Saic F 2008
Saic F 2008
Saic F 2008
00 31-Dec-18
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A Y/N
No. DATE
A Equipment Documentation
All construction and pre-commissioning activities for the project shall G.I.-2.710
A4
have been completed. Para. 4.1.1.2
Installed Relief Valves were verified and the corresponding Form G.I.-2.710-05,
B3
3099A signed. (Ref: SAES-J-600, Sec. 10) Item 6 e
Paint and/or tag all relief valves, car sealed valves and safety G.I.-2.710-05,
B4
equipment per Aramco Standards. Item 6 g
Pressure gages are installed with block and bleed valves. (The SAES-J-100,
B6
bleed valve shall be plugged.) Para. 6.5.4
Temperature Gages installed are of the same range as shown in the P&ID #
B7
P&ID. ____________
GI-2.710-05,
B9 Furnace dry-out is complete.
Item 5.5 h
GI-2.710-05,
B10 Couple fans to drivers after successful run-in of driver.
Item 5.5 i
Internal cleanliness and vessel closure has been performed. Note: 32-SAMSS-029,
B11
Inspection Checklist for Heater box closure, SAIC-F-2009, is signed. Para. 17.1.20
All new fire protection equipment, systems and facilities are GI-2.710-05,
B12
commissioned. Item 6 k
C Heater Coils
G.I.-2.710-05,
C1 Perform hydrostatic test per SAES-A-004.
Item 5.5 a
All skin thermocouples on the heater coils are properly installed and G.I.-2.710-05,
C4
functional. Item 5.5 e
D Structural Items:
All bolted connections for ducts, plenums, and header boxes are 32-SAMSS-029,
D6
provided with suitable gaskets to prevent air or flue gas leakage. Para. 12.2.12
Header boxes containing plug fittings are provided with threaded 32-SAMSS-029,
D7
couplings for drains and smothering steam connections. Para. 12.3.1.6
32-SAMSS-029,
D8 Access doors are bolted and are airtight.
Para. 12.3.2.7
G.I.-2.710-05,
D11 Mechanical operation of soot blowers and dampers was verified.
Item 5.5 d
Heater coil vents, drains, sample, instrument, and chemical cleaning 32-SAMSS-029,
D12
connections are accessible from heater platforms or grade. Para. 12.4.14
Insulation required for noise attenuation and weatherproofing for air 32-SAMSS-029,
D13
ducts and windboxes are installed. Para. 13.1.8
E Associated Piping/Trim
A 2" dia. block valve is installed at top and bottom connection of the
SAES-J-100,
E6 standpipe to the vessel. (SA Library Drawing DC-950045.) Type of
Par. 7.1.1
block valve installed is in conformance with project drawing or P&ID
Vent valve with plug installed on top blind flange & drain valve on SAES-J-100,
E7
bottom blind flange of standpipe. (SA Library Drawing DC-950045.) Par. 7.1.3
Atmospheric drain and vent valves shall be provided with a plug or SAES-L-108,
E10
blind on the discharge side. Para. 7.7
GI-2.710-5,
E11 Pressure test of field installed piping (ie:fuel gas line) are complete.
Item 4a
GI-2.710-5,
E12 All nuts and bolts of flange connections are fully engaged.
Item 1.j.
Flange joints for piping Class ANSI 600# and above were verified to
be tightened using the applicable Torque procedure and the GI-2.710-5,
E13
applicable gasket material listed in Items D15 & D16 below. Item 1.j.
(NOTE: Refer to SAIC-L-2014 & SATR-L-2001)
F Painting Works
Identification of all equipment are provided and are legible from 50 GI-2.710-05,
F1
feet away for process equipment. Item 1a
GI-2.710-05,
G1 All fire proofing are complete.
Item 1c
H Welding works
All welds are free from cracks, overlaps, and unacceptable profile SAES-M-001,
H1
as shown in AWS DI.1, Figure 5.4. SAIC-M-2012 was accepted. Para. 3.2
The edges of all tightly contacting surfaces are completely seal SAES-M-001,
H2
welded. Para. 7.1.13.3
REMARKS:
Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date: