INTRODUCTION
The concept of buildability emerged in the late 1970s as a direct result of research
and practical applications aimed at improving the efficiency, cost effectiveness and
quality of construction projects. In 1983, the Construction Industry Research and
Information Association, CIRIA, defined it as `the extent to which the design of a
building facilitates ease of construction, subject to the overall requirements for the
completed building'. The adoption of buildability in the UK does not seem to
have been high. This is believed to be because research was limited in focus with
an emphasis on improving site productivity through implementing concepts such
as design rationalisation. This restriction, together with the separation of inputs
characterising the UK's traditional building process, led to a lack of general
interest in and application of buildability concepts.
In contrast, research and construction practice in the USA focused more
purposefully on the concept of constructability (CII USA 1987). Interests took
advantage of the close link between building owners and contractors, emphasising
a management systems approach to think creatively about the practicalities of the
building process. Research in Australia adopted a similar management-based
approach (CIIA 1993) presenting practical measures to improve the total
construction process by focusing on key issues for consideration, rather than
recommending specific procedures. The development of constructability princi-
ples serves to accommodate variations in organisational cultures, procedures and
practices, thereby broadening the appeal of and encouraging the potential for the
application of constructability concepts.
The aim of this paper is to review critically the concepts and principles of con-
structability which are recognised today and which evolved from the early research
studies into and practical applications of buildability. This focus is pertinent as
there has been much creditable research and application of constructability
concepts in recent times. Moreover, there remains some confusion in defining the
conceptual boundaries of buildability and constructability. Until the boundaries
are made clear, difficulties will likely remain in establishing the real benefits
available to the construction industry from applying the concepts and principles of
constructability.
Objectives
The specific objectives of this paper are:
1 To describe in detail the development of constructability concepts and clearly
determine the boundaries of constructability and the boundaries of buildability.
2 To identify and develop the key principles of constructability which allow its
concepts to be applied with the maximum potential during any construction
project
3 To anticipate likely future developments in constructability research and
practice based upon current activities, concerns and issues.
Collection of information
The information for this paper was gathered predominently from the large body of
knowledge in the fields of buildability and constructability which has been
assembled over the last 25 to 30 years. The information, published extensively in
the form of journal papers, books and conference proceedings, reflects research
and practice in the UK, USA and Australia, these being the countries where
research interest has been at its height. A practical example of constructability
from recent research is described, which lends considerable support to the con-
cepts and principles which are presented. These sources of information combine
to facilitate a level of insight into the likely future orientation of constructability
research and practice.
Early experience
A UK governmental report in the early 1960s raised considerable concern at the
distinct separation between the processes of design and construction, drawing
specific attention to the inadequacies of communication and co-ordination which,
it was said, was responsible for many of the problems then being experienced
within the construction industry (Emmerson 1962). A number of general
difficulties were identified, the principal ones being: the poor preparation of
drawings and specifications; the inefficiencies of pre-contract design procedures;
and the inadequate level of communication between the designer and contractor.
Following this theme, a further report (Banwell 1964) suggested that:
`design and construction must be considered together and that in the tradi-
tional contracting situation, the contractor is too far removed from the design
stage at which his specialised knowledge and techniques could be put to
invaluable use'
The report called for more attention to be given to pre-contract planning and
design formulation and criticised professionalism as being narrow sighted, giving
rise to unnecessary and inefficient construction practices. It was suggested that:
clients define their building requirements clearly at the start of the design stage;
the building process should better integrate the stages of design and construction;
and that traditional construction practices should be reviewed to seek inter-
disciplinary approach. A subsequent study (Economic Development Council
1967) reported that the recommendations made in the Banwell Report had not
been successfully implemented within the construction industry and that flexible
approaches to traditional procedures should be sought and new initiatives
developed if meaningful change within the industry was to be achieved. The
Wood Report in the mid-1970s (National Economic Development Office 1975)
suggested that in the decade following the Emmerson and Banwell reports some
improvements had been made in the quest for integrating better the processes of
design and construction. In general however, the original problems remained and
it was suggested that efforts should be directed towards increasing the level of
awareness for the problems and designing measures to bring together the design
and construction processes such that the construction stage might directly
capitalise on design initiatives.
ability takes a more holistic perspective, focusing on the consideration of all stages
in the total building process. There is, of course, a very real and major implication
to constructability as a practical concept for application throughout the total
building process. Constructability is fundamentally dependent upon: the client
being committed to its inclusion in project development from the outset; the
efforts of the project team to avidly pursue its principles; and the early and
dedicated involvement of the main contractor. Early commitment to construct-
ability in the project life cycle is also essential as the ability to influence project
success will be greater in the initial stages of project development. When
constructability is considered early and endorsed by the project team its concepts
and principles have the potential to bring tangible benefits to the total building
process. The following section develops this theme further and describes how
principles of constructability have been developed which are applicable to each
stage of the total building process.
Design
Design concepts; specifications; construction details; task dependency; standar-
disation; tolerances; dimensional co-ordination; and drawings and communica-
tion.
Post-construction
Installation and commissioning; operational requirements; user requirements;
and life cycle provision and maintenance.
Constructability principles
Between 1991 and 1993, the CII Australia collaborated extensively with the CII in
the USA to develop a Constructability Principles File appropriate for the Australian
context (CII Australia 1993). The research team evaluated the concepts of
buildability and constructability that had been the subject of research carried out
in the UK, USA and Australia over the last 25 to 30 years against a series of local
case studies and developed a set of principles tailored to the Australian con-
struction industry. The concepts developed consist of a best-practice, how-to-do-
it manual, covering:
1 Implementation advice on how organisations can establish a constructability
programme
2 A flowchart indicating the applicability of principles at each stage in the building
process
3 Executive summaries explaining the principles of constructability
4 The key principles of constructability
5 A database to record examples of the savings made from implementing
constructability.
An important development by the task force is the concept that principles of
constructability are not applied sequentially as the building process develops, but
rather may be developed during several stages. A flowchart was presented which
advises the user which principles are most likely to be relevant at particular stages
in the project life cycle. The constructability file presents 12 overriding principles
which represent the best in current constructability practice and are aimed at
encouraging the project team to apply them, where appropriate, to their project.
The team may find that some principles directly relate to their project while others
do not, but the goal of the file is to stimulate thought about constructability and
how to make it work. The approach deliberately avoids a checklist approach that
likely stifles creative thought, and instead addresses the difficulties associated with
implementation by indicating the relative importance of each principle at any
particular stage of a typical construction project. The CIIA principles of con-
structability are described as follows:
Integration
Constructability must be made an integral part of the project plan.
Construction knowledge
Project planning must actively involve construction knowledge and experience.
Team skills
The experience, skills and composition of the project team must be appropriate
for the project.
Corporate objectives
Constructability is enhanced when the project team gains an understanding of the
client's corporate and project objectives.
Available resources
The technology of the design solution must be matched with the skills and
resources available.
External factors
External factors can affect the cost and/or program of the project.
Program
The overall program for the project must be realistic and construction-sensitive,
and have the commitment of the project team.
Construction methodology
The project design must consider construction methodology.
Accessibility
Constructability will be enhanced if construction accessibility is considered in the
design and construction stages of the project.
Specifications
Project constructability is enhanced when construction efficiency is considered in
specification development.
Construction innovation
The use of innovative techniques during construction will enhance construct-
ability.
Feedback
Constructability can be enhanced on similar future projects if a post-construction
analysis is undertaken by the project team.
Barriers to implementation
It would be unrealistic and therefore irresponsible to suggest that constructability
can address all the questions, difficulties and problems that confront any and all
construction projects. Creating a building that is easier to construct cannot be the
sole aim of the client (Griffith & Sidwell 1995). Each building project is an
individual and often unique entity which requires, in its formulation, a multitude
This section presents a recently completed research case study example of con-
structability to exemplify constructability consideration within the building pro-
cess. The example reviewed should not be interpreted as stereotypical of
constructability interest and activity, but rather serve as a persuasive indication of
the propensities of constructability concepts and principles in application. This
case study example of constructability application concerns the procurement,
design and construction of a large public arts and entertainment centre, a state
government initiative in Australia. The brief for the project called for: a 12,000
seat public arena; backstage facilities and storage; public amenities; corporate
suites; and a main foyer and auditorium. Speed of construction was considered to
be the overriding priority of the client as was the effectiveness of construction
techniques and management as the project held considerable public and political
attention at that time. In addition, a project management approach was to be used
for the project. At the recommendation of the client, constructability considera-
tion was to be encouraged throughout the total building process. The benefits of
constructability emerging from this interest were as follows:
tenders and the successful contractor then completes the design and carries out the
works. For this project, the design consultant developed the design to the point of
novation and then engaged their own subconsultant and a building consultant,
appointed jointly by them and the project management team, to specifically assist
with project methodology and planning. This approach was highly beneficial as the
close interaction between the subconsultant, building consultant and project
management team allowed constructability to be a key feature of their organisation
and planning for the project. Tenders were requested from a number of contractors
and detailed negotiations followed with the lowest bidder.
Design
The selected contractor allowed the project management team to scrutinise the
bid during which the high cost elements could be identified and the opportunity
explored to make cost savings. From this process a range of design and
construction alternatives were suggested, leading to subsequent cost-effective
modifications.
Construction
The project was situated on an area of poor ground. As this was identified early on
in the conceptual planning stage, project management had taken the opportunity
to re-confirm their site investigation survey data such that when the contractor
tendered and subsequently carried out the construction works the nature of the
ground conditions was known with accuracy. Construction methods that had
been considered during the conceptual planning stage were reviewed with the
selected contractor and aspects which would encourage good constructability in
methods and sequencing were incorporated into the site works.
Construction management
A prominent concern of site management was the method and sequence by which
the steel space frame trusses would be set in position for the large span roof. It was
impossible to construct the entire roof at ground level and then lift it into position,
so it was decided to use multiple and co-ordinated crane lifts to raise and sling the
main trusses into position. Specially fabricated working cages were then sus-
pended from the cranes to allow operatives to fix the roof coverings. This method
alleviated the need for temporary working platforms which reduced time and costs
considerably. Special provision for safe working had to be agreed with site labour
and trade unions before the method was implemented.
study shows quite unambiguously that there are real benefits to be accrued from
the detailed consideration of constructability.
This review of constructability concepts, principles and practice has shown that
there has, over time, been considerable re-assessment of its form. Interest has
grown from the narrow perspective of buildability to the strategic consideration of
constructability as a valuable management tool to bring real benefit across the
total building process. A truly workable approach to constructability requires
recognition that there are many and diverse factors that impinge upon the building
processes. These factors were presented earlier in this paper. Constructability will
not gain full support within the construction industry until these factors are better
understood and until constructability principles are seen in context with them. To
develop a conceptual approach which appreciates the influence of these factors
and relates them better to constructability will not be an easy task.
Recent research (Chen & McGeorge 1994) states `that many researchers have
recognised the importance of being able to identify all relevant factors . . . this has
been an ideal which has been too complex to model conceptually and therefore
too difficult to implement'. Chen and McGeorge suggest that `the greatest
potential gains will be achieved by better management of information to support
project decision making'. They support a systems approach to examine a three-
dimensional model in which participants, project factors and project stages are
significant to constructability strategies. Further research by Griffith and Sidwell
(1995) presents an outline for developing a constructability strategy at each key
stage of the construction process. This considers many of the factors suggested by
Chen and McGeorge. This approach sought to stimulate creative thought about
the nature of each stage such that important questions and considerations about
the building process would not be missed and to encourage action to be taken by
the respective participants to pursue constructability.
In the strategic consideration of constructability it is likely that future research
and practice might focus on: the more holistic view of constructability to develop
more encompassing strategies to be developed for considering constructability at
each stage in the total building process; the concentration on a fewer number of
factors which influence constructability such that greater reliability can be built in
to the strategies developed; and the formulation of management methods that are
readily adaptable to the individual project situation, including non-traditionally
procured projects.
CONCLUSIONS
It can be seen clearly from this paper that constructability concepts transcend the
total building process. Constructability has a valuable role to play in conceptual
planning, procurement, design, construction and use. The timing of its imple-
mentation is crucial to its success as the ability to influence the project outcome is
greatest early in the project lifestyle. The application of constructability thinking at
the project's inception will therefore maximise its potential to deliver real benefits.
Constructability will achieve greater success when its concepts and principles
become an inherent and recognised part of the way in which a construction project
is conceived, organised and managed. For benefits to be guaranteed, the project
team led by the client must have a collective project policy which is actively
pursued through a structured programme of measures designed to encourage
constructability from day one of the project's conception.
Three factors are significant to the successful implementation of construct-
ability: first, the conscious perception, drive and commitment of the client; sec-
ond, the earliest possible involvement of construction knowledge, skills and
experience in the building process; and third and perhaps the most important
factor, the collective response and support of all the members of the project team.
Better value for money, improved quality of service and significant savings in
project cost and time are shown to be possible through constructability con-
sideration. A strategic approach in the future will likely see constructability being
focused on a number of key issues within the construction process ± those which
have a significant capability to influence the project outcome. Constructability will
need to be understood fundamentally within the context of these factors if its
concepts and principles are to develop, become applied more widely and have
greater success in the future.
References
Adams, A. (1989) Practical Buildability. Construction Industry Research and Information Association
(CIRIA)/Butterworth, London.
Banwell, H. (1964) The Placing and Management of Contracts for Building and Civil Engineering Work.
HMSO, London.
Bishop, D. (1985) Buildability: The Criteria for Assessment. Chartered Institute of Building (CIOB),
Ascot.
Business Roundtable (1982) Integrating Construction Resources and Technology into Engineering. Business
Roundtable, New York.
Chen, S.E. & McGeorge, W.D. (1994) A Systems Approach to Managing Buildability. Australian
Institute of Building (AIB) Papers.
CII Australia (1993) Constructability Principles File. Construction Industry Institute, Adelaide.
CII USA (1987) Constructability Concepts File. Construction Industry Institute, Texas.
CIRIA (1983) Buildability: An Assessment. Construction Industry Research and Information Associa-
tion, London.
Economic Development Council (EDC) (1967) Action on the Banwell Report. HMSO, London.
Emmerson, H. (1962) Survey of Problems Before the Construction Industry: a report prepared for the Ministry
of Works. HMSO, London.
Griffith, A. (1984) A critical investigation of factors influencing buildability and productivity. PhD Thesis,
Heriot-Watt University, Edinburgh.
Griffith, A. (1985a) Buildability: The Effect of Design and Management on Construction: A Case Study.
Science and Engineering Research Council (SERC)/Heriot-Watt University, Edinburgh.
Griffith, A. (1985b) Buildability: Time for Re-assessment. Building Technology and Management,
Journal of The Chartered Institute of Building (CIOB), Feb, CIOB, Ascot.
Griffith, A. & Sidwell, A.C. (1995) Constructability in Building and Engineering Projects. Macmillan,
Basingstoke.
Hon, S.L. (1988) A study of buildability within a project management system. M.Bldg. Thesis, University
of Melbourne, Melbourne.
Hon, S.L., Gairns, D.A. & Wilson, O.D. (1989) Buildability: A Review of Research and Practice. Aus-
tralian Institute of Building (AIB) Papers, Vol.3, AIB, Australia.
McGeorge, W.D., Chen, S.E. & Ostwald, M.J. (1992) The Development of a Conceptual Model of
Buildability Which Identifies User Satisfaction as a Major Objective. International Council for Building
Research Studies and Documentation (CIB) Conference, Rotterdam.
National Economic Development Office (NEDO) (1975) The Wood Report: The Public Client and The
Construction Industry. HMSO, London.
New South Wales Government Construction Policy Steering Committee (1993) Capital Project Pro-
curement Manual. NSW Government Office, Australia.
O'Connor, J.T., Rusch, S.E. & Schulz, M.J. (1986) Constructability Improvement During Engineering and
Procurement. Construction Industry Institute (CII), USA.
O'Connor, J.T. & Davis, J.S. (1988) Constructability during field operations. Journal of Construction
Engineering and Management, 114, (4).
Tatum, C.B., Vanegas, J.A. & Williams, J.M. (1986) Constructability Improvement During Conceptual
Planning. Construction Industry Institute (CII), USA.