Inception Report: November 2022
Inception Report: November 2022
Inception Report: November 2022
2, 3
INCEPTION REPORT
November 2022
November 2022
The preparation of detailed Master Plan of Entire Bay Terminal and detailed Job number
Engineering Design, Drawing and Estimates for Terminal-1 of Bay Terminal
Project under CPA 22-47-005 (CPA)
Draft 00 08/Nov/22
Inception Report for Phase 2, 3
Description
Prepared by Checked by Approved by
Signature
Filename
Description
Prepared by Checked by Approved by
Name
Signature
Filename
Description
Prepared by Checked by Approved by
Name
Signature
Filename
Description
Prepared by Checked by Approved by
Name
Signature
Page 1
Page 3
Page 4
Page 5
the Chittagong Port and Chittagong Export Processing Zone. The Bay Terminal was proposed
to deal with capacity limits at the nearby Chittagong Port. The maximum draft of Chittagong
R04 Draft Final Report with detailed Within 4 months of the start of
tender documentations etc. Phase 2, 3 and 4
complete
R05 Final Report with detailed Within 6 months of the start of
tender documentations etc. Phase 2, 3 and 4
complete
Phase - 5
25 copies and
R01 Inception Report with detailed Within 15 days of the start of
work program at least 3 soft
Phase 5
copies in
R02 Monthly Progress Reports Every month
CDs/Flash
R03 Work Completion Certificates At the completion of Project
Drivers
R04 Test and Reports As required
R05 As Built Drawings As required
Page 11
The Consultant enforces all necessary means to effectively coordinate the works for the
Project. The Management Plan is to assure the safe and reliable quality in Project
Management, in compliance with the requirements stipulated in the Contract between the
Consultant and the Client. The Project Management Plan addresses all aspects relevant to the
management of the Project. It is reviewed (and updated) throughout the duration of the
Project and is issued and available to all the project teams so that they are fully aware of
project details, it’s key principles, the success criteria, the main parties involved and their
roles. The Team Leader holds the responsibility for the document's preparation, issuance and
maintenance, with the support of the Project Group and, in particular, the Project Quality
Manager.
The Project Management Plan is based on;
• contractual documentation;
• general operating procedures of Kunhwa, DAEYOUNG Engineering and SAA;
• specific operating procedures prepared for the Project;
• the Project Management Plan; and
• the Project Quality Plan.
The Project Management Plan is interpreted as a living document throughout the project
development. The Project Control Process is shown on the Figure 4. In general, the Project
Page 14
Management includes the processes and activities of the performing organization that
determine policies, objectives, and responsibilities so that the Project will satisfy the needs
for which it is undertaken.
Page 16
accomplish the objectives of the consultancy services in detailed design and supervision of
construction throughout the service period, including the defects notification period in
Page 20
CPA provided data that is related to the Bay Terminal Gauge station (which is located near
the project site) is applied as tidal data in the project. As the result, the range between
Mean High-Water Spring (MHWS) and Mean Low Water Spring (MLWS) at the Project site
is estimated at about 5.475m and the Chart Datum Level (CD) is at about 2.323m under
the Mean Sea Level (MSL) as shown in Table 5.
Table 5: Tide Condition at the Project Area
Page 21
Figure 6: Probability of Non-Exceedance and Return Period of the Historical Water Levels at Chittagong
and Fitting of Four Well-known Distributions to the Data
As for the annual average water level rise in the Chittagong area, an annual average of
11mm/yr which is the value of the Rangadia area closest to the project area, was applied. The
design water level is the sum of HW100 and other allowances depending on the structure in
question. For the terminal area and the quays, the design water level should at least include
allowance for sea level rise, which is 11 mm/year for Bay Terminal. If a life time of 50 years is
considered, then a sea level rise allowance of at least 0.55 m is required, and the design level
considering the seasonal variation of 0.4 m is 10.873 m ISLW.
The Bay Terminal Layout Plan is shown in Figure 7. Bay Terminal consists of three terminals,
and is located in the order of Container Terminal-1, Mulitpurpose Terminal, and Container
Terminal-2 from north to south, and the total berth length is 3.5 km. Quay line length is
3,560m inclusive of 60m gate to the service jetty. Functions of each terminal are given below:
Container Terminal-1 and Container Terminal-2 handle container volume and quay
length of each terminal is 1.0 km with 3 berths.
Mulitpurpose Terminal handles various Cargo volumes and continars such as grains,
minerals, woods, irons,… etc., and has a quay length of 1.5 km.
Berthing facilities are located on the west side of the terminal, with yards and warehouses
in the center of the terminal, 8-lane road (50m wide) in the east side of the terminal, building
zones, railway terminal, and recreation areas for efficient operation of the terminal.
Breakwater and dredging will be constructed on a design done by a separate consultant. This
breakwater will be placed 1km to the west of the terminal for safe berthing of the vessels at
the Bay Terminal and smooth loading & unloading operations of the terminal.
(2) Quay Wall
Due to the soil conditions, a structure with a deep foundation is required. The difference
in the quay and dredge level combined with high earthquake loads made the selection of a
sheet pile wall unfavourable.
A reinforced concrete suspended deck on circular steel piles was selected as the most
practical / economical option. The weak soil conditions result in large slip circular failure
planes, which required widening of the suspended deck and the addition of additional
concrete elements in certain areas. See Figure 8 for the proposed Quay Wall structure.
Page 22
Page 23
The Bay Terminal, which consists of Container Terminals and Mulltipurpose Terminal, will be used
by various cargo and container vessels such as Panamax-class containers and bulk carriers.
Table 6: Design Vessel for Different Commodities
Vessel Type DWT(t) Loa(m) Beam(m) Draught(m) Remarks
Container Panamax
42,000 285 32.3 12.0
Vessel (4,700TEU)
Multipurpose
15,000 162 21.7 9.1
Vessel
Bulk Carrier 50,000 222 32.6 11.9
Bay Terminal is planned to have a total of 11 berths, and length of total berth is 3,500m.
- The length of one berth for container vessel is planned at 333m per 42,000 DWT.
- The length of one berth for cargo vessel is planned at 250m per 50,000 DWT.
Table 7: Length of Berth
Authority of Bangladesh Railway is implementing the Feasibility Study & Detail Design for the
Construction of a railway Link to the Proposed Bay Terminal of Chittagong Port Railway. In
order to discuss the connection with BR’s existing railway and to collect the new railway link’s
plan, several interfacing meeting with BR’s consultant had been held at the Bay Terminal
Project office. The several design issues to be influenced had been given by BR’s consultant
that has conducted the railway link to Chittagong Bay Terminal as below:
Railway link to Bay Terminal will connect with existing railway station, CGPY ;
Railway Link to Bay Terminal will cross the existing road, Coastal Road and Port Link
Road by level Crossing. It had been discussed and agreed with relevant authorities;
The Role and Responsibility of BR’s consultant is up to the point of alignment where
is the end of crossing Coastal road’s edge, eastern side border of Port area; and
The effective length of the track in the railway should not be less than 750m and a
loop track for locomotive shall be considered.
As per the recommendation of BR, the inland railway design will be completed by BR
regarding Railway Link to Bay Terminal, including its design and construction. Therefore, the
conceptual alignment of the access railway should be along with BR’s rail which is shown in
Figure 11.
Two railway terminals are placed. Container rail terminal is located in the east of the Multipurpose
Terminal. This container rail terminal will be shared by two other container terminals (i.e. CT-1 and
CT-2) as a method of transportation to be able to quickly transport cargoes from the Port site to the
The capacity of the planned container railway terminal will share up to eight percent of the
total volume of containers that are handled by two Container Terminals and one
Multipurpose Terminal. Cargo railway terminal (extra railway terminal) located at the jetty of
the Multipurpose Terminal shall handle heavy cargoes. The arrangement of tracks is shown
in Table 8, including the underlying parameters. The track layout of the railway terminal
including Extra is shown in Figure 13.
Effective Nos. of
Item No. of Track Location
Length Rail Crane
Freight
4 Loading/Unloading Minimum
Railway Delivery Yard 3
1 Loop track 750.0m
Terminal
Extra 1 Loading/Unloading track Minimum
Railway Port -
Terminal 1 Loop Track 7500.0m
Page 27
Primary objective of the study is to assess the drainage volume of the upstream catchment
area and to assess the adequate drainage facilities for the proposed Bay Terminal of the
Chittagong Port.
Specific objectives include:
• Catchment delineation of the study area using hydrological model;
• Assess the existing drainage characteristics of the study area; and
• Provide drainage arrangements and design dimension of drainage system.
(2) Catchment Area
For management of efficient and sustainable drainage and ensuring natural discharge, this
area has been divided into four catchments. Table 9 shows total discharge amount from the
catchment areas along with the parameters in determining the discharge amount. Figure 14
shows the catchment area.
Table 9: Drainage Area and Discharge Amount
Total Discharge Additional Climate change
Rainfall Total
Drainage Drainage Runoff from Drainage (m3/s) impact volume
Name Intensity Discharge
area (ha) Area(A) in coefficient Rainfall (CWAS STP+ CEPZ (23% of rainfall)
(I)in mm (m3/s)
ha (m3/s) ETP) in (m3/s)
Cat-1 127.5
Cat-2 407.4
Page 28
It is planned that the discharge of catchment rainwater and CWASA’s STP(under planning)
should be directly connected to the proposed drainage channel (downstream side) and the
level of the discharged pipe should be kept above the high tide level. As it is a tidal dominating
area, the Gate of the Regulators remains closed during the high tide. The Figure 15 shows the
drainage plan.
Page 29
Page 30
TASKS ACTIVITIES
PHASE 1: PREPARATION of FEASIBILITY STUDY UPDATE and DETAILED M ASTER PLAN FOR BAY TERMINAL
Task 1 Review and Update of Financial Analysis
Task 1.1 Determining the key objectives of the Financial Model
Task 1.2 Developing the structure of the Financial Model
Task 1.3 Preparing the Input Sheets (CAPEX Assumption sheet, Capital cost summary
sheet, Demand forecast sheet)
Task 1.4 Processing Sheets (Sources of finance sheet, Revenue sheet, Depreciation
sheet, O&M Costs sheet, CAPEX year sheet)
Task 1.5 Preparing the Financial Statements (Income Statement, Cash Flow Analysis)
Task 1.6 Preparing the Result (Financial Indicator) Sheets (Internal Rate of Return,
Payback Period)
Task 1.7 Conducting Sensitivity Analysis
Task 1.8 Conducting Economic Analysis
Task 1.9 Advancing on Tax Structure
Task 2 Review of Master Plan of Bay Terminal
Task 2.1 Container Terminal
Task 2.2 Multi-Purpose Terminal
Task 3 Review of Connectivity of Bay Terminal
Task 4 Review of Other Facilities of Bay Terminal
Task 4.1 Mosque
Task 4.2 Recreational Area
Task 4.3 Ansar Barracks
PHASE 2: DETAILED DESIGN OF TERMINAL 1 OF BAY TERMINAL
Task 5 All Necessary Surveys
Task 5.1 Topographic and Bathymetry Survey
Task 5.2 Geotechnical Investigation
Task 5.3 Material Source Survey
Page 31
All survey and investigation activities were covered in the Inception Report for the Phase 1
because topographic/bathymetric surveys and geotechnical investigation commenced in the
Maintenance reviews will be carried out for each structure to determine to what extent the
different designed structures are able to cope with extreme conditions. The review will focus
on the maintainability of structures. This will be valued in terms of durability, reparability,
availability of used materials and expected repair costs.
Main Jetty
The main jetty of Multipurpose terminal is given as:
• The size of jetty: 1,500m(Berth length) x 60m(Width), and
• The type of main jetty is deck slab with steel pile.
The piled deck structure for main jetty is proposed in the Feasibility Study Update in Phase -1
because of the local condition with soft soils and large retaining height as shown in Figure 16.
Piled deck structures are common for port facilities and below situation at Chittagong are
special in a few aspects:
• Very soft soil conditions, which will have an impact on the slope steepness, the deck
width and the bearing capacity/length of piles;
• Very high deck, much higher than the normal water levels, which will have an impact
on the level of fender and bollards; and
• Fender should be installed around the normal water level line. But with the deck is
Page 34
around 7-10m higher, the fender need to be attached to the first row of piles to
spread the loads and not overload the front row of piles.
Pile Design
Soil profiles of jetty area based on the existing borehole data consist of about 15-10m
thickness find sand and silt deposit and followed by sand, clay and progressively coarser sand
as depth increases. That is a common feature shown in the fluvial sedimentary layer.
The SPT N-values show a gradual increase with depth. Design considerations for successful
pile design of the Jetty are as follows:
• Check the bearing layer, N>50(soil investigation for the jetty area);
• Stability check of piles(bearing capacity, settlement, etc.,);
• Stability of the revetment(slop stability, settlement, lateral movement);
• Pile Load Test Plan(PDA test or Static); and
• Seismic Design(Zone Ⅲ).
Service Jetty
The service jetty of Multipurpose terminal is given as:
• The Size of service jetty: 245m(Berth length); and
• The type of service jetty is deck slab with pile.
Service Jetty is included in the major components of the work and it deemed for unloading
the construction material from the sea route. Service jetty will be located south side of main
jetty to handle the construction material throughout the construction period, thus it has to
have low influence from the tidal level. Upon completion of construction, service jetty will be
used for berthing port service and operation vessels.
Page 35
The Bay Terminal, which consists of Container Terminals and Mulltipurpose Terminal, will be
used by various types of cargo and container vessels such as Panamax-class containers and
bulk carriers. Design vessels are indicated in Table 13.
Table 13: Design vessels
Vessel Type DWT(t) Loa(m) Beam(m) Draught(m) Remarks
Container Panamax
42,000 285 32.3 12.0
Vessel (4,700TEU)
Multipurpose
15,000 162 21.7 9.1
Vessel
Bulk Carrier 50,000 222 32.6 11.9 Handymax Size
A sea water level with a return period of 100-years is 7.60m MSL according to the previous FS
Report. Using the relationship MSL = 2.323m ISLW (based on CPA data), HW100 is CD.(+)9.923m.
Including water level with a return period of 100-years, sea level rise for 50 years and seasonal
variation, the design high water level of the target area is CD.(+)10.873m and this value will
be considered in the Detailed Design. Therefore, the top elevation for terminal is determined
to be CD.(+)12.50m considering wave height (Hs=1m) and clearance in addition to the design
Page 36
Various factors will be considered for the design of jetty such as the scale for a structure that is
capable of berthing the design vessel and determination various loading cases. The design
dead load to be applied to the jetty structure is given in Table 15. Live load and combination
of load cases will be determined following the appropriated design code as explained below.
Table 15: Design Dead Load
Jetty 60kN/m2
Standard Code
The structural design will be carried out according to the relevant and mutually compatible
system of British, European, International, US, Korea and Japanese codes and standards based
on BNBC.
Design Load Combination
USD(Ultimate Strength Design Method) will be applied to slab and beam design.
ASD(Allowable Strength Design Method) applied to steel tubular pile design.
Modeling and Boundary Condition
Midas Civil 2021(Finite element analysis program) will used in the structural modeling. In order
to model the structure, plate elements are used for slab and walls and frame elements are
used for the beam and piles.
The maximum bending moment, the maximum shear force and the maximum axial force will
be used to review the structural capacity of each element.
Task 7.3 Bridges
Bay Terminal access interchange is planned as PSC BEAM, PSC BOX, RCC BOX bridge that is
connected to Port Link Road after crossing Coastal Road, and has a good structural quality
and is advantageous in cost effectiveness. The substructure shall be designed to safely
transfers the upper load to the support base, so it should be firmly sustained by the
underground layer, harmonizes with the super structure to pursue an aesthetically pleasing
shape, and secures ductility and elasticity to resist earthquake activities.
Page 37
The geological condition at the project location is composed mostly of silty sand. For this
reason, structures are planned on pile foundation in consideration of design load, field
workability, and design support layer because vertical load acts largely on bridge foundation.
Pavement Design
The Consultant will prepare designs based on the typical pavement sections, applying sound
engineering practice, taking into account traffic forecasts and incorporating coastal
considerations along with conducting road safety and giving due regard general local practice.
Pavement design for the project roads is
based on the section of asphalt pavement of
Road Design Manual. The Consultant will
determine the pavement composition and
thickness during the detailed design through
the discussion with CPA and reexamination for
the traffic volume. A sample of typical
pavement structure is given in Figure 18.
Figure 18: Pavement Structure
Page 39
The design standards, parameters, and criteria adopted for the Bay Terminal rail track are
consistent with the overall strategy for improving regional connectivity and enhancing the
capacity of Bangladesh Railway to handle an increasing share of regional traffic. The rail
infrastructure to be introduced is designed to achieve the ultimate vision for gauge unification
in Bangladesh. The track is designed to be built as dual gauge consisting of broad gauge and
metre gauge. The design standards, parameters, and criteria adopted are for dual gauge and
will cater for both broad gauge and metre gauge train operations.
Design for access railway and terminal will basically refer to the Design Standards of Railway
Link to Bay Terminal Project and the others will be referred to Terms of Reference in the
Project’s Contract Agreement, and the other references as below:
• Indian Railway Standard (IRS);
• British Standards (BS);
• American Railway Engineering and Maintenance of Way Assossiation (AREMA);
Page 40
It is necessary to carry out the detailed geotechnical investigation in the container terminal
area, Multipurpose Terminal area, and truck terminal area and to study the residual
Page 42
1) Design drawings showing all finished, location of Jetty structures, Detail Drawings of Jetty
structures (Pile, Deck, Berthing Wall, Mooring and Fender system etc.) and Yard facilities
like decks, lighting, walkways, roads, landscape etc.;
2) Plans and Profile, Alignment, details of structural components of Bridges and showing
blow-ups where necessary;
3) Plans and Profile, Alignment, details Sections of Bridges and showing blow-ups where
necessary;
4) Plans and details of joinery work (e.g. -floor/deck and painting specifications, Road
Marking, Reflecting studs etc.);
5) Drainage working drawing, detail and blow-ups where necessary;
6) Utility layouts showing location and size of electric power lines, lighting, drainage;
7) Electro-mechanical layout/outlay including Lifting operation and locations of ducts,
pipes and equipment required, transformers, generators etc.;
8) Electrical drawings including circuit diagrams with location and types of all switches,
outlets, fixtures, circuit breakers, generating and other electrical equipment such as sub-
station, generator, service entrance, panel boards and size of all conductors; and
9) Structural drawings showing plan, elevation, section and detailing.
Container handling systems can be categorized on the basis of using combinations of the
equipment in conjunction with the movement of containers by tractor/trailer between the
quayside and the storage yard into tractor-trailer system, straddle carrier(SC) system,
Status of ESIA Study and Development of Environment, Health & Safety Guidelines
(Continued from Phase 1)
1.0 Status of Environmental Social Impact Assessment(ESIA) Study
The proposed “ Bay Terminal” will be one of the green and sustainable port in the country
where, it will be ensured:
Compliance with all applicable legal requirements regarding the environment, health
and social issues;
Development, Implementation and maintained a comprehensive Environment &
Social Impact Management system;
Minimization/substitution of resource use like; the use of solar energy, rainwater
harvesting, and reuse of wastewater from the sewage treatment plant;
Use of surface water and rainwater beside the ground for a source of the water
Page 45
treatment plant;
Sub-surface recharge through development infiltration gallery;
Stakeholder engagement
Stakeholder engagement is an inclusive process that involves stakeholders in meaningful
consultations throughout the project life cycle. Stakeholder consultation is a regulatory
process as per ECR-1997 of DoE, where an open and transparent engagement with all relevant
stakeholders during project planning and throughout the project cycle for determining the
environmental and social impacts associated with project planning and implementation.
According to ESS10, an “effective stakeholder engagement can improve the environmental
and social sustainability of projects, enhance project acceptance, and make a significant
contribution to successful project design and implementation”.
information support about the proposed drainage plan. The stakeholder’s feedback is used
as constructive input for improving project planning, design, implementation and other
activities related to the project. For the study of the Bay Terminal drainage, several
The Public Consultation and Disclosure in 21 Sept 2022 at CPA Shaheed Md. Fazlur Rahman
Munsi Auditorium with CPA Stakeholders & port User
Presentation & Discussion Agenda was the master plan & ESIA of the projects and the urban
drainage design of the project surroundings.
The total Participant was 152 out that CPA 49, DFI 1, Army 3, BAF Base Johirul 2, Bangladesh
Power Distribution Board(BPDB) 1, Coast Guard 1, Customs House Chittagong 1, City
Corporation 5, DoE 1,
RHD-1, Public Private Partner Ship 1, PPSL 1, BIWTC 3, Bangladesh Railway 3, BIWTA 1,
Bangladesh Water Development Board, Chittagong 1, Shipping Ministry 1, CDA 2, Chittagong
WASA 1, Karnofulli Tunnel 1, NSI 2,Chittagong Metropolitan Police 2, Ward Counselor 5,
Electronic Meadia( BTV, Shomoy TV, Jumuna TV, NTV, DBC News, Chanel 24, Bangla TV and
EKHON TV, SP TV) and Print Media 23, Bangladesh Shipping Corporation(BSC)1, Consultant 7,
Contractor 2, Shipping Agent 12, CNF Agent 2, Transport 3, BKMEA 2, Community 5 person.
2.0 Development Environment, Health & Safety Guidelines(EHSGs) for construction work:
Environment Health & Safety Management System will be developed by using the concept of
ISO-14001:2015(Environmental Management System) & ISO-45001:2018(Safety
Management System).
For the development EHS the following legal and others guideline will consider which is given
Page 47
below;
The goal of an EHS management system is to protect workers from job-related injuries and
illnesses, identify and mitigate physical, chemical and biological hazards in the workplace as
well as improve training and communications that clearly explain the objectives of the project
for promoting a safe and healthy work environment throughout the construction of the
projects.
Page 48
Based on the context of construction activities a list of Environment, Health and Safety
risks will have identified.
Based on the Potentiality of impacts/risks, local legal requirements, World Bank(WB)
guidelines, and the view of other potential stakeholders, a list of significates
Impacts/Risks is identified. In the risk priority use idea of Likelihood of occurrence
which provides an assessment of how likely it is that this risk will occur; and severity
of effect which provides an assessment of the impact that the occurrence of this risk
would have on the project;
To mitigate the Impacts/Risks a list action program will be developed of respective
hazards. In the Impact or risk management method the hierarchy control measure will
use.
To ensure proper implementation of the Impacts/Risks program the concept
monitoring & measurement, inspection checklist and internal protocol will be
established.
b) Scope of Work:
o To ensure the sustainable supply of potable drinking water for port office and ship.
d) Scope of Work:
Page 49
o To ensure an obstruction-free natural drainage system that will cross the project.
o To ensure that the Chittagong city drainage system will not be hampered by the
project development.
f) Scope of Work:
Page 50
1.3.1 Review of exist data: Review of exist data work will be start on 7 th
September/2022 and end on 27th November/2022
Detailed Design
Detail design including Jetty, Terminal with Yard Facilities, Service Jetty, Bridges, Access Road,
Soft Soil Treatment Design and Railway Connection start on 7th September/2022 and end on
17th January/2023
2.1 Jetty: Jetty Detail Design work will be start on 7th September/2022 and end on 17th
January/2023
2.1.1 Jetty with Slope protection: Jetty with Slope protection Design will be start on
7th September/2022 and end on 27th October/2022
2.1.2 Layout Plan: Layout Plan work will be start on 27thSeptember/2022 and end on
17th December/2022
2.1.3 Determination of detailed section with Slope Protection: Determination of
detailed section with Slope Protection Design will be start on 27th
September/2022 and end on 17th January 2023
2.1.4 Structural Analysis including Accessory facilities: Structural Analysis including
Accessory facilities work will be start on 27th September /2022 and end on 17th
January/2023
2.1.5 Detail Design Report Including Drawing & Quantities: Detail Design Report
Including Drawing & Quantities work will be start on 27th November/2022 and
end on 17th January/2023
2.2 Terminal with Yard Facilities: Terminal with Yard Facilities design work will be start on
7th September/2022 and end on 17th January/2023
2.2.1 Layout Plan of Terminal with Yard Facilities: Layout Plan of Terminal with Yard
Facilities work will be start on 7th September/2022 and end on 27th
October/2022
2.2.2 Detail Design including Drawing & Quantities: Detail Design including Drawing
Page 52
& Quantities work will be start on 27th October/2022 and end on 7th
January/2023
2.7.3 Station Design: Station design will be start on 7th December/2022 and end on
7th January/2023
Deliverables
A Inception Report: Will be submitted on 10th November/2022
B All Survey Report: Will be start on 17th November/2022 and end on 7th October/2022
B1 Topographic Survey Report: Will be submitted on 15th November/202
B2 Bathymetric Survey Report: Will be submitted on 15th November/2022
B3 Geotechnical Investigation Report: Will be submitted on 30 th November/2022
C Design Report : will be start on 7th January/2023 and end on 17th February/202
C1 Draft Design Report: Will be submitted on 15th January/2023
C2 FINAL Design Report: Will be submitted on 15th February/2023
D Procurement Document: Will be start on 7th February/2022 and end on 17th
March/2023
D1 Draft Tender Documents: Will be submitted on 15th February/2023
D2 Final Tender Documents: Will be submitted on 15th February/2023
Page 54
55
Figure 24: Project Schedule – Phase 2, 3
56
57
58
59
60
61