1-Mos Block Dac With Rams
1-Mos Block Dac With Rams
1-Mos Block Dac With Rams
Project Name:
LIST OF CONTENTS
Page
This Work Method Statement refers to various work procedures contained within project
control documents, which explains and covers the Concrete Masonry Work.
3.1 This project procedure is a controlled document as required by the Project Policyand
issued in accordance with the contractual requirements.
3.2 Revision of this document will be issued in accordance with the project procedure
andrequirement.
PC Project Coordinator
CM Construction Manager
MS Method Statement
FM Checklist / Form
RA Risk Assessment
ITR Inspection & Testing Request
QCP Quality Control Procedure
ITL Independent Testing Laboratory
QA / QC Quality Assurance / Quality Control
HSE Health & Safety Engineer
BS British Standard
ASTM American Society for Testing and Materials
PTW Permit to Work
3
Client: Telalah Residence Project Contractor:
Project Name:
5.0 RESPONSIBILITY
6.0 Resources
Nail gun
Trowel
Mason’s Hammer
Blocking chisel
Mashing hammer
Level bar
Mason’s line
Steel square
Brushes
Shovels
Electrical drills
6.2 Materials
Sand
Cement
Steel bars.
Concrete
Block
4
Client: Telalah Residence Project Contractor:
Project Name:
6.3 Manpower
Foreman
Site Engineer
Surveyor
Masons
Safety Officers
Helpers
Using hand mix 1:3, it shall be mix in a clean and water tight
platform. The mortar shall be mixed until dry
Uniform mix is obtained then water is added and mix
continuously until a homogenous mix is obtained.
Freshly mix mortar shall be protected at all times to avoid
contamination and prevent excessive evaporation.
5
Client: Telalah Residence Project Contractor:
Project Name:
6
Client: Telalah Residence Project Contractor:
Project Name:
Project specific HSE Plan covering all aspects of construction safety, environmental
protection and unity protection has been submitted to the Client for approval. This
plan included:
A dedicated Health and Safety team will be deployed to the site under the
supervision of a Health and Safety Engineer and Safety Officers. The project
will be controlled as per the approved health and Safety plan.
It is DAC policy that every employee shall be provided with a healthy and
safe environment in Which to work. To this end, every effort will be made
and positive action taken at all times, by all employees, to ensure healthy and
safe working conditions at all company project work site and facilities
The general philosophy is each person on site is responsible for safe working practice
HSE team shall monitor, guide and train all employees to achieve a safe working
environment by implementing Work Rules to Achieve these goals.
Regular job safety analysis will be done
Regular awareness programs will be conducted
Special training programs
Encourage communication from work force
Encourage daily reminders by each supervisors
Weekly surveillance of all rigging equipment and tools, site manpower distribution
Fire prevention program, identify hazardous areas, material and storage, establish
Alarms response teams, regular checks on firefighting equipment, fire watcher’s
Training and firefighting training.
Daily tool box meetings for supervisory and non-supervisory work force.
7
Initial Risk Residual Risk Action Verified
Score Score
Consequence
Likelihood
Risk Rating
Consequence
Likelihood
Risk Rating
Task or Activity Control Measure
Hazard Possible Consequence(s)
By
By
Delivering, unloading & storing Plant & Traffic movement First Aid Cases, Medical Supervisor to ensure the following:
of Blocks , plastering materials Run over by vehicles Treatment Cases, Don’t allow workers or operators or take rest near or under vehicle Constructi
and fitting using Trailer and Hit by reversing equipment Amputations & Disabilities Workplace and all access to be well illuminated on
unloading by boom truck or Overhead Obstructions Fatalities, Legal liabilities,
Enforce speed limit Manager,
Trailer etc. Vehicle break down Schedule Delays, Site
Investigation costs, Loss of Ensure materials are properly secured /tied to avoid from falling
Collision with other vehicles 3 4 12 1 4 4 Engineer HSE Officer
Reputation Ensure Blocks must be in weighted capacity
Personal injury Superviso
Fatality due to poor lightning & visibility Ensure Blocks not to be stacked above height of trolley r&
(operation at night). Foreman&
Over Loading Of materials (fall of operatives
materials & personal injury).
Material Storing Slips trips & Fall First Aid Cases, Medical Ensure accesses are kept clear at all time
Poor Housekeeping Treatment Cases, Disabilities Housekeeping to be carried regularly throughout the day Constructi
Fall of materials (Over Stacking of Fatalities, Legal liabilities,
Supervisors to ensure operators stacking materials properly in safe on
Materials. Property damage, Schedule Manager,
condition
Fall of workers (obstructed access) Delays, Investigation costs, Site
Loss of Reputation, High Provide adequate lighting especially during night hours
Scattered Materials (Personal injury). 3 4 12 1 4 4 Engineer HSE Officer
Irritation to skin & eyes, lunge disease Insurance Premiums. Loss of Appropriate space around storage area for workers to move safely Superviso
(expose to cement dust). workers morale without tripping or being trapped r&
Maintain good housekeeping Foreman&
Cement to be stored in well ventilated area operatives
Fall from height Medical Treatment Cases, Ensure proper working platform with complete fall protection
Falling objects Disabilities Fatalities, Legal Ensure scaffolding platform properly erected with safe to use Tag
Installation Of Blocks & Protruding objects liabilities, Property damage,
Hand tools must be secured
Plastering work. Access & egress Schedule Delays,
Investigation costs, Loss of Materials strictly not allowed to be stored on platform
Sharp edges of tools & equipment not
easily spotted. Reputation, High Insurance Ensure avoid reaching & climbing on handrail
Back injury due to improper manual Premiums. Loss of workers Scaffold access must be free from obstruction
handling technique. morale Ensure sufficient illumination at night in working area Constructi
Fall of tools, equipment & materials. Ensure while installing the fitting & support to use safe tools to avoid any on
Unsafe practices during job execution injury Manager,
(personal injury fall from height) Site
Housekeeping for the area after completion of the job.
Slips trips & falls 3 4 12 1 4 4 Engineer HSE Officer
Provide guards to sharp edges of all equipment
Poor housekeeping Superviso
Fatality due to poor lightning & visibility Experienced & competent workers & supervisors to do the work. r&
(operation at night). Maintain proper manual lifting technique, divide load . Foreman&
Stuck in between during installation. Assign sufficient numbers of personnel who could sustain the load when operatives
Flying Particles (eye injury) doing manual handling
Collapse of platform (unstable ground, Observed proper communication between the team during execution
overload).
Ensure area well arrange & free from any obstacles to prevent slips
Over head obstruction (face eye injury)
hazard
Initial Risk Residual Risk Action Verified
Score Score
Consequence
Likelihood
Risk Rating
Consequence
Likelihood
Risk Rating
Task or Activity Control Measure
Hazard Possible Consequence(s)
By
By
Confined Space Works Lack of communication First Aid Cases, Medical Confined space entry safe work practices should be followed.
Lack of ventilation Treatment Cases, Supervisor shall review all emergency procedures with al entrants
Oxygen deficient /enrichment Amputations & Disabilities
Gas Testing must be done before start of any work in CS
Asphyxiation Fatalities, Legal liabilities,
Schedule Delays, Ventilation shall be equipped to ensure adequate airflow
Fire
Investigation costs, Loss of Sufficient illumination shall be provided.
Electric Hazard Superviso
Noise Reputation Hearing protection apparatus shall be worn.
r&
Poor visibility 4 4 16 Any tools to be used in CS shall be check thoroughly in advance 1 4 4
Foreman&
HSE Officer
Fall & Trip Hazards Sufficient no of inspected & approved fire extinguisher shall be placed operatives
Miscommunication around work area in case of possible fire.
Lack of emergency preparedness Maintain housekeeping & use proper access to prevent slips, trips & falls.
Worker must be provided with frequent rest breaks & job relations
Ensure CS Entrance Is closed properly if there is no work.
Housekeeping Sharp objects First Aid Cases, Medical Ensure access is free from obstructions
Slips trips & falls Treatment Cases, Housekeeping must be done after finishing the pouring and before
Amputations & Disabilities Superviso
Fatalities, Legal liabilities, leaving the site. r&
3 3 9 1 4 4 HSE Officer
Schedule Delays, All tools and remaining material to be returned back to store Foreman&
Investigation costs, Loss of operatives
Reputation
Working under high Heat exhaustion First Aid Cases, Medical Arrange adequate drinking water & rest shelter
temperature, direct sunlight, Heat stroke Treatment Cases, Drinking plenty of water
dusty high wind Amputations & Disabilities
Dehydration If feeling something unusual immediately inform supervisor
Fatalities, Legal liabilities,
Personal injuries to high temperature Schedule Delays, Makeshift to operate the routine work Superviso
Sun stroke & tiredness Investigation costs, Loss of Do not allow alone work r&
4 4 16 1 4 4 HSE Officer
Reputation Frequent breaks Foreman&
operatives
Proper supervision available
Heat stress training to be provided
Proper signages for drinking water
Working at night shift Poor visibility due to darkness /poor First Aid Cases, Medical Proper illumination & lighting
illumination Treatment Cases, Ensure proper communication & close supervision
Amputations & Disabilities Superviso
Lone worker Fatalities, Legal liabilities,
Avoid lone working at night shift
r&
Schedule Delays,
3 4 12 Proper training for workers on emergency response in case of any 1 4 4
Foreman&
HSE Officer
Investigation costs, Loss of emergency operatives
Reputation
Initial Risk Residual Risk Action Verified
Score Score
Consequence
Likelihood
Risk Rating
Consequence
Likelihood
Risk Rating
Task or Activity Control Measure
Hazard Possible Consequence(s)
By
By
PM – Project Manager
Project Telalah Residential Villas CM – Construction Manager