided for in this sub-clause shall be claimed and
determined in accordance with this clause 9 and clause 10. Programme contingency may be
drawn-down when Substantial Completion has been, is being, or will be delayed beyond the
Date for Substantial Completion minus the unused part of the threshold. In making a
determination under sub-clauses 9.3 and 10.5 in respect of a delay to Substantial Completion
of the Works, the Employer’s Representative shall notify the Contractor and the Employer of
how much of the programme contingency threshold has been used-up by delays to
Substantial Completion of the Works caused by Compensation Events.

31
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

9.5 Omissions and Reduction of Time


If a Change Order omits any of the Works, and the omission will result, or has resulted, in a reduction
of the time required to complete the Works or any Section, the Date for Substantial Completion shall
be reduced by any amount agreed between the Employer’s Representative and the Contractor. [If
there is no agreement, there shall be no reduction.]

9.6 Substantial Completion


9.6.1 The Contractor shall achieve Substantial Completion of the Works and each Section by its
Date for Substantial Completion.
9.6.2 Within 20 working days after receiving the Contractor’s request to certify Substantial
Completion of the Works or a Section, the Employer’s Representative shall give to the
Contractor and the Employer
(1) a certificate stating the date that Substantial Completion occurred or
(2) the reasons for not issuing the certificate.
But if the Schedule, part 1H, so states, the Employer’s Representative shall not be required to
certify Substantial Completion of the Works or a Section before its Date for Substantial
Completion. The certificate may include a list of Defects and any outstanding work [but
nothing in the certificate, including the failure to list any Defect, relieves the Contractor of any
obligations].

9.7 (sub-clause not used)

9.8 Liquidated Damages


9.8.1 If the Works do not reach Substantial Completion by the Date for Substantial Completion of
the Works, the Contractor shall pay the Employer [and the Employer may deduct from
payments to the Contractor] liquidated damages calculated at the rate stated in the Schedule,
part 1G, for the period from the Date for Substantial Completion of the Works to the date of
substantial completion of the Works.
9.8.2 If a Section does not reach Substantial Completion by its Date for Substantial Completion, the
Contractor shall pay to the Employer liquidated damages calculated at the rate stated in the
Schedule for the period from the Date for Substantial Completion of the Section to the date of
substantial completion of the Section (or, if earlier and if the Schedule states a rate of
liquidated damages for the Works, to the Date for Substantial Completion of the Works).
9.8.3 In this sub-clause 9.8 date of substantial completion means the date certified by the
Employer’s Representative that the Works or Section reached Substantial Completion.

32
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

10 CLAIMS AND ADJUSTMENTS

10.1 Compensation Event


10.1.1 Subject to and in accordance with this sub-clause 10.1, if a Compensation Event occurs the
Contract Sum shall be adjusted [upward or downward] by the amount provided in sub-clause
10.6. However, if the adjustment is an increase it shall only take effect to the extent that all of
the following apply to the Compensation Event:
(1) The Compensation Event is not a result of the Contractor’s or Contractor’s Personnel’s
act or omission or the Contractor’s breach of the Contract
(2) The Contractor makes all reasonable efforts to avoid and minimise the adverse effects
of the Compensation Event
(3) The Contractor has complied with this clause 10 in full [including giving notices and
details within the time required]
(4) The Contract does not provide otherwise.
10.1.2 The Contractor’s sole remedies for a Compensation Event shall be those stated in the
Contract.

10.2 Contractor to Pay Employer’s Cost of Checking Quantities


The Contractor shall pay the Employer’s cost of having a check done if the Contractor calls for an
adjustment to the Contract Sum because of a difference between the Contract value of the Works
according to the quantities and descriptions in a Bill of Quantities (if any) in the Pricing Document and
the Contract value of the Works according to the Works Requirements (when this is a Compensation
Event), and it is found that no increase is to be made to the Contract Sum.

10.3 Contractor Claims


10.3.1 If the Contractor considers that under the Contract there should be an extension of time or an
adjustment to the Contract Sum, or that it has any other entitlement under or in connection
with the Contract, the Contractor shall, as soon as practicable and in any event within 20
working days after it became aware, or should have become aware, of something that could
result in such an entitlement, give notice of this to the Employer’s Representative. The notice
must be given according to sub-clause 4.14 and prominently state that it is being given under
sub-clause 10.3 of the Contract. Within a further 20 working days after giving the notice, the
Contractor shall give the Employer’s Representative details of all of the following:
(1) all relevant facts about the claim
(2) a detailed calculation and, so far as practicable, a proposal, based on that calculation,
of any adjustment to be made to the Contract Sum and of the amount of any other
entitlement claimed by the Contractor
(3) if the Contractor considers that the programme contingency referred to in sub-clause
9.4 should be used or that there should be an extension of time, the information
required under sub-clause 9.3, and, so far as practicable, a proposal, based on that
information for any use of the programme contingency or any extension to the Date for
Substantial Completion of the Works and any affected Section.
The Contractor shall give any further information about the event or circumstance requested
by the Employer’s Representative.
10.3.2 If the Contractor does not give notice and details in accordance with and within the time
provided in this sub-clause 10.3, except where the Contractor has been required to and has
given a proposal complying in full with sub-clause 10.4 [notwithstanding anything else in the
Contract] the Contractor shall not be entitled to an increase to the Contract Sum or extension
of time or use of the programme contingency referred to in sub-clause 9.4 [and the Employer
shall be released from all liability to the Contractor in connection with the matter].

33
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

10.3.3 If the cause of the claim has a continuing effect, the Contractor shall update the information at
monthly intervals
(1) stating the extension of time and adjustment to the Contract Sum claimed for delay and
cost already incurred and
(2) so far as practicable, proposing a final adjustment to the Contract Sum and Date for
Substantial Completion of the Works and any affected Section and
(3) providing any other information the Employer’s Representative reasonably requires.
10.3.4 The Contractor shall keep detailed contemporary records to substantiate any aspect of an
event or circumstance about which it has given, or is entitled to give, notice under this sub-
clause 10.3, and its resulting costs. These shall include any records the Employer’s
Representative directs the Contractor to keep. The Contractor shall give the records to the
Employer’s Representative if so directed.

10.4 Proposed Instructions


The Employer’s Representative may direct the Contractor to make proposals for a proposed
instruction. The Contractor shall not implement the proposed instruction unless and until the
Employer’s Representative has confirmed the instruction as given. Within 20 working days after the
Employer’s Representative directs the Contractor to make proposals, the Contractor shall give to the
Employer’s Representative all of the following:
(1) a detailed calculation and proposal, based on the calculation, of any adjustment to the
Contract Sum that would result from the proposed instruction
(2) if the proposed instruction would cause a delay, the information required under sub-clause
9.3, and a proposal, based on that information for any use of the programme contingency
referred to in sub-clause 9.4 or extension to the Date for Substantial Completion of the Works
and any affected Section
(3) if the proposed instruction is to omit any of the Works, a revised programme and, if
appropriate, a proposed earlier Date for Substantial Completion of the Works and any
affected Section
(4) any Contractor’s Documents required in connection with the proposed instruction, or a
timetable for them.

10.5 Employer’s Representative’s Determination


10.5.1 If the Contractor has made a claim or proposal under sub-clauses 10.3 or 10.4, the
Employer’s Representative shall, within 20 working days of receiving it, do one of the
following:
(1) direct the Contractor to give additional information or revised proposals, in which case
the Contractor shall do so within 10 working days and the Employer’s Representative
shall reply in accordance with this sub-clause within a further 10 working days, but that
reply must not require the Contractor to give additional information or a revised proposal
(2) notify the Contractor and the Employer that the Contractor’s proposals are agreed and
make any resulting adjustments to the Contract Sum, use of the programme
contingency referred to in sub-clause 9.4 or extension to the Date for Substantial
Completion of the Works and any affected Section
(3) make a determination of any adjustments to the Contract Sum, use of the programme
contingency referred to in sub-clause 9.4 or extension to the Date for Substantial
Completion of the Works and any affected Section, and notify the Contractor and the
Employer
(4) in response to a proposal under sub-clause 10.4, notify the Contractor that the
proposed instruction will not be given.
10.5.2 The Employer’s Representative may [but is not bound to] determine an extension of time for a
Compensation Event that is a breach of the Contract by the Employer on its own initiative
even if the Contractor has not made a claim or proposal under sub-clauses 10.3 or 10.4.

34
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

10.5.3 If the Employer’s Representative fails to take any of the actions in sub-clause 10.5.1 within the
time stated, the Employer’s Representative will be taken to have made a determination under
sub-clause 10.5.1(3) that there be no adjustment to the Contract Sum, no use of programme
contingency referred to in sub-clause 9.4, and no extension to any Date for Substantial
Completion. The determination will be taken to have been made on the last day of the time
provided for in sub-clause 10.5.1.
10.5.4 A determination of the Employer’s Representative notified to the Contractor and the Employer
under sub-clause 10.5.1(3) or 10.5.2 shall be final and binding on the Parties unless, within 28
days after receiving notice of the determination (or, if sub-clause 10.5.3 applies, within 28 days
after the determination is taken to have been made), the Contractor or the Employer gives
notice to the other under sub-clause 13.1.1 disputing the determination and referring the
dispute to conciliation.
10.5.5 Notice of an agreement under sub-clause 10.5.1(2) shall be final and binding on the Parties
unless, within 28 days after receiving the notice, either:
(1) the Contractor both (a) notifies the Employer’s Representative and the Employer that the
Contractor disagrees that the notice correctly records agreed terms and (b) gives notice
to the Employer under sub-clause 13.1.1 referring the dispute to conciliation or

(2) the Employer both (a) notifies the Employer’s Representative and the Contractor that the
Employer does not agree with the terms notified by the Employer’s Representative and
(b) gives notice to the Contractor under sub-clause 13.1.1 referring the dispute to
conciliation.

10.6 Adjustments to the Contract Sum


Adjustments to the Contract Sum for a Compensation Event shall only be for the value of any
additional, substituted, and omitted work required as a result of the Compensation Event under this
sub-clause 10.6 and any delay cost under sub-clause 10.7. [Where an adjustment to the Contract Sum
arises from additional, substituted or omitted named Specialists’ Works, the percentage addition
tendered by the Contractor, and included in the Schedule Part 3B, for that named Specialist shall be
taken into account in the valuation]. Additional, substituted, and omitted work shall be valued as
follows:
10.6.1 If the Compensation Event requires additional, substituted or omitted work, similar to work for
which there are rates in the Pricing Document, to be executed under similar conditions, the
determination shall use those rates.
10.6.2 If the Compensation Event requires additional, substituted or omitted work that is not similar
to work for which there are rates in the Pricing Document, or is not to be executed under
similar conditions, the determination shall be on the basis of the rates in the Pricing
Document when that is reasonable.
10.6.3 If the adjustment cannot be determined under the above rules, the Employer’s
Representative shall make a fair valuation based on rates for similar work in the locality, if
available.
10.6.4 Instead of sub-clause 10.6.1, 10.6.2 and 10.6.3 applying, the Employer’s Representative may
conclusively direct that additional or substituted work required as a result of a Compensation
Event be determined (in full or in part) on the basis of the cost of performing the additional or
substituted work, compared with the Contractor’s cost without the Compensation Event,
determined as follows:
(1) the number of hours worked or to be worked by each category of work person engaged
on the work to which the Compensation Event relates, on or off the Site, multiplied in
each case by the basic hourly rate for the relevant category of worker in an applicable
sectoral employment order implemented under the Industrial Relations Act 1946-2015
to which is applied the tendered percentage addition to costs of labour stated in the
Schedule, part 2D. Where the additional or substituted work includes named Specialist
Works, the percentage addition to costs of labour tendered by the respective named
Specialist in Appendix part 2C of their sub-contract is applied. (If the category of work
person is not covered by an applicable order made in accordance with the Industrial
Relations Acts 1946 – 2015 the Employer’s Representative will determine the most
appropriate basic hourly rate based on the category of work person’s skills and
experience). (If the category of work person is not covered by an applicable order

35
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

made in accordance with the Industrial Relations Acts 1946 – 2015 the Employer’s
Representative will determine the most appropriate basic hourly rate based on the
category of work person’s skills and experience) and
(2) the cost of materials used in that work, taking into account discounts and excluding
VAT, plus the percentage adjustment tendered by the Contractor and stated in the
Schedule, part 2D. Where the additional or substituted work includes named Specialist
Works, the percentage addition to costs of material tendered by the respective named
Specialist in Appendix part 2C of their sub-contract is applied. (But if the percentage
adjustment tendered is negative or blank it will be read as 0%) and
(3) the cost of plant reasonably used for that work, whether hired or owned by the
Contractor, at the rates in the document listed in the Schedule, part 1K (as that
document may be modified according to the Schedule, part 1K) plus or minus the
percentage adjustment tendered by the Contractor and included in the Schedule, part
2D. Where the additional or substituted work includes named Specialist Works, the
percentage addition to costs of plant tendered by the respective named Specialist in
Appendix part 2C of their sub-contract is applied. (But if the percentage adjustment
tendered is a deduction of more than 50% it will be read as a deduction of 50% or if the
entry is blank it will be read as 0%). If the document listed in the Schedule does not
give a rate for a plant item, a market rental rate shall be used, plus or minus the
percentage adjustment.

10.7 Delay Cost


10.7.1 If the Date for Substantial Completion of the Works has been extended because of a
Compensation Event [and not otherwise, and subject to sub-clause 10.7.2], there shall be
added to the Contract Sum an amount for delay cost, either (whichever it says in the
Schedule, part 1K)
(1) the expenses [excluding profit and loss of profit] unavoidably incurred by the Contractor
as a result of the delay to the Date for Substantial Completion of the Works caused by
the Compensation Event in respect of which that date has been extended under the
Contract.
or
(2) for each Site Working Day for which the Date for Substantial Completion of the Works
has been extended because of the Compensation Event, the daily rate of delay cost
tendered by the Contractor in the Schedule, part 2D [and to the extent that named
Specialists’ Works are delayed by a Compensation Event under the Contract between
the Employer and Contractor, the tendered rate of delay costs for the respective named
Specialists in Appendix part 2C of their sub-contract shall be used to determine the
delay cost]
10.7.2 If the Works are concurrently delayed by more than one cause, and one or more of the
causes is not a Compensation Event, there shall be no increase to the Contract Sum for
delay cost for the period of concurrent delay.
10.7.3 Except as provided in this sub-clause 10.7 [notwithstanding anything else in the Contract]
losses or expenses arising from or in connection with delay, disruption, acceleration, loss of
productivity or knock-on effect shall not be taken into account or included in any increase to
the Contract Sum, and the Employer shall have no liability for such losses or expenses.
10.7.4 [There shall be no delay cost paid as a result of extensions to the Date for Substantial
Completion of a Section].
10.7.5 If the Schedule states more than one rate for delay cost, the rate for the period when the
delay occurred or delayed part of the Works shall be used. This shall be determined by the
Employer’s Representative.

10.8 Price Variation


The Contract includes clause PV1 attached.

36
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

10.9 Employer’s Claims


10.9.1 If the Employer or the Employer’s Representative considers that, under the Contract, there
should be a reduction of the Contract Sum, or that any amount is due to the Employer from
the Contractor under the Contract, the Employer or the Employer’s Representative shall, as
soon as practicable, give notice and particulars of the event or circumstances to the other,
and to the Contractor. The notice shall include
(1) details of the event or circumstances giving rise to the notice, and all relevant facts and
(2) a calculation, and a proposal based on that calculation, of any adjustment to be made to
the Contract Sum or any amount due by the Contractor to the Employer.
10.9.2 The Contractor shall be entitled, within 20 working days of receipt of such a notice, to give a
response to the Employer’s Representative and shall, if the notice was given by the
Employer, give a copy of any response to the Employer. Within 20 working days after
receiving the Contractor’s response, or after the time for responding has elapsed, if the
Contractor has not responded within that time, the Employer’s Representative shall determine
the matter in accordance with the Contract.
10.9.3 The Employer may deduct from any amount due to the Contractor
(1) any amount determined by the Employer’s Representative to be due, or likely to
become due, from the Contractor to the Employer under the Contract and
(2) any amount due from the Contractor to the Employer under any contract.
10.9.4 The procedure in this sub-clause 10.9 shall apply until either the Defects Certificate or the
certificates required following termination have been issued, but this does not limit the
Employer’s rights after then.

37
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

11 PAYMENT

11.1 Interim Payment


11.1.1 At each of the following times
(i) the periods for interim payment stated in the Schedule, part 1L, if the amount payable
is more than the minimum amount stated in the Schedule and
(ii) upon issue of the certificate of Substantial Completion for the Works or any Section
the Contractor shall give a payment claim notice to the Employer’s Representative, in the
form of an interim statement, [not later than 5 days after the date agreed between the
Parties to be the payment claim date], showing all of the following:
(1) the progress of the Works
(2) the instalment of the Contract Sum that the Contractor considers should, under the
Contract, be paid on an interim basis
(3) a detailed breakdown using the Pricing Document, and individually detailing proposed
payments to named Specialists so that payments to each named Specialists are easily
distinguished from each other.
(4) any supporting evidence the Employer’s Representative requires (including
confirmation of whether and, if so, the extent to which, the rates have been adjusted by
the Applicable Factor (Contractor) and Applicable Factor (Specialist).
The interim statement given on Substantial Completion shall include all amounts due to the
Contractor at that time for the Works or Section.
11.1.2 The instalment of the Contract Sum that the Contractor shall be entitled to be paid on an
interim basis shall be
(1) the Contract value of the Works properly executed by the Contractor [according to the
Pricing Document, as a portion of the Contract Sum] and
(2) any amount the Employer’s Representative considers proper under sub-clause 11.2
and
(3) amounts for adjustments to the Contract Sum for Compensation Events, as
determined under the Contract and
(4) any amount to be paid according to clause PV1 attached and
(5) amounts included in the Pricing Document for Contractor’s Documents properly
completed and supplied as required by the Contract.
11.1.3 (a) So far as relates to that portion of the Contract Sum payable to the named Specialist,
unless already adjusted either:
(i) by a named Specialist in its application to the Contractor included in the detailed
breakdown at sub-clause 11.1.1 (3), or
(ii) if not so adjusted by the named Specialist, by the Contractor in the detailed
breakdown at sub-clause 11.1.1 (3);
the rates in the Pricing Document for those portions of the Contract Sum payable to the named
Specialists shall be adjusted by the relevant Applicable Factor (Specialist) for each named
Specialist.
(b) So far as relates to that portion of the Contract Sum not payable to the named
Specialists, unless already adjusted by the Contractor in the detailed breakdown at sub-
clause 11.1.1 (3), the rates in the Pricing Document for those portions of the Contract Sum
not payable to the named Specialists shall be adjusted by the Applicable Factor
(Contractor).
11.1.4 Within 14 days of receipt of the payment claim notice the Employer’s Representative shall
issue a response to the payment claim notice to the Contractor in the form of a certificate,
sending a copy to the Employer, setting out the amount of interim payment that, in the
Employer’s Representative’s opinion, is to be made by the Employer to the Contractor,
taking account of retention under sub-clause 11.3 and deductions and amounts due from the
Contractor to the Employer [including damages for delay and deductions under sub-clause
11.4], together with calculations and the reasons for the opinion. The Employer’s

38
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

Representative shall issue to the individual named Specialists, details of the gross and net
amount included within the certificate to the respective named Specialists.
11.1.5 If there is a sum due to the Contractor, the Contractor shall send an invoice to the Employer
for that sum after receiving the response to the payment claim notice. The Employer shall
pay the amount due on the invoice within 21 days after receiving the invoice.

11.2 Unfixed Works Items


At the discretion of the Employer’s Representative, but only when so provided in the Schedule, part
1L, interim payments may include any amount, not exceeding the percentage of value stated in the
Schedule, part 1L, the Employer’s Representative considers proper for each of the following:
(1) the Contract value of any Works Items that comply with all of the following requirements, all
to the satisfaction of the Employer’s Representative:
(a) they have been completed and are substantially ready to be incorporated in the Works
(b) title to them has been vested in the Employer
(c) they are stored suitably at the Site
(d) they have not been delivered to the Site prematurely
(2) the Contract value of any Work Items not delivered to the Site that comply with all of the
following requirements, all to the satisfaction of the Employer’s Representative:
(a) they have been completed and are substantially ready to be incorporated in the Works
(b) title to them has been vested in the Employer
(c) they are stored suitably and set aside and marked to show clearly that their destination
is the Site and that they are the property of the Employer
(d) they are clearly identified in a list given to the Employer’s Representative, together with
documentary evidence that title is vested in the Employer
(e) they are insured as required by the Contract, and will be insured as required while in
transit
(f) the Contractor has given the Employer a bond in the form for such bonds in the Works
Requirements, or if there is none, a form approved by the Employer, executed by a
surety approved by the Employer’s Representative, for the amount to be paid.
In this clause 11.2, the Contract value of a Works Item means a portion of the Contract Sum the
Employer’s Representative determines is for supplying of the Works Item, having regard to the Pricing
Document. [If the Pricing Document has a rate or price for supplying and fixing a Works Item, the
Contract value includes only the portion for supplying the Works Item, as determined by the
Employer’s Representative.]

11.3 Retention
11.3.1 There shall be deducted from each interim payment to the Contractor the retention
percentage stated in the Schedule, part 1L.
11.3.2 Upon issue of the certificate of Substantial Completion of the Works, the Contractor shall be
entitled to invoice the Employer for half of the amount so retained and the Contractor shall
furnish the Employer’s Representative with a copy of the invoice. Upon the issue of the
Defects Certificate, the Contractor shall be entitled to invoice the Employer for the balance
of the money so retained and the Contractor shall furnish the Employer’s Representative
with a copy of the invoice.
11.3.3 If, within 14 days of the issue of the certificate of Substantial Completion of the Works, or
another date agreed by the Employer’s Representative, the Contractor provides to the
Employer a retention bond in the form in the Work Requirements, or, if there is none, a form
approved by the Employer, for the amount retained by the Employer, and executed by a
surety approved by the Employer, the Contractor shall be entitled to invoice the Employer for
the balance of the money retained.
11.3.4 Upon issue of the certificate of Substantial Completion of a Section of the Works, the
retention amount to be withheld until issue of the certificate of Substantial Completion of the
Works shall be reduced by the amount stated in the Schedule, part 1G, and the Contractor

39
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

shall be entitled to invoice the Employer for that amount.


11.3.5 The Employer shall pay the Contractor the amount due on an invoice under this sub-clause
11.3 within 21 days after receiving the invoice [less any amount that the Employer is entitled
to deduct according to sub-clause 10.9].

11.4 Full Payment


The payments to the Contractor under this Contract are for compliance in full with the Contractor’s
obligations to the time of payment [including construction management, programming, reporting,
payment of wages and observing employment requirements] [but payment does not imply acceptance
that the obligations have been performed]. When the Contractor has not fully complied with its
obligations, the Employer is not required to make payment in full [without limiting its other rights or
remedies]. In particular
11.4.1 If the Contractor has not given a collateral warranty by the date stated in the Schedule, part
1F(i), the Employer is entitled to deduct from payment to the Contractor the amount stated in
the Schedule, part 1F(i) until the collateral warranty is given.
11.4.2 If the Contractor has not submitted a programme or given a progress report when required
by sub-clauses 4.9 and 4.10, the Employer is entitled to deduct 15% of each payment to the
Contractor until the programme or report has been submitted or given.
11.4.3 If the Contractor has not complied with sub-clause 5.3, the Employer is entitled to make the
deduction provided for in sub-clause 5.3.6.
11.4.4 If the Contractor does not give the certificate required by sub-clause 5.3.7 with an interim
statement, there shall be no payment due under sub-clause 11.1 for the relevant Work Item
until the certificate is given.
11.4.5 Deductions from payments because of obligations that the Contractor has still not complied
with by the date the Defects Certificate was issued shall be deducted from the Contract
Sum. In the case of a deduction from the Contract Sum because of failure to give the
certificate required by sub-clause 5.3.7, the amount deducted shall be the portion of the
Contract value of the relevant Work Item that the Employer determines to be the labour
portion. The Contractor shall give the Employer any information the Employer requires for
this determination.

11.5 Final Statement


11.5.1 Within 2 months after Substantial Completion of the Works is certified, the Contractor shall
give to the Employer’s Representative a final statement. The Contractor shall include in that
statement all money that the Contractor considers to be due from the Employer to the
Contractor under or in connection with the Contract. The Employer shall have no liability to
the Contractor under or in connection with the Contract for any matter not detailed in the
final statement, except under the indemnities in the Contract or Compensation Events
occurring after Substantial Completion of the Works was certified. If no final statement is
given within the time required, the Employer shall be released from all liability to the
Contractor under or in connection with the Contract.
11.5.2 Within 3 months after receipt of the Contractor’s final statement, the Employer’s
Representative shall issue to the Contractor and to the Employer a penultimate payment
certificate certifying the amount that, in the Employer’s Representative’s opinion, will be due
from the Employer to the Contractor, less any final retention to be paid after the Defects
Certificate is issued, or from the Contractor to the Employer.
11.5.3 As soon as practicable, no more than 3 months, after the Defects Certificate is issued, the
Employer’s Representative shall issue a final payment certificate certifying the amount that,
in the Employer’s Representative’s opinion, is finally due from the Employer to the
Contractor, or from the Contractor to the Employer. The amount in the final payment
certificate shall be the same as the amount in the penultimate payment certificate, except for
(1) the final payment of retention and
(2) adjustments to the Contract Sum because of Compensation Events that happen after
Substantial Completion of the Works is certified and
(3) amounts owed by the Contractor that were not included in the penultimate certificate

40
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

[for example, for Defects that the Contractor has not rectified] and
(4) deductions from the Contract Sum under sub-clause 11.4 and
(5) other amounts that, according to the Contract, are to be paid after Substantial
Completion of the Works [such as payments for testing after Substantial Completion].
11.5.4 If the penultimate or final payment certificate states that there is a sum owing to the
Contractor, the Contractor shall issue an invoice to the Employer for that sum and the
Employer shall pay the amount due on the invoice within 21 days after receiving the invoice.
If the penultimate or final payment certificate states that there is a sum owing to the
Employer, the Contractor shall pay the amount due within 14 days of receipt of the
Employer’s demand for payment. [Payments and certificates, including the penultimate and
final payment certificates and the Defects Certificate, will not relieve the Contractor of any
obligations, or be evidence of the value of work or that work has been completed
satisfactorily].

11.6 Time for Payment and Interest


11.6.1 When a payment is to be made under the Contract, and no time for payment is stated, the
amount due shall be paid within 30 days of receipt of a demand for payment.
11.6.2 Interest shall be added to any payment not made within the time provided in the Contract,
from the date the payment was due under the Contract, at the rate provided in the European
Communities (Late Payment in Commercial Transactions) Regulations 2012.

11.7 Value Added Tax


11.7.1 The Contractor’s completed form of tender states whether, and to what extent, the Contract
Sum includes VAT.
11.7.2 To the extent that the Contract Sum excludes VAT, the Employer shall pay the Contractor
(or the Revenue Commissioners when required by Law or their practice) any VAT arising on
the supply under the Contract in addition to the Contract Sum.
11.7.3 To the extent that the Contract Sum includes VAT,
(`1) adjustments to the Contract Sum shall be on a net-of-Vat basis, and the appropriate
sum for VAT shall be added or subtracted and
(2) any VAT included in the Contract Sum that the Employer is required to pay the
Revenue Commissioners (by Law or their practice) shall be deducted from the
Contract Sum.
11.7.4 So therefore, if the Contract Sum includes VAT chargeable at the standard rate only, then
the Employer shall pay the Contractor (or the Revenue Commissioners when required by
Law or their practice).
 The Contract Sum, including the VAT chargeable at the standard rate that is included in
the Contract Sum and also
 Any VAT arising on the supply under the Contract that is chargeable at another rate.
In the Contract ‘standard rate’ means the VAT rate specified in section 46(1)(a) of the Value-
Added Tax Consolidation Act, 2010.
11.7.5 Amounts in the Contract other than the Contract Sum exclude VAT, unless otherwise stated.
11.7.6 The Contractor shall send the Employer, for each payment, an invoice complying with 66 of
the Value-Added Tax Consolidation Act, 2010.

11.8 Withholding Tax


The Employer shall be entitled to make any deduction or withholding on account of tax required by
Legal Requirements or the practice of the Revenue Commissioners.

41
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

12 TERMINATION

12.1 Termination on Contractor Default


12.1.1 The Employer may, without limiting any other right or remedy, terminate the Contractor’s
obligation to complete the Works by notice to the Contractor if any of the following occurs:
(1) the Contractor fails to comply with its obligations under the Contract, and, if the failure
can be cured, the Employer’s Representative has directed the Contractor to put the
matter right, and the Contractor has not done so within 14 days after receiving the
direction
(2) the Contractor abandons or, except where required or permitted by the Contract,
suspends the execution of the Works
(3) the Contractor fails to proceed regularly and diligently with the execution of the Works
(4) the Contractor fails to maintain the required insurances or performance bond
(5) the Starting Date has not occurred or the Contractor has not started to execute the
Works on the Site within 6 weeks of the date the Contract requires
(6) any of the Contractor’s warranties in sub-clause 2.5 or sub-clause 2.6 are untrue
(7) the Contractor has committed or caused the Employer to commit a serious breach of
Legal Requirements concerning the Works
(8) the Contractor or Contractor’s Personnel have committed a breach of the Safety,
Health and Welfare at Work Act 2005 or any regulations or code of practice made
under it concerning the Works
(9) the Contractor has not complied with sub-clauses 5.3.2 or 5.3.3 either (a) within 14
days after notice from the Employer requiring a failure to be put right or (b)
persistently
(10) the Contractor has subcontracted all or any part of the Works in breach of the
Contract
(11) any of the following insolvency events occur:
(a) a petition is presented to wind up the Contractor and is not dismissed within 10
working days of presentation
(b) any meeting of creditors or members of the Contractor is convened or held for
the purpose of considering a resolution to wind up the Contractor
(c) any arrangement or composition with or for the benefit of its creditors [including
any compromises or arrangements entered into under sections 201 to 204 of
the Companies Act 1963] are proposed or entered into by or in respect of the
Contractor
(d) a liquidator, supervisor, receiver, administrator, administrative receiver, trustee
or encumbrancer takes possession of or is appointed over the Contractor or any
of its assets, or any distress, execution or other process is levied or enforced,
and not discharged within 10 working days, on the Contractor or any of its
assets
(e) the Contractor ceases or threatens to cease carrying on business, or is, or is
regarded by law or by a court to be, or declares itself to be, insolvent or unable
to pay its debts as they fall due
(f) a petition is presented to appoint an examiner to the Contractor, or an order is
made appointing an examiner to the Contractor
(g) the Contractor, being an individual, becomes bankrupt
(h) any event similar to the above insolvency events occurs in respect of the
Contractor in any jurisdiction in which it is incorporated or has a place of
business
(12) the Contractor, if an individual, dies or becomes incapable of performing the Contract.

42
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

12.1.2 If the Contractor is more than one person, if any of the insolvency events occur in respect of
any of them, the Employer may either
(1) terminate the Contractor’s obligation to complete the Works or
(2) terminate the obligation to complete the Works of the person concerned and the
others shall remain liable to perform the Contractor’s obligations.
12.1.3 If any insolvency events occur in respect of any person who has guaranteed the
Contractor’s performance of the Contract to the Employer, or a guarantee ceases to be
enforceable against the guarantor, the Employer may terminate the Contractor’s obligation
to complete the Works unless, within 10 working days of the event, the Contractor has
arranged a replacement guarantee and guarantor to the Employer’s satisfaction.

12.2 Consequences of Default Termination


If the Contractor’s obligation to complete the Works is terminated under sub-clause 12.1, the following
shall apply:
12.2.1 The Contractor shall leave the Site in an orderly manner.
12.2.2 Payment of all sums of money that may then be due from the Employer to the Contractor
shall be postponed, and the Employer shall not be required to make any further payment to
the Contractor except as provided in this sub-clause.
12.2.3 The Employer’s Representative shall, as soon as practicable, determine the amount due to
the Contractor under the Contract for the Works completed in accordance with the Contract
and unpaid (the termination value).
12.2.4 The Contractor shall not remove any Works Items or Contractor’s Things from the Site
unless directed to do so by the Employer, and if directed, shall promptly remove from the
Site any Works Items and Contractor’s Things, as directed.
12.2.5 The Employer may engage other contractors, use any Works Items and Contractor’s Things
on the Site and do anything necessary for the completion of the Works.
12.2.6 The Contractor shall, if so directed by the Employer’s Representative, assign to the
Employer [without further payment] the benefit of any subcontract, contract for the supply of
any Works Item, or other contract concerning the Contract.
12.2.7 The Employer may pay to any Subcontractor or supplier to the Contractor any amount due
to it that the Employer’s Representative certifies as included in any previous interim payment
to the Contractor. The Contractor shall re-pay to the Employer such an amount on request.
12.2.8 The Contractor shall give the Employer all Works Requirements and Contractor’s
Documents it [or Contractor’s Personnel] has.
12.2.9 When the Works have been completed and the termination amount as described below has
been determined, the Employer’s Representative shall give a certificate to the Contractor
and the Employer setting out the total of the following (the termination amount):
(1) the Employer’s additional cost of completing the Works compared with the cost that
would have been incurred if the Works had been completed by the Contractor in
accordance with the Contract
(2) loss and damage incurred by the Employer as a result of the termination and its
cause
(3) amounts due to the Employer by the Contractor under or in connection with the
Contract or in connection with the Works.
12.2.10 If the Employer does not begin to put in place arrangements to complete the Works within 6
months after the termination, the Employer’s Representative shall issue this certificate as
soon as practicable after the end of this 6 month period, based, if necessary, on estimates.
12.2.11 If the termination amount is less than the termination value, the Contractor shall issue an
invoice to the Employer for the difference and the Employer shall pay the amount due on the
invoice within 15 working days after receiving the invoice. If the termination amount is more
than the termination value, the Contractor shall pay the Employer the difference within 10
working days of receiving the Employer’s demand for payment.

43
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

12.3 Suspension by the Contractor


If the Employer fails to pay any amount due under clause 11, the Contractor may, on giving notice to
the Employer, in accordance with the Construction Contracts Act 2013, suspend execution of the
Works until the amount has been paid. On receiving the payment or notice has been served by either
Party referring the dispute to Adjudication, the Contractor shall resume execution of the Works.

12.4 Termination by the Contractor


The Contractor shall be entitled to terminate the Contractor’s obligation to complete the Works by
notice to the Employer if any of the following occur:
(1) the Contractor has suspended the execution of the Works for 15 working days in
accordance with sub-clause 12.3, and the Employer has still not paid
(2) work has been suspended by direction of the Employer’s Representative under sub-clause
9.2 and a right to terminate has arisen under that sub-clause
(3) the execution of the Works or a substantial part of the Works has been suspended for a
period of at least 3 months as a consequence of loss or damage that is at the Employer’s
risk under sub-clause 3.1
(4) an event or circumstance outside the control of the Parties makes it physically impossible or
contrary to Law for the Contractor to fulfil its obligations under the Contract for a period of at
least 6 months.

12.5 Termination at Employer’s Election


12.5.1 The Employer shall be entitled to terminate the Contractor’s obligation to complete the
Works at its election on 20 working days notice to the Contractor.
12.5.2 The Employer may not terminate the Contractor’s obligation to complete the Works under
this sub-clause 12.5 for the purpose of retaining another contractor to execute the Works.
12.5.3 The Employer shall return any performance bond required under this Contract to the
Contractor on termination under this sub-clause 12.5.

12.6 Consequences of Termination by Contractor or at Employer’s Election


If the Contractor’s obligation to complete the Works is terminated under sub-clause 12.4 or sub-clause
12.5 the following shall apply:
12.6.1 The Contractor shall leave the Site in an orderly manner and remove any Contractor’s
Things.
12.6.2 The Contractor shall give the Employer all Works Requirements and all Contractors’
Documents.
12.6.3 The Contractor shall, as soon as practicable, give the Employer’s Representative a
statement of the total of the following (the termination sum):
(1) the unpaid value of the parts of the Works completed to the date of termination in
accordance with the Pricing Document, disregarding any provision limiting the
Employer’s obligation to pay for partially completed work
(2) the Contractor’s reasonable costs of removal from the Site as a consequence of the
termination
(3) all other amounts due to the Contractor under the Contract but not damages.
12.6.4 Within 10 working days of receiving this statement, the Employer’s Representative shall
issue a certificate to the Contractor and the Employer of the amount due from the Contractor
to the Employer or the Employer to the Contractor, including the termination sum in the
calculation of the amount due from the Employer to the Contractor. If the certificate shows
an amount owing to the Contractor, the Contractor shall issue an invoice to the Employer for
that amount, and the Employer shall pay the amount due on the invoice within 15 working
days after receiving the invoice. If the certificate shows an amount due to the Employer, the
Contractor shall pay the amount due within 10 working days of receiving the Employer’s
demand for payment.

44
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

12.7 Survival
Termination of the Contractor’s obligation to complete the Works shall not affect the Contractor’s
obligations under the Contract, other than the obligation to complete the Works. [In particular the
following provisions of the Contract continue to have effect after termination: sub-clauses 1.1, 1.2, 1.3,
1.4, 1.7, 1.8, 1.9, 2.1, 2.6, 2.7, 3.4, 3.5, 4.16, 4.17, clause 6, this clause 12 and clause 13.]

12.8 Payment
On termination of the Contractor’s obligation to complete the Works, the Employer’s liability to the
Contractor under or in connection with the Contract shall be limited to payment of the amount provided
for in this clause 12, and any other amount that fell due under the Contract before the termination.

12.9 Reference to Conciliation


12.9.1 The Employer may [but is not required to] refer to conciliation under sub-clause 13.1 the
issue of whether the Employer has become entitled to terminate the Contractor’s obligation
to complete the Works under sub-clause 12.1.
12.9.2 Sub-clause 13.1 shall apply to the conciliation, except that the conciliator’s time to give the
recommendation shall be 21 days after appointment. Clause 13.5 shall also apply.
12.9.3 If the conciliator recommends that the Employer is entitled to terminate the Contractor’s
obligation to complete the Works under sub-clause 12.1, and the Employer does so within
63 days after receiving the conciliator’s recommendation, and it is subsequently found that
the Employer was not entitled to do so, then the following shall apply:
(1) the termination shall stand [even if the circumstances have changed] and have effect
as if the Employer’s termination notice under sub-clause 12.1 was a valid termination
notice under sub-clause 12.5.1
(2) sub-clauses 12.6.1 to 12.6.4 inclusive shall apply retrospectively from the date of the
termination notice under sub-clause 12.1
(3) sub-clause 12.5.2 shall not apply
(4) the Contractor shall have no other rights or remedies under the Contract or otherwise
at law for the termination.

45
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

13 DISPUTES

13.1 Conciliation
13.1.1 If a dispute arises under the Contract, either Party may, by notice to the other, refer the
dispute for conciliation under this sub-clause 13.1. The notice shall state that it is given
under sub-clause 13.1 of the Contract.
13.1.2 Within 10 working days of the referral of a dispute to conciliation, the Parties shall jointly
appoint a conciliator who is competent to adjudicate upon the dispute and independent of
the Parties. If the Parties fail to appoint a conciliator within 10 working days of the referral, or
if a person appointed refuses to act or becomes unable to act, the conciliator shall be
appointed by the appointing body or person named in the Schedule, part 1N, on the
application of either Party. If there is a fee for making the appointment, the Parties shall
share it equally. If one Party pays the entire fee, it shall be entitled to reimbursement of the
other Party’s share from the other Party on demand.
13.1.3 Each Party shall, within the period set by the conciliator, send to the conciliator and the other
Party brief details of the dispute stating its contentions as to the facts and the Parties’ rights
and obligations concerning the dispute. The conciliator may, for this purpose, suggest
further actions or investigations that may be of assistance.
13.1.4 The Parties shall promptly make available to the conciliator all information, documents,
access to the Site and appropriate facilities that the conciliator requires to resolve the
dispute.
13.1.5 The conciliator shall consult with the Parties in an attempt to resolve the dispute by
agreement. The conciliator may do any of the following, or any combination of them:
(1) meet the Parties separately from each other or together and consider documents
from one Party not sent or shown to the other
(2) conduct investigations in the absence of the Parties
(3) make use of specialist knowledge
(4) obtain technical or legal advice
(5) establish the procedures to be followed in the conciliation
13.1.6 The conciliator shall not be an arbitrator and the Arbitration Act 2010 and the law relating to
arbitration shall not apply to the conciliation.
13.1.7 The conciliator’s terms of appointment shall be those in the Works Requirements or, if there
are none, those agreed by the Employer and the Contractor with the conciliator.
13.1.8 If the dispute is not resolved by agreement within 42 days after the conciliator was
appointed, or a longer period proposed by the conciliator and agreed by the Parties, the
conciliator shall give both Parties a written recommendation. The conciliator shall base the
recommendation on the Parties’ rights and obligations under the Contract.
13.1.9 If either Party is dissatisfied with the conciliator’s recommendation, it may, within 42 days
after receiving the conciliator’s recommendation, so notify the other Party. The notice shall
state that it is given under sub-clause 13.1 of the Contract, and shall state the matters in
dispute and the reasons for dissatisfaction. If the conciliator has failed to give a
recommendation within 42 days after appointment, either Party may give a notice of
dissatisfaction. If notice of dissatisfaction has been given in accordance with this clause,
either Party may refer the dispute to arbitration under sub-clause 13.3.
13.1.10 If neither Party gives notice of dissatisfaction within 42 days after receiving the conciliator’s
recommendation, the recommendation shall be conclusive and binding on the Parties, and
the Parties agree to comply with it. If, in such circumstances, a Party fails to comply with the
conciliator’s recommendation, the other Party may [without limiting its other rights] refer the
failure itself to Adjudication, [where the dispute is a dispute relating to payment], or to
arbitration under sub-clause 13.3, and need not invoke this sub-clause 13.1 for this reference.

46
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

13.1.11 If the conciliator has recommended the payment of money and a notice of dissatisfaction is
given, the following shall apply:
(1) The Party concerned shall make the payment recommended by the conciliator,
provided that the other Party first
(a) gave a notice, complying with the arbitration rules referred to in sub-clause
13.3, referring the same dispute to arbitration and
(b) gave the paying Party a bond executed by a surety approved by the paying
Party, acting reasonably, in the form included in the Works Requirements, or if
there is none, a form approved by the paying Party, acting reasonably, for the
amount of the payment.
(2) If, when the dispute is finally resolved, it is found that the Party receiving payment on
the conciliator’s recommendation was not entitled to some or all of the amount paid,
then that Party shall repay the amount it was paid and found not to be entitled to,
together with interest.
(3) When the dispute is finally resolved, interest will be deducted from final payment
under the award or judgment.
(4) Interest under this sub-clause is calculated at the reference rate referred to in the
European Communities (Late Payment in Commercial Transactions) Regulations
2012 plus 2% per year and runs from the date of the original payment to the date of
the repayment or final payment.
(5) [This provision for interest is confidential under sub-clause 13.1.12, and in particular
shall not be taken into account or referred to in arbitration until all other matters are
resolved.]
13.1.12 The conciliation shall be confidential, and the Parties shall respect its confidentiality, except
when any of the exceptions in sub-clause 4.16 apply, or to the extent necessary to enforce a
recommendation that has become conclusive and binding. All documents provided by a
Party in connection with a conciliation shall be returned when the conciliation is concluded.
13.2 Adjudication
13.2.1 The parties have recourse to Adjudication in accordance with the Construction Contracts
Act 2013
13.2.2 Where an adjudicator reaches a decision on a dispute referred under the Construction
Contracts Act 2013, that same dispute shall not be referred to conciliation under the
Contract.
13.2.3 If a dispute between the Parties is referred to Adjudication, any conciliation relating to that
dispute immediately adjourns. In the event that no decision is reached by the adjudicator,
the parties may continue to resolve the dispute under the conciliation from the date the
dispute was referred to Adjudication. In the event that a decision is reached by the
adjudicator, the conciliation for that dispute shall be terminated.

13.3 Arbitration
Any dispute that, under sub-clause 13.1, may be referred to conciliation shall, subject to sub-clause
13.1 be finally settled by arbitration in accordance with the arbitration rules identified in the Schedule,
part 1N. For purposes of those rules, the person or body to appoint the arbitrator, if not agreed by the
Parties, is named in the Schedule, part 1N.

13.4 Jurisdiction
Subject to the above provisions of this clause, the Parties submit to the jurisdiction of the Irish courts to
settle any dispute that may arise out of or in connection with the Contract or the Works.

47
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

13.5 Agent for Service


If an agent for service of legal proceedings on the Contractor is named in part 2A of the Schedule, the
Contractor confirms to the Employer that it has irrevocably appointed the named person as its agent
for the service of all documents relating to legal proceedings, and that failure of the agent to notify the
Contractor of receipt of a document will not invalidate any proceedings or the service of the document.

13.6 Continuing Obligations


[Despite the existence of a dispute, the Parties shall continue to perform their obligations under the
Contract.]

48
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

14 COVID-19 MANDATORY CLOSURE


14.1 Covid-19 Definitions
14.1.1 Covid-19 means Covid-19 or such variant thereof as each is listed in the schedule to the
Infectious Diseases Regulations 1981.

14.1.2 Covid-19 Mandatory Closure means the closure of the Site due to Covid-19 mandated by
Law and/or mandated by order of a public authority exercising authority under Law, that did
not arise as a result of or in connection with an act, omission or breach of Legal Requirements
of the Contractor or the Contractor’s Personnel or a breach of the Contract by the Contractor.

14.1.3 Site Closure Costs has the meaning set out in the Site Closure Costs Supplement.

14.1.4 Site Closure Costs Supplement means the document of the same name in the Works
Requirements or, if there is none, the version of the document of the same name published
on the Office of Government Procurement website most recently before the Designated Date.

14.2 Covid-19 General Provisions

14.2.1 The Contractor’s sole remedies for a Covid-19 Mandatory Closure shall be those stated in
sub-clause 9.3 for a Delay Event under the Schedule Part 1K Event 15 and Site Closure Costs
under this clause 14. The provisions of clause 10 shall apply in respect of any extension of
time to the Date of Substantial Completion under sub-clause 9.3 for a Delay Event under the
Schedule Part 1 K Event 15 and an adjustment to the Contract Sum for the Site Closure Costs
under this clause 14 in respect of a Covid-19 Mandatory Closure.

14.2.2 The period of any Covid-19 Mandatory Closure shall not be taken into consideration in
calculating the period under sub-clause 12.4(4).

14.3 Covid-19 Costs

14.3.1 In the event of a Covid-19 Mandatory Closure there shall be added to the Contract Sum the
Site Closure Costs for the period of the Covid-19 Mandatory Closure[s], excluding the first [7]
days in total of the Covid-19 Mandatory Closure or where there is more than one Covid-19
Mandatory Closure, the Covid-19 Mandatory Closures.

14.3.2 The Contractor shall only be entitled to Site Closure Costs to the extent that all of the following
apply:

(1) the Site Closure Costs are not a result of the Contractor’s or Contractor’s Personnel’s
act or omission or the Contractor’s breach of the Contract

(2) if the Works are concurrently delayed by more than one cause, and one or more of the
causes is not a Covid-19 Mandatory Closure, there shall be no increase to the Contract
Sum for Site Closure Costs for the period of concurrent delay

(3) the Contractor makes all reasonable efforts to avoid and minimise the adverse effects
of the Covid-19 Mandatory Closure

(4) the Contractor has complied with sub-clause 10.3, clause 14 and the Site Closure
Costs Supplement in full [including giving notices and details within the time required]
and continues to comply with its obligations under the Contract

(5) the Contractor has not claimed or received as part of the Site Closure Costs, any costs
in respect of which it is entitled to claim assistance or receive payment under any
scheme, relief, benefit or otherwise [including under the Financial Provisions (Covid-
19) (2) Act 2020 (Act No. 8 of 2020) or similar Law]

49
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

(6) the Contract does not provide otherwise.

14.3.3 The Contractor warrants that the details that it provides as required by the Site Closure Costs
Supplement are a complete and full break-down of the relevant costs, on a transparent and
‘open book’ basis.

14.3.4 Any adjustment to the Contract Sum in accordance with sub-clause 14.3.1 shall be paid as
part of the Contract value of the Works properly executed by the Contractor under sub-clause
11.1.2(1). The retention percentage at 11.3.1 shall not apply to payments under clause 14.

End of Conditions.

50
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

CLAUSE PV1 – Price Variation


PV1.1 Contract Sum Adjustment
The Contract Sum is adjusted for fluctuations in costs of resources only in respect of increases or
decreases that occur in workers’ wages or expenses, or material prices, or are made by Law, as
follows:
PV1.1.1 Timing:
(a) The Base Date means the first day of the 25th month after the Tender Inflation
Indexation Date.
(b) No increase or decrease that comes into being after the Date for Substantial
Completion shall be taken into account for the purpose of this clause PV1.
PV1.1.2 Workers’ remuneration and expenses
The Contract Sum shall be adjusted by the amount of an increase or decrease in workers’
remuneration and expenses that satisfies all these requirements:
(i) it is made to the standard rates of remuneration payable to workers according to
any sectoral employment orders implemented under the Industrial Relations Acts
1946 to 2015 and
(ii) it becomes payable after the Base Date in accordance with the relevant sectoral
employment order and
(iii) the workers in respect of whom an increase is being claimed have received in
Ireland for the relevant work at least the increased remuneration

Remuneration has the meaning set out in Section 13 of the Industrial Relations
(Amendment) Act 2015.

Workers means
(a) any individuals employed by, or otherwise working for the Contractor or the
Contractor’s Personnel on or adjacent to the Site and fall within any categories of
workers to whom a relevant sectoral employment order applies in accordance with
its terms and
(b) any foreperson, charge hand or other person who supervises or administers while
performing duties within (a) but in respect only of the remuneration according to
sub-clause PV1.1.2(i) applicable to those duties and 50% of their total hours
worked.
[Site agents, managers, other full time supervisors and administrators, and surveyors, for
example, are excluded.]

Expenses means PRSI payable by the Contractor as employer.


[All other increases are excluded, even where calculated as a percentage of a standard
rate. So, for example, the Contractor is not entitled to any payment for local or site
bargaining provisions; any parity or restructuring increases; any bonus under a site
agreement, subsistence or country money, productivity, incentive, or other bonus;
insurance premiums, other on-costs or consequential costs].

51
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

PV1.1.3 Materials
The Contract Sum shall be adjusted by the amount of an increase (in the case of an
increase) or the amount of a decrease (in the case of a decrease) in the Price of material
that results from either or both of these calculations where applicable:
 So far as the Price of any material at the Purchase Date has increased or decreased
by more than 15 percent of the Price at the Tender Inflation Indexation Date, then that
excess percentage over 15 percent is applied to its Price at the Tender Inflation
Indexation Date (the “First Adjustment”).
 So far as the Price of any material at the Base Date has increased or decreased at the
Purchase Date by more than 10 percent, then that excess percentage over 10 percent
is applied to the Price at the Base Date (the “Second Adjustment”)
PROVIDED THAT

 in the case of an increase arising from both the First Adjustment and the Second
Adjustment, the Contract Sum shall only be adjusted by the amount of the higher of
the two increases, but not the amount of both; and
 in the case of a decrease arising from both the First Adjustment and the Second
Adjustment, the Contract Sum shall only be adjusted by the amount of the lower of the
two decreases, but not the amount of both.

Material means only


(a) material invoiced to the project
(b) for incorporation in the permanent Works [as fixtures or unfixed goods],
(c) or for temporary works used on the Site
(d) and not used on any previous project or usable on any subsequent one [for
example, replaceable components in formwork]. [Tools or equipment are not
‘material’. There is no deduction of normal wastage from the allowable quantity of
material, or of extra or surplus material taken over by the Employer].
Purchase Date means the date when the particular material was invoiced to the project.
Price means the average price at which the relevant volume of the relevant material is
available in the market at the relevant time from a representative number of reputable
manufacturers or suppliers.
[There is no adjustment for any alteration in the price of material except as specified in
this sub-clause].
PV1.1.4 Law
The Contract Sum shall be adjusted by the amount of any increase or decrease in the
Contractor’s cost of performing its obligations under the Contract as a result of a change
in Law made after the Designated Date that
(i) changes [whether by alteration, addition or removal] VAT, customs or excise
duties, requirements for a licence to import or export any commodity or Pay-
Related Social Insurance and
(ii) is not identified in the Works Requirements and
(iii) has not resulted in an adjustment in the Contract Sum under another part of this
clause PV1 or the Contract.

PV1.2 Communications
The Contractor shall maintain arrangements to become aware of any significant possibility of an
increase or decrease in the Contract Sum that may arise in accordance with this clause PV1 and
shall immediately notify the Employer’s Representative of any such possibility and keep him informed
of any opportunities to minimise an increase.

PV1.3 Compensation Events


The Pricing Document and the valuation rules in sub-clause 10.6 shall not cease to determine, apply
to or be the basis of the valuation of a Compensation Event by reason of price fluctuations in material
52
PW-CF5 v2.6 07/01/2022
PUBLIC WORKS CONTRACT FOR MINOR WORKS

costs, but the following principles shall apply:


(i) No departure from rates in the Pricing Document shall be made in respect of fluctuations
affecting the cost of material omitted by a Change Order.
(ii) Valuation of a Change Order shall include any increase in the cost to the Contractor of material
substituted or added by the Change Order that is due to price fluctuation after the Tender
Inflation Indexation Date so far as it is likely to exceed the price fluctuation increase that under
this clause PV1 would have been the Contractor’s risk for the original material.
No adjustment under this clause PV1 shall apply to an adjustment or the part of an adjustment of the
Contract Sum valued under sub-clauses 10.6.4 or 10.7.
PV1.4 Efficiency
[In addition to sub-clause PV1.1.1(b),] increases of the Contract Sum will only apply so far as the
increased costs incurred by the Contractor occur despite its efficient progress and procurement and
reasonable efforts to minimise increases.
PV1.5 Certificates & Payment
The Contractor shall fully detail and vouch any fluctuations in costs relevant to this clause PV1 as
soon as practicable, and they shall then be allowed for in interim and final certificates and payments
under and subject to clause 11.

53
PW-CF5 v2.6 07/01/2022

You might also like