Cafc - QCP General Civil Works

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 26

B405b CAFC

GAS GATHERING

QUALITY CONTROL PLAN

GENERAL CIVIL WORKS

REVISION HISTORY

EX-CO 00 SF
Validity Rev.
Status number Prepared Checked Approved Company Company
Date Description
by by by Check Approval
Revision Index
Company logo and business name Project name Eni E&P Document ID:

B405b
CAFC Sonatrach Document ID:
Gas Gathering

Job N.
Vendor logo and business name Vendor Document ID

Order N.
Facility Name Location Scale Sheet of Sheets
CAFC - Central Area Field Complex  OnShore n.a.

Document Title Supersedes N.

QCP – General Civil Works Superseded by N.


Plant Area Plant Unit

Software: Microsoft Word 97-2003 File No. 652844163.doc


This document is property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to civil and penal
provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
2 / 26
EX-CO 00

Rev. Date Nr. of Description


sheets
EX-CO 27 First issue

This document is property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
3 / 26
EX-CO 00

CONTENTS

1. GENERAL 4
1.1. Scope and Objective 4
1.2. Terms and definitions 4

2. QUALITY CONTROL PLANNING 6


2.1. Information Related to this Document 6
2.2. Preparation and Issuing of QCP and ITPs 6
2.3. Construction Contractor responsibility 6
2.4. Local Regulations 7

3. APPLICABLE DOCUMENTATION 8
3.1. Specifications Codes and Standards 8

4. SPECIFIC QUALITY REQUIREMENTS FOR


CONSTRUCTION 9
4.1. Project Technical Provision 9
4.2. Procedures 9
4.3. Civil Materials 9
4.4. Batching Plant 9

5. ATTACHMENTS 10
5.1. ITP List 10
5.2. Forms List 10

1 GENERAL

2 Scope and Objective

This document provides guidance and minimum requirements for inspecting, checking and testing
of Construction Contractor for the execution of General Civil Works related works to be performed
during construction of CAFC Project.

This document is additional to and shall be read together with Project Quality Plan and with all other
applicable contractual documentation.

3 Terms and definitions


The following terms and definitions shall be used by Construction Contractor in the preparation of
any quality related document:

Project CENTRAL AREA FIELD COMPLEX (CAFC) in the Algerian Sahara


desert of North Africa.

This document is property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
4 / 26
EX-CO 00

Company Contracting Authority – Sonatrach (SH) and First Calgary Petroleums


(FCP) acting jointly.
Contractor The firm/corporation who will carry out the construction and
commissioning of those elements of the project and includes the
CONTRACTOR’s personnel representative, successor and permitted
assignees.
Sub-Contractor The firm/corporation to which the CONTRACTOR may in turn sub-
contract part of the WORK subject to prior approval of the COMPANY.
Work All temporary and permanent work described in the Contract and
specifications.
Vendor/Supplier The organization to be awarded a Purchase order/Contract for supply of
materials, equipment or service required.
Manufacturer The organization responsible for the manufacture of the equipment (not
necessary the VENDOR/SUPPLIER).
TPI Third Party Inspection: any organization, authority, person or persons, to
which Construction Contractor has subcontracted the execution of
inspection and or laboratory testing related activities or local Authority.
QMS Quality Management System: part of the organization’s management
system that focuses on achievement of results, in relation to the quality
objectives, to satisfy the needs, expectations and requirements of
Contractor/Client and of any other interested parties, as appropriate.
QCP Quality Control Plan: Construction Contractor plan contain all quality
control requirements. This plan complements and compiles all applicable
ITP(s).
ITP Inspection and Test Plan: Construction Contractor plan of inspection and
tests required by engineering and vendors documents or elsewhere
specified. ITP(s) shall provide references to applicable procedures,
acceptance criteria, documentation, quality records and inspection
attendance to be performed, in chronological order, from initial
inspection, throughout final inspections and mechanical completion.
ITP(s) and relevant forms shall be issued as QCP enclosures.
MDT Inspection report Form, attached to the ITP. They shall be used during
checks and inspections /tests and signed by the involved parties, as per
relevant QC code
RFI Request for Inspection: Written notification to be issued by Construction
Contractor in order to allow all parties involved to perform their inspection
and test witness as planned in the applicable ITP;
QA Quality Assurance: Part of quality management focused on providing
confidence that quality requirements will be fulfilled;
QC Quality Control: Part of quality management focused on fulfilling quality
requirements;
NCR Non Conformity Report: Document recording a non-fulfilment of a
requirement;
Non Conformity The non-fulfilment of specified requirements;
Special Process A process, the results of which are highly dependent on the control of the
process or the skill of the operator and in which the specified quality
cannot be readily determined by inspection or test on the product;
This document is property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
5 / 26
EX-CO 00

Calibration Comparison of a measurement and test equipment with a reference


standard or with another one provided with better tolerance in order to
detect or to measure possible inaccuracies and to document or eliminate
them.

Any other terms related to quality and not listed above shall conform to section 3 “Term and
Definition” of ISO 9000:2005 “Quality Management System – Fundamentals and vocabulary”.
4 QUALITY CONTROL PLANNING

5 Information Related to this Document

This document includes the ITPs and forms listed under the paragraph 5.1 and 5.2, for performing
as minimum Civil Works inspection, tests and certification.

The ITPs can be separated into the two following groups:


- General ITPs include the initial necessary checks and verification to be performed but not
limited to:
- Documentation;
- Personnel and equipment;
- Material receiving;
- Climatic conditions;
- Etc..
- Specific ITPs include inspection and tests which are directly related to construction items
and or part of the Works that can be identified and tracked through engineering drawings.

6 Preparation and Issuing of QCP and ITPs

Construction Contractor has reissued this document “Quality Control Plan” (QCP) same as the
approved “Quality Control Specification” (QCS), improving the enclosed ITPs in accordance to the
project requirements and completing the information requested on clause 3.1 and the ITPs columns
“Reference document” & “Acceptance Criteria”

If during Works Construction Contractor will need additional ITP/ ITP phase for further test and
checks with the relevant QC Codes, the same shall be numbered adding an alphanumeric suffix to
the preceding available QC Code. New QC Codes shall be submitted and approved by Client.

Construction Contractor during the execution of the Works shall revise and update, as and when
required, the QCP(s) and relevant ITP(s) to incorporate any other pertinent requirements set forth in
engineering specifications, standards, design codes, recommended practices, safety design,
referred hereafter or included elsewhere in the contractual and vendors documents.

Before starting of Works, the QCP containing the ITPs applicable for the project items and works,
shall be submitted by the Construction Contractor for Client review and approval.

7 Construction Contractor responsibility

Construction Contractor in order to meet all the contractual requirements will prepare and update
any other necessary QCP(s) and ITP(s), and quality procedures which include all inspections,
examinations and tests required to verify the quality of the Works. The above documents shall be
timely submitted to Client for review and approval in order to ensure their availability in approved
status prior to starting of the welding works.
This document is property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
6 / 26
EX-CO 00

Construction Contractor will perform and record all inspections, examinations and tests required and
shall carry out all the works necessary for the preparation of inspections, examinations and tests,
including adequate scaffolding for safely witnessing the inspection.

Construction Contractor will provide, for the execution of testing, inspection and measurements all
necessary equipment, tools and shall make available the applicable international Standards and
Codes.

Construction Contractor will issue inspections, examinations and tests reports immediately after the
completion of each inspection activity. All reports shall be approved and signed off by Construction
Contractor authorized personnel prior to submission to Client for review or approval, as appropriate.

8 Local Regulations

Inspections and tests required by Algerian law and regulation shall be strictly adhered to,
documented by Construction Contractor and shall take precedence over this specification.

When Algerian law and local regulations are different from the applicable design codes,
Construction Contractor shall inform Client for the necessary actions.

This document is property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
7 / 26
EX-CO 00

9 APPLICABLE DOCUMENTATION

10 Specifications Codes and Standards


11 Project specifications:
- CAFC-00-ST-ZG-99ZO03 Specification for Earthworks
- CAFC-00-ST-ZG-99ZO02 Specification for Site Preparation
- CAFC-00-ST-ZC-99ZO01 Specification for Concrete Materials and
Construction
- CAFC-ROA-ST-ZG-93ZO01 Specification for Road Construction
- CAFC-00-ST-S-99SO10 Specification for Steelwork Materials and
Construction
- CAFC-00-ST-ZG-99ZO01 Specification for Chain Link Fencing and Gates

12 Codes and Standards:


Applicable Codes and Standards are those referred in the Contract reference “Code &
Standards” doc.

This document is property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
8 / 26
EX-CO 00

13 SPECIFIC QUALITY REQUIREMENTS FOR CONSTRUCTION

14 Project Technical Provision

The Main Technical Provisions are indicated on the drawings, or in Project specifications that must
be mentioned on the drawings. The remaining provisions not mentioned on drawings are given in
the Standard Specifications.

The applicable Standard specifications are listed in paragraph 3 and their applicability to the test
codes are indicated in the ITP.

15 Procedures

Construction Contractor has to issue project specific procedures before start of any related work.

16 Civil Materials

Prior to purchase of construction materials for road works, the Construction Contractor will submit
the documentation, indicating the material sources, the technical characteristics with reference to
pertinent Codes and Standards, and the Manufacturer's name along with catalogues and data
sheets, etc., in order to obtain required approval.

Prior to using the materials on Site, the Construction Contractor has carry out all the inspections,
examinations and tests prescribed by this document and the Project specifications in the sequence
and with the involvement of the Parties foreseen in this Plan, None of these materials shall be used
in construction unless it has passed all the necessary inspections, examinations and tests.

As concerns the sampling of the material to be tested, the Construction Contractor shall submit the
relevant RFI. The sampling shall be carried out in the presence of parties involved, whenever this is
required.

The Construction Contractor shall organize a Site Laboratory suitable to carry out the routine tests
on materials of civil works. Client has the right to require the substitution of the laboratory personnel
or equipment that it considers unsuitable.

Testing that cannot be carried out at the Site Laboratory can be executed by an external laboratory
duly approved by Client. In that case Client reserves the right to attend these inspections and/or
tests carried out at the External Laboratory and shall receive the relevant RFI.

17 Batching Plant

The Construction Contractor is fully responsible for the supply of concrete asphalt and wearing
course that meets Project’s requirements and complies with the applicable standards. However in
order to ensure homogeneous product with the required properties, the Construction Contractor
shall submit to Client the complete Batching Plan QC dossier with the necessary documented
evidence of compliance with the applicable code and Algerian regulation.

An informal visit by Client and Construction Contractor shall be made to verify the above aspects,
before starting asphalt production.

This document is property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
9 / 26
EX-CO 00

18 ATTACHMENTS

19 ITP List

General ITP for Initial Inspection:


ITP No. CV-0001 Survey Instrument Stations and Electronic Operating System, Project Bench
Marks
ITP No. CV-0002 Earthworks- Fill And Base Material for Roads, Parking Areas, Paving
Subbase, Main Item Foundation Base, Area Finishing & Surfacing Materials
ITP No. CV-0003 Asphalt Concrete, Bituminous Products and Asphalt Concrete Related
Materials
Specific ITP for construction:
ITP No. CV-0201 Earthworks (Excavation & Fill) for Roads and General Site Preparation
ITP No. CV-0202 Roads and Parking Areas Works (Asphalt)

20 Forms List

Inspection and test report forms:


a) General:
MDT.CV.CDQ.0016 Inspection Report Regarding Established Project Bench Marks
b) Specific:
MDT.CV.CDQ.0204 Inspection Report Form for Density/Compaction Test (Excel Register)
MDT.CV.CDQ.0208 Finishing Inspection Report on Final Course of Completed Asphalt or
Concrete Roads, Parking Areas and Paving Works
MDT.CV.CDQ.0214 Inspection Report on Formation Level for: Roads, Parking Areas,
Paving, Lean Concrete, Foundation
MDT.CV.CDQ.0218 Asphalt Log Book (Excel Register)
MDT.CV.CDQ.0230 Inspection Report of Final Finished Surfaced Areas

This document is property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 10 / 26
Sonatrach Document ID: Status

EX-CO 00

ITP No. CV-0001 DISCIPLINE


Title: SURVEY INSTRUMENT STATIONS AND ELECTRONIC CIVIL GENERAL
OPERATING SYSTEM , PROJECT BENCHMARK Involvement
Reference Acceptance Report GTP TP1 CL Notes
QC CODE Description Document Ref. Criteria Form CC QC ARH SH-FCP

AFC Drwgs.
CV 0001 01 Check and verify Topographic Instrument Certificates / P R
certificates before Topographic works Instruments
Certificate
register list

Topographic
CV 0001 02 Before commencement the Project works survey and/or MDT.CV.CDQ. P H R
check & verify Client’s given bench marks grading plans 0016
Obtain permits for wellpads
Confirm centre line and fence lines
Confirm elevations comply with detail
drawings.
Establish a new a permanent Project bench
marks placed on a secure, stable object that
is easily identifiable and recoverable at a
suitable location in the vicinity of the Project.

ORGANIZATION CODE INVOLVEMENT CODE


CC – Construction Contractor TP1 – Third Party P – Perform/Submit W – Witness (minimum 20% inspection rate)
QC – QC Construction Contractor CL – Client S – Surveillance H – Hold Point (100% inspection rate)
R – Review M- Monitoring
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 11 / 26
Sonatrach Document ID: Status

EX-CO 00

ITP No. CV-0002 DISCIPLINE

Title: EARTHWORKS- FILL AND BASE MATERIAL FOR ROADS, CIVIL GENERAL
PARKING AREAS, PAVING SUBBASE, MAIN ITEM FOUNDATION BASE, Involvement
AREA FINISHING & SURFACING MATERIALS
Reference Acceptance Report GTP TP1 CL Notes
QC CODE Description Document Ref. Criteria Form
CC QC ARH SH-FCP
AFC Drwgs. SPC. 00-CA-E-
CV 0002 01 Check and verify sieve, physical and chemical 10014 Certificates / P H R R
properties compliance with Project CAFC-00-ST- MLEG-00-ST- Certificate
requirements of existing natural soil or ZG-99ZO03 ZG-99ZS02 register List
imported borrow pit to be used under the
foundation of main items and general CAFC-00-ST-
backfilling area ZG-99ZO02

AFC Drwgs. SPC. 00-CA-E-


CV 0002 02 Check and verify sieve, physical and chemical 10014 Certificates / P H P R
properties compliance with Project CAFC-00-ST- MLEG-00-ST- Certificate
requirements of either suitable Site excavated ZG-99ZO03 ZG-99ZS02 register List
material or imported borrow pit suitable
material to be used as base and sub-base CAFC-00-ST-
course for roads and parking areas. ZG-99ZO02
-

AFC Drwgs. SPC. 00-CA-E-


CV 0002 03 Check and verify properties compliance with 10014 Certificates / P H P R
Project requirements of either suitable Site CAFC-00-ST- MLEG-00-ST- Certificate
available finishing/surfacing material or ZG-99ZO03 ZG-99ZS02 register List
imported borrow pit suitable material to be
used as areas final finishing/surfacing CAFC-00-ST-
ZG-99ZO02

ORGANIZATION CODE INVOLVEMENT CODE


CC – Construction Contractor TP1 – Third Party P – Perform/Submit W – Witness (minimum 20% inspection rate)
QC – QC Construction Contractor CL – Client S – Surveillance H – Hold Point (100% inspection rate)
R – Review M- Monitoring
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 12 / 26
Sonatrach Document ID: Status

EX-CO 00

ITP No. CV-0002 DISCIPLINE

Title: EARTHWORKS- FILL AND BASE MATERIAL FOR ROADS, CIVIL GENERAL
PARKING AREAS, PAVING SUBBASE, MAIN ITEM FOUNDATION BASE, Involvement
AREA FINISHING & SURFACING MATERIALS
Reference Acceptance Report GTP TP1 CL Notes
QC CODE Description Document Ref. Criteria Form
CC QC ARH SH-FCP
AFC Drwgs. SPC. 00-CA-E-
CV 0002 04 Check and verify mix, compliance with Project 10014 Certificates / P H P R
requirements of soil-cement mix to be used as CAFC-00-ST- MLEG-00-ST- Certificate
foundation for roads and parking areas. ZG-99ZO03 ZG-99ZS02 register List

CAFC-00-ST-
ZG-99ZO02

ORGANIZATION CODE INVOLVEMENT CODE


CC – Construction Contractor TP1 – Third Party P – Perform/Submit W – Witness (minimum 20% inspection rate)
QC – QC Construction Contractor CL – Client S – Surveillance H – Hold Point (100% inspection rate)
R – Review M- Monitoring
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 13 / 26
Sonatrach Document ID: Status

EX-CO 00

ITP No. CV-0003 DISCIPLINE


Title: ASPHALT CONCRETE, BITUMINOUS PRODUCTS AND CIVIL GENERAL
ASPHALT CONCRETE RELATED MATERIALS Involvement
Reference Acceptance Report GTP TP1 CL
Notes
QC CODE Description Document Ref. Criteria Form CC QC ARH SH-FCP

CV 0003 01 Check and verify compliance with Project AFC Drwgs. SPC. 00-CA-E-
Certificates / H P R
requirements of the material to be used for the 10015
Certificate
asphalt works, (Binder, surface course, surface CAFC-00-ST- MLEG-00-ST-
register List
treatment, Bituminous product for surface ZG-99ZO03 ZG-93ZR01
treatment)
CAFC-00-ST-
ZG-99ZO02

AFC Drwgs. SPC. 00-CA-E-


CV 0003 02 Check and verify compliance with Project 10015 Manufacturer P R R
requirements of traffic markings and striping, CAFC-00-ST- MLEG-00-ST- data
traffic signs, road guardrails and any other ZG-99ZO03 ZG-93ZR01
correlated material to be used with asphalt
concrete in the Project. CAFC-00-ST-
ZG-99ZO02

ORGANIZATION CODE INVOLVEMENT CODE


CC – Construction Contractor TP1 – Third Party P – Perform/Submit W – Witness (minimum 20% inspection rate)
QC – QC Construction Contractor CL – Client S – Surveillance H – Hold Point (100% inspection rate)
R – Review M- Monitoring
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 14 / 26
Sonatrach Document ID: Status

EX-CO 00

ITP No. CV-0201 DISCIPLINE

Title: EARTHWORKS (EXCAVATION & FILL) FOR ROADS CIVIL


AND GENERAL SITE/WELL SITE PREPARATION Involvement
Reference Acceptance Report GTP TP1 CL Notes
QC CODE Description Document Ref. Criteria Form
CC QC ARH SH-FCP
AFC Drwgs. CAFC-00-ST-
CV 0201 01 Preliminary check: ZG-99ZO03 Certificates / P W W
CAFC-00-ST- Certificate
Before commencement the filling activities, register List
ZG-99ZO03 CAFC-00-ST-
Check on materials for fill ZG-99ZO02
- Prior to backfilling ensure all CAFC-00-ST-
formwork is removed. ZG-99ZO02

- Company approval obtained for


construction works prior to
backfilling.
- Suitable backfill material selected;
check sub grade to 300mm from
grade and final two layers of
150mm are compacted

AFC Drwgs CAFC-00-ST-


CV 0201 02 In-situ density of compacted soils: ZG-99ZO03 Compaction H H W *Excel register to be
test certificate maintained by CC/QC for
Check for each layer the compaction in CAFC-00-ST- daily recording details of
accordance to the Project requirements ZG-99ZO03 CAFC-00-ST- Certificate density Test and items
ZG-99ZO02 excel register related traceability.
CAFC-00-ST- MDT.CV.CDQ.
ZG-99ZO02 0204*

ORGANIZATION CODE INVOLVEMENT CODE


CC – Construction Contractor TP1 – Third Party P – Perform/Submit W – Witness (minimum 20% inspection rate)
QC – QC Construction Contractor CL – Client S – Surveillance H – Hold Point (100% inspection rate)
R – Review M- Monitoring
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 15 / 26
Sonatrach Document ID: Status

EX-CO 00

ITP No. CV-0201 DISCIPLINE

Title: EARTHWORKS (EXCAVATION & FILL) FOR ROADS CIVIL


AND GENERAL SITE/WELL SITE PREPARATION Involvement
Reference Acceptance Report GTP TP1 CL Notes
QC CODE Description Document Ref. Criteria Form
CC QC ARH SH-FCP
AFC Drwgs. CAFC-00-ST-
CV 0201 03 Finishing inspection: ZG-99ZO03 MDT.CV.CDQ. P W W
CAFC-00-ST- 0230
Check completeness of surfaced areas
works:, i.e. vertical and horizontal levels, ZG-99ZO03 CAFC-00-ST-
slope, thickness, dimensions and surface ZG-99ZO02
finishing materials compliance with Project CAFC-00-ST-
requirements ZG-99ZO02

ORGANIZATION CODE INVOLVEMENT CODE


CC – Construction Contractor TP1 – Third Party P – Perform/Submit W – Witness (minimum 20% inspection rate)
QC – QC Construction Contractor CL – Client S – Surveillance H – Hold Point (100% inspection rate)
R – Review M- Monitoring
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 16 / 26
Sonatrach Document ID: Status

EX-CO 00

ITP No. CV-0202 DISCIPLINE

Title: ROADS AND PARKING AREAS WORKS (ASPHALT) CIVIL


Involvement
Reference Acceptance Report GTP TP1 CL Notes
QC CODE Description Document Ref. Criteria Form
CC QC ARH SH-FCP
AFC Drwgs. CAFC-ROA-ST-
CV 0202 01 Preliminary check: ZG-93ZO01 Certificates/ P W W
CAFC-ROA- Certificate
Before commencement the filling activities, register List
ST-ZG-93ZO01 CAFC-00-ST-
Check on materials for fill ZG-99ZO03
CAFC-00-ST-
ZG-99ZO03 CAFC-00-ST-
ZG-99ZO02
CAFC-00-ST-
ZG-99ZO02

AFC Drwgs. CAFC-ROA-ST-


CV 0202 02 In-situ density of compacted soils: ZG-93ZO01 Compaction H H H W *Excel register to be
test certificate maintained by CC/QC for
Check for each layer the compaction in CAFC-ROA- daily recording details of
accordance to the Project requirements ST-ZG-93ZO01 CAFC-00-ST- excel register density Test and items
ZG-99ZO03 MDT.CV.CDQ. related traceability.
CAFC-00-ST- 0204
ZG-99ZO03 CAFC-00-ST-
ZG-99ZO02
CAFC-00-ST-
ZG-99ZO02

AFC Drwgs. CAFC-ROA-ST-


CV 0202 03 On grade field inspection: MDT.CV.CDQ. P W W Check if CV-0003 were
ZG-93ZO01 0214 successfully completed
Check on before bituminous prime coat CAFC-ROA-
delivery/placement: formation grade status, ST-ZG-93ZO01 CAFC-00-ST- .
vertical and horizontal levels, slope and ZG-99ZO03
dimensions. CAFC-00-ST-
ZG-99ZO03 CAFC-00-ST-
ZG-99ZO02
CAFC-00-ST-
ZG-99ZO02

ORGANIZATION CODE INVOLVEMENT CODE


CC – Construction Contractor TP1 – Third Party P – Perform/Submit W – Witness (minimum 20% inspection rate)
QC – QC Construction Contractor CL – Client S – Surveillance H – Hold Point (100% inspection rate)
R – Review M- Monitoring
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 17 / 26
Sonatrach Document ID: Status

EX-CO 00

ITP No. CV-0202 DISCIPLINE

Title: ROADS AND PARKING AREAS WORKS (ASPHALT) CIVIL


Involvement
Reference Acceptance Report GTP TP1 CL Notes
QC CODE Description Document Ref. Criteria Form
CC QC ARH SH-FCP
AFC Drwgs. CAFC-ROA-ST-
CV 0202 04 Inspection during delivering bituminous Excel register P W P W  Only for sampling
ZG-93ZO01
prime coat and asphalt concrete: CAFC-ROA- MDT.CV.CDQ. *Excel register to be
Check the bituminous and asphalt concrete ST-ZG-93ZO01 CAFC-00-ST-
0218 * maintained by CC/QC for
quality during delivery ZG-99ZO03 daily recording details of
CAFC-00-ST- density Test and items
Note: i.e. asphalt concrete temperature, ZG-99ZO03 CAFC-00-ST- related traceability.
Project Tag/Item and taken specimens ZG-99ZO02
traceability code, etc. CAFC-00-ST-
ZG-99ZO02
AFC Drwgs. CAFC-ROA-ST-
CV 0202 05 After poured asphalt concrete report: ZG-93ZO01 Excel register P R Excel register to be
maintained by CC/QC for
Registration of data of poured asphalt CAFC-ROA- MDT.CV.CDQ.
daily recording and items
concrete ST-ZG-93ZO01 CAFC-00-ST- 0218
related traceability.
ZG-99ZO03
CAFC-00-ST-
ZG-99ZO03 CAFC-00-ST-
ZG-99ZO02
CAFC-00-ST-
ZG-99ZO02

AFC Drwgs. CAFC-ROA-ST-


CV 0202 06 Check & verify compliance between asphalt
ZG-93ZO01 Excel register P R P R *Excel register to be
concrete design requirements and core maintained by CC/QC for
specimens reached test results (certificate CAFC-ROA- MDT.CV.CDQ.
daily recording details of
test result), data registration ST-ZG-93ZO01 CAFC-00-ST- 0218
density Test and items
ZG-99ZO03
related traceability.
CAFC-00-ST-
ZG-99ZO03 CAFC-00-ST-
ZG-99ZO02
CAFC-00-ST-
ZG-99ZO02

ORGANIZATION CODE INVOLVEMENT CODE


CC – Construction Contractor TP1 – Third Party P – Perform/Submit W – Witness (minimum 20% inspection rate)
QC – QC Construction Contractor CL – Client S – Surveillance H – Hold Point (100% inspection rate)
R – Review M- Monitoring
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 18 / 26
Sonatrach Document ID: Status

EX-CO 00

ITP No. CV-0202 DISCIPLINE

Title: ROADS AND PARKING AREAS WORKS (ASPHALT) CIVIL


Involvement
Reference Acceptance Report GTP TP1 CL Notes
QC CODE Description Document Ref. Criteria Form
CC QC ARH SH-FCP
AFC Drwgs. CAFC-ROA-ST-
CV 0202 07 Finishing inspection: MDT.CV.CDQ. P W W
ZG-93ZO01 0208
Check completeness of asphalt concrete CAFC-ROA-
roads and parking areas works:, i.e. ST-ZG-93ZO01 CAFC-00-ST-
wearing course surface texture, vertical and ZG-99ZO03
horizontal levels, slope and dimensions CAFC-00-ST-
compliance with Project requirements. ZG-99ZO03 CAFC-00-ST-
ZG-99ZO02
CAFC-00-ST-
ZG-99ZO02

ORGANIZATION CODE INVOLVEMENT CODE


CC – Construction Contractor TP1 – Third Party P – Perform/Submit W – Witness (minimum 20% inspection rate)
QC – QC Construction Contractor CL – Client S – Surveillance H – Hold Point (100% inspection rate)
R – Review M- Monitoring
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 19 / 26
Sonatrach Document ID: Status

EX-CO 00

ITP No. CV-0201 DISCIPLINE

Title: STEELWORKS and FENCING CIVIL


Involvement
Reference Acceptance Report GTP TP1 CL Notes
QC CODE Description Document Ref. Criteria Form
CC QC ARH SH-FCP
AFC Drwgs. CAFC-00-ST-
CV 0201 08 Check materials received are in line with ZG-99ZO03 Certificates / P H W *refer to QCP
delivery, size, quantity, etc… CAFC-00-ST- Certificate WELDING
register List
Visually inspect material for any regularities / ZG-99ZO03 CAFC-00-ST-
damages during handling ZG-99ZO02
CAFC-00-ST-
Welding related activities* ZG-99ZO02

CAFC-00-ST-
CV 0201 09 Carry out 10% check on bolted connections S-99SO10 MDT.CV.CDQ. P W W
0230

AFC Dwrgs. CAFC-00-ST-


CV 0201 10 Inspect: ZG-99ZO01 MDT.CV.CDQ. P W
CAFC-00-ST- 0230
- Post spacing & height
ZG-99ZO01
- Chain link fastening
- Placements of struts & bracing
- Gates

ORGANIZATION CODE INVOLVEMENT CODE


CC – Construction Contractor TP1 – Third Party P – Perform/Submit W – Witness (minimum 20% inspection rate)
QC – QC Construction Contractor CL – Client S – Surveillance H – Hold Point (100% inspection rate)
R – Review M- Monitoring
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 20 / 26
Sonatrach Document ID: Status

EX-CO 00

ITP No. CV-0201 DISCIPLINE

Title: STEELWORKS and FENCING CIVIL


Involvement
Reference Acceptance Report GTP TP1 CL Notes
QC CODE Description Document Ref. Criteria Form
CC QC ARH SH-FCP
CAFC-00-SP- CAFC-00-SP-
CV 0201 11 Inspect coating/painting activities MP-00NG10 MP-00NG10 MDT.CV.CDQ. P H
0230
Final Inspection Final survey carried out
prior to acceptance CAFC-00-SP- CAFC-00-SP-
MP-00NG10 MP-00NG10

CAFC-00-SP- CAFC-00-SP-L-
L-00OO22 00OO22

ORGANIZATION CODE INVOLVEMENT CODE


CC – Construction Contractor TP1 – Third Party P – Perform/Submit W – Witness (minimum 20% inspection rate)
QC – QC Construction Contractor CL – Client S – Surveillance H – Hold Point (100% inspection rate)
R – Review M- Monitoring
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
21 / 26
EX-CO 00

INSPECTION REPORT REGARDING ESTABLISHED PROJECT BENCH MARKS

DRAWING/Specification No. & rev.

System description: Oily/ PAGE OF

COORDINATES ELEVATIONS
BENCH MARK No. RATING REMARKS
NORTH EAST FROM MEAN SEA LEVEL

NOTES INSPECTION NOTIFICATION REFERENCE

RFI No.

QC CONSTRUCTION CONTRACTOR CLIENT


NAME  NAME 

SIGNATURE SIGNATURE

Date Date

Form code: MDT.CV.CDQ.0016

This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
22 / 26
EX-CO 00

INSPECTION REPORT FORM FOR DENSITY/COMPACTION TEST


ROADS / GENERAL SITE PREPARATION / MAIN ITEMS

PAGE OF

COMPACTION TEST Log Book MDT CV CDQ 0204

Element / Compaction test certificate Compaction design


Tag Item Drawing n° Compaction test DATE RESULT RFI n°
position / layer n° requirements

C  NC 
C  NC 
C  NC 
C  NC 
C  NC 
C  NC 
C  NC 
C  NC 
C  NC 
C  NC 
C  NC 
C  NC 
C  NC 
C  NC 

NOTES INSPECTION NOTIFICATION REFERENCE


See enclosed certificate / report No.:
RFI No.

QC CONSTRUCTION CONTRACTOR TP1 CLIENT


NAME  NAME  NAME 

SIGNATURE SIGNATURE SIGNATURE

Date Date Date

Form code: MDT.CV.CDQ.0204

This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
23 / 26
EX-CO 00

FINISHING INSPECTION REPORT ON FINAL COURSE OF COMPLETED ASPHALT OR CONCRETE ROADS,


PARKING AREAS AND PAVING WORKS
PAGE OF
REFERENCE DWG. VERTICAL AND HORIZONTAL LEVELS
Tag - Item / Element LOCATION / COORDINATES/ SURFACE TEXTURE
No. Rev.
ELEVATION / SLOPE / DIMENSIONS

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

NOTES: INSPECTION NOTIFICATION REFERENCE

RFI No.

QC CONSTRUCTION CONTRACTOR CLIENT


NAME  NAME 

SIGNATURE SIGNATURE

Date Date

Form code: MDT.CV.CDQ.0208

This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
24 / 26
EX-CO 00

INSPECTION REPORT ON FORMATION LEVEL FOR: CONCRETE POURING FOR ROADS, PARKING
AREAS, PAVING, LEAN CONCRETE, FOUNDATION

PAGE OF

VERTICAL AND HORIZONTAL 1)POLY-ETHYLENE SHEET /GEOTEXTILE


REFERENCE DRAWING
LEVELS FABRIC
2)SLOPE/SHAPE
Tag - Item / Element 3)FORMWORK
LOCATION/
No. Rev. ELEVATION 4)REINFORCEMENT
COORDINATE
5)JOINTS
6)FORMATION GRADE/SUBGRADE STATUS

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

NOTES INSPECTION NOTIFICATION


REFERENCE

RFI No.

QC CONSTRUCTION CONTRACTOR TP1 CLIENT


NAME NAME  NAME 

SIGNATURE SIGNATURE SIGNATURE

Date Date Date

Form code: MDT.CV.CDQ.0214

This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of Sheets

Validity
Rev. 25 / 26
Sonatrach Document ID: Status

EX-CO 00

COLD Asphalt Concrete, Log Book MDT CV CDQ 0218

temperature C°

Result C/NC
WEARING
COURSE

Minimum
BINDER

Ambient
Laboratory
Daily Delivery Casting Core
Road Tag identification Portion Core Location Certificate RFI n°
note date Specimen n°
number

                     

                       

                       

                       

                       

                       

                       

                       

                       

                       

                       

Form code: MDT.CV.CDQ.0218

This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Eni E&P Document ID : Revision Index Sheet of
Sheets
Validity
Rev.
Sonatrach Document ID: Status
26 / 26
EX-CO 00

FINAL INSPECTION REPORT OF FINISHED SURFACED AREAS

PAGE OF
VERTICAL /HORIZONTAL LEVELS /
REFERENCE DWG. SURFACING STATUS
DIMENSIONS

LOCATION/
Tag - Item / Element GRAVEL
ELEVATION/ WIDTH / LENGTH / SLOPE
No. Rev GRASS
SOIL

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

C NC  C NC 

NOTES: INSPECTION NOTIFICATION REFERENCE

RFI No.

QC CONSTRUCTION CONTRACTOR CLIENT

NAME NAME

SIGNATURE SIGNATURE

Date Date

Form code: MDT.CV.CDQ.0230