Chapter-3 Economic Evaluation of Highway Projects
Chapter-3 Economic Evaluation of Highway Projects
Chapter-3 Economic Evaluation of Highway Projects
Chapter-3:
Economic Evaluation
of Highway Projects
Instructor: Amare T.
amentilahun23@gmail.com
Lecture Outlines
2
2
Introduction and Overview
3
3
Introduction and Overview
4
Terms:
o Engineering Analysis
o Engineering Economic
o Life Cycle Cost (LCC)
o Methods
Engineering analysis
A proper economic analysis should be conducted for
every pavement construction project. In order to
conduct economic analysis, it is necessary to
understand some key concepts and the techniques that
help us to compare alternatives on the basis of
economics and have reasonable estimates of different
types of costs associated with pavement projects. 4
Introduction and Overview
5
Engineering Economics:
Economic analysis can be conducted at two levels:
➢ 1st, at the network level to determine the feasibility and
scheduling of a project and,
➢ second, at the project level to achieve maximum economy within
a specific selected project by comparing different alternatives.
➢ For the second case, all of the alternatives must be able to satisfy
the project requirements and should be considered over the same
time period. The economic evaluation of the different
alternatives must consider accurate (as far as possible) estimates
of economic variables and costs and benefits associated with the
pavement.
➢ Life cycle cost (LCC) analysis provides a rational method of
conducting such economic analysis.
5
Introduction and Overview
6
6
Time Value of Money
7
Example 1:
Find the future worth of birr 100,000 at the end of 20 years
invested at a compound rate of interest of 12% per year.
Solution:
Equation: 𝑭 = 𝑷 𝟏 + 𝒊 𝒏
𝑭 = 𝟏𝟎𝟎, 𝟎𝟎𝟎 𝟏. 𝟏𝟐 𝟐𝟎
=100,000x9.6463
=Birr 964,630
Therefore, future worth at the end of 20 years=Birr
964,630
Time Value of Money
14
Example 2:
What is the present worth of a sum of Birr 75,000 at the end
of 10 years when the discount rate is 10% per year?
Solution:
𝑭
Equation: 𝑷= 𝒏
𝟏+𝒊
𝟕𝟓,𝟎𝟎𝟎
=
𝟏.𝟏𝟎 𝟏𝟎
𝟕𝟓,𝟎𝟎𝟎
=
𝟎.𝟑𝟖𝟓𝟓
=Birr 28,912.50
Therefore, present worth at the end of 10 years=Birr
28,912.50
Time Value of Money
15
Example 3:
The annual cost of maintenance of a new road thrown open to
traffic is Birr 1,500,000. what is the future worth of this
expenditure at the end of 10 years when the rate of interest is
15% per year?
Solution:
𝐀 𝟏+𝐢 𝐧 −𝟏
Equation: 𝐅 =
𝐢
𝟏, 𝟓𝟎𝟎, 𝟎𝟎𝟎 𝟏 + 𝟎. 𝟏𝟓 𝟏𝟎 − 𝟏
𝐅=
𝟎. 𝟏𝟓
= 𝑩𝒊𝒓𝒓 𝟏, 𝟓𝟎𝟎, 𝟎𝟎𝟎 × 𝟐𝟎. 𝟑𝟎𝟑𝟕
= 𝑩𝒊𝒓𝒓 𝟑𝟎, 𝟒𝟓𝟓, 𝟓𝟓𝟎
Time Value of Money
16
Example 4:
A major rehabilitation of a pavement will be done 10 years
from hence at a cost of Birr 10 million. What should be the
series of uniform annual payments that must be set apart to
accumulate this amount, if the interest rate is 9% per year.
Solution:
𝒊
Equation: 𝑨 = 𝑭
𝟏+𝒊 𝒏 −𝟏
𝟔
𝟎. 𝟎𝟗
𝑨 = 𝟏𝟎 ×
𝟏 + 𝟎. 𝟎𝟗 𝟏𝟎 − 𝟏
= 𝟏𝟎𝟔 × 𝟎. 𝟎𝟔𝟓𝟖
= 𝑩𝒊𝒓𝒓 𝟔𝟓𝟖, 𝟎𝟎𝟎
Time Value of Money
17
Example 5:
The annual maintenance cost of a major bridge is Birr 50,000.
what is the present worth of this cost incurred for 10 years
after the opening of this bridge? The discount may be taken as
12% per year.
Solution:
𝟏+𝒊 𝒏 −𝟏
Equation: 𝑷 = 𝑨
𝒊 𝟏+𝒊 𝒏
𝟏+𝟎.𝟏𝟐 𝟏𝟎 −𝟏
𝑷 = 𝟓𝟎, 𝟎𝟎𝟎
𝟎.𝟏𝟐 𝟏+𝟎.𝟏𝟐 𝟏𝟎
= 𝟓𝟎, 𝟎𝟎𝟎𝒙𝟓. 𝟔𝟓𝟎𝟐
=Birr282,510
Time Value of Money
18
Example 6:
The cost of construction of a new facility is Birr 200 million at
current price and is met with by raising a loan. What is the
annual payment of equal amount of for 20 years to repay the
loan, if the rate of interest is 10% per year.
Solution:
𝟏+𝒊 𝒏 ×𝒊
Equation: 𝑨 = 𝑷
𝟏+𝒊 𝒏 −𝟏
𝟔 𝟏+𝟎.𝟏 𝟐𝟎 ×𝟎.𝟏
= 𝟐𝟎𝟎 × 𝟏𝟎
𝟏+𝟎.𝟏 𝟐𝟎 −𝟏
= 𝟐𝟎𝟎 × 𝟏𝟎𝟔 × 𝟎. 𝟏𝟏𝟕𝟓
= 𝑩𝒊𝒓𝒓 𝟐𝟑. 𝟓 𝒎𝒊𝒍𝒍𝒊𝒐𝒏
Total Transportation Cost
19
Total Highway
Cost
Vehicle
Operating Cost
Delay Cost
Accident Cost
Economic aspect of road construction
23
Solution:
o Initial investment (P) = birr 4,000,000
o Annual fuel savings during the first year (A) = birr 600,000
birr 50,000
o Life of the project (n) = 15 years
Total PW of costs
= initial investments (P) +Pw of annual O&M cost (Ac)
=Birr 4,000,000+P(P/A,I,n)
=Birr 4,000,000 +Birr 150,000(P/A,12%,15)
=Birr 4,000,000 +Birr 150,000x6.8109
=Birr 5,021,635
Total PW of benefits
=A(P/A,12%,15)+G[(A/G,12%,15)x((P/A,12%,15)]
=Birr600,000(P/A,12%,15)+50,000[(A/G,12%,15)x((P/A,12%,15)]
=Birr600,000x6.8109+50,000[(4.9803)x((6.8109)]
=Birr600,000x6.8109+50,000x(33.9203)
=Birr 5,782,556
Methods of Economic Evaluation of
Highway Projects
36
Example-2:
1. A proposed highway project requires an initial investment of
€ 10 million and a supplementary investment of € 5 million
at the end of the tenth year. The project will have an useful
life of 50 years, counting from the date of the initial
investment. The interest rate is 6%. The cost of operation
and maintenance is € 200,000 per year. The benefits of the
project has been estimated to begin with € 1.0 million per
year for the first 15 years (at the end of each year),
thereafter increasing at once to € 2.75 million per year and
remaining constant for the remaining 35 years. Determine:
a) Net Present Value (NPV) Method
b) Benefit-cost (B/C) ratio Method
c) Internal Rate of Return (IRR) Method
Methods of Economic Evaluation
38
Solution
Methods of Economic Evaluation
39
Methods of Economic Evaluation
40
Methods of Economic Evaluation
41
Examples-3:
For an analysis period of 20 years, there are two alternative
pavement designs with equal salvage values. The first alternative
is to reconstruct the pavement when it reaches failure, while the
second alternative is to improve the condition of the pavement at
the 8th, 16th, and 24th years. Assume the interest rate is 4% for both
alternatives.
The costs are as follows:
Alternative-A: initial cost: $18 million; cost to
reconstruct after 20 years: $9 million.
Alternative-B: initial cost: $15 million; cost for
improvement at 8th, 16th, and 24th years: $5 million each
occurrence
Which alternative should be selected?
Methods of Economic Evaluation
42
Solution:
𝑵𝑷𝑽𝒂𝒍𝒕𝒆𝒓𝒏𝒂𝒕𝒊𝒗𝒆−𝑨
𝟏
= 𝒊𝒏𝒊𝒕𝒊𝒂𝒍 𝒄𝒐𝒔𝒕 + 𝒓𝒆𝒄𝒐𝒏𝒔𝒕𝒓𝒖𝒄𝒕𝒊𝒐𝒏 𝒄𝒐𝒔𝒕
𝟏+𝒊 𝒏
𝟏
= 𝟏𝟖 𝒎𝒊𝒍𝒍𝒊𝒐𝒏 + 𝟗 𝒎𝒊𝒍𝒍𝒊𝒐𝒏
𝟏+𝟎.𝟎𝟒 𝟐𝟎
= 𝟐𝟐. 𝟏 𝒎𝒊𝒍𝒍𝒊𝒐𝒏
𝑵𝑷𝑽𝒂𝒍𝒕𝒆𝒓𝒏𝒂𝒕𝒊𝒗𝒆−𝑩
𝟏
= 𝒊𝒏𝒊𝒕𝒊𝒂𝒍 𝒄𝒐𝒔𝒕 + 𝒊𝒎𝒑𝒓𝒐𝒗𝒆𝒎𝒆𝒏𝒕 𝒄𝒐𝒔𝒕
𝟏+𝒊 𝒏
𝟏 𝟏 𝟏
= 𝟏𝟓 𝒎𝒊𝒍𝒍𝒊𝒐𝒏 + 𝟓 𝒎𝒊𝒍𝒍𝒊𝒐𝒏[ + + ]
𝟏+𝟎.𝟎𝟒 𝟖 𝟏+𝟎.𝟎𝟒 𝟏𝟔 𝟏+𝟎.𝟎𝟒 𝟐𝟒
= 𝟐𝟑. 𝟑 𝒎𝒊𝒍𝒍𝒊𝒐𝒏
Methods of Economic Evaluation
43
44