Lecture 3
Lecture 3
GRDAMAND MOHAMMED
grdamand_etc@yahoo.co.uk
Lecture 3
Summery of Lecture 2
Tracked Deformation/ Measurement
1. Longitudinal Track Profile
2. Visual inspection
3. Ballast / Sub-ballast / Subgrade Investigation
4. Radar Survey
5. Structural Evaluation
Ballast Properties
1. Particle Strength
2. Granular Material Behaviour
3. Properties of an Ideal Ballast
Permanent Deformation within Ballast
Strength and Permanent Deformation
Ballast Fouling
2
Lecture Contents
SUB-BALLAST AND SUBGRADE
INHERENT TRACK QUALITY
‘BEAM ON ELASTIC FOUNDATION’ ANALYSIS
3
SUB-BALLAST & SUBGRADE
4
SUB-BALLAST & SUBGRADE
Low Stiffness
Second Case
5
SUB-BALLAST & SUBGRADE
Strain-gauged
band
vs
SUB-BALLAST & SUBGRADE
9
SUB-BALLAST & SUBGRADE
80MPa
100MPa
120MPa
Sub-ballast
SUB-BALLAST & SUBGRADE
2. What is Sub-ballast?
• Often, sub-ballast is just ballast which is a little lower down in
the structure.
• On an old track, which has been re-ballasted many times, the
most recent, clean ballast will sit on top of older layers of
increasingly fouled ballast.
• These layers can be thought of as sub-ballast, but were never
designed to be so.
11
SUB-BALLAST & SUBGRADE
12
SUB-BALLAST & SUBGRADE
As a Result Sub-ballast:
Usually a broadly-graded crushed rock
Sometimes in practice it is just underlying fouled ballast
14
SUB-BALLAST & SUBGRADE
• The interlock between the grid and the ballast (or subballast)
stones means that the stones are prevented from moving
sideways.
• This is a form of confinement.
• It means that the ballast ‘thinks’ it is sitting on a stiff support
and so appears to be stiff, strong and to resist deformation.
• Cost: around $5.00 per square metre – which would buy about
80mm of sub-ballast)
improved by 0.5
Renewal
the geogrid 0
0 50 100 150 200
Week Number
SUB-BALLAST & SUBGRADE
The University
of Nottingham
Railway Test
Facility
3 Sleepers
95kN load/sleeper
Sinusoidal loading
Loaded 90 out of phase
3Hz ≈ 17mph
1m ballast/subgrade
Tamping bank available
SUB-BALLAST & SUBGRADE
Railway Test 8
Facility 6
0
0 200000 400000 600000 800000 1000000
Number of load applications
SUB-BALLAST & SUBGRADE
35
Svertical Soverburden
Geogrid
Shorizontal spreads load
SUB-BALLAST & SUBGRADE
ii. A Stabilised or Bound Foundation
• Pretty obviously, if the behaviour of ballast is so affected by
what it is sitting on, why not make the support layer really stiff?
The options are:
• In-situ stabilisation using cement, lime or both Placement of a plant-
mixed layer of cement bound material An asphalt layer of some sort
21
SUB-BALLAST & SUBGRADE
• For new track, this is not too difficult (though it requires
engineering knowledge on the part of the railway authority!).
• For example, it is standard practice to add an asphalt layer to
the foundation of heavily used tracks in Italy. The result is that
the ballast receives excellent support and will therefore
deteriorate much more slowly.
Stabilised/bound layer
23
SUB-BALLAST & SUBGRADE
• Conventional ‘dig out and replace’
a) remove rails and sleepers to side of track
b) remove ballast
c) dig out and remove soft or contaminated materials
d) replace with a ‘filter’ (sand layer or geotextile), and compacted high
quality fill, possibly cement or lime stabilised, then sub-ballast
e) replace ballast (probably fresh material)
f) relay track
g) top up with ballast
h) tamp
• This has now been used in several places where other treatments didn’t
seem to work; also helpful in combating critical velocity problems.
THICKNESS DESIGN
4. Design of
Ballast/Sub-ballast
thickness
• As well as the effect the
subgrade has on the
behaviour of the layers
above, it has the potential
to ‘fail’ itself. It is basically a
bearing capacity type
failure.
26
THICKNESS DESIGN
Drainage
Even a potentially good subgrade will lose strength and
stiffness if too wet.
Put a drain in increase inherent track quality
Drainage
3. Critical Velocity
In some cases, no matter how well the track is constructed, the
subgrade is of such low stiffness that a further effect comes into
play.
• Train loading causes a pulse of load to spread through the
ground.
Wave propagation
with speed v
32
INHERENT TRACK QUALITY
3. Critical Velocity
• Rapid train movement means that the waves in the ground are
‘foreshortened’.
Train speed V
33
INHERENT TRACK QUALITY
3. Critical Velocity
Firm ground
When the train speed
approaches the speed
of ground waves,
there will be
‘constructive
interference’.
The result is large
amplitude vibrations.
Peak here if
Soft ground
INHERENT TRACK QUALITY
3. Critical Velocity
• On most lines this is not a problem. It is only when track runs
over marshy ground that the effect is significant.
• Speed restrictions have to be placed in these cases.
• The speed of wave propagation is termed the critical velocity
and trains have to keep well below this value.
35
TRACK ANALYSIS
1. Idealising Track
Deflections
y
x P
M E, I
F 36
R = ky
TRACK ANALYSIS
• The first step is to consider a small length of rail, ẟx, and to look
at the forces applying to the element.
37
TRACK ANALYSIS
d4y/dx4 = - ky/EI
0.5
1.5
2.5
TRACK ANALYSIS
From this we can calculate not only the deflected shape of the
track but also the shear and bending moment distribution.
TRACK ANALYSIS
• Example:
42
TRACK ANALYSIS
Solution
43
TRACK ANALYSIS
44
…next lecture
SUB-STRUCTURE STRESS ANALYSIS
TRAIN DYNAMICS
45