Weekly Task List - Weekly Task List - Construction of Courtyard by Marriett Hotel G-11 Project Islamabad, From August 15, 2022 To August 20, 2022
Weekly Task List - Weekly Task List - Construction of Courtyard by Marriett Hotel G-11 Project Islamabad, From August 15, 2022 To August 20, 2022
Weekly Task List - Weekly Task List - Construction of Courtyard by Marriett Hotel G-11 Project Islamabad, From August 15, 2022 To August 20, 2022
MONDAY
TUESDAY
1).Conduct Morning Meeting
2).Detail site visit & monitoring of construction work as per updated IFC
structure drawings and specification following the related codes of practice to
maintain the quality of construction work and international standards.
August 23, 2022 3).Discussing and sorting any issues of contractor/consultant/site team
4).Design / Site Coordination with Design Section/PMO/EMC/MEP/S&F and
NDA. 5). Coordination with IMARAT different
departmnents like procurement, store, horticulture, maintenace, HR, admin &
finance department
6).Ensure site beautification & safety protocols on site
WEDNESDAY
1).Conduct Morning Meeting
August 24, 2022 2).Detail site visit & monitoring of construction work as per updated IFC
structure drawings and specification following the related codes of practice to
maintain the quality of construction work and international standards.
THURSDAY
FRIDAY
SATURDAY
1).Tbts (1 daily)
2).HSE Trainings (Twice a week).
3).HSE Induction of site staff visitors and ensuring safe site visits.
Incidents Reporting (If any).
4).HSE Inspections (Weekly and monthly as per the set frequency).
5).Fire Safety Inspection (Once a week).
6).HSE Innovation and Hazard identification through HSE signages.
7).Coordination with contractor and client teams on the closure of HSE observations.
7).Coordination with contractor and client teams on the closure of HSE observations.
12).Site beautification and coordination with horticulture department for ensuring timely
bushes and grass cutting.
13).Welfare facilities management.
1).Tbts (1 daily)
2).HSE Trainings (Twice a week).
3).HSE Induction of site staff visitors and ensuring safe site visits.
Incidents Reporting (If any).
4).HSE Inspections (Weekly and monthly as per the set frequency).
5).Fire Safety Inspection (Once a week).
6).HSE Innovation and Hazard identification through HSE signages.
7).Coordination with contractor and client teams on the closure of HSE observations.
7).Coordination with contractor and client teams on the closure of HSE observations.
1).Tbts (1 daily)
2).HSE Trainings (Twice a week).
3).HSE Induction of site staff visitors and ensuring safe site visits.
Incidents Reporting (If any).
4).HSE Inspections (Weekly and monthly as per the set frequency).
5).Fire Safety Inspection (Once a week).
6).HSE Innovation and Hazard identification through HSE signages.
7).Coordination with contractor and client teams on the closure of HSE observations.
1.Preparation of Block Masonry Measurment sheet for First Floor & 2nd Floor
2. Verification of Cement & Steel Demand Submitted by PB.
3.Coordinaton With Contracts Depart for BBS Verifcation.
4.Coordinaton With Contracts Depart for IPC # 09 Verfication.
5. Verification of Claims & Varation order submitted by Principal Builder.(Formwork & Floor Hardner etc)
1.Preparation of Block Masonry Measurment sheet for 3rd & 4th Floor
2.Verification of Material Reconcilition
3.Coordinaton With Contracts Depart for BBS Verifcation.
4.Coordinaton With Contracts Depart for IPC # 09 Verfication.
5. Verification of Claims & Varation order submitted by Principal Builder.(Formwork & Floor Hardner.
1.Preparation of Block Masonry Measurment sheet for 5th & 6th Floor
2.Verification of Price Adjustment for current month Workdone.
3.Coordinaton With Contracts Depart for BBS Verifcation.
4.Coordinaton With Contracts Depart for IPC # 09 Verfication.
1. Staircase no. 01 formwork follow up, inspection and ensuring to be get it ready on time. 2. Formwork of 8th floor
slab erection follow up and inspection. 3. Concrete pouring inspection and follow up of
staircase no. 03. 4. Formwork staircase 05 fixing inspection and follow up.
5. Keeping check for testing of concrete cylinders, steel delivered and blocks delivered and batching plant
operations.
1. Block masonry working follow up for mezzanine floor, inspection and ensuring to be get it done on time.
2. Formwork of 8th floor slab erection follow up and
inspection. 3. Block work inspection and follow up of staircase no. 03.
4. Concrete pouring inspection of staircase 05 nspection and follow up. 5.
Keeping check for testing of concrete cylinders, steel delivered and blocks delivered and batching plant operations.
6. Follow up and back support and checking of steel
fixing of beams and drop panels of 8th floor slab.
ABAD, FROM AUGUST 15, 2022 to AUGUST 20, 2022
1).Inspection of steel of shear wall lift lobby from 7th to 8th Floor (Zone-2)
2).Inspection of Block Masonary at Ground Floor.
3).Inspection of Block Masonary at First Floor.
4).Inspection of 9th Floor Slab & Beams Formwork & steel Zone 1
5).Inspection of Formwork, steel & Pouring of Concrete Stair Case 6).Verification of Daily Progress
Report of PB.
7).Sign Inspection Requests as per daily work carried out at Site 8). Monitering of 8th Floor
Slab & Beams Formwork Zone 2
Inspection of Formwork & Pouring of Concrete in Columns at 7th to 8th Floor (Zone-2) 6 Nos
Inspection of Block Masonary at Ground Floor.
Inspection of Block Masonary at First Floor.
Inspection of 9th Floor Slab & Beams Formwork. Zone 1 (50 % Area )
Verification of Daily Progress Report of PB.
Sign Inspection Requests as per daily work carried out at Site
Inspection of Formwork & Pouring of Concrete in Columns at 7th to 8th Floor (Zone-2) 9 Nos
Inspection of Block Masonary at Ground Floor.
Inspection of Block Masonary at First Floor.
Inspection of 9th Floor Slab & Beams Formwork Zone 1 ( 100 % Area )
Verification of Daily Progress Report of PB.
Sign Inspection Requests as per daily work carried out at Site
Inspection of Block Masonary Stiffner Columns & Lintel Beams at Ground Floor.
Inspection of Block Masonary , Stiffner Columns & Lintel Beams at First Floor.
Inspection of Beams Bottom Reinforcement for 9th Floor
Verification of Daily Progress Report of PB.
Sign Inspection Requests as per daily work carried out at Site
Inspection of Block Masonary Stiffner Columns & Lintel Beams at Ground Floor.
Inspection of Block Masonary , Stiffner Columns & Lintel Beams at First Floor.
Inspection of Beams Bottom Reinforcement for 9th Floor.
Verification of Daily Progress Report of PB.
Sign Inspection Requests as per daily work carried out at Site
Malik Dilawar Khan (Supervisor)
Drawing Study
Drawing Study
Plant visit before Slab concreting to check the availbilty of aggretes and sieve anasyis
Get IRS signature from Site Team & ARE and IGC PM
Scan the Concrete cylinder testing Results and update the Log.
Make copy of IRS and get received by Main Contractor
Updating Mater Log Sheet.