Contractor: Project
Contractor: Project
Contractor: Project
Contractor
M/s SEW Infrastructure Ltd. M/s ISAN Corporation in JV with M/s
6-3-871, ‘SNEHALATA’. Greenlands Road, Chaitanya Projects Consultancy Pvt Ltd in
Begumpet, Hyderabad 500 016, Association with M/s Infra Illumination
Telangana, India. LLP.
.
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
Table of Contents
1. Introduction
1.2 The Project
1.2.1 Salient Features of Proposed Enhancements
1.1.1 Scope
1.1.2 Natural Environment
Page 2 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
4. Environmental Monitoring Reporting
a. Environmental Monitoring Plan
i. Performance Indicators
ii. Ambient Air Quality (AAQ) Monitoring
iii. Water Quality Monitoring
iv. Noise levels Monitoring
Page 3 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
1. Introduction
1.1 The Project
1.1 Salient Features of the Project
1.1.1 Scope
1.2 Natural Environment
Page 4 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT
PLAN
National Highway Authority of India. is engaged in the development of Roads and as part of
this endeavor, the Authority has decided to undertake “Six Laning of Paravoor (Design
Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-
47) in the State of Kerala under bharatmala pariyojna on EPC mode”.
1. The Existing length of the Project Highway is 37.5 Km and Design Length is 37.5
Kms.
3. There are Major/Minor Bridges, VUP & LVUP, Box and HP Culverts, Protection
Works etc.
The scope of the project includes “Six Laning of Paravoor (Design Ch. 417.000) –
Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under bharatmala pariyojna on EPC mode”The proposed improvement aims
at improving the geometric deficiencies at various intersections, riding quality, journey
speed and reducing congestion of traffic on the highway. It is proposed to add service
roads, adequate drainage system, road furniture, utilities and amenities wherever
required. Due attention has been paid throughout the design to minimize resettlement
problems, cutting of trees, shifting of cultural properties, etc., as far as possible through
engineering design. At the congested / built – up areas, it has been proposed to provide
service roads along with footpath and drains on both sides to segregate the through and
local traffic, besides improving the drainage problems. Wherever National Highways,
District roads with substantial traffic are crossing the State Highway, junctions have
been proposed. All the junctions have been improved with proper junction design
connections. All these measures are going to substantially improve the environmental
and traffic safety aspects.
Page 5 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
1.2 Natural Environment
1. WATER
2. FLORA
1. Pure avenues plantation with single species (only to be) planted for a
number of kilometers (or the stretch between two marketplaces) provide
harmonious and pleasing look, and a regular and wavelike skyline. This
row of trees forms the first and innermost line.
Page 6 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
3. Selection of tree species in outer rows (where multiple rows are to be
grown) were considered from economic point of view. Therefore, trees
that provide fuel and fruit as well as small timber for agricultural
implements have been suggested. Some fuel and small timber producing
trees include babul, baking and mesquite (all of them are fast-growing
trees); the fruit producing trees are varieties of mango, Kathal, guava and
mahua.
In stretches where water logging occurs, on both sides of the road, the
selectiontree species should be from amongst the moisture loving trees, for
example, Lagerstroemia floss – reginae, arjuna (Terminalia arjuna) species
of Cassia like C. marginata. C nodosa, C, siamea, and a variety of jamun,
Syzygium operculala (the fruits are small and not edible), Eucalyptus,
Tanarix, Salix etc.
The tree species to be grown near the ponds and other water bodies include
Kadamba (Anthocephalus Cadamba), Sita Ashok (Saraca Indica),
different
Page 7 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
varieties of Kachnar (Bauhinia Purpurea. B. Variegata. B. Racemosa),
Lagerstroemia Floss – Reginae, Peltophorum Ferrugineum Temple tree
(Pumaria Alba and P Acutitolia) etc.
Near market places and congested areas, the trees known for behaving as
‘pollution sink’ have been proposed. Though, trees in general absorb the
pollutants,filter the air from pollutants, and act as noise barrier, but some
trees like Neem (Azadirachta indica), Mango (Mangifera indica), Ashok
(Polyalthia longifolia), Putranjiva Roxburghii, Moulshree (Mimusops
elengi), Ficus Retura, Pakur (Ficus infectoria), Shisham (Dalbergia sisso),
Imli (Lamarindus indica), Mahua (Bassia latifolia) can do it in a better way.
Near sensitive areas like schools and hospitals, tall trees with thick
canopies can create a wind screen through which the air can be filtered and
the noise levels be considerably reduced. Some such trees are Ashok
(Polyalthia longifolia), Putranjiva Roxburghii and Alstonia Scholaris.
Thorny trees like Acacia Arabica and Ber (Zizyphus jujuba) should be
avoided since their thorns are a nuisance for the pneumatic tyres of motor
vehicles.
On the basis of the above criteria, the tree species recommended for
landscaping of theHighway are as under:
Page 8 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT
PLAN
Species of Plants Minimum No. of Distance from the edge of
Botanical Name Local Name Rows Carriage Way (m)
Azadirachta Indica Neem 2 - do -
Eucalyptus Eucalyptus Only where stagnant - do -
Atriodora Globulus water exists
Bouhunia Pupuria Kanchan 3 - do -
Acacia arabica Imli 2 - do -
Ficus Bengalensis Bargad 2 - do -
Delonix regia Gulmohar 2 - do -
Dalbergia sisso Shisham 2 - do -
Ficus religiosa Pipal 3 - do -
Acacia arabica Babul 3 - do -
Bauhinia Variegata Kachnar 2 - do -
4. SOCIAL ENVIRONMENT
New Bus Stops would be provided with shade, benches, and railings.
Interpretative signage would be displayed in Hindi and English that could
deliver information about the bus numbers, origin & destination, and routes of
buses. These bus stops will be provided with paved approach and connected
with the service road separated with raised median so as to reduce the effect of
congestion as well as air pollution.
Landscaping:
Page 9 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
Page 10 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
The project passes through mainly flat /rolling terrain and there are no substantial cut
and fill operations required by the project. All the effort have been made to locate borrow
areas in barren and non-productive lands with due consent from the individual
landowners and designated borrow areas. No new stone and rock quarries have been
proposed to be opened for the purpose of the project.
All the quarrying and borrowing work will be carried out after getting requisite
environmental clearances from the concerned statutory agencies and proper
redevelopment plans for these borrow areas have been formulated.
The soils in the region are mainly of the alluvial type and are very fertile lands but a
major part of the agricultural lands fall under the unirrigated category. Environmental
impacts on the soils include compaction of soils, contamination of soils and loss of
productive soils through borrowing of earth and soil erosion.
The air quality monitoring carried out for the project purpose revealed that the levels of
pollutants meet the National Ambient Air Quality Standards for most of the project
stretch except in the case of Suspended Particulate Matter (SPM) at the built-up
locations withinthe contract package.
For the purpose of impact prediction, CALINE-4 line source pollution dispersion
model was used for the project purpose. The predictions were done up to the year 2032
and the results indicate that the predicted CO levels for the locations selected were within
the prescribed NAAQ Standards for ambient air quality in the respective category of
land use. However, the NO2 levels are expected to violate the prescribed standards at
almost all the locations used for prediction modelling.
Page 11 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
Surface water bodies include natural drainage channels (rivers, stream and canals) and
static water bodies. Besides, a large number of irrigation channels and several tube-
wells are there in the area for irrigation purposes. The major surface water bodies
intersecting the project highway include rivers and Canal.
Good management practices during construction shall ensure that there is minimal
leachate of pollution into the groundwater and surface water sources and there will be
minimum contamination of water resources due to any project activity. Enhancement
measures have been proposed for ponds and water bodies falling under the direct impact
zone of the project.
Most of the areas in the project stretch have baseline noise levels that exceed the
prescribedlevels for their respective land use category and are especially significant for
residential andcommercial areas with sound pressure levels of the order of 65 dBA
during day and 55dBA during the day.
For predicting the increase in the sound pressure levels at the time of highway operation
with the increased traffic volumes and traffic speeds as well as better road conditions
along with cutting of trees, a noise prediction model by FHWA (Highway Noise Model)
was used. The results of the modeling indicate that the change in noise levels for the year
2020 as compared with the years 2003 and 2005 exceed the permissible limits but the
increase is not much significant, keeping in view the manifold increase in the distances
up to 100 mand 150 m from the centre line of the road for all the locations modelled
between kms 280 and 386. The decrease in noise levels with distance varies between 20-
25 dBA, which is significant as the noise levels get reduced below the standard limits
prescribed for Ambient Air Quality-Noise.
The project corridor does not pass through any reserved or protected forests between its
entire length and no endangered flora species have been reported along the highway. The
impact of removal of trees however should be a concern trees within the ROW are likely
to be affected due to the project.
As regards the fauna of the region, the historical human influence and the
continuoushuman habitation along the NH-66 has meant that there is very little faunal
presence exceptfor domestic animals along the highway and there are no reports of any
endangered species present or identified in the project-affected area.
Page 12 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
The dominant land use along the highway is agricultural. The major crops grown are
Rabi, Kharif & Jayad that includes Paddy, Wheat, Sugarcane, Potato and maize. A
number of public and private buildings such as schools, hospitals about the road. The
proposed widening and strengthening will affect road-side amenities and some locations
will be morevulnerable than before. It is envisaged that the agricultural land along the
highway will get converted to industrial/commercial use to realize the value of the
improved connectivity of the area. Increased vehicular speed mean that the fringe areas
along the road are at increased risk from speeding vehicles.
Page 13 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
Page 14 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
The broad environmental categories that are likely to be impacted include: Physical
Environment, Biological Environment and Social Environment.
To minimize the adverse impacts of the project, mitigation measures have been
formulated and shall be implemented during the project implementation phase. The
mitigation measures would be directed towards the restoration of the dynamicbalance
of nature. The mitigation of negative impacts involve reduction in magnitude of the
adverse impacts during various stages of the project through:
Most of the impacts of the overall project cycle in the project will be at the construction
stage of the project and hence, it requires great attention in the overallEMP. In addition
to the monitoring of the construction activity itself to the pollution levels within the
permissible limits, the enhancement of cultural
Page 15 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
The requirements of the Environmental Management Plan during the operation stage
will essentially entail monitoring activities along the corridor for ascertaining the
effectiveness of environmental mitigation measures and also the need for additional
measures required in the future. The monitoring for pollutants specified in the
Monitoring Plan will serve the two purposes. In addition to checking the efficacy of the
protection/mitigation/enhancement measures implemented, this will help verify or
refute the predictions made as a part of the impact assessment. Thus,it will complete
a very important feedback loop for the Authority.
The responsibility for implementation and supervision of EMPs are vested with three
agencies, namely Contractor, Authority and Authority’s Engineer. The Contractors
herein mean the agency hired for execution of the construction works for the
respective contract packages. Authority would be the implementation agency in the
EMP. The term ‘Authority’s Engineer’, wherever used, refers to the Supervision
Consultant.
Page 16 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
Acquisition of structures to be dismantled/removed for the project
Joint field verification of EMP by the Engineer (or the SC) and
the Contractor
Page 17 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
Page 18 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
Page 19 of 53
Table – 3.1 Environmental Management Plan
Responsibility
S. Environmental Assessed Avoidance, Mitigation and Reference Implementation Implementation Supervision
No. Parameter Impact Location Enhancement Measures Document Time Frame
Pre-construction Stage
Physical Environment
1. Meteorology Change in Project Stretch a) Compensatory Planting of trees. During Construction Contractor Authority
Microclimate For every tree felled, four trees to
be planted
2. Land Resources a) Loss of Labour Camps, a) Minimize the acquiring of Appendix …. Before Construction Contractor Supervision
Productive Soils Stockyards etc. productive agricultural land for (EMP) Starts Consultant
uses such as locating construction
camps, stockyards and storage go
downs.
b) Borrowing of Borrow Pits, a) In selection of the borrow areas MoRTH: 305.2 Design Stage Design Authority
Earth and Stone Stone Quarries care was taken during the design and MoRTH: Consultant
Crushing stage itself to ensure minimum loss 305.2.2.2
Operations of fertile and productive
agricultural soil as well as loss of Appendix….
vegetation is minimum. (EMP)
4. Water Resources a) Entire Project a) Construction camps shall be During Contractor Supervision
Contamination Stretch, Water located away from any sensitive Construction Consultant,
of Water Bodies, Rivers, water resources like surface water Mobilization Period Authority
Resources Wells, Ponds, bodies.
Lakes etc.
b) Transportation of soils etc.
during the pre-construction stage
shall ensure proper handling of the
raw material so as not to result any
contaminated runoff into water
resources.
b) Community Entire Project a) During the design stage of the Design Stage DPR Authority
and Private Stretch, project, maximum efforts were Consultant
Water Community made to reduce the number of
Resources Ponds, Wells, community and private water
Hand-pumps sources to be affected by project by
varying the alignment of highway.
Biological Environment
Page 21 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
Responsibility
S. Environmental Assessed Avoidance, Mitigation and Reference Implementation Implementation Supervision
No. Parameter Impact Location Enhancement Measures Document Time Frame
1. Flora Loss of Trees, Entire Project a) During the design stage and the Design Stage of the DPR Authority
Canopies, Stretch Environmental Screening Study, Project Consultant
Green Tunnels various options for highway
alignment were considered so as to
reduce/minimize the loss of trees
due to project implementation.
Social Environment
1. Land Resources Acquisition of Within Corridor a) Avoidance measures were taken RAP Document Before Construction Authority
Land of impact, during the design and Starts
Borrow Pits environmental screening study of
the project to minimize the
acquisition of land for the purpose of
the project.
Before Construction
b) All the titleholders and Project NGOs,
Starts
Displaced People (PDP) shall be Authority,
relocated as per the measures and Grievance
entitlements as described in the RAP Redressal Cell
before the start of the construction.
Construction Stage
Physical Environment
1. Land Resources a) Loss of Quarries, a) Borrow pits shall not be dug MoRTH: 305.2 During Construction Contractor Supervision
Productive Soils Borrow Pits, continuously in a stretch. The Consultant,
Camps location, shape and size of the Authority
Stockyards etc. designated borrow areas shall be as
approved by the Engineer and in
Page 22 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
Responsibility
S. Environmental Assessed Avoidance, Mitigation, and Reference Implementation Implementation Supervision
No. Parameter Impact Location Enhancement Measures Document Time Frame
accordance to the IRC-10-1961
recommended practice for borrow
pits for road embankments.
b) Topsoil up to a depth of 0.15 m
from all permanently covered area
(construction camps etc.) and
borrow areas shall be stockpiled for
productive reuse
b) Soil Erosion Entire Project a) Slope protection shall be MoRTH: During Construction Contractor Supervision
Stretch, high provided on embankments abutting 305.2.2.2 Consultant
embankments, water bodies by providing stone
edges of ponds pitching or by providing Gabion MoRTH: 306.2
lakes, rivers etc. structures made of wire-mesh
baskets and stone boulders.
Page 23 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
Responsibility
S. Environmental Assessed Avoidance, Mitigation and Reference Implementation Implementation Supervision
No. Parameter Impact Location Enhancement Measures Document Time Frame
b) Brick-pitching/Stone-pitching
shall be provided on slopes and
embankments as applicable.
c) Slopes and depth shall be
regulated in borrow pits to prevent
erosion.
c) Maximum reuse of
constructional wastes (dismantled
pavement debris etc.) shall be
considered as applicable.
Page 24 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
e) Unusable and hazardous wastes
shall be properly disposed on
identified locations.
Responsibility
S. Environmental Assessed Avoidance, Mitigation and Reference Implementation Implementation Supervision
No. Parameter Impact Location Enhancement Measures Document Time Frame
d) Compactionof Entire Project a) Heavy, wide and slow-moving During Construction Contractor Supervision
Soils Stretch, Fertile vehicles should be kept away from Consultant,
areas exposed to Authority
the sensitive routes. Use of heavy
heavy vehicles,
machinery on productive land to be
machinery
minimized.
b) Limitation on the axle load shall
be identified such that topsoil is
protected from compaction.
e) Borrowing of Soil Quarries, a) Transport of the soil/earth shall be During Construction Contractor Supervision
Earth and Stone Rock Quarries, done by covering the haulage Consultant,
Crushing Stone Crushers vehicles with tarpaulin or any other Authority
Operations good quality material.
Page 25 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
f) Dust suppression measures be
carried out like sprinkling of water at
the construction site where these are
stored and used.
Responsibility
S. Environmental Assess Avoidance, Mitigation, and Reference Implementation Implementation Supervision
No. Parameter ed Location Enhancement Measures Document Time Frame
Impact
2. Ambient AirQuality a) Generation of Entire Project a) All crushers identified to be used MoRTH: 111.1 Contractor Environmental
Dust Stretch in construction shall conform to Expert of SC and
relevant dust emission control MoRTH: 111.5 Authority
legislation of the respective SPCB. MoRTH: 111.9
b) All the construction plants shall
MoRTH: 111.10
be sited at least 1 km in the downwind
direction from the nearest human MoRTH: 118.1
settlement.
Contract
c) Asphalt mixing sites and the Document
batching plants should be at a
distance of at least 800 m from
residential zone.
Page 26 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
Page 27 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
d) Air pollution monitoring shall be
carried out at least once a month to
verify that air pollution norms are
being followed by the contractor
and the air quality at the construction
site does not exceed the prescribed
limits.
3. Water Resources a) Lakes, Ponds, a) Preparation of temporary drains MoRTH 113.13 During Construction Contractor Supervision
Contamination Rivers etc. to dispose of the eroded sediments Consultant,
of Water and to prevent them from entering MoRTH: 111.1 Authority
Resources the surface water bodies.
MoRTH: 111.4
b) Construction work near wells
and groundwater sources should be
carried only out after properly
covering them.
c) To prevent contamination of
water resources due to contaminants
from construction camps,
wastewater collection and treatment
shall be provided.
d) Contaminated discharges
containing oil/grease contributed by
vehicle parking/repair areas and
workshops shall be collected and
treated using oil interceptors.
Page 28 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
capability using treatment wetland
technology.
4. Noise Environment Increase in Entire Project a) The plants and equipment used MoRTH: 111.13 During Construction Contractor Supervision
Sound Levels Stretch for construction shall strictly Consultant,
MoRTH: 111.1 Authority
during conform to Central Pollution
construction Control Board (CPCB) noise MoRTH: 111.6
standards.
b) Vehicles, equipment, and
construction machinery shall be
monitored regularly with particular
attention to silencers and mufflers
Page 29 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
Responsibility
S. Environmental Assess Avoidance, Mitigation, and Reference Implementation Implementation Supervision
No. Parameter ed Location Enhancement Measures Document Time Frame
Impact
1. Fauna Poaching of Entire Project a) It shall be the duty of the During Construction Contractor Supervision
animals, Stretch Contractor to ensure that all the Consultant
fishes, works carried out as part of the
accidents project implementation during the
involving construction stage shall not cause
domesticated any damage or disruption to the
animals etc. fauna.
b) Strict rules regarding
unauthorized poaching of animals
and fishing shall be enforced among
the construction workers to ensure
these activities do not occur.
Page 30 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
d) The Contractor shall take all
necessary measures for the safety of
traffic during construction.
Responsibility
S. Environmenta Assessed Avoidance, Mitigation, and Reference Implementation Implementation Supervision
No. lParameter Impact Location Enhancement Measures Document Time Frame
Operation Stage
Physical Environment
1. Ambient Increase in Areas a) Planting of trees along the During Construction Contractor Authority,
AirQuality concentrations adjacentto highway as part of compensatory and Post Construction Supervision
of pollutants in project planting and also at locations sensitive maintenance Consultant
ambient air corridor to air pollution likeschools, hospitals
etc. which are very near to the highway
boundary.
c) To prevent contamination of
surface water bodies like ponds,
Page 31 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
riparian strips shall be provided along
the edges of the pond.
Page 32 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design Ch.454.500) section of New NH-66 (Old NH-47) in the State
of Kerala under Bharatmala Pariyojna on EPC mode”.
Responsibility
S. Environmental Assess Avoidance, Mitigation and Reference Implemen Implementation Supervision
No. Parameter ed Location Enhancement Measures Document tation
Impact Time
Frame
e) The locations where the school and
colleges exist nearby the existing
highway, service road, traffic signage
(Informatory & cautionary) and zebra
crossing havebeen proposed.
Page 33 of 53
ENVIRONMENTAL MANAGEMENT PLAN
5. Institutional/Implementation
Arrangements and Environmental
Management Capacity Building
Page 35 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
Management Indicators
Page 36 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
TABLE 4.1: PERFORMANCE INDICATORS
Management Indicators
Page 37 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
Page 38 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
Method
24 hours** 30 g/m3 120 g/m3 90 g/m3 Ultraviolet fluorescence
Carbon Monoxide (CO) 8 hours** 1000 5000 g/m3 2000 g/m3 Nondispersive infrared
g/m3 spectroscopy
1 hour 2000 1000 g/m3 4000 g/m3
g/m3
Lead (Pb) Annual* 0.50 1.0 g/m3 0.75 g/m3 AAS Method 24 hours after
g/m3 sampling using EPM 20000
or equivalent filter paper
24 hours** 0.75 1.5 g/m3 1.00 g/m3
g/m3
Respirable Particulate Annual* 50 g/m3 120 g/m3 60 g/m3
Matter
(RPM)- Size less than 24 hours** 75 g/m3 150 g/m3 100 g/m3
10m
Suspended Particulate Annual* 70 g/m3 360 g/m3 140 g/m3 Average flow rate not less
than 1.1 cum / minute
Matter (SPM) 24 hours** 100 g/m 3
500 g/m 3
200 g/m 3
Page 39 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
*Average Arithmetic mean of minimum 104 measurement in a year taken for a week
24 hourly at uniforminterval.
**24 hourly/8 hourly values should meet 98 percent of the time in a year
Permissible
Sl. Requirement Undesirable Effect Limit in the Methods of
Substance or
(Desirable Outside the Desirable Absence of Test (Ref. Remarks
No. Characteristic
Limit) Limit Alternate To IS)
Source
Essential Characteristics
b) Test at several
dilutions
3 Taste Agreeable - - 3025 (Part 7 Test to be
and 8) conducted only
after safety has
1984 been established
4 Turbidity NTU, 5 Above 5, consumer 10 3025 (Part -
Max. acceptance decreases 10)
1984
5 Ph Value 6.5 to 8.5 Beyond this range, the No relaxation 3025 (Part -
water will affect the 11)
mucous membrane 1984
and/or water supply
system
6 Total hardness 300 Encrustation in water 600 3025 (Part -
(as CaCO3) supply structure and 21)
MG/1, Max adverse effects on
domestic use 1983
Page 40 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
Permissible
Sl. Requirement Undesirable Effect Limit in the Methods of
Substance or
(Desirable Outside the Desirable Absence of Test (Ref. Remarks
No. Characteristic
Limit) Limit Alternate To IS)
Source
7 Iron (as Fe) 0.3 Beyond this limit 1 32 of 3025 : -
mg/1, Max taste/appearance are 1964
affected, has adverse
effect on domestic uses
and water supply
structures, and promotes
iron bacteria
8 Chlorides (as 250 Beyond this limit, taste, 1000 3025 (Part -
CI) mg/1, Max corrosion and 32)
palatability are affected
1988
9 Residual, free 0.2 - - 3025 (Part To be applicable only
chlorine, mg/1, 26) when water is chlorinated.
Min Tested at consumer end.
1986 When protection against
viral infection is required, it
should be Min 0.5 mg/1
Desirable Characteristics
6 Sulphate (as 200 Beyond this causes 400 3025 (Part May be extended up to
200 SO4) gastro intestinal irritation 24) 1986 400 provided (as Mg)
mg/1, Max when magnesium or does not exceed 30
sodium are present
Page 41 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
Permiss
Sl. Requirem Undesirable Effect ibleLimit Methods of
Substance or
ent Outside the Desirable in the Test (Ref. Remarks
No. Characteristic
(Desirable Limit Absenc To IS)
Limit) e of
Alternat
e
Source
8 Fluoride (as F)mg/1, Max 1 Fluoride may be kept aslow 1.5 23 of 3025: -
as possible. High fluoride may 1964
cause fluorosis
9 Phenolic compounds (As 0.001 Beyond this, it may cause 0.002 54 of 3025: -
C6H5OH) objectionabletaste and 1964
mg/1, Max odor
10 Mercury (as Hg) mg/1, 0.001 Beyond this, the water No (see Note) To be tested
Max becomes toxic relaxation Mercury ion when pollution is
analyzer suspected
11 Cadmium (as Cd), mg/1, 0.01 Beyond this, the water No (See note) To be tested
Max becomes toxic relaxation when pollution is
suspected
12 Selenium (as Se), mg/1, 0.01 Beyond this, the water No 28 of 3025: To be tested
Max becomes toxic relaxation 1964 when pollution is
suspected
13 Arsenic (As As) mg/1, max 0.05 Beyond this, the water No 3025 (Part To be tested
becomes toxic relaxation 37) 1988 when pollution is
suspected
14 Cyanide (As CN), mg/1, 0.05 Beyond this limit, thewater No 3025 (Part To be tested
Max becomes toxic relaxation 27) 1986 when pollution is
suspected
15 Lead (as Pb),mg/1, Max 0.05 Beyond this limit, thewater No (see note) To be tested
becomes toxic relaxation when pollution is
suspected
16 Zinc (As Zn).Mg/1, Max 5 Beyond this limit it cancause 15 39 of 3025: To be tested
astringent taste and an 1964) when pollution is
opalescence in water suspected
17 Anionic detergents (As 0.2 Beyond this limit it cancause 1 Methylene- To be tested
MBAS) mg/1, Max a light froth in water blue when pollution is
extraction suspected
method
18 Chromium (AsCr6+) mg/1, 0.05 May be carcinogenic above No 38 of 3025: To be tested
Max this limit relaxation 1964 when pollution is
suspected
19 Poly nuclear aromatic - May be carcinogenicabove - - -
hydrocarbons(as PAH) this limit
g/1,Max
20 Mineral oilmg/1, Max 0.01 Beyond this limit undesirable 0.03 Gas -
taste and odor after Chromatogr
chlorinationtake place -aphic
method
Page 42 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
Permissible
Sl. Requirement Undesirable Effect Limit in the Methods of
Substance or
(Desirable Outside the Desirable Absence of Test (Ref. Remarks
No. Characteristic
Limit) Limit Alternate To IS)
Source
22 Radioactive materials: 58 of -
3025:01964
23 a) Alpha - - 0.1 - -
emitters Bq/1,
Max
24 Beta emiters - - 1 - -
pci/1, Max
25 Aluminum (as 200 Beyond this limit taste 600 13 of -
Al), mg/1, becomes unpleasant 3025:1964
Max
26 Aluminum (as 0.03 Cumulative effect is 0.2 31 of 3025: -
A1), mg/1, reported to cause 1964
Max dementia
27 Boron, mg/1, 1 - 5 29 of 3025: -
Max 1964
Source: Indian Standard Drinking Water Specification-IS10500:1991
The measurements for monitoring noise levels would be carried out at all
designated locations in accordance to the Ambient Noise Standards
formulated by Central Pollution Control Board (CPCB) in 1989 (refer Table
4.5) Sound pressure levels would be monitored on twenty-four hour
basis. Noise should be recorded at a “A” weighted frequency using a “
slow time response mode” of the measuring instrument. The location,
duration and the noise pollution parameters to be monitored and the
responsible institutional arrangements are detailed in the Environmental
Monitoring Plan (Table 4.2).
TABLE 4.5: NOISE LEVEL STANDARDS (CPCB)
Commercial 65 55
area
Residential 55 45
area
Silence zone 50 40
Page 43 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
Page 44 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT PLAN
As part of the institutional strengthening and capacity building for environmental and
social management aspects of the project, a review of existing institutional setup was
carried out. Also, a review of previously suggested measures for institutional
strengthening in past projects was carried out. The review of previously proposed
measures was found to be very comprehensive and suitable for this project. It is
recommended that the same shall be followed and implemented.
Page 45 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT
PLAN
Progress Reporting
Compliance Reporting
NHIDCL is responsible for managing different components of the project that include
DPR preparation, Environmental and Social Assessment, contract preparation and
evaluation, Construction Supervision (through SC) among other components that
usually go with a project. The HIMS would provide a common platform for tracking of
project progress at different stages of the project. The system designed with preset
reporting formats, would allow progress tracking based on tasks completed and tasks
in progress. The dynamic progress reporting system helps in identifying the lacunae
in project progress and project execution.
Page 46 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT
PLAN
photographic evidence to the compliance report and geo-reference them through the
base maps using Web-GIS engine.
The reporting system followed in the past projects has been a linear and hierarchical
reporting system with the contractor reporting to the Supervision Consultants, who
in turn reported to the Authority. All reporting by the contractor and Supervision
Consultant was done on a quarterly basis.
As part of the capacity building for effective monitoring and evaluation of the work
performance, a new reporting system is proposed. This new reporting system is based
on the use of latest technology to make reporting easier and carried out at a greater
frequency, thereby ensuring prompt decision making on matters of immediate
importance such inability of the contractor to comply with the EMP or in case of any
situation of environmental emergency created at the project site.
The proposed reporting system is an intranet (WAN) or an internet (Web) based
computer application for reporting of project activities. The system would be a
Highway Information Management System (HIMS) based on the MIS concept
integrating environmental, social and overall project information on a common
platform. The application would provide multi-functionality ability to different levels
of user-groups depending on the responsibility endowed to that user group. Different
user groups that would be created through the project would essentially be
the
Page 47 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
stakeholders discussed above along with the top-management of NHIDCL and the
general public.
It is also recommended to bring in use of GIS as a tool for information monitoring and
reporting and project management. It is proposed to build a Web-GIS component into
the Highway Information Management System that would provide ease in
informationdissemination and greater understanding of project components to the
uninitiated useralong with making better and more informed decision-making for the
management level staff.
The modules of the proposed computer application are discussed below:
Application Database
o GIS engine
Page 48 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT
PLAN
Project design
Environmental information
Social Information
o Reporting system
o Data entry
o Data viewing
o Data Analysis
o Decision Support
Reporting System
Public Interface
Page 49 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT
PLAN
Regional
Office
Project
Stakehold
(We-b
Head Office Interfac
Web
Server
Regional Regional
Office Office
Page 50 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT
PLAN
The suggested rights, duties and functionalities of different user groups regarding
usage of Highway Information Management System have been discussed in the
following section.
The Highway Information Management System would facilitate more frequent review
of project progress for the senior management. It will also facilitate prompt decision-
making.
5.3.2.2 Authority
The Authority would use the HIMS as project management tool for coordinating
different project activities under the project. The Authority would have complete
access rights on the application but would primarily use the application for review and
analysis of information.
The Environmental cell will use the HIMS for reporting, analysis and compliance
monitoring by the data provided by contractor, SC or any other consultant.
The DPR consultant would use the application for reporting progress on the project
design process and submission of technical reports, clarifications or any other data as
required or asked for by the Authority.
The SC will use the application as a tool for reporting the project progress through the
web-interface facilitating frequent project reporting and progress tracking by the
Authority. The progress tracking system of the application would provide tracking of
minute details on the status of project activities including design, environmental and
social aspects to be filled in by the SC.
Page 51 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT
PLAN
5.3.2.6 Contractor
The contractor will use the application for furnishing information on project progress
that will first go to the SC, who will then validate the information by verifying onto the
ground and then send it to the Authority though the HIMS.
The website for Authority will incorporate the web module of the application and
provide access to information on the project to the general public. The information
that would be accessible to the general public include project information (including
design), project implementation progress, project reports (EIA, SIA, EMP). Information
dissemination would also be done by GIS based reporting that would be able to
pinpoint the project activities and mitigation/enhancement measures onto a map for
greater comprehensibility/appreciation to a common man. The GIS engine would
facilitate functions like zooming in/out, preset query analysis, other Web-GIS
functionality. A section of the application would be devoted to invite comments,
suggestions and concerns of the general public, which shall be directly accessible to
the senior officials for different concerns (Environmental, Social, equity in benefit
distribution to the PAPs etc.) voiced by the public.
o Project Progress
o Project Deliverables
Page 52 of 53
“Six Laning of Paravoor (Design Ch. 417.000) – Kottunkulangara (Design
Ch.454.500) section of New NH-66 (Old NH-47) in the State of Kerala under
Bharatmala Pariyojna on EPC mode”.
ENVIRONMENTAL MANAGEMENT
PLAN
Construction Progress
RAP measures
o Compliance reporting
Page 53 of 53