OBRA:AMPLIACIÓN DE ALMACÉN
CONTRATISTA: MARCO CASAS CONTRATISTAS GRLS.
PROPIETARIO: SENCICO
ANTERIOR
ITEM DESCRIPCIÓN UND. CANT. P.UNIT PARCIAL CANT. IMP.
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=175 KG/CM2. M3. 12.00 333.94 4,007.28 12 4,007.28
1.01.02 ENCOF.-DESENCOF. M2. 60.00 42.00 2,520.00 60 2,520.00
1.01.03 ACERO KG. 800.00 4.94 3,952.00 800 3,952.00
1.02 VIGA
1.02.01 CONCRETO F'C=175 KG/CM2. M3. 8.00 305.15 2,441.20
1.02.02 ENCOF.-DESENCOF. M2. 40.00 46.53 1,861.20 30 1,395.90
1.02.03 ACERO KG. 500.00 4.94 2,470.00
1.03 LOSA ALIGERADA
1.03.01 CONCRETO F'C=175 KG/CM2. M3. 9.00 279.22 2,512.98
1.03.02 ENCOF.-DESENCOF. M2. 120.00 33.07 3,968.40 100 3,307.00
1.03.03 ACERO KG. 700.00 4.94 3,458.00 200 988.00
1.03.04 LADRILLOS 0.15X0.30X0.30 UND. 1020.00 2.67 2,723.40 600.00 1,602.00
2.00 MURO
2.01 LAD. KK. 18 HCO. SOGA M2. 30.00 48.84 1,465.20 30 1,465.20
2.02 LAD. KK. 18 HCO. CABEZA M2. 48.00 76.09 3,652.32 48.00 3,652.32
COSTO DIRECTO 35,031.98 22,889.70
GG (15%) 5,254.80 3,433.46
U ( 10%) 3,503.20 2,288.97
SUBTOTAL 43,789.98 28,612.13
% AVANCE 100.00 65.34%
SALDO V1 V2 V3
12.00 12.00
40.00 20.00 40.00
800.00
8.00 8.00
40.00 30.00 10.00
500.00 500.00
9.00 9.00
120.00 100.00 20.00
700.00 200.00 500.00
1,020.00 600.00 420.00
OBRA: AMPLIACION
CONTRATISTA: P.B= 43,789.98
ESPECIALIDAD: ESTRUCTURAS FECHA= ENE.
AREA GEOGRAFICA: LAMBAYEQUE
DIC 202
MONo. DESCRIPCION SIMBOLO I.U C.I % Io
1 CEMENTO P.T 1 21 72.93% 449.56
PIEDRA CHANCADA CPM 5 0.133 17.29% 441.59
MAQUINARIA NACIONAL 48 9.78% 384.41
441.81
2 LADRILLO ARCILLA 17 11.93% 853.65
LA 0.109
ARENA GRUESA 4 88.07% 1116.52
1085.16
3 MADERA NACIONAL P/ENCOFR 43 0.103 89.32% 1052.23
DH
HERRA. 37 10.68% 334.28
975.55
4 ACERO CORRUGADO F 3 0.170 100.00% 611.38
5 MANO DE OBRA INC. BS J 47 0.285 100.00% 632.89
6 G.G.U G.G.U 39 0.200 100.00% 469.68
1.000
DONDE:
A.B.C.= % PARTICIPACIÓN
IU: INDICES UNIFICADOS DE LOS MATERIALES
DS# 11-79-VC
K> 1 REAJUSTE +
K<1 REAJUSTE -
CÁLCULO DE REAJUSTE
OBRA:
SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE:
PRESUPUESTO CONTRATADO:
K= COEFICIENTE DE REAJUSTE
D = DEDUCCION Ka=
VRC = V x K - A x V / C (K / Ka - 1)
AVANCE DE OBRA
Nº FECHA APA ARA ESTADO
1 JUN. 11,015.50 11,015.50 NORMAL
2 JUL. 28,612.13 28,612.13 NORMAL
3 AG. 43,789.98 43,789.98 NORMAL
REAJUSTE R= V (K-1)
Nº FECHA Vpro Vre K-1 Rprog Rreal Rrecon.
1 JUN. 11,015.50 11,015.50 0.067 738.04 738.04 738.04
2 JUL. 17,596.63 17,596.63 0.074 1,302.15 1,302.15 1,302.15
3 AG. 15,177.85 15,177.85 0.074 1,123.16 1,123.16 1,123.16
3,163.35
- 1,917.01
1,246.34
605.853 132.19
1,302.15
1,434.34
CUADRO RESUMEN DE VALORIZACION N° 01 ()
DEL 01 AL 30 AGOSTO DE 2021
TOTAL CONTRACTUAL
Avances en porcentaje
DEDUCCIONES (D)
POR ADELANTO DIRECTO
POR ADELANTO PARA MATERIALES
TOTAL DEDUCCIONES
AMORTIZACIONES (A)
AMORTIZACION DEL ADELANTO DIRECTO
AMORTIZACION DEL ADELANTO PARA MATERIALES
RETENCIONES ( C )
MULTA
TOTAL
1,246.34 3,163.35
16,424.19 46,953.32
16,424.19
16,424.19
2,956.35
19,380.54
S/. 19,380.54
N° 0 1 2 3
MES 0 JUL. AG. SET
A.P.A 0 11,015.50 28,612.13 43,789.98
A.R.A 0 11,015.50 28,612.13 43,789.98
MIN. 80%A.P.A 0 8,812.40 22,889.70 35,031.98
45,000.00
40,000.00
35,000.00
30,000.00
SOLES
25,000.00
20,000.00
15,000.00
10,000.00
5,000.00
0.00
0 JUL. AG.
SOLES