University of Cape Town: Power Station Thermal Efficiency Performance Method Evaluation
University of Cape Town: Power Station Thermal Efficiency Performance Method Evaluation
University of Cape Town: Power Station Thermal Efficiency Performance Method Evaluation
n
w
To
e
ap
C
Prepared by:
Heeran Heerlall
of
HRLHEE001
ty
Supervisor:
Dr. Ryno Laubscher
ni
U
February 2021
Submitted to the Department of Mechanical Engineering at the University of Cape Town in partial
fulfilment of the academic requirements for a Master’s of Science degree in Mechanical
Engineering
Key Words: STEP, thermal performance, coal-fired, power plant, sequential perturbation,
uncertainty propagation.
n
w
To
The copyright of this thesis vests in the author. No
quotation from it or information derived from it is to be
e
published without full acknowledgement of the source.
ap
The thesis is to be used for private study or non-
commercial research purposes only.
C
Published by the University of Cape Town (UCT) in terms
of
Eskom’s thermal accounting tool, the STEP model, was reviewed against relevant industry
standards (BS 2885, BS EN 12952-15, IEC 60953-0/Ed1) to evaluate the model uncertainty for
losses computed via standard correlations. Relatively large deviations were noted for the boiler
radiation, turbine deterioration and make-up water losses. A specific review of OEM (Original
Equipment Manufacturer) heat rate correction curves was carried out for the determination of
turbine plant losses, where these curves were suspected to have high uncertainty, especially when
extrapolated to points of significant deviation from design values. For an evaluated case study, the
final feed water correction curves were adjusted based on an analysis done with the use of power
plant thermodynamic modelling tools namely: EtaPro Virtual Plant® and Steam Pro®.
A Python® based computer model was developed to separately propagate systematic (instrument)
and combined uncertainties (including temporal) through the STEP model using a numerical
technique called sequential perturbation. The study revealed that the uncertainties associated
with thermal efficiency, heat rate and individual thermal losses are very specific to the state of
operations, as demonstrated by individual unit performance and the power plant’s specific design
baseline performance curves. Whilst the uncertainties cannot be generalized, a methodology has
been developed to evaluate any case. A 3600 MWe wet-cooled power plant (6 x 600 MWe units)
situated in Mpumalanga was selected to study the impact of uncertainties on the STEP model
outputs.
The results from the case study yielded that the thermal efficiency computed by the “direct
method”, had an instrument uncertainty of 0.756% absolute (abs) versus the indirect method of
0.201% abs when computed at the station level for a 95% confidence interval. For an individual
unit, the indirect efficiency uncertainty was as high as 0.581% abs.
A study was conducted to find an optimal resolution (segment size) for the thermal performance
metrics to be computed, by discretizing the monthly data into smaller segment sizes and studying
the movement of the mean STEP model outputs and the temporal uncertainty. It was found that
i
the 3-hour segment size is optimal as it gives the maximum movement of the mean of
performance metrics without resulting in large temporal uncertainties. When considering the
combined uncertainty (temporal and instrument uncertainty) at a data resolution of 1 minute and
segment size of 3 hours, the “direct method”, had a combined thermal efficiency uncertainty of
0.768% abs versus the indirect method of 0.218% abs when computed at the station level for a
95% confidence interval. This would mean that the temporal uncertainty contribution to the
combined uncertainty is 2.915% for the “direct method” and 14.919% for the “indirect method” of
the above-stated uncertainties.
The term “STEP Factor” can be used synonymously with effectiveness (percentage of the actual
efficiency relative to the target efficiency). For the case evaluated, the mean “indirect method”
STEP Factor at the station level moved from 86.698% (using monthly aggregated process data) to
86.135% (when discretized to 3-hour segments) which is roughly a 0.189% abs change in the
station’s thermal efficiency. This would appear fairly small on the station’s overall efficiency but
had a significant impact on the evaluation of the STEP Factor losses and the cost impact by the
change in the plant efficiency, e.g. the final feed water STEP Factor loss at a unit level moved from
2.6% abs to 3.5% abs which is significant for diagnostic and business case motivations.
Later the discrepancy between the direct STEP Factor and indirect STEP Factor were investigated
as the uncertainty bands did not overlap as expected. The re-evaluation of the baseline
component performance data resulted in the final feed water and the condenser back-pressure
heat rate correction curves being adjusted. The exercise revealed that there could be potentially
be significant baseline performance data uncertainty. The corrected indirect STEP Factor
instrument uncertainty was now found to be 0.468% abs which translates to 0.164% abs overall
efficiency. The combined uncertainty was corrected to 0.485% abs at a 3-hour segment size which
translates to 0.171% abs overall efficiency.
It has been deduced that the figures stated above are case-specific. However, the models have
been developed to analyse any coal-fired power plant at various operating conditions.
Furthermore, the uncertainty propagation module can be used to propagate uncertainty through
any other discontinuous function or computer model.
Various recommendations have been made to improve: the model uncertainty of STEP, data
acquisition, systematic uncertainty, temporal uncertainty and baseline data uncertainty.
ii
Declaration
I, Heeran Heerlall, hereby declare the work contained in this dissertation to be my own. All
information that has been gained from various journal articles, textbooks or other sources has
been referenced accordingly. I have not allowed, and will not allow, anyone to copy my work with
the intention of passing it off as their own work or part thereof.
_________________________
H Heerlall
iii
Acknowledgements
The Almighty is acknowledged in all my achievements and endeavours.
I would like to thank my wife, Karen Heerlall and children for the support given during the period
of this study and always.
Thanks to my academic supervisor for providing guidance, insight on the subject matter of this
study and steering me to acquire new valuable skills in the process of carrying out the study.
Thanks to Eskom’s: EPPEI, Energy Efficiency Care Group, Steering Committee of Technology,
Hendrina Power Station management and Production Integration Coal management for the
support.
Thanks to my team (Hendrina Power Station - Process Engineering Department) for affording me
time through their flexibility and diligence in their duties.
Thanks to Matimba Power Station’s –Performance and Test Department for the data provided.
Thanks to Kusile Power Station’s –Performance and Test Department for including me in their
performance tool development.
Thanks to Duvha Power Station’s –Performance and Test Department for access to plant data, and
signal processing tools.
Thanks to Nick Moolman for sharing his wisdom and information on the subject matter.
Thanks to the academic team at the Department of Mechanical Engineering at UCT for
contributions and insight and advice during course work and colloquiums.
iv
Table of Contents
List of Figures .................................................................................................................................... viii
List of Tables......................................................................................................................................... x
1. Nomenclature ................................................................................................................................. xi
1.1. General symbols ....................................................................................................................... xi
1.2. Acronyms and abbreviations .................................................................................................... xi
1.3. The naming convention for equations and program variables ...............................................xiv
1.4. Definitions ................................................................................................................................xv
2. Introduction ..................................................................................................................................... 1
2.1. Purpose ...................................................................................................................................... 2
2.2. Goals and objectives.................................................................................................................. 4
3. Literature review .............................................................................................................................. 6
Thermal power plants ...................................................................................................................... 6
World energy outlook ...................................................................................................................... 6
Thermal efficiency performance methodology ............................................................................... 9
Boiler efficiency principles ............................................................................................................. 10
Turbine plant efficiency .................................................................................................................. 11
Cycle losses ..................................................................................................................................... 12
Fundamental principles of STEP ..................................................................................................... 13
Uncertainty analysis ....................................................................................................................... 14
Law of Error Propagation ............................................................................................................... 14
Sequential Perturbation (SP) .......................................................................................................... 15
Monte Carlo.................................................................................................................................... 15
4. Methodology .................................................................................................................................. 18
4.1. Understanding STEP ................................................................................................................ 18
4.2. Data validation ........................................................................................................................ 25
4.3. Modelling for uncertainty analysis .......................................................................................... 28
5. Results and discussion.................................................................................................................... 42
5.1. Model uncertainty ................................................................................................................... 42
5.2. Instrument uncertainty ........................................................................................................... 47
v
5.4. Temporal uncertainty .............................................................................................................. 56
5.5. Baseline data uncertainty ........................................................................................................ 61
6. Conclusions and summary of recommendations .......................................................................... 63
6.1. Conclusion ............................................................................................................................... 63
6.2. Recommendations................................................................................................................... 63
7. References ...................................................................................................................................... 68
Appendix A. Equations and correlations from literature ................................................................... 73
A.1. Boiler performance principles [14] ............................................................................................. 73
A.1.1. Boiler efficiency ....................................................................................................................... 73
A.1.2. Flue gas / chimney loss ............................................................................................................ 74
A.1.3. Unburned CO loss .................................................................................................................... 74
A.1.4. Ash sensible and unburned combustible heat loss ................................................................. 74
A.1.5. Radiation and convection losses.............................................................................................. 75
A.2. Turbine plant performance principles [15]................................................................................. 75
A.2.1. Turbine deterioration Loss [15] .............................................................................................. 75
A.2.2. Turbine back pressure Loss...................................................................................................... 76
A.2.3. Other turbine plant losses ....................................................................................................... 76
A.3. Cycle losses[33] ........................................................................................................................... 78
A.3.1. Make-Up water loss ................................................................................................................. 78
A.4. Error propagation techniques ..................................................................................................... 78
A.4.1. Gaussian Quadrature (GQ) ...................................................................................................... 78
A.4.2. Method of Moments (MM) ..................................................................................................... 79
A.4.3. Sigma Point (SP) ....................................................................................................................... 80
A.4.4. Polynomial Chaos Expansion (PCE) and Probabilistic Collocation Method (PCM) ................ 81
Appendix B. STEP calculations ........................................................................................................... 82
Appendix C. Model uncertainty analysis .......................................................................................... 125
C.1. Carbon in refuse as per STEP [33] ............................................................................................. 125
C.2. Carbon in refuse as per BS EN standard [14] ............................................................................ 126
C.3. Carbon monoxide loss as per BS EN 12952-15 [14] .................................................................. 126
C.4. Dry flue gas (DFG) loss as per STEP [33] ................................................................................... 127
C.5. Dry flue gas (DFG) loss as per BS 2885 [5] ................................................................................ 128
vi
C.6. Dry flue gas (DFG) loss as per BS EN 12952-15 [14] ................................................................. 128
C.7. Hydrogen and moisture loss as per BS EN 12952-15 [14] ........................................................ 131
C.8. Hydrogen and moisture loss as per STEP [33] ......................................................................... 132
C.9. Make-up water [33] .................................................................................................................. 133
C.10. Radiation and convection loss as per BS EN 12952-15 [14] ................................................... 135
C.11. Radiation loss as per STEP [14] ............................................................................................... 135
C.12. Turbine deterioration loss as per STEP ................................................................................... 136
C.13. Turbine deterioration loss as per the IEC [72] ........................................................................ 136
C.14. Turbine deterioration loss as per ASME PTC 6 Report-1985 [46].......................................... 136
Appendix D. STEP program inputs details ........................................................................................ 137
Appendix E. STEP program output tag list ....................................................................................... 143
Appendix F. Results .......................................................................................................................... 149
Appendix G. Model verification ....................................................................................................... 155
vii
List of Figures
Figure 2-1: Diagram of a typical coal-fired thermal power station [9] ................................................ 3
Figure 2-2: Illustration of the impact of averaging inputs rather than the result ............................... 4
Figure 3-3: South African overall efficiency vs availability (courtesy: Y. Maharaj-Eskom) .................. 8
Figure 3-4: Efficiency of public conventional thermal power production in Europe [11] ................... 9
Figure 3-5: Illustration of Monte Carlo randomized iterations for Gaussian distributed inputs and
outputs - adapted from [47] .............................................................................................................. 16
Figure 3-6: Demonstration of Monte Carlo convergence as a function of the number of iterations
[54] ..................................................................................................................................................... 17
Figure 4-15: Step 4 -Uncertainty propagation to calculated variable per segment run for each input
variable ............................................................................................................................................... 40
viii
Figure 4-16: Step 6 - Illustration of segmented operational data ..................................................... 40
Figure 4-17: Step 8 - Example of combined uncertainty of calculated variables per segment run .. 41
Figure 5-3: Variable significance on station cycle indirect STEP Factor uncertainty ......................... 52
Figure 5-4: Final feed water - original heat rate correction factor curves ........................................ 53
Figure 5-5: Variable significance on station cycle direct STEP Factor loss uncertainty ..................... 53
Figure 5-6: Variable significance on uncertainty on the station cycle and turbine plant SF losses .. 54
Figure 5-7: Variable significance on uncertainty on the station boiler SF losses .............................. 55
Figure 5-9: Station STEP Factor results with uncertainty bounds ..................................................... 58
Figure 5-13: Station STEP Factor results with uncertainty bounds – corrected ................................ 62
Figure 5-14: Station STEP Factor systematic vs combined uncertainty - corrected .......................... 62
ix
List of Tables
Table 2-1: Legend to Figure 2-1 ........................................................................................................... 3
Table 3-1: Summary of the evolution of coal-fired power plants (adapted from[9][10]) ................... 6
Table 5-2: Sensitivity analysis on the fraction of make-up water lost at main steam conditions ..... 44
Table 5-4: Truncated results drill-down approach – instrument uncertainty propagation .............. 50
x
1. Nomenclature
1.1. General symbols
Cp Specific heat capacity at constant pressure (J/kg.K)
Eff or η Efficiency
h Specific enthalpy (J/kg)
h Hour
i Range variable – each power cycle unit (i.e. 1..6 for a 6 unit power plant)
j Range variable - generic
J Energy
k Empirical constant
L Loss (%)
m Mass
M Molar mass (kg/kMol)
ṁ or `m or MFR Mass flow rate
N ,n Number
P Pressure
P or Pow Power
PF Power factor
Q Heat
S Sample standard deviation
T Temperature
t Time
u Uncertainty
V Volume
w Absolute humidity (kg/kg)
x Mass fraction (kg/kg)
y Volume fraction (V/V)
Greek symbols
η or Eff Efficiency
µ Mass ratio relative to the mass of fuel
σ Population standard deviation
xi
AS Atomizing steam(for fuel oil firing)
ASME American Society of Mechanical Engineers
AT Acceptance test
Aux Auxiliary
AVL Average load generated
BA Bottom ash
BD Blow down
BFPT Boiler feed pump – turbine driven
BMCR Boiler maximum continuous rating
Boil Boiler
Bool Boolean
BP Backpressure (Condenser Pressure)
BR Burn rate
BS British Standard
BSI British Standards Institute
Ce Carbon equivalent
BCEGB British Central Electricity Generating Board
CEP Condensate extraction pump
CF Correction factor
CIR /CIG Carbon In refuse / Carbon in grit
CLF Capability loss factor (unavailability)
CO Carbon Monoxide
Comb Prod Combustion products
Comm Commissioning
Cond Condensate
Cons Consumption
Corr Correction or corrected
CSV Comma-separated values
Cu Unburned coal (fraction of coal-fired)
CV Calorific value
DA Dry Air
Depres Depression (difference between LP turbine exhaust temperature and steam
saturation temperature at low-pressure exhaust pressure
Det Deterioration
DFC Mass ratio of Dry Flue Gas to 1kg Carbon burned
DFG Mass ratio of Dry Flue Gas to 1kg fuel burned
DIN Deutsches Institut für Normung (German Institute for Standardization)
DMAIC Define, Measure, Analyze, Improve and Control
EFP Electric (driven) feed water pump
EM Excess moisture
EPPEI Eskom Power Plant Engineering Institute
Equiv Equivalent
Extr Extraneous
FA Fly ash
FC Fixed Carbon
FD Forced draught fan
FO Fuel oil
FW Feedwater
Gen Generator
GQ Gaussian Quadrature
GT Generator transformer
xii
HGI Hard Grove Index
HPT High-pressure turbine
HR Heat rate
HV High voltage
IEC International Electrotechnical Commission
Imp Import
Incr Incremental
IPT Intermediate pressure turbine
ISO International Organization for Standardization
L Loss (%)
Leak Leakage (%)
LF Load factor
LH Left hand
LPT Low-pressure turbine
LS Live Steam (steam at high-pressure turbine inlet)
LV Low voltage
MCR Maximum continuous rating
MCS Monte Carlo simulations
MF Moisture-free Basis
moist Moisture
MP Measurement point
MR Mill rejects
MS Main steam
MU Make-up (demineralized water)
MV Medium voltage
NER Normal economic rating
NL No load
OL Off -load
Opt Optimum
PCLF Planned capability loss factor (%) -the measure of planned unavailability
Pract Practical
R&E Revenue and expenditure
Rad Radiation
RC Radiation and convection
ref Reference
ReH Re-heater
Rej Rejection (To Atmosphere)
RH Right hand
RSS Root sum square
RT Run time
RW Raw water
SA Steam air heater
SAH Sulphur
Sat Saturation
SB Station board
Sby Standby
SD Shutdown
SF STEP factor (actual – target)
SFP Steam (driven) feed water pump
SM Surface moisture
STEP Station Thermal Efficiency Performance
xiii
Chapter 2. Introduction
2. Introduction
South Africa and Africa as a whole is currently faced with a significant challenge of meeting its
energy demand whilst transforming to cleaner electric energy production. Eskom is a state-owned
power utility that manages the distribution, transmission and dispatching of electricity on the
South African power grid. Almost 85% of South Africa’s electric energy is provided via Eskom’s
conventional coal-fired power plants [1]. One of the challenges identified is the ageing of Eskom’s
power generation fleet with limited capital to meet the maintenance requirements for optimal
performance and reliability. Over the last decade or two, there has been a great focus on
minimizing load shedding which might have meant that some of the assets would have been
operated at higher load factors and in some cases exceeding recommended maintenance
intervals, to compensate for diminished capacity. A significant portion of the power production
fleet is in the final 10 years of its designed operating life. Six out of the thirteen fully commercial
power plants are to be decommissioned by 2030 as per the Integrated Resource Plan 2018 Update
[2]. Naturally, significant investments in these power plants would be curbed as it would be
difficult to justify a return on investment for a short remaining operating life.
A consequence of the cited challenges and constraints is the decline in the fleet’s thermal
efficiency. Thermal efficiency is an indication of the state of the plant's performance and
correlates with the plant’s availability. A lower thermal efficiency will result in: plant components
having to work near design limits for extended periods which reduces the remnant life of the
components, or the power plant not being able to achieve the rated generating capacity. The
improvement of a power plant’s thermal efficiency should contribute positively to the power
generation capacity and is a significant aspect in reducing the cost of operations.
The path to recovery would require some engineered methods of getting the maximum
performance gains with minimum capital injection. Whilst there are various tools employed in
industry, Eskom being the largest power producer in Africa has adopted a program called Station
Thermal Efficiency Performance (STEP) to evaluate the thermal performance of their coal-fired
power plants.
The goal of this research is to improve the means of efficiency and thermal loss evaluation for
coal-fired power plants so that improvement initiatives can be confidently justified. A key focus of
the study is the evaluation of the accuracy of the stated method that is used.
1
Chapter 2. Introduction
2.1. Purpose
South Africa is the largest power producer in Africa [3]. Eskom claims to produce 95% of this
power [1], with 90% of its generating capacity in the form of conventional coal-fired power plants
[4]. These plants employ the typical regenerative-reheat Rankine cycle where: the turbines are
driven by superheated steam (see Figure 2-1), the LP turbine exhaust steam is condensed via
condensers supplied by wet or dry cooling water systems, the condensate is preheated by
regenerative feedwater heaters and steam is generated by pulverized fuel (PF) boilers. Eskom uses
a thermal performance model called STEP to evaluate the Rankine cycle performance and identify
losses in the power generation process. Although there are differences in technology, such as
drum-boilers vs once-through, air-cooled condenser (ACC) vs wet natural draught cooling towers,
subcritical vs supercritical boilers, reheat and non-reheat cycles, the model uses a standardized
approach with a few differences in the calculation methodology applied. The differences in the
calculation methodologies are augmented with customized inputs for each power station. There is
also functionality to compensate for differences in the configuration (positions of measured
inputs) and technology (mainly the cooling water system employed).
The STEP model intends to provide an assessment to quantify the state of operations and
monetary impact for the deviations from ideal or expected performance (see section 4.1 for more
details). The calculation principles of STEP are based on industry standards for acceptance testing
of boilers [5] and turbines [6], which typically employ energy balances based on the Rankine cycle
thermodynamics (see Figure 2-1: Diagram of a typical coal-fired thermal power station [9], the
principles are further elaborated in section 4.1 and Appendix B).
The current topic for research and development was initiated from the need for continuous
improvement on the thermal efficiency performance/accounting tools. In the current global
context, there is a strong focus on cleaner electricity production coupled with affordability. Even
though coal-fired power plants are viewed as a “dirty” production process, it is envisaged that
coal-fired generation will have a significant contribution to the energy mix in the next fifty years to
come [7].
In the South African context, the power plants are ranked in merit order for the dispatching of
electricity to the national grid. The ranking is determined predominantly by the cost of primary
energy. The power plant industry is transitioning to competitive dispatching of energy that
considers the cost of productions, thermal efficiency and emission offsets such as carbon tax [8].
STEP is an instrument that can be used to drive the medium-term objectives of environmental
sustainability and cost reduction through energy efficiency maximization. In the current work, the
STEP model is extended to evaluate instrument and temporal (random) uncertainties on the
2
Chapter 2. Introduction
model output values. The quantification of these uncertainties, and insights gained from the STEP
modelling approach, could lead to an increase in accuracy. To implement the uncertainty
estimation, a computer model of the STEP calculation methodology is developed using the Python
3.8 programming language. During the development of the computer model, the calculation
approach will also be reviewed.
3
Chapter 2. Introduction
The function evaluated at the average input, x = 2 (4) does not equate to the average of the
results for x = 1 and x = 3 (8). The above principle demonstrated would be much more critical
in the case of flexible operations i.e. load swings for non-baseload power plants. With the
increasing penetration of renewable power generation, it is expected that the power plants
would operate with an increase in load transients due to the nature of renewable power
production.
5
Chapter 3. Literature review
3. Literature review
This chapter will focus on the evolution of thermal power plant technology and the development
of performance standards, the adoption of these standards in the development of the STEP
modelling approach and uncertainty propagation methods employed in power plant efficiency
evaluation applications.
Thermal power plants were developed during the 18 th century with the first commercial plant
being commissioned in 1882 based on the reciprocating steam engine technology [9]. The first
steam turbine was developed in 1884 with a thermal efficiency of only 1.6% [10]. By 1905 steam
turbines replaced all reciprocating engines in large central power stations. During the 1900s
boilers were constructed with evaporators, economizers and superheaters. By the 1910s
condensing turbines with extractions for feed heating operated at a thermal efficiency of 15%. In
the 1930s, pulverised fuel boilers with reheat steam had become prominent. Supercritical steam
plants were produced by the 1960s. A summary of the technology evolution for coal-fired power
plants can be found in Table 3-1.
Table 3-1: Summary of the evolution of coal-fired power plants (adapted from[9][10])
(IEA) and Statista suggest that coal and other fossil fuels will maintain a significant share in the
world’s energy mix in the medium-term. Coal-fired technologies are still maintained by 2050 even
on the “New Policy Scenario”, hence significant effort must be made to improve the thermal
efficiencies of conventional fossil plants to reduce the carbon footprint as well as NOx and SOx
emissions. According to The World Bank, about 40 countries have already implemented carbon
pricing globally with significant commitments from others to move in this direction [8]. These
countries particularly in Europe have demonstrated this improvement [11].
The South African average power generation efficiency has shown a steady decline over recent
years as observed from Figure 3-3 (x and y labels removed for confidentiality reasons, indicative
only) The planned and unplanned unavailability has increased from the financial year 2012. A
direct relationship between thermal efficiency and plant availability can be observed. In the
current state, there are significant opportunities to improve thermal efficiency through enhanced
deficiency identification and resolution. There are significant factors that may have a detrimental
effect on thermal efficiency which include: inadequate funding, execution of maintenance
strategies, remnant design lifespan, skills, coal quality, etc.
Other parts of the world have shown an upward trend in thermal efficiency where carbon pricing
has been implemented, particularly in Europe. Thermal efficiency had been on a decline in this
region from 2010 but has recovered post-2014 as demonstrated in Figure 3-4 by the European
Environment Agency (EEA).
7
Chapter 3. Literature review
8
Chapter 3. Literature review
Figure 3-4: Efficiency of public conventional thermal power production in Europe [11]
Standard energy balance methods have been employed in the power plant industry since the
1800s. The first ASME boiler test code was established in 1884 (ASME established in 1880) [14].
The DIN 1942 and BS 2885 standards can be traced back to 1975 and 1974 respectively.
Of late, the number of performance standards has reduced due to merging and collaborations of
standards by the standards institutes, especially in Europe. The major standards applied to
Eskom’s generating fleet thermal performance analysis are the: BS-EN standard [15], BS–EN(IEC)
standards [6][16] and ASME standards [17][18][19].
From the mid-’90s to current, there is a growing interest in exergy analysis which has yielded
various studies on fossil-fired power plants. The exergy efficiency method accounts for non-useful
energy by using the 2nd law of thermodynamics i.e. entropy change of a stream to be brought to
equilibrium with its surroundings (destruction of exergy) and hence usually yields higher
efficiencies when compared to standard thermal efficiency calculation techniques. Many authors
deem exergy analysis to be the preferred method of analysing an energy conversion process as it
would differentiate between losses to the environment vs internal irreversibilities. Rashad and
Elaihy [20] presented both an energy and exergy analysis on a 1260 MWe natural gas power plant
in Egypt in 2009 which demonstrated the above point. Aljundhi presented an exergy study done
for 396 MWe heavy fuel oil power plant in Jordan also in 2009 [21], and Mahamad et al. presented
9
Chapter 3. Literature review
across and within the boiler tubes coupled with a CFD simulation to acquire fluid properties
external to the wall tubes. The CFD simulation incorporated combustion dynamics. The method
could further be expanded to explore the impact of coal properties on the dry flue gas loss. It
would be interesting to explore the heat transfer impact as a function of the coal elemental
composition, that influences the thermodynamic losses.
The turbine plant efficiency is computed conventionally by the method below [16] in generalized
form:
Pnett
Turb.Plant (3.3)
m j hj
where Pnett is the power measured at the generator terminal less the power consumed for
auxiliaries and j is the flows to which heat is added from external sources. The above method was
demonstrated by Geete and Khandwawala [28] which had been applied to a 120 MWe thermal
power generating unit. They used the method to study the impact on heat rate by varying the
main steam (throttle) temperature. Similar work was carried out by Rout et al. [29] where the
output power was also studied. Karakurt and Gunes [30] used this methodology to investigate the
turbine performance relative to partial loads.
The specific efficiency of a turbine cylinder is computed by the “Enthalpy Drop” method:
hin hOut
Turb.Cylinder (3.4)
hin hIsentropic @ POut
where hIsentropic @POut is isentropic enthalpy (or enthalpy of steam at the turbine outlet pressure and
inlet entropy). The word cylinder implies all turbine stages including the inlet valves.
Turbine plant losses or the indirect method are detailed in Appendix A.2. The quantification of
losses are derived from the heat rate correction factors associated with parameter deviations
from design. These curves are typically supplied by the plant designers. GE Power Generation [31]
presented examples of typical heat rate correction curves which are aligned with the requirements
of the ASMEs performance test code [32]. There are various turbine process modelling tools that
can be used to generate the heat rate correction curves; Akpan and Fuls [33] recently (2020)
demonstrated a methodology for developing and validating such models and went on to develop a
generalized means of predicting the turbine cycle heat rate as a function of load. The validation
11
Chapter 3. Literature review
included a comparison to actual performance data from 11 South African coal-fired power plants
against models developed with the ETAPro® -Virtual Plant software.
Cycle losses
Works power loss is typically expressed as a percentage of electrical energy used for internal
operation in the power plant to the electrical energy that is supplied to the national grid [34],[35].
Naturally, electricity will be consumed by components in the power generation cycle i.e. motors,
heating elements, controllers, etc. Therefore, this loss cannot be avoided but it is important to
quantify and compare to a baseline, to be able to detect plant performance abnormalities. The
measurement is done at strategic locations i.e. unit transformers, station transformers, station
electrical boards and unitized electrical boards. Some online performance tools such as EtaPro®
can calculate the power consumption by using the current transducer readings for each motor
installed in the power plant. Whilst this method is very useful for diagnostics, the uncertainty is
considered to be too large for energy accounting purposes and not all components are measured.
Cycle Make-up water losses are usually quantified by measuring the top-up that is required to
maintain the deaerator or condenser levels and is expressed as a percentage of the total steam
raised. Ideally, the steam-condensate-feed-water system is a closed loop, however practically it is
not the case, as losses can be experienced from passing drain/blowdown valves across the cycle,
boiler tube and pipe leaks, venting, pump gland leakage, etc. Generally, the boiler and turbine
plant manufacturers estimate an acceptable loss relative to the MCR live/throttle steam flow.
Eskom targets these losses to be between 0.8 to 1%. The heat efflux through these losses is
attempted to be quantified through simple thermodynamics which employs various assumptions
(see Appendix A.3.1 for details on a methodology used in industry). A study conducted by Sewlall
[36] in 2019 indicated that: for purpose of water accounting in Eskom, it is assumed that 50% of
the total make-up is evaporated and the balance is recovered as a liquid into the station drains. It
is stated that actual plant data is required to improve this estimate of a typical split between
losses at steam and feedwater conditions. There are various texts [37],[38],[39],[40] involving
power plant water balances, energy conservation and cycle isolation, that mention feedwater
make-up losses, but omit detail in localized quantification and costing. However, these texts do
suggest that make-up loss targets could be as low as 0.5%. A study by Kaushik and Khanduja [41]
was carried out on a combined cycle thermal plant in 2007. A great effort was made to quantify
the contributions to demineralized water make-up using the Six Sigma DMAIC methodology. It was
assumed that all of the make-up water supplied is due to losses at main steam conditions.
12
Chapter 3. Literature review
STEP was developed by the Central Electricity Generating Board (CEGB) in the U.K in 1966. In 1970
STEP was adopted by Eskom and over the years been adapted based on operational experience
gained from plants within their fleet [42]. The STEP program baselined the power plant
performance as per the acceptance test data acquired during the initial commissioning of each
type of unit design. The acceptance tests were based on the boiler performance standards [5],[43]
and the turbine performance standard [6]. The current version of STEP is prescribed in an internal
standard [34] and has been implemented to run on a centralized application server in 2015 (the
STEP model is computed using the application software - ETAPro®). A superseded manual [44],
also contains a detailed calculation methodology on how the calculations were previously
performed which give some history in the development.
In general, heat rate targets for acceptance tests are produced by applying correction factors
deduced by design sensitivity analysis to account for externally imposed conditions that differ
from design parameters namely: load factors, ambient temperature, ash in coal, H2 and moisture
in fuel feedstock, power factor, turbine backpressure associated with ambient temperature, etc.
The target is then compared to the actual performance test results. The STEP model differs by
applying these correction factors when the actual condition deviates from the parameters
established during acceptance testing and compare to the actual performance. In South Africa,
most of the coal-fired plants employed the British and IEC standards for acceptance testing.
The resolution of the STEP program input is one month (monthly average operating parameters
are inputted to the model). The typical outputs of STEP include targets, actuals, SF (STEP Factor)
and cost impact of losses refected in Table 3-2.
Table 3-2: STEP loss categories generated from [33]
Exergy analysis considers the conditions of surroundings to determine the quality of energy
available, thereby giving a more realistic measure of effectiveness. It only considers the useful
portion of energy that is to be transformed as a maximum base for effectiveness analysis. The SF
approach achieves this by calculating the deviation in thermal performance from the ideal case
(maximum base), which essentially focuses on what is within the utility’s control. The SF method
goes further to consider the impact of other externalities e.g. the grid-induced power factors and
13
Chapter 3. Literature review
load factor. Refer to Appendix B for a detailed calculation methodology in the form of sample
calculations or section 4.1 for a summarized calculation flow in the form of a diagram.
Uncertainty analysis
There are two main approaches to uncertainty propagation, namely the derivative approach which
is also known as the Law of error propagation [44] and the probabilistic approach [52]. Both these
approaches have various numerical methods for their implementation. Whilst there is a multitude
of approaches and variants of these methods, this study will be limited to some of the more
popular methods. General statistics and probability principles are explained in more detail in
section 4.3.2.
Uncertainty indication in power plant thermal performance evaluation has been included in the
performance standards in recent revisions and has also been included as a quality measure for
acceptance testing contracting. Typical turbine efficiency uncertainty for turbine acceptance
should be within 0.6 -0.9% [16], the typical uncertainty for steam generators that is coal-fired is
between 0.4% and 0.8% [17] and the maximum acceptable for the cycle is 3.0% using the direct
method [18]. The performance standards as per previous references prescribe a method for
uncertainty propagation as per the Laws of Error Propagation. Most texts on error propagation
make some reference to the GUM- Guide to the expression of uncertainty in measurement by ISO
[45], which demonstrate these laws by the equations below (derived from the 1st order Taylor
expansion of a function. The laws are synonymous with other standard publishers such as VDI[46]
and ASME[47]. BSI has also adopted the GUM which is described by the equations below:
2
R
L
uR .uxi (3.5)
i 1 xi x x
i
K
uxi u
k 1
k
2
(3.7)
The uncertainties are combined by the Root Sum Square (RSS) method as per the equation (3.7),
14
Chapter 3. Literature review
where:
R - result
uR - propagated uncertainty to the result of a function at the mean of each input variable
Sequential Perturbation is a controlled numerical method that gives the same result as the
equation (3.5) as demonstrated by Figliola and Beasley [48]. The method circumvents the need for
carrying out the first-order differentiation of complex functions. SP is ideal for smaller amounts of
input variables and is relatively computationally inexpensive. This method had already been
employed by Moffat [49] in 1988 and demonstrated by Mantheufel [50] in 2013 for thermal fluid
applications. Sequential Perturbation is further detailed in section 4.3.1. There are variations in
sequential perturbation such as the Sigma Point methods, where the perturbations for each
variable are weighted as a function of its probability density function [51].
Monte Carlo
Monte Carlo simulation (MCS) is a probabilistic numerical method where the uncertainty of each
variable in a function is randomly varied as a function of its probability density function. MCS was
experimented with during the 1930s and developed in the late 1940s for use in nuclear weapons
projects [52]. Monte Carlo simulation for uncertainty analysis is currently used in a broad
spectrum of applications i.e. finance, engineering, physical science, supply chain, risk
management, applied statistics, computational biology, etc.
The MCS method is used in complex functions with a significant multitude of the input variables
but can be computationally expensive as the iterations could run into the order of 10 4 to 106
before the distribution of the result converges to the specified standard deviation [48]. Padulo et
al. [51] have deemed this method as impractical for robust engineering design due to the high
number of iterations required for numerical convergence to be reached (see also Figure 3-6:
Demonstration of Monte Carlo convergence as a function of the number of iterations [55]).
15
Chapter 3. Literature review
MCS is the most commonly used method due to its flexibility, minimal limitations and ease of
scripting. There are variations in the employment of the method (i.e. Sequential Monte Carlo,
Quasi-Monte Carlo, Markov Chain Monte Carlo) to reduce the computational expensive by the
improved sampling of the input variables [53]. The method has a reasonable comparison with the
GUM [45] as proven by Papadopoulos and Yeung [54] with an average deviation of 0.03% and
maximum sample deviation of 0.8% shown in their study.
Figure 3-5 demonstrates the application of Monte Carlo simulation where x' is the true value of
any input variable which is estimated to be x and R' is the true value of any output variable.
Monte Carlo simulations were recently applied (2017) by Keshavarzian in reliability analysis for
cyclic fatigue [55]. Figure 3-6 is an example of a convergence graph for a bolt hole damage
parameter demonstrated in this study which further demonstrates the computational expense of
the method.
The MCS is commonly used as a benchmark in various comparative uncertainty studies. There are
multitudes of numerical and probabilistic methods with their variations that are lessor used in the
research work involving uncertainty propagation. These include Gaussian quadrature [56], method
of moments [51], sigma point [57], polynomial chaos expansion and probabilistic collocation
method [51],[58],[59],[60],[61],[62],[60],[63],[64]. Refer to Appendix A.4 for more detail on these
techniques.
Input variables are randomly varied iteratively within this range to produce a results data
set. The iteration continues until estimated result or when the result converges within a
specified tolerance, Result niterations tolerance . In many cases the variance, 2 is used
instead.
Figure 3-5: Illustration of Monte Carlo randomized iterations for Gaussian distributed inputs and outputs - adapted
from [48]
16
Chapter 3. Literature review
Figure 3-6: Demonstration of Monte Carlo convergence as a function of the number of iterations [55]
17
Chapter 4. Methodology
4. Methodology
A 6 x 600MWe wet-cooled power plant situated in Mpumalanga-South Africa, was modelled using
the STEP methodology. The power plant was selected based on its location, availability of process
data, and support of site personnel. See Table 4-1 for technical description.
Table 4-1: Case study - power plant description
It is important to reiterate some of the concepts and terminology that is used in STEP to
understand the findings and results of the current study. Thermal performance can be
measured/calculated using two methods. The first being: the “Direct Method” also known as the
“Input-Output Method”. Here the thermal efficiency of a system is determined by only quantifying
the energy flowing into a system and the desired energy output. So the conventional rule applies:
EOutput
Direct (4.1)
EInput
In the case of a power plant, the desired output is the electrical energy sent out to the grid, the
input energy would be the chemical energy of the fuel. The second approach is the “Indirect
Method” also known as the “Energy Balance Method”. Here the thermal efficiency of a system is
determined by quantifying energy losses as a percentage of the total energy input. The principle
employed is that the energy output must be equal to the input energy minus all of the losses.
18
Chapter 4. Methodology
Ideally, both methods should give the same value; however, a deviation can be expected due to
the uncertainty of the measurements used in both approaches.
From Figure 4-1 it can be observed that STEP intends to normalize thermal performance against
the target efficiency, so the STEP Factor (SF) is the percentage of the target efficiency achieved.
The STEP Factor can be viewed as a thermal effectiveness metric. The STEP Factor losses are also
relative to the target, so the ∑STEP Factor losses and the indirect STEP Factor must add up to
100%. The unaccounted STEP Factor losses will then be the difference between the direct STEP
Factor and the indirect STEP Factor. The mathematical expressions can be found below:
Direct
SFDirect 100
Target (4.3)
N
SFIndirect 100 - Loss.SFj (4.5)
j 1
where j is the individual losses i.e. Carbon in Refuse, Dry Flue Gas, Hydrogen & Moisture,
Backpressure, etc.
Figure 4-2: STEP calculation architecture, illustrates the basic architecture of STEP, where the
calculations are categorized into four sections namely the boiler, turbine, cycle and station
sections. The outcomes of each section are listed in Figure 4-2. Figure 4-3, Figure 4-4 and Figure
4-5 show an overview of the inner workings of the STEP calculation methodology. The detailed
STEP calculations are provided in Appendix B. The station section of the calculation as depicted in
the architecture diagram (Figure 4-2), are merely the aggregating of the calculations performed at
the unit level to acquire station results.
19
Chapter 4. Methodology
21
Chapter 4. Methodology
22
Chapter 4. Methodology
`
Figure 4-5: STEP cycle calculation sequence
23
Chapter 4. Methodology
The model uncertainty is appreciated by reviewing the thermal losses computed in STEP against its
latest version of its referenced standards [6],[15]. In some cases, other standards are explored
where there are significant conflicts. Sample calculations are performed for losses that are
omitted in the STEP program, to appreciate the magnitude of such model omissions. The model
uncertainty would then be relative to the adopted set of standards as used in the performance
baseline testing [65]. The losses that are reviewed include Carbon in Refuse, Dry Flue Gas, Carbon
Monoxide, Make-up Water, Radiation, Turbine Deterioration, and Hydrogen and Fuel Moisture.
The turbine plant losses are mostly a function of parameter sensitivity studies performed on
thermodynamic modelling packages. (Refer to Appendix C for calculation methodology and results
of the sample calculations). The results are discussed in Section 5.1.
25
Chapter 4. Methodology
kg 60s 1Gg
See point 2 in Figure 4-8, mFW .1 min mFW .avg
s 1 106 kg
A significant amount of the STEP input parameters are not directly measured and had to be
derived. This is particularly in the case of component running hours, where time is accumulated by
the summation of the time step where the motor current signals are filtered to be above the
26
Chapter 4. Methodology
assigned off-load drift tolerance. In the very same manner power (MW) is converted to energy
totals (GWh) for electric power, e.g.:
kg 1 min
See point 1 in Figure 4-8, RTBoil . for 1 min If ( mMain _ Steam 20 , ,0 )
s 60 min/ hour
STEP has two types of input data, namely average input parameters and cumulative input
parameters. The STEP computer model internally segments the data into specified chunk sizes. For
each segment analysed, the average input parameters are weighted by the electrical units
generated, e.g.:
NSegment _ size
i 1
PowGeneratedi
For cumulative input parameters, the entries are summed and extrapolated for a month as the
STEP program is designed for monthly inputs, e.g.:
NSegment _ size
44640
See range 3 on Figure 4-8 : RTBoil .segment i 1
RTBoil .1 mini
NSegment _ size
The average input parameters include temperature, pressure, the carbon in refuse (CIR), and
specific mass flow rates. The data processing is further demonstrated in Section 4.3.5.
In certain cases, data had to be up-scaled to a minute resolution i.e. coal flow rates were
discretized to a minute resolution by calibrating the mill feeder mass flow signals to the summed
monthly conveyor belt mass meter indications. Although some unquantifiable uncertainties would
be introduced as feeders degrade over time and mill configurations change within the month, this
was thought to be relatively insignificant and necessary to compare the direct and indirect
efficiency computation.
Figure 4-8 is an example of the CSV file produced from the processed signals. This file is read in as
input data to the STEP model. The data file had consisted of 112 tags per unit x 44640 temporal
entries.
27
Chapter 4. Methodology
R0 f x1 x2 ,, xL (4.6)
Ri Ri R0 (4.9)
Ri Ri R0 (4.10)
Ri Ri R
Ri ux i (4.11)
2 xi xi xi
2
L R
uR i uxi or uR RSS( Ri ) (4.12)
i 1 xi x x
i
The above method is detailed by Fiogiola and Beasly [48]. The significance or impact of each
variable relative to the total uncertainty can be derived as follows:
2
R
i uxi
xi x x
SignificanceUi i 100%
2
(4.13)
L
Ri
uxi
i 1 xi x x
i
or
uRi 2
SignificanceUi 100% (4.14)
uR2
where:
R0 -evaluation of the function with the inputs being the mean of each variable
Ri -is the result of the function where the absolute uncertainty for each variable is added to the
mean sequentially
Ri - is the result of the function where the absolute uncertainty for each variable is subtracted
from its mean sequentially
29
Chapter 4. Methodology
uR - Propagated combined uncertainty to the result of a function at the mean of each input
variable
ui - Propagated individual uncertainty to the result of a function at the mean of each input variable
Figure 4-9 and Figure 4-10 demonstrate the difference between random and systematic errors
where the systematic error is fixed in time which is a result of some static influence such as
measurement equipment calibration. On the other hand random errors change due to a temporal
influence on repeatability. An example of where the random error could occur is human
subjectivity when a measure resolution is too low, variations in operating and environmental
conditions.
30
Chapter 4. Methodology
For repeated measurements, the calculated statistical parameters are given below [66]:
1 N
x xi
N i 1
(4.15)
where:
N = number of measurements
1 N
Sx ( xi x )2
N 1 i 1
(4.16)
The standard deviation of means or standard error for a sample is given by:
Sx
Sx (4.17)
N
31
Chapter 4. Methodology
where:
P% = probability percentage
In the case of multiple, independent and similar measurements points to acquire the same
measurand such as in the case of two thermocouples measuring the same parameter, the
combined uncertainty is given by [47]:
ux
uc (4.19)
NMP
where:
The above equation is derived from the equation (4.17) where the numerator remains unchanged
for additional measurements but the denominator becomes N NMP .
32
Chapter 4. Methodology
assumed that all STEP inputs are non-correlated therefore the covariance had not been analysed
in this study.
The uncertainty model has been limited to the first layer or primary uncertainty propagation,
meaning that a derived variable that may have additional uncertainties from the method of
derivation is omitted in the propagation to the result. A typical example to demonstrate this point
is that, in thermodynamics, the enthalpy is looked up from steam tables using steam pressure and
temperature. The uncertainty in the steam temperature and pressure measurement may be
considered as primary uncertainties. The uncertainty associated with the development of the
steam tables can be considered as secondary uncertainty and is a function of the temperature and
pressure. From literature [68], uncertainty estimates are provided for steam tables, however, it
would require significant effort in coding and introduce additional computational expense. The
processing of the 2nd tier of calculations is of limited value to the objectives of this study. The
second tier would be a consideration for the analysis using STEP models specific to dry cooled
sliding pressure power plants as Eskom employs the direct method in the turbine performance
analysis due to the thermal performance being more sensitive to the load factor and ambient
conditions. The model used in the case study was that of a wet-cooled static pressure power plant
hence did not require any look-ups from steam tables.
The STEP program utilizes coefficients for polynomial performance curves derived from regression
fitting of the acceptance test data. Seeing that these tests were only performed once (not
repeated), there are no estimates in the uncertainty of this data. Similarly, all other parameters
derived from single plant tests have no uncertainty estimates and therefore could not be modelled
at this stage of the study.
For the current study, all parallel or series measurements used in the variable averaging are
assumed to be measuring a homogeneous stream i.e. the uncertainty pertaining to spatial non-
uniformity of the measurement is ignored. Even though in some cases stratification in flue gas
ducting could cause large deviations between points of measurement and consequentially
introduce significant uncertainty of the measured temperature, more detailed practical studies are
required to estimate the impact of these cases which may be very specific to the physical layout of
the plant. The spatial uncertainty can be easily incorporated into the uncertainty model for future
work.
34
Chapter 4. Methodology
interval, would require significant computational resources, seeing as the STEP model would have
to be run ≈ 1.6 M times.
Due to the significant number of calculated variables in STEP (approx. 1700) and the operation
sequence required in the processing of the uncertainties, it had been anticipated that significant
computational processing would be required, especially in the handling of large data sets. This had
necessitated that the modelling be moved to a platform more capable for large data analytics.
Python® with the Pandas library was chosen due to availability (open source), online
support/training, and the experience and recommendation of fellow scholars, academics and
peers in the industry.
35
Chapter 4. Methodology
36
Chapter 4. Methodology
Step 2: The base input variables are read in from a CSV file to the input data frame in the STEP
computer program. The CSV file is generated from an MS Excel workbook where data is manually
copied in from the EtaPro database client. The data is thereafter automatically processed for input
to the developed STEP computer program so that various monthly composite datasets can be
easily imported to the model as per Figure 4-13.
Step 3: The STEP module is run and the results are exported for verification (see also Appendix G).
Figure 4-14 is a truncated view of the calculated variables. These values had been compared with
the MathCAD calculation sheet mentioned in section 4.1 to verify the model and have proven to
be extremely useful in eradicating errors such as unit conversions and code debugging e.g. divide
by zeros or empty entries and syntax errors for the STEP module of the program. Refer to
Appendix E for the description of the calculated variables.
Step 4: The uncertainty model is run with only the systematic uncertainties read in. The results are
exported to an MS Excel file (refer to Figure 4-15).
Step 5: The plant operational data on a 1-minute resolution is read into a data frame from a CSV
file.
Step 6: Each segment/chunk is processed to acquire the average or sum of the variables (refer to
Figure 4-16). The standard deviation for each segment and each variable is computed to
determine the temporal uncertainty at a 95% confidence interval. The associated uncertainty of
each input variable (rows) to the calculated variable (columns) is reported per segment run. The
table as shown in Figure 4-15 is produced for each segment run. The overall impact of each input
variable on a calculated variable is the weighted average value of all segments by the USO.
Step 7: The temporal uncertainty for each segment is combined with the systematic uncertainty as
shown in Figure 4-12.
Step 8: Recall equations (4.6) to (4.12). The δRi for each calculated variable is exported for each
segment run. The RSS of the δRi is the combined impact of all input uncertainties per calculated
variable. Each row entry in Figure 4-17 represents the results of a segment run. The overall
uncertainty of each calculated variable is the weighted average of the RSS values by the USO for all
segment runs.
Step 9: The results are fed into post-processing tools to generate visuals, see section 5.
37
Chapter 4. Methodology
Unit(Cycle) Number
Input Variable Station 1 2 3 4 5 6 Unit Step
of Code
measure
AH_LH_Gas_Out_T 0.000 113.824 113.824 129.384 129.384 125.661 125.661 °C IDB001
AH_RH_Gas_Out_T 0.000 115.843 115.843 129.468 129.468 126.529 126.529 °C IDB002
FD_LH_AIR_In_T 0.000 29.303 29.303 32.741 32.741 29.455 29.455 °C IDB004
FD_RH_AIR_In_T 0.000 31.447 31.447 30.268 30.268 31.544 31.544 °C IDB005
AH_LH_Gas_In_O2_x 0.000 3.677 3.677 3.712 3.712 3.892 3.892 % IDB007
AH_RH_Gas_In_O2_x 0.000 3.623 3.623 3.350 3.350 4.169 4.169 % IDB008
Boil_Run_hrs 0.000 744.000 744.000 627.800 627.800 727.970 727.970 h IDB010
FW_Tot_Mass 0.000 1 144.900 1 144.900 1 003.250 1 003.250 864.360 864.360 Gg IDB011
BD_Tot_Mass 0.000 0.000 0.000 0.000 0.000 0.000 0.000 t IDB012
AH_LH_Gas_Out_O2_x 0.000 5.677 5.677 5.712 5.712 5.892 5.892 % IDB013
AH_RH_Gas_Out_O2_x 0.000 5.623 5.623 5.350 5.350 6.169 6.169 % IDB014
Boil_Starts_0to7hrs 0.000 0.000 0.000 0.000 0.000 0.000 0.000 IDB022
Boil_Starts_7to15hrs 0.000 0.000 0.000 0.000 0.000 0.000 0.000 IDB023
Boil_Starts_15to24hrs 0.000 0.000 0.000 1.000 1.000 1.000 1.000 IDB024
Boil_Starts_24to168hrs 0.000 0.000 0.000 1.000 1.000 0.000 0.000 IDB025
Boil_DownTime_0to7hrs 0.000 0.000 0.000 0.000 0.000 0.000 0.000 h IDB026
Boil_DownTime_7to15hrs 0.000 0.000 0.000 19.450 19.450 0.000 0.000 h IDB027
Boil_DownTime_15to24hrs 0.000 0.000 0.000 0.000 0.000 18.220 18.220 h IDB028
Boil_DownTime_24to168hrs 0.000 0.000 0.000 96.750 96.750 0.000 0.000 h IDB029
HotSby_Time 0.000 0.000 0.000 0.000 0.000 0.000 0.000 h IDB030
Boil_ColdStarts 0.000 0.000 0.000 0.000 0.000 0.000 0.000 IDB031
Mill_Reject_Mass 0.000 0.000 0.000 0.000 0.000 0.000 0.000 ton IDB070
Mill_Reject_CV 0.000 15.000 15.000 15.000 15.000 15.000 15.000 MJ/kg IDB071
AH_Gas_In_CIR 0.000 3.043 3.043 3.105 3.105 3.793 3.793 % IDB076
CoarseAsh_CIR 0.000 0.761 0.761 0.777 0.777 0.947 0.947 % IDB077
MILL_A_Run_Hrs 0.000 641.830 641.830 573.330 573.330 556.070 556.070 Hrs IDB091
MILL_B_Run_Hrs 0.000 676.270 676.270 617.390 617.390 665.890 665.890 Hrs IDB092
MILL_C_Run_Hrs 0.000 289.170 289.170 442.030 442.030 357.510 357.510 Hrs IDB093
MILL_D_Run_Hrs 0.000 706.260 706.260 460.380 460.380 118.770 118.770 Hrs IDB094
MILL_E_Run_Hrs 0.000 597.400 597.400 445.860 445.860 657.570 657.570 Hrs IDB095
MILL_F_Run_Hrs 0.000 742.280 742.280 529.430 529.430 677.540 677.540 Hrs IDB096
Gen_LV_Main_J 0.000 375.157 375.157 340.861 340.861 316.510 316.510 GWh IDT012
Gen_LV_Check_J 0.000 375.157 375.157 340.861 340.861 316.510 316.510 GWh IDT013
AuxPower_Main_J 0.000 19.295 19.295 23.511 23.511 26.116 26.116 GWh IDT014
AuxPower_Check_J 0.000 19.295 19.295 23.511 23.511 26.116 26.116 GWh IDT015
Gen_AboveNER_J 0.000 0.000 0.000 0.000 0.000 0.000 0.000 GWh IDT019
Gen_AboveNER_RT 0.000 0.000 0.000 0.000 0.000 0.000 0.000 h IDT025
Gen_Reactive_J 0.000 -42.369 -42.369 -17.357 -17.357 4.281 4.281 GVARh IDT020
Gen_RT 0.000 744.000 744.000 622.060 622.060 716.040 716.040 h IDT024
AuxPower_Import_Trip_J 0.000 0.000 0.000 1 256.840 1 256.840 1 239.740 1 239.740 MWH IDT100
AuxPower_SB_J 0.000 20.470 20.470 25.820 25.820 28.680 28.680 GWh IDT089
A_EFP_RT 0.000 0.000 0.000 632.790 632.790 742.990 742.990 h IDT085
B_EFP_RT 0.000 0.000 0.000 628.420 628.420 619.870 619.870 h IDT100
C_EFP_RT 0.000 0.000 0.000 0.000 0.000 0.000 0.000 h IDT110
… 0.000 0.000 0.000 0.000 0.000 0.000 0.000
38
Chapter 4. Methodology
39
Chapter 4. Methodology
Figure 4-17: Step 8 - Example of combined uncertainty of calculated variables per segment run
41
Chapter 5. Results and discussion
42
Chapter 5. Results and discussion
CO2 and O2. Typical gas analysers measure these gases on a dry volumetric basis which suits the
calculation of the Dry Flue Gas loss. It is observed that the heat capacity of the flue gas ( cP .FG ) is
static as per STEP calculations and the BS 2885 [5]. The approach is different as per the BS EN
12952 -15 as the cP .FG is calculated based on the CO2 mass fraction and temperature of the flue
gas.
For the case demonstrated, the STEP calculation and the BS 2885 [5] yielded very similar results as
the same gas composition was used in the calculation. The loss as per STEP was calculated to be
4.797% or 0.901 MJ/kg coal (refer to Appendix C.4) versus 4.843% or 0.909 MJ/kg coal using the BS
2885 approach (refer to Appendix C.5). The difference between the two methods is that STEP
calculates the mass ratio of dry flue gas to a kg of coal-fired and BS 2885 [5] leaves it on a molar
basis. They both calculate the relative gas flows based on the CO2 concentration in the flue gas.
The principle is based on 1 mol C → 1 mol CO2. The method employed in STEP to calculate the CO2
concentration in the flue gas is not referenced but appears to be based on some empirical
relationships of the coal composition (some parameters being on a proximate analysis base).
The BS EN 12952-15 [15] calculates the mass ratios of gas products through stoichiometric
reactions of the elements within the coal, hence the ultimate analysis of the constituents is
required. The excess air is determined by the oxygen depletion method (see Appendix C.6 –
calculation (C.31)). In this case, the result is marginally different yielding a loss of 4.660% or 0.875
MJ/kg Coal (see Appendix C.6 - calculations (C.42) and (C.43)).
43
Chapter 5. Results and discussion
test codes assume that these defects are resolved before acceptance testing. These flows are
typically not measured at a power plant. The make-up water loss is one of the highest losses
experienced in South African power plants as per the STEP program and hence had been identified
for critical review.
The calculation methodology is demonstrated by calculations in Appendix C.9. The methodology
was deemed to be fundamentally satisfactory. However, STEP makes approximations of these
flows by assuming that a 3rd of the make-up water is lost at the boiler feed water conditions and
2/3rd is lost at main steam conditions (see Appendix C.9 calculation (C.54)). The approximation is
not referenced in the STEP manuals [34][42] nor could be found in the literature. For the case
evaluated the make-up loss was determined to be 2.657%. See Table 5-2 for the results of the
sensitivity study.
Table 5-2: Sensitivity analysis on the fraction of make-up water lost at main steam conditions
From the above table is it quite obvious that the fraction of make-up water lost at main steam
(MS) conditions has a significant impact on the thermal loss determination. The spread or range
would become even wider when conditions of high make-up are experienced.
From calculation (C.59) in Appendix C.9, It can be seen that demineralized water flows that are
external to the Rankine cycle are included in the hot make-up volume. It becomes difficult to
standardize these calculations done in STEP as the various plant metering configurations are
different. It is incorrect to include the water losses in the thermal loss calculations e.g. the water
supplied to the hydrogen plant for electrolysis or cooling water to the compressed air systems
cannot be considered to be lost at main steam condition neither at feed water conditions.
Another major risk to the accuracy of the make-up determination is the method to distinguish
between hot make-up and cold make-up flow especially if this is done manually. Manual methods
44
Chapter 5. Results and discussion
of recording the integrated volume of make-up may not be synchronized to the unit
synchronization and uncoupling from the grid. Hot make-up is the demineralized water top-up to
the Rankine cycle when the unit is synchronized to the electricity grid. The make-up used during
commissioning should also be discounted as the input energy to the cycle (coal & oil-fired) during
commissioning is discounted in the calculation of the running plant heat rate. Make-up flow during
cold conditions (unit offload and cooled) has negligible thermal energy value. In many cases where
power plants are equipped with modern data systems, the quantification of the make-up volume
can be determined through the integration of the instantaneous flow meter signals and can be
filtered directly by the plant data systems. In this case calculation (C.59) in Appendix C.9 may be
circumvented to a direct input.
47
Chapter 5. Results and discussion
48
Chapter 5. Results and discussion
The Table 5-3 is a truncated form of the stated table where the variables with uncertainties
greater than 5% are shown at a unit level. The results above are valuable to understand the
uncertainty of each calculated variable but it must be emphasized that even though the
uncertainty of the calculated variable may be extremely high, it may be relatively insignificant to
the final result of STEP i.e. cycle efficiency, turbine efficiency, boiler efficiency and associated STEP
Factors (% of targets achieved). The above information, however, may be vitally important for
specific business case sensitivity analysis, where an individual parameter may be of high
importance e.g. the cost of feed water temperature loss may be a significant input parameter in a
feasibility study to replace the feedwater heaters.
It is observed that the parameter uncertainty at a station level is lower than that of a unit level by
the typical factor, Nunits , where the station parameters are a mere composite of unit parameters.
This is not the case where the unit parameters are influenced by some common input parameters
e.g. coal quality parameters, common plant auxiliary power consumption, common plant
demineralized water consumption.
From the results above is already noticeable that some significant contributors to the uncertainty
of the listed variables are temperature measurement (thermocouples), make-up water flow
(orifice plates), condenser pressure transducer, coal quality parameters (total moisture) and
electrical metering. The method of flagging the items in the table by the percentage uncertainty is
very sensitive to the base run conditions, hence a more holistic and in-depth analysis was
performed on the parameters of specific interest with consideration for the absolute uncertainty
with a drill-down approach.
It is interesting to observe from Table 5-4 (highlighted in blue), there is quite a large difference
between the direct and indirect STEP Factor uncertainty i.e. 0.571% vs 2.210%. It is vastly accepted
that the indirect method should yield lower uncertainties due to the fact it is not directly
dependent on the coal flow rate measurement, which is prone to significant measurement noise.
49
Chapter 5. Results and discussion
50
Chapter 5. Results and discussion
A negative unaccounted cycle loss as indicated in the table above (In blue text) would indicate
either that the direct-method cycle efficiency is overstated or that the losses are overstated, or
both. The unaccounted SF loss (3.788%) is the difference between the direct STEP Factor and the
indirect STEP Factor, and is used as an indication of the uncertainty of either of the stated metrics.
If one combines the systematic uncertainty of both parameters (0.571% + 2.210%), it could only
justify a maximum deviation of 2.781%, which would be only 73 % of the unaccounted loss, hence
it can be deduced that other significant uncertainties affect these computations, which will be re-
examined in Section 5.5 of this document.
From Figure 5-2, the backpressure loss and final feed water loss have the highest instrument
uncertainty for the case analysed. The other loss uncertainties are significant but relatively much
lower.
1.400 0.500
Uncertainty (%-abs)
Uncertainty (%-abs)
1.200 0.450
0.400
1.000 0.350
0.800 0.300
0.250
0.600 0.200
0.400 0.150
0.100
0.200 0.050
0.000 0.000
BP_SF_L
MR_SF_L
MU_SF_L
DFG_SF_L
Radiation_L
FW_SF_L
AuxPower_SF_L
CIR_SF_L
H2_Moist_SF_L
Turb_Est_Det_L
MS_SF_T_L
ReH_SF_T_L
AuxPower_SF_L
MR_SF_L
BP_SF_L
DFG_SF_L
Radiation_L
MU_SF_L
H2_Moist_SF_L
FW_SF_L
ReH_SF_T_L
CIR_SF_L
Turb_Est_Det_L
MS_SF_T_L
51
Chapter 5. Results and discussion
The aim was to find the segment size that would yield the highest number of stable load segments
and lowest number of transition segments by a statistical method. Naturally one would expect this
to be achieved by discretizing to the highest possible resolution at which the data is available,
however, the temporal uncertainty within each segment had to be quantified with the reduction
in the sample data size i.e. the segment size. The minimum sample size of 30 minutes or 30
observations was set to conform to the principles of statistics, where the sample standard
deviation can be approximated to the population standard deviation as per equation (4.17). It is
important to note that, it is a requirement that the load remains stable for 4 hours to deem an
acceptance test to be successful, hence the baseline performance data is very specific to the unit
loads rather than the average of transient conditions [14] and therefore should only be applied to
actual stable loads rather than averages.
Each loss has a significant parameter e.g. condenser backpressure loss is a function of the LP
exhaust pressure, final feedwater temperature loss is a function of the economizer inlet
temperature, etc. These significant parameters also have some degree of variability relative to
time or resolution. If one examines Figure A- 1 in Appendix A.2.2, it can be deduced that large
deviations in either the load or the significant parameter (in this case LP-turbine condenser
pressure) from the design point will result in a significant change in the heat rate which is used to
determine the losses, especially when the deviated points are in the exponential zones of the
curves.
Figure 5-9 compares the STEP Factors when run at various resolutions. As expected, the direct
STEP Factor appears to be fairly static due to the simple calculation of the actual direct efficiency
(see Appendix B equations (B.255) & (B.256)) which is not affected by plant process parameters.
The most significant parameter: coal CV, is weighted by the coal mass within and across all
segments. The coal mass and USO are summative parameters hence does not vary with the time
resolution analysis. The target efficiency is derived through the application of correction factors,
but these are normally small adjustments to the heat rate to compensate for external conditions
and not as significant as plant deficiencies.
57
Chapter 5. Results and discussion
minimal movement of the mean for the direct SF. The indirect SF accrued an uncertainty of
0.571% abs when only considering the systematic uncertainty propagation and a combined
uncertainty of 0.617% abs at a 3-hour resolution. Here the findings suggest that the temporal
uncertainty contribution is significant and the movement of the mean is also significant when
compared to a monthly composite run. The above phenomenon is also expected as previously
explained. When zooming into the uncertainty profile as per Figure 5-10, it would suggest that
there is a limit to the resolution at which STEP should be run, as the temporal uncertainty sharply
increases from a time resolution of 3-hour. The phenomenon is due to the reduction of the sample
Sx
size for each segment which makes the temporal uncertainty higher, recall Sx equation
N
(4.17).
One of the objectives of STEP is to accurately quantify the losses at a unit level so that
maintenance work or defect resolution can be prioritized especially in a capital-constrained
environment. Figure 5-11 reveals that the final feed water temperature loss could be perceived to
be 2.378% when evaluated at a month resolution, however, increases to 3.188 % when evaluated
by a 3-hour segment run which is significant. The turbine back-pressure loss moved from 3.511%
to 3.164%. The auxiliary power consumption is baselined with the boiler steam feed pumps (BFPTs
– pumps driven by a steam turbine) in service. When the BFPTs are unavailable the energy
consumed for the operations of the electric motor driven boiler feed pumps (EFPs) are estimated
by the power vs load curve as indicated in equations (B.106) and (B.107) in Appendix B. The target
auxiliary power is adjusted by the estimated power consumption, which in principle gives a zero
nett effect on the STEP Factor loss. For the data used in this study, it is not the case, which
indicates that there is a possible deviation with the power vs load curve (i.e. it overestimates the
power consumption of the EFPs).
Unit 5 results indicate that the unit suffers from the same deficiencies as Unit 4 however the
magnitude is much higher. The weighted average final feed water temperature deviation from the
design is 99 oC, which is typical of operating the unit without both banks of HP heaters. The
operating condition translates to a STEP Factor loss of approximately 14.8% as indicated in Figure
5-12. The uncertainty in this value is expected to be extremely high as the operating point will fall
in the extrapolated zone of Figure 5-4 with the largest distance from actual performance data.
59
Chapter 6. Conclusions and recommendations
6.2. Recommendations
63
Chapter 6. Conclusions and recommendations
The calculation of the sensible heat loss in ash that is emitted by the boiler is to be
accounted for in the STEP calculations.
The hydrogen and fuel moisture losses should be updated as per BS 2885-1974 [5] or the
sample the calculation performed in Appendix C.7.
The losses associated with partial combustion or CO production are to be expressed in
STEP.
The demineralized water loss appropriation assumption is to be reviewed through a
practical study (the assumption that a 3rd of make-up water is lost is at feed water
condition and the balance at the main steam condition). A practical study using a
calibrated instrument is to be carried out. The existing water balance model should be
configured in the future to estimate this ratio based on plant data, which then could
become a volatile input to STEP. In the case of input errors then default values being based
on some proven principle from baseline tests be used.
All empirical correlations derived from losses as a function of load factor to be re-based
lined over time. STEP baseline testing should include sensitivities at extreme operating
condition so that the polynomial regression fitting is done with a data scatter over the
entire operating range, e.g. heat rate test and modelling should be done with both banks
of HP heaters offload or with the LP turbines operated at maximum allowable
backpressure as per the operating philosophy.
Throttle losses are included in overall turbine losses as a function of load. Deviations from
expected to be identified and quantified in STEP. The mentioned loss could be beneficial in
identifying issues with final steam pressure control such as defects with emergency shut-
off valves, governor valves and strainers.
The direct unitized cycle efficiency calculation should be performed for power stations
fitted with new technology coal feeders such as the gravimetric belt feeders. The
calculation could be carried through to stations with spiral and table feeders for trending
purposes only (identify feeder calibration issues). The uncertainty in the latter would be
too high in the case of volumetric coal flows as the density of coal can vary significantly
with mineral composition, moisture content and size grading.
Coal quality is considered for Carbon in Refuse losses and Hydrogen and Moisture losses,
but, the ash impact on Dry Flue Gas loss (radiation impact) and Auxiliary Power loss are to
be further studied and incorporated into STEP.
The unitized Auxiliary Power STEP Factor losses are erroneous, based on the treatment of
off-load auxiliary power that is equally shared by all units. The unit that supplies the loop
64
Chapter 6. Conclusions and recommendations
supply (interconnected auxiliary power reticulation between units and common plant) is
not credited for its contributions to the common auxiliaries and other units.
The auxiliary power STEP Factor loss is baselined with the boiler steam feed pumps (BFPTs
– pumps driven by a steam turbine) in service, when the BFPTs are unavailable the energy
consumed for the operations of the electric motor driven boiler feed pumps (EFPs) are
estimated by the power vs load curve as indicated in equations (B.106) and (B.107) in
Appendix B. The target auxiliary power is adjusted by the estimated power consumption,
which in principle should give a zero nett effect on the STEP Factor loss. STEP does not
account for the cycle heat rate gains by running the EFPs instead of the BFPTs. The above
philosophy could have adapted due to the number of tests that would have to be done to
cover all possible configurations. It is therefore recommended that validated
thermodynamic models be used to generate the load sensitivity correlations as done in
software such as Virtual Plant or Steam Pro and be expressed as a separate loss. The target
auxiliary power should be adjusted by the measured actual EFPs electric energy
consumption rather than using a correlation to determine.
A study to determine the turbine deterioration factors should be initiated to consider the
local history of turbine cylinder efficiency test or enthalpy drop test for specific turbine
designs and sizes.
A system should be designed/configured and proved to process data to enable the running of STEP
at a higher resolution. Section 4.2.3 can be considered a pilot exercise in determining the
methodology. Future work could entail the automation and integration with existing plant data
systems.
65
Chapter 6. Conclusions and recommendations
The STEP input or segment resolution should be kept a minimum of 3-hours, even though 6 hours
would be adequate the segmenting windows would have to be aligned to separate the peaks for
off-peak data. The 3-hour segment size is the size up to overcome alignment issues and also the
next size down from the 1-hour segment size, where an increased temporal uncertainty at this
resolution is observed.
66
Chapter 6. Conclusions and recommendations
The water balance models developed should be integrated or linked to the STEP program to
ensure the improvement of the method by reasonably appropriating the losses based on the
enthalpy of the water at its point of release.
The spatial uncertainties associated with the location of the measurement points and sampling
methods were omitted from this study as practical case-specific studies would be required to
determine these uncertainties. It would be interesting to carry out a study that investigates the
temperature, oxygen content, and unburned carbon in ash by traversing the flue gas ducting at
various points.
67
Chapter 7. List of References
7. References
[1] Eskom, “Company Info Overview.” [Online]. Available:
http://www.eskom.co.za/OurCompany/CompanyInformation/Pages/Company_Information
.aspx. [Accessed: 18-Dec-2019].
[2] Department of Energy South Africa, “Integrated Resources Plan for South Africa (2018),”
2018.
[3] Central Intelligence Agency, “Country Comparision : Electricity Production,” The World Fact
Book. [Online]. Available: https://www.cia.gov/library/publications/the-world-
factbook/fields/252rank.html. [Accessed: 28-Dec-2019].
[4] Eskom, “Electricity technologies.” [Online]. Available:
http://www.eskom.co.za/AboutElectricity/ElectricityTechnologies/Pages/Electricity_Techno
logies.aspx. [Accessed: 18-Dec-2019].
[5] British Standards Institution, “Acceptance tests on stationary steam generators of the
power station type,” BS 2885, London, 1974.
[6] International Electrotechnical Commission, “Rules for steam turbine thermal acceptance
tests,” IEC 953-1, Frankfurt, 1990.
[7] International Energy Agency, “World Energy Outlook,” Paris, 2015.
[8] The World Bank, “Pricing carbon,” 2019. [Online]. Available:
https://www.worldbank.org/en/programs/pricing-carbon. [Accessed: 25-Jun-2019].
[9] Wikipedia Commons, “Typical coal thermal power station,” Wikipedia. [Online]. Available:
https://en.wikipedia.org/wiki/Thermal_power_station. [Accessed: 02-Jun-2018].
[10] A. Harvey, A. Larson, and S. Patel, “History of Power: The Evolution of the Electric
Generation Industry,” in Connected Plant Conference, 2017, no. September 1882, pp. 1–16.
[11] “Efficiency of conventional thermal electricity and heat production in Europe,” European
Environment Agency, 2018. [Online]. Available: https://www.eea.europa.eu/data-and-
maps/indicators/efficiency-of-conventional-thermal-electricity-generation-4/assessment-2.
[Accessed: 24-Jun-2019].
[12] “Global outlook on electricity generation by energy source 2015-2050,” Statista, 2019.
[Online]. Available: https://www.statista.com/statistics/238610/projected-world-electricity-
generation-by-energy-source. [Accessed: 21-Jun-2019].
[13] Y. Maharaj, “South African overall efficiency vs availability,” Eskom. 2019.
[14] The American Society of Mechanical Engineers, “History of ASME Standards.” [Online].
Available: https://www.asme.org/codes-standards/about-standards/history-of-asme-
standards.
[15] British Standards Institution, “Water-tube boilers an auxiliary installation -Acceptance
tests,” BS EN 12952-15, London, 2003.
[16] International Electrotechnical Commission, “Rules for steam turbine thermal acceptance
tests Part 0: Wide range of accuracy for various types,” IEC 60953-0/Ed1, Frankfurt, 2018.
68
Chapter 7. List of References
[17] The American Society of Mechanical Engineers, “Fired Steam Generators,” ASME PTC 4,
New York, 2008.
[18] The American Society of Mechanical Engineers, Overall Plant Performance. New York: ASME
PTC 46, 2013.
[19] The American Society of Mechanical Engineers, “Procedures for Routine Performance Test
of Steam Turbines,” ASME PTC 6S, New York, 1988.
[20] A. Rashad and A. A. Elmaihy, “Energy and Exergy Analysis of a Steam Power Plant in Egypt,”
in Aerospace Sciences and Aviation Technology, vol. 9, no. 4, p. 399.
[21] I. H. Aljundi, “Energy and exergy analysis of a steam power plant in Jordan,” Appl. Therm.
Eng., vol. 29, no. 2–3, pp. 324–328, 2009.
[22] R. Mahamud, M. M. K. Khan, M. G. Rasul, and M. G. Leinster, “Exergy Analysis and Efficiency
Improvement of a Coal Fired Thermal Power Plant in Queensland,” 2016.
[23] P. Rousseau and W. Fuls, Systems Analysis. Department of Mechanical Engineering,
University of Cape Town, 2018.
[24] L. S. Paraschiv, A. Serban, and S. Paraschiv, “Calculation of combustion air required for
burning solid fuels (coal / biomass / solid waste) and analysis of flue gas composition,”
Energy Reports, vol. 6, no. September, pp. 36–45, 2020.
[25] A. M. Lahijani and F. Kalantari, “a Review of Indirect Method for Measuring Thermal,” vol.
34, no. 1, pp. 1825–1832, 2018.
[26] A. Chirag, P. N. Mehta, and P. J. Dabhi, “Research paper on Analysis of Boiler losses to
improve Unit heat rate of coal fired thermal power plant,” Int. J. Adv. Eng. Res. Dev., vol. 1,
no. 05, pp. 1–6, 2014.
[27] R. Laubscher and P. Rousseau, “Numerical investigation on the impact of variable particle
radiation properties on the heat transfer in high ash pulverized coal boiler through co-
simulation,” Energy, vol. 195, p. 117006, 2020.
[28] A. Geete and A. I. Khandwawala, “Thermodynamic analysis of 120 MW thermal power plant
with combined effect of constant inlet pressure (124.61 bar) and different inlet
temperatures,” Case Stud. Therm. Eng., vol. 1, no. 1, pp. 17–25, 2013.
[29] I. Rout, “Thermal Analysis of Steam Turbine Power Plants,” IOSR J. Mech. Civ. Eng., vol. 7,
no. 2, pp. 28–36, 2013.
[30] A. S. Karakurt and Ü. Güneş, “Performance analysis of a steam turbine power plant at part
load conditions,” J. Therm. Eng., vol. 3, no. 2, pp. 1121–1128, 2017.
[31] GE Power Systems, “Thermal Performance Evaluation and Assessment of Steam Turbine
Units,” GER-3953, New York, 1996.
[32] The American Society of Mechanical Engineers, “Performance Test Code 6 on Steam
Turbines,” ASME PTC 6-1996, New York, 1996.
[33] P. Akpan and W. Fuls, “Methodology for Developing and Validating Representative Process
Models for Coal- Fired Power Plants,” no. October, 2020.
[34] Eskom, “Station Thermal Efficiency Performance,” 240-133560870, Johannesburg, 2018.
69
Chapter 7. List of References
[35] Eskom, “Title : Metering and Measurement Systems for Power Stations in Generation,” 240-
53459028, Johannesburg, 2018.
[36] P. Sewlall, “A methodology for implementing a power plant water balance on the online
condition monitoring software EtaPRO,” UCT, 2021.
[37] A. M. Carpenter, “Water conservation in coal-fired power plants Water conservation in coal-
fired power plants,” IEA Clean Coal Cent., no. February, pp. 1–72, 2017.
[38] Electric Power Research Institute, “Heat Rate Improvement,” TM-114073, Palo Alto, 2014.
[39] Electric Power Research Institute, “Range and applicability of heat rate improvements,” CA:
2014. 3002003457, Palo Alto, 2014.
[40] United States Department of Energy, “Power Plant Water Usage and Loss Study,” 2007.
[41] P. Kaushik and D. Khanduja, “DM make up water reduction in thermal power plants using
Six Sigma DMAIC methodology,” J. Sci. Ind. Res. (India)., vol. 67, no. 1, pp. 36–42, 2008.
[42] P. Moolman, STEP Training Material. Johannesburg, 2019.
[43] British Standards Institution, “Assessing thermal performance of boilers for steam, hot
water and high temperature heat transfer fluids,” BS 845-1, London, 1987.
[44] P. Moolman and J. Murphy, Station Thermal Efficiency Performance Manual. Johannesburg:
Eskom, 2014.
[45] International Organization for Standardization, “Uncertainty of measurements - Guide to
the expression of uncertainty in measurement,” ISO/IEC 98-3, Geneva, 2008.
[46] The Association of German Engineers, “Uncertainties of measurement during acceptance
tests on energy conversion and power plants - Fundaments,” VDI 2048 Part 1, Dusseldorf,
2000.
[47] The American Society of Mechanical Engineers, “Guidance for Evaluation of Measurement
Uncertainty in Performance Tests of Steam Turbines,” ASME PTC 6 -Report 1985, New York,
1997.
[48] R. S. Figliola and D. E. Beasley, Theory and Design for Mechanical Measurements, 5th ed.
Hoboken: John Wiley and Sons Inc., 2011.
[49] R. J. Moffat, “Describing the uncertainties in experimental results,” Exp. Therm. Fluid Sci.,
vol. 1, no. 1, pp. 3–17, 1988.
[50] R. D. Manteufel and A. Karimi, “Influence of uncertainties and assessment of significant
digits in thermodynamics,” ASEE Annu. Conf. Expo. Conf. Proc., 2013.
[51] M. Padulo, M. S. Campobasso, M. D. Guenov, M. S. Campobasso, and M. D. Guenov,
“Comparitive Analysis Of Uncertainty Propagation Methods For Robust Engineering Design,”
Int. Conf. Eng. Des., no. August, pp. 1–12, 2007.
[52] N. Metropolis, “The beginning of the Monte Carlo Method,” 1987.
[53] K. N. Hasan, R. Preece, and J. V. Milanović, “Existing approaches and trends in uncertainty
modelling and probabilistic stability analysis of power systems with renewable generation,”
Renew. Sustain. Energy Rev., vol. 101, no. December 2017, pp. 168–180, 2019.
[54] C. E. Papadopoulos and H. Yeung, “Uncertainty estimation and Monte Carlo simulation
70
Chapter 7. List of References
London, 1990.
[74] Eskom, “Fossil Fuel Firring Regulations Standard,” 240-105453648, Johannesburg, 2016.
[75] British Standards Institution, “Solid mineral fuels — Determination of gross calorific value by
the bomb calorimetric method and calculation of net calorific value,” BS ISO 1928, London,
2009.
[76] Eskom, “Coal Quantity and Quality Accounting Standard for Thermal Efficiency
Determination,” 240-87607698, Johannesburg, 2018.
[77] International Organization for Standardization, “Solid mineral fuels — Determination of
gross calorific value by the bomb calorimetric method and calculation of net calorific value,”
BS ISO 1928, London, 2009.
[78] British Standards Institution, “Tracked Changes Hard coal and coke — Mechanical sampling
Part 2 : Coal — Sampling from moving streams,” BS ISO 13909-2, 2016.
[79] South African National Standards, “Solid mineral fuels — Determination of ash content,”
SANS 131, Pretoria, 2011.
[80] South African National Standards, “Hard coal — Determination of total moisture,” SANS
589, Pretoria, 2007.
[81] South African National Standards, “Hard coal and coke — Determination of volatile matter,”
SANS 50, Pretoria, 2011.
[82] South African National Standards, “Coal — Determination of forms of sulfur,” SANS 402,
Pretoria, 2005.
[83] D. Ratlhagana and F. Lombard, “Abrasive and Hardgrove Index : Realistic Boiler Chemical
Analysis,” Eskom, 2013.
[84] South African National Standards, “Hard coal — Determination of Hardgrove grindability
index,” SANS 5074, Pretoria, 1994.
[85] Eskom, “Title : Coal Quality Specifications for ESKOM Power Stations at Staithe / Silo Inlet
rev 1,” 240-71273834, Johannesburg, 2019.
[86] The American Society for Testing and Materials, “Standard Test Method for Heat of
Combustion of Liquid Hydrocarbon Fuels by Bomb Calorimeter,” ASTM D240 -19, West
Conshohocken, 2019.
72
Appendix A. Formulas from literature
Where:
Turbine cylinder efficiency tests are performed on the HP and IP turbine sections by the enthalpy
drop method to assess the actual performance or condition of the turbine cylinders. The stated
method is preferred as per the IEC [16] to determine the turbine loss due to ageing, however, a
theoretical method to estimate the target turbine efficiency degradation as a function of age for
the cylinder efficiencies is given by:
150
DetTurbine k f (A.13)
P
Where:
Cylinder tests are typically conducted during initial commissioning and thereafter after major plant
outages therefore In STEP the actual turbine deterioration is set equal to the target for monthly
performance evaluation and baselined after each cylinder efficiency test.
75
Appendix A. Formulas from literature
77
Appendix A. Formulas from literature
The generalized expression for computing the mean and variance of a function subjected to input
variability can be found below [51],[56]:
y E f ( x ) f ( x )p ( x )dx
x (A.17)
f ( x ) E f ( x ) p ( x )dx
2
2 x (A.18)
N N N
yGQ Wi1 Wi2 ...Win f ( xi1 ,i1 ,...,in ) (A.19)
i 1
i1 1 2 in 1
N N N
y2 Wi Wi ...Wi f ( xi ,i ,...,i ) yGQ (A.20)
GQ 1 2 n 1 1 n
i1 1 i2 1 in 1
1 n 2 f 2 1 n 3 f 3 1 n 4 f 4
yMM f ( x )
2 p1 x p2
xp 3 p xp 4
6 p1 x p 24 p1 x p
p xp (A.21)
M1 M2 M3 M4
2
n f n 2
f f n n
3 f f 2 2
p xp 2 x p xp
2
2
3
2
x xp xq
p 1 x p p 1 x p p 1 q 1 x p xq
yMM
p qp
q
2 2
(A.21)
n 2 f
n 2 2 1 n 3 f f 1 n 2 f
p 1 xp
1
xp xq 3 p x4p 2 4
79
Appendix A. Formulas from literature
The above equations apply to independent input variables and the Taylor series expansion to the
4th order. M = moments. MM used in uncertainty propagation is relatively inaccurate for inputs
with large variation if the second and higher-order derivatives are eliminated. MM has been
significantly used in Robust Design Optimization in the aircraft design [51]
SP methods are synonymous with the sequential perturbation of uncertainties described in section
4.3.1, however, a weight is applied to each variable perturbed ( Wp ) as a function of its
distribution. The SP method is further categorized as Unscented Transformation (UT) and Divided
Difference Filter (DDF), where UT only considers the first-order polynomial approximation and DDF
creates a second-order polynomial approximation. A significant advantage of this method is the
ability to propagate uncertainties through discontinuous functions and relatively lower
computational expense (2n +1), n is the number of variables with uncertainties. The DDF has a
higher accuracy when compared with UT, however increases the computational expense. SP has
been recently demonstrated by Bhonsale et al. [57] to be the most favourable method to be
employed to breakage population models in the pharmaceutical design process. The comparison
with MCS yielded a good correlation for significantly fewer function evaluations.
The SP method is described by the equations below [51] :
n
yUT W0 f ( x0 ) Wp f ( x p ) f ( x p ) (A.22)
p 1
n
2 2
y2 W0 f ( x ) yUT Wp f ( x ) yUT f ( x ) yUT
2
(A.23)
UT 0
p1 p
p
1 n 2 2
2
Wp f ( x p ) f ( x p 2
) ( Wp 2Wp f ( x p ) f ( x p ) 2 f ( x0 ) (A.24)
2 p1
yDDF
where:
x p - positive perturbation of each variable by its uncertainty,
80
Appendix A. Formulas from literature
PCE is a probabilistic numeral method that was first introduced by mathematician Robert Wiener
in 1938. It has since been improved by various authors such as Martin & Cameron, Ghanem &
Spanos , Bhabuska,Schwab [38],[58]. There have been various comparative studies to determine
the suitability of PCE for various applications; Persio et al. tested PCE for interest rate models
[58],Yang et al. [71] and Fenfen et al. [60] for engineering design.
There is very little use of PCE in the application of this method possibly due to its high
computational expense especially with a large number of input variables, mathematical
complexity and the requirement to express a model as a single function. Some examples of
applied uncertainty analysis include software performance estimation by Aleti et al. [61] and
robust design of Integrated Circuits (ICs) by Kaintura et al. [62]. PCE makes use of appropriate
orthogonal polynomials (Hermite, Legendre, Jacobi, Laguerre, and General Laguerre) relative to
probability density functions (Gaussion, Uniform, Beta, Exponential, and Gamma) also known as
the Askey Scheme to estimate a function. The properties of orthogonality are used to simplify the
calculations of the statistical moments(mean, variance, kurtosis and skewness) of the outputs
relative to input distribution properties, see [51],[58],[59],[60],[61],[60],[63] for mathematical
detail.
PCM is one of the non-intrusive methods in solving the coefficients of the orthogonal polynomial
in the Estimate Function. This entails selecting collocation points similar to the GQ integration
technique. These points are generally the roots of the next higher-order polynomials in the Askey
Scheme [64].
81
Appendix B. STEP calculations
TAir.RH.FD.In TAir.LH.FD.In
i i
TAir.FD.In
i 2 (B.2)
xO2.RH.Eco.Out xO2.LH.Eco.Out
i i
xO2.Eco.Out
i 2 (B.3)
xO2.LH.AH.Out xO2.LH.Eco.Out
i i
% % (B.4)
LeakAH.LH
i xO2.LH.AH.Out
i
21
%
xO2.RH.AH.Out xO2.RH.Eco.Out
i i
% % (B.5)
LeakAH.RH
i xO2.RH.AH.Out
i
21
%
82
Appendix B. STEP calculations
QStart.Cold.1
i
kQ.OffLoad
i GWh
NStarts.0to7hrs
QStart.Cold.1 1 e N
i
Starts.0to7hrs otherwise
i i
QStart.Cold.1
i
kQ.OffLoad
i GWh
NStarts.7to15hrs
QStart.Cold.1 1 e i N
Starts.7to15hrs otherwise
i i
QStart.Cold.1
i
kQ.OffLoad
i GWh
NStarts.15to24hrs
QStart.Cold.1 1 e i N
Starts.15to24hrs otherwise
i i
QStart.Cold.1
i
kQ.OffLoad
i GWh
NStarts.24to168hrs
QStart.Cold.1 1 e N
i
Starts.24to168hrs otherwise
i i
tSby.Hot kQ.OffLoad 1
QSby.Hot
i
QStart.Cold.1 1 e
i
hr
i i (B.25)
85
Appendix B. STEP calculations
6
LCIR.Act.Stn LCIR.Act FracTot.Stm
i i (B.59)
i 1
6
LDFG.Targ.Stn LDFG.Targ FracTot.Stm
i i (B.61)
i 1
6
LDFG.Act.Stn LDFG.Act FracTot.Stm
i i (B.62)
i 1
6
LH2_Moist.Targ.Stn LH2_Moist.Targ FracTot.Stm
i i (B.64)
i 1
6
LH2_Moist.Act.Stn LH2_Moist.Act FracTot.Stm
i i (B.65)
i 1
6
LRad.Stn LRad FracTot.Stm
i i (B.67)
i 1
6
LMR.Act.Stn LMR.Act FracTot.Stm
i i (B.68)
i 1
90
Appendix B. STEP calculations
6 (B.72)
QOffLoad.Stn QOffLoad.Boil
i
i 1
CFLF.Boil mStm.Boil
i i (B.73)
i 1
CFLF.Boil.Stn
mStm.Stn
CFFuel.Boil mStm.Boil
i i (B.74)
i 1
CFFuel.Boil.Stn
mStm.Stn
6 (B.75)
xCIR.Stn xCIR FracTot.Stm
i i
i 1
6
xO2.AH.Gas.In.Stn xO2.Eco.Out FracTot.Stm
i i (B.76)
i 1
6
LeakAH.RH.Stn LeakAH.RH FracTot.Stm
i i (B.77)
i 1
6
LeakAH.LH.Stn LeakAH.LH FracTot.Stm
i i (B.78)
i 1
JGen.LV.Main JGen.LV.Check
i i
JGen.LV
i 2 (B.79)
91
Appendix B. STEP calculations
JAuxPower.Main JAuxPower.Check
i i
JAuxPower.UB
i 2 (B.80)
i i
i
JGen.HV JGen.LV 1 BinaryMP JAuxPower.UB GT JAuxPower.UB
i
(B.81)
6
JAuxPower.Stn JAuxPower.UB JImp.Stn
i (B.84)
i 1
JGen.HV
i
FracGen
i JGen.HV.Stn (B.87)
92
Appendix B. STEP calculations
tRT.Gen tGen.>NER
i i
QAT.NLtoNER QCons_hr.NLtoNER
i i hr hr (B.92)
tGen.>NER
i
QAT.NERtoMCR QCons_hr.NERtoMCR
i i hr (B.96)
93
Appendix B. STEP calculations
6
LFUSO.Stn LFUSO FracGen
i i (B.111)
i 1
6
LFUSO.Stn LFUSO FracGen
i i (B.112)
i 1
LFUSO
4
LFUSO
3
i i
FAuxPower.Est % % (B.113)
i
2
LFUSO LFUSO
i i
%
%
JEFPs.Targ
F FractAuxPower.min.ACC
i
otherwise
AuxPower.Esti i JUSO
i
96
Appendix B. STEP calculations
P10deg P6deg
i i
TACC.Air.In /°C 6 P6deg if 6 TACC.Air.In /°C 10
10 6 i i i
P15deg P10deg
i i
ACC.Air.In
T /°C 10 10deg
P if 10 TACC.Air.In /°C 15
15 10 i i i
P20deg P15deg
i i
ACC.Air.In
T /°C 15
15deg
P if 15 TACC.Air.In /°C 20
20 15 i i i
P25deg P20deg
i i
ACC.Air.In
T /°C 20 20deg
P if 20 TACC.Air.In /°C 25
25 20 i i i
P30deg P25deg
i i
TACC.Air.In /°C 25 P25deg if 25 TACC.Air.In /°C 30
30 25 i i i
P35deg P30deg
i i
TACC.Air.In /°C 30 P30deg if 30 TACC.Air.In /°C 35
35 30 i i i
P40deg P35deg
i i
TACC.Air.In /°C 35 P35deg if 35 TACC.Air.In /°C 40
40 35 i i i
P42deg P40deg
i i
TACC.Air.In /°C 40 P40deg if 40 TACC.Air.In /°C 42
42 40 i i i
P42deg otherwise
i
PBP.Targ
4
PBP.Targ
3
i i
CFBP.Targ.40% kPa kPa (B.127)
i
2
PBP.Targ PBP.Targ
i i
kPa
kPa
PBP.Targ
4
PBP.Targ
3
i i
CFBP.Targ.60% kPa kPa (B.128)
i
2
PBP.Targ PBP.Targ
i i
kPa
kPa
99
Appendix B. STEP calculations
PBP.Targ
4
PBP.Targ
3
7 i i
CFBP.Targ.80% kPa kPa (B.129)
i
2
PBP.Targ PBP.Targ
i i
kPa
kPa
PBP.Targ
4
PBP.Targ
3
i i
CFBP.Targ.100% kPa kPa (B.130)
i
PBP.Targ
2
PBP.Targ
i
i
kPa kPa
FracMU.Targ
i
1 RQ.MU
CFMU.Targ
i % (B.132)
i Frac MU.Targi
1 RQ.MU FMU.Est
i % i
100
Appendix B. STEP calculations
6
VMU.Other VMU.MeterA.Stn VMU.MeterB.Stn VMU
i (B.159)
i 1
6
VMU.ExclU VMU.Stn VMU
i (B.162)
i 1
MCRLV MW (B.166)
i
105
Appendix B. STEP calculations
6
TIPT.Targ.In TIPT.Targ.In FracGen
i i (B.205)
i 1
6
TMS.Act.Stn THPT.Act.In FracGen
i i (B.206)
i 1
6
TIPT.Act.Stn.In TIPT.Act.In FracGen
i i (B.207)
i 1
6
LMS.SF.Stn LMS.SF FracGen
i i (B.208)
i 1
6
LReH.SF.Stn LReH.SF FracGen
i i (B.209)
i 1
113
Appendix B. STEP calculations
6
PBP.Targ.Stn PBP.Targ FracGen
i i (B.210)
i 1
6
PBP.Act.Stn PCond FracGen
i i (B.211)
i 1
6
LBP.SF.Stn LBP.SF FracGen
i i (B.212)
i 1
6
LTurb.Det.Stn LDet.Turb FracGen
i i (B.213)
i 1
6
TFW.Targ.Stn TFW.Targ FracGen
i i (B.214)
i 1
6
TFW.Act.Stn TFW.Act FracGen
i i (B.215)
i 1
6
LFW.SF.Stn LFW.SF FracGen
i i (B.216)
i 1
6
LMU.Targ.Stn LMU.Targ FracGen
i i (B.218)
i 1
114
Appendix B. STEP calculations
6
LMU.Act.Stn LMU.Act FracGen
i i (B.219)
i 1
6 (B.220)
RQ.MU.Stn RQ.MU FracGen
i i
i 1
LMU.SF.Stn LMU.Act.Stn LMU.Targ.Stn RQ.MU.Stn100 (B.221)
6
FractAuxPower.Act.Stn FractAuxPower.Act FracGen
i i (B.222)
i 1
6
FractAuxPower.Targ.Stn FracAuxPower.Targ FracGen
i i (B.223)
i 1
6
HRIncr.Act.Stn HRIncr.Act FracGen
i i (B.225)
i 1
6
HRIncr.MCR.Act.Stn HRIncr.MCR.Act FracGen
i i (B.226)
i 1
CostCoal.Incremental
CostQ.Incr
CVCoal
(B.227)
115
Appendix B. STEP calculations
QTot.Targ Cost
i Q.Incr
GWh c
kWh
CostL 1000 (B.228)
i LU.SF.derived
i
%
LMS.SF
i
CostL.MS CostL FracGen
i % i i (B.229)
LReH.SF
i
CostL.ReH CostL FracGen
i % i i (B.230)
LBP.SF
i
CostL.BP CostL FracGen
i % i i (B.231)
LDet.Turb
i
CostL.Det.Turb CostL FracGen
i % i i (B.232)
LFW.SF
i
CostL.FW CostL FracGen
i % i i (B.233)
LMU.SF
i
CostL.MU CostL FracGen
i % i i (B.235)
LAuxPower.SF
i
CostL.AuxPower CostL FracGen
i % i i (B.236)
116
Appendix B. STEP calculations
LCIR.SF
i
CostL.CIR CostL FracTot.Stm
i % i i (B.237)
LDFG.SF
i
CostL.DFL CostL FracTot.Stm
i % i i (B.238)
LH2_Moist.SF
i
CostL.H2_Moist CostL FracTot.Stm
i % i i (B.239)
4 3
LFBoil LFBoil
i i
Load.AT.Boil % % (B.244)
i
2
LFBoil
i
%
LFBoil
i
%
117
Appendix B. STEP calculations
QStn.In
HRAct.Stn
JUSO.Stn JAuxPower.Offload.Stn
(B.255)
1
overall
HRAct.Stn
(B.256)
QTot.Targ.Stn (B.257)
HRTarg.Stn
JUSO.Stn JAuxPower.Offload.Stn
HRTarg.Stn
SFDirect.Stn
HRAct.Stn
(B.258)
mCoal.StnCostCoal_Ton
CostCoal_USO
JUSO.Stn
(B.263)
mFO.Stn CostFO_ton
CostFO_USO
JUSO.Stn
(B.264)
119
Appendix B. STEP calculations
CostCoal.Incremental
CostQ.Incr
CVCoal
(B.266)
6 (B.268)
P'Cap.Installed.USO.Stn P'Cap.Installed.USO
i
i 1
mCoal.StnSFDirect.Stn
m'Coal.Stn
JUSO.Stn 1 LAcc.Stn LUnacc.prev.month.Stn (B.269)
JUSO.Stn JAuxPower.Offload.Stn
LFStd.USO.Stn
P'Cap.Installed.USO.Stnthr_month
(B.270)
6
FractAuxPower.min.ACC.Stn FractAuxPower.min.ACC FracGen
i i (B.271)
i 1
JEFPs.Targ.Stn
1 FractAuxPower.Targ.Stn JUSO.Stn
(B.272)
CFAuxPower.Stn
1 FractAuxPower.min.ACC.Stn
JUSO.Stn (B.273)
LFSby.Stn
JSby.Stn
120
Appendix B. STEP calculations
VRW.Stn (B.275)
Litre_USORW
JUSO.Stn
VWW.Stn (B.276)
Litre_USOWW
JUSO.Stn
121
Appendix B. STEP calculations
JAuxPower.Offload.Stn (B.293)
FAuxPower.OffLoad.Stn
JUSO.Stn JAuxPower.Offload.Stn
CVCoal (B.294)
CVAdj.EM
1 xEM.Coal
CVCoal (B.295)
CVMF
1 xTM.Coal
QAdj.Gen.Stn
HRStn
JUSO.Stn
(B.297)
1 (B.298)
Stn
HR Stn
122
Appendix B. STEP calculations
mCoal.Stn (B.301)
BRStn
JUSO.Stn
6
QTot.TurbTarg.Stn QCons.AT CFPF CFBP.Targ
i i i (B.302)
i 1
JGen.HV.Stn
Turb.Stn
QTot.TurbTarg.Stn
1 LTot.Turb.SF.Stn
(B.303)
VMU.Stn
l
RatioMU_Stm.Stn (B.304)
mStm.Stn
kg
JAuxPower.Stn (B.305)
FractAuxPower.Stn
JUSO.Stn
JUSO.Stn
LFSby
JSby.Stn
(B.306)
JUSO.Stn
LFMax.Demand
thr_month USOMax.Stn
(B.307)
JGen.HV.Stn
LFRunning.Stn
JCap.Stn
(B.308)
JUSO.Stn
LFUSO.Stn
P'Cap.Installed.USO.Stnthr_month
(B.309)
123
Appendix B. STEP calculations
LFUSO.Stn
EUFStn
EAFStn
(B.310)
124
Appendix C. Model uncertainty analysis
xCIR FA xC.FA 1 FA xC.BA 0.017 (C.1)
The equation below is also derived from 1st principles mass balance at a higher level.
xCu (C.2)
xCIR
xCu xAsh.Coal
xCIR xAsh.Coal
xCu 0.005
1 xCIR (C.3)
MJ
LCIR.Act xCu CVC 0.177
kg Coal_fired
(C.5)
125
Appendix C. Model uncertainty analysis
MJ (C.6)
hBA Cp.BA TBA Tref xC.BA CVC 1.712
kg
MJ (C.7)
hFA Cp.FA TFA Tref xC.FA CVC 0.629
kg
xAsh.Coal 1 xVM.Ash xC.BA xC.FA (C.8)
xCu BA FA 0.008
1 xAsh.Coal xTM.Coal
1 xC.BA 1 xC.FA
xAsh.Coal 1 xVM.Ash BA FA MJ (C.9)
LCIR.Act hBA hFA 0.206
1 xCu
1 xC.BA 1 xC.FA
kg Coal_fired
xAsh.Coal 1 xVM.Ash BA FA
hBA hFA
1 xCu
LCIR.Act
1 xC.BA 1 xC.FA
1.097 % (C.10)
CVCoal
3 (C.11)
DFG m
VDFG 12.657
DFG kg Coal_fired
MJ (C.12)
LCO.Act VDFG yCO.DFG CVCO 0.032
kg Coal_fired
Or
126
Appendix C. Model uncertainty analysis
xCIR
CV
xC.Coal % Coal
xS.Coal
Ce 0.375 46.236 (C.13)
% kJ %
33820 kg
xC.Coal xVM.Coal (C.14)
k 6.28 0.0897 0.023 2.586
% %
yO2.AH.Out
21
%
yCO2.AH.Out % 0.124
xH.Coal xVM.Coal
2.37 0.375 k (C.15)
1
% %
Ce
The calculations above aim to estimate the volume fraction of CO2 and N2 on a dry basis, by an
approximated molar balance relative to the O2 depleted from the air, where:
Ce - Carbon Equivalent
k - Empirical constant relating to N2 and O2 content in coal (not referenced in [34]). It is assumed
that this term is synonymous with the xN ,O .Coal as mentioned on page 42 [15].
xS.Coal kg
DFG DFC xC.Coal xCu 9.399
2.67 kg Coal_fired
(C.18)
127
Appendix C. Model uncertainty analysis
DFG Cp.DFG TGas.AH.Out TAir.FD.In (C.19)
LDFG.Act 4.797 %
CVCoal
MJ (C.20)
LDFG.Act DFG Cp.DFG TGas.AH.Out TAir.FD.In 0.901
kg Coal_fired
kJ xCu 0.005
Cp.FG.mol 30.6
kmol K [5]
xS.Coal kg
xC.Coal xCu 100
DFG
2.67 kg Coal_fired
0.313
kmol
(C.21)
kg yCO2.AH.Out yCO.DFG kg Coal_fired
12
kmol % %
MJ
LDFG.Act DFG Cp.FG.mol TGas.AH.Out TAir.FD.In 0.909
kg Coal_fired
(C.22)
DFG Cp.FG.mol TGas.AH.Out TAir.FD.In
LDFG.Act 4.843 %
CVCoal
(C.23)
kg kg kg
xH.Coal 0.031 xS.Coal 0.009 MNO2 46.010 MSO2 64.065 MCO2 44.0098
kmol kmol kmol
kg kg kg
MO2 32.000 MN 14.010 MS 32.065 0.192 S 1
kmol kmol kmol N
The BS EN 12952-15 [15] and provides an alternative method of calculating the gas products and
heat coefficients i.e. calculating the boiler excess air through an O2 balance. Stoichiometric
128
Appendix C. Model uncertainty analysis
quantities are derived from elemental balances. Properties of air are acquired from DIN 1871 as
referenced in [15]. Other chemical properties not stated were acquired from [72].
xN.Coal 0.015 1 xAsh.Coal xTM.Coal 0.009 (C.24)
The nitrogen content of coal is assumed to be 1.5 % on a dry-ash-free basis as per [15]. The
calculation above converts to as received/fired basis. The combined nitrogen and oxygen, xN ,O .Coal
is required. In this case, it is set to be equal to k = 0.026 as computed in the STEP dry flue gas loss
calculation above.
kg (C.26)
DA.Stoich 11.5122 xC.Coal 34.2974 xH.Coal 6.421
kg Coal_fired
4.3129 xS.Coal 4.3212 xO.Coal
3 3
m m
VDFG.Stoich 8.8930 xC.Coal 20.9724 xH.Coal 4.807
3.319 x kg kg Coal_fired (C.27)
S.Coal 2.6424 xO.Coal
0.7997 xN.Coal
kg (C.28)
CO2.Stoich 3.6699 xC.Coal 0.0173 xH.Coal 1.719
kg Coal_fired
0.0022 xS.Coal 0.0022 xO.Coal
kg (C.29)
CO2 CO2.Stoich 1.720
kg Coal_fired
yO2.AH.Out
DA.STP VDFG.Stoich x
yO2.DA yO2.AH.Out CO2.DA
kg
DA DA.Stoich 8.422 (C.30)
kg Coal_fired
yO2.AH.Out
DA.STP VDFG.Stoich
yO2.DA yO2.AH.Out
kg (C.31)
DA DA.Stoich 8.422
kg Coal_fired
yO2.AH.Out
DA.STP VDFG.Stoich
yO2.DA yO2.AH.Out
kg (C.32)
N2 DA.Stoich xN2.DA 6.367
kg Coal_fired
yO2.AH.Out
DA.STP VDFG.Stoich x
yO2.DA yO2.AH.Out N2.DA
129
Appendix C. Model uncertainty analysis
yO2.AH.Out kg
O2 DA.STP VDFG.Stoich x 0.462
yO2.DA yO2.AH.Out O2.DA kg Coal_fired
(C.33)
MNO2 kg
NO2 xN.Coal N 0.006
MN kg Coal_fired
(C.34)
MSO2 kg
SO2 xS.Coal S 0.018 (C.35)
MS kg Coal_fired
N , S - Nitrogen and sulphur conversions are assumed for wall-fired boilers. The nitrogen
converted is approximated to 100% nitrogen dioxide and sulphur to 100% sulphur dioxide.
kg
DFG SO2 NO2 N2 CO2 O2 8.573
kg Coal_fired
(C.36)
MCO2
yCO2 0.139 (C.37)
CO2 SO2 N2 O2 NO2
MCO2 MSO2 MN2 MO2 MNO2
CO2 (C.38)
xCO2 0.201
DFG
4 06 (C.39)
0.1919210 10 0.5883483 10 2
Cp.DA.0 ( T ) 1.004173 T T
2 3
9 12
0.7011184 10 3 0.3309525 10 4
T T
4 5
16
0.5673876 10 5
T
6
The integral heat capacity of dry air relative to 0oC is given by the function above.
130
Appendix C. Model uncertainty analysis
3 06
0.7661864 10 0.9259622 10 2
P2m( T ) 0.1002311 T T
2 3 (C.40)
9 12
0.5293496 10 3 0.1093573 10 4
T T
4 5
The above polynomial function is given in [15] to calculate the heat capacity of flue gas. See below:
TGas.AH.Out TGas.AH.Out
Cp.DFG.0
K K
TAir.FD.In TAir.FD.In
Cp.DFG.0
K K kJ kJ (C.41)
Cp.DFG 1.074
TGas.AH.Out TAir.FD.In kg K kg K
K K
MJ (C.42)
LDFG.Act DFG Cp.DFG TGas.AH.Out TAir.FD.In 0.875
kg Coal_fired
DFG Cp.DFG TGas.AH.Out TAir.FD.In (C.43)
LDFG.Act 4.660 %
CVCoal
kJ … from steam tables
hH20.FG hsteam 1bar TGas.AH.Out "" "" """ 2737.718
kg
kJ …from steam tables
hH20.Tref.liquid hsteam 1.bar TAir.FD.In "" """ """ 104.301
kg
kJ … from steam tables
hH20.Tref.Gas hsteam "" TAir.FD.In "" 1 """ 2546.272
kg
MJ (C.46)
LH20 H20 hH20.FG hH20.Tref.Gas 0.089
kg Coal_fired
H20 hH20.FG hH20.Tref.Gas
LH20 0.476% (C.47)
CVCoal
131
Appendix C. Model uncertainty analysis
It can be deduced from the term H20 , the fuel moisture is assumed to be in a gaseous phase
hence combined with the moisture in combustion air and atomizing steam to determine only the
sensible heat losses. This would not apply to solid fuels. The calculations below will individually
compute the moisture in fuel loss and the moisture in combustion air which is congruent with BS
2885-19974 [5]. The reference enthalpy for moisture in fuel loss will be considered in the liquid
phase.
MJ (C.48)
LH20.Moist_Air DA w hH20.FG hH20.Tref.Gas 0.021
kg Coal_fired
DA w hH20.FG hH20.Tref.Gas (C.49)
LH20.Moist_Air 0.112%
CVCoal
MJ (C.50)
LH20.Fuel H20.Fuel hH20.FG hH20.Tref.liquid 0.940
kg Coal_fired
H20.Fuel hH20.FG hH20.Tref.liquid (C.51)
LH20.Fuel 5.007%
CVCoal
xTM.Coal xH.Coal
9
% %
(C.52)
LH_Moist.Act kL.H_Moisture.1 % 4.897%
CVCoal T
Gas.AH.Out
/°C
MJ TAir.FD.In /°C
kg 2
kL.H_Moisture.2
The origins of the above equation cannot be traced back to the BS 2885 [5], however KL.H _ Moist .1 is
the latent heat of water (MJ/kg) and KL.H _ Moist .2 is the inverse of the heat capacity of liquid water
(K.kg/MJ). So it is simplified that the fuel moisture would absorb sensible heat in the liquid phase
to the midpoint between TGas .AH .Out and TAir .Fd .In , thereafter in the form of latent. The sensible heat
absorbed in the gas phase is ignored.
132
Appendix C. Model uncertainty analysis
kg kg kJ kJ
FracGen 1 m'ReH.in 626 m'MS 630 hRW 104.913 hMS 3381.453
s s kg kg
kJ kJ kJ
hFW 1148.252 hReH.Out 3601.370 hReH.in 3003.550
kg kg kg
m'ReH.in (C.53)
kJ
h Boil hMS hFW hReH.Out hReH.in 2827.225
m'MS kg
In the above calculation, h Boil is the total heat absorbed per kg steam produced by the boiler.
2 1
hMS hFW hRW
3 3
RQ.MU 0.008 (C.54)
h Boil
100
Boil
where RQ.MUis the make-up heat ratio which can also be expressed as:
FracMU (%)
Then:
FracMU.Targ (C.55)
LMU.design RQ.MU 0.806 %
%
4 3
8 LFUSO LFUSO
FMU.Est 3.4643 10 8.231 10 6 1.107
% % (C.56)
2
4 USO
LF LFUSO
6.1239 10 8.0326 10 3 1.554
% %
133
Appendix C. Model uncertainty analysis
The above factor calculated is a polynomial function to estimate the make-up water to steam
raised, mass fraction relative to design conditions at MCR, as a function of the sent out load factor
and is specific to a Unit design.
FracMU.MCR
1 RQ.MU
%
CFMU.Targ 1.001 (C.57)
FracMU.MCR
1 RQ.MU FMU.Est
%
The target cycle heat rate correction factor relative to the sent-out load factor is expressed above.
FracMU.MCR (C.58)
LMU.Targ FMU.Est CFMU.Targ RQ.MU 0.893 %
%
It can be seen that there is now compensation for changes in efficiency specific to the deviation in
the make-up water fraction, CFMU.Targ . Initially, the energy input to the cycle was calculated by
setting the boiler efficiency to 90% as in calculation(C.49). The correction factor is necessary, for
the thermal loss to be normalized to one unit of energy input to the cycle.
VMU FracGen VMU.Other VMU.Cold ML
FMU.Hot 0.032
mStm.Boil Gg
(C.59)
From the above calculation, it is observed that make-up when the unit is off-load or before
synchronization, VMU.Cold is deducted from the total make-up accounted for. This is sensible as
this heat is accounted for in the heat for commissioning and should be included in the running unit
heat rate calculation. FracGen VMU.Other is the means to apportion all other demineralized water
flow that is not directly fed to the unit Rankine cycle to an individual unit. This would typically
include water used in the auxiliaries cooling loops, hydrogen production and other common plant
areas.
In most cases it is difficult to split this flow further into what is recovered to the Rankine cycle
typically via the condenser cleans drains tank and what would be lost externally to the Rankine
cycle such as the flows to the hydrogen production plant or compressed air supply plants. Each
power plant’s metering configuration should be carefully analysed to establish if this flow should
be considered for thermal losses or a factor should be applied which station-specific is. It is noted
that the density of water in the calculation (C.54) is approximated to 1kg/m3 and is therefore
134
Appendix C. Model uncertainty analysis
FMU.Hot approximated to a mass fraction. A sensitivity calculation with a density of 0.997 kg/m3
FracMU.MCR
FMU.Hot 1 R Q.MU
LMU.Act
% R (C.60)
Q.MU 2.657 %
ML
%
FMU.Hot
Gg 1 RQ.MU
ML
%
Gg
LMU.SF LMU.Act LMU.Targ 1.764 % (C.61)
Note: In STEP, the term RQ.MU is dropped from calculations (C.54) and (C.55), but added to the
calculation (C.56) to give the same effect as the above.
3
Q'Boil.Out 1.363 10 MW @ 97% MCR design
0.7
Q'Boil.Out
LRC C MW 4.183MW (C.62)
MW
LRC
LRC 0.289% (C.63)
m'Coal CVCoal
4 3
LFBoil LFBoil
CFLF.Boil (C.64)
% %
2
LFBoil LFBoil
% %
135
Appendix C. Model uncertainty analysis
4 3
LFBoil LFBoil
kL.Rad 0.551 (C.65)
% %
2
LFBoil LFBoil
% %
kL.Rad
LRad 0.568% (C.66)
LFBoil
CFLF.Boil
%
%
LDet.Turb DetTurb.Previous 0.1 N F 0.85% (C.67)
yr yr Availability
150 % 0.05 %
DetTurb.1st_Year k1st_year f (C.68)
P month month
MW
150 % 0.03 %
DetTurb.2nd_Year k2nd_year f (C.69)
P month month
MW
DetTurb.120_Month 12 DetTurb.1st_Year 108DetTurb.2nd_Year FAvailability 3.264% (C.70)
P
BF10yrs psi
DetTurb.10_yrs f % 1.402% (C.71)
Pow
log
2400
MW
136
Appendix D. STEP program inputs details
137
Appendix D. STEP program inputs details
i]
19 t Sby .Hoti HotSby_Time[i] Period where the boiler is kept on hot hrs 5.000 5.0 % 1 default
standby
20 NStarts .Coldi Boil_ColdStarts[i] Boiler cold starts (RTS after being offload for - 5.000 5.0 % 1 default
>168 hours)
21 mMRi Mill_Reject_Mass[i] Mass of mill rejects ton 5.000 5.0 % 1 default
22 CVMRi Mill_Reject_CV[i] Calorific value of mill rejects MJ/kg 0.300 0.3 abs 1 [75]
23 xC .FAi AH_Gas_In_CIR[i] Air heater gas inlet carbon in ash % 1.000 1.0 % 5 [17]
(m/m)
24 xC .BAi CoarseAsh_CIR[i] Boiler bottom carbon in ash % 1.000 1.0 % 200 [17]
(m/m)
25 tRT .Mill .Ai MILL_A_Run_Hrs[i] Mill “A” running hours hrs 5.000 5.0 % 1 default
26 tRT .Mill .Bi MILL_B_Run_Hrs[i] Mill “B” running hours hrs 5.000 5.0 % 1 default
27 tRT .Mill .Ci MILL_C_Run_Hrs[i] Mill “C” running hours hrs 5.000 5.0 % 1 default
28 tRT .Mill .Di MILL_D_Run_Hrs[i] Mill “D” running hours hrs 5.000 5.0 % 1 default
29 tRT .Mill .Ei MILL_E_Run_Hrs[i] Mill “E” running hours hrs 5.000 5.0 % 1 default
30 tRT .Mill .Fi MILL_F_Run_Hrs[i] Mill “F” running hours hrs 5.000 5.0 % 1 default
31 JGen.LV .Maini Gen_LV_Main_J[i] Energy measured at the generator GWH 5.000 5.0 % 1 [47]iv
terminals main meter
32 JGen .LV .Checki Gen_LV_Check_J[i] Energy measured at the generator terminals GWH 5.000 5.0 % 1 [47]
check meter
33 JAuxPower .Maini AuxPower_Main_J[i] Energy measures at auxiliary power tap-off GWH 5.000 5.0 % 1 [47]
point main meter
34 JAuxPower .Checki AuxPower_Check_J[i] Energy measures at auxiliary power tap-off GWH 5.000 5.0 % 1 [47]
point check meter
35 JGen.NERi Gen_AboveNER_J[i] Energy measured at generator terminals GWH 5.000 5.0 % 1 [47]
when generating above NER
36 tGen.NERi Gen_AboveNER_RT[i] Time that generator operates above NER hrs 5.000 5.0 % 1 default
37 JReactive .Geni Gen_Reactive_J[i] Generator reactive energy GVARs 5.000 5.0 % 1 [47]
38 tRT .Geni Gen_RT[i] Generator run time (synchronization to Hrs 5.000 5.0 % 1 [47]
separation from the power grid)
39 JUnit .AuxPower .Tripi AuxPower_Offload_J[i] Auxiliary power measured when generator GWH 5.000 5.0 % 1 [47]
not synchronized
40 JUnit .AuxPower .SBi AuxPower_SB_J[i] Auxiliary power supplied from the station GWH 5.000 5.0 % 1 [47]
138
Appendix D. STEP program inputs details
board
41 tRT .EFP .Ai A_EFP_RT[i] Electric feed water pump “A” run time hrs 5.000 5.0 % 1 default
42 tRT .EFP .Bi B_EFP_RT[i] Electric feed water pump “B” run time hrs 5.000 5.0 % 1 default
43 tRT .EFP .Ci C_EFP_RT[i] Electric feed water pump “C” run time hrs 5.000 5.0 % 1 default
o
44 TFW .Acti Eco_FW_In_T[i] Economizer feedwater inlet temperature C 5.556 5.6 abs 1 [47]
o
45 TLH .HPT .Ini HPT_LH_MS_In_T[i] High-pressure turbine left hand inlet C 3.928 5.6 abs 2
temperature [47]
o
46 TRH .HPT .Ini HPT_RH_MS_In_T[i] High-pressure turbine right hand inlet C 3.928 5.6 abs 2
temperature [47]
o
47 TLH .IPT .Ini IPT_LH_Stm_in_T[i] Intermediate-pressure turbine left hand C 3.928 5.6 abs 2
inlet temperature [47]
o
48 TRH .IPT .Ini IPT_RH_Stm_in_T[i] Intermediate-pressure turbine right hand C 3.928 5.6 abs 2
inlet temperature [47]
49 mHPT .Ini HPT_Stm_In_MFR[i] High-pressure turbine inlet mass flow rate kg/s 1.000 1.0 % 1 [47]
50 PHPT .Ini HPT_Stm_In_P[i] High-pressure turbine inlet pressure bar 0.250 0.5 % 4 [47]
51 mIPT .Ini IPT_Stm_In_MFR[i] Intermediate-pressure turbine inlet mass kg/s 1.000 1.0 % 1 [47]
flow rate
52 PIPT .Ini IPT_Stm_In_P[i] Intermediate-pressure turbine inlet bar 0.250 0.5 % 4
[47]
pressure
53 mReH .Ini ReH_Stm_In_MFR[i] Re-heater inlet mass flow rate kg/s 1.000 1.0 % 1 [47]
54 PHPT .Outi HPT_Stm_Out_P[i] High-pressure turbine outlet pressure bar 0.354 0.5 % 2 [47]
o
55 THPT .Outi HPT_Stm_Out_T[i] High-pressure turbine outlet temperature C 3.928 5.6 abs 2 [47]
56 mReH .SWi ReH_SW_MFR[i] Re-heater spray water mass flow rate kg/s 1.000 1.0 % 1 [47]
o
57 TReH .SW .Ini ReH_SW_T[i] Re-heater spray water supply temperature C 5.556 5.6 abs 1 [47]
58 tRT .CEP .Ai CEP_A_RT[i] Condensate extraction pump “A” run time hrs 5.000 5.0 % 1 default
59 tRT .CEP .Bi CEP_B_RT[i] Condensate extraction pump “B” run time hrs 5.000 5.0 % 1 default
o
60 TACC .Air .Ini ACC_Fan_In_T[i] Air cooled condenser air inlet temperature C 2.778 2.8 abs 1 [47]
o
61 TACC .Air .Outi ACC_Out_T[i] Air cooled condenser air outlet temperature C 2.778 2.8 abs 1 [47]
62 PCondi Cond_Act_P[i] Condenser actual pressure kPa 0.354 0.5 % 2 [47]
63 NStart .Hot .TurbI Turb_HotStart_Num[i] Number of turbine hot starts - 5.000 5.0 % 1 default
64 NStart .Cold .TurbI Turb_ColdStart_Num[i] Number of turbine cold starts - 5.000 5.0 % 1 default
139
Appendix D. STEP program inputs details
140
Appendix D. STEP program inputs details
89 Cos tCoal _ ton Coal_PerTon_Cost Coal cost per ton R/ton 0.000 0.0 % 1 n/a
90 mFO .Stn FO_Mass Mass of fuel oil burned for all units ton 5.000 5.0 % 1
91 CVFO FO_CV Calorific value of fuel oil MJ/kg 0.300 0.3 abs 1 Typical
certificate
vi
98 USOMax .Stn USO_Max_Stn Maximum electrical units sent out (power) MW 0.000 0.0 % 1 n/a
99 UCFStn UCF_Stn Station unit capability factor % 0.000 0.0 % 1 n/a
100 xEM .Coal Coal_EM_x Coal excess moisture content % 1.500 1.5 abs 1 [80]
101 JSby .Stn Tot_Sby_Load_J Total standby load GWH 5.000 5.0 % 1 [47]
102 tGen .Stn Stn_Run_Time Station running hours hrs 5.000 5.0 % 1 default
103 Cos tFO _ ton FO_Cost Fuel oil cost R/ton 0.000 0.0 % 1 n/a
104 thr .month Month_Hrs Hours for the specific month hrs 5.000 5.0 % 1 default
105 EAFStn Stn_EAF Station availability factor % 0.000 0.0 % 1 n/a
141
Appendix D. STEP program inputs details
uLiterature
i
The uncertainty, ui , where uLiterature is transformed to a % form by dividing by the typical variable value x 100 if given in units.
Ntransmitters
ii
The word “default” in the reference column indicates that a quantitative assessment had not been determined, a chosen default value to test the sensitivity of the
variable. Used typically for manual human errors however these should be neglected when the estimation of running hours is done through an automated electronic
process.
iii
The subscript “i” or “[i]” = 1-6 (for each unit number). If omitted from the variable name, then the property refers to a composite value for the entire station.
iv
Even though the referenced text indicates that the uncertainty for uncalibrated electrical metering can be in excess of 5% a more conservative figure of 2.5% has been
evaluated based on the authors experience.
v
ISO [78] indicates that mechanical sampling systems should be design to a 1% uncertainty on ash content which was translated to the CV using the South African ash/CV
correlation[85] to achieve an uncertainty of 0.37 MJ/kg on an as received basis. ISO [77] suggests an uncertainty of 0.3 MJ/kg on an air dried basis. The uncertainties were
combined by the RSS method.
vi
ISO [86] indicates a 0.1% uncertainty, however typical supplier test certification indicate 7.5% uncertainty in the measured CV
142
Appendix E.STEP program output tag list
143
Appendix E.STEP program output tag list
144
Appendix E.STEP program output tag list
145
Appendix E.STEP program output tag list
146
Appendix E.STEP program output tag list
147
Appendix E.STEP program output tag list
148
Appendix F. Results
Appendix F. Results
Table F- 1: Systematic uncertainty propagation full results
149
Appendix F. Results
150
Appendix F. Results
151
Appendix G. Model verification
Calculation
No. Variable [Unit No.] MathCAD Python Difference
1 AH_GAS_OUT_T[1] 130.50000 130.50000 0.00000
2 FD_In_T[1] 35.50000 35.50000 0.00000
3 AH_Gas_In_O2_x[1] 4.35000 4.35000 0.00000
4 AH_LH_Leak[1] 5.76920 5.76923 0.00003
5 AH_RH_Leak[1] 3.70370 3.70370 0.00000
6 Stm_Mass[1] 1 450.00000 1 450.00000 0.00000
7 Boil_LF[1] 92.93206 92.93206 0.00000
8 Boil_LF_CF[1] 1.00050 1.00053 0.00003
9 CIR_Targ_CF[1] 0.96829 0.96829 0.00000
10 L_Corr_Ash[1] -0.03942 -0.03942 0.00000
12 Coal_H2_x[1] 3.09715 3.09715 0.00000
13 L_Corr_H2andMoist[1] 0.17021 0.17021 0.00000
14 L_Corr_H2andMoist[1] 0.17021 0.17021 0.00000
16 L_Corr_VM[1] 0.00000 0.00000 0.00000
17 L_Corr_VM[1] 0.00000 0.00000 0.00000
18 Boil_Fuel_CF[1] 1.00147 1.00147 0.00000
23 Heat_Boil_Hot_Starts[1] 1.09043 1.09043 0.00000
24 Heat_Boil_Cold_Starts[1] 0.46440 0.46440 0.00000
25 Heat_Boil_HotSby[1] 0.36133 0.36133 0.00000
26 Boil_OffLoad_Heat_GWH[1] 1.91616 1.91616 0.00000
27 CIR[1] 1.65964 1.65964 0.00000
31 AH_Gas_Out_CO2_x[1] 12.41016 12.41016 0.00000
32 DFG_AT_L[1] 4.97287 4.97287 0.00000
33 Cu[1] 0.52199 0.52199 0.00000
34 CIR_Targ_L[1] 1.21408 1.21408 0.00000
35 Tcu[1] 0.69662 0.69662 0.00000
36 DFG_Targ_L[1] 5.04333 5.04333 0.00000
38 DFC[1] 20.27211 20.27211 0.00000
39 Dfg[1] 9.45542 9.45542 0.00000
155
Appendix G. Model verification
156
Appendix G. Model verification
157
Appendix G. Model verification
158
Appendix G. Model verification
159
Appendix G. Model verification
160