Passenger Hoist
Passenger Hoist
Passenger Hoist
12/2012/03
List of activities and detail explanation on how the work is going to execute,
EHS requirements as a part of activities and / or separate requirements.
Describe the anticipated emergency, start/ shut down situation/ malfunction etc. and determine action to
be taken with higher degree of control.
Add all technical details with reference of drawing.
Attach HIRAC that shall be prepared based on this.
It shall be prepared well before execution of job: at Pre/ post award stage.
Add following sequence of activities.
SEQUENCE OF ACTIVITIES
Sequence of Activities Indicate Reference To
Sr. No.
[From 1st to last Activity] [Drawing/Plan/Specification/SOP]
1 Installation of passenger hoist:
Transportation:
Check all required document of vehicle (licence,
R.C, Pollution, insurance and Fitness certificate of
vehicle)
Given induction to whole unloading team.
Provide complete PPE’S to whole team before
enter in site.
Deployed signal man to avoid man moment and
park the vehicle on suggested place by area in-
charge.
Unloading
Unload program organised in the presence of
area in-charge.
Check all lifting equipment’s like physical
condition and T.P.I certificate. (After taken
approved by Area In-charge then unloading
program will start).
Barricade provide the work place.
Page No. 1
C3 - Confidential
TRIL/CORP/EHS/F/8.12/2012/03
Operation
Procedure for daily use
1. Remove the padlock and turn MAIN SWITCH from
ground station switch box to position.
2. Check that all EMERGENCY STOP push buttons (3x) on
the control boxes are released.
3. Check the SAFETY CIRCUIT Green light = OK (cabin
doors locked, etc.).
4. Turn the joy stick to position UP. If the hoist does not
raise: - Check and correct the phase sequence.
5. Check the following items:
- anchoring and cable guiding
- presence of safety and protective devices
- mast section connections
- upright position of masts and level position of cabin
- any loose parts - loose parts on cabin roof
- ground supports and quality of foundation
- electrical connections (cable, voltage)
- safety aspects - correct functioning of end switches (upper,
lower, emergency upper, emergency lower)
Page No. 2
C3 - Confidential
TRIL/CORP/EHS/F/8.12/2012/03
disassembly.
Press the emergency stop push button when
disassembling a mast section or an anchor.
Pay attention to the risk of getting jammed
when passing anchoring or other obstacles.
1. Hoist operation during disassembly Set the key switch
on the cabin roof switchbox to position 2.
INSPECTION. By pressing the Up and DOWN push
buttons, the mechanic can drive the cabin up and
down. When the push-button is released, the hoist
stops. (‘hold to run’) When the key switch is in
position.
2. INSPECTION all other operating elements are
inhibited, except the EMERGENCY STOP buttons.
3. Check if the hoist can be operated safely. Warn all
people in the neighbourhood.
4. Disassemble the landing protection Ensure that the
landing openings are closed.
5. Remove the mast sections one by one from above the
uppermost anchor using a crane.
6. Remove uppermost anchor. First carry down the
disassembled mast sections. The maximum
permissible load for building situations must never be
exceeded.
7. At the same time the mast is being disassembled,
remove the anchor tubes, the anchors and the cable
guides. If a crane is available at the work site, the
mast can be disassembled quicker. Up to six mast
sections can be removed in one time and
disassembled on the ground.
8. Repeat this procedure until the motor carrier is ready
to be disassembled and the cabin is in its lowest
position.
9. Steady lower the cabin onto the buffers by releasing
the motor brakes.
10. Uncouple the motor carrier from the cabin by
loosening the bolts. The motor carrier can be raised
with the UP pushbutton until the motor bracket with
the load pin is above the dividing point of the mast.
11. Disconnect all connectors.
12. Disassemble the mast section including the motor
carrier, and lift it. Avoid damaging of the motor
bracket when lowering to the ground or on the truck.
13. Disassemble the roof fencing. The base machine can
Page No. 4
C3 - Confidential
TRIL/CORP/EHS/F/8.12/2012/03
2. Work Planning:
It shall be prepared and approved before job execution. Template is given below.
Page No. 5
C3 - Confidential
TRIL/CORP/EHS/F/8.12/2012/03
As per above
2. Work Planning:
(A) GENERAL
Contractor Name of In-charge Mobile: 9650281554
………………………..
HIFZUR REHMAN E-mail: la-vida@agsinfra.com
Finish
Date/Time:
Name and/or Designation Roles, Responsibility & Authority
HIFZUR REHMAN Work In-charge
HIFZUR REHMAN Engineer In-charge
Key Personnel Involved
in work execution NITISH RANA Work Supervisor
Quality In-charge
NABEEL ATA Safety In-charge
Type Number Specialist/Trade Expert Number
Skilled Workers 12 Electrician 01
Semi-Skilled Workers 0 Equipment operator 0
Estimation of Work Unskilled Workers 10 Welder 2
Force
Plumber 08
Mason 02
Any other specialist 0
Assessment on Type Specify Qualification/ Specify Medical Fitness
Competency & Medical Experience Certification Certification needed*
Page No. 6
C3 - Confidential
TRIL/CORP/EHS/F/8.12/2012/03
needed*
Electrician 01 Pre-Employment medical
&certified
Fitness[Certificate to be WELDER 02 Pre-Employment medical
submitted before start
of work] MASON 02 Pre-Employment medical
Plumber 08 Pre-Employment medical
Signal Man NA NA
Any other specialist NA NA
*Refer the guideline enclosed.
(B)TECHNICAL REQUIREMENTS
List of Equipments, Tools & Tackles Indicate
Equipments & Tools Fitness Test & Certification Needed
[Submit Test Certificate Brush NA
before start of work]
Plastic bucket
Page No. 7
C3 - Confidential
TRIL/CORP/EHS/F/8.12/2012/03
Hazardous Substances
[Attach MSDS if required]
[C] ENCLOSURES
Enclosures Yes No
Sr. No. - No
1 Copy of Drawing - No
2 Copy of Engineering Plan - No
3 Copy of Specification (internal/external) -
4 Copy of HIRAC (Hazard Identification, Risk Assessment YES -
& Control)
5 Work Area Access/Egress Sketch - No
6 Copy of MSDS (Material Safety Data Sheet) if YES
applicable
7 Copy of Quality Assurance Plan (QAP) - NO
8 Copy of Standard Operating Procedure - NO
9 Copy of Inspection & Test Plan - NO
10 Copy of Checklists - NO
11 Copy of Formats - NO
[D] APPROVAL
Prepared By: HIFZUR REHMAN Reviewed By: RAVI KUMAR VANKA Approved By: SUNIL CHAUHAN
Designation: Project Manager Designation: Asst. Manager Designation: Project Head
Date: Date: Date:
Contractor Client
Page No. 9
C3 - Confidential
TRIL/CORP/EHS/F/8.12/2012/03
We (the undersigned) have read and understood the attached method statement and will comply with
the specified requirements and control measures. If the work activity changes or deviates from that
originally envisaged, we will seek further advice and request an amended method statement.