Ejemplo Verification Teste DNV - LiDAR Zephir
Ejemplo Verification Teste DNV - LiDAR Zephir
Ejemplo Verification Teste DNV - LiDAR Zephir
MARCH 2018
SITE INSTALLATION REPORTS
Wind Resource Mapping in the Maldives
This report was prepared by DNV GL, under contract to The World Bank.
This document is an interim output from the above-mentioned project, and the content is the sole
responsibility of the consultant authors. Users are strongly advised to exercise caution when utilizing the
information and data contained, as this may include preliminary data and/or findings, and the document has
not been subject to full peer review. Final outputs from this project will be marked as such, and any
improved or validated wind resource data will be incorporated into the Global Wind Atlas.
The World Bank, comprising the International Bank for Reconstruction and Development (IBRD) and the
International Development Association (IDA), is the commissioning agent and copyright holder for this
publication. However, this work is a product of the consultants listed, and not of World Bank staff. The
findings, interpretations, and conclusions expressed in this work do not necessarily reflect the views of The
World Bank, its Board of Executive Directors, or the governments they represent.
The World Bank does not guarantee the accuracy of the data included in this work and accept no
responsibility for any consequence of their use. The boundaries, colors, denominations, and other
information shown on any map in this work do not imply any judgment on the part of The World Bank
concerning the legal status of any territory or the endorsement or acceptance of such boundaries.
The material in this work is subject to copyright. Because The World Bank encourages dissemination of its
knowledge, this work may be reproduced, in whole or in part, for non-commercial purposes as long as full
attribution to this work is given. Any queries on rights and licenses, including subsidiary rights, should be
addressed to World Bank Publications, The World Bank Group, 1818 H Street NW, Washington, DC 20433,
USA; fax: +1-202-522-2625; e-mail: pubrights@worldbank.org. Furthermore, the ESMAP Program Manager
would appreciate receiving a copy of the publication that uses this publication for its source sent in care of
the address above, or to esmap@worldbank.org.
Contents:
1. This document is intended for the sole use of the Client as detailed on the front page of this document to
whom the document is addressed and who has entered into a written agreement with the DNV GL entity
issuing this document (“DNV GL”). To the extent permitted by law, neither DNV GL nor any group
company (the "Group") assumes any responsibility whether in contract, tort including without limitation
negligence, or otherwise howsoever, to third parties (being persons other than the Client), and no company
in the Group other than DNV GL shall be liable for any loss or damage whatsoever suffered by virtue of any
act, omission or default (whether arising by negligence or otherwise) by DNV GL, the Group or any of its or
their servants, subcontractors or agents. This document must be read in its entirety and is subject to any
assumptions and qualifications expressed therein as well as in any other relevant communications in
connection with it. This document may contain detailed technical data which is intended for use only by
persons possessing requisite expertise in its subject matter.
2. This document is protected by copyright and may only be reproduced and circulated in accordance with the
Document Classification and associated conditions stipulated or referred to in this document and/or in DNV
GL’s written agreement with the Client. No part of this document may be disclosed in any public offering
memorandum, prospectus or stock exchange listing, circular or announcement without the express and prior
written consent of DNV GL. A Document Classification permitting the Client to redistribute this document
shall not thereby imply that DNV GL has any liability to any recipient other than the Client.
3. This document has been produced from information relating to dates and periods referred to in this
document. This document does not imply that any information is not subject to change. Except and to the
extent that checking or verification of information or data is expressly agreed within the written scope of its
services, DNV GL shall not be responsible in any way in connection with erroneous information or data
provided to it by the Client or any third party, or for the effects of any such erroneous information or data
whether or not contained or referred to in this document.
4. Any wind or energy forecasts estimates or predictions are subject to factors not all of which are within the
scope of the probability and uncertainties contained or referred to in this document and nothing in this
document guarantees any particular wind speed or energy output.
Task and objective: provide a permanent record of the site characteristics and measurement equipment
for the LIDAR at Thulusdhoo.
Reference to part of this report which may lead to misinterpretation is not permissible.
5 REFERENCES ................................................................................................................ 17
The World Bank (the “Client”) has retained Garrad Hassan America, Inc. (“DNV GL”) to provide a
validated mesoscale wind atlas for the Maldives, including associated deliverables and wind energy
development training courses. During Phase 1 of the project, which has been completed, preliminary
mesoscale mapping was carried out covering the entire country [1]. Phase 2 of the project, which is
currently underway, involves the installation of two Light Detection and Ranging (LIDAR) based wind
measurement sites in the country. Meteorological data collected at these sites over a two-year period will
provide the basis for validating the mesoscale modeling outputs from Phase 1.
LIDAR units and associated equipment have been commissioned at the two measurement sites,
Hoarafushi and Thulusdhoo, in April 2017.
This report documents the installation of the LIDAR site at Thulusdhoo, and presents the characteristics
of the site, as well as details of the measurement equipment, power supply and data acquisition system.
2 SITE INFORMATION
Male
MALDIVES
Figure A-1 in Appendix A presents a map of the site vicinity, showing 0 and 3 m elevation contours
based on SRTM-1 data [2]. It should be noted that SRTM-1 data can be influenced by trees and buildings,
and may not accurately reflect the ground elevation. It should also be noted that since the available
SRTM-1 data predates the recent land reclamation, the reclaimed land does not appear on the contour
map. Figure A-2 in Appendix A presents imagery from Google Earth showing the reclaimed land for
reference.
Figure A-3 in Appendix A presents a map of estimated surface roughness zones in the vicinity of the site.
It should be noted that this map does take into consideration the reclaimed land.
Table 2-1 presents details of the site location coordinates and elevation.
Coordinates Coordinates
(Geographic)2 (UTM, Zone 43 N)2
Commissioning Elevation
Site name
Date [m ASL]1
Latitude Longitude Eastings Northings
[degrees] [degrees] [m] [m]
2. Datum: WGS 84
3 SITE EQUIPMENT
The unit is secured to a concrete pad footing and is enclosed by fencing. Figure 3-1 to Figure 3-3 show
photographs of the LIDAR unit as installed on site.
The LIDAR unit is equipped with a washing system for cleaning the window, as shown in Figure 3-4. The
washing system is connected to an external cleaning fluid supply bottle, as shown in Figure 3-5.
Figure 3-5 Base of LIDAR unit showing cleaning fluid supply bottle
The LIDAR simultaneously records 10-minute average, maximum, minimum, and standard deviation
statistics for the horizontal and vertical wind speeds, and average and standard deviation statistics for
wind direction, at eleven specified measurement heights between 10 m and 200 m above the top of the
unit. The LIDAR measurement configuration is summarised in Table 3-2 below.
Measurement
Measurement Measurement
heights Unit Channels
parameter interval
[m AGL]
Mean / minimum /
Horizontal wind
m/s maximum /
11, 20, 30, 39, speed
standard deviation 10 minutes
50, 60, 80,
(continuous
100, 120, 150,
Vertical wind speed m/s Mean scan)
200
Wind direction1 Degrees Mean
The LIDAR unit has been subjected to independent testing and performance verification in accordance
with the second edition of the reviewed IEC 61400-12-1 standard, Annex L [2][3]. A copy of the
performance verification report is presented in Appendix D.
Figure 3-7 shows the location of the meteorological station in relation to the LIDAR enclosure.
Figure 3-8 below shows a close up photograph of the meteorological station taken during the installation
process.
The batteries located inside the enclosure are shown in Figure 3-10.
Table 3-4 summarizes the key specifications of the power supply system.
2 x 12V 100 Ah, AGM deep cycle Victron Energy Blue Power 12/25 - 12V, 25A
3.4 Communications
The system uses an external 3G modem and directional antenna for data transmission.
DNV GL will provide both raw and quality controlled data from the LIDAR device.
A laser scan determines the axis of the wind direction. The direction of the wind along that axis is then
determined in conjunction with the met station reading.
If the met direction in the above diagram pointed in the opposite direction, the reported direction would
be the other axial possibility in the first diagram. For example:
The Met Station direction reading only needs to be very coarse for this purposes as is only used to
determine the direction ‘phase’. However, if the met station is shadowed or if it is placed in areas of wind
recirculation then there is the potential for a 180 degrees direction ambiguity to result.
Given the proximity of the LIDAR device and met station to buildings, trees and other obstacles, the
potential for a 180 degree ambiguity in the wind direction measurements exists. Care should be taken
when using the raw data from the LIDAR device that instances where the 180 degree direction ambiguity
exists are corrected.
b) Check the LIDAR device and ancillary equipment have not been damaged or soiled
As a first step, local staff on the islands will perform a visual inspection of the unit and correct any issues
if possible. If further inspection, troubleshooting, or maintenance of the unit is required, a corrective
maintenance team consisting of in-country trained personnel from DNV GL’s Local Partner will visit the
site. In cases where the issue cannot be resolved by local staff, and where appropriate, expert personnel
from DNV GL will travel from Australia to the Maldives to perform the necessary corrective maintenance.
DNV GL will remotely assist with the interventions at all stages of the process.
Figure A-2 Satellite imagery of Thulusdhoo LIDAR site showing recently reclaimed land on western side of island
W (350442, 483661) E
1. This document is intended for the sole use of the Client as detailed on the front page of this document to
whom the document is addressed and who has entered into a written agreement with the DNV GL entity
issuing this document (“DNV GL”). To the extent permitted by law, neither DNV GL nor any group
company (the "Group") assumes any responsibility whether in contract, tort including without limitation
negligence, or otherwise howsoever, to third parties (being persons other than the Client), and no company
in the Group other than DNV GL shall be liable for any loss or damage whatsoever suffered by virtue of any
act, omission or default (whether arising by negligence or otherwise) by DNV GL, the Group or any of its or
their servants, subcontractors or agents. This document must be read in its entirety and is subject to any
assumptions and qualifications expressed therein as well as in any other relevant communications in
connection with it. This document may contain detailed technical data which is intended for use only by
persons possessing requisite expertise in its subject matter.
2. This document is protected by copyright and may only be reproduced and circulated in accordance with the
Document Classification and associated conditions stipulated or referred to in this document and/or in DNV
GL’s written agreement with the Client. No part of this document may be disclosed in any public offering
memorandum, prospectus or stock exchange listing, circular or announcement without the express and prior
written consent of DNV GL. A Document Classification permitting the Client to redistribute this document
shall not thereby imply that DNV GL has any liability to any recipient other than the Client.
3. This document has been produced from information relating to dates and periods referred to in this
document. This document does not imply that any information is not subject to change. Except and to the
extent that checking or verification of information or data is expressly agreed within the written scope of its
services, DNV GL shall not be responsible in any way in connection with erroneous information or data
provided to it by the Client or any third party, or for the effects of any such erroneous information or data
whether or not contained or referred to in this document.
4. Any wind or energy forecasts estimates or predictions are subject to factors not all of which are within the
scope of the probability and uncertainties contained or referred to in this document and nothing in this
document guarantees any particular wind speed or energy output.
DNV GL
Project name: ZP 597 DNV GL - Energy
Report title: Independent analysis and reporting of ZephIR Renewables Advisory
Lidar performance verification at Pershore test Suite 25, Level 8,
site, including IEC compliant validation analysis 401 Docklands Drive, Docklands,
Customer: The World Bank, Victoria 3008, Australia
1818 H Street, N.W. Tel: +61 3 9600 1993
Washington, DC 20433
Contact person: Sandeep Kohli
Date of issue: 6 March 2018
Project No.: 702909
Report No.: 702909-AUME-R-07, Rev. B
Reference to part of this report which may lead to misinterpretation is not permissible.
A 30 Aug 2017 Draft (electronic version, only) M Quan F Dahhan, B Schmidt T Gilbert
DNV GL
Table of contents
1 INTRODUCTION .............................................................................................................. 2
4 RESULTS ..................................................................................................................... 11
4.1 System availability 11
4.2 Data availability 12
4.3 Data filtering 12
4.4 Wind speed comparison 12
4.5 Wind direction comparison 16
4.6 Performance verification according to revised IEC standard, Annex L 17
4.6.1 Performance verification uncertainty 19
6 CONCLUSION ............................................................................................................... 26
7 REFERENCES ................................................................................................................ 28
8 GLOSSARY ................................................................................................................... 29
Appendices
KEY PERFORMANCE INDICATORS AND ACCEPTANCE CRITERIA, IN LINE WITH
[2] 30
LIST OF FIGURES
Figure 1: Map of the Pershore test site near Throckmorton, UK. The position of the reference mast is
marked by a red dot. 3
Figure 2: Schematic of the sensor level and boom distribution at the 90.5 m mast, as taken from [1].
See Table 1 for sensor distribution according to the alphanumeric label per boom (A to N) and the
actually valid serial numbers. 5
Figure 3: Typical setup of ZephIR Lidars next to the reference mast at Pershore. 7
Figure 4: Wind direction sectors used to select undisturbed wind speed data from oppositely arranged
cup carrying booms for comparison. 9
Figure 5: Plots of linear wind speed regression results for 20, 45, 70 and 91 m (note that regression
slopes are forced through the origin) 15
Figure 6: Regression plot of wind direction comparisons at 44 m (left) and 88 m (right) 16
Figure 7: Comparison of the horizontal wind speed component for ZP 597 – 20 m (top left), 45 m (top
right), 70 m (bottom left), 91 m (bottom right) 18
Figure 8: Bin-wise comparison of the horizontal wind speed component for ZP 597 – 20 m (top left), 45
m (top right), 70 m (bottom left), 91 m (bottom right) 19
DNV GL has prepared an independent analysis and report of a ZephIR Lidar performance verification. In
this analysis and report, the ZephIR Lidar with the serial number ZP 597 will be discussed. The
verification measurements for this device were performed by ZephIR Ltd. at their test site in Pershore,
UK between 2016-12-23 to 2017-01-31.
The met tower was equipped with classical anemometry components (cup anemometers, wind vanes etc.)
serving as the verification reference for the Lidar wind speed and wind direction comparisons. Those
comparisons were performed in line with a Remote Sensing (RS) best practice verification approach as
developed within the EU-FP7-Projekt NORSEWInD [2] against corresponding Key Performance Indicators
(KPIs) and Acceptance Criteria (ACs; compare Appendix A).
In addition, a performance verification and uncertainty calculation is carried out in accordance with the
second edition of the reviewed IEC 61400-12-1 standard, Annex L [4].
DNV GL is accredited according to ISO 17025 for measurements on wind turbines and for wind resource
measurements and energy assessments. DNV GL is also a full member of the network of measurement
institutes in Europe ‘MEASNET’.
The following description and figures of the Pershore test site, which is a disused air field, are taken from
a technical report by ZephIR Ltd. [1]:
The terrain in the vicinity of the mast is flat and covered with sparse low growing vegetation. A number
of hangars and outbuildings exist in sectors between 260° and 317° at distances between 300m and
700m from the mast. These buildings are estimated not to exceed 14m in height. Approximately 500 m
to the North-East lies the small village of Throckmorton which consists of a few scattered farms and
houses. 700 m to the South-West of the mast between 190° and 240° lies an area of spoil heaps and
filtration pools associated with a mining operation. On a wider scale the site is surrounded by flat arable
land that is devoid of any dense closed canopy forest. The larger conurbations of Pershore and Evesham
lie at distances of 5km and 9km to the South West and South East respectively.
Figure 1: Map of the Pershore test site near Throckmorton, UK. The position of the reference
mast is marked by a red dot.
The site specifications given in the above description have been verified during a site visit by a DNV GL
expert on 2015-09-01, see [8]. Further details on the site are given in [1], a 360° photo round is shown
in Appendix B.
In the following sections technical details and specifications of the measuring equipment are described.
This description covers the meteorological reference mast (met mast) including its sensors and data
acquisition system as well as the tested Lidar.
The following items regarding the meteorological measurement systems have been verified during the
above mentioned site visit:
• Site suitability and exact positions of mast and Lidar test stand
• Validity of MEASNET [6] calibrations of cups and correct application of calibration factors and
offsets
The mast has been constructed to be fully compliant with the 2005 edition of IEC 61400-12-1 [3] and
the terrain of the test site falls within requirements for testing without a site calibration. All cup
anemometers installed on the reference mast are class 1A instruments as defined by [3] and have
undergone individual rotor specific MEASNET [6] calibration at a MEASNET certified wind tunnel.
All boom and upright dimensions have been determined using the lattice porosity and mast dimensions
provided by the manufacturer and in compliance with [3] to operate within a maximum flow distortion of
0.5% at the wind measurement locations. The directional vanes are installed with their North markings
aligned along the booms towards the mast. The boom orientation is compensated for in the data logger.
The main mast installation documents (as presented in [1]) are included for reference in Appendix B and
the instrument calibration certificates are included in Appendix E. Those calibrations belong to the most
recently changed anemometers (see Table 1), hence being valid for the wind speed sensors of the met
tower during this verification campaign.
The met mast is a guyed 90.5 m triangular lattice tower with a face width of 0.7 m. The MEASNET
calibrated [6] cup anemometers (cups) of type Vector Instruments A 100 LM and Thies Frist Class
Advanced (TFCA) are mounted on booms aside the mast at heights of 20.5 m, 45.5 m and 70.5 m and in
a top mounting position at 90.5 m A.G.L., see
Figure 2. Those mounting arrangements are consistent with the IEA [Error! Reference source not
found.] and IEC [3] recommendations for the use of cup anemometry at masts.
The legend in Figure 2 describes the sensor at each positionTable 1 lists the sensors operating during the
campaign period. Respective calibration certificates for each sensor are given in Appendix E. The photo
in Figure 2 shows mast anemometry levels between 20 and 90.5 m AGL.
Label A E F G H K L
Orientation (⁰ ) Mast
300 300 120 300 120 300 120
to Instrument
Calibration
14/10/2016 22/08/2014 17/08/2015 17/08/2015 22/08/2014 22/08/2014 17/08/2015
Date
DWG Slope 0.04596 0.09714 0.046 0.04602 0.09767 0.09745 0.04603
Table 1: List of meteorological sensors and individual anemometers installed at the mast
during verification campaign, as of Appendix B, and list of calibration factors for cup
anemometers. The valid calibration certificates are attached to this report in Appendix E.
Figure 3 shows an array of ZephIR Lidars under test being typically located to the East of the base of the
met mast, and Table 2 lists wind speed and wind direction measurement and comparison levels as given
and selected for the performance verification.
Figure 3: Typical setup of ZephIR Lidars next to the reference mast at Pershore.
ZP300 Meas.
10 20 38 45 70 91 120 149 200 250 300
Levels [m]
Mast/WS-Cup
20 45 70 91
Levels [m]
Mast/WD-Vane
44 88
Levels [m]
1 Standard height in ZephIR ZP300 devises (automatically recorded)
Table 2: Height settings of ZP300 Lidar and reference mast. Levels for wind speed and wind
direction comparisons are highlighted in bold letters.
In the process of the LPV trial the following test conditions and filters are applied
• All comparisons are based on 10-minute average wind values returned from wind vanes and
MEASNET calibrated cup anemometers installed on the reference mast (primary reference) and
concurrent wind direction and wind speed data from the Lidar under test.
• All data collected during periods of possible icing at cup anemometers, i.e. temperatures below
2 °C and humidity of above 80% are excluded.
• All data collected during periods of precipitation (i.e. when precipitation is detected by the watch
sensor with a ten minute averaged period) are excluded.
• All other reported data (particularly wind speed) within undisturbed free-stream wind direction
sector relative to the reference mast as well to the Lidar are used in the comparison analysis.
• For the validation of Lidar wind speeds against the mast the wind speeds from the cup
anemometers at 20 m, 45 m, 70 m and 91 m are used. The Lidar data are selected according to
the sector screening of the cup data prior to comparison, see following section.
If cup data from both boom directions is available (i.e. for wind directions out of the remaining two
sectors), the wind speed average of the two oppositely mounted instruments is used as reference for the
comparison with the Lidar wind speeds. Wind data is further screened within the two disturbance sectors
whereby wind speed data from a single cup, i.e. from the one mounted on the upwind directed boom is
considered valid, only.
Wind speed data measured at 91.5 m and 70.5 m are screened against wind direction data at the 88 m
vane. Instruments at the 45.5 m and 20.5 m are screened against directional data from the 43.5 m vane.
For the validation of ZephIR wind speeds against the mast, only wind speeds from the cup anemometers
are used as reference.
All recorded data at any given timestamp where these criteria are not satisfied is excluded. A maximum
horizontal speed limit was not applied given manual horizontal wind speed filtering will be applied in the
analysis.
The following data coverage definitions are prescribed for the LPV:
• The overall minimum number of 10 minute data points after filtering (according to sections 3.1
and 3.2) for the WS ranges [all > 3 m/s] and [4 to 16 m/s] should not be lower than 600.
• At least 200 10-minute data points should to be in the WS range between 4 and 8 m/s and 200
data points between 8 and 12 m/s.
These data coverage requirements are regarded as achievable for a typical test period of 4 weeks.
3.5 LPV evaluation
The performance of the LIDAR under test is evaluated for its system and data availability as well as for
its wind data accuracy, based on a number of Key Performance Indicators (KPI) and according
Acceptance Criteria (AC).
The performance assessment of the given KPIs and respective Acceptance Criteria regarding Availability
and Accuracy is executed at each reference level present, in this case at each of the four (4) met tower’s
1st Class reference anemometry levels which are 20 m, 45 m, 70 m and 91 m above ground level.
Table 3: Number of 10 minute data points after filtering used for WS comparison at each of
the four (4) levels.
The completeness requirements as of section 3.4 are fulfilled for all WS ranges.
4.1 System availability
The system availability as applied to the Lidar device is defined by a percentage of the maximum
possible number of ten-minute periods within the above mentioned total campaign duration. The total
number of 10 min intervals for the campaign duration of ZP 597 is 5704 corresponding to 39.6 days. As
Lidar ten-minute data entries were present (regardless of the data validity) the Lidar device achieved a
system availability of almost 100 % see table below.
✓ The Acceptance Criterion for Data Availability (KPI SACA) to be ≥95 % is successfully met.
Test height / m 20 45 70 91
Table 4: Summary of system and data availabilities for ZP 597 at respective heights
✓ The Acceptance Criterion for Data Availability (KPI DACA) to be ≥90 % is successfully met for all
measurement levels.
Data for individual heights were treated as available when they show a numeric value in contrast to a
value being flagged as NaN (not a number), 9999, or not fully operational. The difference in number of
available data between the rows “system” and “data availability” as shown in Table 4 reflect the
reduction of valid data according to internal system filtering.
• wind direction to avoid non-valid wind speed sectors being influenced by e.g. mast wake effects,
(refer to section 3.2);
• air temperature and humidity measurements recorded at 43.5 m and 88 m respectively at the
mast were used to filter out potential icing of the mast cup anemometers. WS and wind direction
(WD) measurements were excluded whenever the temperature dropped below 2° and relative
humidity exceeded 80 %.
After the application of those filters the number of ten-minute data points remaining to be processed was
reduced to a percentage between 44.0 % at 20 m and 55.7 % at 91 m (refer to Table 4).
Wind speed as treated in this LPV process are assessed by means of Linear Regressions through the
origin of the form
y = m x + b and b=:0
between Lidar (y-axis) wind speeds and cup (x-axis) wind speeds for the four mentioned heights, and
were derived from the comparison of data from the following wind speed ranges
a) 4 to 16 m/s 1
1) slope (m) (KPI Xmws) between 0.98 and 1.02 for all WS ranges a) and b)
1 In consistency with the IEC bin selection criteria the actual range spans from 3.75 to 16.25 since 4 m/s and 16 m/s are the central points of
the corresponding 0.5 m/s wide bins.
The time series of wind speeds as recorded by the Lidar (for all 5 pre-set heights) covering 39.6 days, is
overlapped by that of the met mast system. Two comparison heights (70m and 91m) are shown in
Appendix C.
Table 5 summarizes the wind speed regression results at all four (4) comparison heights showing that
the ZephIR Lidar achieves a high level of accuracy compared to the cups at respective heights in terms
of regression slopes (m) which are close to unity and good regression coefficient R2 (KPI R2mws). Figure 5
shows the corresponding regression plots for the wind speed range >= 3 m/s.
The mean Lidar wind speeds averaged over all used values (KPI Cmwsd) resemble those of the cups very
closely (see columns 5 and 6 from Table 5), yielding very low relative Campaign Mean WS Differences
(KPI Cmwsd) at all measurement heights and WS ranges.Table 6 reflects the results according to the
absolute wind speed error criterion. It shows that for the wind speed range of 3 to 16 m/s at all heights
between 20 to 91 m, a small fraction of data ranging between 0.5% and 5.1 % of concurrent ten-minute
data points exceed the prescribed wind speed difference threshold of 0.5 m/s which is below the allowed
upper limit of 10 %.
With respect to the linear WS regressions the following KPI’s Acceptance Criteria are passed
✓ Regression slope (KPI Xmws) between 0.98 and 1.02 at all treated levels and for all WS ranges;
meeting the Acceptance Criteria.
✓ R2 (KPI R2mws) > 0.97 at all treated levels for both the WS ranges a) [all > 3 m/s] and b) [4 to
16 m/s]; meeting the Acceptance Criteria.
✓ The Acceptance Criterion for the relative Campaign Mean Wind Speed Difference (KPI Cmwsd)
(see Table 5, column 7) is successfully passed at the three highest assessment levels (45, 70
and 91 m) in both WS ranges.
Furthermore, the following wind speed related Acceptance Criteria were met:
✓ Absolute Wind Speed Difference (KPI Awsd) at all comparison levels and for all analysed wind
speed data between 3 and 16 m/s, see Table 6.
The following deviation from applicable test conditions and performance criteria are reported.
o The Acceptance Criterion for the relative Campaign Mean Wind Speed (KPI Cmwsd) is missed at
the lowest measurement level (20 m) for both WS ranges.
Table 5: Regression results comparison for ZPH 597; acceptance relevant results are colour
shaded. Note the regression lines are forced through the origin.
ZPH 594
Criterion for > 0.5 m/s for 3 to 16 m/s > 2% above 16 m/s
abs WS error KPI Awsd
Height Level total # identified # fraction % total # identified # fraction %
20 1917 10 0.5 0 0 N/A
45 2026 25 1.2 0 0 N/A
ZPH597
70 2156 57 2.6 6 1 16.7
91 2178 99 4.5 13 4 30.8
Table 6: Summary of absolute wind speed differences between cups and Lidar
The results of such regression are shown in the x-y-plots in Figure 6 with the vane wind direction at 44
and 88 m on the x-axis and the Lidar direction at 45 and 91 m on the y-axis respectively. For this
analysis the data was again filtered for Lidar and the cup wind speeds at 91 m, i.e. for WS >=3 m/s (to
avoid false readings from the vane at low wind speeds), but not for possibly disturbed wind directions
sectors.
Note that a few 180° wind direction ambiguities were observed, when ZephIR Lidar data were correlated
to the wind vane readings at 88 and 44 m (see Appendix D). These ambiguities were removed whenever
there was a distinct 180° offset when compared with the mast vane wind direction measurements as the
reference. This mast based correction is justified by the assumption, that a few 180° offset occurrences
are related to lower wind speeds in combination with near ground site induced turbulence effects. Wind
direction time series present during the course of the campaign period together with raw data
correlations and WD distribution statistics can be found in Appendix D.
The directional offsets are within typical directional setup uncertainties for wind vanes and remotes
sensing devices. Table 7 summarizes the WD comparison results for the acceptance relevant WD
comparison levels at 88 and 44 m vanes, showing an equally good resemblance slope.
✓ The Acceptance Criteria for the respective KPIs for wind direction assessment (KPIs for Xmwd,
OFFmwd, and R2mwd) are successfully passed.
The bin averaging procedure was performed using 0.5 m/s wide wind speed bins centred on integers of
from 4 to 16 m/s. In order to achieve statistical relevance this IEC approach requires
• a minimum of three (3) 10-minute values available within each wind speed bin; and
• a total amount of 180 hours of valid data (corresponding to a number of 1080 10-min values)
Figure 7 shows the scatter plots of the wind speed comparison based on 10 min averages between the
data pairs of the ZP 597 Lidar and the cups at 20, 45, 70 and 91 m. Additionally, the 10 minute
averaged deviation for each data point of the two data sets is plotted (orange dots).
Furthermore, the correlation coefficient, mean deviation and standard deviation of the deviations are
shown in Table 8. The relative deviation of the data pairs was calculated in relation to the cup wind
speeds as reference.
Figure 8: Bin-wise comparison of the horizontal wind speed component for ZP 597 –
20 m (top left), 45 m (top right), 70 m (bottom left), 91 m (bottom right)
2. Mean deviation of the remote sensor measurements and the reference measurements
The different uncertainty components are added in quadrature for each wind speed bin. The uncertainty
due to non-homogenous flow between the measurement volume of the Lidar and at the met mast is
assumed to be negligible due to the proximity of the Lidar to the mast and the benign terrain conditions
at the Pershore test site. Details on the calculation of the separate uncertainty components are described
in Appendix F.
The results of the uncertainty calculation for the IEC compliant verification of the Lidar device at every
comparison level are plotted in Figure 8. The finally combined uncertainties of the remote sensing RSD
(VRSD) for the different WS bins and comparison levels show results values well below 2 % within most of
the bins except for at the 20 m measurement level.
For the current Lidar verification campaign the completeness requirement to yield 180 hours of valid and
useable concurrent data (which translates into 7.5 days of data) in the WS range 4 and 16 m/s between
the RSD and the reference cup is met for each comparison level.
The additional data completeness requirement of yielding a minimum of 3 data pairs in each 0.5 m/s
wide wind speed bin is fulfilled for most of the WS bins and comparison levels. Note that uncertainties
are not calculated for wind speed bins with less than 3 data points.
In Appendix G the environmental parameters - present during the performance verification test - are
documented.
*
Insufficient number of data points for uncertainty calculations
*
Insufficient number of data points for uncertainty calculations
*
Insufficient number of data points for uncertainty calculations
*
Insufficient number of data points for uncertainty calculations
Furthermore, the IEC compliant bin-wise uncertainty implementation may serve as a traceable means to
judge the uncertainty of the RSD as determined from a well-defined verification process.
Any statement given in the context of system integrity and data quality related results within this report are
limited to the given test site conditions, to the prevailing atmospheric (in particular wind) conditions and to
the specific Lidar configuration as selected for this LPV campaign.
For sites with non-benign terrain and atmospheric conditions, an LPV is not thought to replace the
requirement for an on-site verification of a Lidar in real field campaigns. In this situation it may be
necessary to conduct measurements in close proximity to an on-site mast over a reasonable period. .
The overall system availability for the mentioned total campaign duration of 36.9 days for ZP 597 is 99.9 %.
The data availabilities at the selected Lidar measurement levels 20 m, 45 m, 70 m and 91 m was in the
range of 93.9 % to 97.5 %. These data coverage figures are relative to the number of maximum possible
ten-minute data points for the total duration of the campaign.
Wind speed (and direction) correlations were carried out for each of the four WS measurement heights (one
for WD) mentioned above. The wind speeds of both techniques at all treated heights correlated very well,
showing a very low level of scatter and an excellent resemblance of Lidar wind speeds to those of cups, in
terms of linear regression slopes.
✓ The Acceptance Criterion for System Availability (KPI SACA) to be ≥95 % is successfully passed
(Table 4).
✓ The Acceptance Criterion for Data Availability (KPI DACA) to be ≥90 % is successfully met at all
assessment levels (Table 4).
✓ Regression slope (KPI Xmws) between 0.98 and 1.02 at all treated levels and for all WS ranges,
meeting the Acceptance Criteria (Table 5, column 2).
✓ R2 (KPI R2mws) > 0.97 at all treated levels for the WS ranges a) [all WS > 3 m/s]and b) [4 to
16 m/s], meeting the Acceptance Criteria (Table 5, column 3).
✓ The Acceptance Criterion for the relative Campaign Mean Wind Speed Difference (KPI Cmwsd) (see
Table 5, column 7) is successfully passed at the 45, 70 and 91 m assessment levels for both WS
ranges.
✓ Absolute Wind Speed Difference (KPI Awsd) at all comparison levels and for all analysed wind speed
data between 3 and 16 m/s where wind speed difference of greater than 0.5 m/s makes up < 5 % of
the full dataset (Table 6).
✓ The Acceptance Criteria for the respective KPIs for wind direction assessment (KPIs for Xmwd,
OFFmwd, and R2mwd) are successfully passed at all comparison levels.
o The Criterion for the relative Campaign Means Wind Speed Difference (KPI Cmwsd) (see Table 5,
column 7) is missed at the 20 m measurement level.
The performance verification and uncertainty calculation has also been carried out in accordance with the
IEC standard yielding a traceable uncertainty measure. The following deviation from the applicable IEC test
conditions are reported:
▪ 14.5 m/s and 15.5 m/s bins for the 45 m measurement level;
In summary, this Pershore validation campaign indicates that the ZephIR 300 Lidar with the serial number
ZP 597 is able to reproduce cup anemometer wind speeds and wind vane directions at an accurate and
acceptable level. DNV GL considers that the ZephIR 300 Lidar device under test (with the serial number ZP
597) can be used for formal wind potential and long-term wind resource assessments. Specifically, DNV GL
concludes that this Lidar may be employed as a standalone measurement system – replacing a conventional
met mast – given the following criteria are met:
(1) The Lidar is deployed in a location with benign terrain and atmospheric conditions.
▪ recording data for a period sufficient to obtain an adequate in-situ correlation to an onsite
reference (e.g. a short met. mast);
Finally, DNV GL recommends, that care needs to be taken with respect to the formal use of Lidar turbulence
and extreme wind speed measures, not treated in this report but known to be different from classical
anemometry measures. DNV GL likes to point out that good measurement and data collection practices need
to be maintained for all wind speed measurements, be they Lidar or more conventional anemometry.
Therefore, special care needs to be exercised in the transportation, installation and on-going maintenance of
the Lidar as it may be exposed to a wide range of environmental conditions at different sites over time. A
key element of any formal wind study is the traceability of the wind speed data uncertainty. Hence, a strict
uncertainty assessment (which is not part of this report) should be employed. Furthermore it is
recommended that thorough practices of documenting the salient features of Lidar installation and
maintenance are instigated from the outset.
2. Kindler, D., " Best Practice Test and Verification Procedure for Wind LiDARs on the Høvsøre Test Site”,
GL GH-D Report WT 6960/09 for EU-Project NORSEWInD, Deliv. 1.1, June 2009.
3. International Standard: IEC 61400-12-1: Wind turbines – Part 12-1: Power Performance Measurements
of Grid Connected Wind Turbines. Ed. 1. International Electronic Commission.
3, rue de Varembé Geneva. Switzerland, Dec. 2005.
4. International Standard: IEC 61400-12-1: Wind turbines – Part 12-1: Power performance measurements
of electricity producing wind turbines. Ed. 2. CD. International Electronic Commission.3, June. 2013.
5. IEA Expert Group Study on Recommended Practices for Wind Turbine Testing and Evaluation 11. Wind
speed measurement and use of cup anemometry, 1. Edition 1999.
7. W. Barker, E. Burin des Roziers, "Pershore: 91m Anemometer Mast Specification and Data Validation,
Revision 2", by ZephIR Ltd., issued: 10/10/2012.
8. Stein, D. “Technical Note of Inspection of ZephIR’s Reference Met Mast and Lidar Test Site (exec. 2015-
09-01) at Pershore/Throckmorton, UK” DNV GL Report, No. GLGH-4257 15 13307 267 T-0001, Rev. B,
2016-05-02.
Abbreviation
Meaning
Acronym
AC Acceptance Criterion
a.g.l. Above ground level
DNV GL New company name, successor of legacy GL GH
IEC International Electro-technical Commission
IEA International Energy Agency
GH-D GL Garrad Hassan Deutschland GmbH
MM Meteorological Mast
PAR Performance Assessment Requirement
LPV Lidar Performance Verification
TI Turbulence Intensity
WD Wind direction
WS Wind speed
Table 13: List of KPIs and ACs relevant for System and Data Availability assessment
Acceptance Criteria
KPI Definition / Rationale across total
campaign duration
SACA System Availability ≥95%
The Lidar system is ready to function according to
specifications and to deliver data, taking into account all
time stamped data entries in the output data files
including flagged data (e.g. by NaNs or 9999s) for the
pre-defined total campaign length.
The System Availability is the number of these time
stamped data entries relative to the maximum possible
number of data entries (for 10 minute intervals) within
the pre-defined total campaign period.
In the above table, during periods of maintenance; the system is deemed unavailable.
* Undisturbed sectors: this means sectors with no significant flow distortion e.g. by wake effects of nearby
wind turbines
Acceptance Criteria
KPI Definition / Rationale
Vector A100 LM Cup S/N 8920 at 70.5 m, 300° orientation (Deutsche Wind Guard Calibration)
The anemometer uncertainty of the specific reference heights is calculated based on the wind tunnel
calibration of the individual anemometer, the anemometer classification and the mounting effect at the met
tower.
2. Mean deviation of the remote sensor measurements and the reference measurements
This is the relative deviation between the bin averages of the RSD and the mast reference measurement
divided by with the reference measurement.
The standard deviation of the measurements was divided by the square root of the number of data records
per bin. The relative uncertainty was calculated by dividing the value by the bin average wind speed of the
mast (reference) measurement.
The uncertainty of the remote sensing device due to non-ideal levelling was estimated to be 0.5 %.
The Lidar device is located in close proximity of the met tower just a few m to the East of the tower base. As
a result the uncertainty due to non-homogenous flow within the measurement volume is considered to be
negligible.
# PiA Quality
BIN BIN Shear exponenet TI Wind direction Temperature Air Density Wind Veer
Vmm Factor
Lower Upper 70 m -20 m at 70 m at 88 m at 44 m at 44 m 88 m - 44 m
at 70 m
Average Average Std Average Std Average Std Average Std Average Std Average Std Average Std
[m/s] [m/s]
[m/s] [-] [-] [-] [-] [#] [#] [°] [°] [°C] [°C] [kg/m3] [kg/m3] [°] [°]
3.75 4.25 3.99 0.48 0.28 0.098 0.047 34.4 1.4 171.9 82.7 3.4 2.7 1.286 0.020 7.2 12.7
4.25 4.75 4.49 0.48 0.28 0.093 0.044 34.4 1.4 197.0 85.1 3.6 2.7 1.282 0.019 7.5 10.3
4.75 5.25 5.01 0.42 0.25 0.099 0.044 34.2 1.4 222.0 87.2 4.1 2.9 1.278 0.020 6.9 7.9
5.25 5.75 5.51 0.37 0.22 0.104 0.045 34.2 1.5 215.8 81.8 4.5 2.9 1.274 0.018 5.6 6.0
5.75 6.25 6.00 0.35 0.19 0.098 0.041 34.3 1.5 221.1 72.4 4.5 2.9 1.271 0.018 6.2 5.8
6.25 6.75 6.51 0.31 0.17 0.097 0.037 34.2 1.4 229.8 68.6 5.0 2.9 1.269 0.018 5.7 5.5
6.75 7.25 6.99 0.28 0.14 0.100 0.034 34.1 1.5 222.2 60.6 5.4 2.6 1.264 0.018 5.7 4.8
7.25 7.75 7.49 0.28 0.10 0.096 0.035 34.3 1.4 231.0 61.0 5.4 2.8 1.263 0.018 6.4 5.1
7.75 8.25 7.98 0.28 0.10 0.094 0.033 34.5 1.3 239.0 62.9 5.2 2.8 1.263 0.017 6.1 4.9
8.25 8.75 8.48 0.27 0.10 0.096 0.034 34.6 1.1 241.2 56.1 5.6 3.0 1.263 0.018 5.7 4.6
8.75 9.25 8.99 0.24 0.08 0.104 0.034 34.6 1.1 241.6 48.0 6.6 3.0 1.257 0.014 4.0 2.2
9.25 9.75 9.50 0.22 0.07 0.111 0.032 34.3 1.4 246.9 59.2 6.8 3.2 1.255 0.014 3.3 2.1
9.75 10.25 9.98 0.23 0.06 0.105 0.027 34.6 1.1 245.8 43.2 7.2 2.7 1.255 0.012 3.6 2.1
10.25 10.75 10.46 0.22 0.05 0.119 0.031 34.5 1.0 251.7 38.7 7.4 3.0 1.253 0.013 3.3 1.6
10.75 11.25 10.99 0.19 0.05 0.121 0.040 34.3 1.1 247.0 32.6 8.4 2.7 1.252 0.013 2.8 2.0
11.25 11.75 11.54 0.19 0.05 0.130 0.033 34.4 0.9 249.0 31.7 9.4 2.8 1.246 0.013 2.4 2.3
11.75 12.25 11.99 0.19 0.05 0.130 0.032 34.5 1.0 253.3 37.4 9.1 3.3 1.245 0.012 2.1 1.5
12.25 12.75 12.48 0.19 0.03 0.135 0.030 34.5 0.9 252.7 34.4 9.4 2.7 1.244 0.009 2.0 1.0
12.75 13.25 12.97 0.18 0.04 0.145 0.037 34.5 0.8 258.2 35.6 9.5 1.8 1.244 0.007 2.1 1.0
13.25 13.75 13.60 0.19 0.05 0.137 0.037 34.8 1.1 259.7 43.1 8.8 2.0 1.245 0.008 1.6 0.9
13.75 14.25 14.03 0.16 0.04 0.146 0.028 34.7 1.0 241.3 42.5 9.4 2.2 1.244 0.008 2.1 0.9
14.25 14.75 14.50 0.17 0.03 0.137 0.022 33.3 2.0 222.4 34.8 10.1 0.9 1.240 0.005 1.8 0.7
14.75 15.25 15.01 0.18 0.04 0.147 0.022 34.1 2.0 261.0 51.4 9.0 2.8 1.240 0.010 1.3 0.9
15.25 15.75 15.43 0.17 0.03 0.160 0.024 34.3 1.7 255.5 55.2 8.8 2.7 1.243 0.009 1.4 1.2
15.75 16.25 16.07 0.16 0.06 0.131 0.020 33.6 2.1 220.1 41.9 10.4 0.9 1.237 0.001 2.0 0.6
1. This document is intended for the sole use of the Client as detailed on the front page of this document to
whom the document is addressed and who has entered into a written agreement with the DNV GL entity
issuing this document (“DNV GL”). To the extent permitted by law, neither DNV GL nor any group
company (the "Group") assumes any responsibility whether in contract, tort including without limitation
negligence, or otherwise howsoever, to third parties (being persons other than the Client), and no company
in the Group other than DNV GL shall be liable for any loss or damage whatsoever suffered by virtue of any
act, omission or default (whether arising by negligence or otherwise) by DNV GL, the Group or any of its or
their servants, subcontractors or agents. This document must be read in its entirety and is subject to any
assumptions and qualifications expressed therein as well as in any other relevant communications in
connection with it. This document may contain detailed technical data which is intended for use only by
persons possessing requisite expertise in its subject matter.
2. This document is protected by copyright and may only be reproduced and circulated in accordance with the
Document Classification and associated conditions stipulated or referred to in this document and/or in DNV
GL’s written agreement with the Client. No part of this document may be disclosed in any public offering
memorandum, prospectus or stock exchange listing, circular or announcement without the express and prior
written consent of DNV GL. A Document Classification permitting the Client to redistribute this document
shall not thereby imply that DNV GL has any liability to any recipient other than the Client.
3. This document has been produced from information relating to dates and periods referred to in this
document. This document does not imply that any information is not subject to change. Except and to the
extent that checking or verification of information or data is expressly agreed within the written scope of its
services, DNV GL shall not be responsible in any way in connection with erroneous information or data
provided to it by the Client or any third party, or for the effects of any such erroneous information or data
whether or not contained or referred to in this document.
4. Any wind or energy forecasts estimates or predictions are subject to factors not all of which are within the
scope of the probability and uncertainties contained or referred to in this document and nothing in this
document guarantees any particular wind speed or energy output.
Task and objective: provide a permanent record of the site characteristics and measurement equipment
for the LIDAR at Hoarafushi.
Reference to part of this report which may lead to misinterpretation is not permissible.
5 REFERENCES ................................................................................................................ 16
The World Bank (the “Client”) has retained Garrad Hassan America, Inc. (“DNV GL”) to provide a
validated mesoscale wind atlas for the Maldives, including associated deliverables and wind energy
development training courses. During Phase 1 of the project, which has been completed, preliminary
mesoscale mapping was carried out covering the entire country [1]. Phase 2 of the project, which is
currently underway, involves the installation of two Light Detection and Ranging (LIDAR) based wind
measurement sites in the country. Meteorological data collected at these sites over a two-year period will
provide the basis for validating the mesoscale modeling outputs from Phase 1.
LIDAR units and associated equipment have been commissioned at the two measurement sites,
Hoarafushi and Thulusdhoo, in April 2017.
This report documents the installation of the LIDAR site at Hoarafushi, and presents the characteristics of
the site, as well as details of the measurement equipment, power supply and data acquisition system.
2 SITE INFORMATION
Figure A-2 in Appendix A presents a map of estimated surface roughness zones in the vicinity of the site.
Table 2-1 presents details of the site location coordinates and elevation.
Coordinates Coordinates
(Geographic)2 (UTM, Zone 43 N)2
Commissioning Elevation
Site name
Date [m ASL]1
Latitude Longitude Eastings Northings
[degrees] [degrees] [m] [m]
2. Datum: WGS 84
3 SITE EQUIPMENT
The unit is secured to a concrete pad footing and is enclosed by fencing. Figure 3-1 to Figure 3-3 show
photographs of the LIDAR unit as installed on site.
The LIDAR unit is equipped with a washing system for cleaning the window, as shown in Figure 3-4
below. The washing system is connected to an external cleaning fluid supply bottle, which can be seen in
Figure 3-2.
The LIDAR simultaneously records 10-minute average, maximum, minimum, and standard deviation
statistics for the horizontal and vertical wind speeds, and average and standard deviation statistics for
wind direction, at eleven specified measurement heights between 10 m and 200 m above the top of the
unit. The LIDAR measurement configuration is summarised in Table 3-2 below.
Measurement
Measurement Measurement
heights Unit Channels
parameter interval
[m AGL]
Mean / minimum /
Horizontal wind
m/s maximum /
11, 20, 30, 39, speed
standard deviation 10 minutes
50, 60, 80,
(continuous
100, 120, 150,
Vertical wind speed m/s Mean scan)
200
Wind direction1 Degrees Mean
1. The unit is aligned at a bearing of approximately 3° from true north.
The LIDAR unit has been subjected to independent testing and performance verification in accordance
with the second edition of the reviewed IEC 61400-12-1 standard, Annex L [2][3]. A copy of the
performance verification report is presented in Appendix D.
The batteries located inside the enclosure are shown in Figure 3-9.
Table 3-4 summarizes the key specifications of the power supply system.
2 x 12V 100 Ah, AGM deep cycle Victron Energy Blue Power 12/25 - 12V, 25A
3.4 Communications
The system uses an external 3G modem and directional antenna for data transmission.
DNV GL will provide both raw and quality controlled data from the LIDAR device.
A laser scan determines the axis of the wind direction. The direction of the wind along that axis is then
determined in conjunction with the met station reading.
If the met direction in the above diagram pointed in the opposite direction, the reported direction would
be the other axial possibility in the first diagram. For example:
The Met Station direction reading only needs to be very coarse for this purposes as is only used to
determine the direction ‘phase’. However, if the met station is shadowed or if it is placed in areas of wind
recirculation then there is the potential for a 180 degrees direction ambiguity to result.
Given the proximity of the LIDAR device and met station to buildings, trees and other obstacles, the
potential for a 180 degree ambiguity in the wind direction measurements exists. Care should be taken
when using the raw data from the LIDAR device that instances where the 180 degree direction ambiguity
exists are corrected.
b) Check the LIDAR device and ancillary equipment have not been damaged or soiled
As a first step, local staff on the islands will perform a visual inspection of the unit and correct any issues
if possible. If further inspection, troubleshooting, or maintenance of the unit is required, a corrective
maintenance team consisting of in-country trained personnel from DNV GL’s Local Partner will visit the
site. In cases where the issue cannot be resolved by local staff, and where appropriate, expert personnel
from DNV GL will travel from Australia to the Maldives to perform the necessary corrective maintenance.
DNV GL will remotely assist with the interventions at all stages of the process.
W (267756, 772433) E
1. This document is intended for the sole use of the Client as detailed on the front page of this document to
whom the document is addressed and who has entered into a written agreement with the DNV GL entity
issuing this document (“DNV GL”). To the extent permitted by law, neither DNV GL nor any group
company (the "Group") assumes any responsibility whether in contract, tort including without limitation
negligence, or otherwise howsoever, to third parties (being persons other than the Client), and no company
in the Group other than DNV GL shall be liable for any loss or damage whatsoever suffered by virtue of any
act, omission or default (whether arising by negligence or otherwise) by DNV GL, the Group or any of its or
their servants, subcontractors or agents. This document must be read in its entirety and is subject to any
assumptions and qualifications expressed therein as well as in any other relevant communications in
connection with it. This document may contain detailed technical data which is intended for use only by
persons possessing requisite expertise in its subject matter.
2. This document is protected by copyright and may only be reproduced and circulated in accordance with the
Document Classification and associated conditions stipulated or referred to in this document and/or in DNV
GL’s written agreement with the Client. No part of this document may be disclosed in any public offering
memorandum, prospectus or stock exchange listing, circular or announcement without the express and prior
written consent of DNV GL. A Document Classification permitting the Client to redistribute this document
shall not thereby imply that DNV GL has any liability to any recipient other than the Client.
3. This document has been produced from information relating to dates and periods referred to in this
document. This document does not imply that any information is not subject to change. Except and to the
extent that checking or verification of information or data is expressly agreed within the written scope of its
services, DNV GL shall not be responsible in any way in connection with erroneous information or data
provided to it by the Client or any third party, or for the effects of any such erroneous information or data
whether or not contained or referred to in this document.
4. Any wind or energy forecasts estimates or predictions are subject to factors not all of which are within the
scope of the probability and uncertainties contained or referred to in this document and nothing in this
document guarantees any particular wind speed or energy output.
DNV GL
Project name: ZP 594 DNV GL - Energy
Report title: Independent analysis and reporting of ZephIR Renewables Advisory
Lidar performance verification at Pershore test Suite 25, Level 8,
site, including IEC compliant validation analysis 401 Docklands Drive, Docklands,
Customer: The World Bank, Victoria 3008, Australia
1818 H Street, N.W. Tel: +61 3 9600 1993
Washington, DC 20433
Contact person: Sandeep Kohli
Date of issue: 6 March 2018
Project No.: 702909
Report No.: 702909-AUME-R-06, Rev. B
Reference to part of this report which may lead to misinterpretation is not permissible.
A 30 Aug 2017 Draft (electronic version, only) M Quan F Dahhan, B Schmidt T Gilbert
DNV GL
Table of contents
1 INTRODUCTION .............................................................................................................. 2
4 RESULTS ..................................................................................................................... 11
4.1 System availability 11
4.2 Data availability 11
4.3 Data filtering 12
4.4 Wind speed comparison 12
4.5 Wind direction comparison 16
4.6 Performance verification according to revised IEC standard, Annex L 17
4.6.1 Performance verification uncertainty 19
6 CONCLUSION ............................................................................................................... 26
7 REFERENCES ................................................................................................................ 28
8 GLOSSARY ................................................................................................................... 29
Appendices
KEY PERFORMANCE INDICATORS AND ACCEPTANCE CRITERIA, IN LINE WITH
[2] 30
LIST OF FIGURES
Figure 1: Map of the Pershore test site near Throckmorton, UK. The position of the reference mast is
marked by a red dot. 3
Figure 2: Schematic of the sensor level and boom distribution at the 90.5 m mast, as taken from [1].
See Table 1 for sensor distribution according to the alphanumeric label per boom (A to N) and the
actually valid serial numbers. 5
Figure 3: Typical setup of ZephIR Lidars next to the reference mast at Pershore. 7
Figure 4: Wind direction sectors used to select undisturbed wind speed data from oppositely arranged
cup carrying booms for comparison. 9
Figure 5: Plots of linear wind speed regression results for 20, 45, 70 and 91 m (note the regression
results are forced through the origin) 15
Figure 6: Regression plot of wind direction comparisons at 45 m (left) and 88 m (right) 16
Figure 7: Comparison of the horizontal wind speed component for ZP 594 – 20 m (top left), 45 m (top
right), 70 m (bottom left), 91 m (bottom right) 18
Figure 8: Bin-wise comparison of the horizontal wind speed component for ZP 594 – 20 m (top left), 45
m (top right), 70 m (bottom left), 91 m (bottom right) 19
DNV GL has prepared an independent analysis and report of a ZephIR Lidar performance verification. In
this analysis and report, the ZephIR Lidar with the serial number ZP 594 will be discussed. The
verification measurements for this device were performed by ZephIR Ltd. at their test site in Pershore,
UK between 2016-12-09 to 2017-01-31.
The met tower was equipped with classical anemometry components (cup anemometers, wind vanes etc.)
serving as the verification reference for the Lidar wind speed and wind direction comparisons. Those
comparisons were performed in line with a Remote Sensing (RS) best practice verification approach as
developed within the EU-FP7-Projekt NORSEWInD [2] against corresponding Key Performance Indicators
(KPIs) and Acceptance Criteria (ACs; compare Appendix A).
In addition, a performance verification and uncertainty calculation is carried out in accordance with the
second edition of the reviewed IEC 61400-12-1 standard, Annex L [4].
DNV GL is accredited according to ISO 17025 for measurements on wind turbines and for wind resource
measurements and energy assessments. DNV GL is also a full member of the network of measurement
institutes in Europe ‘MEASNET’.
The following description and figures of the Pershore test site, which is a disused air field, are taken from
a technical report by ZephIR Ltd. [1]:
The terrain in the vicinity of the mast is flat and covered with sparse low growing vegetation. A number
of hangars and outbuildings exist in sectors between 260° and 317° at distances between 300m and
700m from the mast. These buildings are estimated not to exceed 14m in level. Approximately 500 m to
the North-East lies the small village of Throckmorton which consists of a few scattered farms and houses.
700 m to the South-West of the mast between 190° and 240° lies an area of spoil heaps and filtration
pools associated with a mining operation. On a wider scale the site is surrounded by flat arable land that
is devoid of any dense closed canopy forest. The larger conurbations of Pershore and Evesham lie at
distances of 5km and 9km to the South West and South East respectively.
Figure 1: Map of the Pershore test site near Throckmorton, UK. The position of the reference
mast is marked by a red dot.
The site specifications given in the above description have been verified during a site visit by a DNV GL
expert on 2015-09-01, see [8]. Further details on the site are given in [1], a 360° photo round is shown
in Appendix B.
In the following sections technical details and specifications of the measuring equipment are described.
This description covers the meteorological reference mast (met mast) including its sensors and data
acquisition system as well as the tested Lidar.
The following items regarding the meteorological measurement systems have been verified during the
above mentioned site visit:
• Site suitability and exact positions of mast and Lidar test stand
• Validity of MEASNET [6] calibrations of cups and correct application of calibration factors and
offsets
The mast has been constructed to be fully compliant with the 2005 edition of IEC 61400-12-1 [3] and
the terrain of the test site falls within requirements for testing without a site calibration. All cup
anemometers installed on the reference mast are class 1A instruments as defined by [3] and have
undergone individual rotor specific MEASNET [6] calibration at a MEASNET certified wind tunnel.
All boom and upright dimensions have been determined using the lattice porosity and mast dimensions
provided by the manufacturer and in compliance with [3] to operate within a maximum flow distortion of
0.5% at the wind measurement locations. The directional vanes are installed with their North markings
aligned along the booms towards the mast. The boom orientation is compensated for in the data logger.
The main mast installation documents (as presented in [1]) are included for reference in Appendix B and
the instrument calibration certificates are included in Appendix E. Those calibrations belong to the most
recently changed anemometers (see Table 1), hence being valid for the wind speed sensors of the met
tower during this verification campaign.
The met mast is a guyed 90.5 m triangular lattice tower with a face width of 0.7 m. The MEASNET
calibrated [6] cup anemometers (cups) of type Vector Instruments A 100 LM and Thies Frist Class
Advanced (TFCA) are mounted on booms aside the mast at levels of 20.5 m, 45.5 m and 70.5 m and in
a top mounting position at 90.5 m A.G.L., see
Figure 2. Those mounting arrangements are consistent with the IEA [5] and IEC [3] recommendations
for the use of cup anemometry at masts.
The legend in Figure 2 describes the sensor at each position. Table 1 lists the sensors operating during
the campaign period. Respective calibration certificates for each sensor are given in Appendix E. The
photo in Figure 2 shows mast anemometry levels between 20 and 90.5 m AGL.
Label A E F G H K L
Orientation (⁰ ) Mast
300 300 120 300 120 300 120
to Instrument
Calibration
14/10/2016 22/08/2014 17/08/2015 17/08/2015 22/08/2014 22/08/2014 17/08/2015
Date
DWG Slope 0.04596 0.09714 0.046 0.04602 0.09767 0.09745 0.04603
Table 1: List of meteorological sensors and individual anemometers installed at the mast
during verification campaign, as of Appendix B, and list of calibration factors for cup
anemometers. The valid calibration certificates are attached to this report in Appendix E.
The Lidar under test is a ZephIR of type Z 300 Doppler Wind Lidar, employing a CW laser (continuous
wave laser) that has specifically been designed to measure wind speeds at levels in the boundary layer
of the atmosphere. The serial number of the lidar device is ZP 594. During the verification campaign the
Lidar system was configured to record wind speed measurements at 11 different levels between 10 and
300 m. The actual Lidar measurement levels were 10, 20, 38, 45, 70, 91, 120, 149, 200, 250 and 300 m
above ground. The four levels at 20, 45, 70 and 91 m were used for the comparison to the cup/mast
reference measurements.
Figure 3 shows an array of ZephIR Lidars under test being typically located to the East of the base of the
met mast, and Table 2 lists wind speed and wind direction measurement and comparison levels as given
and selected for the performance verification.
Figure 3: Typical setup of ZephIR Lidars next to the reference mast at Pershore.
ZP300 Meas.
10 20 38 45 70 91 120 149 200 250 300
Levels [m]
Mast/WS-Cup
20 45 70 91
Levels [m]
Mast/WD-Vane
44 88
Levels [m]
1 Standard level in ZephIR ZP300 devises (automatically recorded)
Table 2: Level settings of ZP300 Lidar and reference mast. Levels for wind speed and wind
direction comparisons are highlighted in bold letters.
In the process of the LPV trial the following test conditions and filters are applied:
• All comparisons are based on 10-minute average wind values returned from wind vanes and
MEASNET calibrated cup anemometers installed on the reference mast (primary reference) and
concurrent wind direction and wind speed data from the Lidar under test.
• All data collected during periods of possible icing at cup anemometers, i.e. temperatures below
2 °C and humidity of above 80% are excluded.
• All data collected during periods of precipitation (i.e. when precipitation is detected by the watch
sensor with a ten minute averaged period) are excluded.
• All other reported data (particularly wind speed) within undisturbed free-stream wind direction
sector relative to the reference mast as well to the Lidar are used in the comparison analysis.
• For the validation of Lidar wind speeds against the mast the wind speeds from the cup
anemometers at 20 m, 45 m, 70 m and 91 m are used. The Lidar data are selected according to
the sector screening of the cup data prior to comparison, see following section.
If cup data from both boom directions is available (i.e. for wind directions out of the remaining two
sectors), the wind speed average of the two oppositely mounted instruments is used as reference for the
comparison with the Lidar wind speeds. Wind data is further screened within the two disturbance sectors
whereby wind speed data from a single cup, i.e. from the one mounted on the upwind directed boom is
considered valid, only.
Wind speed data measured at 91.5 m and 70.5 m are screened against wind direction data at the 88 m
vane. Instruments at the 45.5 m and 20.5 m are screened against directional data from the 43.5 m vane.
For the validation of ZephIR wind speeds against the mast, only wind speeds from the cup anemometers
are used as reference.
All recorded data at any given timestamp where these criteria are not satisfied is excluded. A maximum
horizontal speed limit was not applied given manual horizontal wind speed filtering will be applied in the
analysis.
• The overall minimum number of 10 minute data points after filtering (according to sections 3.1
and 3.2) for the wind speed (WS) ranges [all > 3 m/s] and [4 to 16 m/s] should not be lower
than 600.
• At least 200 10-minute data points should to be in the WS range between 4 and 8 m/s and 200
data points between 8 and 12 m/s.
These data coverage requirements are regarded as achievable for a typical test period of 4 weeks.
The evaluation approach in terms of the applicable KPIs and according ACs is outlined in Appendix A,
where KPIs and ACs for system and data availability are listed in Table 13 those for wind data quality in
Table 14.
Table 3: Number of 10 minute data points after filtering used for WS comparison at each of
the four (4) levels.
The completeness requirements as of section 3.4 are fulfilled for all WS ranges.
4.1 System availability
The system availability as applied to the Lidar device is defined by a percentage of the maximum
possible number of ten-minute periods within the above mentioned total campaign duration. The total
number of 10 min intervals for the campaign duration of ZP 594 is 7707 corresponding to 53.5 days.
✓ The Acceptance Criterion for System Availability (KPI SACA) to be ≥95 % is successfully met.
Test level / m 20 45 70 91
Table 4: Summary of system and data availabilities for ZP 594 at respective levels
o The Acceptance criterion for Data Availability (KPI DACA) to be ≥90 % is missed by a small
margin at the 91 m measurement level.
Data for individual levels were treated as available when they show a numeric value in contrast to a
value being flagged as NaN (not a number), 9999, or not fully operational. The difference in number of
available data between the rows “system” and “data availability” as shown in Table 4 reflect the
reduction of valid data according to internal system filtering.
• wind direction to avoid non-valid wind speed sectors being influenced by e.g. mast wake effects,
(refer to section 3.2);
• air temperature and humidity measurements recorded at 43.5 m and 88 m respectively at the
mast were used to filter out potential icing of the mast cup anemometers. WS and wind direction
(WD) measurements were excluded whenever the temperature dropped below 2° and relative
humidity exceeded 80 %.
After the application of those filters the number of ten-minute data points remaining to be processed was
reduced to a percentage between 40.5 % at 20 m and 54.9 % at 91 m, (refer to Table 4).
Wind speed as treated in this LPV process are assessed by means of Linear Regressions through the
origin of the form
y = m x + b and b=:0
between Lidar (y-axis) wind speeds and cup (x-axis) wind speeds for the four mentioned heights, and
were derived from the comparison of data from the following wind speed ranges
a) 4 to 16 m/s 1
1) slope (m) (KPI Xmws) between 0.98 and 1.02 for all WS ranges a) and b)
1 In consistency with the IEC bin selection criteria the actual range spans from 3.75 to 16.25 since 4 m/s and 16 m/s are the central points of
the corresponding 0.5 m/s wide bins.
The time series of wind speeds as recorded by the Lidar (for all 5 pre-set levels) covering 53.5 days, is
overlapped by that of the met mast system. Two comparison levels (70m and 91m) are shown in
Appendix C.
Table 5 summarizes the wind speed regression results at all four (4) comparison levels showing that the
ZephIR Lidar achieves a high level of accuracy compared to the cups at respective levels in terms of
regression slopes (m) which are close to unity and good regression coefficient R2 (KPI R2mws). Figure 5
shows the corresponding regression plots for the wind speed range >= 3 m/s.
The mean Lidar wind speeds averaged over all used values (KPI Cmwsd) resemble those of the cups very
closely (see columns 5 and 6 from Table 5), yielding very low relative Campaign Mean WS Differences
(KPI Cmwsd) at all measurement levels and WS ranges. Table 6 reflects the results according to the
absolute wind speed error criterion. It shows that for the wind speed range of 3 to 16 m/s at all levels
between 20 to 91 m, a small fraction of data ranging between 0.6 % and 3.8 % of concurrent ten-
minute data points exceed the prescribed wind speed difference threshold of 0.5 m/s which is below the
allowed upper limit of 10 %.
With respect to the linear WS regressions the following KPI’s Acceptance Criteria are passed
✓ Regression slope (KPI Xmws) between 0.98 and 1.02 at all treated levels and for all WS ranges;
meeting the Acceptance Criteria.
✓ R2 (KPI R2mws) > 0.97 at all treated levels for both the WS ranges a) [all > 3 m/s] and b) [4 to
16 m/s]; meeting the Acceptance Criteria.
✓ The Acceptance Criterion for the relative Campaign Mean Wind Speed Difference (KPI Cmwsd)
(see Table 5, column 7) is successfully passed at all assessment levels and for 20, 45 and 70 m
measurement levels for both WS rangeslevel.
Furthermore, the following wind speed related Acceptance Criteria were met:
✓ Absolute Wind Speed Difference (KPI Awsd) at all comparison levels and for all analysed wind
speed data between 3 and 16 m/s, see Table 6.
The following deviation from applicable test conditions and performance criteria are reported.
o The Acceptance Criterion for the relative Campaign Mean Wind speed Difference (KPI Cmwsd) is
missed at the 91 m level measurement level for both wind speed ranges.
Table 5: Regression results comparison for ZPH 594; acceptance relevant results are colour
shaded. Note the regression lines are forced through the origin.
ZPH 594
Criterion for > 0.5 m/s for 3 to 16 m/s > 2% above 16 m/s
abs WS error KPI Awsd
Level Level total # identified # fraction % total # identified # fraction %
20 2533 11 0.4 0 0 N/A
45 2980 27 0.9 1 0 0.0
ZPH594
70 3152 50 1.6 7 1 14.3
91 2955 101 3.4 14 3 21.4
Table 6: Summary of absolute wind speed differences between cups and Lidar
The results of such regression are shown in the x-y-plots in Figure 6 with the vane wind direction at 44
and 88 m on the x-axis and the Lidar direction at 45 and 91 m on the y-axis respectively. For this
analysis the data was again filtered for Lidar and the cup wind speeds at 91 m, i.e. for WS >=3 m/s (to
avoid false readings from the vane at low wind speeds), but not for possibly disturbed wind directions
sectors.
Note that a few 180° wind direction ambiguities were observed, when ZephIR Lidar data were correlated
to the wind vane readings at 88 and 44 m (see Appendix D). These ambiguities were removed whenever
there was a distinct 180° offset when compared with the mast vane wind direction measurements as the
reference. This mast based correction is justified by the assumption, that a few 180° offset occurrences
are related to lower wind speeds in combination with near ground site induced turbulence effects. Wind
direction time series present during the course of the campaign period together with raw data
correlations and WD distribution statistics can be found in Appendix D.
The regression plots in Figure 6 reveal a close resemblance in measurement between the Lidar against
the wind vanes for levels at 44 and 88 with an offset (in terms of a mean difference) of 5.1° at 45 m and
2.1° at 91 m.
It should be noted that the calculated directional offset for ZPH 594 at 45 m is 5.1°, which does not lie
within the applicable OFFmwd bounds. The remaining directional offsets are however within typical
directional setup uncertainties for wind vanes and remotes sensing devices. Table 7 summarizes the WD
comparison results for the acceptance relevant WD comparison levels at 88 and 44 m vanes, showing an
equally good resemblance slope.
✓ The Acceptance Criteria for the respective KPIs for wind direction assessment (KPIs for Xmwd and
R2mwd) are successfully passed for both comparison levels. The Criteria for the KPI OFFmwd for
the wind direction assessment is passed at higher level.
o The criterion for the KPI OFFmwd for the wind direction assessment is missed by a small margin
at the 45 m measurement level.
The bin averaging procedure was performed using 0.5 m/s wide wind speed bins centred on integers of
from 4 to 16 m/s. In order to achieve statistical relevance this IEC approach requires
• a minimum of three (3) 10-minute values available within each wind speed bin; and
• a total amount of 180 hours of valid data (corresponding to a number of 1080 10-min values)
Figure 7 shows the scatter plots of the wind speed comparison based on 10 min averages between the
data pairs of the ZP 594 Lidar and the cups at 20, 45, 70 and 91 m. Additionally, the 10 minute
averaged deviation for each data point of the two data sets is plotted (orange dots).
Furthermore, the correlation coefficient, mean deviation and standard deviation of the deviations are
shown in Table 8. The relative deviation of the data pairs was calculated in relation to the cup wind
speeds as reference.
Figure 8: Bin-wise comparison of the horizontal wind speed component for ZP 594 –
20 m (top left), 45 m (top right), 70 m (bottom left), 91 m (bottom right)
2. Mean deviation of the remote sensor measurements and the reference measurements
The different uncertainty components are added in quadrature for each wind speed bin. The uncertainty
due to non-homogenous flow between the measurement volume of the Lidar and at the met mast is
assumed to be negligible due to the proximity of the Lidar to the mast and the benign terrain conditions
at the Pershore test site. Details on the calculation of the separate uncertainty components are described
in Appendix F.
The results of the uncertainty calculation for the IEC compliant verification of the Lidar device at every
comparison level are plotted in Figure 8. The finally combined uncertainties of the remote sensing RSD
(VRSD) for the different WS bins and comparison levels show results values well below 2 % within most of
the bins.
For the current Lidar verification campaign the completeness requirement to yield 180 hours of valid and
useable concurrent data (which translates into 7.5 days of data) in the WS range 4 and 16 m/s between
the RSD and the reference cup is met for each comparison level.
The additional data completeness requirement of yielding a minimum of 3 data pairs in each 0.5 m/s
wide wind speed bin is fulfilled for most of the WS bins and comparison levels. Note that uncertainties
are not calculated for wind speed bins with less than three data points.
In Appendix G the environmental parameters - present during the performance verification test - are
documented.
*
Insufficient number of data points for uncertainty calculations
*
Insufficient number of data points for uncertainty calculations
*
Insufficient number of data points for uncertainty calculations
*
Insufficient number of data points for uncertainty calculations
Furthermore, the IEC compliant bin-wise uncertainty implementation may serve as a traceable means to
judge the uncertainty of the RSD as determined from a well-defined verification process.
Any statement given in the context of system integrity and data quality related results within this report are
limited to the given test site conditions, to the prevailing atmospheric (in particular wind) conditions and to
the specific Lidar configuration as selected for this LPV campaign.
For sites with non-benign terrain and atmospheric conditions, an LPV is not thought to replace the
requirement for an on-site verification. In this situation it may be necessary to conduct measurements in
close proximity to an on-site mast over a reasonable period.
The overall system availability for the mentioned total campaign duration of 53.5 days for ZP 594 is 96.8 %.
The data availabilities at the selected Lidar measurement levels 20 m, 45 m, 70 m and 91 m was in the
range of 89.7 % to 94.6 %. These data coverage figures are relative to the number of maximum possible
ten-minute data points for the total duration of the campaign.
Wind speed (and direction) correlations were carried out for each of the four WS measurement levels (one
for WD) mentioned above. The wind speeds of both techniques at all treated levels correlated very well,
showing a very low level of scatter and an excellent resemblance of Lidar wind speeds to those of cups, in
terms of linear regression slopes.
✓ The Acceptance Criterion for System Availability (KPI SACA) to be ≥95 % is successfully passed
(Table 4).
✓ The Acceptance Criterion for Data Availability (KPI DACA) to be ≥90 % is successfully met at the 20,
45 and 70 m measurement levels.
✓ Regression slope (KPI Xmws) between 0.98 and 1.02 at all treated levels and for all WS ranges,
meeting the Acceptance Criteria (Table 5, column 2).
✓ R2 (KPI R2mws) > 0.97 at all treated levels for the WS ranges a) [all WS > 3 m/s]and b) [4 to
16 m/s], meeting the Acceptance Criteria (Table 5, column 3).
✓ The Acceptance Criterion for the relative Campaign Mean Wind Speed Difference (KPI Cmwsd) (see
Table 5, column 7) is successfully passed at the 20, 45 and 70 m measurement levels for both WS
ranges.
✓ Absolute Wind Speed Difference (KPI Awsd) at all comparison levels and for all analysed wind speed
data between 3 and 16 m/s where wind speed differences of greater than 0.5 m/s makes up < 5 %
of the full dataset (Table 6).
✓ The Acceptance Criteria for the respective KPIs for wind direction assessment (KPIs for Xmwd and
R2mwd) is successfully passed at only the for both measurement levels. The Criterion for KPI OFFmwd
for the wind direction assessment is passed at the 88 m level.
o Acceptance Criterion for Data Availability (KPI DACA) to be ≥90 % is missed for the 91 m
measurement level (Table 4).
o The Acceptance Criterion for the relative Campaign Mean Wind Speed Difference (KPI Cmwsd) (see
Table 5, column 7) is missed at the 91 m measurement level.
o The Criterion for the KPI OFFmwd for the wind direction assessment is missed at the 45 m level.
o During the verification campaign the bins for the following measurement levels cannot be calculated
given insufficient data points:
▪ 14.5 m/s and 15.5 m/s bins for the 45 m measurement level;
In summary, this Pershore validation campaign indicates that the ZephIR 300 Lidar with the serial number
ZP 594 is able to reproduce cup anemometer wind speeds and wind vane directions at an accurate and
acceptable level. DNV GL considers that the ZephIR 300 Lidar device under test (with the serial number
ZP 594) can be used for formal wind potential and long-term wind resource assessments. Specifically,
DNVGL concludes that this Lidar may be employed as a standalone measurement system – replacing a
conventional met mast – given the following criteria are met:
(1) The Lidar is deployed in a location with benign terrain and atmospheric conditions.
▪ recording data for a period sufficient to obtain an adequate in-situ correlation to an onsite
reference (e.g. a short met. mast);
Finally, DNV GL recommends, that care needs to be taken with respect to the formal use of Lidar turbulence
and extreme wind speed measures, not treated in this report but known to be different from classical
anemometry measures. DNV GL likes to point out that good measurement and data collection practices need
to be maintained for all wind speed measurements, be they Lidar or more conventional anemometry.
Therefore, special care needs to be exercised in the transportation, installation and on-going maintenance of
the Lidar as it may be exposed to a wide range of environmental conditions at different sites over time. A
key element of any formal wind study is the traceability of the wind speed data uncertainty. Hence, a strict
uncertainty assessment (which is not part of this report) should be employed. Furthermore it is
recommended that thorough practices of documenting the salient features of Lidar installation and
maintenance are instigated from the outset.
2. Kindler, D., " Best Practice Test and Verification Procedure for Wind LiDARs on the Høvsøre Test Site”,
GL GH-D Report WT 6960/09 for EU-Project NORSEWInD, Deliv. 1.1, June 2009.
3. International Standard: IEC 61400-12-1: Wind turbines – Part 12-1: Power Performance Measurements
of Grid Connected Wind Turbines. Ed. 1. International Electronic Commission.
3, rue de Varembé Geneva. Switzerland, Dec. 2005.
4. International Standard: IEC 61400-12-1: Wind turbines – Part 12-1: Power performance measurements
of electricity producing wind turbines. Ed. 2. CD. International Electronic Commission.3, June. 2013.
5. IEA Expert Group Study on Recommended Practices for Wind Turbine Testing and Evaluation 11. Wind
speed measurement and use of cup anemometry, 1. Edition 1999.
7. W. Barker, E. Burin des Roziers, "Pershore: 91m Anemometer Mast Specification and Data Validation,
Revision 2", by ZephIR Ltd., issued: 10/10/2012.
8. Stein, D. “Technical Note of Inspection of ZephIR’s Reference Met Mast and Lidar Test Site (exec. 2015-
09-01) at Pershore/Throckmorton, UK” DNV GL Report, No. GLGH-4257 15 13307 267 T-0001, Rev. B,
2016-05-02.
Abbreviation
Meaning
Acronym
AC Acceptance Criterion
a.g.l. Above ground level
DNV GL New company name, successor of legacy GL GH
IEC International Electro-technical Commission
IEA International Energy Agency
GH-D GL Garrad Hassan Deutschland GmbH
MM Meteorological Mast
PAR Performance Assessment Requirement
LPV Lidar Performance Verification
TI Turbulence Intensity
WD Wind direction
WS Wind speed
Table 13: List of KPIs and ACs relevant for System and Data Availability assessment
Acceptance Criteria
KPI Definition / Rationale across total
campaign duration
SACA System Availability ≥95%
The Lidar system is ready to function according to
specifications and to deliver data, taking into account all
time stamped data entries in the output data files
including flagged data (e.g. by NaNs or 9999s) for the
pre-defined total campaign length.
The System Availability is the number of these time
stamped data entries relative to the maximum possible
number of data entries (for 10 minute intervals) within
the pre-defined total campaign period.
In the above table, during periods of maintenance; the system is deemed unavailable.
* Undisturbed sectors: this means sectors with no significant flow distortion e.g. by wake effects of nearby
wind turbines
Acceptance Criteria
KPI Definition / Rationale
45 m
10% 20% 30% 40% 10% 20% 30% 40%
The anemometer uncertainty of the specific reference levels is calculated based on the wind tunnel
calibration of the individual anemometer, the anemometer classification and the mounting effect at the met
tower.
2. Mean deviation of the remote sensor measurements and the reference measurements
This is the relative deviation between the bin averages of the RSD and the mast reference measurement
divided by with the reference measurement.
The standard deviation of the measurements was divided by the square root of the number of data records
per bin. The relative uncertainty was calculated by dividing the value by the bin average wind speed of the
mast (reference) measurement.
The uncertainty of the remote sensing device due to non-ideal levelling was estimated to be 0.5 %.
The Lidar device is located in close proximity of the met tower just a few m to the East of the tower base. As
a result the uncertainty due to non-homogenous flow within the measurement volume is considered to be
negligible.
# PiA Quality
BIN BIN Shear exponenet TI Wind direction Temperature Air Density Wind Veer
Vmm Factor
Lower Upper 70 m -20 m at 70 m at 88 m at 44 m at 44 m 88 m - 44 m
at 70 m1
Average Average Std Average Std Average Std Average Std Average Std Average Std Average Std
[m/s] [m/s]
[m/s] [-] [-] [-] [-] [#] [#] [°] [°] [°C] [°C] [kg/m3] [kg/m3] [°] [°]
3.75 4.25 3.99 0.43 0.27 0.099 0.047 34.4 1.5 175.5 76.4 4.3 3.0 1.280 0.021 7.3 12.0
4.25 4.75 4.50 0.43 0.26 0.096 0.043 34.3 1.3 185.0 77.0 4.8 3.2 1.274 0.022 7.9 9.7
4.75 5.25 5.01 0.40 0.23 0.098 0.043 34.2 1.3 200.3 81.2 5.1 3.2 1.273 0.021 7.1 7.7
5.25 5.75 5.51 0.36 0.20 0.102 0.045 34.2 1.3 205.5 74.4 5.5 3.2 1.269 0.020 6.2 6.1
5.75 6.25 6.00 0.34 0.18 0.098 0.040 34.2 1.7 207.4 65.6 5.7 3.4 1.265 0.020 6.6 6.1
6.25 6.75 6.50 0.30 0.15 0.097 0.036 34.2 1.3 215.4 61.9 6.1 3.3 1.263 0.019 6.1 5.5
6.75 7.25 6.99 0.29 0.13 0.098 0.034 34.2 1.4 215.1 55.2 6.1 2.9 1.261 0.018 6.0 4.9
7.25 7.75 7.49 0.28 0.10 0.094 0.034 34.3 1.4 221.5 56.1 6.0 2.9 1.262 0.017 6.3 5.0
7.75 8.25 7.99 0.29 0.10 0.092 0.034 34.5 1.2 228.8 57.0 5.8 2.8 1.262 0.017 6.3 5.1
8.25 8.75 8.49 0.27 0.09 0.097 0.034 34.5 1.1 232.8 52.0 6.3 3.3 1.260 0.018 5.6 4.7
8.75 9.25 9.00 0.25 0.09 0.102 0.035 34.6 1.1 232.1 43.6 7.0 3.2 1.256 0.015 4.5 3.8
9.25 9.75 9.50 0.23 0.09 0.107 0.035 34.4 1.3 235.1 53.1 7.0 3.2 1.255 0.014 3.8 3.5
9.75 10.25 9.98 0.23 0.07 0.106 0.031 34.5 1.1 240.6 41.8 7.5 3.0 1.255 0.013 3.9 2.8
10.25 10.75 10.46 0.22 0.06 0.118 0.033 34.6 0.8 250.0 39.6 7.4 2.8 1.254 0.012 3.5 2.3
10.75 11.25 10.99 0.19 0.06 0.120 0.041 34.5 1.1 247.6 34.2 8.4 2.7 1.252 0.013 2.8 2.3
11.25 11.75 11.54 0.19 0.05 0.129 0.033 34.6 1.2 250.4 32.9 9.3 2.7 1.246 0.012 2.4 2.3
11.75 12.25 11.99 0.19 0.05 0.130 0.032 34.8 1.9 253.3 37.4 9.1 3.3 1.245 0.012 2.1 1.5
12.25 12.75 12.48 0.19 0.03 0.135 0.030 34.5 0.9 252.7 34.4 9.4 2.7 1.244 0.009 2.0 1.0
12.75 13.25 12.97 0.18 0.04 0.145 0.037 34.7 0.7 258.2 35.6 9.5 1.8 1.244 0.007 2.1 1.0
13.25 13.75 13.60 0.19 0.05 0.137 0.037 35.0 0.9 259.7 43.1 8.8 2.0 1.245 0.008 1.6 0.9
13.75 14.25 14.03 0.16 0.04 0.146 0.028 34.2 3.0 241.3 42.5 9.4 2.2 1.244 0.008 2.1 0.9
14.25 14.75 14.50 0.17 0.03 0.137 0.022 33.6 2.1 222.4 34.8 10.1 0.9 1.240 0.005 1.8 0.7
14.75 15.25 15.01 0.18 0.04 0.147 0.022 34.1 1.8 261.0 51.4 9.0 2.8 1.240 0.010 1.3 0.9
15.25 15.75 15.43 0.17 0.03 0.160 0.024 34.0 1.4 255.5 55.2 8.8 2.7 1.243 0.009 1.4 1.2
15.75 16.25 16.07 0.16 0.06 0.131 0.020 34.0 1.2 220.1 41.9 10.4 0.9 1.237 0.001 2.0 0.6
1. Packets in Average (PiA) quality factor records for the Lidar were missing for a total of approximately two days during the measurement campaign.