P3 MAIA - DUCTWORK
1 1.2MM(THK) GI SHEET PRESSURE : 1000PA M2 0 -
2 1.0MM(THK) GI SHEET PRESSURE : 1000PA M2 0 -
3 0.75MM(THK) GI SHEET PRESSURE : 1000PA M2 140 55.20 31.50 12,138.00
4 0.6MM(THK) GI SHEET PRESSURE : 1000PA M2 0 -
5 BRACKET M2 140 62.50 8,750.00
6 K-FLEX INSULATION GRADE B1、30MM(THK) M2 140 101.50 14,210.00
7 FLANGE JOINT M2 140 30.00 4,200.00
8 ADHESIVE M2 140 7.50 1,050.00
9 ABOVE CEILING WORK M2 140 - 2.20 308.00
10 RETURN GRILLE 2'x 4' C/W OBD SET 8 125.00 75.00 1,600.00
11 RETURN PLENUM 50mm PIR PANEL M2 64 145.00 50.00 12,480.00
AIRFLOW: 2000cmh
12 HEPA FILTER EFFICIENCY: H14 SIZE: NO. 24 880.00 21,120.00
4'x 2' C/W OBD
13 FLEXIBLE AIR DUCT ø14" SET 24 250.00 6,000.00
14 FAN INSTALLATION & FAN CONNECTION SET 8 500.00 400.00 7,200.00
15 AIR BALANCING LOT 1 4,400.00 4,400.00
16 OTHERS RIVET,PAINTING,ETC. LOT 1 3,800.00 3,800.00
TOTAL 97,256.00
BILL OF QUANTITY
TOTAL 65,520.00
BILL OF QUANTITY
TOTAL 32,665.00
BILL OF QUANTITY
D PRELIMINARIES
- PROJECT MANAGEMENT 1 LOT 5,500.00
- CONTRACT STAMPING DUTY 1 LOT 7,300.00
- CIBD CONTRIBUTION 1 LOT 200.00
- INSURANCE 1 LOT 300.00
- SHOP DRAWING & AS-BUILT DRAWING 1 LOT 99.00
- HOUSEKEEPING 1 LOT 600.00
- SAFETY COMPLIANCE 1 LOT 1,600.00
- TESTING & COMMISSIONING 1 LOT 800.00
- THIRD PARTY CLEANROOM CERTIFICATIN (NEBB REPORT) 1 LOT 2,000.00
- OVERTIME 1 LOT -
- CLEANROOM HOARDING TO JINKO REQUIREMENT 1 LOT 1,800.00
- VALID FOREIGN WORKER PERMIT & CIBD CARD 1 LOT -
- TUBULAR SCAFFOLDING 1 LOT 1,600.00
TOTAL 21,799.00
TENDER BILL OF QUANTITY
SUMMARY