VALORIZACIÓN N°01

DEL 01 AL 31 DE AGOSTO DEL …

OBRA:AMPLIACIÓN DE ALMACÉN
CONTRATISTA: MARCO CASAS CONTRATISTAS GRLS.
PROPIETARIO: SENCICO
ANTERIOR
ITEM DESCRIPCIÓN UND. CANT. P.UNIT PARCIAL CANT. IMP.
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=175 KG/CM2. M3. 12.00 333.94 4,007.28 12 4,007.28
1.01.02 ENCOF.-DESENCOF. M2. 60.00 42.00 2,520.00 60 2,520.00
1.01.03 ACERO KG. 800.00 4.94 3,952.00 800 3,952.00
1.02 VIGA
1.02.01 CONCRETO F'C=175 KG/CM2. M3. 8.00 305.15 2,441.20
1.02.02 ENCOF.-DESENCOF. M2. 40.00 46.53 1,861.20 30 1,395.90
1.02.03 ACERO KG. 500.00 4.94 2,470.00
1.03 LOSA ALIGERADA
1.03.01 CONCRETO F'C=175 KG/CM2. M3. 9.00 279.22 2,512.98
1.03.02 ENCOF.-DESENCOF. M2. 120.00 33.07 3,968.40 100 3,307.00
1.03.03 ACERO KG. 700.00 4.94 3,458.00 200 988.00
1.03.04 LADRILLOS 0.15X0.30X0.30 UND. 1020.00 2.67 2,723.40 600.00 1,602.00
2.00 MURO
2.01 LAD. KK. 18 HCO. SOGA M2. 30.00 48.84 1,465.20 30 1,465.20
2.02 LAD. KK. 18 HCO. CABEZA M2. 48.00 76.09 3,652.32 48.00 3,652.32
COSTO DIRECTO 35,031.98 22,889.70
GG (15%) 5,254.80 3,433.46
U ( 10%) 3,503.20 2,288.97
SUBTOTAL 43,789.98 28,612.13
% AVANCE 100.00 65.34%

ACUMULADO= ANTERIOR + ACTUAL

SALDO= PRESUPUESTO - ACUMULADO


ZACIÓN N°01
31 DE AGOSTO DEL …

ACTUAL ACUMULADO SALDO %


CANT. IMP. CANT. IMP. CANT. IMP. AVANCE

0.00 12.00 4,007.28 0.00 0.00 0.00%


0.00 60.00 2,520.00 0.00 0.00 0.00%
800.00 3,952.00 0.00 0.00 0.00%
0.00 0.00
8.00 2,441.20 8.00 2,441.20 0.00 0.00 0.00%
10.00 465.30 40.00 1,861.20 0.00 0.00 0.00%
500.00 2,470.00 500.00 2,470.00 0.00 0.00 0.00%
0.00 0.00
9.00 2,512.98 9.00 2,512.98 0.00 0.00 0.00%
20.00 661.40 120.00 3,968.40 0.00 0.00 0.00%
500.00 2,470.00 700.00 3,458.00 0.00 0.00 0.00%
420.00 1,121.40 1020.00 2,723.40 0.00 0.00 0.00%
0.00 0.00
30.00 1,465.20 0.00 0.00 0.00%
48.00 3,652.32 0.00 0.00 0.00%
12,142.28 35,031.98 0.00
1,821.34 5,254.80 0.00
1,214.23 3,503.20 0.00
15,177.85 43,789.98 0.00
34.66% 100.00% 0.00%
METRADOS DE AVANCE

ITEM DESCRIPCIÓN UND. CANT. ANT. ACTUAL ACUMULADO


1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.0 CONCRETO F'C=175 KG/CM2. M3. 12.00
1.01.0 ENCOF.-DESENCOF. M2. 60.00 20.00 20.00
1.01.0 ACERO KG. 800.00 800.00 800.00
1.02 VIGA
1.02.0 CONCRETO F'C=175 KG/CM2. M3. 8.00
1.02.0 ENCOF.-DESENCOF. M2. 40.00
1.02.0 ACERO KG. 500.00
1.03 LOSA ALIGERADA
1.03.0 CONCRETO F'C=175 KG/CM2. M3. 9.00
1.03.0 ENCOF.-DESENCOF. M2. 120.00
1.03.0 ACERO KG. 700.00
1.03.0 LADRILLOS 0.15X0.30X0.30 UND. 1020.00
2.00 MURO
2.01 LAD. KK. 18 HCO. SOGA M2. 30.00 20.00 20.00
2.02 LAD. KK. 18 HCO. CABEZA M2. 48.00 40.00 40.00
METRADOS

SALDO V1 V2 V3

12.00 12.00
40.00 20.00 40.00
800.00

8.00 8.00
40.00 30.00 10.00
500.00 500.00

9.00 9.00
120.00 100.00 20.00
700.00 200.00 500.00
1,020.00 600.00 420.00

10.00 20.00 10.00


40.00 8.00
FORMULA POLINOMICA

OBRA: AMPLIACION
CONTRATISTA: P.B= 43,789.98
ESPECIALIDAD: ESTRUCTURAS FECHA= ENE.
AREA GEOGRAFICA: LAMBAYEQUE
DIC 202
MONo. DESCRIPCION SIMBOLO I.U C.I % Io
1 CEMENTO P.T 1 21 72.93% 449.56
PIEDRA CHANCADA CPM 5 0.133 17.29% 441.59
MAQUINARIA NACIONAL 48 9.78% 384.41
441.81
2 LADRILLO ARCILLA 17 11.93% 853.65
LA 0.109
ARENA GRUESA 4 88.07% 1116.52
1085.16
3 MADERA NACIONAL P/ENCOFR 43 0.103 89.32% 1052.23
DH
HERRA. 37 10.68% 334.28
975.55
4 ACERO CORRUGADO F 3 0.170 100.00% 611.38
5 MANO DE OBRA INC. BS J 47 0.285 100.00% 632.89
6 G.G.U G.G.U 39 0.200 100.00% 469.68
1.000

MONOMIOS: 4,5,6 K= CIx Ir/Io

MONOMIOS:1,2,3 K= CI (AxIr1) + (BxIR2) + (CxIr3)


(AxIo1) + (BxIo2) + (CxIo3)

DONDE:
A.B.C.= % PARTICIPACIÓN
IU: INDICES UNIFICADOS DE LOS MATERIALES
DS# 11-79-VC

JUNIO JULIO AGOSTO


MAYO JUNIO JULIO
Ir K Ir K Ir K
449.56 449.56 449.56
445.56 0.133 447.54 0.134 450.75 0.134
392.42 393.71 395.18
443.28 443.75 444.45
877.69 869.6 872.43
1145.84 1157.98 0.113 1171.81 0.114
1113.85 0.112 1123.58 1136.09
1101.89 1118.92 1138.76
357.60 0.108 362.2 0.110 377.25 0.112
1022.40 1038.10 1057.43
767.7 0.213 796.31 0.221 802.21 0.223
633.53 0.285 633.53 0.285 633.53 0.285
477.31 0.203 479.79 0.204 484.63 0.206
1.055 1.067 1.074

K> 1 REAJUSTE +
K<1 REAJUSTE -
CÁLCULO DE REAJUSTE

OBRA:

SUPERVISOR:

CONTRATISTA:

PRESUPUESTO BASE:

PRESUPUESTO CONTRATADO:

FORMULA POLINOMICA UNICA

A= MONTO DEL ADELANTO DIRECTO (SIN IGV)

C= MONTO CONTRACTUAL (SIN IGV)

K= COEFICIENTE DE REAJUSTE

Ka = COEFICIENTE DE REAJUSTE AL MES DEL ADELANTO EN EFECTIVO FECHA:

D = DEDUCCION Ka=

VRC = V x K - A x V / C (K / Ka - 1)

AVANCE DE OBRA
Nº FECHA APA ARA ESTADO
1 JUN. 11,015.50 11,015.50 NORMAL
2 JUL. 28,612.13 28,612.13 NORMAL
3 AG. 43,789.98 43,789.98 NORMAL

REAJUSTE R= V (K-1)
Nº FECHA Vpro Vre K-1 Rprog Rreal Rrecon.
1 JUN. 11,015.50 11,015.50 0.067 738.04 738.04 738.04
2 JUL. 17,596.63 17,596.63 0.074 1,302.15 1,302.15 1,302.15
3 AG. 15,177.85 15,177.85 0.074 1,123.16 1,123.16 1,123.16
3,163.35
- 1,917.01
1,246.34
605.853 132.19
1,302.15
1,434.34
CUADRO RESUMEN DE VALORIZACION N° 01 ()
DEL 01 AL 30 AGOSTO DE 2021

OBRA: CASCO ESTRUCTURAL DE OFICINAS ADMINISTRATIVAS


SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE: 43,789.98 + IGV
PRESUPUESTO CONTRATADO: 43,789.98 + IGV

MONTO CONTRATADO VALORIZACION


DESCRIPCIÓN
SIN IGV (S/.) ANTERIOR (S/.)

VALORIZACIÓN (V) 43,789.98 28,612.13

TOTAL CONTRACTUAL
Avances en porcentaje

REAJUSTES (R) 1,917.01

DEDUCCIONES (D)
POR ADELANTO DIRECTO
POR ADELANTO PARA MATERIALES

TOTAL DEDUCCIONES

VALORIZACIÓN BRUTA (VB = V + R - D)

AMORTIZACIONES (A)
AMORTIZACION DEL ADELANTO DIRECTO
AMORTIZACION DEL ADELANTO PARA MATERIALES

TOTAL AMORTIZACIONES (A)

VALORIZACIÓN NETA (VN = VB - A)

RETENCIONES ( C )
MULTA
TOTAL

MONTO A PAGAR AL CONTRATISTA


EN EFECTIVO (VN-C) 11,621.35
MONTO POR I.G.V. (VN x 0,18) 2,091.84

MONTO TOTAL CON I.G.V. 13,713.19

TOTAL COMPROMISO DE PAGO>>>>>>>>>>>>>>>> S/. 19,380.54


DE VALORIZACION N° 01 ()
AGOSTO DE 2021

VALORIZACION % DE AVANCE SALDO POR VALORIZAR


ACTUAL (S/.) ACUMULADO (S/.) ACUMULADO (S/.)

15,177.85 43,789.98 100.00% 0.00

1,246.34 3,163.35

16,424.19 46,953.32

16,424.19

16,424.19
2,956.35

19,380.54

S/. 19,380.54
N° 0 1 2 3
MES 0 JUL. AG. SET
A.P.A 0 11,015.50 28,612.13 43,789.98
A.R.A 0 11,015.50 28,612.13 43,789.98
MIN. 80%A.P.A 0 8,812.40 22,889.70 35,031.98

CURVA "S" AGOSTO


50,000.00

45,000.00

40,000.00

35,000.00

30,000.00
SOLES

25,000.00

20,000.00

15,000.00

10,000.00

5,000.00

0.00
0 JUL. AG.

SOLES

A.P.A A.R.A MIN. 80%A.P.A


G. SET