Graphical techniques are popular because they are easy to understand and use. These plans
work with a few variables at a time to allow planners to compare projected demand with existing
capacity. They are trial-and-error approaches that do not guarantee an optimal production plan,
but they require only limited computations and can be performed by clerical staff. Following are
the five steps in the graphical method:
2. Determine capacity for regular time, overtime, and subcontracting each period.
3. Find labor costs, hiring and layoff costs, and inventory holding costs.
4. Consider company policy that may apply to the workers or to stock levels.
If demand for June increases to 1,200 (from 1,100), [Answer: The daily rate for June will go up
to 60, and average production will increase to 50.8 (6,300/124)
1|Page
Possible strategy
(Call it plan 1) for the manufacturer described in Example 1 is to maintain a constant workforce
throughout the 6-month period.
A second (plan 2) is to maintain a constant workforce at a level necessary to meet the lowest
demand month (March) and to meet all demand above this level by subcontracting. Both plan 1
and plan 2 have level production and are, therefore, called level strategies.
Plan 3 is to hire and lay off workers as needed to produce exact monthly requirements—a chase
strategy.
Cost of increasing daily production rate (hiring and training) $300 per unit
Analysis of plan 1 Approach: Here we assume that 50 units are produced per day and that we
have a constant workforce, no overtime or idle time, no safety stock, and no subcontractors.
The firm accumulates inventory during the slack period of demand, January through March, and
depletes it during the higher-demand warm season, April through June. We assume beginning
inventory =0 and planned ending inventory= 0
Table 1.1
2|Page
Month Productio Production Demand Monthly Ending
n at Forecast Inventory Inventory
Days 50 Units Change
per Day
1850
Total units of inventory carried over from one month to the next month = 1,850 units
Workforce required to produce 50 units per day = 10 workers because each unit requires 1.6
labor-hours to produce, each worker can make 5 units in an 8-hour day.
If demand for June decreases to 1,000 (from 1,100), what is the change in cost?
Total inventory carried will increase to 1,950 at $5, for an inventory cost of $9,750 and total cost
of $108,950
3|Page
Although a constant workforce is also maintained in plan 2, it is set low enough to meet demand
only in March, the lowest demand-per-day month. To produce 38 units per day (800/21) in-
house, 7.6 workers are needed. (You can think of this as 7 fulltime workers and 1 part-timer.) All
other demand is met by subcontracting. Subcontracting is thus required in every other month. No
inventory holding costs are incurred in plan 2.
SOLUTION _ Because 6,200 units are required during the aggregate plan period, we must
compute how many can be made by the firm and how many must be subcontracted:
Regular-time labor $ 75,392 (= 7.6 workers * $80 per day * 124 days)
Subcontracting $ 29,760
If demand for June increases to 1,200 (from 1,100), what is the change in cost? Subcontracting
requirements increase to 1,588 at $20 per unit, for a subcontracting cost of $31,760 and a total
cost of $107,152.
The final strategy, plan 3, involves varying the workforce size by hiring and layoffs as
necessary. The production rate will equal the demand, and there is no change in production from
the previous month, December.
SOLUTION _ Table 1.2 shows the calculations and the total cost of plan 3. Recall that it costs
$600 per unit produced to reduce production from the previous month’s daily level and $300 per
unit change to increase the daily rate of production through hirings.
Table 1.2
4|Page
Daily Production Cost of Cost of Cost $
rate Cost
Increasing Decreasing
(demand *
1.6 Production Production
Thus, the total cost, including production, hiring, and layoff, for plan 3 is $117,800.
Note the substantial cost associated with changing (both increasing and decreasing) the
production levels.
If demand for June increases to 1,200 (from 1,100), what is the change in cost? [: Daily
production for June is 60 units, which is a decrease of 8 units in the daily production rate from
May’s 68 units, so the new June layoff cost is $4,800 1= 8 * $600 with a total plan 3 cost of
$114,800.]
The final step in the graphical method is to compare the costs of each proposed plan and to select
the approach with the least total cost. A summary analysis is provided in Table 1.3. We see that
because plan 2 has the lowest cost, it is the best of the three options.
5|Page
(constant
Inventory $ 9,250 0 0
carrying
Overtime labor 0 0 0
Hiring 0 0 9,000
Layoffs 0 0 9,600
Subcontracting 0 29,760 0
N.B. Many other feasible strategies can be considered in a problem like this, including
combinations that use some overtime.