Observed Behaviors of A Long and Deep Excavation Constructed by Cut-and-Cover Technique in Shanghai Soft Clay
Observed Behaviors of A Long and Deep Excavation Constructed by Cut-and-Cover Technique in Shanghai Soft Clay
Abstract: A 16–18 m deep excavation for a metro station with in-plane dimensions of approximately 20 m wide by 290 m long was
constructed by using the cut-and-cover technique in soft clay in the Shanghai metropolitan area, in which many high-rise buildings and
utilities exist. To investigate the performance of this deep excavation and the associated effect on the adjacent buildings and utility pipelines,
a long-term comprehensive instrumentation program was conducted during construction. Field observations included deflections of
diaphragm walls, vertical movements at wall tops, ground settlements, and settlements of surrounding buildings and utilities. Analyses
of field data indicated that overexcavation (i.e., removing more soil than designed) and a long construction duration caused the diaphragm
walls to develop substantial deflections. The base and middle floor slabs played dominant roles in suppressing postexcavation wall deflections
and ground settlements. This excavation in general exhibited different behaviors than other excavation projects because of its relatively long
shape. Behaviors of deep excavations in Shanghai soft clay are affected not only by construction duration (i.e., time effects), but also by their
geometries (i.e., space effects). This project serves as a special case study and provides insights into the design and construction of a long and
deep excavation that uses the cut-and-cover technique in soft soils and in a metropolitan environment. DOI: 10.1061/(ASCE)GT.1943-5606
.0000553. © 2012 American Society of Civil Engineers.
CE Database subject headings: Excavation; Soft soils; Clays; Measurement; Time factors; China.
Author keywords: Long and deep excavation; Soft clay; Field measurement; Time effects; Length effects; Postexcavation.
Introduction Hashash et al. 2008; Tan and Li 2011). However, few studies
documented the effects of overexcavation (i.e., removing more
Construction of underground parking garages, deep basements, and soil than designed) on retaining wall deflections and ground
underground transportation systems in urban areas calls for exca- settlements.
vations supported by retaining structures. In a congested urban Two categories of methods commonly used to predict retaining
environment where space is limited, the movements of retaining wall deflections and ground settlements and to evaluate damage
walls and the ground must be controlled within acceptable levels. potentials in adjacent buildings due to excavation are (1) analytical
Otherwise, adjacent structures or facilities may be damaged and studies or numerical analyses (e.g., Finno and Harahap 1991;
loss of lives may occur. Therefore, field monitoring of the perfor- Hashash 1992; Whittle et al. 1993; Hashash and Whittle 1996,
mance of a deep excavation that can provide immediate feedback to 2002; Finno and Calvello 2005; Finno et al. 2005; Son and Cording
engineers is necessary to ensure the safety of the project. Relevant 2005; Hashash et al. 2006; Osouli et al. 2010) and (2) empirical or
field data provide a good case history to calibrate and verify semiempirical methods (e.g., Peck 1969; Mana and Clough 1981;
numerical tools and facilitate a thorough understanding of the gen- Clough and O’Rourke 1990; Ou et al. 1993; Hsieh and Ou 1998;
eral behaviors of deep excavations. Since the publication of Peck Long 2001; Moormann 2004; Roboski and Finno 2006; Kung et al.
(1969), many researchers and engineers have contributed a huge 2007; Hashash et al. 2008; Schuster et al. 2009). Compared with
amount of field data to the knowledge of performance of excava- analytical studies or numerical analyses, empirical and semiempir-
tions and adjacent facilities (e.g., O’Rourke et al. 1976; Boscardin ical methods provide probably less accurate yet more straightfor-
et al. 1978; O’Rourke 1981; Finno et al. 1989; Ou et al. 1998; ward estimations. Thus, empirical and semiempirical methods are
Finno and Bryson 2002; Finno and Roboski 2005; Liu et al. appropriate approaches for the initial estimation of excavation
2005; O’Rourke and McGinn 2006; Blackburn and Finno 2007; performance and to validate numerical analysis results. Because
empirical and semiempirical methods are established from field
1
Assistant Professor, Dept. of Geotechnical Engineering, Tongji Univ., measurements, a large volume of comprehensive and detailed
1239 Siping Rd., Shanghai 200092, P.R. China (corresponding author). project data is usually required.
E-mail: tanyong21th@tongji.edu.cn Before the advent of the three-dimensional (3D) numerical tech-
2
Senior Engineer, China Railway Er-yuan Engineering Group Co., Ltd., nique, excavation was commonly treated as a plane-strain problem
Floor 24, Haili Building, 88 Dapu Rd., Shanghai 200023, P.R. China. in design and the effect of excavation length in the longitudinal
E-mail: bb951245@hotmail.com direction was disregarded. Through field measurements or finite-
Note. This manuscript was submitted on March 13, 2010; approved on
element (FE) analyses, some researchers (Ou and Chiou 1993;
April 12, 2011; published online on April 14, 2011. Discussion period open
until June 1, 2012; separate discussions must be submitted for individual Wong and Patron 1993; Lee et al. 1998; Ou and Shiau 1998;
papers. This paper is part of the Journal of Geotechnical and Geoenvir- Ou et al. 2000; Blackburn and Finno 2007) found that arching
onmental Engineering, Vol. 138, No. 1, January 1, 2012. ©ASCE, ISSN effects cause wall deflections at the excavation corners to be
1090-0241/2012/1-69–88/$25.00. significantly smaller than those at the central sections, where
3D simulations. New Village between South Pudong Road and North Nanquan
In this study, the performance of a long and deep excavation Road, a six-story concrete building along North Nanquan Road,
constructed by the cut-and-cover technique in soft clay in the met- two one-story brick structures for gas-pressure control stations,
ropolitan area of Shanghai, China, was investigated by dense arrays and a two-story brick structure. These buildings are all supported
of measurements on diaphragm wall deflections, vertical move- by shallow foundations. On the south side of the excavation pit are
ments at wall top, ground settlements, and settlements of buildings four heavy high-rise concrete structures (i.e., 38-story Xinmei Twin
and utility pipelines in the proximity. This long excavation was Tower Building, 24-story Neiwailian Building, 32-story Liangyou
compared with some cases in Shanghai with different excavation Building, and 29-story Lekai Building). These four high-rise build-
lengths to investigate the potential length effects on wall deflection ings rest on deep foundations, which are basically auger cast-
and ground settlements. in-place (ACIP) piles with diameters of 600–800 mm and lengths
of 40–45 m below the ground surface (BGS). The distances be-
tween the buildings and the excavation pit varied between 10 and
Project Description 40 m (see Fig. 1). All the buildings are relatively new and no more
than 20 years old. Other than the buildings, the excavation is also
As the largest city and the commercial and financial center of surrounded by many utility pipelines, including iron water pipe-
China, Shanghai is located at the estuary of Yangtze River on lines, iron power cable pipelines, and iron communication cable
China’s east coast. The city sits on the flat alluvial plain known pipelines. They are buried at depths of 0.7–1.5 m BGS.
as Yangtze River Delta, which features high groundwater tables To protect the city environment from potentially adverse or even
and thick soft clay in the upper layers. The investigated excavation detrimental effects caused by excavation, local metro construction
standard SZ-08-2000 (Shanghai Municipal Engineering Authority unloading stress levels, the soil samples deformed drastically
2000) was enacted by the Shanghai Municipal Engineering Author- and then failed quickly.
ity (SMEA), in which different protection grades are specified for
metro excavations in Shanghai (see Table 1). According to this
code, protection Grade 2 was designated for construction of this Construction Procedures
deep excavation, i.e., the maximum excavation-induced wall
The investigated excavation consisted of four sections: Section 1 =
deflection, δ hm , should be no more than 54 mm, and the maximum
west shaft, Section 2 = standard segment, Section 3 = standard seg-
ground settlement, δ vm , no more than 36 mm. In addition, the maxi- ment, and Section 4 = east shaft. Tables 2 and 3 summarize the
mum allowable settlement of 60 mm was specified for concrete construction activities at Sections 1–4. The site work began with
structures, 40 mm for brick masonry structures, and 20 mm for the construction of concrete diaphragm walls and compaction-
utility pipelines. These criteria were defined on the basis that grouting the soils within 3 m below the final excavation level; these
settlements should not cause apparently cracking to buildings or activities were conducted between March 24 and May 16, 2007.
severe damage to utilities, which have occurred in excavation In excavation practice within the Shanghai area, the quality of
experiences in Shanghai in the past decades. compaction-grouting is usually difficult to control because of the
techniques and complex soil condition. In most cases, the reinforce-
ment layers below the excavation bases just functioned as curtains
Soil Conditions for cutting off the seepage of waterflow but did not constrain lateral
wall movements. Thereafter, excavation was initiated and strutting
Before the excavation, soil conditions at the site were explored by systems were propped as soils were removed. Excavation started
a series of field exploration programs (e.g., boreholes, standard from Section 4 on May 26, 2007 and ended at Section 3 on April
penetration test (SPT) borings, cone penetration test (CPT) sound- 26, 2008. The strutting systems consisted of steel pipes 609 mm in
ings, and dilatometer (DMT) soundings). In general, the site was diameter (external) and 16 mm in wall thickness, which were hori-
characterized by a thin layer of fill (Layer I) in the upper 2 m BGS, zontally spaced at 2–3 m along the longitudinal direction of the
followed by a layer of firm silty clay (Layer II) to a depth of excavation. All the steel pipe struts were preloaded with approxi-
5 m BGS. The next layer was very soft to soft muddy clay inter- mately 50% of their design strut load before propping. To allow
bedded with a thin layer of sandy silt (Layer III) extending to maximum working space inside the excavation, diagonal strutting
a depth of 17 m BGS, underlain by soft-to-stiff clay and silty was used at the corners. The vertical distance from the centers of
clay (Layer IV) to a depth of 28 m BGS. Beneath Layer IV, the the pipe struts to the nearest excavation surface directly below was
field exploration encountered dense-to-very-dense silty fine sand approximately 0.5 m. Finally, metro-station structures were con-
(Layer V) until the termination depth of 70 m BGS. The ob- structed in the order of base slabs, middle slabs, and roof slabs,
served long-term groundwater table at the site was approximately accompanied by the removal of the propping struts. The Young’s
1.0 m BGS. moduli, E, of the concrete and steel used at this site were 3 ×
The soil properties along the depth were characterized by a 107 kPa and 2 × 108 kPa, respectively.
series of laboratory tests and in situ tests. The laboratory tests in- Fig. 3 presents the typical cross section of the standard segments
cluded oedometer tests (confined compression tests), triaxial tests, (Sections 2 and 3). The excavation depths were 18 m at Sections 1
and unconfined compression tests. The effective cohesion, c0 , and and 4 and 16 m at Sections 2 and 3. The depths of diaphragm walls
friction angle, ϕ0 , were obtained from consolidated undrained were 33.0 m at Section 1, 33.6 m at Sections 2 and 3, and 31.2 m at
(CU) triaxial tests. The coefficient of compressibility, avð0:1–0:2Þ , Section 4. At the two end shafts (Sections 1 and 4), the excavation
and constrained modulus, E0:1–0:2 , were defined by oedometer tests was propped by six levels of steel pipe struts. At Sections 2 and 3,
at stress ranges of 100–200 kPa. The in situ vane shear test results the excavation was originally designed with five levels of steel
showed that the soft soils in the upper 25 m BGS exhibited medium pipes. However, to reduce the project cost and the construction
sensitivity, St , of approximately 2.5–5.0. This implied that the duration, the contractor did not follow the original design but
strength and stiffness of the soft clay would degrade substantially adopted a new excavation scheme in which the pit was propped by
once it was subjected to disturbances arising from construction only four levels of struts. This move caused overexcavation (i.e.,
removing more soil than designed) at each level for the central stan-
activities. The soil profiles along with the measured soil properties
dard segments.
are presented in Fig. 2. Both laboratory and field testing results
indicated that the soft soils in the upper layers feature relatively
high water content, high void ratio, high compressibility, and Instrumentation
low strength. Through a series of triaxial unloading creep tests, Fu
et al. (2009) reported that Shanghai clay exhibits apparent creep To monitor the performance of this excavation and ensure the safety
behavior during the process of unloading. At relatively high of the project, a long-term comprehensive field instrumentation
program was conducted. The observed excavation performance Observed Excavation Behaviors
included the deflections of diaphragm walls, vertical movements
at wall tops, and ground settlements behind the diaphragm walls. Lateral Movements of Diaphragm Walls
Excavation may cause the buildings and utility pipelines nearby to
settle uniformly or non-uniformly. Large settlements, especially Fig. 4 presents the development of diaphragm wall deflections
differential settlements, may induce serious structural damages to during construction. The field data show that at each section,
the measured wall deflections at the north side of the excavation
these buildings and utility pipelines and even cause the loss of lives.
exhibited similar developing patterns as those observed at the south
Therefore, the settlements of buildings and utilities in the proximity
side, which were propped by the same struts. As the excavation
were also surveyed throughout the construction.
proceeded to lower levels, the diaphragm walls began to develop
Fig. 1 shows the instrumentation layout used for monitoring the
deep-seated movements (bulging profiles) toward the excavation
performance of the excavation and the adjacent buildings. The de-
side. At Section 4, the diaphragm walls at B3 and B25 developed
flections of the diaphragm walls were monitored by 26 inclinometer
deflections of approximately 10 mm between Stages 5(a) and 6(a),
tubes (designated as B1 to B26) that were affixed to the steel which contrasted sharply with those measured at B2 and B4. This
reinforcement cages and later covered by concrete. The lengths of discrepancy might be because at B3 and B25 the struts at Level 4
these inclinometer tubes were approximately 17–30 m. To monitor were not promptly or properly propped. The continuous develop-
the ground settlements behind the diaphragm walls, 13 critical sec- ment of deep-seated deflections did not stop even when excavation
tions (designated as JS1-1 to JS1-5 through JS13-1 to JS13-5) were reached the final level. During the subsequent construction of the
selected for instrumentation. The settlement points were 5–25 m base slabs, middle slabs, and roof slabs, the diaphragm walls de-
away from the diaphragm walls and spaced 5 m apart. Ground set- veloped substantial postexcavation deflections toward the excava-
tlements were surveyed by level instruments. To address the safety tion side. The postexcavation wall deflections between Stages 8 and
concerns regarding the adjacent buildings and utility pipelines, their 11(a) were approximately 7.3 mm (50% of the measured final
settlements were also surveyed during and after excavation. deflection, δ hf ) at B2, 10.8 mm (35% δ hf ) at B3, and 7.8 mm
Unfortunately, the inclinometer tubes at locations B1, B6, B9, (28% δ hf ) at B25. According to the construction log in Table 2, the
B16, B22, B24, and B26, and the settlement points at JS2-3, JS5-1, contractor began to remove the struts at Level 6 just 6 days after the
JS5-2, JS6-1, JS6-2, JS10-2, JS11-1, and JS13-5 were damaged cast of the base slabs—much earlier than the concrete slabs could
during construction. Therefore, their measurements were not avail- gain sufficient strength (a curing time of 14 days is required for
able for this study. concrete to reach 70–80% of its design strength). These significant
postexcavation wall deflections may result from insufficient con- the roof slabs were constructed. Further examination showed that
crete curing time. As the base slabs gained strength over time most of the postexcavation wall deflections occurred before the
and the middle floor slabs were cast, the diaphragm wall move- completion of the middle slabs. Thereafter, the diaphragm walls
ments decreased gradually and almost stopped completely after developed very limited additional wall deflections. The diaphragm
Fig. 4. Lateral deflections of wall at the north and the south sides of the excavation
Depth (m)
Depth (m)
between the construction of the base slabs and the construction of
8 8 531 kN/m the middle slabs; afterwards, the diaphragm walls hardly developed
814 kN/m additional movements.
10 10 The deflection rate of a diaphragm wall is another critical index
1064 kN/m
Downloaded from ascelibrary.org by WASHINGTON UNIV IN ST LOUIS on 08/05/13. Copyright ASCE. For personal use only; all rights reserved.
50 50
Remove struts
Middle slabs
constructed
Middle slabs
Roof slabs
constructed
Section 4 Section 1
constructed
45
Remove struts
constructed
45
Base slabs
constructed
Base slabs
at level 6
to final level
40
to final level
40
at level 6
Excavate
Excavate
35 35
30 30
δ h (mm)
25 25
Excavation
B2
to level 2
20 20
15 B3
15
10 B4 10 B14
5 B25 5 B15
0 0
6-13-2007
6-23-2007
7-13-2007
7-23-2007
8-12-2007
8-22-2007
9-11-2007
9-21-2007
6-3-2007
7-3-2007
8-2-2007
9-1-2007
11-14-2007
11-24-2007
12-14-2007
12-24-2007
12-4-2007
1-13-2008
1-23-2008
2-12-2008
2-22-2008
1-3-2008
2-2-2008
3-3-2008
50 50
45 Section 2 B10 45 Section 3
constructed
Roof slabs
40 B11 40
35 B12 35
30
δ h (mm)
30
Middle slabs
B13
constructed
25 25
B16-1 B7
20 20
constructed
Base slabs
B17
to final level
B8
to final level
constructed
15
Base slabs
15
Excavate
Excavate
10 B18 B20
10
5 B19 B21
5
0
0
12-15-2007
12-25-2007
1-14-2008
1-24-2008
2-13-2008
2-23-2008
3-14-2008
3-24-2008
4-13-2008
1-4-2008
2-3-2008
3-4-2008
4-3-2008
3-22-2008
4-11-2008
4-21-2008
5-11-2008
5-21-2008
5-31-2008
6-10-2008
6-20-2008
6-30-2008
7-10-2008
7-20-2008
4-1-2008
5-1-2008
Fig. 6. Development of the measured maximum wall deflections with time during construction
and 3, wall deflection rates during excavation were much larger 0:08%H when H was less than 10 m; it then fell between δ h ¼
than those at Sections 1 and 4. As noted previously, overexcavation 0:08%H and δ h ¼ 0:13%H when H was equal to 12 m. Until H
resulted in greater unloading stress levels and caused the soft clay reached 12 m, δ h at the overexcavated sections followed the same
to creep. However, because the contractor managed to finish exca- developing pattern as that at the normally excavated sections. How-
vation as soon as possible, the magnitudes of the wall deflections ever, δ h at the overexcavated sections showed an abrupt increase
during excavation at Sections 2 and 3 were still comparable to those when H reached 16 m. Except for one scattering point, most of the
at Section 1 and those of B3 and B25 at Section 4. The deflection measured δ h lay between δ h ¼ 0:13%H and δh ¼ 0:23%H when
rates were greatly reduced after the base slabs and middle slabs H ¼ 16 m. This phenomenon indicates that in this project, overex-
were poured. Similar to the observations at Sections 1 and 4, the cavation in the upper 12 m BGS hardly imposed substantial effects
diaphragm walls at Section 3 did not developed apparent deflec- on δ h , while it affected δ h significantly when H was deeper than
tions following the casting of the middle slabs. The preceding 12 m BGS. Therefore, overexcavation at greater depths should
analyses indicate that to reduce diaphragm wall deflections induced be avoided.
by a cut-and-cover excavation in sensitive and creep Shanghai soft On the basis of case histories worldwide, some empirical rela-
clay, (1) excavation should be finished within a short time; (2) base tionships between δ h and H have been developed. The comparisons
slabs should be constructed right after excavation and middle slabs in Fig. 7 indicated that the measured δ h at this site was significantly
Fig. 7. Relationship between the maximum wall deflections and excavation depths
Hm (m)
Hm (m)
B3 On the basis of the field data collected from eight case histories,
B4
B14 Ou et al. (1993) found that the ratio of H m =H is approximately
10 10 B15 equal to 1.0 for excavations in Taipei soft clay, where H m = location
-6 B25
H where the maximum wall deflection occurs; and H = excavation
=
Downloaded from ascelibrary.org by WASHINGTON UNIV IN ST LOUIS on 08/05/13. Copyright ASCE. For personal use only; all rights reserved.
B12
Hm B13 deeper portions of diaphragm walls would increase significantly
B16-1 (refer to Fig. 5). As a result, the chance that δ h occurred below
10 10 B17
-6 B18 the excavation surface would be increased.
H B19
=
Hm B20 Three-Dimensional Effects on the Maximum Wall
5 5
B21
Deflections
0 0 The dense arrangement of inclinometer casings at this project site
0 2 4 6 8 10 12 14 16 18 20 enabled the investigation on the effects of 3D geometry shape on
H (m) wall deflections. Fig. 9 presents the relationships between the nor-
malized maximum wall deflections, δ hm =H e , and the distance ratio,
Fig. 8. Relationship between the location of maximum wall deflections
d h =L, where δ hm = measured maximum wall deflection at the com-
and excavation depths
pletion of excavation to the final level; H e = final excavation depth;
d h = horizontal distance between an inclinometer casing and the
smaller than those reported by Peck (1969) for excavations in soft leftmost point of the excavation; and L = total length of the exca-
clay, by Clough and O’Rourke (1990) for excavations in stiff clay, vation along the longitudinal direction. To further examine the
and by Kung et al. (2007) for excavations in soft-to-medium clay, geometry effects on wall deflections in Shanghai soft clay, the
although the measured δh was close to Hashash et al. (2008) for reported data from four metro-station excavations (Yishan Road,
This study: L = 290 m, D = 31.2 ~ 33.6 m, W = 20 m, He = 16 ~ 18 m, L/W = 14.5, D/He = 1.7 ~ 2.1, L/He = 16.1 ~ 18.1;
Yishan Road: L = 335 m, D = 28 m, W = 17.3 m, He = 15.5 m, L/W = 19.4, D/He = 1.8, L/He = 21.6;
South Pudong Road: L = 169 m, D = 38 m, W = 22.8 m, He = 20.6 m, L/W = 7.4, D/He = 1.8, L/He = 8.2;
Pudian Road: L = 194 m, D = 26.5 m, W = 20.4 m, He = 16.5 m, L/W = 9.5, D/He = 1.6, L/He = 11.8;
Yanchang Road: L = 226 m, D = 27 m, W = 18.1 m, He = 15.2 m, L/W = 12.5, D/He = 1.8, L/He = 14.9;
L - Length of excavation in the longitudial direction;
D - Depth of diaphragm wall;
W - Width of central standard segment in the traverse direction;
He - Final excavation depth.
Fig. 9. Relationship between the normalized maximum wall deflection and the distance ratio
observed from the other four metro excavations, but the magnitude for the Yishan Road Station, all the metro excavations and build-
of δ hm =H e was smaller. Usually, the excavation-induced wall de- ing basement excavations were constructed by the cut-and-cover
flections are affected by factors such as the geometric shape of a method with multipropped concrete diaphragm walls. However, the
pit, wall embedment ratio, type of retaining wall, type of propping aspect ratios of length over width, AR, for the metro excavations
system, construction duration and length of unpropped wall expo- were much larger than those of the basement excavations. For the
sure, construction method, soil condition, and construction quality. metro excavations, AR ranged from 7.4–19.4, much larger than
To make the cases comparable, these factors were checked one 1.0–2.0 for those basement excavations. Fig. 10 shows that most
by one. The detailed geometric information and wall embedment building excavation data fell within the boundaries proposed by
ratio, D=H e , of each case are listed in Fig. 9, and they are reason- Mana and Clough (1981), although most of the metro excavation
data were near or below the lower boundary. This comparison dem-
ably close. All of the five metro excavations were retained by
onstrates the previous finding, i.e., a long and narrow multipropped
600–800 mm thick stiff concrete diaphragm walls propped by
excavation supported by rigid diaphragm walls is strongly capable
609-mm-diameter steel pipes. It is common practice in the excava-
of suppressing wall deflections during excavation.
tions of Shanghai metro to remove soils by 2–3 m with propping
systems, hence the wall exposure lengths were very similar in all Effects of System Stiffness on the Maximum Wall
cases. For the construction method, only Yishan Road was con- Deflections
structed by the top-down method, and the rest were constructed
Fig. 11 plots the normalized maximum wall deflections, δ hm =H e ,
by the cut-and-cover technique. Among the five cases, two are
and the normalized retaining system stiffness, EI=ðγw h4 Þ at this
located in the Puxi area (Yishan Road and Yanchang Road), where
site, in which EI=ðγw h4 Þ was defined by Clough et al. (1989).
the soil conditions are different from that of Pudong area. Puxi The six metro-station excavations reported by Wang et al. (2005)
features soft clay in upper 40–45 m BGS followed by dense sand and the 92 building excavations of Xu (2007) in Shanghai were also
layers, and Pudong is characterized by soft clay in upper 25–30 m included in this figure for comparison. Similar to Fig. 10, most
BGS, underlain by dense sand layers. However, when comparing of the observed δ hm =H e from the building excavations fell within
the cases of similar soil conditions, the measured δ hm =H e at Yishan the ranges proposed by Clough et al. (1989), although most of the
Road was much smaller than that of the Yanchang Road, and the observed δ hm =H e from the metro excavations was below the curve
measured δ hm =H e at Shangcheng Road (this case) was smaller of corresponding FOS of Clough et al. (1989) because of the afore-
than those of the South Pudong and Pudian roads. The excavation mentioned excavation geometry effects. As reported in literature
lengths of Yishan Road and Shangcheng Road (this case) were (e.g., Long 2001; Moormann 2004), an increase in system stiffness
exceptionally long. On the basis of the aforementioned consider- only imposes limited effects on reducing the normalized wall
ations, the significantly smaller δhm =H e measured in this study deflection.
may result from its long and narrow geometry. This can be justified
in that a long and narrow multipropped excavation supported by Vertical Movements at Wall Top
a concrete diaphragm wall is strongly capable of suppressing wall Substantial differential settlements of diaphragm walls could lead
deflections along the longitudinal direction during excavation. to the wracking of the entire supporting system. Therefore, it is
3.0
Section 1 (this study)
Sections 2 and 3 (this study)
2.5
Section 4 (this study)
Yishan Road Station
2.0 South Xizang Road Station
δ hm/He (%)
0.0
0.0 0.5 1.0 1.5 2.0 2.5 3.0
FOS
Fig. 10. Normalized maximum wall deflection versus FOS against basal heave
FOS
Sections 2 and 3 (this study)
FOS
Section 4 (this study)
FO
1.6
= 1.
= 1.
Yishan Road Station
S=
0
1
1.4 South Xizang Road Station
1 .4
South Pudong Road Station
δ hm/He (%)
1.2
Pudongdadao Station
1.0 Pudian Road Station
FO Yanchang Road Station
0.8 S=
2.0 Xu (2007)
0.6
FO
0.4 S=
3.0
Downloaded from ascelibrary.org by WASHINGTON UNIV IN ST LOUIS on 08/05/13. Copyright ASCE. For personal use only; all rights reserved.
0.2
0.0
10 100 1000 10000
System stiffness, EI/γ wh4
Fig. 11. Normalized maximum wall deflection versus normalized system stiffness
22
20 Section 1 B14
Vertical movement at wall top
18
Stage 10(a)
16 B15
Stage 11(a)
14
Stage 9(a)
Stage 7(a)
12 B16
Stage 6(a)
Stage 4(a)
Stage 5(a)
10
Stage 8
(mm)
Stage 2(a)
8
Stage 3(a)
6
4
2
0
-2 Date (mm/dd/year)
-4
12-31-2007
11-1-2007
12-1-2007
1-30-2008
2-29-2008
3-30-2008
4-29-2008
5-29-2008
6-28-2008
7-28-2008
22
20 Section 2
Vertical movement at wall top
B10
18
Stage 6
Stage 5(a)
14 Stages 9(a)
B12
12
(mm)
10 B13
8 B16-1
6
4 B17
2 Stage 7(a) B18
0
-2 Date (mm/dd/year) B19
Stage 3(a)
-4
12-31-2007
11-1-2007
12-1-2007
1-30-2008
2-29-2008
3-30-2008
4-29-2008
5-29-2008
6-28-2008
7-28-2008
22
20 B7 Section 3
Vertical movement at wall top
Stage 6
18
16 B8
14 B9
Stage 5(a)
12
Stage 3(a)
Stage 4(a)
B20
(mm)
10
Stage 2(a)
8 B21
Stage 8(a)
6
Stage 7(a)
4 B22
2
0
-2 Date (mm/dd/year)
-4
12-31-2007
11-1-2007
12-1-2007
1-30-2008
2-29-2008
3-30-2008
4-29-2008
5-29-2008
6-28-2008
7-28-2008
Fig. 12. Development of the vertical movements at wall top during construction
additional rebound of basal soils. At Section 3, exceptionally large along JS6-3 to JS6-5, JS7-1 to JS7-5, and JS8-1 to JS8-5 during
wall heaves occurred with a magnitude twice the wall heaves the construction of Section 1. During excavation, the measured
at Section 2 and three times the wall heaves at Section 1. Other ground settlements at these sections showed development patterns
than overexcavation, the excavation geometry and construction similar to those observed at JS1-1 to JS1-5 and JS2-1 to JS2-2.
sequence may contribute to this. When Section 3 was excavated, As the cast base slabs gained strength over time, the ground settle-
a wide-ranged stress field had been induced because of the extraor- ments started to decrease and completely stopped on February 9,
dinary length of the excavation. Therefore, soils were mobilized at 2008. Fig. 14 also shows that although excavation of Section 2 was
a large scale and tried to move toward those boundaries with weak executed around the same time, it did not impose any apparent
restraints (i.e., Section 3 being excavated). Following the cast of influences on the settling rates of the ground around Section 1.
Fig. 15 presents the development of ground settlements at JS5-3
concrete base slabs after the excavation, the wall heaves continued
to JS5-5 and JS9-1 to JS9-5 during the construction of Sections 2
to increase with time until the construction of the middle slabs. The
and 3. Contrary to the observations at JS5-3 to JS5-5 and those in
maximum wall heaves were approximately 5–7 mm at Section 1,
Figs. 13 and 14, even after the completion of the roof slabs, the
6–12 mm at Section 2, and 10–21 mm at Section 3. The diaphragm ground settlements at JS9-1 to JS9-5 did not stop until the start
walls at Section 3 developed a maximum differential heave of excavation at Section 3. This exception may be attributable
of 11 mm. to the combined effects of ancillary construction activities, traffic
The postconstruction measurements (i.e., after the completion of nearby, or other unknown factors. The ground almost stabilized at
the roof slabs) at Section 2 indicated that the diaphragm walls the time of the excavation of Section 3.
stopped heaving and settled down before they completely stabi- Fig. 16 presents the development of ground settlements at JS4-1
lized. This could be ascribed to the soil-structure interaction that to JS4-5 and JS10-1 to JS10-5 during the construction of Sections 2
tended to stabilize as excavation terminated and major structures and 3. Because these two surveyed sections were close to the boun-
were completed. dary of Sections 2 and 3, the measured ground settlements were
6-11-2007
6-21-2007
7-11-2007
7-21-2007
7-31-2007
8-10-2007
8-20-2007
8-30-2007
6-1-2007
7-1-2007
9-9-2007
0.0
Date (mm/dd/year)
JS1-1
-5.0
Settlement (mm)
JS1-2
-10.0 JS1-3
JS1-4
-15.0
Excavation of section 4 JS1-5
Construction of floors
-20.0
-25.0
6-11-2007
6-21-2007
7-11-2007
7-21-2007
7-31-2007
8-10-2007
8-20-2007
8-30-2007
6-1-2007
7-1-2007
9-9-2007
0.0
Date (mm/dd/year)
-5.0 JS2-1
Settlement (mm)
JS2-2
-10.0
Construction of floors
-15.0
-20.0
Excavation of section 4
-25.0
Fig. 13. Development of the ground settlements at JS1-1 to JS1-5 and JS2-1 to JS2-2
11-21-2007
12-11-2007
12-21-2007
12-31-2007
11-1-2007
12-1-2007
1-10-2008
1-20-2008
1-30-2008
2-19-2008
2-29-2008
3-10-2008
3-20-2008
3-30-2008
2-9-2008
0.0
Date (mm/dd/year)
-5.0 Excavation at
Settlement (mm)
section 2
-10.0
Construction of floor slabs at section 2
-15.0
-20.0 JS6-3
-25.0 JS6-4
Excavation at
-30.0 JS6-5 section 1
Downloaded from ascelibrary.org by WASHINGTON UNIV IN ST LOUIS on 08/05/13. Copyright ASCE. For personal use only; all rights reserved.
11-11-2007
11-21-2007
12-11-2007
12-21-2007
12-31-2007
11-1-2007
12-1-2007
1-10-2008
1-20-2008
1-30-2008
2-19-2008
2-29-2008
3-10-2008
3-20-2008
3-30-2008
2-9-2008
0.0
Date (mm/dd/year)
-5.0 Excavation at
Settlement (mm)
section 2
-10.0 Construction of floor slabs at section 2
JS7-1
-15.0 JS7-2
-20.0 JS7-3 Excavation at
section 1
-25.0 JS7-4
-30.0 JS7-5 Construction of floor slabs at section 1
-35.0
11-11-2007
11-21-2007
12-11-2007
12-21-2007
12-31-2007
11-1-2007
12-1-2007
1-10-2008
1-20-2008
1-30-2008
2-19-2008
2-29-2008
3-10-2008
3-20-2008
3-30-2008
2-9-2008
0.0
Date (mm/dd/year)
-5.0 Construction of floor slabs at section 2
Settlement (mm)
-10.0
JS8-1
-15.0
JS8-2 Excavation at
-20.0 section 2
JS8-3
-25.0 JS8-4
Excavation at Construction of floor slabs at section 1
-30.0 JS8-5 section 1
-35.0
Fig. 14. Development of the ground settlements at JS6-3 to JS6-5, JS7-1 to JS7-5, and JS8-1 to JS8-5
greatly affected by excavation at Section 2. At JS4-1 to JS4-5, the Section 4. Therefore, the actual ground settlements caused by ex-
ground settlements stopped following the construction of the con- cavation at these two sections remained unknown. The magnitudes
crete floor slabs at Section 3. However, the ground at JS10-1 to of the ground settlements at JS12-1 to JS12-5 and JS13-1 to JS13-4
JS10-5 continued to settle with time. As the cast floor slabs gained located at Section 4 were only half of those observed at JS3-1 to
strength over time, the ground settlements at JS10-1 to JS10-5 sta- JS3-5 and JS11-1 to JS11-5 at Section 3. The substantial ground
bilized gradually and finally stopped approximately 1 month after settlement development (up to 12–15 mm) at JS12-1 to JS12-5 and
the casting of the roof slabs. This aberrant postexcavation ground JS13-1 to JS13-4 during the excavation of the nearby Section 3
settlement development at J10-1 to J10-5 can be partially inter- indicates that although these two survey sections were distant, their
preted by the significant postexcavation wall deflection between settlements were still affected by the stress field created by the
Stages 7(a) and 8(a) observed at B20 in the proximity (see Fig. 4).
excavation in the proximity. Unfortunately, the final measurements
Unfortunately, the final measurement at B20 was taken at the com-
were taken before the casting of the middle slabs. Hence, the long-
pletion of the middle slabs, and the long-term postexcavation wall
term postexcavation ground settlements at these sections were
deflection development was unknown. Therefore, the aforemen-
tioned reason for why J10-1 to J10-5 experienced distinct long- unknown.
term postexcavation ground settlements cannot be verified. As Fig. 18 plots the relationships between the measured maximum
observed at JS9-1 to JS9-5, it may be attributable to the combined ground settlements, δ vm , at each survey section and excavation
effects of ancillary construction activities, traffic nearby, or other depth, H. At Sections 1 and 4, δvm was bounded by δ vm ¼ 0:03%H
unknown factors. and δvm ¼ 0:15%H, whereas at Sections 2 and 3 it fell between
Fig. 17 presents the development of ground settlements along δ vm ¼ 0:03%H and δvm ¼ 0:18%H. The developed boundaries
JS3-1 to JS3-5, JS11-2 to JS11-5, JS12-1 to JS12-5, and JS13-1 for δvm at this site were much lower than those of Clough and
to JS13-4 during excavation of Section 3. Unfortunately, the ground O’Rourke (1990) for excavations in stiff clay. The upper boundary
settlements at JS12-1 to JS12-5 and JS13-1 to JS13-4 at the com- at Sections 1 and 4 was significantly below the corresponding
pleted Section 4 were not monitored during the excavation of line of Hashash et al. (2008) in medium-stiff Boston clay. At the
12-21-2007
12-31-2007
12-1-2007
1-10-2008
1-20-2008
1-30-2008
2-19-2008
2-29-2008
3-10-2008
3-20-2008
3-30-2008
4-19-2008
4-29-2008
2-9-2008
4-9-2008
0.0
Date (mm/dd/year)
-5.0
Excavation
Settlement (mm)
-10.0 of section 2 Construction
of floors
-15.0
Excavation of section 3
-20.0 JS5-3
-25.0 JS5-4
-30.0 JS5-5
Downloaded from ascelibrary.org by WASHINGTON UNIV IN ST LOUIS on 08/05/13. Copyright ASCE. For personal use only; all rights reserved.
-35.0
12-11-2007
12-21-2007
12-31-2007
12-1-2007
1-10-2008
1-20-2008
1-30-2008
2-19-2008
2-29-2008
3-10-2008
3-20-2008
3-30-2008
4-19-2008
4-29-2008
2-9-2008
4-9-2008
0.0
-5.0 Date (mm/dd/year)
Settlement (mm)
-10.0
JS9-1
-15.0
JS9-2 Excavation Construction
of section 2 of floors
-20.0
JS9-3
-25.0 JS9-4
-30.0 Excavation of section 3
JS9-5
-35.0
Fig. 15. Development of the ground settlements at JS5-3 to JS5-5 and JS9-1 to JS9-5
12-31-2007
12-1-2007
1-30-2008
2-29-2008
3-30-2008
4-29-2008
5-29-2008
6-28-2008
7-28-2008
8-27-2008
9-26-2008
0.0
-5.0 Date (mm/dd/year)
JS4-1
-10.0
Settlement (mm)
1-30-2008
2-29-2008
3-30-2008
4-29-2008
5-29-2008
6-28-2008
7-28-2008
8-27-2008
9-26-2008
0.0
-5.0 Date (mm/dd/year)
-10.0 Excavation of
Settlement (mm)
section 2
-15.0
-20.0 JS10-1
-25.0 JS10-3 Construction of
floor slabs
-30.0 JS10-4 at section 2 Excavation of
section 3
-35.0 JS10-5
Construction of floor slabs at section 3
-40.0
Fig. 16. Development of the ground settlements at JS4-1 to JS4-5 and JS10-1 to JS10-5
overexcavated Sections 2 and 3, it was close to that of Hashash settlements attributable to excavation. By plotting the ground
et al. (2008). settlements, δ v , against the distance, d, away from retaining walls
On the basis of the ground settlement data from excavations sup- (δ v and d are normalized by the excavation depth, H e ), Peck (1969)
ported by temporary sheet pile walls and soldier piles, Peck (1969) categorized the ground settlements into three zones: I, II, and III.
proposed the first practical approach for the estimation of ground Fig. 19(a) shows the relationship between the normalized ground
3-30-2008
4-19-2008
4-29-2008
5-19-2008
5-29-2008
4-9-2008
5-9-2008
6-8-2008
0.0
Date (mm/dd/year)
-5.0
-10.0
Settlement (mm)
-15.0 JS3-1
-20.0 JS3-2
JS3-3
-25.0
JS3-4
-30.0
Downloaded from ascelibrary.org by WASHINGTON UNIV IN ST LOUIS on 08/05/13. Copyright ASCE. For personal use only; all rights reserved.
3-30-2008
4-19-2008
4-29-2008
5-19-2008
5-29-2008
4-9-2008
5-9-2008
6-8-2008
0.0
-5.0 Date (mm/dd/year)
Settlement (mm)
-10.0
-15.0
JS11-2
-20.0
JS11-3
-25.0
JS11-4
-30.0 Excavation of section 3 Construction of floor slabs
JS11-5
-35.0
3-20-2008
3-30-2008
4-19-2008
4-29-2008
5-19-2008
5-29-2008
4-9-2008
5-9-2008
6-8-2008
0.0
Date (mm/dd/year)
-5.0
-10.0
Settlement (mm)
Excavation of section 3
-15.0
JS12-1 Construction of floor slabs
-20.0 JS12-2
-25.0 JS12-3
JS12-4
-30.0
JS12-5
-35.0
3-20-2008
3-30-2008
4-19-2008
4-29-2008
5-19-2008
5-29-2008
4-9-2008
5-9-2008
6-8-2008
0.0
Date (mm/dd/year)
-5.0
-10.0
Excavation of section 3
Settlement (mm)
-15.0
Construction of floor slabs
-20.0 JS13-1
-25.0 JS13-2
JS13-3
-30.0
JS13-4
-35.0
Fig. 17. Development of the ground settlements at JS3-1 to JS3-5, JS11-1 to JS11-5, JS12-1 to JS12-5, and JS13-1 to JS13-5
settlements and normalized distances for this project. Both mea- ground settlements fell below δvm ¼ 0:2%H e specified for the pro-
surements at completion of the excavation and the final readings tection Grade 2 (see Table 1). To better understand excavation
were presented. This shows that most of the measured maximum behaviors in Shanghai soft clay, the ground settlement data from
H
H
(1) JS2-1~JS2-2
.2%
Maximum ground settlement, δvm (mm)
0.5%
20 JS6-1~JS6-5
=0
H
5%
JS7-1~JS7-5
δvm =
0 .1
δv
JS8-1~JS8-5
=
(1) Clough and O'Rourke (1990)
vm
δ
15 (2) Hashash et al. (2008)
(3) This study
10
(2)
H
05%
Downloaded from ascelibrary.org by WASHINGTON UNIV IN ST LOUIS on 08/05/13. Copyright ASCE. For personal use only; all rights reserved.
δ vm = 0. (3)
5
δ vm = 0.03%H
0
0 2 4 6 8 10 12 14 16 18 20
Excavation depth, H (m)
25
(2) (3) Excavation of Sections 2 and 3
(1)
H JS3-1~JS3-5
(1)
.2%
JS4-1~JS4-5
H
Maximum ground settlement, δvm (mm)
0 .5 %
20 JS5-1~JS5-5
=0
H
5% JS9-1~JS9-5
%H
m
δvm =
δv
0.1
JS10-1~JS10-5
.1 8
=
=0
JS11-1~JS11-5
vm
15
δ
JS12-1~JS12-5
m
δv
JS13-1~JS13-5
(1) Clough and O'Rourke (1990)
10 (2) Hashash et al. (2008)
(2) (3) This study
%H
0 .0 5
δ vm =
(3)
5
H
δ vm = 0.03%
0
0 2 4 6 8 10 12 14 16 18 20
Excavation depth, H (m)
Fig. 18. Relationship between the maximum ground settlement and excavation depths
six metro excavations (Wang et al. 2005) and the 92 cut-and-cover along the measurement section; d = distance away from the dia-
excavations for building basements (Xu 2007) were also included phragm wall; and H e = final excavation depth. In this figure,
in this figure. The comparison of the measurements from metro the measurements at the completion of excavation and the final
excavations in Shanghai and those reported in literature showed measured data were plotted. Published case histories (Clough
that the metro excavation data in terms of magnitudes and distri- and O’Rourke 1990; Hsieh and Ou 1998; Wang et al. 2005; Xu
bution patterns in Shanghai soft clay were consistent with the Cen- 2007; Hashash et al. 2008) were also included for comparison.
tral Artery/Tunnel (CA/T) Project (11.3 km long) in medium-stiff Clough and O’Rourke (1990) pointed out that when the ground
Boston clay (Hashash et al. 2008), but far away from Zone III of settlements in Peck (1969) for excavation in soft to medium clay
Peck (1969) for very-soft-to-soft clay. Except for a few scattering are plotted as fractions of maximum settlements, the settlement dis-
data points, most of the data from the 92 building excavations also tribution is bounded by a trapezoidal envelope in which the zones
fell within Zone I of Peck (1969). However, the maximum ground of movements can be identified. When 0 ≤ d=H e ≤ 0:75, the maxi-
settlements attributable to the building excavations were much mum settlements occur; when 0:75 < d=H e ≤ 2:0, a transition
greater than those attributable to the metro excavations. This com- zone in which the settlements decrease from maximum to negli-
parison demonstrates that a long and narrow multistrutted excava- gible values exists. On the basis of the field measurements in Taipei
tion retained by rigid diaphragm walls is capable of suppressing soft clay, Hsieh and Ou (1998) defined the zone of d=H e ≤ 2:0 as
excavation-induced movements. In sharp contrast with the metro the primary influence zone and the zone of 2:0 < d=H e ≤ 4:0 as the
excavation data, the building excavation data exhibited an apparent secondary influence zone. Analyzing the field measurements from
tendency to decrease rapidly with distance from the excavation pits. those excavations in Shanghai soft clay (Wang et al. 2005; Xu
This discrepancy indicates that a much longer excavation might 2007; this study) showed that the ground settlements attributable
incur a much wider influencing zone behind the pit. to the building basement excavations (Xu 2007) were consistent
Fig. 19(b) presents the relationships between the normalized with those of Clough and O’Rourke (1990) for soft-to-medium clay
ground settlements, δ v =δ vm , and the distance ratio, d=H e for this and with those of Hsieh and Ou (1998) for Taipei soft clay. In con-
project, in which δ v = ground settlement along the surveyed section trast, the distribution ranges of the ground settlements during the
behind the diaphragm wall; δ vm = maximum ground settlement metro-station excavations were much wider. Fig. 19(b) shows the
0.2
δv / He (%)
0.4 I
0.6 II
I - Sand and soft to hard clay
0.8
III II - Very soft to soft clay
III - Very soft to soft clay to a great depth
1.0
Downloaded from ascelibrary.org by WASHINGTON UNIV IN ST LOUIS on 08/05/13. Copyright ASCE. For personal use only; all rights reserved.
d / He
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0
0.0
0.5 Xu (2007)
Clough and O'Rourke (1990)
Hashash et al. (2008)
Hsieh and Ou (1998)
Wang et al. (2005)
1.0
(b)
Max. settlement Transition zone
Fig. 19. Observed settlement profiles versus those predicted by empirical methods
measured δ v =δ vm at this site spanned across the boundaries of the Distance ratio, dh/L
transition zone defined by Clough and O’Rourke (1990) and the 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
primary influence zone defined by Hsieh and Ou (1998). Most 0.0
of the measured δ v =δ vm lay between 0.5 and 1.0 at this site and 0.1
JS1-1~JS1-5
did not show an apparent tendency to decrease within the distance 0.2
JS2-1~JS2-5
JS6-1~JS6-5
JS8-1~JS8-5
JS9-1~JS9-5
JS7-1~JS7-5
0.3
JS3-1~JS3-5
JS4-1~JS4-5
JS10-1~JS10-5
JS11-1~JS11-5
0.4
to a great distance behind the retaining walls. Unfortunately, the
0.5
ground settlements beyond 25 m (1:6H e ) from the retaining walls
were not surveyed, and hence at what distance δ v =δ vm would 0.6
decrease remained unknown. The significantly wider distributions 0.7 North side (this study)
South side (this study)
of δ v =δvm observed in the Shanghai metro excavations and the 0.8
Yishan Road-side 1
CA/T Project in Boston than those observed in literature for build- 0.9 Yishan Road-side 2
ing basement excavations indicate that a much longer excavation 1.0
would incur a much wider influencing zone behind the pit.
Fig. 20. Relationship between the normalized maximum ground
Three-Dimensional Effects on the Maximum Ground settlement and the distance ratio
Settlements
To examine the 3D geometric effects of the excavation on the excluded. The measured ground settlements during the excavation
ground settlements, the normalized maximum ground settlement, of Yishan Road Metro Station in Shanghai (Liu et al. 2005) were
δ vm =H e , at each monitored critical section behind the diaphragm also included in this figure for comparison. Similar to the observed
walls was plotted against the distance ratio, d h =L, in Fig. 20. H e wall deflections in Fig. 9, the variation of δ vm =H e with d h =L was
= final excavation depth; d h = horizontal distance between a survey very limited, and no apparent corner effect was observed at either
point and the left-most point of the excavation; and L = total length excavation site. The relatively larger δvm =H e observed at the central
of the excavation in the longitudinal direction. Because the ground standard segments of this excavation may arise from overexcava-
settlements at JS12-1 to JS12-5 and JS13-1 to JS13-5 were not tion. Further examination showed that the measured ground settle-
surveyed during excavation of Section 4, their measurements were ments at Section 3 were slightly greater than those of Section 2 with
hm
tionships fell between δ vm ¼ 0:5δ hm and δ vm ¼ δ hm . On the basis of
δ
Mana and Clough (1981)
=
0.4
vm
Wang et al. (2005) the collected data from six metro-station excavations in Shanghai,
δ
δ hm
This study 0.8 Wang et al. (2005) found that most of the data lay between δ vm ¼
=
δ vm 0:2δ hm and δ vm ¼ 0:6δ hm . Fig. 21 summarizes δ vm =H e and δ hm =H e
hm
δ
0.3
.6δ h
δvm / He (%)
collected from Wang et al. (2005) and this project, where H e = final
1.2
m
=0
=
δ vm excavation depth. For this excavation project, the data were
vm
δ
bounded by δ vm ¼ 0:8δ hm and δ vm ¼ 1:2δ hm , which was greater
0.2 .5 δ h m than those of Mana and Clough (1981) and Wang et al. (2005).
=0
δ vm The greater δ vm =H e and the comparatively smaller δ hm =H e at this
Downloaded from ascelibrary.org by WASHINGTON UNIV IN ST LOUIS on 08/05/13. Copyright ASCE. For personal use only; all rights reserved.
6/21/2007
7/11/2007
7/21/2007
7/31/2007
8/10/2007
8/20/2007
8/30/2007
9/19/2007
9/29/2007
10/9/2007
6/1/2007
7/1/2007
9/9/2007
8
Date (mm/dd/year)
6 F1 F2
4 F3 F4
2
Settlement (mm)
F5 F6
0
-2 F7 F8
-4
-6
-8
-10
-12 Gas-pressure control station
-14
6/11/2007
6/21/2007
7/11/2007
7/21/2007
7/31/2007
8/10/2007
8/20/2007
8/30/2007
9/19/2007
9/29/2007
10/9/2007
6/1/2007
7/1/2007
9/9/2007
8
6 Date (mm/dd/year) F13
4 F14
2
Settlement (mm)
F15
0
-2 F16
-4 F17
-6 F18
-8
-10
Le-Kai building
-12
-14